SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction...
Transcript of SEQ Stabling Program Woombye CRG July 2016...Project update – July 2016 Upcoming construction...
SEQ Stabling Program
Woombye CRG – July 2016
Project update – July 2016
Construction activities underway:
• Drainage and culverts
• Earthworks
• Capping placement
• Security fence footings
• Installing of electrical conduits
• Concrete foundations for overhead line
equipment (OHLE) and signals
Culvert outfall - west
Culvert backfill
OHLE foundations
OHLE footing concrete pour
Security fence footing formwork
Security fence footing formwork
Site overview looking north
Security fence panels
Earthworks
Earthworks
Earthworks
Earthworks
Turnout rail construction
Turnout rail construction
Project update – July 2016
Upcoming construction activities:
• Security fence – footings, posts and panels
• Capping import and placement
• Access road and car park works
• Inground services including hydraulics
• Track install – rescheduled due to weather