Scope 18km of sewers (0.5m to 3.0m dia) 2 lift stations
description
Transcript of Scope 18km of sewers (0.5m to 3.0m dia) 2 lift stations
1
Scope
1. 18km of sewers (0.5m to 3.0m dia)
2. 2 lift stations
3. Demolition of 4 pumping stations – Jurong West, Jalan Bahar, Corporation and International Road pumping stations
4. Grouting of 18km of twin pumping mains (0.66m to 0.95m dia)
Sewerage Schemes to serve Developments inSewerage Schemes to serve Developments inJurong Eastern Catchment and Jurong Lake Jurong Eastern Catchment and Jurong Lake
DistrictDistrictObjective
Extend sewers to serve new developments & phase out 4 pumping stations
2
Jurong Eastern Catchment SchemeJurong Eastern Catchment Scheme
3
Jurong Lake District SchemeJurong Lake District Scheme
4
Important Notes for Interested Partners:
1. Tenders for Consultancy Services – end Mar 2010
2. Tenders for Works – Nov 2010
3. Very tight schedule, sewers and lift stations – complete by 2nd half of 2013
4. Potential Tenderers – prepare early, source for suitable pipe jacking machines, and familiarise with site conditions