Project Slide Number
Arbor Heights Elementary School 2
Cascadia Elementary School & Robert Eagle Staff Middle School 13
Genesee Hill Elementary School 24
Hazel Wolf K-8 at Pinehurst 35
Olympic Hills Elementary School 45
Seattle New World School at TT Minor 51
New Thornton Creek Building 63
November 20, 2015
Seattle Public Schools Building Excellence IV Projects Under Construction
Arbor Heights Elementary School Elementary School
• Site: Canopy column footings are being backfilled at the south side of North Building. Asphalt demolition and grading for landscaping and playfield is underway at the west side of the site.
• South Building: Exterior sheathing is ongoing at floor 1. Light-gauge metal framing continues at the exterior and interior walls at floors 2 and 3. Roofing installation is ongoing. Mechanical, plumbing, fire-sprinkler and electrical rough-in are ongoing at floors 1 and 2.
• North Building: Structural steel welding is ongoing. Roof joists installation is on-going.
• Arbor: Structural Glu-Lam columns/beams are getting erected.
Arbor Heights Elementary School Site Plan
July 1, 2015 July 10, 2015
Arbor Heights Elementary School Aerial View from the South
November 3, 2015
Arbor Heights Elementary School South Building First Floor Insulation
November 12, 2015
Arbor Heights Elementary School South Building Third Floor Exterior Wall Framing
November 12, 2015
Arbor Heights Elementary School South Building Third Floor Interior Wall Framing
November 16, 2015
Arbor Heights Elementary School North Building Vapor Barrier at Gymnasium and Cafeteria
November 16, 2015
Arbor Heights Elementary School North Building Mechanical Mezzanine
November 12, 2015
Arbor Heights Elementary School North Building Roof Joists
November 12, 2015
Arbor Heights Elementary School North Building Roof Joist Welding
November 12, 2015
Arbor Heights Elementary School Arbor Glu-Lam Columns
November 16, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School
Site: Pouring concrete curbs at parking lots and prepping for placement
of asphalt.
ES: Pouring concrete slab on grade; re-installed 2nd and 3rd murals at
permanent locations; concrete footings complete.
MS: Pouring concrete footings and concrete stem walls.
SPU Licton Springs Flood Reduction Project: Successfully completed –
neighborhood streets are no longer flooding during 25 year storm
events.
Cascadia Elementary School & Robert Eagle Staff Middle School Site Plan
Cascadia Elementary School & Robert Eagle Staff Middle School Aerial Photo
November 3, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School 2nd Mural Being Relocated to Permanent Location at Elementary School
November 10, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School 3rd Mural Being Set at Permanent Location at Elementary School
November 12, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Concrete Slab on Grade with Mural Placed on South Side
November 13, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Concrete Brace Footings, Looking North
November 12, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Parking Lot Subgrade Prep, Looking West
November 12, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Underground Utilities, Looking East
November 12, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School New Stormwater Intake Structure at Licton Springs Park
November 9, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School SPU Licton Springs Stormwater Improvements and Street Restoration
November 12, 2015
Genesee Hill Elementary School • Site: Began forming curbs at play equipment area.
• Area 1: Installation of GWB at level 1 and 2 stairwell is ongoing; GWB finish process
is ongoing.
• Area 2: Interior framing is ongoing at level 2; CMU veneer installation ongoing;
MEP is ongoing.
• Area 3: Interior framing ongoing; installation of sound insulation at level 1 ongoing;
CMU veneer installation ongoing; installation of flashings in window openings on
going; installation of GWB on going; performing prep work at covered play area for
exterior painting; MEP is ongoing.
• Area 4: Forming stairs at loading dock; exterior painting prep work for exposed roof
at loading dock; Installation of sprinkler system is ongoing; MEP is ongoing.
Genesee Hill Elementary School
Site Plan 4
Genesee Hill Elementary School Aerial View
November 15, 2015
Genesee Hill Elementary School Site - Forming Curbs at Play Equipment Area
Genesee Hill Elementary School Area 1 Level 2 GWB Finish Process
Genesee Hill Elementary School Area 2 Level 1 Electrical Rough-In
Genesee Hill Elementary School Area 2 Mechanical Mezzanine Installing Ductwork
Genesee Hill Elementary School Area 3 Installing CMU Veneer
Genesee Hill Elementary School Area 3 Prepping Covered Play Area for Painting
Genesee Hill Elementary School Area 3 Level 1 Installing Flashing at Windows
Genesee Hill Elementary School Area 3 Level 1 Installing GWB
Hazel Wolf K-8 at Pinehurst
• Site: Deep sewer install continues, backfill around foundations, general clean up. Erosion measures in place and functioning properly.
• Building A: Area (A1) Roofing ongoing membrane installed. Electrical equipment
/conduit install continues. Area (A2) metal stud framing continues on all three floors. Drywall and exterior sheeting continue. Mechanical ducting, electrical equipment /conduit and plumbing install continues. (A3) Structural steel nearly completed. final stem wall waterproofing ongoing and under slab utilities completed. Slab area prepared for concrete.
• Building B: Floor slab concrete pour pending good weather. Structural steel for the outside play area completed. Roofing to start.
• Building C: Concrete slab continues to be covered and protected. Metal roof
decking installation completed. Roof Insulation and roofing material to continue next week weather permitting.
Hazel Wolf K-8 at Pinehurst Site Plan
Hazel Wolf K-8 at Pinehurst Aerial View
Hazel Wolf K-8 at Pinehurst Area A1-A2 Looking West
November 13, 2015
Hazel Wolf K-8 at Pinehurst Area A2 Kindergarten Exterior Sheathing
November 11, 2015
Hazel Wolf K-8 at Pinehurst Area A2 Structural Steel
November 11, 2015
Hazel Wolf K-8 at Pinehurst Area A3 Structural Steel / Waterproofing
November 11, 2015
Hazel Wolf K-8 at Pinehurst Area A3 Administration Waterproofing
November 12, 2015
Hazel Wolf K-8 at Pinehurst Area C and A1 looking South
November 11, 2015
Hazel Wolf K-8 at Pinehurst Area C Roofing
November 11, 2015
Olympic Hills Elementary School
Site: Continuing installation of geothermal wells.
Reviewing bids for Phase 2 GC/CM trade subcontractors.
Olympic Hills Elementary School Site Plan
Olympic Hills Elementary School Aerial Photo
November 4, 2015
Olympic Hills Elementary School Base Course, Looking SW
November 11, 2015
Olympic Hills Elementary School Geothermal Well Drilling, Looking West
November 11, 2015
Olympic Hills Elementary School Site TESC, Looking East
November 11, 2015
Seattle World School at T.T. Minor
• Area A – Administration Office, Student Services, Health Clinic and Library: Administration office addition capillary break material, concrete pour scheduled for 11/19, structural steel and glue lam delivery. Health Clinic concrete slab pour complete. Library demolition complete.
• Area B – Multipurpose, Kitchen, Boiler Room: Steel erection ongoing, structural wood delivery and framing ongoing, boiler pad demolition complete. Installation of electrical conduit and plumbing in crawl space ongoing.
• Area C – Classrooms: New electrical service conduit installation ongoing, underground utility complete, CMU grade beams complete, CMU block wall installation ongoing.
Seattle World School at T.T. Minor Site Plan
Seattle World School at T.T. Minor Area A New Administration Addition Capillary Break Installed
November 13, 2015
Seattle World School at T.T. Minor Area A New Administration Addition Erosion Control
November 13, 2015
Seattle World School at T.T. Minor Area A and B Structural Glue-Lam Delivery
November 13, 2015
Seattle World School at T.T. Minor Area B New Commons Addition Wood Framing
November 13, 2015
Seattle World School at T.T. Minor Area B New Commons Addition Wood Framing
November 16, 2015
Seattle World School at T.T. Minor Area B Electrical Conduit Installation
November 16, 2015
Seattle World School at T.T. Minor Area B New Commons SIP Roof Panel Delivery
November 16, 2015
Seattle World School at T.T. Minor Area C CMU Block Wall Installation
November 16, 2015
Seattle World School at T.T. Minor Area C CMU Block Wall Installation
November 16, 2015
Seattle World School at T.T. Minor Area B Wood Framing
November 16, 2015
New Thornton Creek Building • Site: Continued installing footing drainage piping and downspouts.
Continued Phase II geothermal well drilling in playfield north of the parking lot.
• Building A: Continued with interior backfill around footings. Set subgrade for
remaining concrete slab-on-grade. Continued installing underground plumbing and electrical including drains.
• Building B: Continued edge form for slab-on-deck. Continued erecting
structural steel in both library and two story academic wing. Continued placing decking in first story of two story wing.
• Building C: Continued interior framing on classrooms. Continued installing
interior hollow metal window frames in hallway for classrooms. Began installing gypsum wall board (GWB) above hallway ceiling. Continued installing HVAC ductwork and above ceiling plumbing and electrical. Continued with plumbing and electrical rough-in in classroom walls.
• Building D: Continued excavation of footings for Covered Play Area.
New Thornton Creek Building Key Plan
New Thornton Creek Building Aerial Photo
October 15, 2015
New Thornton Creek Building Building A Underground Electrical and Plumbing Rough-in
New Thornton Creek Building Building A Geothermal Header Piping to Main Mechanical Room
New Thornton Creek Building Building A Geothermal Header Piping to Main Mechanical Room
New Thornton Creek Building Building B Structural Steel Erection
New Thornton Creek Building Building B Structural Steel Erection
New Thornton Creek Building Building B Structural Steel Erection
New Thornton Creek Building Building B Structural Steel for Mechanical Penthouse
New Thornton Creek Building Building B Drain Installed in Slab-on-Deck
New Thornton Creek Building Building C Cold Fluid Applied Air Barrier on Exterior Wall
New Thornton Creek Building Building C Cold Fluid Applied Air Barrier on Exterior Wall
New Thornton Creek Building Building C GWB Installed above Ceiling
New Thornton Creek Building Building D Footing for Covered Play Area
New Thornton Creek Building Building D Footing for Covered Play Area