Schedule Risk Analysis (SRA) Tariq Ashraf Systems Engineering Feb 24, 2005.
-
Upload
caroline-coffey -
Category
Documents
-
view
219 -
download
0
Transcript of Schedule Risk Analysis (SRA) Tariq Ashraf Systems Engineering Feb 24, 2005.
Schedule Risk Schedule Risk Analysis (SRA)Analysis (SRA)
Tariq AshrafTariq Ashraf
Systems EngineeringSystems Engineering
Feb 24, 2005Feb 24, 2005
Why SRA?Why SRA?
Prior to program execution, management needs to Prior to program execution, management needs to know what are the potential schedule road blocks know what are the potential schedule road blocks ahead of him/herahead of him/her– Establish warning indicators up frontEstablish warning indicators up front– Build mitigation into the IMS during planningBuild mitigation into the IMS during planning
Deterministic model fallacy Deterministic model fallacy – Critical path based upon linked activities with Critical path based upon linked activities with
the least amount of float the least amount of float – Assumes all linked activities are low risk – not Assumes all linked activities are low risk – not
true in real lifetrue in real life
ProgramAttention
ProgramAttention
ProgramAttention
Risk Impact on Critical PathRisk Impact on Critical Path
Activity X Potential Critical Path
Probabilistic Model
Activity 1 Activity 2 Activity 3
Activity 4 Activity 5 Activity 6
Activity 7 Activity 8 Activity 9
9-10-12 14-15-17 19-20-22 51
14-15-17 9-10-12 14-15-17 51
9-10-12 9-10-12 19-20-34 58
High RiskActivity
Deterministic Model
Activity 1 Activity 2 Activity 3
Activity 4 Activity 5 Activity 6
Activity 7 Activity 8 Activity 9
10 15 20 45
15 10 15 40
10 10 20 40
Activity X Critical Path
Brief ObjectiveBrief Objective
Describe a structured methodology for conducting Schedule Risk Analysis (SRA)
Schedule Risk Assessment Schedule Risk Assessment MethodologyMethodology
Two step process:Two step process:– Step 1 : Assess and determine the risk level of each Step 1 : Assess and determine the risk level of each
IMS activity to identify activities that are high or IMS activity to identify activities that are high or moderate/medium risk – moderate/medium risk – the most important element of the most important element of SRA SRA
– Step 2 : Determine potential impact of the Step 2 : Determine potential impact of the High/Moderate risk activities on program events using a High/Moderate risk activities on program events using a simulation tool simulation tool
Step 1. How to Determine the Step 1. How to Determine the Risk Level of an Activity?Risk Level of an Activity?
Assess each activity against the Assess each activity against the elements that impact the activityelements that impact the activity– The activity model provides the answerThe activity model provides the answer
Activity ModelActivity Model
ActivityActivityInputInput
Dependency
Input Dependency – One Input Dependency – One PredecessorPredecessor
Ps = 80%Activity 1(Ps = 80%)
Activity 2
Ps = Probability of Success
Input Dependency – Multiple Input Dependency – Multiple Concurrent PredecessorConcurrent Predecessor
The greater the number of concurrent predecessor activities,the lower the Cumulative Probability of Success
Activity 1(Ps = 80%)
Activity 2(Ps = 80%)
Activity 3(Ps = 80%)
Activity 4(Ps = 80%)
Activity 5
Cumulative Ps
80% x 80% x 80% x 80% = 41%
Ps = Probability of Success
Ps = 41%
Activity Model (continued)Activity Model (continued)
ActivityActivityInputInput
Dependency
Source
Timeliness of input is dependent uponcontrol exercised over the input source
Activity Model (continued)Activity Model (continued)
ActivityActivity
Res
ou
rce
Res
ou
rce
InputInput
Dependency
Source
Constraint
Resource ConstraintResource Constraint
There is a loss in resource efficiency when a resourceis applied to multiple concurrent activities
Activity 1
Resource A
Activity 2
Elapsed Time
Setup
Work on Task
Suspend
Non Productive Work
Productive Work
Theory of Constraint
Activity Model (continued)Activity Model (continued)
EnvironmentEnvironment
ActivityActivity
Res
ou
rce
Res
ou
rceP
rocess
Pro
cess
InputInput OutputOutput
Dependency
Source
Constraint
Maturity Complexity
Expectancy
Source
State
So Now What?So Now What?
Develop a likelihood rating matrix for each Develop a likelihood rating matrix for each activity element activity element – Example:Example:
Input DependencyInput Dependency– 1 – No Predecessor1 – No Predecessor– 5 – N Concurrent Predecessors5 – N Concurrent Predecessors
Resource StateResource State– 1 – Existing1 – Existing– 5 – New development using state-of-the art5 – New development using state-of-the art
Likelihood MatrixLikelihood Matrix
Dependency Source Maturity Complexity Constraint Source State
5>7 Concurrent Predecessor Activities
Outs ide Agency New ProcessExtremely Complex
Resource dedicated to more
than two concurrent activities
Outs ide Agency
New resource to be developed
using s tate-of-the art technology
Low Confidence that output will
meet expectation
Fully Dependent (100% of duration)
45-6 Concurrent
Predecessor Activities
CustomerMajor
modification to exis ting Process
Significantly Complex
Resource dedicated to more than two activities
Customer
New resource to be developed using exis ting technology
Insufficient data to make
judgement
Major Dependency (75%
of duration)
33-4 Concurrent
Predecessor Activities
Within Corporation
Moderate modification to exis ting process
Moderately Complex
Resource dedicated to two
concurrent activities
Within Corporation
Major Modification to
exis ting resource
Slight Confidence, based on past
experience, that output will meet
expectation
Moderately (50% of duration) Dependent
21-2 Concurrent
Predecessor Activities
Subcontractor OR Supplier
Minor modification to exis ting process
Minor ComplexityResource
dedicated to two activities
Subcontractor OR Supplier
Minor Modification to
the Resource
Moderate Confidence, with backup data, that out put will meet
expectation
Minor (25% of duration)
Dependency
1 No Predecessor Activity
Within Program Process Exis ts SimpleResource
dedicated to this activity
Within Program Resource Exis ts
High Confidence, with backup data, that out put will meet expectation
Not Dependent
Likelihood FactorsLevel Output
ExpectencyEnvironment Dependency
Input Process Resource
EXAMPLE
So Now What?So Now What?Now that the activity elements have been identified develop a likelihood rating Now that the activity elements have been identified develop a likelihood rating matrix for each activity element matrix for each activity element – Example:Example:
Input DependencyInput Dependency– 1 – No Predecessor1 – No Predecessor– 5 – N Concurrent Predecessors5 – N Concurrent Predecessors
Resource StateResource State– 1 – Existing1 – Existing– 5 – New development using state-of-the art5 – New development using state-of-the art
For each activityFor each activity– Using the likelihood rating matrix, determine the level for each activity element Using the likelihood rating matrix, determine the level for each activity element – Determine the schedule consequence using the criteria provided in the risk planDetermine the schedule consequence using the criteria provided in the risk plan– Determine the activity risk level by mapping highest likelihood level to schedule Determine the activity risk level by mapping highest likelihood level to schedule
consequenceconsequenceEstablish Max-Min durations criteria for high, moderate, low risk activityEstablish Max-Min durations criteria for high, moderate, low risk activity– DurationsDurations– ++ of % of ML of % of ML
The risk level determines the The risk level determines the estimate confidence and estimate confidence and
duration spread (Min-ML-Max) duration spread (Min-ML-Max) of an activity of an activity
High Risk Activity
Min Duration Spread
MaxMost Likely
Confidence Level Low High
Moderate/Medium Risk Activity
Min
Duration Spread
Max
Most Likely
Confidence Level Low High
Low Risk Activity
Low Confidence Level High
Most Likely
Duration Spread
MinMax
Step 2. Determining the Impact of High/Moderate Risk Step 2. Determining the Impact of High/Moderate Risk Activities on Program Event(s)Activities on Program Event(s)
Review the IMS logic for the following:Review the IMS logic for the following:– All activities are linkedAll activities are linked– The logic makes senseThe logic makes sense
Maximize FS relationships. Simulation models do not like other Maximize FS relationships. Simulation models do not like other relationships (SS, SF, FF). Also minimize lags in the activity logic i.e. relationships (SS, SF, FF). Also minimize lags in the activity logic i.e. FS+20, FS-20, etc.FS+20, FS-20, etc.For each activity, input estimates (Minimum , Most Likely, Maximum ) based For each activity, input estimates (Minimum , Most Likely, Maximum ) based upon the risk level of the activity and run simulationsupon the risk level of the activity and run simulationsOut put generated by simulation toolOut put generated by simulation tool– Probability vs. Time curve for each event selected for analysisProbability vs. Time curve for each event selected for analysis– Criticality Index for each task (during the simulation, the number of times an Criticality Index for each task (during the simulation, the number of times an
activity fell on the critical path)activity fell on the critical path)Results from the first simulation may not meet expectationResults from the first simulation may not meet expectationAdjust IMS and reiterateAdjust IMS and reiterate
ConclusionConclusionRisk is inherent in a complex system with multiple Risk is inherent in a complex system with multiple stakeholdersstakeholders
Prior to execution, management must know what Prior to execution, management must know what risks are embedded in the IMSrisks are embedded in the IMS
Applying a structured methodology ensures schedule Applying a structured methodology ensures schedule risk is identified consistently by all stakeholdersrisk is identified consistently by all stakeholders
Analysis is time consuming and requires input from Analysis is time consuming and requires input from all stakeholders but the value cannot be all stakeholders but the value cannot be underestimated underestimated