SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302...

30
Page 1 of 2 WR4980302 (9/15/2009) Final Submittal SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, BLDG 154 1. PROJECT DISCRIPTION: Building 154 was constructed in 1943 as a Temporary Warehouse, and contains about 116,000 square feet of warehouse, administrative, and shop space. Approximately 54,000 square feet of space at the south end of Building 154 is currently occupied by the Defense Reutilization & Marketing Office (DRMO), with a receiving area that totals approximately 8000 square feet. This warehouse space is currently unheated and has practically zero thermal insulation. At one time, this space was heated with propane unit heaters, but they have since been taken out of service by the activity due to excessive propane cost. This project proposes to install propane radiant heaters to heat the DRMO receiving area. 2. GENERAL CONTRACT REQUIREMENTS: a. The work location is Building 154, located on Cleveland Drive south of “A” Street, MCAS Cherry Point NC. The contractor is responsible for an on-site inspection of the work area to verify work required. Work shall commence upon award of contract with all work completed within 120 days of notice to proceed. Work includes providing all labor, supervision, tools, equipment, materials, and transportation needed for completion of the project. The Contractor shall submit manufacturer's product data and installation instructions for each material and product used to include all items listed in Para 3.b and 3.c below to the Contracting Officer for Facilities Engineering approval prior to ordering material. b. Phased Construction Schedule: (1) General: Within the overall project schedule, commence and complete the work in phases. Demolition and construction shall proceed in accordance with Para 2.b.2, Phasing Schedule, below. On-site working hours shall be between 0700 hours to 1600 hours (or as coordinated with the Contracting Officer). The building will be occupied. Prior to initiating any work, the contractor shall coordinate a final schedule with the Contracting Officer. Every effort shall be made to minimize interruptions to building operations. All equipment and materials shall be on hand prior to start of construction. Any utility outages shall be coordinated a minimum of 15 days in advance with the Contracting Officer with indicated length of required outage. Specific items listed below are major items that will impact Building 154 and are not all- inclusive. Any items later identified, which could impact Building 154 operation, shall be coordinated with the Contracting Officer for order of implementation. The Contractor shall coordinate any changes to the schedule with the Contracting Officer and have approval by the Contracting Officer prior to implementing changes. (2) Phasing Schedule: PHASE 1: 1. Mobilize. 2. Provide submittals. 3. Order equipment.

Transcript of SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302...

Page 1: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Page 1 of 2 WR4980302 (9/15/2009)

Final Submittal

SCOPE OF WORK PROJECT WR4980302

INSTALL RADIANT HEATERS FOR DRMO, BLDG 154 1. PROJECT DISCRIPTION: Building 154 was constructed in 1943 as a Temporary Warehouse, and contains about 116,000 square feet of warehouse, administrative, and shop space. Approximately 54,000 square feet of space at the south end of Building 154 is currently occupied by the Defense Reutilization & Marketing Office (DRMO), with a receiving area that totals approximately 8000 square feet. This warehouse space is currently unheated and has practically zero thermal insulation. At one time, this space was heated with propane unit heaters, but they have since been taken out of service by the activity due to excessive propane cost. This project proposes to install propane radiant heaters to heat the DRMO receiving area. 2. GENERAL CONTRACT REQUIREMENTS: a. The work location is Building 154, located on Cleveland Drive south of “A” Street, MCAS Cherry Point NC. The contractor is responsible for an on-site inspection of the work area to verify work required. Work shall commence upon award of contract with all work completed within 120 days of notice to proceed. Work includes providing all labor, supervision, tools, equipment, materials, and transportation needed for completion of the project. The Contractor shall submit manufacturer's product data and installation instructions for each material and product used to include all items listed in Para 3.b and 3.c below to the Contracting Officer for Facilities Engineering approval prior to ordering material. b. Phased Construction Schedule: (1) General: Within the overall project schedule, commence and complete the work in phases. Demolition and construction shall proceed in accordance with Para 2.b.2, Phasing Schedule, below. On-site working hours shall be between 0700 hours to 1600 hours (or as coordinated with the Contracting Officer). The building will be occupied. Prior to initiating any work, the contractor shall coordinate a final schedule with the Contracting Officer. Every effort shall be made to minimize interruptions to building operations. All equipment and materials shall be on hand prior to start of construction. Any utility outages shall be coordinated a minimum of 15 days in advance with the Contracting Officer with indicated length of required outage. Specific items listed below are major items that will impact Building 154 and are not all-inclusive. Any items later identified, which could impact Building 154 operation, shall be coordinated with the Contracting Officer for order of implementation. The Contractor shall coordinate any changes to the schedule with the Contracting Officer and have approval by the Contracting Officer prior to implementing changes. (2) Phasing Schedule: PHASE 1:

1. Mobilize. 2. Provide submittals. 3. Order equipment.

Page 2: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Page 2 of 2 WR4980302 (9/15/2009)

Final Submittal

PHASE 2: 1. Install radiant heaters and gas lines. 2. Construct equipment pad for propane tank. PHASE 3: 1. Test the system for leaks and proper operation. PHASE 4: 1. Miscellaneous work and general clean up. c. The Contractor shall perform all work and incorporate the intent of this project as stated. Install equipment not covered in this scope, or in manufacturer’s instructions, as recommended by the manufacturer’s representative. The removal, installation, and disposal of all material and equipment shall comply with the Unified Facilities Criteria as they apply to this project. All discarded equipment and debris shall become the property of the Contractor and be disposed off Government property by the Contractor at no additional cost to the Government. The Contractor shall be responsible for any damages to Government property during the performance of this contract. 3. SPECIFIC CONTRACT REQUIREMENTS:

a. Mechanical:

(1) Propane Infrared Radiant Heaters: (a) Provide tubular infrared radiant heaters in accordance with the attached

specification section (23 54 16.00 10 – HEATING SYSTEM; GAS-FIRED HEATERS). Radiant heaters shall each be a Detroit Radiant Products model HL2-20-65, or an approved equal. Each heater shall have its own exhaust vent.

(2) LP Gas Piping: (a) Provide a leased aboveground LP gas tank. (b) Provide LP Gas piping in accordance with the attached specification sections (23

11 25 – FACILITY GAS PIPING AND 33 11 23 – NATURAL GAS AND LIQUID PETROLEUM PIPING). Underground LP gas pipe is to be polyethylene. Aboveground LP gas pipe (both indoors and outdoors) is to be ASTM A-53 Schedule 40 steel, painted blue.

c. Electrical:

(a) Install a 1-pole, 30-amp circuit breaker in the existing panel “MDP” (120/208

VAC, 3-phase, 4-wire, 400A). Provide an updated panel schedule. (b) Install ¾” EMT conduit connecting panel “MDP” with each radiant heater.

Provide two #10 AWG copper THHN/THWN conductors plus one #10 ground.

Page 3: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

SECTION 23 11 25

FACILITY GAS PIPING11/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN GAS ASSOCIATION (AGA)

AGA XR0603 (2006) AGA Plastic Pipe Manual for Gas Service

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI Z21.45 (1995) Flexible Connectors of Other Than All-Metal Construction for Gas Appliances

AMERICAN PETROLEUM INSTITUTE (API)

API 570 (1998; Addendum 1 2000, Addendum 2 2001, Addendum 3 2003, Addendum 4 2006) Piping Inspection Code

API MPMS 2.2E (2004) Petroleum and Liquid Petroleum Products - Calibration of Horizontal Cylindrical Tanks - Part 1: Manual Methods

API RP 1110 (2007) Pressure Testing of Liquid Petroleum Pipelines

API RP 2009 (2002) Safe Welding, Cutting, and Hot Work Practices in the Petroleum and Petrochemical Industries

API Spec 5CT (2005; Errata 2006; Errata 2006) Specification for Casing and Tubing

API Std 598 (2004) Valve Inspecting and Testing

API Std 607 (2005) Fire Test for Soft-Seated Quarter-Turn Valves

ASME INTERNATIONAL (ASME)

ASME B1.20.1 (1983; R 2006) Pipe Threads, General Purpose (Inch)

ASME B16.11 (2005) Forged Fittings, Socket-Welding and Threaded

ASME B16.21 (2005) Nonmetallic Flat Gaskets for Pipe

SECTION 23 11 25 Page 1

Page 4: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

Flanges

ASME B16.3 (2006) Malleable Iron Threaded Fittings, Classes 150 and 300

ASME B16.33 (2002; R 2007) Manually Operated Metallic Gas Valves for Use in Gas Piping Systems Up to 125 psi, Sizes NPS 1/2 - NPS 2

ASME B16.39 (1998; R 2006) Standard for Malleable Iron Threaded Pipe Unions; Classes 150, 250, and 300

ASME B16.5 (2003) Standard for Pipe Flanges and Flanged Fittings: NPS 1/2 Through NPS 24

ASME B16.9 (2007) Standard for Factory-Made Wrought Steel Buttwelding Fittings

ASME B31.9 (2008) Building Services Piping

ASME BPVC SEC IX (2007; Addenda 2008) Boiler and Pressure Vessel Code; Section IX, Welding and Brazing Qualifications

ASME BPVC SEC VIII D1 (2007; Addenda 2008) Boiler and Pressure Vessel Code; Section VIII, Pressure Vessels Division 1 - Basic Coverage

ASTM INTERNATIONAL (ASTM)

ASTM A 53/A 53M (2007) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

ASTM D 2513 (2008a) Thermoplastic Gas Pressure Pipe, Tubing, and Fittings

CANADIAN STANDARDS ASSOCIATION (CSA)

CSA CGA 9.2 (1988; R 2003) Manually Operated Shut-Off Valves for Gas Piping Systems - First Edition; General Instruction No 1

CSA AMERICA, INC. (CSA/AM)

CSA/AM Z21.24 (2006) Connectors for Gas Appliances

CSA/AM Z21.41 (2003; A 2005; Errata 2007) Quick-Disconnect Devices for Use with Gas Fuel Appliances

CSA/AM Z21.69 (2002; Addenda A 2003; Addenda B 2006; R 2007) Connectors for Movable Gas Appliances

MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS INDUSTRY (MSS)

MSS SP-25 (1998) Standard Marking System for Valves,

SECTION 23 11 25 Page 2

Page 5: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

Fittings, Flanges and Unions

MSS SP-58 (2002) Standard for Pipe Hangers and Supports - Materials, Design and Manufacture

MSS SP-69 (2003; R 2004) Standard for Pipe Hangers and Supports - Selection and Application

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 54 (2008) National Fuel Gas Code

NFPA 58 (2007; Amendment 1 2007; Amendment 2 2007; Amendment 3 2007; Amendment 4 2008) Liquefied Petroleum Gas Code

NFPA 70 (2007; AMD 1 2008) National Electrical Code - 2008 Edition

THE SOCIETY FOR PROTECTIVE COATINGS (SSPC)

SSPC SP 6 (7) Commercial Blast Cleaning

UNDERWRITERS LABORATORIES (UL)

UL 125 (2007) Standard for Valves for Anhydrous Ammonia and LP-Gas (Other than Safety Relief)

UL 842 (2007) Standard for Valves for Flammable Fluids

UL 860 (2001) Standard for Pipe Unions for Flammable and Combustible Fluids and Fire-Protection Service

UL Gas&Oil Dir (2008) Flammable and Combustible Liquids and Gases Equipment Directory

1.2 SYSTEM DESCRIPTION

The gas piping system includes liquid petroleum piping and appurtenances from point of connection with supply system, as indicated, to gas operated equipment within the facility.

1.2.1 Gas Facility System and Equipment Operation

Include shop drawings showing piping layout, locations of system valves, and gas line markers; step-by-step procedures for system start up, operation and shutdown (index system components and equipment to the system drawings); isolation procedures including valve operation to shutdown or isolate each section of the system (index valves to the system maps and provide separate procedures for normal operation and emergency shutdown if required to be different).

1.2.2 Gas Facility System Maintenance

Include maintenance procedures and frequency for system and equipment;

SECTION 23 11 25 Page 3

Page 6: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

identification of pipe materials and manufacturer by locations, pipe repair procedures, and jointing procedures at transitions to other piping material or material from a different manufacturer.

1.2.3 Gas Facility Equipment Maintenance

Include identification of valves, shut-offs, disconnects, and other equipment by materials, manufacturer, vendor identification and location; maintenance procedures and recommended tool kits for valves and equipment; recommended repair methods (i.e., field repair, factory repair, or replacement) for each valve and piece of equipment; and preventive maintenance procedures, possible failure modes and troubleshooting guide.

1.3 QUALITY ASSURANCE

Submit manufacturer's descriptive data and installation instructions for approval for compression-type mechanical joints used in joining dissimilar materials and for insulating joints. Mark all valves, flanges and fittings in accordance with MSS SP-25.

1.3.1 Welding Qualifications

a. Weld piping in accordance with qualified procedures using performance qualified welders and welding operators in accordance with API RP 2009, ASME BPVC SEC IX, and ASME B31.9. Welding procedures qualified by others, and welders and welding operators qualified by another employer may be accepted as permitted by ASME B31.9. Notify the Contracting Officer at least 24 hours in advance of tests, and perform at the work site if practicable.

b. Submit a certified copy of welders procedures and qualifications metal and PE in conformance with ASME B31.9 for each welder and welding operator. Submit the assigned number, letter, or symbol that will be used in identifying the work of each welder to the Contracting Officer.

1.3.2 Jointing Thermoplastic and Fiberglass Piping

Perform all jointing of piping using qualified joiners and qualified procedures in accordance with AGA XR0603. Furnish the Contracting Officer with a copy of qualified procedures and list of and identification symbols of qualified joiners. Submit manufacturer's installation instructions and manufacturer's visual joint appearance chart, including all PE pipe and fittings.

1.3.3 Shop Drawings

Submit drawings for complete Gas Piping System, within 30 days of contract award, showing location, size and all branches of pipeline; location of all required shutoff valves; and instructions necessary for the installation of gas equipment connectors and supports. Include LP storage tank, pad, and mounting details.

1.4 DELIVERY, STORAGE, AND HANDLING

Handle, transport, and store plastic pipe and fittings carefully. Plug or cap pipe and fittings ends during transportation or storage to minimize dirt and moisture entry. Do not subject piping to abrasion or concentrated external loads. Discard PE pipe sections and fittings that have been damaged.

SECTION 23 11 25 Page 4

Page 7: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

PART 2 PRODUCTS

2.1 MATERIALS AND EQUIPMENT

Provide materials and equipment which are the standard products of a manufacturer regularly engaged in the manufacture of the products and that essentially duplicate items that have been in satisfactory use for at least 2 years prior to bid opening. Asbestos or products containing asbestos are not allowed. Submit catalog data and installation instructions for pipe, valves, all related system components, pipe coating materials and application procedures. Conform to NFPA 58 and with requirements specified herein. Provide supply piping to appliances or equipment at least as large as the inlets thereof.

2.2 GAS PIPING SYSTEM AND FITTINGS

2.2.1 Steel Pipe, Joints, and Fittings

a. Pipe: Black carbon steel in accordance with ASTM A 53/A 53M, Schedule 40, threaded ends for sizes 2 inches and smaller; otherwise, plain end beveled for butt welding.

b. Threaded Fittings: ASME B16.3, black malleable iron.

c. Socket-Welding Fittings: ASME B16.11, forged steel.

d. Butt-Welding Fittings: ASME B16.9, with backing rings of compatible material.

e. Unions: ASME B16.39, black malleable iron.

f. Flanges and Flanged Fittings: ASME B16.5 steel flanges or convoluted steel flanges conforming to ASME BPVC SEC VIII D1, with flange faces having integral grooves of rectangular cross sections which afford containment for self-energizing gasket material.

2.2.2 Thermoplastic Pipe, Tubing, Joints, and Fittings

Provide thermoplastic pipe, tubing,casing and joints and fittings conforming to ASTM D 2513 and API Spec 5CT.

2.2.3 Sealants for Steel Pipe Threaded Joints

Provide joint sealing compound as listed in UL Gas&Oil Dir, Class 20 or less. For taping, use tetrafluoroethlene tape conforming to UL Gas&Oil Dir.

2.2.4 Warning and Identification

Provide pipe flow markings, warning and identification tape, and metal tags as required.

2.2.5 Flange Gaskets

Provide gaskets of nonasbestos compressed material in accordance with ASME B16.21, 1/16 inch thickness, full face or self-centering flat ring type, containing aramid fibers bonded with styrene butadiene rubber (SBR) or nitrile butadiene rubber (NBR) suitable for a maximum 600 degree F

SECTION 23 11 25 Page 5

Page 8: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

service, to be used for hydrocarbon service.

2.2.6 Pipe Threads

Provide pipe threads conforming to ASME B1.20.1.

2.2.7 Escutcheons

Provide chromium-plated steel or chromium-plated brass escutcheons, either one piece or split pattern, held in place by internal spring tension or set screw.

2.2.8 Gas Transition Fittings

a. Provide steel to plastic (PE) designed for steel-to-plastic with tapping tee or sleeve conforming to AGA XR0603 requirements for transitions fittings. Coat or wrap exposed steel pipe with heavy plastic coating.

c. Provide manually operated shut-off valve conforming to CSA CGA 9.2

2.2.9 Insulating Pipe Joints

2.2.9.1 Insulating Joint Material

Provide insulating joint material between flanged or threaded metallic pipe systems where shown to control galvanic or electrical action.

2.2.9.2 Threaded Pipe Joints

Provide threaded pipe joints of steel body nut type dielectric unions with insulating gaskets.

2.2.9.3 Flanged Pipe Joints

Provide joints for flanged pipe consisting of full face sandwich-type flange insulating gasket of the dielectric type, insulating sleeves for flange bolts, and insulating washers for flange nuts.

2.2.10 Flexible Connectors

a. Provide flexible connectors for connecting gas utilization equipment to building gas piping conforming to CSA/AM Z21.24, ANSI Z21.45, or CSA/AM Z21.41 for quick disconnect devices, and flexible connectors for movable food service equipment conforming to CSA/AM Z21.69.

b. Do not install the flexible connector through the appliance cabinet face. Provide rigid metallic pipe and fittings to extend the final connection beyond the cabinet, except when appliance is provided with an external connection point.

2.3 VALVES

Provide lockable shutoff or service isolation valves as indicated in the drawings conforming to the following:

SECTION 23 11 25 Page 6

Page 9: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

2.3.1 Valves 2 Inches and Smaller

Provide valves 2 inches and smaller conforming to ASME B16.33 of materials and manufacture compatible with system materials used.

2.4 RISERS

Provide manufacturer's standard riser, transition from plastic to steel pipe with 7 to 12 mil thick epoxy coating. Use swaged gas-tight construction with O-ring seals, metal insert, and protective sleeve. Provide remote bolt-on or bracket or wall-mounted riser supports.

2.5 PIPE HANGERS AND SUPPORTS

Provide pipe hangers and supports conforming to MSS SP-58 and MSS SP-69.

2.6 LIQUIFIED PETROLEUM GAS - (LPG), LPG CONTAINERS AND ACCESSORIES

Provide NFPA 58 compliant containers with appurtenances, system working pressure, minimum design pressure, that is LPG vapor pressure at 100 degrees F, and water capacity as indicated. Provide containers with piping and fittings, fuse plugs, hose and flexible hose connectors, and marking conforming to NFPA 58, and API MPMS 2.2E for horizontal cylindrical tanks Provide valves conforming to UL 125 and UL 842. Provide pipe unions conforming to UL 860.

PART 3 EXECUTION

3.1 EXAMINATION

After becoming familiar with all details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy or areas of conflict before performing the work.

3.2 GAS PIPING SYSTEM

Provide a gas piping system from the point of delivery, defined as the outlet of the shutoff valve, to the connections to each gas utilization device.

3.2.1 Protection and Cleaning of Materials and Components

Protect equipment, pipe, and tube openings by closing with caps or plugs during installation. At the completion of all work, thoroughly clean the entire system.

3.2.2 Workmanship and Defects

Piping, tubing and fittings shall be clear and free of cutting burrs and defects in structure or threading and shall be thoroughly brushed and chip-and scale-blown. Repair of defects in piping, tubing or fittings is not allowed; replace defective items when found.

SECTION 23 11 25 Page 7

Page 10: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

3.3 PROTECTIVE COVERING

3.3.1 Aboveground Metallic Piping Systems

3.3.1.1 Ferrous Surfaces

Touch up shop primed surfaces with ferrous metal primer. Solvent clean surfaces that have not been shop primed . Mechanically clean surfaces that contain loose rust, loose mill scale and other foreign substances by power wire brushing or commercial sand blasted conforming to SSPC SP 6 and prime with ferrous metal primer. Finish primed surfaces with two coats of exterior oil paint.

3.4 INSTALLATION

Install the gas system in conformance with the manufacturer's recommendations and applicable provisions of NFPA 58, AGA XR0603, and as indicated. Perform all pipe cutting without damage to the pipe, with an approved type of mechanical cutter, unless otherwise authorized. Use wheel cutters where practicable. On steel pipe 6 inches and larger, an approved gas cutting and beveling machine may be used. Cut thermoplastic and fiberglass pipe in accordance with AGA XR0603.

3.4.1 Metallic Piping Installation

Bury underground piping a minimum of 18 inches below grade. Make changes in direction of piping with fittings only; mitering or notching pipe to form elbows and tees or other similar type construction is not permitted. Branch connection may be made with either tees or forged branch outlet fittings. Provide branch outlet fittings which are forged, flared for improvement of flow where attached to the run, and reinforced against external strains. Do not use aluminum alloy pipe in exterior locations or underground.

3.4.2 Thermoplastic and Fiberglass Piping, Tubing, and Fittings

Installation of thermoplastic and fiberglass piping, tubing, and fittings is permitted only outside and underground. Bury piping a minimum of 18 inches below grade. Install the piping to avoid excessive stresses due to thermal contraction, and use only where indicated.

3.4.3 Connections Between Metallic and Plastic Piping

Connections between metallic and plastic piping are only allowed outside, underground, and with approved transition fittings.

3.4.4 Concealed Piping in Buildings

Do not use combinations of fittings ( unions, tubing fittings, running threads, right- and left-hand couplings, bushings, and swing joints) to conceal piping within buildings.

3.4.4.1 Piping in Partitions

Locate concealed piping in hollow, rather than solid, partitions. Protect tubing passing through walls or partitions against physical damage both during and after construction, and provide appropriate safety markings and labels.

SECTION 23 11 25 Page 8

Page 11: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

3.4.5 Aboveground Piping

Run aboveground piping as straight as practicable along the alignment and elevation indicated, with a minimum of joints, and separately supported from other piping system and equipment. Install exposed horizontal piping no farther than 6 inches from nearest parallel wall and at an elevation which prevents standing, sitting, or placement of objects on the piping.

3.4.6 Final Gas Connections

Unless otherwise specified, make final connections with rigid metallic pipe and fittings. Flexible connectors may be used for final connections to gas utilization equipment. In addition to cautions listed in instructions required by ANSI standards for flexible connectors, insure that flexible connectors do not pass through equipment cabinet. Provide accessible gas shutoff valve and coupling for each gas equipment item.

3.5 PIPE JOINTS

Design and install pipe joints to effectively sustain the longitudinal pull-out forces caused by contraction of the piping or superimposed loads.

3.5.1 Threaded Metallic Joints

Provide threaded joints in metallic pipe with tapered threads evenly cut and made with UL approved graphite joint sealing compound for gas service or tetrafluoroethylene tape applied to the male threads only. Threaded joints up to 1-1/2 inches in diameter may be made with approved tetrafluoroethylene tape. Threaded joints up to 2 inches in diameter may be made with approved joint sealing compound. After cutting and before threading, ream pipe and remove all burrs. Caulking of threaded joints to stop or prevent leaks is not permitted.

3.5.2 Welded Metallic Joints

Conform beveling, alignment, heat treatment, and inspection of welds to NFPA 54. Remove weld defects and make repairs to the weld, or remove the weld joints entirely and reweld. After filler metal has been removed from its original package, protect and store so that its characteristics or welding properties are not affected adversely. Do not use electrodes that have been wetted or have lost any of their coating.

3.5.3 Thermoplastic and Fiberglass Joints

a. Thermoplastic and Fiberglass: Conform jointing procedures to AGA XR0603. Do not make joints with solvent cement or heat of fusion between different kinds of plastics.

b. PE Fusion Welding Inspection: Visually inspect butt joints by comparing with, manufacturer's visual joint appearance chart. Inspect fusion joints for proper fused connection. Replace defective joints by cutting out defective joints or replacing fittings. Inspect, in conformance with API 570, 100 percent of all joints and re-inspect all corrections. Arrange with the pipe manufacturer's representative in the presence of the Contracting Officer to make first time inspection.

3.5.4 Joining Thermoplastic or Fiberglass to Metallic Piping or Tubing

When compression type mechanical joints are used, provide gasket material

SECTION 23 11 25 Page 9

Page 12: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

in the fittings compatible with the plastic piping and with the gas in the system. Use an internal tubular rigid stiffener in conjunction with the fitting, flush with end of the pipe or tubing, extending at least to the outside end of the compression fitting when installed. Remove all rough or sharp edges from stiffener. Do not force fit stiffener in the plastic. Split tubular stiffeners are not allowed.

3.5.5 Press Connections

Make press connections in accordance with manufacturer's installation instructions using tools approved by the manufacturer. Fully insert the tubing into the fitting and then mark at the shoulder of the fitting. Check the fitting alignment against the mark on the tubing to assure the tubing is fully inserted before the joint is pressed.

3.6 PIPE SLEEVES

Provide pipes passing through concrete or masonry walls or concrete floors or roofs with pipe sleeves fitted into place at the time of construction. Do not install sleeves in structural members except where indicated or approved. Make all rectangular and square openings as detailed. Extend each sleeve through its respective wall, floor or roof, and cut flush with each surface, except in mechanical room floors not located on grade where clamping flanges or riser pipe clamps are used. Extend sleeves in mechanical room floors above grade at least 4 inches above finish floor. Unless otherwise indicated, use sleeves large enough to provide a minimum clearance of 1/4 inch all around the pipe. Provide steel pipe for sleeves in bearing walls, waterproofing membrane floors, and wet areas . Provide sleeves in nonbearing walls, floors, or ceilings of steel pipe, galvanized sheet metal with lock-type longitudinal seam, or moisture-resistant fiber or plastic.

3.7 ESCUTCHEONS

Provide escutcheons for all finished surfaces where gas piping passes through floors, walls, or ceilings except in boiler, utility, or equipment rooms.

3.8 SPECIAL REQUIREMENTS

Provide drips, grading of the lines, freeze protection, and branch outlet locations as shown and conforming to the requirements of NFPA 58.

3.9 BUILDING STRUCTURE

Do not weaken any building structure by the installation of any gas piping. Do not cut or notch beams, joists or columns. Attach piping supports to metal decking. Do not attach supports to the underside of concrete filled floors or concrete roof decks unless approved by the Contracting Officer.

3.10 PIPING SYSTEM SUPPORTS

Support gas piping systems in buildings with pipe hooks, metal pipe straps, bands or hangers suitable for the size of piping or tubing. Do not support any gas piping system by other piping. Conform spacing of supports in gas piping and tubing installations to the requirements of NFPA 58. Conform the selection and application of supports in gas piping and tubing installations to the requirements of MSS SP-69. In the support of multiple

SECTION 23 11 25 Page 10

Page 13: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

pipe runs on a common base member, use a clip or clamp where each pipe crosses the base support member. Spacing of the base support members is not to exceed the hanger and support spacing required for any of the individual pipes in the multiple pipe run. Rigidly connect the clips or clamps to the common base member. Provide a clearance of 1/8 inch between the pipe and clip or clamp for all piping which may be subjected to thermal expansion.

3.11 ELECTRICAL BONDING AND GROUNDING

Provide a gas piping system within the building which is electrically continuous and bonded to a grounding electrode as required by NFPA 70.

3.12 SHUTOFF VALVE

Install the main gas shutoff valve controlling the gas piping system to be easily accessible for operation, as indicated, protected from physical damage, and marked with a metal tag to clearly identify the piping system controlled.

3.13 TESTING

Submit test reports in booklet form tabulating test and measurements performed; dated after award of this contract, and stating the Contractor's name and address, the project name and location, and a list of the specific requirements which are being certified. Test entire gas piping system to ensure that it is gastight prior to putting into service. Prior to testing, blow out the system, clean, and clear all foreign material. Test each joint with an approved gas detector, soap and water, or an equivalent nonflammable solution. Inspect and test each valve in conformance with API Std 598 and API Std 607. Complete testing before any work is covered, enclosed, or concealed, and perform with due regard for the safety of employees and the public during the test. Install bulkheads, anchorage and bracing suitably designed to resist test pressures if necessary, and as directed and or approved by the Contracting Officer. Do not use oxygen as a testing medium.

3.13.1 Pressure Tests

Submit test reports in booklet form tabulating test and measurements performed; dated after award of this contract, and stating the Contractor's name and address, the project name and location, and a list of the specific requirements which are being certified. Before appliances are connected, test by filling the piping systems with air or an inert gas to withstand a minimum pressure as specified in NFPA 58 without showing any drop in pressure. Do not use Oxygen for test. Measure pressure with a mercury manometer, slope gauge, or an equivalent device calibrated to be read in increments of not greater than 0.1 pound. Isolate the source of pressure before the pressure tests are made.

3.13.2 Pressure Tests for Liquified Petroleum Gas

Pressure test system as described above. When appliances are connected to the piping system, use fuel gas for testing appliances to withstand a pressure of not less than 10.0 inches nor more than 14.0 inches water column ( 0.36 nor more than 0.51 pounds per square inch) for a period of not less than 10 minutes without showing any drop in pressure. Measure pressure with a water manometer or an equivalent device calibrated to be read in increments of not greater than 0.1 inch water column. Isolate the

SECTION 23 11 25 Page 11

Page 14: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

source of pressure before the pressure tests are made.

3.13.3 Test With Gas

Before turning on gas under pressure into any piping, close all openings from which gas can escape. Immediately after turning on the gas, check the piping system for leakage by using a laboratory-certified gas meter, an appliance orifice, a manometer, or equivalent device. Conform all testing to the requirements of NFPA 58. If leakage is recorded, shut off the gas supply, repair the leak , and repeat the tests until all leaks have been stopped.

3.13.4 Purging

After testing is completed, and before connecting any appliances, fully purge all gas piping. LPG piping tested using fuel gas with appliances connected does not require purging. Conform testing procedures to API RP 1110. Do not purge piping into the combustion chamber of an appliance. Do not purge the open end of piping systems into confined spaces or areas where there are ignition sources unless the safety precautions recommended in NFPA 58 are followed.

3.13.5 Labor, Materials and Equipment

Furnish all labor, materials and equipment necessary for conducting the testing and purging.

-- End of Section --

SECTION 23 11 25 Page 12

Page 15: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

SECTION 23 54 16.00 10

HEATING SYSTEM; GAS-FIRED HEATERS04/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

CSA AMERICA, INC. (CSA/AM)

CSA Directory (updated continuously online) Certified Products Listings

CSA/AM Z21.66 (1996; R 2006) Automatic Vent Damper Devices for Use with Gas-Fired Appliances

CSA/AM Z83.19 (2001; R 2005; Addenda 2007) Gas-Fired Infrared Heaters

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA MG 1 (2007) Standard for Motors and Generators

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 211 (2006) Chimneys, Fireplaces, Vents, and Solid Fuel-Burning Appliances

NFPA 54 (2008) National Fuel Gas Code

UNDERWRITERS LABORATORIES (UL)

UL Gas&Oil Dir (2008) Flammable and Combustible Liquids and Gases Equipment Directory

1.2 QUALITY ASSURANCE

Submit detail drawings consisting of illustrations, schedules, performance charts, instructions, brochures, diagrams, and other information to illustrate the requirements and operation of the system. Detail drawings for space heating equipment, controls, associated equipment, and for piping and wiring. Drawings shall show proposed layout and anchorage of equipment and appurtenances, and equipment relationship to other parts of the work including clearances for maintenance and operation.

1.3 DELIVERY, STORAGE, AND HANDLING

Protect all equipment delivered and placed in storage from weather, humidity and temperature variations, dirt and dust, or other contaminants.

SECTION 23 54 16.00 10 Page 1

Page 16: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

1.4 EXTRA MATERIALS

Submit spare parts for each different item of material and equipment specified, after approval of the detail drawings, and not later than one month prior to the date of beneficial occupancy. Include in the data a complete list of parts and supplies, with current unit prices and source of supply.

PART 2 PRODUCTS

2.1 MATERIALS AND EQUIPMENT

2.1.1 General

Provide materials and equipment which are standard products of a manufacturer regularly engaged in manufacturing of the products and that essentially duplicate equipment that has been in satisfactory use at least 2 years prior to bid opening.

2.1.2 Nameplates

Secure a plate to each major component of equipment containing the manufacturer's name, address, type or style, model or serial number, and catalog number. Also, affix an ENERGY STAR label as applicable.

2.1.3 Equipment Guards

Belts, pulleys, chains, gears, couplings, projecting setscrews, keys, and other rotating parts so located that any person may come in close proximity thereto shall be completely enclosed or guarded. High-temperature equipment and piping so located as to endanger personnel or create a fire hazard shall be guarded or covered with insulation of type specified for service.

2.2 ELECTRICAL WORK

Electrical motor driven equipment shall be provided complete with motors, motor starters, and controls. Motors shall conform to NEMA MG 1. Electrical characteristics shall be as specified or indicated. Integral size motors shall be premium efficiency type in accordance with NEMA MG 1. Motor starters shall be provided complete with thermal overload protection and other appurtenances necessary for the motor control specified. Each motor shall be of sufficient size to drive the equipment at the specified capacity without exceeding the nameplate rating of the motor. Manual or automatic control and protective or signal devices required for the operation specified and any control wiring required for controls and devices specified, but not shown, shall be provided.

2.3 HEATERS

Heaters shall be equipped for and adjusted to burn liquified petroleum gas. Each heater shall be provided with a gas pressure regulator that will satisfactorily limit the main gas burner supply pressure. Heaters shall have an intermittent or interrupted electrically ignited pilot or a direct electric ignition system. Safety controls shall conform to the ANSI standard specified for each heater. Mounting brackets and hardware shall be furnished by the heater manufacturer and shall be factory finished to match the supported equipment.

SECTION 23 54 16.00 10 Page 2

Page 17: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

2.3.1 Infrared Heaters

Heaters shall conform to the requirements of CSA/AM Z83.19 and shall be vented type as indicated. Vented heaters shall be vented to the outside atmosphere. Heater style shall be tubular type as indicated. Reflector shape shall be standard as indicated. Heaters shall be provided with space thermostats which control the unit's burner. Thermostats located in the direct radiation pattern shall be covered with a metal shield.

2.4 THERMOSTATS

Thermostats shall be the adjustable electric or electronic type. Control wiring required to complete the space temperature control system shall be included. Thermostats shall have a 3 degree F differential and a set point range of 40 to 75 degrees F.

2.5 VENT PIPING

Vent piping shall conform to the requirements of NFPA 54. Plastic material polyetherimide (PEI) and polyethersulfone (PES) are forbidden to be used for vent piping of combustion gases.

2.6 ELECTRIC AUTOMATIC VENT DAMPERS

Electric automatic vent dampers shall conform to the requirements of CSA/AM Z21.66 and shall be provided in the vents of heaters using indoor air for combustion air.

2.7 FACTORY FINISHES

Equipment and component items, when fabricated from ferrous metal, shall be factory finished with the manufacturer's standard finish.

PART 3 EXECUTION

3.1 EXAMINATION

After becoming thoroughly familiar with all details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy before performing any work.

3.2 INSTALLATION

Install equipment as indicated and in accordance with the recommendations of the equipment manufacturer and the listing agency, except as otherwise specified.

3.2.1 Heating Equipment

Install heaters with clearance to combustibles, complying with minimum distances as determined by CSA Directory, UL Gas&Oil Dir and as indicated on each heater approval and listing plate. Support heaters independently from the building structure, as indicated, but not relying on suspended ceiling systems for support.

3.2.2 Vents

Locate vent dampers, piping and structural penetrations as indicated. Vent damper installation shall conform to CSA/AM Z21.66. Vent pipes, where not

SECTION 23 54 16.00 10 Page 3

Page 18: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

connected to a masonry chimney conforming to NFPA 211, shall extend through the roof or an outside wall and shall terminate, in compliance with NFPA 54. Vents passing through waterproof membranes shall be provided with the necessary flashings to obtain waterproof installations.

3.2.3 Gas Piping

Connect gas piping as indicated, complying with the applicable requirements at Section 23 11 25 FACILITY GAS PIPING.

-- End of Section --

SECTION 23 54 16.00 10 Page 4

Page 19: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

SECTION 33 11 23

NATURAL GAS AND LIQUID PETROLEUM PIPING08/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI Z21.45 (1995) Flexible Connectors of Other Than All-Metal Construction for Gas Appliances

ASME INTERNATIONAL (ASME)

ASME B1.1 (2003; R 2008) Unified Inch Screw Threads (UN and UNR Thread Form)

ASME B1.20.1 (1983; R 2006) Pipe Threads, General Purpose (Inch)

ASME B16.11 (2005) Forged Fittings, Socket-Welding and Threaded

ASME B16.3 (2006) Malleable Iron Threaded Fittings, Classes 150 and 300

ASME B16.33 (2002; R 2007) Manually Operated Metallic Gas Valves for Use in Gas Piping Systems Up to 125 psi, Sizes NPS 1/2 - NPS 2

ASME B16.38 (2007) Large Metallic Valves for Gas Distribution (Manually Operated, NPS 2 1/2 to 12, 125 psig Maximum)

ASME B16.39 (1998; R 2006) Standard for Malleable Iron Threaded Pipe Unions; Classes 150, 250, and 300

ASME B16.5 (2003) Standard for Pipe Flanges and Flanged Fittings: NPS 1/2 Through NPS 24

ASME B16.9 (2007) Standard for Factory-Made Wrought Steel Buttwelding Fittings

ASME B18.2.1 (1996; Addenda A 1999; Errata 2003; R 2005) Square and Hex Bolts and Screws (Inch Series)

ASME B18.2.2 (1987; R 2005) Standard for Square and Hex Nuts

ASME B31.8 (2007) Gas Transmission and Distribution

SECTION 33 11 23 Page 1

Page 20: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

Piping Systems

ASME BPVC SEC VIII D1 (2007; Addenda 2008) Boiler and Pressure Vessel Code; Section VIII, Pressure Vessels Division 1 - Basic Coverage

ASTM INTERNATIONAL (ASTM)

ASTM A 193/A 193M (2008b) Standard Specification for Alloy-Steel and Stainless Steel Bolting Materials for High-Temperature Service

ASTM A 194/A 194M (2008b) Standard Specification for Carbon and Alloy Steel Nuts for Bolts for High-Pressure or High-Temperature Service, or Both

ASTM A 53/A 53M (2007) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

ASTM D 2513 (2008a) Thermoplastic Gas Pressure Pipe, Tubing, and Fittings

ASTM D 2683 (2004) Standard Specification for Socket-Type Polyethylene Fittings for Outside Diameter-Controlled Polyethylene Pipe and Tubing

CSA AMERICA, INC. (CSA/AM)

CSA/AM Z21.41 (2003; A 2005; Errata 2007) Quick-Disconnect Devices for Use with Gas Fuel Appliances

CSA/AM Z21.69 (2002; Addenda A 2003; Addenda B 2006; R 2007) Connectors for Movable Gas Appliances

MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS INDUSTRY (MSS)

MSS SP-58 (2002) Standard for Pipe Hangers and Supports - Materials, Design and Manufacture

MSS SP-69 (2003; R 2004) Standard for Pipe Hangers and Supports - Selection and Application

MSS SP-89 (2003) Pipe Hangers and Supports - Fabrication and Installation Practices

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 54 (2008) National Fuel Gas Code

NFPA 58 (2007; Amendment 1 2007; Amendment 2 2007; Amendment 3 2007; Amendment 4 2008) Liquefied Petroleum Gas Code

SECTION 33 11 23 Page 2

Page 21: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

U.S. DEPARTMENT OF DEFENSE (DOD)

MIL-STD-101 (Rev B) Color Code for Pipelines & for Compressed Gas Cylinders

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

49 CFR 192 Transportation of Natural and Other Gas by Pipeline: Minimum Federal Safety Standards

49 CFR 195 Transportation of Hazardous Liquids by Pipeline

1.2 QUALITY ASSURANCE

1.2.1 Welder's Qualifications

Comply with ASME B31.8. The steel welder shall have a copy of a certified ASME B31.8 qualification test report. The PE welder shall have a certificate from a PE pipe manufacturer's sponsored training course. Contractor shall also conduct a qualification test. Submit each welder's identification symbols, assigned number, or letter, used to identify work of the welder. Affix symbols immediately upon completion of welds. Welders making defective welds after passing a qualification test shall be given a requalification test and, upon failing to pass this test, shall not be permitted to work this contract.

1.2.2 PE Welder's Qualifications

Prior to installation, Contractor shall have supervising and installing personnel trained by a PE pipe manufacturer's sponsored course of not less than one week duration, or present proof satisfactory to the Contracting Officer that personnel are currently working in the installation of PE gas distribution lines.

1.2.3 Safety Standards

49 CFR 192 and 49 CFR 195.

1.3 DELIVERY, STORAGE, AND HANDLING

Handle, transport, and store plastic pipe and fittings carefully. Plug or cap pipe ends during transportation or storage to minimize dirt and moisture entry. Do not subject to abrasion or concentrated external loads. Discard PE pipe sections and fittings that have been damaged.

1.4 WARRANTY

PART 2 PRODUCTS

2.1 MATERIALS AND EQUIPMENT

Conform to NFPA 54 and with requirements specified herein. Supply piping to appliances or equipment shall be at least as large as the inlets thereof.

SECTION 33 11 23 Page 3

Page 22: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

2.2 PIPE AND FITTINGS

2.2.1 Aboveground and Within Buildings and Vaults

a. Pipe: Black steel in accordance with ASTM A 53/A 53M, Schedule 40, threaded ends for sizes 2 inches and smaller; otherwise, plain end beveled for butt welding.

b. Threaded Fittings: ASME B16.3, black malleable iron.

c. Socket-Welding Fittings: ASME B16.11, forged steel.

d. Butt-Welding Fittings: ASME B16.9, with backing rings of compatible material.

e. Unions: ASME B16.39, black malleable iron.

f. Flanges and Flanged Fittings: ASME B16.5 steel flanges or convoluted steel flanges conforming to ASME BPVC SEC VIII D1. Flange faces shall have integral grooves of rectangular cross sections which afford containment for self-energizing gasket material.

2.2.2 Underground Polyethylene (PE)

PE pipe and fittings are as follows:

a. Pipe: ASTM D 2513, 100 psig working pressure, Standard Dimension Ratio (SDR), the ratio of pipe diameter to wall thickness, 11.5 maximum.

b. Socket Fittings: ASTM D 2683.

c. Butt-Fusion Fittings: ASTM D 2513, molded.

2.2.3 Risers

Manufacturer's standard riser, transition from plastic to steel pipe with 7 to 12 mil thick epoxy coating. Use swaged gas-tight construction with O-ring seals, metal insert, and protective sleeve. Provide remote bolt-on or bracket or wall-mounted riser supports.

2.2.4 Transition Fittings

a. Steel to Plastic (PE): As specified for "riser" except designed for steel-to-plastic with tapping tee or sleeve. Coat or wrap exposed steel pipe with heavy plastic coating.

2.3 VALVES, ABOVEGROUND

Provide lockable valves where indicated.

2.3.1 Shutoff Valves, Sizes Larger Than 2 Inches

Cast-iron or steel body ball valve with flanged ends in accordance with ASME B16.38. Provide PTFE seats.

SECTION 33 11 23 Page 4

Page 23: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

2.3.2 Shutoff Valves, Sizes 2 Inches and Smaller

Bronze body ball valve in accordance with ASME B16.33, full port pattern, reinforced PTFE seals, threaded ends, and PTFE seat.

2.3.3 Pressure Regulator

Self-contained with spring-loaded diaphragm pressure regulator, psig to inches water reduction, pressure operating range as required for the pressure reduction indicated, volume capacity not less than indicated, and threaded ends for sizes 2 inches and smaller, otherwise flanged.

2.4 GAS EQUIPMENT CONNECTORS

a. Flexible Connectors: ANSI Z21.45.

b. Quick Disconnect Couplings: CSA/AM Z21.41.

c. Semi-Rigid Tubing and Fittings: CSA/AM Z21.69.

2.5 BURIED UTILITY WARNING AND IDENTIFICATION TAPE

Provide detectable aluminum-foil plastic-backed tape or detectable magnetic plastic tape manufactured specifically for warning and identification of buried piping. Tape shall be detectable by an electronic detection instrument. Provide tape in rolls, 3 inch minimum width, color-coded yellow for natural gas, with warning and identification imprinted in bold black letters continuously and repeatedly over entire tape length. Warning and identification shall be "CAUTION BURIED GAS PIPING BELOW" or similar wording. Use permanent code and letter coloring unaffected by moisture and other substances contained in trench backfill material.

2.6 HANGERS AND SUPPORTS

MSS SP-58, as required by MSS SP-69.

2.7 WELDING FILLER METAL

ASME B31.8.

2.8 PIPE-THREAD TAPE

Antiseize and sealant tape of polytetrafluoroethylene (PTFE).

2.9 BOLTING (BOLTS AND NUTS)

Stainless steel bolting; ASTM A 193/A 193M, Grade B8M or B8MA, Type 316, for bolts; and ASTM A 194/A 194M, Grade 8M, Type 316, for nuts. Dimensions of bolts, studs, and nuts shall conform with ASME B18.2.1and ASME B18.2.2 with coarse threads conforming to ASME B1.1, with Class 2A fit for bolts and studs and Class 2B fit for nuts. Bolts or bolt-studs shall extend through the nuts and may have reduced shanks of a diameter not less than the diameter at root of threads. Bolts shall have American Standard regular square or heavy hexagon heads; nuts shall be American Standard heavy semifinished hexagonal.

2.10 GASKETS

Fluorinated elastomer, compatible with flange faces.

SECTION 33 11 23 Page 5

Page 24: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

2.11 IDENTIFICATION FOR ABOVEGROUND PIPING

MIL-STD-101 for legends and type and size of characters. For pipes 3/4 inch od and larger, provide printed legends to identify contents of pipes and arrows to show direction of flow. Color code label backgrounds to signify levels of hazard. Make labels of plastic sheet with pressure-sensitive adhesive suitable for the intended application. For pipes smaller than3/4 inch od, provide brass identification tags 1 1/2 inches in diameter with legends in depressed black-filled characters.

2.12 (LIQUEFIED PETROLEUM GAS) LPG CONTAINERS AND ACCESSORIES

NFPA 58 containers with appurtenances, system working pressure, minimum design pressure, that is LPG vapor pressure at 100 degrees F, and water capacity as indicated. Provide containers with piping and fittings, fuse plugs, hose and flexible hose connectors, strainer, and marking conforming to NFPA 58.

PART 3 EXECUTION

3.1 INSTALLATION

Install gas piping, appliances, and equipment in accordance with NFPA 54. Install and store liquefied petroleum gas piping, appliances, and equipment in accordance with NFPA 58.

3.1.1 Excavating and Backfilling

Place pipe directly in trench bottom and cover with minimum 3 inches of sand to top of pipe. If trench bottom is rocky, place pipe on a 3 inch bed of sand and cover as above. Provide remaining backfilling. Coordinate provision of utility warning and identification tape with backfill operation. Bury utility warning and identification tape with printed side up at a depth of 12 inches below the top surface of earth or the top surface of the subgrade under pavements.

3.1.2 Piping

Cut pipe to actual dimensions and assemble to prevent residual stress. Within buildings, run piping parallel to structure lines and conceal in finished spaces. Terminate each vertical supply pipe to burner or appliance with tee, nipple and cap to form a sediment trap. To supply multiple items of gas-burning equipment, provide manifold with inlet connections at both ends.

3.1.2.1 Cleanliness

Clean inside of pipe and fittings before installation. Blow lines clear using 80 to 100 psig clean dry compressed air. Rap steel lines sharply along entire pipe length before blowing clear. Cap or plug pipe ends to maintain cleanliness throughout installation.

3.1.2.2 Aboveground Steel Piping

Determine and establish measurements for piping at the job site and accurately cut pipe lengths accordingly. For 2 inch diameter and smaller, use threaded or socket-welded joints. For 2 1/2 inch diameter and larger, use flanged or butt-welded joints.

SECTION 33 11 23 Page 6

Page 25: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

a. Threaded Joints: Where possible use pipe with factory-cut threads, otherwise cut pipe ends square, remove fins and burrs, and cut taper pipe threads in accordance with ASME B1.20.1. Provide threads smooth, clean, and full-cut. Apply anti-seize paste or tape to male threads portion. Work piping into place without springing or forcing. Backing off to permit alignment of threaded joints will not be permitted. Engage threads so that not more than three threads remain exposed. Use unions for connections to valves for which a means of disconnection is not otherwise provided.

b. Welded Joints: Weld by the shielded metal-arc process, using covered electrodes and in accordance with procedures established and qualified in accordance with ASME B31.8.

c. Flanged Joints: Use flanged joints for connecting welded joint pipe and fittings to valves to provide for disconnection. Install joints so that flange faces bear uniformly on gaskets. Engage bolts so that there is complete threading through the nuts and tighten so that bolts are uniformly stressed and equally torqued.

d. Pipe Size Changes: Use reducing fittings for changes in pipe size. Size changes made with bushings will not be accepted.

e. Painting: Paint new ferrous metal piping. Do not apply paint until piping tests have been completed.

f. Identification of Piping: Identify piping aboveground in accordance with MIL-STD-101, using adhesive-backed or snap-on plastic labels and arrows. In lieu of labels, identification tags may be used. Apply labels or tags to finished paint at intervals of not more than 50 feet. Provide two copies of the piping identification code framed under glass and install where directed.

3.1.2.3 Buried Plastic Lines

Provide totally PE piping. Prior to installation, obtain printed instructions and technical assistance in proper installation techniques from pipe manufacturer.

a. PE Piping: Prior to installation, Contractor shall have supervising and installing personnel, certified in accordance with paragraph entitled "Welder's Qualifications." Provide fusion-welded joints except where transitions have been specified. Use electrically heated tools, thermostatically controlled and equipped with temperature indication. (Where connection must be made to existing plastic pipe, contractor shall be responsible for determination of compatibility of materials and procedural changes in fusion process necessary to attain maximum integrity of bond.)

b. Laying PE Pipe: Bury pipe 24 inches below finish grade. Lay in accordance with manufacturer's printed instructions.

3.1.3 Valves

Install valves approximately at locations indicated. Orient stems vertically, with operators on top, or horizontally. Provide support for valves to resist operating torque applied to PE pipes.

SECTION 33 11 23 Page 7

Page 26: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

3.1.3.1 Pressure Regulator

Provide ball valve ahead of regulator. Install regulator outside of building and 18 inches aboveground on riser. On outlet side of regulator, provide a union and a 3/8 inch gage tap with plug.

3.1.3.2 Stop Valve and Shutoff Valve

Provide stop valve on service branch at connection to main and shut-off valve on riser outside of building.

3.1.4 Pipe Sleeves

Where piping penetrates concrete or masonry wall, floor or firewall, provide pipe sleeve poured or grouted in place. Make sleeve of steel or cast-iron pipe of such size to provide 1/4 inch or more annular clearance around pipe. Extend sleeve through wall or slab and terminate flush with both surfaces. Pack annular space with oakum, and caulk at ends with silicone construction sealant.

3.1.5 Piping Hangers and Supports

Selection, fabrication, and installation of piping hangers and supports shall conform with MSS SP-69 and MSS SP-89, unless otherwise indicated.

3.1.6 Final Connections

Make final connections to equipment and appliances using rigid pipe and fittings.

3.2 FIELD QUALITY CONTROL

3.2.1 Metal Welding Inspection

Inspect for compliance with NFPA 54. Replace, repair, and then re-inspect defective welds.

3.2.2 PE Fusion Welding Inspection

Visually inspect butt joints by comparing with, manufacturer's visual joint appearance chart. Inspect fusion joints for proper fused connection. Replace defective joints by cutting out defective joints or replacing fittings. Inspect 100 percent of all joints and reinspect all corrections. Arrange with the pipe manufacturer's representative in the presence of the Contracting Officer to make first time inspection.

3.2.3 Pressure Tests

Use test pressure of 1 1/2 times maximum working pressure, but in no case less than 50 psig. Do not test until every joint has set and cooled at least 8 hours at temperatures above 50 degrees F. Conduct testing before backfilling; however, place sufficient backfill material between fittings to hold pipe in place during tests. Test system gas tight in accordance with NFPA 54. Use clean dry air or inert gas, such as nitrogen or carbon dioxide, for testing. Systems which may be contaminated by gas shall first be purged as specified. Make tests on entire system or on sections that can be isolated by valves. After pressurization, isolate entire piping system from sources of air during test period. Maintain test pressure for

SECTION 33 11 23 Page 8

Page 27: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Install Radiant Heaters for DRMO, Bldg 154 4980302

at least 8 hours between times of first and last reading of pressure and temperature. Take first reading at least one hour after test pressure has been applied. Do not take test readings during rapid weather changes. Provide temperature same as actual trench conditions. There shall be no reduction in the applied test pressure other than that due to a change in ambient temperature. Allow for ambient temperature change in accordance with the relationship PF + 14.7 = (P1 + 14.7) (T2 + 460) / T1 + 460), in which "T" and "PF" represent Fahrenheit temperature and gage pressure, respectively, subscripts "1" and "2" denote initial and final readings, and "PF" is the calculated final pressure. If "PF" exceeds the measured final pressure (final gage reading) by 1/2 psi or more, isolate sections of the piping system, retest each section individually, and apply a solution of warm soapy water to joints of each section for which a reduction in pressure occurs after allowing for ambient temperature change. Repair leaking joints and repeat test until no reduction in pressure occurs. In performing tests, use a test gage calibrated in one psi increments and readable to 1/2 psi.

3.2.4 System Purging

After completing pressure tests, and before testing a gas contaminated line, purge line with nitrogen at junction with main line to remove all air and gas. Clear completed line by attaching a test pilot fixture at capped stub-in line at building location and let gas flow until test pilot ignites. Procedures shall conform to NFPA 54.

-CAUTION-

Failure to purge may result in explosion within line when air-to-gas is at correct mixture.

-- End of Section --

SECTION 33 11 23 Page 9

Page 28: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

General Decision Number: NC080055 07/24/2009 NC55 Superseded General Decision Number: NC20070055 State: North Carolina Construction Type: Building County: Craven County in North Carolina. Modification Number Publication Date 0 02/08/2008 1 03/07/2008 2 06/06/2008 3 01/30/2009 4 02/13/2009 5 02/20/2009 6 07/24/2009 BOIL0030-001 01/01/2009 Rates Fringes Boilermaker....................$ 27.63 13.96 Welder: Pressure welder: $.75 per hour additional. ---------------------------------------------------------------- * SUNC2000-002 03/21/2000 Rates Fringes Carpenter _(includes drywall hanging).$ 9.82 Cement mason/concrete finisher.....................$ 9.75 Electrician....................$ 10.18 Laborer, general...............$ 7.25 Painter, brush.................$ 10.00 Pipefitter _(includes HVAC piping).....$ 13.50 .93 Plumber _(does not include HVAC piping)..................$ 11.75 .66 Power equipment operators: _Backhoe operator...........$ 10.54 Sheet metal worker _(includes HVAC duct work)..$ 11.56 .97

Page 29: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

Truck driver...................$ 7.88 ---------------------------------------------------------------- WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental. ================================================================ Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)). ---------------------------------------------------------------- In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing. ---------------------------------------------------------------- WAGE DETERMINATION APPEALS PROCESS 1.) Has there been an initial decision in the matter? This can be: * an existing published wage determination * a survey underlying a wage determination * a Wage and Hour Division letter setting forth a position on a wage determination matter * a conformance (additional classification and rate) ruling On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed. With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to: Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to: Wage and Hour Administrator

Page 30: SCOPE OF WORK PROJECT WR4980302 INSTALL RADIANT HEATERS ... · PDF filePROJECT WR4980302 INSTALL RADIANT HEATERS FOR DRMO, ... Provide two #10 AWG copper THHN/THWN conductors plus

U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue. 3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to: Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 4.) All decisions by the Administrative Review Board are final. ================================================================ END OF GENERAL DECISION