Second Report of Commonwealth Games Village

87
HIGH LEVEL COMMITTEE 2011 Commonwealth Games Village Second Report of HLC V IGYAN BHAWAN ANNEXE , NEW DELHI

description

All details of Commonwealth Games Village. Gupta Realty, Patparganj, New Delhi

Transcript of Second Report of Commonwealth Games Village

  • COMMONWEALTH GAMES VILLAGE

    2/11/2011

    Second Report of

    Second Report of HLC

    Vigyan Bhawan Annexe, New Delhi

    HIGH LEVEL COMMITTEE

    2011

    Commonwealth Games

    Village Second Report of HLC

    V I G Y A N B H A W A N A N N E X E , N E W D E L H I

  • Commonwealth Games Village

    Page 1

    Contents Chapter Particulars Page No.

    Acronyms 2

    Executive Summary 3

    1 Introduction 9

    2 Location of Games Village 14

    3 Planning and Bidding 21

    4 Project Development Agreement and Execution 31

    5 Bailout Package and Release of Funds 41

    6 Completion and Handover 69

    7 Main Findings 75

    8 Recommendations 81

    Appendix 1: List of Documents Reviewed 82

    Appendix 2: List of persons interviewed 85

    Annexures

  • Commonwealth Games Village

    Page 2

    Acronyms AGL Above Ground Level

    ACIL M/s Ahluwalia Contracts (India) Ltd.

    BSES Bombay Sub-urban Electric Supply

    CGV Commonwealth Games Village

    CGF Commonwealth Games Federation

    CFO Chief Financial Officer.

    CPWD Central Public Works Department

    COS Committee of Secretaries

    CW&PRS Central Water and Power Research Station

    DDA Delhi Development Authority

    DJB Delhi Jal Board

    DPCC Delhi Pollution Control Committee

    DUAC Delhi Urban Art Commission

    Emaar MGF M/s Emaar MGF Construction Private Limited

    FM Finance Member

    FAR Floor Area Ratio

    GoM Group of Ministers

    GoI Government of India

    HLC High Level Committee

    HIG High Income group

    ITDC Indian Tourism Development Corporation

    LIG Lower Income Group

    LG Lieutenant Governor of Delhi

    MCD Municipal Corporation of Delhi

    MIG Middle Income Group

    MoYAS Ministry of Youth Affairs and Sports

    MoUD Ministry of Urban Development

    MoEF Ministry of Environment and Forests

    NDMC New Delhi Municipal Council

    NEERI National Environmental Engineering Research Institute

    NOC No Objection Certificate

    OC Organizing Committee

    PIL Public Interest Litigation

    PPP Public Private Partnership

    PDA Project Development Agreement

    PD Project Developer

    PWD Public Works Department

    RFP Request For Proposal

    RFQ Request For Qualification

    SBI State Bank of India

    SC Supreme Court of India

    YJA Yamuna Jiye Abhiyaan

  • Commonwealth Games Village

    Page 3

    Executive Summary

    Nodal Agency for Games Village 1. Delhi Development Authority (DDA) is the nodal agency for urban planning and its implementation

    in Delhi. It has been the primary organization for undertaking urban development projects in Delhi

    since 1957.

    2. DDA was assigned the responsibility for development of the Games Village, arguably the most

    important infrastructure necessary for holding the Commonwealth Games, 2010. It was designed

    to accommodate about 8000 athletes and Team officials during the Games.

    3. The Games Villages residential zone was developed by M/s Emaar MGF Construction Private

    Limited (Emaar MGF). The residential zone consisted of 34 residential towers and 1168 apartments.

    The unit mix of the total apartments constructed was as under:

    Particulars 2 Bedroom 3 bedroom 4 Bedroom 5 Bedroom Total

    Number of

    apartments

    31 765 209 163 1168*

    *Source Data submitted by Emaar MGF to DDA (March-April 2009)

    Loss of Precious Time 4. While the Games were awarded to India on 13th November, 2003, by when the site for Games

    Village had also been frozen, the decision on the mode of development of the Games village was

    finally taken and agreed to by all stakeholders only by January 2006. This delay of over two years in

    finalizing the development strategy proved costly to DDA in so far as it prevented DDA from

    considering an alternative in the situation which emerged in 2008-09.

    Development Costs associated with Site 5. The site selected for the development of the Games Village suffered from several shortcomings,

    which got highlighted with the passage of time. Due to this particular location, the site necessitated

    an expenditure of about 633.06 crore on construction of an elevated road over Barapullah Nullah

    (linking CGV to JLN Sports complex), Flyover on NH 24 near the Games Village (to provide

  • Commonwealth Games Village

    Page 4

    uninterrupted ingress and egress into and from CGV) and noise barriers along NH24 and adjacent

    railway track. The details of the cost are in Chapter 2 of the Report.

    Project Execution in Public Private Partnership mode 6. According to DDA documents, the decision to adopt the PPP mode for developing the

    Commonwealth Games Village was taken keeping in view constraints of scale, time, quality,

    specifications and the need for 4000 rooms during the Games period. Based on their

    recommendation, Government approval for implementation of the project on a Public Private

    Partnership mode (PPP) was granted. However, the PPP mode of execution, little understood by

    DDA, was distorted to such an extent by the Project Developer and DDA that it virtually ceased to

    be a PPP project. Instead it became a project implemented by DDA and constructed by the

    Developer through a sub-contractor.

    Deviations from Model Concession Agreement in PDA

    7. DDA did not include certain key provisions of the Model Concession Agreement, in particular, those

    relating to (a) establishing an escrow account and, (b) audit in the Project Development Agreement

    (PDA) signed with the selected Project Developer. This significantly diluted the ability of DDA to

    monitor the implementation of the CGV project and make a proper assessment of the fund

    requirement of the Project Developer in 2009.

    Failure to meet Contractual Obligations 8. Emaar MGF sought concessions / relaxations not contained in the PDA. These included, inter- alia,

    extension on milestones and financial assistance. Emaar MGF contrived an emergency situation;

    DDA chose neither to enforce contractual rights nor to resist Emaar MGF demands.

    9. DDA spent substantial amount on items which were to be taken up by Emaar MGF and has to

    recover the amount from the Project Developer. The total amount due from Emaar MGF on

    account of quality issues and non-performance aggregates to 96.33 crore. However, this amount

    is under dispute. Details are in Chapter 6 of the Report.

  • Commonwealth Games Village

    Page 5

    Fallout of emergency situation

    10. According to the Project Development Agreement signed on 14th September, 2007, DDA and

    Emaar MGF were to share the residential apartments in the ratio of 1:2. This was effectively

    changed to 1:0.63 with the decision to bail out the Project Developer through purchase of 333

    apartments from Emaar MGFs share of the apartments. It should be noted that the Project

    Developer had asked for 321 crore as loan at normal rate of interest or purchase of 250

    apartments. It was DDAs decision to purchase 333 apartments.

    11. The Bailout package was premeditated, suggestive of the outcome preceding the process. DDA

    formed a Valuation Committee which, in turn, appointed two Independent Consultants to

    determine fund requirement of Emaar MGF and the value of apartments (in March 2009) for

    arriving at the number of additional apartments to be purchased by DDA. A Negotiation

    Committee, which was set up with the approval of LG, was unable to reach a mutually acceptable

    sale price with Emaar MGF. Emaar MGF, then addressed a letter to LG dated 22.04.2009 stating

    their readiness to accept a rate of 11,000 per sft which was endorsed with alacrity on 24.04.2009

    at a meeting chaired by LG, attended by Secretary and Joint Secretary, Ministry of Urban

    Development, Vice Chairman, DDA and Finance Member and Engineer Member, DDA. The locus

    standii of this Group to take such an important decision is not known. It is surprising that such a

    decision was not taken by the competent Authority: DDA. Such a major decision with large financial

    implications, not being taken by the competent authority, renders it suspect. It was referred to the

    Authority only in June 2009 after the Bailout Agreement had been signed in May, 2009.

    12. The Technical consultants, based on the project specifications, estimated the cost price of the

    project at 934.49 crore (excluding the land cost). This estimation was later ignored. In the process

    of finalizing a sale price, which was also agreeable to Emaar MGF, the sale price recommended by

    the Financial Consultants was revised several times to finally accommodate 10% cost of capital and

    15% Developers margin. It may be noted that as per industry norms, cost of capital is borne by the

    Developer. In the calculations, the sub-contract price of 1168.21 crore was accepted at face value

    even though no signed contract was shown to the Financial consultant.

    13. A copy of the sub contract between Emaar MGF and M/s Ahluwalia Contracts (India) Ltd., which

    was apparently not earlier available to the DDA, was obtained and referred to a Consultant of the

  • Commonwealth Games Village

    Page 6

    HLC. Based on this document, the TDS returns filed by Emaar MGF and the Project Report

    submitted to SBI by the PD, the Consultant has calculated that the total estimated Project Cost was

    1368.42 crore and the per sft. Cost, inclusive of Developers margin, should not have been more

    than 7829 per sft.

    14. Expert analysis of the cash flow statements of Emaar MGF Constructions Pvt. Ltd., Emaar MGF Land

    Ltd. and the Group for the years 2007-08, 2008-09 and 2009-10 reveal that the Project Developer

    did not really require the fund infusion from DDA for completion of the project and it was just a

    ruse for selling off a huge chunk of its share of unsold flats to a bulk buyer at a price that was

    acceptable to them and at a time when the real estate market was sluggish!

    Undue Favours to Project Developer 15. Some of the undue favours that were bestowed on the Project Developer by DDA are as under:

    (a) Purchase of apartments

    DDA purchased the apartments from Emaar MGF at the rate of 11,000 per sft, which was way

    higher than the rate of 7829 per sft. arrived at by the Consultant of HLC based on assessed

    cost of the Project or the market price of 9068 per sft arrived at by HLC. The sale price paid

    by DDA was also much higher than what had been recommended by the experts of DDA and

    the highest price initially recommended by the Valuation Committee, which was 9,720 per sft.

    Whether based on the assessed cost of the Project or the market price determined by HLC,

    the purchase of 333 apartments by DDA @ 11,000 per sft. caused undue financial gain for

    the Project Developer of an amount ranging between 134 crore to 220 crore.

    (b) Recovery from Customers

    The Valuation Committee based on the advice of the experts recommended to the Negotiation

    Committee that the funding by DDA to the Developer under the Bailout package should be net

    of the funds received by Emaar MGF from the sale of apartments. While this advice was noted,

    the Negotiation Committee failed to include any definitive clause in the Bailout package to

    ensure that cognizance of this stream of funds was taken while deciding the installment

    amount to be released by DDA to the PD.

  • Commonwealth Games Village

    Page 7

    (c ) Unauthorized payments

    The Bailout Agreement specified the expenditure which could be met through the funds

    received from the bailout package aggregating to 766.89 crore. Emaar MGF made payments

    to other Group companies, incurred marketing expenditure etc. (as indicated in their utilization

    certificate) which was not authorized and hence has been termed unauthorized expenditure

    by the Financial Consultant. As per the utilization certificate for the period ending 3rd March

    2010, such payments aggregated to 64 crore. Further, excess funds aggregating to 192.71

    crore from the Bailout package with Emaar MGF as on 31st March, 2010 were parked by the

    Developer in a short term investment fund.

    16. The summary of the financial favours/ loss to DDA by a series of decisions taken to support Emaar

    MGF are set out in the following Table:

    S.NO. Particulars Claim ( Crore) Reference

    I Non levy of Liquidated Damages on the Emaar MGF as per the Agreement terms DDA waived the damages

    81.45 Chapter 4

    II Bailout Package

    A Purchase of apartments at a very high rate of 11,000 per sft

    134.00 220.00 Chapter 5

    B Recovery from customers and sale of new apartments not reduced from the fund requirement for the project (as recommended by the Financial consultants to the Valuation Committee)

    686.34 Chapter 5

    C Unauthorized payments contrary to the Agreement 64.00 Chapter 5

    D Investments (as on 31st March, 2010) 192.71 Chapter 5

    Poor Monitoring 17. Although DDA had an oversight and monitoring responsibility, it failed to detect contract violations

    / other problems. Records reveal that on several occasions the Monitoring Committee discussed

    the significant delays and other related issues but the same were documented in a very

    perfunctory manner.

  • Commonwealth Games Village

    Page 8

    Box: 1 Games Village Saga

    DDA was the chosen agency for development of the Games Village for CWG, 2010. The Village was over-

    designed to accommodate 8000 athletes and officials while provision for 6000 would have been

    adequate. This was mentioned in the Report of the Evaluation Commission set up by CGF in October 2003

    itself.

    Over two years were frittered away in deciding the development strategy. Ultimately, it was decided to

    adopt the Public Private Partnership model for development of Games Village in January 2006 and the

    Project Development Agreement could be signed only in September, 2007.

    Trouble began to brew by early 2008 and in February, 2009, the Project Developer (Emaar MGF) formally

    sought financial assistance from DDA/Government. Bailout package was given to the Developer on his

    terms and conditions as by then DDA had concluded that it had no other viable option left if the Games

    Village was to be ready in time. So, as with other CWG projects, in the national interest DDA decided to

    forego terms and conditions of a valid legal document the Project Development Agreement and

    sacrifice its own interests.

    DDAs decision to purchase 333 apartments from Emaar MGFs share in 2009 only helped the Project

    Developer to offload his share of unsold flats in bulk at a price that was acceptable to him and was way

    above the prevailing market price. Funds made available by DDA in 2009-10 enabled the Project

    Developer to divert funds to various applications other than the CGV Project such as repayment of interest

    bearing loans, investment of surplus funds into mutual funds and transferring funds to other Group

    companies.

    Finally the Games Village was ready but at a huge cost. Key principles of PPP model were ignored and the

    only principle that remained was that risk and loss would be borne by DDA while profit would be of

    Emaar MGF.

  • Commonwealth Games Village

    Page 9

    Chapter 1: Introduction Bidding for the Games

    1.1 In May 2003 Government of India gave its nod to the Indian Olympic Association (IOA) to bid for

    the Commonwealth Games 2010 (CWG) at an estimated expenditure of 296 crore towards sports

    infrastructure and conduct of games, with expenditure on security and Games Village to be incurred by

    the Government and Delhi Development Authority (DDA)

    1.2 India was awarded the rights to host the Commonwealth Games (CWG) for 2010 by the

    Commonwealth Games Federation in November 2003.

    1.3 Indian Olympic Association/ Organizing Committee together with the Government of National

    Capital Territory of Delhi and Government of India entered into the Host City Contract with the

    Commonwealth Games Federation on 13th November, 2003 for holding of XIX Commonwealth Games

    in Delhi during 03-14 October 2010.

    1.4 The major responsibilities regarding the successful delivery of the XIX Commonwealth Games

    were of the OC, GNCTD and GOI. The major responsibilities of the stakeholders were as follows:

    Key Activities Stakeholders

    Sports Infrastructure Ministry of Youth Affairs & Sports; Govt. Of Delhi; Delhi

    Development Authority (DDA) and New Delhi Municipal

    Council (NDMC)

    City Infrastructure City Government; Municipal Council of Delhi (MCD) and

    NDMC

    Games Village Delhi Development Authority (DDA)

    Conduct and Delivery of Games Organizing Committee (OC)

    Host Broadcasting and Media Press

    Centre

    Prasar Bharati and Ministry of Information &

    Broadcasting

    Tourism and Accommodation for

    Tourists

    Ministry of Tourism

    Security Ministry of Home Affairs

  • Commonwealth Games Village

    Page 10

    Role of DDA

    1.5 DDA was created in 1957 under the provisions of the Delhi Development Act, 1957 to promote

    and secure the planned development of Delhi. The charter lists the following objectives as incidental

    and ancillary to the working and functioning of DDA:

    To formulate a Master Plan for covering the present and future growth of Delhi and to

    promote and secure the development of Delhi according to the plan covering all possible

    activities.

    To acquire, hold, manage and dispose of land and other property.

    To carry out building, engineering, mining and other operations.

    To provide services and amenities incidental to the above

    1.6 DDA was given the following mandate with respect to the XIX Commonwealth Games:

    Development of the Games Village for the accommodation of the participants during the

    Games;

    Development of the Yamuna Sports Complex;

    Development (including up-gradation) of the Siri Fort Sports Complex;

    Development of Vasant Kunj flats to accommodate tourists during the Games; and

    Development of 33 hotels to accommodate the projected tourists during the Games.

    Organizational Structure

    1.7 The present organization structure of DDA is illustrated in the following chart:

  • Commonwealth Games Village

    Page 11

    1.8 To ensure timely completion of the CWG projects, various divisions were created by DDA under

    the supervision of Director (Sports) and entrusted with the responsibility of construction of the same.

    Under this format, 13 divisions were formed.

    a. Division 1 - 9 : Responsible for civil work at various projects

    b. Division 10 - 13: Responsible for electrical work at various projects

    Governance Structure for CWG projects - DDA

    1.9 Various committees were constituted by DDA to monitor the progress and provide constant

    quality assurance with regards to the CWG project. Four major committees were constituted for this

    purpose, namely:

    Monitoring Committee (CGV)

    The Monitoring Committee was formed under the chairmanship of an Independent engineer,

    (who was unanimously elected by the two parties to the Agreement) and had Chief Engineer,

    SEZ, DDA and a representative of the Project Developer for the Games Village project, as

    members. The committee was mandated to meet every month to review the progress of work

    at the Commonwealth Games Village

    Chairman, DDA (LG of

    Delhi)

    Vice Chairman

    FinanceMember

    Engineer Member

    Principal Commissioner

    Principal Commissioner

    Principal Commissioner cum Secretary

    Chief Officers, Engineers ,

    Commissioners, & Directors

    Chief Legal Advisor

    Principal Commissioner

    (CWG)

    Commissioner Planning

    Chief Vigilance Officer

  • Commonwealth Games Village

    Page 12

    Stadia Committee

    The mandate prescribed for the Stadia Committee was to conduct regular meetings to address

    all issues relating to the development of the Games Village site. Weekly meetings were to be

    held to assess the progress of the project and resolve all project related issues relating to

    flyover, residential facility, temporary overlays, practice venues etc.

    Weekly Site Coordination Committee

    This committee was formed on 27th May 2009 by the Principal Commissioner (CWG) to facilitate

    internal co-ordination amongst the contractors, consultants and the DDA engineers and

    resolution of issues of mutual interest.

    High Powered Committee (HPC)

    The Vice Chairman, DDA constituted a HPC to monitor the progress regarding preparation for

    the Commonwealth Games. The committee was empowered to monitor and ensure early

    solutions of all issues relating to the Commonwealth Games. Following were the committee

    members:

    Finance Member, DDA - Chairman

    Engineer Member, DDA

    Pr. Commissioner (CWG), DDA

    Director Sports (Member Secretary), DDA

    Representative of Delhi Govt. (GNCTD)

    Representative of Organizing Committee, Commonwealth Games 2010

    Copies of orders constituting the above mentioned Committees are at Relevant Document 1.

    Scope of Report

    1.10 This Report reflects the findings and conclusions of the High Level Committee (HLC) on various

    aspects relating to the development of the Commonwealth Games Village for providing

    accommodation to the participating athletes and Team officials.

    1.11 The HLC through its team of officers / experts examined the performance of the DDA against

    the Terms of Reference of the Committee, with special focus on:

  • Commonwealth Games Village

    Page 13

    Planning and execution of development of Games Village execution and delivery with

    reference to time, cost and quality

    The effectiveness of the organizational structure and governance, in particular, within DDA

    Weakness in management, alleged irregularities, wasteful expenditure and wrongdoing in

    performance of the tasks assigned to DDA

    Criteria

    1.12 The HLC evaluated the management and performance of the key functions carried out by DDA

    in the background of reasonable timelines for initiating and completing the projects in accordance with

    established standards, generally accepted best practices and conformity to good governance.

    Methodology

    1.13 The key procedures carried out for the purpose of review were:

    a. Identification and examination of relevant file notes of DDA, Ministry of Urban

    Development, extracts of the Notes for Cabinet, records of the meetings of GoM, and

    correspondence on the subject matter. The list of documents reviewed is at Appendix 1.

    b. Interview with officers and functionaries responsible for planning, execution and

    monitoring of the CGV project. The list is placed at Appendix 2.

  • Commonwealth Games Village

    Page 14

    Chapter 2: Location of the Commonwealth Games Village

    2.1 The Games Village is located in Pocket III of Sub-Zone 6 of the River Yamuna, developed on an

    area of 59.28 hectare between river Yamuna and the flood protection bund on the eastern side.

    2.2 The HLC has been informed by DDA that the location of the Games Village was identified by the

    Planning Department of DDA in consultation with the then LG, Shri Vijai Kapoor, in the year 2003.

    However, there is no documentary evidence to suggest the type of inputs that were taken into account

    before it was concluded that the present location of the Games Village is the best available site.

    2.3 On 14th May, 2003, the LG in his letter addressed to the Chairman, Commonwealth Games

    Federation (CGF) mentioned that we have set aside land for building a brand new Games Village. A

    copy of the letter is at Annexure 1.

    2.4 Further, in his letter dated 22nd August 2003 to the Secretary, Department of Youth Affairs and

    Sports, Government of India (GOI), the LG stated that the site was showcased to the Evaluation

    Commission of the Commonwealth Games Federation (CGF) that had visited New Delhi in August 2003

    to evaluate the citys bid for Commonwealth Games 2010. There is a mention in the said letter that the

    site was liked immensely keeping in view its salubrious environs, its location vis-a-vis the competition

    sites and its location on the transportation map which will include metro line from NOIDA to the

    centre of the city by the year 2010. A copy of the letter is at Relevant Document 2.

    Box: 2 Excerpts from the Report of the CGF Evaluation Commission (October 2003)

    The DDA (Government) is constructing the Village on a pleasant and high quality site. No

    detailed architectural planning has been undertaken to date. A design competition will be

    conducted. 40 hectares of land has been reserved in the heart of Delhi.

    The proposed Village site adjoins the National Highway-24 and will be connected with the

    Mass Rapid Transit System (MRTS) and Electric Magnetic Unit (EMU) Trains.

    The estimated cost of construction of the Commonwealth Games Village will be Rs.185.8 crore

    (USD 38.8 million).

  • Commonwealth Games Village

    Page 15

    2.5 Subsequently, on 11th September 2003, Union Cabinet approved the site of the Games Village

    at the current location based on the proposal of LG.

    2.6 The HLC, based on the records made available to it, finds that the Union Cabinet was not

    provided with all the information regarding the pros and cons of the location of the Games Village. The

    Cabinet approval, therefore, seems to be based solely on the assertions made by the LG. Moreover,

    the Group of Ministers (GoM) merely acknowledged the decision of the Cabinet and asked DDA to

    make available strategy options for development of the Games Village in its 4th meeting held on 17th

    March, 2005.

    2.7 Once the site had the seal of approval of various authorities, what followed was a series of

    steps undertaken by DDA to regularize the decision.

    Change in Land Use

    2.8 The first step towards regularization of the site for development of the Games Village was in

    the form of change of land use of the earmarked area. Vide notification dated 2nd March, 20061, the

    land use of area measuring 42.5 hectares (105.0 acres) was sought to be changed from agricultural

    and water body to public and semi-public facilities. Further, vide notification dated 18th August,

    20062 (a modification of the earlier notification), the land use of an area of 16.5 hectares was changed

    to Residential for 11 hectares and 5.5 hectares to Commercial/ Hotel.

    2.9 Initially, DDA had proposed that hotels would also come up at the same site. However, this was

    opposed by Chairman, OC on the ground that it would be discriminatory to put up some athletes and

    Team officials in hotels and others in Games Village. On 19.11.2006 GoM agreed, in principle with the

    model where the residential accommodation for the athletes may be developed on a PPP model in the

    form of a residential complex with additional hotel accommodation being provided in close proximity

    to the Games Village which would assist OC officials in making arrangements for technical officials.

    1 See Relevant Document 3 2 See Relevant Document 4

  • Commonwealth Games Village

    Page 16

    2.10 Through February-August 2007, a NGO named Yamuna Jiye Abhiyaan (YJA) in its

    communication to several GOI ministries including MoUD, MoEF, and MYA&S had raised many

    pertinent issues relating to the location of the Games Village. YJA sought an appointment with these

    agencies, including the GoM, to discuss their submission of the issues highlighted; however, they were

    only given an audience by GoM during the 12th meeting held on 12th November 2007. By this time the

    GoM had taken all major decisions relating to the development of the Games Village at the site

    selected and the PDA had also been signed by DDA and Emaar MGF. Thereafter, any appeal to change

    the location of the Games Village could be brushed aside stating that the current time frame to

    develop the Games Village did not permit any deliberation on the matter.

    Alternative Sites

    2.11 Perusal of the presentation made by YJA to the GoM, indicates that it had suggested certain

    alternative sites, which included

    (a) Safdarjung airport

    (b) Jasola Sports complex and

    (c) Dwarka - Sector 20.

    While the HLC has not examined the suitability of such sites vis a vis the current site, it may be stated

    that the Government and DDA ought to have examined various options before zeroing in on the

    location of the Games Village. It may be pertinent to note that the Asian Games Village in 1982 was

    located within two kms. of the Jawahar Lal Nehru Stadium and hence faced minimal transportation

    problems. HLC has been informed that during the run up to the CWG 2010, there were suggestions for

    an alternative location close to Jawahar Lal Nehru Sports complex which, unfortunately, was never

    considered.

    Environmental Clearance

    2.12 At the first instance, MoEF granted conditional clearances vide its letter dated 14th December,

    20063. MoEF insisted that a study needs to be conducted to assess the impact of Akshardham bund on

    3 See Relevant Document 5

  • Commonwealth Games Village

    Page 17

    the area of flood plain in the upstream reaches of river Yamuna. Accordingly Central Water Power

    Research Station (CW&PRS) was entrusted with the study. CW&PRS submitted its report to MoEF in

    March 20074. The report indicated that the bund would cause insignificant flood problem upstream as

    well as in the region of the bund. Accordingly, MoEF amended its environmental clearance of 14th

    December 2006 and issued an amended letter on 29th March 20075.

    2.13 In January 2008, DDA made a reference to National Environmental Engineering Research

    Institute (NEERI) seeking their opinion on whether the proposed site for Games Village was part of the

    Yamuna Flood Plain and whether having complied with the MoEF conditions for environmental

    clearance, there would be any further threat of environmental degradation / loss of ground water

    recharge and /or if there are any additional abatement / measures required to be undertaken. The

    opinion indicated that the project posed insignificant risk6.

    2.14 Environmental clearances /reports, in particular NEERI Report, ought to be viewed in context of

    what happened during August September, 2010. It rained as it should; unfortunately for these

    agencies, more heavily than usual. Yamuna water including seepage compromised the site to a point

    where its use was in question unless the monsoon abated. Vestiges remain; the jury is still out on

    remedial measures, costs, responsibility et al.

    2.15 While the process of compliance with environmental issues may appear transparent at first

    glance, the HLC noted that DDA did not inform the following agencies / statutory authorities, which

    have regulatory role vis--vis the river Yamuna. These include:

    Yamuna Standing Committee (YSC) of Central Water Commission No approval

    accorded by the concerned authority with respect to the development of the Games

    Village as this project was never referred to it.7

    4 See Relevant Document 29 5 See Relevant Document 6 6 See Relevant Document 7 7 It may be noted that since October 2003, 19 projects had been cleared by the Yamuna Standing Committee including construction of elevated road over Barapullah Nallah but the Games Village Project was never referred to YSC of Central Water Commission for their approval. See Relevant Document 8.

  • Commonwealth Games Village

    Page 18

    Central Ground Water Authority (CGWA)

    Yamuna Removal of Encroachments Monitoring Committee

    Public Interest Litigation 2.16 Thereafter, a plethora of objections were raised and a Public Interest Litigation (PIL) was also

    filed. The issues addressed in the PIL were finally dismissed by the Supreme Court judgment dated 30th

    July 20098. The judgment was largely based on expert opinion. However, this case took considerable

    time of the various government authorities including MoEF, Ministry of Youth Affairs and Sports,

    Ministry of Urban Development and Poverty Alleviation, Government of Delhi and DDA as all had to file

    separate counter affidavits dealing with all the subjects including the apprehensions about the alleged

    damage to the ecology of the Yamuna riverbed, floodplain and other environmental hazards.

    Avoidable Development Cost

    2.17 As brought out in the preceding paragraphs, the process of regularization of the current site

    for development of the Games Village took considerable time and Government also had to bear

    possibly avoidable development cost of about 633.06 crore towards removing/mitigating inter alia

    transportation bottlenecks and noise pollution, which was highlighted by Mr. Mark Fennel, President,

    CGF. Details of such expenditure are as under:

    Particulars Expenditure

    ( in crore)

    Comments

    Additional Land requirement 21.34 DDA/ Ministry of Urban Development negotiated with the Government of Uttar Pradesh the purchase

    of land measuring 31.542 acres

    Bund Road 13.39 Widening and strengthening of the bund road between NH-24, Railway line near Akshardham

    temple

    Construction of flyover on the

    intersection of NH-24 and

    bund road near the Games

    Village

    90.77 The proposal for construction of the flyover was rejected by DUAC vide their letter dated 29

    th

    October, 2007 stating that keeping in view the short

    duration of the games with the volume of traffic and

    also with the Noida mode interchange which was

    8 See Relevant Document 9

  • Commonwealth Games Village

    Page 19

    approved and likely to be commissioned by 2010, the

    traffic during the games could be managed with

    suitable traffic management interventions. A copy of the Letter from DUAC is at Relevant Document 10.

    Noise Barrier 4.84 The CGF COCOM raised issue related to noise management at the selected site on account of

    railway line running close to the proposed village and

    the construction of flyover at the proposed

    intersection. OC had raised this issue in the 8th GOM meeting and recommended change of Games Village

    location. LG indicated that the change of site would

    not be possible. However, it was agreed that the

    issue of noise pollution would be taken care of. In order to mitigate the issue of noise, noise barriers

    were constructed on the side of the flyover and

    temporary noise barrier was constructed along the

    railway line.

    A copy of the relevant minutes of the GoM meeting is

    at Relevant Document 11.

    Elevated road over Barapulla

    Nullah

    440.00 As per the Chief Minister, Delhis submission to the GOM, the said flyover did not have any legacy value

    after it ceased to achieve its objective of connectivity

    of the Games Village to the Jawaharlal Nehru

    Stadium. However, the same was constructed as the

    decision for locating the Games Village was cited as

    an irreversible decision on account of limited time

    available before the commencement of the Games.

    A Copy of the letter from the Chief Minister is at

    Relevant Document 12.

    Extra Piles driven

    (proportionate cost)

    62.72 This expenditure relates to the extra piling work done by the project developer (M/s Emaar MGF

    Construction Pvt. Ltd.) due to soil conditions of the

    selected site. As against an approximate figure of

    2850 piles, approximately 14060 piles were driven for

    the structure of the residential complex.

    A copy of the letter from Emaar MGF giving the piles

    actually driven as against the estimates is at Relevant

    Document 13.

    TOTAL 633.06

    2.17 Based on the review of the documents and discussions with the DDA officials, the HLC is of the

    view that various options regarding suitable site for Games Village were not adequately examined and

  • Commonwealth Games Village

    Page 20

    documented, which indicates lack of informed decision making process. The site recommended by the

    then LG was accepted by OC, CGF, Cabinet and GoM at its face value. In fact, several steps had to be

    taken later to regularize the site for the purpose of development of the Games Village.

    2.18 The site, inter alia, had a number of constraints with respect to zoning, land ownership,

    Akshardham temple interface and transportation / access issues apart from the fact that it was located

    close to the Yamuna river. The flooding of the basements of the newly constructed residential towers

    in August September 2010, following heavy rainfall in Delhi served to highlight the potential danger

    that could be posed by Natures fury to buildings constructed in this fragile and vulnerable location.

  • Commonwealth Games Village

    Page 21

    Chapter 3: Planning and Bidding Planning

    3.1 It is evident from records that the site for the Games Village had been identified in May 2003

    itself and had been favourably commented upon by the Evaluation Commission of the CGF in its Report

    forwarded to all Commonwealth Games Associations in October 2003 ahead of the crucial vote for

    selection of Host City for CWG 2010 in November 2003. However, there is nothing on record to suggest

    that DDA undertook any activity relating to the development of Games Village at the identified site

    during the entire year 2004.

    Box: 3 Conclusions of Evaluation Commission regarding Games Village

    Based on the information provided by Delhi and independent expert analysis the Evaluation

    Commission has concluded the following in relation to the Village Plans.

    i. More detailed planning is required. However, the undertakings of Delhi provide sufficient

    comfort at this stage that a suitable Village will be developed.

    ii. When constructing a new site to act as a Village the planning for Games Operations Overlay is

    a major undertaking and is a significant financial commitment. The Village will require a large

    amount of physical space to support the operations of offices, logistical, and athlete service

    areas. The supply and fitout of these spaces will be additional to the cost of constructing the

    actual housing stock. The Commission, while provided comfort by the role of the DDA,

    stressed the need for Delhi to ensure that there is sufficient clarity as between the DDA and

    the future Organising Committee (and now the Bid Committee) to ensure that the Games

    times Operations Overlay is adequately financed.

    iii. Having an extra capacity of upto 2,500 bed spaces does not adversely affect the operation of

    the Village providing it does not cause excessive operational expenditure. It may be possible

    to use some of the surplus spaces for supporting CGA offices and other Village operational

    functions.

    iv. Some services (dining facility/capacity) may be over-scoped however this can be adjusted

    during more detailed planning.

    v. The configuration of bedrooms will be critical to determining if these housing requirements

    can be met in an operationally sound manner and needs to be contemplated in the planning

    process.

    vi. The proximity of the Village to the airport, city and the venues is excellent and will allow all

    athletes to live in one Village.

  • Commonwealth Games Village

    Page 22

    Delay in finalizing Development Strategy 3.2 GOM in its 4th meeting held on 17th March, 2005 instructed DDA to make available two or three

    strategy options to develop the Games Village for the consideration of the GOM. Accordingly, DDA on

    19th April, 2005 submitted the concept paper which provided for the accommodation for 7000 athletes

    and officials in the residential zone which could be utilized post Games as hotels, hostels / apartments.

    A copy of the concept paper is set out as Relevant Document 14.

    3.3 It has been stated that DDA held detailed deliberations with almost all major real estate

    developers, NHAI, Ministry of Urban Development and Planning Commission before they finalized the

    PPP structure of the project. According to DDA officials, the decision to adopt the PPP mode for

    developing the Commonwealth Games Village was taken keeping in view constraints of scale, time,

    quality, specifications and availability of 4000 rooms during the Games period. DDA was of the view

    that it was not possible to develop the residential facility through other options such as auction of land

    or self development.

    3.4 Subsequently, GOM in its 6th meeting held on 8th September, 2005 directed DDA to prepare

    three options for the Games Village including the option relating to its possible use as Games Village

    for Asian Games 2014, in consultation with Organizing Committee (OC). Vice Chairman, DDA made a

    presentation to the GOM in its 7th meeting held on 27th September, 2005 wherein it was proposed that

    the facilities would be developed under the Public-Private-Partnership framework to ensure

    commercial viability. Further, the OC was asked to complete the consultation process with regard to

    the Games Village and venues by 15th October 2005, after discussion with the stakeholders and submit

    their views to the Ministry for placing them before the GOM for consideration.

    3.5 GOM finally decided in the 9th meeting held on 4th January, 2006 that the Games Village would

    be developed on the Public Private Partnership (PPP) model. A copy of the GoM decision is at

    Annexure 2.

    3.6 Thereafter, DDA engaged M/s. Pricewaterhouse Coopers Pvt. Ltd. (PwC) on 16th June 2006 to

    provide expert advice and consultation services with respect to the development of the Games Village

    under the PPP model. The report was submitted by the consultants in August 2006.

  • Commonwealth Games Village

    Page 23

    3.7 Thus, it is clear that there was unacceptable delay in formulating a strategy to develop the

    Games Village and almost three years were lost even after the site had been finalized in the year 2003

    itself.

    3.8 This delay in planning for the Games Village did not leave any room for addressing

    contingencies in an effective manner. As the subsequent events revealed, grave consequence of poor

    planning was witnessed in more areas than one. Some instances are -

    Even when there was extremely poor response to the RFP from reputed developers who

    felt that the time period for project completion was too tight, DDA could not explore

    alternatives;

    DDA had to be content with selection of a project developer even when there was only

    a single successful bidder who had no past record of actual completion of any

    residential project in India.

    DDA had to succumb to the demands of the Project Developer for funding the project.

    3.9 Based on the planned timeline, the total time available for the project development from the

    date of signing of the Agreement was 30 months (September 2007 March 2010).

    Box: 4 Why PPP?

    The reasons for taking the decision to develop Commonwealth Games Village in Public Private Partnership

    mode by DDA are unclear.

    DDA was and is the premier agency undertaking Housing schemes in Delhi and reportedly has a 2/3rd market

    share. Its specialization lies in design, development and construction of housing projects for all sections of

    society. It had developed the Asian Games Village for accommodating athletes and officials during 1982 Asian

    Games.

    DDA reportedly had huge cash reserves. Thus, it had the expertise and the funds to develop the

    Commonwealth Games Village. It had zeroed in on the site and had also been identified as the Nodal Agency

    for developing the Games Village by the Union Cabinet in September 2003 itself.

    Thus, it defies logic why it did not initiate action in this regard in early 2004 and decided to adopt PPP mode

    when there was no precedent in the real estate sector and wherein DDA had no expertise.

  • Commonwealth Games Village

    Page 24

    An Artists impression of the Residential Towers in Commonwealth Games Village, Delhi

    Bidding Process for selection of the Project Developer

    3.11 The selection of the Project Developer (PD) under the PPP model was based on a two-stage

    tendering process.

    (1) Short-listing of the qualified developers through inviting expression of interest from

    interested parties

    (2) Inviting detailed proposal from shortlisted developers

    3.12 The timelines for the bidding process and selection of the project developer is set out below:

    Particulars Date Comments

    Request for Qualification (RFQ) 4th Dec., 2006 During the process a pre-bid meeting was

    conducted by DDA to clarify any doubts of

    developers and invite suggestions Over 30

    developers participated.

    Last Date for submission of RFQ 12th January,

    2007

    15 bidders submitted their response by the

  • Commonwealth Games Village

    Page 25

    Particulars Date Comments

    last date and time.

    Short listing of Bidders 19th January,

    2007

    After evaluation by the committee formed

    for this purpose, 11 parties were qualified

    and notified by DDA.

    Request for Proposal (RFP)

    24th April, 2007 RFP issued. A Copy of the RFP is at Relevant

    Document 15.

    Pre Bid Meeting 15th May, 2007 Pre Bid meeting with Qualified Parties.

    Last Date for receiving Bids 25th May, 2007 No bid was submitted by the submission date. Last date extended to 15th June, 2007

    Relaxation of terms of RFP 7th June, 2007 Relaxation of some of the terms of the RFP by the High Powered Committee

    Addendum to RFP document 8th June, 2007 Addendum to RFP document issued by DDA incorporating the relaxations agreed to in the meeting of HPC on 7th June.

    Revised Last Date for submission

    of Bids

    15th June, 2007 Two bids submitted post the relaxation M/s DLF Ltd. And M/s Emaar MGF Construction Pvt. Ltd.;

    Opening of Bids & Report of

    Technical Evaluation Committee

    15th June, 2007 Bid of M/s DLF Ltd. Bid was found non-responsive and hence disqualified. Only ONE developer qualified Consortium of Emaar MGF

    Issue of LOI 5th July, 2007 DDA issued LOI to Emaar MGF.

    Signing of PDA 14th September,

    2007

    DDA signed the PDA with Emaar MGF

    The above stated sequence of events highlights the poor response to the proposed project by

    experienced Developers and, finally, there was only a single valid bid for the project.

    3.13 During the Pre Bid Meeting held on 15th May, 2007, several queries were raised by the

    prospective Bidders and the clarifications issued by DDA on the same during the Pre-Bid Meeting along

    with concessions announced in the Addendum are represented in the Table below and in Para 3.13:

  • Commonwealth Games Village

    Page 26

    S.No. Question Raised Clarifications

    provided

    Subsequent changes

    incorporated in

    Addendum to RFP/

    concession provided to

    Emaar MGF

    1 Compensation for delay in

    milestone completion should

    be based on fair assessment

    of delay & causes &

    Developer alone should not

    be held liable

    Specific reference

    made to Annexure - 3

    Compensation for delay

    was lowered and was

    refundable to the PD after

    completion of the

    milestone.

    2 Suggestion to lower the

    penalty amounts as per

    suggestions

    No specific reply given

    by DDA, only

    reference is made to

    the concerned

    Annexure & Clauses

    Lowered thereafter vide

    Addendum to RFP issued

    by DDA on 8.6.2007.

    3 Request to extend the first

    milestone considering the

    extensive work involved &

    the delay that could occur

    due to the monsoon season.

    Further the request clearly

    laid out that such extension

    may not delay any further

    milestones.

    DDA extended the

    time for completion of

    first milestone from

    D+120 days to D+150

    days.

    Timelines were extended

    further after starting the

    construction of the

    Project.

    4 Request for extension of

    time limit of the milestone

    for construction &

    completion of the Mock-up

    Unit.

    DDA extended the

    time for completion of

    first milestone from

    D+120 days to D+150

    days.

    The level of achievement

    of first 2 Milestones was

    relaxed by the Addendum

    to RFP.

    5 Clarifications regarding

    layout and construction work

    w.r.t filling of earth &

    conceptual clarity

    DDA specified no

    earth filling is required

    & referred to

    structural drawings

    and other

    architectural material.

    -

  • Commonwealth Games Village

    Page 27

    S.No. Question Raised Clarifications

    provided

    Subsequent changes

    incorporated in

    Addendum to RFP/

    concession provided to

    Emaar MGF

    6 Number of returning

    performance security

    payments may be increased

    in terms of achieving every 2

    milestones, so that it reduces

    the burden on the PD in

    terms of paying interest to

    the banks.

    Please refer to Section

    II, Instructions to

    Bidders, Clause E

    Approved thereafter vide

    Addendum to RFP issued

    by DDA.

    It will be noticed from the Table above that several critical suggestions made at the time of the Pre-Bid

    meeting with 11 selected / qualified bidders were later relaxed and the Addendum was issued on 8th

    June, 2007, which was just seven days prior to the revised last date for submission of bid. The period

    provided for submission of bids, after the Addendum had been issued, appears to be inadequate.

    Changes in Request for Proposal (RFP)

    3.14 In its meeting dated 7 thJune, 2007, following important relaxations were made

    by the High Powered Committee (HPC) and major modifications were made in the RFP

    document, which are as under :

    Percentage share of DDA in the total number of apartments was reduced from 50% to

    33.3%

    Sharing methodology block by block

    Bank guarantee for performance security reduced to 400 crore from 500 crore

    Upfront amount remained at minimum of 300 crore but payment schedule relaxed.

    First two Milestones relaxed.

    Penalty for delay in achievement of Milestones was relaxed from 25 lakh to 20 lakh

    per day after first 15 days of delay.

    Deletion of third penalty slab of 50 lakh per day after 30 days of delay

  • Commonwealth Games Village

    Page 28

    A copy of the minutes of the HPC is set out as Annexure 3.

    3.15 It may be noted that even the modified provisions in the RFP did not lead to active participation

    and only two bids were received. One of the two bids received from M/s DLF Ltd. (DLF) was found to

    be non-responsive on grounds of it being conditional and, hence, rejected by the Evaluation

    committee. A copy of the bid (letter) submitted by DLF is set out as Annexure 4. It is pertinent to note

    that against the reserve price of 300 crore for the land in the RFP, the amount quoted by the single

    bidder was only 321 crore. It is very likely that in case competitive bidding had taken place, this

    amount would have been substantially higher. To that extent, DDA has been a loser.

    3.16 At this stage there was no serious deliberation in the DDA for evaluating the capability of the

    project developer to deliver on the contractual obligations considering the fact that Emaar MGF had no

    past record to demonstrate the delivery of any successful residential project in India. Based on the

    Draft Red Herring prospectus issued by Emaar MGF Land Pvt. Ltd. (Parent company) on 30th

    September, 20109, the company was at that time yet to complete any residential project in India.

    3.17 A due diligence exercise based on common sense and financial prudence was of prime

    importance as the timely completion of this project was critical to the organization of the

    Commonwealth Games. The HLC was informed by the Finance Member, DDA that most developers

    having extensive experience in the Indian market were of the opinion that the timelines were very

    tight and the financial terms were not attractive, the penalty clauses were very severe and not in line

    with market practice.

    3.18 Given the circumstances described above, it was imperative that DDA should have put in place

    a contingency plan to mitigate the risk of the developer failing to deliver on the Agreement.

    3.19 The HLC, based on the sequence of events, finds that while the entire competitive bidding

    process evoked poor response, no other option for the development of Games Village was seriously

    explored before 2006. Even within the selected solution, further options to attract a larger base of

    experienced developers were not explored. The HLC also finds it intriguing that DDA did not deliberate

    9 Extracts are at Relevant Document 16.

  • Commonwealth Games Village

    Page 29

    or seriously consider the option of developing the Games village by itself, one of the two options

    recommended by its consultants.

    3.20 If the objective was not to take on the financial burden or financial risk of the project, then DDA

    failed to achieve its objectives as they ended up doing both infusing funds to complete the project

    and carrying the financial risks of the project as explained in subsequent chapters.

  • Commonwealth Games Village

    Page 30

  • Commonwealth Games Village

    Page 31

    Chapter 4: Project Development Agreement and Execution Public Private Partnership (PPP)

    4.1 The Report of the PPP Sub-Group on Social Sector by Planning Commission states that a Public-

    Private-Partnership (PPP) provides an opportunity for private sector participation in financing,

    designing, construction and operation & maintenance of public sector programmes and projects.

    4.2 Public-Private-Partnership or PPP is a mode of implementing government programmes /

    schemes in partnership with the private sector. The term private in PPP encompasses all non-

    government agencies such as the corporate sector, voluntary organizations, self-help groups,

    partnership firms, individuals and community based organizations. PPP, moreover, subsumes all the

    objectives of the service being provided earlier by the Government, and is not intended to compromise

    on them10.

    4.3 PPP is an approach, under which services are delivered by the private sector (non-profit / for-

    profit organizations) while the responsibility for providing the service rests with the Government11.

    4.4 To sum up, for this project the defining element of a PPP model is that the private party would

    bring in technical, financial and project management skills and the public agency would monitor,

    ensure accountability and timely completion of the project. The financial risk was to be carried by the

    private party.

    Project Development Agreement (PDA)

    4.5 The PDA, which was said to have been modeled on the approved PPP concession agreement,

    was signed on 14th September, 200712 between DDA and M/s Emaar MGF Construction Private

    Limited.

    10 Report of the PPP Sub-Group on Social Sector by Planning Commission, GoI; published in 2004 11 Report of the PPP Sub-Group on Social Sector by Planning Commission, GoI; published in 2004

  • Commonwealth Games Village

    Page 32

    4.6 The HLCs review of the PDA showed that several key clauses related to accountability of the

    private developer and subsequent monitoring mechanisms were not included in the PDA. Such clauses

    form a part of the standard Model Concession Agreement as prescribed by the Planning Commission

    and are extensively used in most infrastructure projects (port, railways etc.) executed on the PPP

    model. Considering the fact that this project was the first of its kind in the real estate sector and

    especially for DDA, prudence demanded inclusion of risk mitigation norms in the Agreement. The

    exclusion of such clauses provided little or no recourse to DDA to detect early signals of problems in

    the development of Games Village. Ironically, the PDA included a non-intrusion clause that prevented

    the DDA from effectively monitoring this critical project for the Commonwealth Games 2010.

    Deviations from Model Concession Agreement

    4.7 The key clauses in accordance with the Model Concession Agreement which were not included

    in the PDA and its implications are set out below:

    Escrow account The clause for maintaining an Escrow account is understood to be

    critical for all PPP agreements. An escrow account plays a critical role to ring fence the

    funds for the project. This was particularly important in this project as the PDA allowed

    the sale of apartments during the period of construction, the proceeds of which were to

    be used to fund the project. Therefore, a sound monitoring system should have been

    provided to ensure that all revenues accruing from the sale of apartments were

    available for completion of the project.

    Absence of an escrow account effectively restricted the ability of the DDA to monitor

    financial parameters and periodic transfers of funds by PD to Emaar MGF Land, the

    parent company.

    Audit and Accounts - The importance of the Audit and Accounts clause is that it enables

    the public party to have access to the books of accounts of the project and if required to

    12 A copy of PDA is at Relevant Document 17

  • Commonwealth Games Village

    Page 33

    audit the accounts of the project. This is a tool used for effective monitoring and control

    over the project executed under the PPP model. Also, in the CGV project this would

    have enabled DDA to get the actual cost of construction when fixing the price for

    purchase of apartments.

    A copy of the Model Concession Agreement recommended by the Planning Commission with respect

    to the two clauses is at Relevant Document 18.

    Risk Assessment & Mitigation

    4.8 Risk assessment and mitigation measures are standard pre-requisites in Project Management

    especially where outputs have to be delivered within a prescribed time frame.

    4.9 DDA failed to undertake risk assessment exercise at several stages of decision making related to

    the development of the Games Village including evaluation of options, selection of a credible

    Developer and ensuring accountability of the Developer.

    4.10 The execution of a PPP contract does not reduce the responsibility and accountability of the

    public agency and public servants concerned. On the other hand, it places substantial responsibility on

    them to see that the arrangement succeeds in safeguarding public interest by managing the PPP

    economically, efficiently and effectively. The absence of the monitoring provisions in the PDA reflects

    Box: 5 Public Private Partnership in Commonwealth Games Village Project?

    DDA decided to develop the Commonwealth Games Village Project in the PPP mode. The Project

    Development Agreement was signed with the selected Project Developer, Emaar MGF on 14th

    September, 2007.

    The way this PDA was executed by DDA accorded a new meaning to Public Private Partnership

    altogether. Here, finally

    all risk was borne by DDA;

    all comforts, legal and financial, were provided to Project Developer by DDA;

    the Developer was able to recoup his investment even before completion of the project;

    defects had to be rectified by the DDA;

    DDA had to bear the cost of blocked capital.

  • Commonwealth Games Village

    Page 34

    the lack of understanding of the risks involved as evidenced by inadequate risk management process

    on the part of DDA. It may be noted that the occurrence of certain future events, primarily the Bailout

    package to the PD, could have been anticipated and pre-empted. To illustrate, the Project

    Development Agreement could have included the clause regarding escrow account. Such an account

    normally requires maintaining of a defined average fund over a period of time. Absence of this

    account resulted in DDA not detecting early signs of possible financial crisis faced by the PD and

    thereby afforded inadequate time for a more deliberated option under the situation. Further, the

    escrow account would have ensured transparency in the project financing as all project related

    revenue and expenditures could have been properly monitored.

    4.11 In the absence of risk assessment and mitigation strategy, DDA could not take remedial steps

    for any potential or actual failure of the developer. Instead, at every instance, the Developer stage

    managed situations exerting pressure on DDA to take decisions that eventually turned out to be

    weighed in favor of the PD.

    Execution of the PDA

    4.12 The PDA recognized 9 milestones in the execution of the Project. Various committees were

    constituted to monitor the progress and provide constant quality assurance with regards to the

    project. Three major committees were constituted by DDA namely:

    Monitoring Committee

    Stadia Committee

    High Powered Committee

    Third Party Quality Assurance by CBRI, Roorkee was also put in place.

    Monitoring Committee

    4.13 The Monitoring Committee formed by DDA included representatives of Emaar MGF and DDA as

    members and was chaired by an Independent Engineer who was unanimously elected by the two

    members.

  • Commonwealth Games Village

    Page 35

    4.14 The committee held 32 meetings over a span of 29 months from its inception on 30th January,

    2008 till the last meeting held on 31st July 2010. The committee was mandated to meet every month to

    review the progress of the project, resolve any issues, and facilitate work on the project and record

    completion of milestones.

    Stadia Committee

    4.15 The mandate prescribed for the Stadia Committee was to conduct regular meetings to address

    all issues relating to the development of the Games Village site. The meetings were held weekly to

    assess the progress of the project and to resolve issues relating to the project site and flyover,

    residential facility, temporary overlays, practice venues etc.

    4.16 These meetings were held on a weekly basis till August 2010, after which daily meetings were

    held in view of the directive given by DDA.

    High Powered Committee

    4.17 The committee was constituted by the VC, DDA and was empowered to find and ensure rapid

    resolution of all issues relating to the Commonwealth Games.

    Third Party Quality Assurance by CBRI, Roorkee

    4.18 The PDA also prescribed regular inspection and supervision of the project by a Third Party

    Quality Assurer (QA) to verify the quality of construction and carry out regular supervision of

    construction work carried out by the PD independently of both parties to the Agreement. The PDA

    required that such appointment be within 6 months of entering into the Agreement, and accordingly

    CBRI, Roorkee were appointed.

    4.19 As per contract, the QA was required to inspect the site on a monthly basis and thereafter

    provide Monthly Quality Assurance Reports to DDA and the PD. These reports served as a benchmark

    for DDA engineers and were forwarded to the PD, who was required to comply with the specific issues

    raised therein. In response, the PD was required to furnish Action-Taken reports on such issues and

    to rectify the structural & quality lapses. The reports were supported by photographs & other

    technical data.

  • Commonwealth Games Village

    Page 36

    Ineffective Monitoring

    4.20 Based on the documentation available it has been noted that there was a delay of 2 months

    from the date of signing of PDA and the actual date of appointment of the QA. Further, the frequency

    of the reports was reduced from monthly to quarterly effective January 2009 without any formal

    communication to this effect from DDA.

    4.21 Review of the Minutes of the Meetings held reveal that the issues and concerns regarding the

    development of the Games Village were documented in a perfunctory manner. The first meeting of the

    Monitoring Committee took place on 5th April 2008, after the Project Developer had missed his first

    milestone and sought revisions13.

    4.22 The oversight and monitoring functions by the committees set up by DDA were ineffective as

    several defects and quality issues relating to the construction of the residential zone by the Project

    Developer continued to persist.

    Milestones

    4.23 The Project Milestones were laid down in the RFP issued for the project. It was stipulated that

    these timelines need to be adhered to and severe liability/ penalty shall be levied in case of default or

    deviation from such dates. However, as the project execution progressed, the project timelines were

    regularly revised at the behest of the PD and these were approved by DDA without documentary

    support or evidentiary proof necessitating such revisions.

    Non Levy of Liquidated Damages

    4.24 Although PDA did not provide for extension of milestones, DDA extended timelines for

    achievement of milestones and did not impose penalty as per the PDA. On account of such decisions,

    DDA has foregone 81.45 crore in favor of Emaar MGF. Details are set out in the Table below:

    13 See Minutes of the First Meeting of Monitoring Committee placed at Relevant Document 19.

  • Commonwealth Games Village

    Page 37

    S.No. Milestone Original Date

    of

    completion

    Actual Date of

    completion

    Delay

    (Number

    of days)

    Liquidated

    damages

    foregone ( in

    crore)

    1 Foundation work (including

    Plinth Level) up to Plinth

    level for 33% of blocks

    11th Feb,

    2008

    11th May,

    2008

    90 17.25

    2 Structure work up to G+2

    level

    11th May,

    2008

    10th Aug,2008 91 17.40

    3 Structure work up to terrace

    level, with associated

    electrical works & B.W. up to

    G+4 level

    07th Nov,

    2008

    29th Jan.,

    2009

    83 15.85

    4 Completion of brick work up

    to terrace level & internal

    plaster, flooring, etc. for 5

    levels, with associated

    electrical works

    06th May,

    2009

    15th Sept,

    2009

    132 25.65

    5 Completion of flooring &

    furnishing, with associated

    electrical works of all blocks

    all levels upto terrace level

    02nd Nov,

    2009

    02nd Dec, 2009 30 5.25

    6 External finish of all blocks &

    all levels

    01st Jan,

    2010

    01st Jan, 2010 0 0

    7 Completion of all electric

    work including lifts, ESS etc.

    & completion of UGR/ Pump

    Rooms/ Lifts/ Pump sets etc.

    31st Jan, 2010 31st Jan, 2010 0 0

    8 Completion of all

    development work including

    landscaping

    02nd Mar,

    2010

    13th Dec, 2010 286 DDA has filed

    for recovery as

    the extension

    was not

    approved

    9 Project Completion Date 01st April,

    2010

    13th Dec 2010 254 DDA has filed

    for recovery as

    the extension

    was not

    approved

    TOTAL 81.45

  • Commonwealth Games Village

    Page 38

    4.25 It is evident from above that nearly all achievement dates were delayed barring Milestones 6 &

    7. It is pertinent to note that all delays, except Milestones 8 & 9, were permitted by DDA without

    levying liquidated damages as provided in the PDA. DDA has issued a claim letter to Emaar MGF in

    October 2010 setting out the recovery of liquidated damages on account of delays related to

    milestones 8 and 9 alone as per the PDA14.

    Construction of excess FAR

    4.26 The site selected for the CWG Village had an approved FAR of 1.67 initially, which was increased

    to an FAR of 2.00 by the Delhi City Master Plan 2021 which came into force effective 07th February,

    2007. The Project was thus approved with a built up FAR of 2,05,140 square meters by the Building

    Section of DDA on 18th March, 200815.

    4.27 However, an actual FAR of 2,30,689.33 square meters was built as per the plan submitted by

    Emaar MGF for obtaining Completion certificate from DDA. The Developer, therefore, constructed an

    FAR of 25,549.33 square meters in excess of the approved plans. This was almost 12.5% more than the

    approved FAR. This was in the knowledge of the Monitoring Committee of DDA at least from January

    2009 (See item 3 in Table above) and also the top officers of DDA including Vice Chairman and LG

    from April, 2009 when the Bailout Package was being finalized.

    4.28 Again, belatedly DDA took a stand on this matter by issuing a Sealing - cum- Demolition notice

    only on 20th August, 2010 in respect of the excess constructed area. Reacting to this notice, the PD had

    filed a case with the Appellate Tribunal of MCD (Order dated 26th October, 2010 of Appeal No. 549 &

    550/ATMCD/2010) which ruled in favour of the PD and advised them to file for a new completion

    certificate. The Tribunal also stated that such lapse is compoundable by DDA within a limit of 5% of the

    permissible FAR on payment of prescribed charges by the PD. A copy of the judgment is at Relevant

    14 See Annexure 5. 15 See Relevant Document 20.

  • Commonwealth Games Village

    Page 39

    Document 21. DDA has filed an appeal against the Order of the Tribunal in the Court of LG and the case

    is still pending.

    4.29 The issue of delayed milestones, approvals to waive liquidated damages without justification on

    record and construction of excess FAR point to the ineffectiveness of the monitoring regime set up by

    the DDA and complicity of DDA officials. These issues incidentally were NEVER placed on the agenda of

    any of the meetings of the Monitoring Committee by any of the several officers specifically stationed at

    the project site by DDA.

    Box: 6 Actual Ground Coverage & Floor Area of Commonwealth Games Village

    (in sq. m.)

    A. Total (Residential Towers + Club /Community Centre

    i. Permitted Ground Coverage (as per PDA) = 36,663.89

    ii. Sanctioned Ground Coverage (27,664.19 + 1438.13) = 29,102.32

    iii. Sanctioned Floor Area (203087.25 + 2052.75) = 2,05,140.00

    iv. Existing Ground Coverage (225900.70 + 3032.06) = 2,28,932.76

    v. Extra Floor Area constructed beyond sanction limit = 23,792.76

    B. Residential Towers:

    i. Existing Floor Area (considered in FAR calculation) at site = 2,25,900.70

    ii. Sanctioned Floor Area (FAR) = 2,03,087.25

    iii. Constructed Floor Area (FAR) under DDAs possession = 1,34,819.48

    Constructed FAR in respect of 11 Towers (1/3rd ) as per PDA = 73,771.90

    Constructed FAR in respect of 333 flats purchased by DDA subsequently =61,047.53

    iv. Total Floor Area in possession of Developer:

    Balance sanctioned FAR under Developers possession (ii iii) = 68,267.77

    v. Extra Floor Area = 22,813.45

    C. Club / Community Area

    i. Existing Floor Area of the Club = 3032.06

    ii. Sanctioned Floor Area = 2052.75

    iii. Extra Floor Area = 979.31

    (Source: Data provided by DDA)

  • Commonwealth Games Village

    Page 40

    Box: 7 Salient Features of the Games Village at a Glance

    No. of residential towers - 34

    No. of 2/3/4/5 bedroom apartments 1168

    Date of signing Project Development Agreement 14.09.2007

    Scheduled Date for Completion 31st March, 2010

    Actual Date of Completion 13th December, 2010

    No. of residential apartments to be shared between DDA and Emaar

    MGF as per PDA in the ratio 1:2

    Ratio of flats to be shared between DDA & Emaar MGF after Bailout

    Package 1:0.63

    No. of apartments finally allocated to DDA after Bailout Package 715

    No. of apartments finally remained with Emaar MGF 453

    Total cash infusion by DDA in Games Village Project 728.89 crore

    Total cash infusion by Emaar MGF in Games Village Project 595

    crore

    No. of apartments sold by Emaar MGF till 28th December, 2010 - 426

    Money raised through sale of 426 apartments by Emaar MGF 1354

    crore

  • Commonwealth Games Village

    Page 41

    Chapter 5: Bailout Package and Release of Funds Background

    5.1 The PDA did not provide for any financial assistance to the PD. However, on the persistent pleas

    of the PD and in order to ensure that the Games Village project could be completed within the planned

    timeframe, DDA entered into a separate Agreement with Emaar MGF to provide financial assistance.

    Brewing Trouble

    5.2 The signs of inability of Emaar MGF to complete the Games Village surfaced as early as January

    2008. These included:

    a. According to the PDA the lead partner of the consortium (Emaar PJSC) was required to

    bring in the equity (26%) within six months from the date of issue of Letter of Intent

    (LOI); while the LOI is dated 4th July 200716, the equity was brought in only on 8th

    February 2008, a delay of 31 days from the agreed deadline date.

    b. According to the PDA, the date for achievement of first milestone was 11th February

    2008. Emaar MGF sought extension till 11th May, 08 and the same was granted by the

    HPC on 21st April 2008. The first milestone was achieved on 11th May 2008. This

    situation was more worrisome considering DDA had extended a relaxation to the

    Developer in the form of permission to begin the construction work at the site while the

    PDA was not executed. Even though the PDA was signed only on 14.09.2007, DDA

    handed over the site to Emaar MGF on 20th August 2007. A copy of the minutes of HPC

    meeting dated 21st April, 2008 is set out as Annexure 6.

    16 See Relevant Document 22.

  • Commonwealth Games Village

    Page 42

    c. In April 2008, Emaar MGF indicated financial problems to DDA and requested pre-

    ponement of allocation of flats. The key premise of Emaar MGF for assistance at this

    stage was its inability to raise funds via advances from the sale of apartments to

    customers, due to non-allotment of the flats. It may be highlighted that the allotment of

    apartments between DDA and Emaar MGF based on the apportionment formula as per

    the PDA was scheduled for 14th June 2008 and such a demand for early allotment was

    therefore not warranted.

    Chronology of Events leading to Bailout Package

    5.3 A chronology of events leading to the signing of the Bailout Agreement between DDA and the

    Project Developer, Emaar MGF, is as under:

    S. No. Date Event

    1 3 r d November, 2008 Decision of Delhi High Court 17

    2 5 th December, 2008 Letter of Emaar MGF to DDA seeking f inancial

    assistance 18

    3 8 th December, 2008 Meeting of Emaar MGF with Secretary, MoUD

    4 9 th December, 2008 Shri Sanjay Malhotra, on behalf of Emaar MGF addressed a letter 19 to Secretary, MoUD wherein they, inter alia, mentioned that due to the recent directions given by the Honble High Court of Delhi in the matter of the CGV project, there has been an adverse fallout on the project in terms of banks/lenders to the projects and the customers (present and potential) raising concerns on the further development of the project. DDA was requested to assist the project by provid ing funding support, which is most crit ical for further

    17 See extracts at Annexure 7 18 See Annexure 8 19 See Annexure 9

  • Commonwealth Games Village

    Page 43

    progress.

    4 10 th December, 2008

    Shri Sanjay Malhotra, on behalf of Emaar MGF addressed another letter 20 to Secretary, MoUD enclosing requests made to DDA as requested by your office

    5 10 th December, 2008

    Secretary, MoUD forwarded details of assistance sought by Emaar MGF group to Shri Arun Ramanathan, Finance Secretary, GoI for appropriate facil itation. 21

    6 11 th December, 2008

    Director (DD), MoUD sought comments of DDA on issues raised in letters of Sanjay Malhotra, Chief Operating Officer, Emaar MGF. 22

    7 18 th December, 2008

    Pr. Comm.(CWG) informed COO, Emaar MGF that in the l ight of Clause 8.8 of the Project Development Agreement, their request for f inancial assistance cannot be accepted.23

    8 10 th February, 2009 Emaar MGF in its letter to DDA sought return of 321 crore as loan

    at nominal rate of interest or suggested that DDA buy 250

    apartments keeping in view the requirement of funds at that

    stage24.

    9 17 th February, 2009 Issue discussed in Meeting of COS.

    10 12 th March, 2009 LG provided in principle approval for 25

    Outright purchase of apartments by DDA from PD

    Constitution of Committee with experts from NBCC, CPWD,

    SBI Capital and DDA to determine the total funding

    requirement and the purchase price of the apartments.

    In response to the PDs request, vide letter dated February 27,

    20 See Annexure 10 21 See Annexure 11 22 See Annexure 12 23 See Annexure 13 24 See Relevant Document 30 25 See Annexure 14

  • Commonwealth Games Village

    Page 44

    2009 of advance of Rs.150 crore, a part payment of Rs.100

    crore may be made under a MoU, which would be adjusted at

    a later stage once the cost of the apartments to be bought as

    determined.

    11 16 th March, 2009 PC (CWG) wrote a letter to Secretary, MoUD on the issue of f inancial assistance to the Project Developer. 26 Reference is made to economic slowdown.

    12 18 th March, 2009 Constitution of Valuation Committee

    13 19 th March, 2009 Valuation Committee briefed by PC (CWG), DDA

    14 25 th March, 2009 LG ordered that in providing the advance of Rs.100 crore, f inancial interest of DDA should be fully secured

    15 26 th March, 2009 DDA asked the PD to provide a Bank Guarantee of Rs.100 crore valid t i l l the date of f inal ization of the purchase agreement, in addit ion to providing an unconditional corporate guarantee, encumberance certif icate from ROC for 75 apartments proposed to be kept at the disposal of DDA and action plan for util iz ing the advance amount.

    16 26 th March, 2009 PD expressed its inabil ity to provide a BG of Rs.100 crore and offer unconditional corporate guarantee to DDA

    17 30 th March, 2009 Shri Mukesh Dham, wrote to Secretary, MoUD wherein he referred to their previous discussions and the funding challenges being faced by the CGV Project due to the l it igation on the project as well as economic slowdown. He also complained thatA committee was formed on 21 s t March 2009 to submit its report within 7 days. We have been providing al l the information required by them, but to date report has not been submitted by the Committee. 27

    26 See Annexure 15 27 See Annexure 16

  • Commonwealth Games Village

    Page 45

    18 30 th March 2009 Note sent by Secretary, MoUD to VC, DDA seeking details of resolution worked out so that t imely implementation of project does not suffer. 28

    19 6 th April , 2009 VC, DDA sent a detai led Note to Secretary, MoUD. 29

    20 9 th April , 2009 Recommendation of Valuation Committee received.

    21 15 th April , 2009 Constitution of Negotiation Committee

    22 22n d Apri l , 2009 Emaar MGF wrote to LG 30

    23 23 r d Apri l , 2009 Meeting held in chamber of VC where Financial experts were cal led and asked to provide for 15% Developers margin on total Project Cost and 10% as cost of capital towards the funds invested by Emaar MGF and finally arrived at a rate of Rs.11,055.64/ - per sft .31

    24 24 th April , 2009 Meeting held under chairmanship of LG which is attended by Secretary and Joint Secretary, MoUD and VC, Finance Member & Engineer Member, DDA which decided the purchase price of f lats under Bailout Package.

    25 5 th May, 2009 Bai lout Agreement signed.

    No CWG Village Bogey

    5.4 In November - December 2008 and January February 2009, Emaar MGF made repeated

    requests to DDA as well as Ministry of Urban Development to provide financial assistance for

    completion of the project. Such requests were rejected by DDA as the PDA did not provide for financial

    assistance. However, in February 2009 Emaar MGF exerted pressure on DDA and cited consequence of

    non-completion of the Games Village within the stipulated time period i.e. 31st March 2010. This led to

    28 See Annexure 17 29 See Annexure 18 30 See Annexure 19 31 See Detailed Background Note at Annexure 20

  • Commonwealth Games Village

    Page 46

    a situation termed by DDA as critical which, according to the LG and Cabinet Secretary, required an

    out of box solution.

    5.5 In its submission to DDA and MoUD in December 2008, Emaar MGF referred to the PIL filed in

    the court against the location of the Games Village stating that the litigation had caused negative

    impact on the project and thereby affected its ability to raise funds for the project.

    5.6 A PIL had been filed and the High Court had issued a notice on 17th July, 2007. The case came

    up for hearing in the High Court only on 9th June, 2008. The High Court passed its judgment on

    3.11.2008. The Court observed that any construction made or third party rights created are at the

    peril and risk of the organizers / Government. DDA filed a SLP in the Supreme Court against this order.

    The interim stay of the Supreme Court was dated 5th December, 2008 which was finally disposed off on

    30th July, 2009. However, at no stage did the High Court or the Supreme Court order suspension of

    the work at the project site.

    5.7 While HLC took note of this submission, it is of the opinion that the entire risk of execution of

    the project was on the Developer and transferring the onus to DDA merely exhibited its inability to

    manage the project.

    5.8 In February 2009, DDA finally took serious note of the developers financial situation and its

    inability to complete the project within the stipulated time. At this stage DDA, in consultation with LG

    and COS, agreed to explore the possibility of financing the project. The COS in its meeting on 17th

    February, 2009 agreed that DDA could explore the option of purchase of flats with due approvals from

    the competent authority.

    Box: 8 Meeting of COS held on 17.02.2009

    At the COS meeting held on 17th February, 2009 to review arrangements related to CWG 2010, it was noted by the

    COS that the LG, Delhi had already given approval to DDA for making purchase of flats out of its own funds. Cabinet

    Secretary observed that an out of box solution may have to be resorted to. It was inter alia decided that

    Option of purchase of flats in the Games Village by DDA may be explored with due approvals duly obtained

    from competent authorities, to help the private developer in overcoming working capital shortfall, as the

    ongoing economic slowdown warrants unconventional options to be given consideration on merits. However,

    proper valuation of flats should be arranged through an independent agency in a transparent manner.

    It is worthwhile noting that the COS considered a decision already taken by the LG and correctly pointed out that in

    such a transaction the proper valuation of flats in a transparent manner would be extremely important.

    Unfortunately, this operational portion of COS decision was not ensured by DDA.

  • Commonwealth Games Village

    Page 47

    5.9 Based on the decision taken by LG on 12th March, 2009, a Valuation Committee comprising of

    representatives from HUDCO, NBCC, CPWD and DDA was formed on 18th March, 200932 to recommend

    within 7 days the rate at which the flats could be purchased and the funding requirement of the

    project. The Valuation Committee, in turn, engaged a Technical consultant (M/s Garg & Associates) and

    a Financial consultant (M/s K N Goyal & Asso