    OVERALL EPC SCHEDULE - METAL PROCESS

    Sl. Activity Description M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

    A New Plant EPC Build

    1.0 Engineering

    Basic Engineering

    Finalise Conceptuals/ Process Configs Final Configs

    Schedule B Pkg

    -- Heat & Mass Balance Study

    -- Hydraulics

    -- Equipment Datasheets-- Utility Summary

    -- Process - PFDs Start Issue PFDs Compl PFD

    -- Process - P&IDS

    Detail Engineering Compl.Hazop

    Sys. & Loss prevention- PFDs / HazopsP&ID-IFA P&ID-IFM P&ID-IFD P&ID-IFC

    Mechanical - MR & Vendor DataCritical MRQ Critical MRP Major NOA Initial VI Final VI Minor VI

    Plant Layout & Piping

    Plot plan -IFD Plot plan -IFC

    MTOsPrelm.MTO

    Intermediate MTO

    3D ModelStart 3D Model Compl. 3D Model

    IsometricsStart Isos Prepn.

    Civil/Strl/ Arch. DrgsGrading drgs Compl. Compl.Piperack drg

    Electrical - SLDs / drgsSLD (IFD) PMTO SLD(IFC) Inter. MTO Set route cabl

    Control Systems ( Inst) drgsPMTO Inter. MTO Final MTO

    2.0 Procurement

    EPC Package

    Fired-Heaters Compl MRQ issue Compl. NOA Compl VI

    Tagged Items

    Super ODCs Compl MRQ issue Compl. NOA Compl VI

    Columns Compl MRQ issue Compl. NOA Compl VI

    Vessels / Drums Compl MRQ issue Compl. NOA Compl VI

    ReactorsCompl MRQ issue Compl. NOA Compl VI

    Compressors Compl MRQ issue Compl. NOA Compl VI

    Pumps Compl MRQ issue Compl. NOA( Crit.pumps) Bal.NOA Compl VI

    Exchangers/Air Coolers Compl MRQ issue Compl. NOA Compl VI

    Filter/Strainers Compl MRQ issue Compl. NOA

    Special/design piping items Compl MRQ issue Compl. NOA

    Transformers Compl MRQ issue Compl. NOA Compl VI

    Panels Compl MRQ issue Compl. NOA

    CVs/RVs/MOVs/IsolVs . Compl MRQ issue Compl. NOA

    ISBL - Package Units Compl MRQ issue Compl. NOA Compl VI

    Bulk Items

    Civil - Cement/Torr. Start MR SO Start Delv Compl.MR

    Strutural Steel Start MR SO Start Delv Compl.MR

    Plates Start MR SO Start Delv Compl.MR FO

    Piping - Pipes/fittings/valves Start MR SO Start Delv Compl MR FO

    El t i l C bl Start MR SO Start Delv Compl MR

    YEAR-1 ' 0'- DATE

  • 8/2/2019 SDC Check Points

    2/3

    Milestones & Check-Points across Project Execution

    for

    System Driven Commissioning

    Milestone Milestone Physical Indicator % Progress Indicator Milestone Check Points

    Engineering Procurement Construction E P C Total Engineering Procurement Construction

    M1 Basic Engineering Completes Major Long Lead Items

    Ordering starts

    Site Preparation under

    Progress30% 40% 10% 30% Sequence for Overall Plant Start-up

    finalised

    Critical Long Lead equipment ETA is

    finalised basis alignment with

    finalised start-up sequence

    Detail Construction lookahead plan

    gets finalised based on process

    sequence.

    3D Modelling Starts Sourcing Plan for Bulk Material

    gets finalised

    Civil Contractor mobilised Agreement obtained from EPCO

    team

    Subsequent Bulk Item Ordering

    follows the same logic

    Plot Plan is IFD Same logic is applied for plant

    mechanical modeliing

    M2 3D Modelling is 30% Long Lead Ordering

    Completes & vendors given

    advance

    Civil foundation &

    superstructure work starts60% 60% 35% 50% First Model review with Constn. &

    Opn. for constructability & operability

    Ensure Long Lead Equipment are on

    schedule and all vendor interface /

    clashes are resolved.

    Detail Civil work liquidation plan

    prepared & actualised as per actual

    progress.

    Plot Plan issued IFC Bulk Material Delivery Starts at

    site

    Underground works start Any clash in constn. expectation /

    process sequencing is duly

    addressed.

    Sequence Bulk material delivery to

    prioritise Bulk commodity liquidation

    Mechanical Contractors are

    appraised about front availability

    forecast & interface needs

    Equipment Vendor Drawing

    review starts

    Mechanical works contractor

    are aligned

    Process Battery Limits & Interfaces

    are clearly identified.

    M3 3D Modell ing Completed Long Lead Item shop

    Inspection starts

    Steel Structure Works Starts 90% 75% 65% 70% Final model review is done and

    complete alignment between EPCO

    team is ensured

    Re-align major equipment despatch

    schedule with system start-up

    sequence and inform vendor

    Detail Mechanical Work completion

    plan is prepared and alignment with

    system start-up target ensured

    All vendor data are validated &

    included in design

    Bulk item ordering completes Piping (A/G, U/G) work starts IFC deliverable of All discipline must

    show battery limit / process interface

    System driven pre-commissioning &

    handover plan prepared. Utilities,

    Consumables & P&M are estimated.

    Major discipline IFC

    deliverable issue neras

    completion

    E&I contractor gets mobilised Detail System definition and

    commodity wise scope are prepared

    E&I contractor is appraised about

    front availability & completion /

    charging target.

    M4 IFC deliverable issue

    completed

    Long Lead items starts arrival

    at site

    Mjor Civil, Structural,

    Mechanical works are

    complete

    100% 96% 98% 97% Field engineering set-up ready for

    quick response regarding schedule

    improvement solution thru innovative

    construction.

    Mobilisation of Equipment Vendor

    Rep. / Technology providers Rep.

    starts as per Start-up sequence

    Closely co-ordinate between

    discipline contractor for timely

    erection of Critical equipment.

    Engineering Package

    transferred to field

    Bulk Item receipt completed E&I work under progress Physical / walk through audit starts

    for ascertaining critical interface /

    battery limit physical completion

    Spares & Consumables, Critical

    Tools & Tackles required for Mech.

    Completion are identified and

    availability ensured at site

    Ensures hook up of elements with

    installed equipment just after

    erection completion.

    Filed engineerig starts Critical equipment erection

    starts

    Mechanical completion task force is

    formed and resources & utilities are

    made ready.

    M5 As built Starts Equipment Order Close out

    process starts

    System Mechanical

    completion & handover to

    operation starts

    100% 99% 99% 99% System dossier need to be prepared

    with certified acceptance record for

    custody transfer.

    Commercial documentation

    completion is ensured.

    Expedite delivery of mechanically

    completed system to operation.

    Trial run of equipments start Mutual walk through of operation to

    identify & liquidate punch points.

  • 8/2/2019 SDC Check Points

    3/3

    Ensures system dossier handover to

    concerned O&M group