sea bed network deployment issues; energy distribution ...

15
talk outline sea bed network deployment issues; energy distribution seabed network issues; data transmission seabed network; data transmission seabed network;

Transcript of sea bed network deployment issues; energy distribution ...

talk outline

� sea bed network deployment issues;

� energy distribution seabed network issues;

� data transmission seabed network;� data transmission seabed network;

seabed network decisional process

specification from physicsspecification from physics

deployment

feasibility

no

yes

data and energy

network compatibility

no

deployment strategythe question is: what to deploy in advance?

the detection units or the seabed network?

Example of SEABED NETWORK

PJB

SJB close

to a towerto a tower

tower

5

MEOC

Cable PJB-SJB

Cable SJB-tower

180 m

This proposal is based on the learned lesson and the current market availability. It strongly takes in account the deployment issues.

The proposal aims to demonstrate the feasibility of the system.

ELECTRICAL POWER SYSTEM Proposal

DESIGN INPUTS & CONSTRAINTS:

• a10kV wet mateable connector is not still tested and ready on the market

for this reason a MV Power distribution network has not been taken in account

at the moment ;

• a 375V DC distribution network has been evaluated

(375 V DC is the ALCATEL MVC output voltage);(375 V DC is the ALCATEL MVC output voltage);

• low voltage (375V DC) distribution network cannot accept huge cable (both in cross section and length) due to deployment issues;

• number of detection unit considered: 90 (expandable to 130);

• detection unit electrical load less than 300W;

• total power consumption: 27kW;

ELECTRICAL SUBSYSTEMS:

On-shore :

• A 50 kW Power Feed Equipment with:

- Input Voltage: 400 V AC 3 phase

ELECTRICAL POWER SYSTEM Proposal

- Input Voltage: 400 V AC 3 phase

- Output Voltage: 10 kV DC

Off-shore :

• A 10kV DC Power Transmission system with sea return using :

- a single conductor cable

- earth terminations

• A Power Distribution network that includes:

- Power conversion from 10 kV to 375V using the 10 kW Alcatel Medium voltage Converters;

Primary Junction Box:

the PJB will hosts:

• Cable end and sea electrode terminations;

• the MVCs;

• a monitoring and control system;

POWER DISTRIBUTION NETWORK

• Input: 10 kV feedthrough;

• Output: 400 V wet mateable connectors.

LV Distribution network - Evaluation process:

1. a LV ring distribution network containing a certain number of SJB;

pro:

- It Is one line fault tolerant: if there is a fault in one LV line it can be isolated, and all the SJBs can be fed without anydetector loss;and all the SJBs can be fed without anydetector loss;

vs:

- a second line fault can cause, in the worst case, the loss of all the detector;

- each SJB (connectors, switches, etc.) and the ring cable has to be designed

for the total detector power, 30kW/375V=80 A. As a consequence the cable cross section must be big to contain voltage drops and joule losses;

- the SJB cannot be passive;

Low Voltage Distribution Network - Evaluation Process:

2. a LV star distribution network containing a certain number of SJBs;

pro:

• The SJB are passive

POWER DISTRIBUTION NETWORK

• The SJB and the PJB-SJB cables have to be designed for a portion of the total power. It depends on the number of SJbs for ex. with 18 SJBs (each SJB feeds 5 DU) we have 30kW/18/375V=4.4A instead

of 80 A;

vs:

• In case of a PJB-SJB line fault a portion of detector is lost (5 DU);

POWER DISTRIBUTION NETWORK

TOWER 1

...MVC

MVC

MVC

...MONITORING & CONTROL

10 kV 375 V

375 V

SJB 1

TOWER 2

TOWER 5...

...

MVC

MVC

MVC

...

CONTROL

SYSTEM

SJB 18

...

SJB 8

PJB

• The PJB will host:

- a MVC Box with 5 MVC both for redundancy and for future grown of - a MVC Box with 5 MVC both for redundancy and for future grown of

the detector (25 years life from Alcatel),

- a switch Box with a monitoring and control system that can be

recovered with an automatic recovery system independently from the MVCs box,

- output 400 V wet mateable connectors including spare connectors.

• The SJB is passive and will hosts: input and output wet mateable connectors including spare connectors, fuses.

PJB

SJB

100 Km

Tower4 x 13mm^2

x 18x5

10 KV

L max 1500 m

375 V

Tower

L max 250 m

4 x 1mm^2

POWER DISTRIBUTION NETWORK

Electro-OpticalCable

PJB

...

SJB

SJB ...

Tower

Tower

• 1 Primary Junction Box (PJB)

• 18 Secondary Junction Boxes (SJB)Power per Tower 300 W

90 Towers total power 27 kW•

• 5 Tower per SJB

• PJB-SJB: radial distribution

• SJB-tower: radial distribution

• Max distance PJB-SJB: 1500m

• Max distance SJB-tower: 300m

90 Towers total power 27 kW

Cable Loss 1 kW

Cable Loss % < 4%

Cable voltage drop% < 4%

Total Power 28 kW

Example of SEABED NETWORK

PJB

SJB close

to a towerto a tower

tower

12

MEOC

Cable PJB-SJB

Cable SJB-tower

180 m

νOne - Optical Network Proposal (1/3): SJBs

DU 1

SJB 1

ROV opticalconnector

DU 2 DU 3 spare opticalConnector 1

• Double Bus topology;

• 1 colour per DU @ 2.5 Gb/s (optionally

2 colours @ 2.5 Gb/s);

1

2 3

7+ + + -1

SJB 11x4

1

5

7+ + -4

OpticalInterlink

2 colours @ 2.5 Gb/s);

• ADD for the colours from the DUs;

• 1 colour for slow control from shore

• DROP and BROADCAST for the slow

control colour @ 2.5 Gb/s;

• 5 Main optical connectors;

• Spare wide bandwidth port is available on each Bus after the Drop node;

1x4

DU 4 DU 5

spare opticalConnector 2

Interlink cable

•on each Bus after the Drop node;

• 2 Spare “colorless” connectors available;

νOne - Optical Network Proposal (2/3): PJB

DU 1 DU 2 DU 5

Cir...

**1

1

SJB 1

PJB

• Double Ring Topology;

• Band ADD&DROP at ring node level (maximum 9 nodes per ring);

• 6 colors per SJB (5 DUs + control) over 1 sub-band;

• 54 channels spreaded over contiguous bands are used by 9

**

**

1

9

...

9

Cir

SJB 9

Cir

**SJB 10

...

SJB 1

...

10

10

Interlink

cable

contiguous bands are used by 9 SJB;

• 1+1 redundancy scheme from Shore Station to SJB;

• Spare connectors can be served by a third ring (not showed)

...

**

**Cir

SJB 10

SJB 18

...

10

18

18

...MEOC

PJB

νOne - Optical Network Proposal (3/3)

• Ring topology based on circulators: doubled offshore and onshore to achieve 100% redundancy;• 1 ring can support as many DUs as fiber bandwidth allows;• Standard 100 GHz ITU grid accommodates up to ~60 colors: 2 rings are needed to transport 90 DUs;• 4 fibers of the Main Electro Optical Cable are used to setup the 2 rings;

PJB

**

*

...

1

9...

*

*

...

...

1

9

1

9

1

9

SJB

1

SJB

9

DWDM

mux

demux

band

mux-demux

...

...

*

*

*

DU 1

DU 5

...

Impossibile v isualizzare l'immagine. La memoria

del computer potrebbe essere insufficiente per aprire l'immagine oppure l'immagine potrebbe essere danneggiata. Riavviare il computer e aprire di nuovo il file. Se v iene visualizzata di nuovo la x rossa, potrebbe essere necessario elim

Impossibile v isualizzare l'immagine. La memoria del computer potrebbe essere insufficiente per aprire l'immagine oppure l'immagine potrebbe essere danneggiata. Riavviare

il computer e aprire di nuovo il file. Se v iene visualizzata di nuovo la x rossa, potrebbe essere necessario elim

Impossibile v isualizzare

Impossibile v isualizzare l'immagine. La memoria

del computer potrebbe essere insufficiente per aprire l'immagine oppure l'immagine potrebbe essere danneggiata. Riavviare il computer e aprire di nuovo il file. Se v iene visualizzata di nuovo la x rossa, potrebbe essere necessario elim

Impossibile v isualizzare l'immagine. La memoria del computer potrebbe essere insufficiente per aprire l'immagine oppure l'immagine potrebbe essere danneggiata. Riavviare

il computer e aprire di nuovo il file. Se v iene visualizzata di nuovo la x rossa, potrebbe essere necessario elim

Impossibile v isualizzare

**

*

...

...

*

*

...

...

10

... ...

*

*

*

SJB

10

SJB

18

demux

Station

MEOC

10

1818

10

18

10

18

DU 86

DU 90

...

Impossibile v isualizzare

l'immagine. La memoria del computer potrebbe essere insufficiente per aprire l'immagine oppure l'immagine potrebbe essere danneggiata. Riavviare il computer e aprire di nuovo il file. Se v iene visualizzata di nuovo la x rossa, potrebbe essere necessario elim

Impossibile v isualizzare l'immagine. La memoria del computer potrebbe essere insufficiente per aprire l'immagine oppure l'immagine potrebbe essere

danneggiata. Riavviare il computer e aprire di nuovo il file. Se v iene visualizzata di nuovo la x rossa, potrebbe essere necessario elim

Impossibile v isualizzare

l'immagine. La memoria del computer potrebbe essere insufficiente per aprire l'immagine oppure l'immagine potrebbe essere danneggiata. Riavviare il computer e aprire di nuovo il file. Se v iene visualizzata di nuovo la x rossa, potrebbe essere necessario elim

Impossibile v isualizzare l'immagine. La memoria del computer potrebbe essere insufficiente per aprire l'immagine oppure l'immagine potrebbe essere

danneggiata. Riavviare il computer e aprire di nuovo il file. Se v iene visualizzata di nuovo la x rossa, potrebbe essere necessario elim

SHORE SUB SEA