Project Management Session 5Scope Management Andre Samuel

Transcript of Session 5 Scope Management 2015-16 - Samuel...

Page 1: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

Project Management

Session 5‐ Scope ManagementAndre Samuel

Page 2: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

This Session

• Define Scope Management• Project Scope Management processes• Scope Creep• Work Breakdown Structure

Page 3: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

Project Scope Management

• Scope management is mandatory; without scope management there is no project

• “ensuring that enough, but only enough, work is undertaken to deliver the project’s purpose successfully” Turner (1999, pg. 93)

• Through the process of managing the scope the owner’s requirements are converted first into the definition of the new asset 

• Secondly, into a statement of the work required to construct and commission that asset

Page 4: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

• In the project context scope may refer to:– Product scope‐ the features and functions that characterize a product or service

– Project scope‐ the work that must be done to deliver a product with the specified features and functions

• Scope is developed from the project’s objectives and product breakdown structure

Page 5: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

Project scope statement includes the following:

• Product scope description‐ Progressively elaborates the characteristics of the product, service, or result described in the project charter and requirements documentation.

• Acceptance criteria ‐ A set of conditions that is required to be met before deliverables are accepted.

• Deliverable ‐ Any unique and verifiable product, result that is required to be produced to complete a process, phase, or project. 

Page 6: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

• Project exclusion ‐ Generally identifies what is excluded from the project. Explicitly stating what is out of scope for the project helps to manage stakeholders’ expectations.

• Constraints ‐ for example, a predefined budget or any imposed dates or schedule milestones that are issued by the customer or performing organization

• See handout on Scope of Work

Page 7: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

Using Breakdown Structures• Product Breakdown 

Structure (PBS)• Work Breakdown 

Structure (WBS)• Organization Breakdown 

Structure (OBS)

• A technique by which the project is divided and subdivided for mgt and control purposes

• ADVANTAGES• Better control of work 

definition• Work delegated in 

coherent package• Work can be defined at 

appropriate level for estimating

• Containment of risk

Page 8: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

WBS‐’Chunking’

• Hierarchical tree of all the tasks needed to complete a project

• Each level progressively gets more and more detailed until the bottom level is reached which shows all the smallest day to day tasks

• Maps out a view of  Project Stages, Phases, Work Packages, Activity ,Tasks or Steps

Page 9: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without
Page 10: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without
Page 11: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without
Page 12: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without
Page 13: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

WBS Exercise

• The construction of Office Spaces at IBIS POINT FORTIN BRANCH

• See handout for Statement of Scope of Works• Draw a WBS based on the specification

Page 14: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

OBS

• Identifies the team structure for carrying out the work

• All the people who are going to do the work

Page 15: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without
Page 16: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without
Page 17: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

Responsibility Charts

• Deliverables are shown as rows• Organizational units are shown as columns• Integration of Product Breakdown Structure (PBS), Work Breakdown Structure (WBS) and Organizational Breakdown Structure (OBS)

• See Handout 1 pg. 20 for sample

Page 18: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without
Page 19: Session 5 Scope Management 2015-16 - Samuel Learningsamuellearning.org/Project_Management_Slides/Session_5_Scope... · Project Scope Management •Scope management is mandatory; without

Scope Change Control

• Scope Creep‐ subtle changes made to product without approvals

• All change request should be documented and evaluated against the project constraints

• Essentially, an impact assessment• The assessment will determine whether or not the change would be implemented 

• Use change request forms, change control log