Second Avenue Subway Newsletter Announcements Issue XXXII – December 2014 72nd Street Station Area Subscribe! Want to stay most informed? Send your email address to outreach@2AveSubway. com to sign up for our e-news distribution list. Be sure to specify “72nd St Station Area.” A new, larger crawler crane is expected to be delivered to the Ancillary 1 work zone (northwest corner of 69th Street and Second Avenue) in early December. To advance progress on Entrance 1 (Northeast corner of 69th Street and Second Avenue) the contractor will need to implement a new pedestrian walkway between 69th and 70th Streets on the east side of Second Avenue. This new walkway configuration will relocate pedestrians into the street, behind barriers, and may go in to effect as early as this month. CIC HOURS of OPERATION Monday: 10 a.m. – 6 p.m. Tuesday: 11 a.m. – 7 p.m. Wednesday: 10 a.m. – 6 p.m. Thursday: 11 a.m. – 7 p.m. Friday: 10 a.m. – 6 p.m. Saturday: 11 a.m. – 3 p.m. (second Saturday of each month) SAS Community News Community Information Center The Second Avenue Subway Community Information Center (CIC) is located at 1628 Second Avenue, between E. 84th and 85th Streets. Open Saturday, December 13th, 11 a.m. – 3 p.m. Coming in December 2014 A Review of SAS Progress Tom Peyton, Second Avenue Subway Construction Director, the man who directs the entirety of the Second Avenue Subway construction project, will present an overview of progress in 2014. The presentation will highlight construction milestones completed in 2014 and anticipate milestones that MTA Capital Construction expects to achieve in the coming year. MTA Second Avenue Subway Community Information Center (CIC) 1628 Second Avenue, between 84th and 85th Streets Thursday, December 18, 2014 6:00 p.m. ADA-Accessible Facility Sub-basement slab has been poured at Ancillary 1 (northwest corner of 69th Street and Second Avenue.

Transcript of Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Newsletter 72nd-Dec_2014.pdfThe Second...

Page 1: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Newsletter 72nd-Dec_2014.pdfThe Second Avenue Subway Community Information Center (CIC) is located at 1628 Second Avenue,

Second Avenue SubwayNewsletter

Announcements

Issue XXXII – December 2014

72nd Street Station Area

Subscribe!Want to stay most informed? Send your email address to outreach@2AveSubway. com to sign up for our e-news distribution list. Be sure to specify “72nd St Station Area.”

A new, larger crawler crane is expected to be delivered to the Ancillary 1 work zone (northwest corner of 69th Street and Second Avenue) in early December.

To advance progress on Entrance 1 (Northeast corner of 69th Street and Second Avenue) the contractor will need to implement a new pedestrian walkway between 69th and 70th Streets on the east side of Second Avenue. This new walkway configuration will relocate pedestrians into the street, behind barriers, and may go in to effect as early as this month.

CIC HOURS of OPERATIONMonday: 10 a.m. – 6 p.m.Tuesday: 11 a.m. – 7 p.m.Wednesday: 10 a.m. – 6 p.m.Thursday: 11 a.m. – 7 p.m.Friday: 10 a.m. – 6 p.m. Saturday: 11 a.m. – 3 p.m. (second Saturday of each month)

SAS Community News

Community Information CenterThe Second Avenue Subway Community Information Center (CIC) is located at 1628 Second Avenue, between E. 84th and 85th Streets. Open Saturday, December 13th, 11 a.m. – 3 p.m.

Coming in December 2014 A Review of SAS ProgressTom Peyton, Second Avenue Subway Construction Director, the man who directs the entirety of the Second Avenue Subway construction project, will present an overview of progress in 2014. The presentation will highlight construction milestones completed in 2014 and anticipate milestones that MTA Capital Construction expects to achieve in the coming year.

MTA Second Avenue Subway Community Information Center (CIC)1628 Second Avenue, between 84th and 85th StreetsThursday, December 18, 20146:00 p.m.ADA-Accessible Facility

Sub-basement slab has been poured at Ancillary 1 (northwest corner of 69th Street and Second Avenue.

Page 2: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Newsletter 72nd-Dec_2014.pdfThe Second Avenue Subway Community Information Center (CIC) is located at 1628 Second Avenue,

72nd StreetStation Finishes

Contractor:Judlau Contracting Inc.

Budget:$271.3 Million

Notice to Proceed Date: September 2013

Contract Forecast Completion: June 2016

Project Overview

72nd Street Station Area – December 2014Second Avenue Subway Newsletter

Follow the SAS project on the MTA website at http://mta.info/sas

72nd Street Station - Entrance 1 at 69th Street and Second Avenue.

The future 72nd Street Station will have three new entrances including 11 escalators, and five street-level ADA accessible elevators at the southeast corner of 72nd Street and Second Avenue. Work in this area included construction of the station cavern and tunnels from the 72nd Street Station to the existing Lexington Av/63rd Street Station. This contract included the demolition of the buildings for ancillary locations at 72nd Street and 69th Street, and required utility relocation for the installation of support of excavation walls. The completion date of this contract was April 2014.

The follow-on contractor has taken over all work zones and will complete the mezzanine, platform, ancillary structures, station entrances, and the mechanical, electrical, and plumbing systems for the station. The estimated completion date of this contract is 2nd quarter 2016.

MONDAY-FRIDAY: 7:00 a.m. to 10:00 p.m.

SATURDAY: 10:00 a.m. to 7:00 p.m. (as needed)

Work is permitted underground 24 hours.

For concerns regarding Second Avenue Subway construction activities after business hours or on weekends please use the SAS 24/7 hotline # (212) 792-9716

Construction Update

Work Hours

Main Station Cavern:• Concretepours,installationofprecastwallpanels,andinstallationofconduitsattheplatformlevel• Mechanical,electricalandplumbingsystemsinstallation• Installationofsubwayoperationsandmaintenancerooms• ConstructionprogressstatisticsasofNovember21: - Upper mezzanine concrete placed: 100 percent - Lower mezzanine concrete placed: 100 percent - Platform concrete placed: 91 percent

Entrance 1: • ExcavationworkforEntrance1constructionwithin301E.69thStreetgarageisapproximatelysixty-fivepercentcomplete.• WorkzonechangestoallowfortheEntrance1streetexcavationandconstruction,thiswillincludeanewpedestrianwalkway configuration• Installationof“SupportofExcavation”wallforstreetentrance

Ancillary 1, Ancillary 2, Entrance 3• ConcretepumpingatAncillary1,Ancillary2andEntrance3• ShotcretetrimmingatEntrance3tofacilitateconstructionofelevatorshaftwalls• ConstructionprogressstatisticsasofNovember: - Waterproofing at Ancillary 1, Ancillary 2, and Entrance 3: 95 percent - Entrance 3 concrete placed: 41 percent - Ancillary 2 concrete placed: 52 percent - Ancillary 1 concrete placed: 26 percent

Miscellaneous• InstallationofnewShopSecondAvenuefencewrapalongstreet and sidewalk work zone fencing• Temporaryworkzonechangesforanewcraneandtoallowthe removal of decking within Ancillary 1 work zone (northwest corner of 69th Street and Second Avenue)• Concretetruckstagingasneededbetween74thand76thStreets