Silicon Valley Clean Water Commission Meeting
May 12, 2016
Agenda Item 8A Flo-Beast Waste Receiving Unit
Agenda Item 8A Flo-Beast Waste Receiving Station
• Piloted Equipment –
Performance Successful
• Cleans FOG of inorganic
material
• Recommend purchase at
$185,082 (+ shipping)
• Lead time is 4-6 months
• Continue to use pilot unit in
the meantime
Agenda Item 8A Flo-Beast Waste Receiving Station
• Current FOG rate = $0.05/gal
• Grant funding will cover majority of purchase cost
Agenda Item 8A Recommendation
Approve Purchase of Enviro-Care Flo-Beast Waste Receiving Unit – $185,082
Agenda Item 8B Electrical-Instrumentation-Controls Consulting Services – Technical Edge
Agenda Item 8B Automation Consulting Services
Field Equipment sends info to PLCs
Field-Level PLCs reads equipment information and sends to HMI
computer
Operator responds to information from Control Room
Agenda Item 8B Electrical-Instrumentation-Controls Consulting Services – Technical Edge
• Technical Edge assists with all aspects
• Relieves need for a consulting firm
– Estimated project cost reductions >$200k
– Rate is $125/hr; comparable to $170-$190/hr
• Authorization Requested - $360,000
Agenda Item 8B Recommendation
Move approval of Task Order to Technical Edge for Automation Services - $360,000
Agenda Item 8C Emergency Force Main Repairs
Construction Contract Change Order
Agenda Item 8C Emergency Force Main Repair CCO
• Pipe replacement ongoing since November 2015
• Unforeseen conditions encountered:
– Unforeseen Utilities
– Isolation Gate and Emergency Connection
– Pump Discharge Manifold Compromised Pipe
Agenda Item 8C Emergency Force Main Repair CCO
Unforeseen Utilities • 30 utilities (vs 5) • Serves County and City • Crosses P.S. Site • Est. Cost = $310k
Agenda Item 8C Emergency Force Main Repair CCO
Isolation Valve Est. Cost = $96k
Emergency Connection Est. Cost = $66k
Pump Discharge Manifold
P#1 P#2 P#6 P#5 P#4 P#3
Agenda Item 8C Emergency Force Main Repair CCO
Discharge Manifold • Pipe Thicknesses Measured • Extremely Thin • Est. Cost = $460k
Pipe wall thickness measurements
0.07
0.09 0.07
0.31
0.31
Agenda Item 8C Emergency Force Main Repair CCO
• Additional Costs due to unforeseen conditions:
– Utilities - $310,000
– Isolation Valve - $162,000
– Discharge Manifold - $460,000
• Increase to contract cost = $932,200
• Less available contingency @ $200,000
• Total authorization requested = $732,200
Agenda Item 8C Recommendation
Approve Construction Contract Change Order to Force Main Emergency Repair - $732,200
Thank you
20
22
Agenda Item 8B Conveyance System Program
Preliminary Design Authorizations
Agenda Item 8B Recommendation
Move approval of Task Orders for
Preliminary Designs Conveyance System Components Total Authorization of $8,406,883
25
Agenda Item 8B Conveyance System Predesign
All Components Required
Collection Systems to
Pump Stations to
Gravity Pipe to
Lift Station to
Headworks to
Treatment Plant
Member Agency
Sewage to SVCW TP
Gravity Pipe
Pump Stations
Receiving Lift
Station
Headworks
Collection Systems
Agenda Item 8B Conveyance System Predesign
• CEQA Status
– Public Comments on NOP minimal and routine
– Minimal risk for major project description changes
• Risks of Non-Action
– Conveyance system failures
– Higher costs: • SRF vs Bonds
• Payback on planning loan accelerated
• Construction inflation
Agenda Item 8B Conveyance System Predesign
Risks to Delay • Conveyance system failures
– In past 4 years, 7 pipe leaks (4 not on 48-in FM) and 2 pump station failures
– Effectiveness of “Bandage” fixes is diminishing
• Higher cost impacts
– SRF monies over-subscribed • If projects are not funded via SRF, over a 30-year term, this adds $234
million in nominal debt service payments (= NPV of $108 million)
– Planning loan repayment shortens to 10 years (vs 30 years) • Affects user rates
– Ongoing repairs to failing facilities
Agenda Item 8B Conveyance System Predesign
• Recommendations to move program forward:
– Allow Program to move into Preliminary Design
– Allow Final Design to proceed • If necessary, hold until Commission approves bidding
• If necessary, capture EIR mitigation measures
– Immediately begin preparing SRF loan application • Including approaching member agency staff for finance package
approvals