![Page 1: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/1.jpg)
SHRP2 R06G Implementation Phase
Liberty & Armstrong Tunnels- Pittsburgh, PA
Advanced Infrastructure Design, Inc. (www.aidpe.com)
Kaz Tabrizi, PhD, PE & Manuel Celaya, [email protected] [email protected]
(732) 648-9003 (915) 253-1493
September 14, 2016
![Page 2: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/2.jpg)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
• AID Background
• Spacetec Technology
– Equipment (Spacetec Scanner)
– Capabilities
– Software
• Testing of Pittsburgh Tunnels
• Post-processing/Analysis (Mapping & Database)
• Cost & other factors
• Limitations
• Conclusions 2
![Page 3: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/3.jpg)
• NDT/E Assessment & Forensic Investigation
– Tunnels
– Bridge Decks
– Bridge Substructures
– Pavements
3
AID Background (staff of 30 in NJ and PA)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Modular Ground
Coupled GPR (Multiple
Antennas)
Air launched GPR
(Single Antennas)
Spacetec
Scanner
PSPA, GPR & Horizontal
Coring
![Page 4: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/4.jpg)
• Pavement Engineering
– Testing
– Design
– LCCA
– LCA
4
AID Background
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
DCP
FWD
Coring
![Page 5: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/5.jpg)
• Asset Management
– PMS Data Collection
– LCMS
– High Resolution Digital
Video Collection
– Pavement Treatment
Recommendations
5
AID Integrated Testing Vehicle (ITV)
AID Background
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
![Page 6: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/6.jpg)
• Utility Mapping(Multi-Channel GPR. Pin-point
accuracy. Export to CAD.
Export to Google Earth)
6
AID Background
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
![Page 7: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/7.jpg)
This report (R06G) evaluated many available technologies and found Spacetec a mature and useful tool for tunnels.
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
![Page 8: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/8.jpg)
Tunnels in USA
Railway/Subway Tunnels
Vehicular Tunnels
Agency Tunnel # of Bores
MTA-NYCT East River 2
MTA-NYCT Newton Creek 2
Amtrak East River 2
Amtrak Hudson River 2
TOTAL 8
Agency Tunnel # of Bores
CBBT Chesapeake
Bay Bridge
1
MDTA Baltimore
Harbor
2
MDTA Fort McHenry 4
SJTA Brigantine 2
NJDOT Rt. 29 2
NJ Transit Roseville 1
PennDOT Armstrong &
Liberty
2
TOTAL 14
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Tunnels Scanned
![Page 9: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/9.jpg)
• Scanner
– 300 Hz Mirror Speed
– 360 °View Angle
– Highest Resolution:
• 1.25 mph
• 10,000 points/rotation
• 0.3 mm Crack Size
• 16 Ft. Optimal Distance
9
Implementation
Spacetec Technology
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
![Page 10: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/10.jpg)
• Capabilities
– Visual Image
• ID all distresses (tied to Station)
• Features (asset management)
– Thermal Image
• All moisture intrusions (tied to station)
• Debonding (possible)
– Profile
• Profile (xyz)
• Clearance
• Close inspection of damage (zoom, 3D) 10
Implementation
Spacetec Technology
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
![Page 11: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/11.jpg)
• Software (options to purchase license. But not necessary)
– TuView
• View/print mapped data
• Export to CAD
– TuDrive
• Virtual drive thru
• View and measure
analyzed data
– Tunnel-Inspector
• Comprehensive
• Mapping/statistical/printing
11
Implementation
Spacetec Technology
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Visual Channel Thermal Channel
![Page 12: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/12.jpg)
12
Research and Development Implementation
Testing of Pittsburgh Tunnels
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Liberty Tunnels Armstrong Tunnels
Liberty Tunnels: only NBTwo tubes, horseshoe profiles, two-12 ft lanes. Only NB tube testedAppx. length: 5,900 ft. 28.6 ft wide, max. height of 20.75 ftConcrete lining, 24 in. thick
Armstrong Tunnels: only NBTwo tubes, horseshoe profiles, two 12 ft lanes.Only NB tube testedAppx. length: 1,300 ft. Tile lining on the walls, concrete on the ceiling
![Page 13: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/13.jpg)
13
Research and Development Implementation
Liberty NB Tube
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Spacetec Scanner
PSPA
Spacetec Scanner:Full coverage. Only NB tube tested.Testing Speed: 1.25 mph (full coverage)Visual, 3D and Thermal imagesTest date: 09/21/15
Portable Seismic Property Analyzer (PSPA):Limited coverage. Point by point testing.Area of 200 ft. by 14 ft. tested (NB Tube).Testing Speed: 1 min/point. 200 points testedDynamic modulus and resonant frequency (IE)Test date: 11/05/15
![Page 14: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/14.jpg)
14
Armstrong NB Tube
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Spacetec Scanner
Spacetec Scanner:Full coverage. Only NB tube tested.Testing Speed: 1.2 mph (full coverage)Visual, 3D and Thermal imagesTest date: 09/21/15
![Page 15: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/15.jpg)
15
Post-processing/Analysis (Spacetec)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Visual Image of the Un-folded Tunnel
![Page 16: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/16.jpg)
16
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Visual Features
• Moisture (Cold Anomaly)
• Water intrusion (Cold Anomaly)
• Delamination & Debonding (Cold/
Warm Anomaly)
• Cracks < 1/8 in.
• Cracks > 1/8 in.
• Spalls
• Missing tiles
• Damage to ceiling/tiles
• Moisture
• Efflorescence
• Stalactites
• Visual Condition
• Other
features/Elements
Thermal Features
Tunnel Features to be “Mapped”
![Page 17: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/17.jpg)
Cold
Anomalie
s
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Visual Profile (Spacetec)
![Page 18: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/18.jpg)
Cold
Anomalies
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Thermal Profile (Spacetec)
![Page 19: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/19.jpg)
19
Post-processing/Analysis (Spacetec)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Visual/Thermal (Side-by-Side View)
![Page 20: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/20.jpg)
20
Post-processing/Analysis (Spacetec)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Liberty Tube: Debonding Results Not Conclusive (not enough thermal gradient)
![Page 21: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/21.jpg)
21
Post-processing/Analysis (Spacetec)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Armstrong Tube: Debonding Results Successful. (confirmed with sounding)
![Page 22: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/22.jpg)
Thermal data
indicates
presence of
moisture in the
ceiling while no such
indication is
observed in
the Visual data
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Sample Results (Spacetec)
![Page 23: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/23.jpg)
Thermal data
indicates a heat
source behind
the ceiling while
no such indication is
observed in the
Visual data
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Sample Results (Spacetec)
![Page 24: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/24.jpg)
water drippingfrom theceiling
Exact
location
(xyz) of any
anomaly can
be seen on the profile
data
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Sample Results (Spacetec)
![Page 25: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/25.jpg)
25
Post-processing/Analysis (Spacetec)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
![Page 26: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/26.jpg)
26
Post-processing/Analysis (Spacetec)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Zoom & 3D-View Capability
![Page 27: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/27.jpg)
27
Reporting (Spacetec)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Summary Results in Graphical & Tabular Formats
0
5
10
15
20
25
30
35
40
45
50
Co
un
t
Station
Crack area Crack < 1/8 inch Crack > 1/8 inch
0
2
4
6
8
10
12
14
16
18
20
Co
un
t
Station
Cold Anomaly Refurbished Honeycombing
![Page 28: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/28.jpg)
28
Reporting (Spacetec)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Summary Results in Graphical & Tabular Formats
0
50
100
150
200
250
Len
gth
[ft]
Station
Crack < 1/8 inch
0
20
40
60
80
100
120
140
160
Len
gth
[ft]
Station
Crack > 1/8 inch
![Page 29: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/29.jpg)
29
Asset Management Application (Spacetec)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
• See and Measure all features in
the tunnel including Signs,
Mechanical, Electrical and
Lighting Systems
• See and measure changes of
any particular feature in
consecutive inspections of a
tunnel (via an automatic
algorithm that highlights the
change)
![Page 30: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/30.jpg)
30
Post-processing/Analysis (PSPA)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
PSPA conducts two Analyses:Modulus analysis: determines the variation in modulus with depth of the exposed layer in the field (USW Method, ASTM C1383, ASTM C215)
Impact Echo (IE) tests: To obtain the frequency spectrum (as per ASTM C1383)
Source
Ultrasonic Sensors
Data Acquisition Card
and Power Supply
Temperature Sensor
Sensor 1 Sensor 2
![Page 31: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/31.jpg)
31
Post-processing/Analysis (PSPA)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Modulus Results:Dynamic/seismic modulus measured with PSPA can be approximately correlated with concrete strength. In general, larger modulus corresponds to larger strength.
A correlation can be obtained if compressive strength data available
Distance from Station 3+000 (ft)
Dis
tance f
rom
Gro
und (
in)
+300+310+320+330+340+350+360+370+380+390+400+410+420+430+440+450+460+470+480+490+50044
59
74
89
104
122
140
158
176
1500
2000
2500
3000
3500
4000
4500
5000
![Page 32: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/32.jpg)
Distance from Station 3+000 (ft)
Dis
tance f
rom
Gro
und (
in)
+300+310+320+330+340+350+360+370+380+390+400+410+420+430+440+450+460+470+480+490+50044
59
74
89
104
122
140
158
176
1
1.5
2
2.5
3
3.5
4
32
Post-processing/Analysis (PSPA)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
IE Results:Frequency domain of the seismic waves is analyzed.Larger variations from the dominant frequency indicate delamination/debonding
Intact vs. Debonded locations can be obtained.
![Page 33: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/33.jpg)
• AID is Spacetec’s representative and service
provider in North America.
• AID does not own the system yet!
• Scanners need to get shipped to US
• Cost depends on scan length (SL):
– Most tubes need to be scanned only once
(distance between scanner and any point <16’)
– 3.8 $/SL to 12 $/SL
33
Cost
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
![Page 34: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/34.jpg)
• Debonding is not full-proof! It can be detected
only if sufficient temperature gradient exists
(between debonded areas and the adjacent
areas) at the time of scanning.
• Probes can be inserted into tunnel walls to
determine the most optimum time, however:
– The ideal time for scanning may not correspond to
Authority’s desired time for closure
– Requires additional closure (for probe installation)
– Costs more! 34
Limitations
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
![Page 35: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/35.jpg)
• A mature/mobile system (SHRP2 study)
• A complete survey of all distresses (walls and
ceiling)
• A complete survey of all locations with
moisture intrusion
• An excellent tool for asset management
• See growth of distresses over time
• Tie profile to survey base-line
• Debonding, if sufficient temperature gradient
exists at time of scanning 35
Conclusions
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
![Page 36: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/36.jpg)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Drive-Thru Simulation (Visual)
![Page 37: SHRP2 R06G Implementation Phaseshrp2.transportation.org/documents/8a_SHRP2_R06G_NDT_tunnels_t… · a nch nch 0 2 4 6 8 10 12 14 16 18 20 t Station Cold Anomaly Refurbished Honeycombing.](https://reader033.fdocuments.net/reader033/viewer/2022060609/6060986b57b01116672b2285/html5/thumbnails/37.jpg)
SHRP2 R06G Pittsburgh TunnelsAdvanced Infrastructure Design (AID)
Drive-Thru Simulation (Thermal)