School of Fine Arts
Facility & Capital Project Update
Colleen Bridgeman
Assistant Dean & COO
August 24, 2018
![Page 2: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/2.jpg)
Renovations – Recent & Ongoing
• Restoration Improvements• Office Operations – Complete• Box Office – Complete• Audience Hall – Complete• Back Stage – Winter Break • Front Lobby – Winter Break
• Video Projector and Screen Replacement Upgrade – Complete
J. Louis von der Mehden Recital Hall
![Page 3: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/3.jpg)
J. Louis von der Mehden Recital Hall– Future Lobby Renovation View
Renovations – Recent & Ongoing
![Page 4: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/4.jpg)
Renovations – Recent & Ongoing
• Flooring & Lighting Upgrades to Gallery Spaces
William Benton Museum of Art
![Page 5: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/5.jpg)
Renovations – Recent & Ongoing
Studio Theatre
• Abatement and Install of New Flooring
• Theatre Seating Replacement
• Improved Aisle Lighting
• Paint Restoration
![Page 6: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/6.jpg)
Renovations – Recent & Ongoing
• Student Collaboration Space
• New Dean’s Suite
• Music Drama Library Resource Center
• Hours of Operation – Fall Semester
Monday – Thursday: 9am – 8pm
Friday: 9am – 5pmSaturday: ClosedSunday: 1pm – 8pm
School of Fine Arts Atrium
![Page 7: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/7.jpg)
Space Expansion and Program
Relocation – Recent & Ongoing
Bishop Center – First Floor
![Page 8: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/8.jpg)
Space Expansion and Program
Relocation – Recent & Ongoing
Kirby Mills
• Visual Arts Research Center Relocating from Lebanon Cottage
• 15 MFA Studios
![Page 9: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/9.jpg)
Space Expansion and Program
Relocation – Recent & Ongoing
Wadsworth Athenaeum
• Future Home of Arts Administration Program
• Currently in Contract Negotiation
• Construction to Start in the Fall 2018
![Page 10: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/10.jpg)
Fine Arts Phase II -Project Overview
Addition – Production
Facility
Parking lot modifications
Interior “courtyard” between
Katter and Drama/Music
Façade
Replacements
Façade
Replacements
Drama/Music
Building Mechanical
Upgrades (west side)
Utility
Relocations
Corridor linkage to Fine Arts Building
Stairs to main
front vestibule
![Page 11: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/11.jpg)
Fine Arts Phase II - Project ScheduleConstruction Started – June 2018
Site Utilities – Ongoing
May 2018 – December 2018
Addition – Production Facility
October 2018 – December 2019
Drama/Music Façade Renovation
(along Bolton Rd)
Winter Break 2018
Drama/Music Façade Renovation
(along RT 195)
May 2019 – August 2019
Fine Arts Building Roof Replacement
Summer 2019
![Page 12: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/12.jpg)
Fine Arts Phase II - Logistics
![Page 13: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/13.jpg)
Fine Arts Phase II - Logistics Drama/Music (west corridor)
![Page 14: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/14.jpg)
Fine Arts Phase II - LogisticsNafe Katter Theatre
Katter Restricted
to Classroom Use
![Page 15: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/15.jpg)
Fine Arts Phase II –Protection of Existing Conditions
Dust Measures: Filter Media at Air
Intakes
Anti-Tracking Pad
Street Sweeping
Watering Truck
Interior daily sweeping of corridors
Noise Measures:
Jobsite Hours
6:00am to
2:30pm
No Work
during Final
Exam Periods
![Page 16: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/16.jpg)
Fine Arts Phase II -Two Week Look Ahead
![Page 17: School of Fine Arts€¦ · Facility & Capital Project Update Colleen Bridgeman Assistant Dean & COO August 24, 2018. Renovations –Recent & Ongoing • Restoration Improvements](https://reader034.fdocuments.net/reader034/viewer/2022042805/5f68f59aa3aae0505b5be799/html5/thumbnails/17.jpg)
SFA Fine Arts Phase II UConn UPDC’s You Tube Video –
https://www.youtube.com/watch?v=yTq46oBgeRI&t=656s