SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction...

17
SEQ Stabling Program Woombye CRG July 2016

Transcript of SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction...

Page 1: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

SEQ Stabling Program

Woombye CRG – July 2016

Page 2: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Project update – July 2016

Construction activities underway:

• Drainage and culverts

• Earthworks

• Capping placement

• Security fence footings

• Installing of electrical conduits

• Concrete foundations for overhead line

equipment (OHLE) and signals

Page 3: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Culvert outfall - west

Page 4: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Culvert backfill

Page 5: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

OHLE foundations

Page 6: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

OHLE footing concrete pour

Page 7: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Security fence footing formwork

Page 8: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Security fence footing formwork

Page 9: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Site overview looking north

Page 10: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Security fence panels

Page 11: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Earthworks

Page 12: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Earthworks

Page 13: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Earthworks

Page 14: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Earthworks

Page 15: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Turnout rail construction

Page 16: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Turnout rail construction

Page 17: SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction activities: • Security fence – footings, posts and panels • Capping import and

Project update – July 2016

Upcoming construction activities:

• Security fence – footings, posts and panels

• Capping import and placement

• Access road and car park works

• Inground services including hydraulics

• Track install – rescheduled due to weather