1
Second Avenue Subway
Quarterly Public Workshop
February 25, 2015
![Page 2: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/2.jpg)
2 MTA Capital Construction
• Overall Construction Progress is 78.7% complete as of 2/1/2015.
• All 10 SAS Contracts have been awarded for Phase 1
• 5 Construction Contracts Completed: − Tunnel Boring Machine Tunneling − 86th St Excavation, Utility Relocation, and Road Decking − 96th St Site Work and Heavy Civil − 72nd St Cavern Mining, Tunnels and Heavy Civil (1/14/14) − 86th St Cavern Mining & Heavy Civil (12/16/14)
Current Project Status
![Page 3: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/3.jpg)
3
96th Street Proposed Art Installation Artist – Sarah Sze, MTA Arts & Design commissioned work
Station Renderings
63rd Street Mezzanine Fare Array
72nd Street Platform Level
86th Street Mezzanine - South Goto http://www.mta.info/SAS and click on Vision Gallery
3
![Page 4: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/4.jpg)
4 4
Community Information Center & Community Tours
Hours Monday: 10AM - 6PM Tuesday: 11AM - 7PM Wednesday: 10 AM - 6PM Thursday: 11AM - 7PM Friday: 10AM - 6PM Saturday: 11AM - 3PM* Sunday: Closed Closed most public holidays *Open the second Saturday of every month.
• 9,300 visitors to date • 48 presentations to school groups with over 1,375 students attending • New exhibit coming in March 2015 • Community Tours- we have hosted 47 tours with 1,493 participants
Opened July 2013
![Page 5: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/5.jpg)
5 MTA Capital Construction
96th Street Station Area
![Page 6: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/6.jpg)
6 6 Above ground Ancillary 1 work at 93rd Street – January 2015
![Page 7: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/7.jpg)
7 96th Street Ancillary 1 Rendering NE corner 93rd Street and Second Avenue
7
![Page 8: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/8.jpg)
8
96th Street Station Area - Utility Installation 93rd – 94th Street & Second Avenue Looking South January 2015
Twin 42” Water Main
30” Gas Main Con Ed Electric
60” Water Main
8
![Page 9: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/9.jpg)
9
Backfill over Utilities 95th – 96th Street and Second Avenue 9
![Page 10: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/10.jpg)
10 MTA Capital Construction
86th Street Station Area
![Page 11: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/11.jpg)
11
11
86th Street Station Mezzanine and Platform Dec. 2014 Looking North
86th Street Milestones
Oct. 3, 2014
All blasting completed on contract and entire Phase 1 project
Nov. 19, 2013
April 10, 2014
Completed dismantling of 83rd - 84th Street Muck House
Aug. 8, 2014
Completed casting of concrete arch ceiling
Completed dismantling of 86th - 87th Street Muck House
Highlight Completed 96% of lower mezzanine slabs in cavern
Dec. 16, 2014
Cavern Mining and Heavy Civil contract substantially completed
11
![Page 12: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/12.jpg)
12 Muck House removal at 86th Street and Second Avenue October 3, 2014
May 2014
12
![Page 13: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/13.jpg)
13 MTA Capital Construction 13 Yorkshire Building at 86th Street and Second Avenue January 28, looking East
![Page 14: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/14.jpg)
14
New 20 foot sidewalks poured on 86th Street
between 1st and 2nd Avenues, East of Yorkshire building
86th Street Station Area
14 Looking east
![Page 15: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/15.jpg)
15 MTA Capital Construction
72nd Street Station Area
![Page 16: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/16.jpg)
16 MTA Capital Construction
72nd Street Station Area
New fence wrap installed in January between 69th and 70th Streets, looking south.
![Page 17: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/17.jpg)
17
72nd Street Station Area
Ancillary 2/Entrance 2 at northwest corner of 72nd Street and Second Ave 17
![Page 18: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/18.jpg)
18
72nd Street Entrance 2 / Ancillary 2 Rendering NW corner 72nd Street and Second Avenue
![Page 19: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/19.jpg)
19 19
72nd Street Station - Mezzanine Public Area Looking North at 69th Street
Ductwork
Arch Ceiling
Electrical Conduits Ventilation Ducts
![Page 20: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/20.jpg)
20 MTA Capital Construction
Lexington Ave / 63rd Street Station Area
![Page 21: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/21.jpg)
21 MTA Capital Construction
Pre repair Post repair
Sidewalk repair 163 E. 63rd Street
Lexington Ave/63rd Street Station Area
21 Looking east towards Third Ave Looking west towards Lexington Ave
![Page 22: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/22.jpg)
22
Water treatment tanks removed from the eastside of Third Avenue between E. 62nd and E. 63rd Streets.
Lexington Ave/63rd Street Station Area
![Page 23: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/23.jpg)
23
Lexington Ave/63rd Street Station Station rehabilitation includes new track wall tiles, ceilings and lighting Lower Level Platform - February 2015
23
![Page 24: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/24.jpg)
24 MTA Capital Construction
Streetscape “Visioning” Process
![Page 25: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/25.jpg)
25
Streetscape “Visioning” Process
• MTACC wanted to give the community something better
• Numerous meetings, emails and calls with city agencies, including DOT and Parks
• Community input solicited at a November 3rd workshop
• Meeting with CB8 Second Avenue Subway Taskforce and CB11 Transportation Committee members to select streetscape components
• Full CB8 board meeting on February 18th
MTA Capital Construction
![Page 26: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/26.jpg)
26
Typical Pre-Construction Block
MTA Capital Construction 26
![Page 27: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/27.jpg)
27 MTA Capital Construction
For conceptual purposes only. Placement and selection of specific street elements to be decided.
Concept Rendering Post-Construction Block
![Page 28: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/28.jpg)
28
City Light
![Page 29: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/29.jpg)
29
Street Trees: Large Canopy Linden Bald Cypress Sweetgum Zelkova
• Red/bronze fall color
• One of the most common street trees • Yellow fall color
• Strong pyramidal shape • Orange/brown fall color
• Strong, yellow fall color
5-inch diameter trees will be used whenever possible
![Page 30: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/30.jpg)
30
Street Trees: Columnar Form
Fastigiata Oak Zelkova Musachino
![Page 31: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/31.jpg)
31
Street Trees: Small Understory
Serviceberry Eastern Redbud Japanese Tree Lilac
Community Board committees decided to let Parks Department make decisions as appropriate
![Page 32: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/32.jpg)
32
Rail Guards for Tree Pits
MTA Capital Construction
![Page 33: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/33.jpg)
33
City Benches
MTA Capital Construction
![Page 34: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/34.jpg)
34
Bicycle Rack
MTA Capital Construction
![Page 35: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of](https://reader034.fdocuments.net/reader034/viewer/2022042319/5f08fb557e708231d424a97e/html5/thumbnails/35.jpg)
35
Way-Finding Signage To be installed by DOT at SBS Bus Stops
MTA Capital Construction