Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and...

78
Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary School 24 Hazel Wolf K-8 at Pinehurst 35 Olympic Hills Elementary School 45 Seattle New World School at TT Minor 51 New Thornton Creek Building 63 November 20, 2015 Seattle Public Schools Building Excellence IV Projects Under Construction

Transcript of Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and...

Page 1: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Project Slide Number

Arbor Heights Elementary School 2

Cascadia Elementary School & Robert Eagle Staff Middle School 13

Genesee Hill Elementary School 24

Hazel Wolf K-8 at Pinehurst 35

Olympic Hills Elementary School 45

Seattle New World School at TT Minor 51

New Thornton Creek Building 63

November 20, 2015

Seattle Public Schools Building Excellence IV Projects Under Construction

Page 2: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Arbor Heights Elementary School Elementary School

• Site: Canopy column footings are being backfilled at the south side of North Building. Asphalt demolition and grading for landscaping and playfield is underway at the west side of the site.

• South Building: Exterior sheathing is ongoing at floor 1. Light-gauge metal framing continues at the exterior and interior walls at floors 2 and 3. Roofing installation is ongoing. Mechanical, plumbing, fire-sprinkler and electrical rough-in are ongoing at floors 1 and 2.

• North Building: Structural steel welding is ongoing. Roof joists installation is on-going.

• Arbor: Structural Glu-Lam columns/beams are getting erected.

Page 3: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Arbor Heights Elementary School Site Plan

July 1, 2015 July 10, 2015

Page 4: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Arbor Heights Elementary School Aerial View from the South

November 3, 2015

Page 5: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Arbor Heights Elementary School South Building First Floor Insulation

November 12, 2015

Page 6: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Arbor Heights Elementary School South Building Third Floor Exterior Wall Framing

November 12, 2015

Page 7: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Arbor Heights Elementary School South Building Third Floor Interior Wall Framing

November 16, 2015

Page 8: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Arbor Heights Elementary School North Building Vapor Barrier at Gymnasium and Cafeteria

November 16, 2015

Page 9: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Arbor Heights Elementary School North Building Mechanical Mezzanine

November 12, 2015

Page 10: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Arbor Heights Elementary School North Building Roof Joists

November 12, 2015

Page 11: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Arbor Heights Elementary School North Building Roof Joist Welding

November 12, 2015

Page 12: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Arbor Heights Elementary School Arbor Glu-Lam Columns

November 16, 2015

Page 13: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Cascadia Elementary School & Robert Eagle Staff Middle School

Site: Pouring concrete curbs at parking lots and prepping for placement

of asphalt.

ES: Pouring concrete slab on grade; re-installed 2nd and 3rd murals at

permanent locations; concrete footings complete.

MS: Pouring concrete footings and concrete stem walls.

SPU Licton Springs Flood Reduction Project: Successfully completed –

neighborhood streets are no longer flooding during 25 year storm

events.

Page 14: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Cascadia Elementary School & Robert Eagle Staff Middle School Site Plan

Page 15: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Cascadia Elementary School & Robert Eagle Staff Middle School Aerial Photo

November 3, 2015

Page 16: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Cascadia Elementary School & Robert Eagle Staff Middle School 2nd Mural Being Relocated to Permanent Location at Elementary School

November 10, 2015

Page 17: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Cascadia Elementary School & Robert Eagle Staff Middle School 3rd Mural Being Set at Permanent Location at Elementary School

November 12, 2015

Page 18: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Concrete Slab on Grade with Mural Placed on South Side

November 13, 2015

Page 19: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Concrete Brace Footings, Looking North

November 12, 2015

Page 20: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Parking Lot Subgrade Prep, Looking West

November 12, 2015

Page 21: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Underground Utilities, Looking East

November 12, 2015

Page 22: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Cascadia Elementary School & Robert Eagle Staff Middle School New Stormwater Intake Structure at Licton Springs Park

November 9, 2015

Page 23: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Cascadia Elementary School & Robert Eagle Staff Middle School SPU Licton Springs Stormwater Improvements and Street Restoration

November 12, 2015

Page 24: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Genesee Hill Elementary School • Site: Began forming curbs at play equipment area.

• Area 1: Installation of GWB at level 1 and 2 stairwell is ongoing; GWB finish process

is ongoing.

• Area 2: Interior framing is ongoing at level 2; CMU veneer installation ongoing;

MEP is ongoing.

• Area 3: Interior framing ongoing; installation of sound insulation at level 1 ongoing;

CMU veneer installation ongoing; installation of flashings in window openings on

going; installation of GWB on going; performing prep work at covered play area for

exterior painting; MEP is ongoing.

• Area 4: Forming stairs at loading dock; exterior painting prep work for exposed roof

at loading dock; Installation of sprinkler system is ongoing; MEP is ongoing.

Page 25: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Genesee Hill Elementary School

Site Plan 4

Page 26: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Genesee Hill Elementary School Aerial View

November 15, 2015

Page 27: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Genesee Hill Elementary School Site - Forming Curbs at Play Equipment Area

Page 28: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Genesee Hill Elementary School Area 1 Level 2 GWB Finish Process

Page 29: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Genesee Hill Elementary School Area 2 Level 1 Electrical Rough-In

Page 30: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Genesee Hill Elementary School Area 2 Mechanical Mezzanine Installing Ductwork

Page 31: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Genesee Hill Elementary School Area 3 Installing CMU Veneer

Page 32: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Genesee Hill Elementary School Area 3 Prepping Covered Play Area for Painting

Page 33: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Genesee Hill Elementary School Area 3 Level 1 Installing Flashing at Windows

Page 34: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Genesee Hill Elementary School Area 3 Level 1 Installing GWB

Page 35: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Hazel Wolf K-8 at Pinehurst

• Site: Deep sewer install continues, backfill around foundations, general clean up. Erosion measures in place and functioning properly.

• Building A: Area (A1) Roofing ongoing membrane installed. Electrical equipment

/conduit install continues. Area (A2) metal stud framing continues on all three floors. Drywall and exterior sheeting continue. Mechanical ducting, electrical equipment /conduit and plumbing install continues. (A3) Structural steel nearly completed. final stem wall waterproofing ongoing and under slab utilities completed. Slab area prepared for concrete.

• Building B: Floor slab concrete pour pending good weather. Structural steel for the outside play area completed. Roofing to start.

• Building C: Concrete slab continues to be covered and protected. Metal roof

decking installation completed. Roof Insulation and roofing material to continue next week weather permitting.

Page 36: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Hazel Wolf K-8 at Pinehurst Site Plan

Page 37: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Hazel Wolf K-8 at Pinehurst Aerial View

Page 38: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Hazel Wolf K-8 at Pinehurst Area A1-A2 Looking West

November 13, 2015

Page 39: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Hazel Wolf K-8 at Pinehurst Area A2 Kindergarten Exterior Sheathing

November 11, 2015

Page 40: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Hazel Wolf K-8 at Pinehurst Area A2 Structural Steel

November 11, 2015

Page 41: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Hazel Wolf K-8 at Pinehurst Area A3 Structural Steel / Waterproofing

November 11, 2015

Page 42: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Hazel Wolf K-8 at Pinehurst Area A3 Administration Waterproofing

November 12, 2015

Page 43: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Hazel Wolf K-8 at Pinehurst Area C and A1 looking South

November 11, 2015

Page 44: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Hazel Wolf K-8 at Pinehurst Area C Roofing

November 11, 2015

Page 45: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Olympic Hills Elementary School

Site: Continuing installation of geothermal wells.

Reviewing bids for Phase 2 GC/CM trade subcontractors.

Page 46: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Olympic Hills Elementary School Site Plan

Page 47: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Olympic Hills Elementary School Aerial Photo

November 4, 2015

Page 48: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Olympic Hills Elementary School Base Course, Looking SW

November 11, 2015

Page 49: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Olympic Hills Elementary School Geothermal Well Drilling, Looking West

November 11, 2015

Page 50: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Olympic Hills Elementary School Site TESC, Looking East

November 11, 2015

Page 51: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor

• Area A – Administration Office, Student Services, Health Clinic and Library: Administration office addition capillary break material, concrete pour scheduled for 11/19, structural steel and glue lam delivery. Health Clinic concrete slab pour complete. Library demolition complete.

• Area B – Multipurpose, Kitchen, Boiler Room: Steel erection ongoing, structural wood delivery and framing ongoing, boiler pad demolition complete. Installation of electrical conduit and plumbing in crawl space ongoing.

• Area C – Classrooms: New electrical service conduit installation ongoing, underground utility complete, CMU grade beams complete, CMU block wall installation ongoing.

Page 52: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor Site Plan

Page 53: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor Area A New Administration Addition Capillary Break Installed

November 13, 2015

Page 54: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor Area A New Administration Addition Erosion Control

November 13, 2015

Page 55: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor Area A and B Structural Glue-Lam Delivery

November 13, 2015

Page 56: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor Area B New Commons Addition Wood Framing

November 13, 2015

Page 57: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor Area B New Commons Addition Wood Framing

November 16, 2015

Page 58: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor Area B Electrical Conduit Installation

November 16, 2015

Page 59: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor Area B New Commons SIP Roof Panel Delivery

November 16, 2015

Page 60: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor Area C CMU Block Wall Installation

November 16, 2015

Page 61: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor Area C CMU Block Wall Installation

November 16, 2015

Page 62: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

Seattle World School at T.T. Minor Area B Wood Framing

November 16, 2015

Page 63: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building • Site: Continued installing footing drainage piping and downspouts.

Continued Phase II geothermal well drilling in playfield north of the parking lot.

• Building A: Continued with interior backfill around footings. Set subgrade for

remaining concrete slab-on-grade. Continued installing underground plumbing and electrical including drains.

• Building B: Continued edge form for slab-on-deck. Continued erecting

structural steel in both library and two story academic wing. Continued placing decking in first story of two story wing.

• Building C: Continued interior framing on classrooms. Continued installing

interior hollow metal window frames in hallway for classrooms. Began installing gypsum wall board (GWB) above hallway ceiling. Continued installing HVAC ductwork and above ceiling plumbing and electrical. Continued with plumbing and electrical rough-in in classroom walls.

• Building D: Continued excavation of footings for Covered Play Area.

Page 64: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Key Plan

Page 65: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Aerial Photo

October 15, 2015

Page 66: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building A Underground Electrical and Plumbing Rough-in

Page 67: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building A Geothermal Header Piping to Main Mechanical Room

Page 68: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building A Geothermal Header Piping to Main Mechanical Room

Page 69: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building B Structural Steel Erection

Page 70: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building B Structural Steel Erection

Page 71: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building B Structural Steel Erection

Page 72: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building B Structural Steel for Mechanical Penthouse

Page 73: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building B Drain Installed in Slab-on-Deck

Page 74: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building C Cold Fluid Applied Air Barrier on Exterior Wall

Page 75: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building C Cold Fluid Applied Air Barrier on Exterior Wall

Page 76: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building C GWB Installed above Ceiling

Page 77: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building D Footing for Covered Play Area

Page 78: Seattle Public Schools Building Excellence IV …...complete. Installation of electrical conduit and plumbing in crawl space ongoing. • Area C – Classrooms: New electrical service

New Thornton Creek Building Building D Footing for Covered Play Area