Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates

Transcript of Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer...

Page 1: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Signal Patterns for Improving Light Rail Operation

Wintana Miller, Associate Transportation EngineerWith Mark Madden, P.E., P.T.O.E.DKS Associates

Page 2: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Transportation in Tacoma Initial Pilot Project Update to Project Signal Timing

What’s Next

Signal Patterns for Improving Light Rail Operation

Page 3: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Transportation in Tacoma

Page 4: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Downtown Tacoma

Page 5: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Tacoma Link Light Rail

Page 6: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Initial Pilot Project

Page 7: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Parties Involved Problems Found Methodology Challenges

Initial Pilot Project

Page 8: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

City of Tacoma Sound Transit Pierce Transit DKS Associates – Technical

Advisers

Parties Involved

Page 9: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Periodic Gridlock Train Headways: 10 minutes (600 seconds) Signal Cycle Length: 70 seconds

Potential Solution: Coordinate Train and Signal Operation

Problems Found

Page 10: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Main Objectives: Compatible cycles = repetitive

operation Same time base = predictable action

across systems Predictable train travel times

Coordinating Train and Signal Operations

Page 11: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Picking a Compatible Cycle Length 100 second cycle

Synchronized Clocks US Official Time: Atomic Clock in

Colorado Springs Sound Transit Train Data

Set Train Schedule

Project Method

Page 12: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Time Space Diagram

Page 13: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

External Logic Allowed for One Timing Plan

Conservative dwell times Unable to use check out detectors No event plans or seasonal variations

Remaining Challenges

Page 14: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

City of Tacoma in the process of upgrading signal system

New signal system has been selected Fine tuning LRT operations

Signal System Upgrades?

Page 15: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Project Update

Page 16: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

New Plan Needed New Light Rail Parameters New Traffic Signal Parameters Unique Phasing for Preempts

New Signal Pattern Development

Page 17: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Driven by New Station Construction New Station in Place Before New Controllers

Need for New Plans

Page 18: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Train Headways Train Travel Times Station Dwell Times

New Light Rail Parameters

Page 19: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

New Headway New Cycle Lengths 90 seconds

New Pedestrian Timing (per 2009 MUTCD) Decreased walking speed from 4.0 ft/sec to 3.5

ft/sec

New Traffic Signal Parameters

Page 20: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Unique Phasing for Preempts

Page 21: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Normally two phases Train preempt activate left turn phase Avoiding the left turn trap

Commerce St Phasing

Page 22: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.
Page 23: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.
Page 24: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.

Support 120 second cycle length Shorter dwell times during off-peak hours Longer dwell times for special events

What’s Next?

Page 25: Signal Patterns for Improving Light Rail Operation Wintana Miller, Associate Transportation Engineer With Mark Madden, P.E., P.T.O.E. DKS Associates.