SeaDataNet Pan-European infrastructure for Ocean & Marine Data management An Integrated research...
-
Upload
sharleen-oliver -
Category
Documents
-
view
222 -
download
1
Transcript of SeaDataNet Pan-European infrastructure for Ocean & Marine Data management An Integrated research...
SeaDataNetPan-European infrastructure for Ocean & Marine Data managementAn Integrated research Infrastructure Initiative (I3)
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
Financial DeliverablesMarie-Pierre Zelverte, IFREMER
Kick-Off Meeting
June 8-10, 2006, Heraklion, Greece
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNetSEADATANET
ELIGIBLE COSTS
ELIGIBLE COSTS INCURRED FOR THE IMPLEMENTATION OF THE PROJECT MUST FULFIL ALL OF THE FOLLOWING CONDITIONS (Article II.19.1 of ANNEX II to General Conditions) :
They must be actual, economic and necessary for the implementation of the project, and
They must be determined in accordance with the usual accounting principles of the contractor, and
They must be incurred during the duration of the project, and
They must be recorded in the accounts of the contractor that incurred them.
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
SEADATANETNON-ELIGIBLES COSTS
THE FOLLOWING NON-ELIGIBLE COSTS MAY NOT BE CHARGED TO THE PROJECT :
Any identifiable indirect taxes, including VAT or duties,Interest owed,Provisions for possible futures losses or charges,Exchange losses,Costs declared, incurred or reimbursed in respect of another Community project,Costs related to return on capital,Debt and debt service chargesExcessive or reckless expenditureAny cost which does not meet the conditions established in Article II.19.1
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
SEADATANETDIRECT COSTS
Direct costs are all those costs which meet the criteria established in Article II.19 of Annex II
They can be identified by the contractor in accordance with its accounting system and can be attributed directly to the project
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
SEADATANETINDIRECT COSTS
For contractors working on the full cost model (FC), indirect costs are all eligible costs determined by the contractor, in accordance with its usual accounting practices, which are not directly attributable to the project but are incurred in direct relation to the direct costs of the project.
For those contractors using either of the flat rate models (FCF, AC) a flat rate is applied to the direct costs to cover the indirect costs.
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
SEADATANETCOST REPORTING MODELS
THERE ARE THREE MODELS FOR REPORTING COSTS UNDER THE CONTRACT
Eligible direct and indirect costs are charged by contractors using the full cost model (FC)
Eligible direct costs and a flat for indirect costs are charged by contractors using the full cost flat rate reporting model (FCF). The flat rate is 20 % of all direct costs minus costs of subcontracts.
Eligible direct additional costs and a flat rate for indirect costs are charged by contractors using the additional cost model (AC). The flat rate is 20 % of all direct additional costs minus costs of subcontracts.
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet SEADATANETMAXIMUM REIMBURSEMENT RATES
Maximum reimbursement rates of eligible costs for integrated infrastructures initiative
ABOUT THE MANAGEMENT : Costs management are reimbursed up to 7% to the total
Consortium budget and not per contractor. Where the costs incurred for management activities exceed the limit of 7% of the Community financial contribution, such costs may be charged to the other relevant activity to which they correspond if they meet the conditions of Articles II.19, II.20 and II.21 applicable to those activities.
Instrument
Research and
innovation
activities (JRA)
Demonstration activities
Management of the consortium activities (NA1)
Other specific activities
Transnational access
Connectivity
services
Others
I3A FC/FCF : 50%AC : 100%
FC/FCF : 35%AC : 100%
AC/FC/FCF : 100%
(up to 7% of the contribution)
UF as indicated in A3.2b
AC/FC/FCF : 50 %
AC/FC/FCF : 100 %
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
SEADATANETthe course of the contract
The project is divided into reporting periods of the following duration :
P1 : from 1st April 2006 to 31st March 2007
P2 : from 1st April 2007 to 31st March 2008
P3 : from 1st April 2008 to 31st March 2009
P4 : from 1st April 2010 to 31st March 2011
All reports and deliverables shall be submitted within 45 days following the end of the respective periods identified in Articles 6 and 7 of the contract
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
SEADATANETthe course of the contract
The Consortium shall submit the following reports to the Commission for each reporting period :
a periodic activity report containing an overview of the activities carried out by the consortium during that period :
a description of progress towards the objectives of the project, a description of progress towards the milestones and deliverables foreseen, the identification of the problems encountered and corrective action taken. An updated plan for using and disseminating the knowledge included as a separate part of this report.
a periodic management report on that period including :a justification of the resources deployed by each contractor, linking them to activities implemented and justifying their necessity,the Form C financial statement set out in ANNEX VI, provided by each contractor for that period,a summary financial report consolidating the claimed costs of all the contractors in an aggregate form, based on the information provided in Form C,a report on the distribution between contractors made during that period of the Community financial contribution.
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
SEADATANETPERSONNEL IN COSTS STATEMENT
Average employment costs are no longer permitted by the FP6 contract.
Only actual costs can be used for each reporting period.
Personnel may include :« Permanent employees » who have permanent working contracts with the contractor.« Temporary employees » who have temporary working contracts with the contractor.
cost for remuneration of personnel should be taken from the payroll account and should reflect the total gross remuneration plus (salary) the employer's portion of social charges (e.g. holiday pay, pension contributions, health insurance and social security payments).
A simple estimation of hours worked is not sufficient. There must be a system that allows the time of anyone working on the project to be followed and audited.
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
Third Party 1 (Y1)
Third Party 2 (Y2)
Third Party 3 (Y3)
Third Party 4 (Y4)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Direct costsOf which
subcontracting
Indirect costsAdjustments to previous period(s)
Total costs
Cost model used
Cost model used
Type of Action (if necessary)
Contract n°
Telephone
Indirect costs (Real or Flat Rate of 20% of Direct costs, except subcontracting)
To
(E)(C)
2- Declaration of eligible costs (in €)
Please complete only the activity covered by the relevant instrument (and type of action) indicated above and as mentioned in Article II.25 and/or in Annexes I and III of the contract.If you are a contractor using the additional cost model (AC):- indica
(B) (E)
Management of the
Consortium
Are there any resources made available on the basis of a prior agreement with third parties identified in Annex I of the contract? (Yes / No)
If Yes, please provide the following information
Legal name
Cost model used
Cost model used
(*) If UF is used under "other specif ic activities: transnational access/connectivity", please mention the tw o cost models used (eg. FC/UF or FCF/UF or AC/UF)
1- Resources (Third party(ies))
Form C - Model of Financial Statement per Activity for Integrated Infrastructure Initiatives
(to be completed by each contractor)
Integrated Infrastructure Initiatives
Type of instrument
Project Title (or Acronym)
(D)
Research and Technological Development /
Innovation
(A)
Demonstration
Total
(G) =(A)+(B)+(C)+(D)+(E)+(F)
Other Specific
Activities
Other Specific Activities:
Coordination / Networking
Other Specific Activities:
Transnational Access /
Connectivity
Legal name
Legal name
Legal name
Type of Activity
If necessary add another Form C
Contractors's legal name
Legal Type
Contact Person
Telecopy
Cost model used (AC/FC or FCF)/ (UF: User Fee)(*)
Period from
General information
1.Resources
2.Declarationof eligiblecosts
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet3.Declarationof receipts
Only for thecoordinator
5.Request forFP6 financialcontribution
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Co
ntr
acto
r
Th
ird
Part
y(i
es)
Total receipts
Cost of the certificate
Total (Z) = (X) + (Ys)If necessary add another Form C.
Y4 : Legal name of the audit firm
Cost of the certificate
Cost of the certificate
Y2 : Legal name of the audit firm
Y3 : Legal name of the audit firm
Cost of the certificate
Audit certificate(s) of the third party(ies) (Ys) (if necessary)
Y1 : Legal name of the audit firm
What is the total cost of this(those) audit certificate(s) (in €) per independent auditor(s) ?
Audit certificate of the contractor (X)
Legal name of the audit firm Cost of the certificate
If No, what are the periods covered by this(those) audit certificate(s) ?
6- Audit certificates
From - to
If Yes, does this(those) audit certificate(s) cover only this Financial Statement per Activity? (Yes / No)
Research and Technological Development /
Innovation
Type of Activity
Total
(G) =
According to the contract, does this Financial Statement need an audit certificate (or several in case of Third party(ies)) delivered by independent auditor(s)? (Yes / No)
5- Request of FP6 Financial Contribution (in €)
For this period, the FP6 Community financial contribution requested is equal to ( amount in €)
Did the pre-financing (advance) you received by the Commission for this period earn interest? (Yes / No)
(D)(A)
Management of the
Consortium
Other Specific Activities:
Transnational Access /
ConnectivityDemonstratio
n
(B)
3- Declaration of receipts (in €)
If you are a contractor using the additional cost model (AC), indicate only receipts covered by Article II.23.c of the contract.
To be completed only by the coordinator.
(E)
4- Declaration of interest generated by the pre-financing (in €)
(E)(C)
(A)+(B)+(C)+(D)+(E)+(F)
Other Specific Activities
If you are a contractor using a full cost model (FC/FCF), indicate receipts covered by Article II.23 of the contract.
Other Specific Activities:
Coordination / Networking
If yes, please indicate the amount (in €)
6.Auditcertificate
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
Contractor’s Stamp
Signature
Date Date
Signature
Name of the duly authorisedFinancial Officerfor the work
Third Party 3 (Y3)
- there is full supporting documentation to justify the information hereby declared. It will be made available at the request of the Commission and in the event of an audit by the Commission and/or by the Court of Auditors and/or their authorised represen
Name of the Person responsible
- Conversion rate of the date of incurred actual costs? (YES / NO)
- Conversion rate of the first day of the first month following the period covered by this Financial Statement? (YES/NO)
- Conversion rate of the first day of the first month following the period covered by this Financial Statement? (YES/NO)
Third Party(ies) (if necessary)
Third Party 1 (Y1)
Third Party 1 (Y2)
- Conversion rate of the first day of the first month following the period covered by this Financial Statement? (YES/NO)
- Conversion rate of the date of incurred actual costs? (YES / NO)
- Conversion rate of the first day of the first month following the period covered by this Financial Statement? (YES/NO)
- Conversion rate of the date of incurred actual costs? (YES / NO)
Please mention the conversion rate used (only one choice is possible) – Please note that the same principle applies for receipts.
Contractor- Conversion rate of the date of incurred actual costs? (YES / NO)
Reminders:
The cost of an audit certificate is included in the costs declared under the activity “Management of the Consortium”. The required audit certificate (s) is (are) attached to this Financial Statement
7- Conversion ratesCosts incurred in currencies other than EURO shall be reported in EURO.
- Conversion rate of the date of incurred actual costs? (YES / NO)
- Conversion rate of the first day of the first month following the period covered by this Financial Statement? (YES/NO)
8- Contractor’s CertificateWe certify that:
Third Party 4 (Y4)
If necessary add another Form C.
- the costs declared above are directly related to the resources used to reach the objectives of the project ;
- the receipts declared above are directly related to the resources used to reach the objectives of the project ;
- the costs declared above fall within the definition of eligible costs specified in Articles II.19, II.20, II.21, II.22 and II.25 of the contract, and, if relevant, in Annex III and Article 9 (special clauses) of the contract ;
- the receipts declared above fall within the definition of receipts specified in Article II.23 of the contract ;
- the interest generated by the pre-financing declared above falls within the definition of Article II.27 of the contract ;
- the necessary adjustments, especially to costs reported in previous Financial Statement(s) per Activity, have been incorporated in the above Statement ;
- the above information declared is complete and true ;
7.Conversionrates
8.Contractors’certificate
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
SEADATANETAbout converting to Euros
Costs incurred in currencies other than the EURO shall be reported in EURO on the basis of the conversion rate applicable on the first day on the month following the end of reporting period. The basis for the conversion rate used shall be indicated in FORM C when reporting costs incurred.
FOR EXAMPLE : The first period finishes on 31st march 2007, so the conversion rate is the rate applicable on the 1st June 2007.
http://www.ecb.int/stats/exchange/eurofxref/
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet SEADATANETJustification of resources deployed
Total effort in person-months (1)
Cost categoryActual direct
eligible costs (€)
Personnel cost (2)
Travel
Consumables
…
Total direct eligible costs
Total indirect costs
Total costs (3)Global estimate of the total costs for AC contractors (not only the eligible costs)
Justify any deviations with respect to the planned budget
(1) AC contractors must include both the total estimated human effort (including permanent staff) and, in brackets, additional staff only. For an access activity do not include the effort charged under the user fees if the UF cost model is used.(2) For TA activities excluding the effort charged under the user fees if the UF cost model is used. (3) Totals should correspond to the respective figures on FORM C - Financial Statement
JRA9 : Atlantic and Global Ocean Products
Justification of costsdescription of expenditure and link to the specif ic w ork carried out (e.g. tasks, w ork packages, …)
One tableper activity
Total costs
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet SEADATANETAUDIT CERTIFICATE
Article 9 – Special clause 39 of the Seadatanet contract
For each period for which an audit certificate is required (financial contribution > 150,000 EUR), each contractor shall provide an audit certificate prepared and certified by an external auditor, certifying that the costs incurred during that period meet the conditions required by the contract.
Final certificate for all partners :
An audit certificate shall be submitted at the latest 45 days after the final reporting period.
This final audit certificate shall cover all periods for which an audit certificate has not been previously submitted.
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet SEADATANETEXTERNAL AUDITOR
Each contractor is free to choose any qualified external auditor, including its usual external auditor, provided that it meets cumulative following professional requirements :
- the external auditor must be independent from the contractor,
- the external auditor must be qualified to carry out statutory audits of accounting documents in accordance with the 8th Council directive 84/253/EEC of 10 April 1984 or similar national regulations.
A contractor that is a public body may opt for a competent public officer to provide an audit certificate, provided that the relevant national authorities have established the legal capacity of that competent public officer to audit that public body.
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
Partner Name Countrycost model
NB audits date1 date2 date3
Audits direct costs
coeff overhead/other costs
audit total costs
1 IFREMER France FC 3 2008 2010 2011 600 0,00 600
2 MARIS Netherlands FC 3 2008 2010 2011 3000 0,00 3000
3 NERC/BODC UK FC 3 2008 2010 2011 600 0,00 600
4 BSH/DOD Germany FC 3 2008 2010 2011 600 0,00 600
5 SMHI Sw eden FC 2 2010 2011 400 0,00 400
6 IEO Spain FC 2 2010 2011 400 0,00 400
7 HCMR/HNODC Greece FCF 2 2010 2011 400 0,20 480
8 OGS Italy FC 2 2010 2011 400 0,00 400
9 RIHMI/WDC Russia FCF 2 2010 2011 400 0,20 480
10 UNESCO/IOC Internat, FR AC 2 2010 2011 400 0,20 480
11 ENEA Italy FC 2 2010 2011 400 0,00 400
12 INGV Italy AC 2 2010 2011 400 0,20 480
13 IMS/METU Turkey AC 2 2010 2011 400 0,20 480
14 CLS France FC 3 2008 2010 2011 3000 0,00 3000
15 AWI Germany FCF 3 2008 2010 2011 600 0,20 720
16 ULG/GHER Belgium AC 2 2010 2011 400 0,20 480
17 IMR Norw ay FC 2 2010 2011 400 0,00 400
18 NERI Denmark FC 2 2010 2011 400 0,00 400
19 ICES Internat, DK FC 2 2010 2011 400 0,00 400
20 JRC internat, IT FCF 2 2010 2011 2000 0,20 2400
21 MI Ireland FC 1 2011 200 0,00 200
22 IHPT Portugal FC 1 2011 200 0,00 200
23 RIZK Netherlands FC 2 2010 2011 400 0,00 400
24 RBINS/MUMM Belgium AC 2 2010 2011 400 0,20 480
25 VLIZ Belgium AC 1 2011 200 0,20 240
26 MRI Iceland FC 2 2010 2011 400 0,00 400
27 FIMR Finland FC 1 2011 200 0,00 200
28 IMGW Poland FC 1 2011 200 0,00 200
29 MSI Estonia AC 1 2011 200 0,20 240
30 IAE/UL Latvia AC 1 2011 200 0,20 240
31 CMR Lithuania AC 1 2011 200 0,20 240
32 SIO/RAS Russia FC 1 2011 200 0,00 200
33 MHI/DMIST Ukraine FCF 1 2011 200 0,20 240
34 IO/BAS Bulgaria AC 1 2011 200 0,20 240
35 NIMRD Romania FC 1 2011 200 0,00 200
36 TSU/DNA Georgia FCF 1 2011 200 0,20 240
37 INRH Morocco AC 1 2011 200 0,20 240
38 IOF Croatia AC 1 2011 200 0,20 240
39 IHM Albania AC 1 2011 200 0,20 240
40 NIB-MBS Slovenia FC 1 2011 200 0,00 200
41 IOI/MOC Malta AC 1 2011 200 0,20 240
42 OC/UCY Cyprus AC 1 2011 200 0,20 240
43 IOLR Israel AC 1 2011 200 0,20 240
44 LCNRS/NCMS Lebanon AC 1 2011 200 0,20 240
45 CNR-ISAC Italy FC 1 2011 200 0,00 200
46 ISMAL Algeria FCF 1 2011 200 0,20 240
47 INSTM Tunisia AC 1 2011 200 0,20 240
Only for AC and FCF
Total cost for all periods without overheads
Kick-off MeetingJune 8-10 2006, Heraklion, Greece
SeaDataNet
THANK YOU FOR YOUR ATTENTION