TUNNEL AND ALLIED WORKS RATES IN THIS FILE ARE LINKED WITH RATES IN BASIC DATA / HIRE CHARGES / LEAD CHARGES FILES TO THE EXTENT THEY ARE RELEVANT. IN THE DIALOG BOX THAT APPEARS ON THE MONITOR SCREEN ON OPENING THIS FILE CLICK ' YES ' AND ' SAVE ' THE FILE. CHANGES MADE IN BASIC DATA / HIRE CHARGES / LEAD CHARGES FILES GET INCORPORATED IN THIS FILE AUTOMATICALLY. ALL DATA IN THIS FILE IS PROTECTED BY PASS WORD. FOR THE YEAR CONTENTS PAGES REFERENCE DATA 1 -- 3 NOTES ON BASIC RATES 4 -- 4 DATA RATES 5 -- 68 GOVERNMENT OF KARNATAKA WATER RESOURCES DEPARTMENT SCHEDULE OF RATES TUNNEL AND ALLIED WORKS 2003-2004 0

Transcript of SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between...

Page 1: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

RATES IN THIS FILE ARE LINKED WITH RATES IN BASIC DATA / HIRE CHARGES / LEAD CHARGES FILES TO THE EXTENT THEY ARE RELEVANT. IN THE DIALOG BOX THAT APPEARS ON THE MONITOR SCREEN ON OPENING THIS FILE CLICK ' YES ' AND ' SAVE ' THE FILE. CHANGES MADE IN BASIC DATA / HIRE CHARGES / LEAD CHARGES FILES GET INCORPORATED IN THIS FILE AUTOMATICALLY. ALL DATA IN THIS FILE IS PROTECTED BY PASS WORD.

FOR THE YEAR :

CONTENTS PAGES

REFERENCE DATA 1 -- 3

NOTES ON BASIC RATES 4 -- 4

DATA RATES 5 -- 68

GOVERNMENT OF KARNATAKA

WATER RESOURCES DEPARTMENT

SCHEDULE OF RATES

TUNNEL AND ALLIED WORKS

2003-2004

0

Page 2: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

PREPARED BY SCHEDULE OF RATES COMMITTEE

JUNE, 2003

1

Page 3: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

FOR THE YEAR :

COST OF MATERIALS:Acetylene gas per cum Rs: 185.00Air hose 25 mm dia per Rm Rs: 120.00Binding wire per kg Rs: 27.00Cement 43 Gr per kg Rs: 2.90Coarse aggregate 10-4.75 mm / cum Rs: 461.00Coarse aggregate 20-10 mm / cum Rs: 358.00Coarse aggregate40-20 mm / cum Rs: 263.00Concrete admixture( Super plasticiser ) per ltr Rs: 55.00Cross bit ( TC ) 75 mm dia per No. Rs: 6200.00Demand charges per KVA / month Rs: 200.00Detonating fuse coil per Rm Rs: 5.00Detonator delay type per No. Rs: 15.00Detonator electric per No. Rs: 8.00Detonator ordinary per No. Rs: 4.50Electric poles with fixtures per No. Rs: 2500.00Energy charges ( HT-2B ) per Kwhr Rs: 4.57Explosive ( small dia ) per kg Rs: 44.00Extension rod with coupling sleeve per Rm Rs: 1000.00Fine aggregate/ sand ( screened ) per cum Rs: 114.00Flood light 500 W per No. Rs: 250.00Flood light set per No. Rs: 1050.00Fluorescent tube 40 W per No. Rs: 47.00Fluorescent tube light set per No. Rs: 195.00G I Pipe 80 mm dia per Rm Rs: 280.00G I Pipe100 mm dia per Rm Rs: 395.00G.I. Bolts and Nuts per kg Rs: 55.00Guniting nozzle per No. Rs: 250.00HT / LT Circuit breaker per No Rs: 25000.00HT / LT Line conductor per km Rs: 19000.00Jungle wood planks per cum Rs: 16000.00Jack hammer drill rod 1.5 m per No. Rs: 2600.00Jack hammer drill rod 2.5 m per No. Rs: 3500.00M S Bolts & Nuts per kg Rs: 45.00Oxygen gas per cum Rs: 40.00Plain G.I. Sheet per t Rs: 32000.00PVC armoured cable 70 sqmm per Rm Rs: 250.00PVC armoured cable 25 sqmm per Rm Rs: 110.00PVC armoured cable 16 sqmm per Rm Rs: 75.00PVC armoured cable 10 sqmm & below per Rm Rs: 25.00Rails 30 kg / m per tonne Rs: 24500.00Reinforcement steel per kg Rs: 18.00Resin bond cement grout capsule per No. Rs: 24.00Rivets per kg Rs: 45.00Shalimastic sealing compound per kg Rs: 53.00Shutter fabrication cost per kg Rs: 8.00Shutter oil per ltr Rs: 15.00Stone chips at dump yard per cum Rs: 100.00Structural steel angle/ channel/ flat per kg Rs: 20.00

2003-2004ITEMS : 1 - 21

TUNNEL AND ALLIED WORKS - REFERENCE DATA

2

Page 4: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Structural steel plate per kg Rs: 24.00Sundries Rs: 22.50Un-coursed rubble stones at dump yard per cum Rs: 85.00Water hose 20 mm dia per Rm Rs: 110.00Welding electrodes per No. Rs: 4.00Wire rope for winch 16 mm dia per Rm Rs: 150.00

ROYALTY CHARGES : Per tonneSand / Fine aggregate 15.00Stone / Coarse aggregate / Chips 10.00

LEAD, LOADING & UNLOADING CHARGES: 1 km lead Loading UnloadingCement Rs: 25.90 27.70 27.70Earth / Sand / Gravel Rs: 24.10 24.80 6.20Steel Rs: 25.90 27.70 27.70Stone / Coarse aggregate Rs: 33.20 29.50 14.75

HIRE CHARGES OF MACHINERY: Hire charge Fuel charge Crew chargesAgitator car truck mounted per hour Rs: 486.00 340.00 52.65Air compressor 15 cmm ( ele ) per hour Rs: 86.00 511.00 34.90Air compressor 8.5 cmm ( ele ) per hour Rs: 87.00 230.00 32.70Bending machine per hour Rs: 31.00 61.00 26.70Batching plant 2 x 1 cum per hour Rs: 236.00 184.00 62.80Concrete placer pump per hour Rs: 102.00 2.00 16.80Convey mucker per hour Rs: 552.00 142.00 34.90DG set 30 KVA Rs: 46.00 248.00 26.20Diesel loco 45 hp per hour Rs: 182.00 209.00 32.90Drilling jumbo per hour Rs: 230.00 17.00 35.10Dumper 5 cum per hour Rs: 352.00 156.00 42.10Grout pump per hour Rs: 16.00 20.00 51.55Guniting equipment per hour Rs: 67.00 5.00 43.00Jack hammer per hour Rs: 11.00 3.00 64.45Pump 10 hp ( ele ) per hour Rs: 4.00 41.00 15.60Pump 20 hp ( ele ) per hour Rs: 9.00 82.00 15.60Pusher leg per hour Rs: 6.00 2.00 ---Tipper 5 cum per hour Rs: 240.00 117.00 32.90Tipping tub 1.5 cum per hour Rs: 24.00 5.00 ---Transformer 250 KVA per month Rs: 1916.00 --- ---Ventilation fan 20 hp per hour Rs: 5.00 82.00 5.35Vibrator ( ele )per hour Rs: 6.00 4.00 30.85Waggon drill Rs: 166.00 5.00 51.55Welding set per hour Rs: 9.00 49.00 ---Winch 35 hp electric per hour Rs: 77.00 100.00 52.65

3

Page 5: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

WAGES OF WORKERS: Per dayBar bender Rs: 94.15Blasting helper Rs: 81.60Carpentor Cl- II Rs: 86.15Electrician Rs: 82.65Fitter shuttering works Rs: 86.15Fitter/ Mechanic Rs: 93.70Foreman Rs: 108.65Helper fitter / erector Rs: 81.60Khalasi Rs: 83.65Licensed Blaster Rs: 84.70Lineman Rs: 81.60Maistry Rs: 81.60Mason Cl-I Rs: 94.15Mason Cl-II Rs: 86.15Mazdoor ( Heavy) Rs: 80.90Mazdoor ( Light ) Rs: 76.40Pipe fitter Rs: 89.20Stone breaker ( Hammerman ) Rs: 83.65Stone chiseller Cl II Rs: 84.20Structural steel marker / erector Rs: 93.70Surveyor Rs: 91.20Tinsmith Rs: 81.65Turner / Driller Rs: 89.70Welder / Gas cutter Rs: 93.70

4

Page 6: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

NOTES ON SCHEDULE OF RATES TUNNEL AND ALLIED WORKS FOR THE YEAR : 2003-2004

1. All notes under General Notes on Schedule of Rates and Notes on Lead, Lift, Loading andun-loading Charges are applicable to Tunnel and Allied Works also to the extent they arerelevant.

2. The basic rates are inclusive of finishing, wastage of materials in handling, incidental works,profit, overheads, small tools / plants, hidden cost on labour etc.

3. The basic rates are inclusive additional costs for working inside tunnel.

4. The basic rates are inclusive of scaling loose material, removal of under-cuts, cleaning bed andlighting and ventilation inside tunnel .

5. The basic rates are inclusive of royalty charges payable on materials.

6. The recovery of royalty charges on materials, wherever applicable, shall be as per the guidelines listed under ' General notes on schedule of rates' and the amount of royalty charges shallbe as per the statement of royalty charges included in this section.

7. Unless otherwise specified the basic rates are inclusive of all lifts.

8. Unless otherwise specified the basic rates are inclusive of standard finish required for concretesurface.

9. For excavation and concrete lining works of approach / exit channels the basic rates asprovided under ' Canal and allied works ' and ' Canal cross drainage works ' shall be adopted.

10. For intake structure, tunnel portals, retaining walls, pitching etc., the rates as provided under 'Dam and allied works ' shall be adopted.

11. The lead charges, wherever applicable, for all materials under various items shall be considered only between quarry/ source of supply and batching plant / fabrication site. Further conveyanceof concrete / fabricated parts / other materials upto final placing site inside tunnel is included inthe basic rates.

12. Cement content specified for cement concrete works in the item description is based on theoritical design mix computations and is exclusive of wastage and requirement for incidentalworks if any. The actual cement content may vary based on trial mix studies. Suitableclause shall be included in the tender for regulating payment for any upword or downwordvariation in cement content.

13. The quantities of materials including wastage, requirements for incidentals etc., for workingout additional lead charges shall be as per the statement of requirement of materials underthis section.

14. The basic rates are exclusive of cost of dewatering. Separate provision shall be made in theestimate for dewatering on Kwhr basis. The total provision for dewatering shall not exceed5 percent of cost of work.

5

Page 7: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

TUNNEL AND ALLIED WORKS- DATA RATES

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 1

ITEM: Excavation for adit by tunnelling methods in all types of rock including cost of all materials,machinery, labour, scaling excavated surface, ventilation, lighting, drainage, removing andhauling the excavated muck outside adit upto specified dump area and all other ancillaryoperations etc., complete with initial lead upto 500 m and all lifts.

DATA:Size of adit assumed ( finished section ) : 4.50 m dia Shape of adit assumed for excavation : D - shapeHeight of adit assumed ( finished section ) : 4.50 m Pay-line margin assumed : 0.20 mDiameter of adit upto pay line for excavation : 4.90 mDistance of dump yard from face : within 500 mHaulage of excavated muck : By dumpers

Pay line

Minimum excavation line

Excavated profile

TYPICAL CROSS SECTION OF ADIT / TUNNEL

1 Checking alignment and marking hole locations :Deploy drilling jumbo for 1 hour for marking hole locations.

2 Drilling holes :Full face method of excavation is assumed.Area of adit upto pay-line ( 0.5 x 0.7857x 4.9 x 4.9 )+( 4.9 x 2.45 ) : 21.43 sqmThe drilling pattern for excavation of tunnel / adit depends on the size and shape of tunnel, rockformation, type of explosive and the fragmentation of rock required to suite the type of mucking equipment. The drilling pattern shall ensure minimum over-break.Generally, the cut holes and easers will be spaced at 65 to 75 cm grid and the trimmers will bespaced at 50 to 60 cm apart along the periphery of excavation area.Considering this, the number of holes for tunnel excavation will be generally in the range of 2.5 to 3 per sqm of cross sectional area for small tunnels and in the range of 2.0 to 2.5 persqm of cross sectional area for large tunnels.For rate analysis 2.5 holes per sqm of cross sectional area considered.

Cut holes

Easers

Trimmers

TYPICAL DRILLING PATTERN FOR ADIT / TUNNEL

6

Page 8: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Number of holes for full face excavation : 54 NosDepth of holes : 2 mExtra drilling considered at 10 percent for inclination cut holes and for any secondary blasting of large fragments during mucking.Depth of drilling for 54 holes ( 54 x 2 x 1.10 ) : 119 mAverage rate of drilling per hour per jack hammer : 6 mDeploy 4 jack hammers with pusher leg for drilling. say : 5 hoursDeploy 1 air compressor 15 cmm for air supply to 4 jack hammers : 5 hoursDeploy drilling jumbo for drilling : 5 hoursDeploy 10 hp pump for water supply to drilling work. : 5 hours

3 Loading explosive and blasting :Depth of pull per blast for 2 m deep holes : 1.80 mQuantity of in-situ excavation per blast ( 21.43 x 1.80 ) : 38.5 cumQuantity of explosive small dia per blast @ 1.00 kg per cum : 38 kgQuantity of explosive for secondary blasting @ 5 % : 2 kgTotal quantity of explosive per blast : 40 kgQuantity of delay detonators per blast : 54 Nos.Quantity of electric detonators for secondary blasting LS : 5 Nos.Fuse coil : 50 RmDeploy drilling jumbo for 1 hour for loading explosives.

4 Defuming and scaling loose materials: No machinery other than ventilation fans are required. For defuming adit ventilation fans are installed in duct system at about 300 m interval and are run for about 1 hour after each blast.Consider 20 hp fan 1 No. for 1 hr.

5 Mucking excavated rock :Quantity of muck to be removed per blast considering 50 % bulkage : 58 cumCapacity of dumper per load : 5.00 cumQuantity of muck per load considered under adit working conditions : 4.50 cumLoading cycle time:Turning / moving and spotting : 1 minutesLoading muck by convey mucker and work force : 20 minutesCycle time of loading dumper per load of 4.50 cum : 21 minutesHaulage cycle time:Running time from loading point to dump yard @ av 10 km / hr : 3.0 minutesTurning and unloading : 2.0 minutesReturn trip to reversing point : 2.0 minutesCycle time for haulage per load of 4.5 cum : 7.0 minutesSince the waiting time will be more than the running time if 2 dumpers are deployed deploy1 dumper for conveying muck.Round trip cycle time of dumper say : 30 minutesQuantity of muck disposal per hour / dumper : 9.00 cumDeploy 1 dumper for conveying muck @ 9 cum per hour : 6.5 hoursDeploy convey mucker and labour force for loading : 6.5 hours

6 Overall cycle time :Checking alignment and marking hole locations : 2.00 hoursDrilling holes : 5.00 hoursLoading explosive and blasting : 2.00 hoursDefuming and scaling loose rock fragments : 2.00 hoursMucking excavated rock : 6.50 hoursBed cleaning, support fixing, rock bolting, lighting etc say : 6.50 hoursTotal cycle of excavation per blast of 1.8 m length : 24.00 hoursDeploy drilling jumbo for total 8 hours including time for movement.

7 Use rate of materials:Cost of drill rod 2.5 m long @ Rs: 3500.00 / No. Rs: 3500.00

7

Page 9: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Life of drill rod with reconditionong : 150 mUse rate of drill rod per Rm drilling ( cost / life ) Rs: 23.33Length of air and water hose assumed : 25 m eachCost of air hose 25 m each @ Rs: 120.00 / Rm Rs: 3000.00Life of air hose : 800 hoursUse rate of air hose per hour ( cost / life ) Rs: 3.75Cost of water hose 25 m each @ Rs: 110.00 / Rm Rs: 2750.00Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 3.44

RATE ANALYSIS UNIT : 38.50 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Small dia explosive kg 40.00 44.00 1760.002 Delay detonators Nos 54.00 15.00 810.003 Electric detonators Nos 5.00 8.00 40.004 Detonating fuse coil Rm 50.00 5.00 250.005 Use rate of drill rod 2.5 m long Rm 119.00 23.33 2776.67

Reconditioning charges @ 10% 277.676 Use rate of air hose Hour 20.00 3.75 75.007 Use rate of water hose Hour 20.00 3.44 68.758 Sundries( paint / template etc ) LS 2.00 22.50 45.00

TOTAL Rs: 6103.08Add for small Tools and Plants @ 1% Rs: 61.03Add for Contractor' Profit @ 10% Rs: 610.31Add for Contrators' Overheads @ 5% Rs: 305.15

Total cost of Materials Rs: 7079.58

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Drilling jumbo Hour 8.00 230.00 1840.00

Fuel / Energy charges Hour 8.00 17.00 136.002 Air compressor 15 cmm ( ele ) Hour 5.00 86.00 430.00

Fuel / Energy charges Hour 5.00 511.00 2555.003 Jack hammer ( 4 x 5 hrs ) Hour 20.00 11.00 220.00

Fuel / Energy charges Hour 20.00 3.00 60.004 Pusher leg Hour 20.00 6.00 120.00

Fuel / Energy charges Hour 20.00 2.00 40.005 Convey mucker Hour 6.50 552.00 3588.00

Fuel / Energy charges Hour 6.50 142.00 923.006 Dumper ( 1 x 6.5 hrs ) Hour 6.50 352.00 2288.00

Fuel / Energy charges Hour 6.50 156.00 1014.007 Pump 10 hp ( ele ) Hour 5.00 4.00 20.00

Fuel / Energy charges Hour 5.00 41.00 205.008 Ventilation fans 20 hp Hour 1.00 5.00 5.00

Fuel / Energy charges Hour 1.00 82.00 82.009 Sundries(explosive van / magazine ) LS 2.00 22.50 45.00

TOTAL Rs: 13571.00Add for small Tools and Plants @ 1% Rs: 135.71Add for Contractor' Profit on DPOL / Energy @ 10% Rs: 506.00Add for Contrators' Overheads @ 5% Rs: 678.55 Total hire charges of Machinery Rs: 14891.26

8

Page 10: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Drilling jumbo Hour 8.00 35.10 280.802 Crew for Air compressor Hour 5.00 34.90 174.503 Crew for Jack hammer Hour 20.00 64.45 1289.004 Crew for Convey mucker Hour 6.50 34.90 226.855 Crew for Dumper Hour 6.50 42.10 273.656 Crew for Pump Hour 5.00 15.60 78.007 Crew for ventilation fans Hour 1.00 5.35 5.358 Surveyor Day 0.50 91.20 45.609 Foreman Day 1.00 108.65 108.65

10 Fitter / Mechanic Day 2.00 93.70 187.4011 Blaster ( Licensed ) Day 1.00 84.70 84.7012 Helper blasting Day 2.00 81.60 163.2013 Hammerman Day 2.00 83.65 167.3014 Maistry 1 in each shift Day 3.00 81.60 244.8015 Khalasi

for mucking shift 4 Nos Day 4.00 83.65 334.6016 Heavy mazdoor

for mucking shift 4 Nos Day 4.00 80.90 323.60for other 2 shifts 1 No each shift Day 2.00 80.90 161.80

17 Light mazdoorfor cleaning & miscellaneous Day 2.00 76.40 152.80

TOTAL Rs: 4302.60Add for small Tools and Plants @ 1% Rs: 43.03Add for Contractor' Profit @ 10% Rs: 430.26Add for hidden cost on Labour @ 15% Rs: 645.39Add for additional hidden cost on labour @ 10% Rs: 430.26Add for Contrators' Overheads @ 5% Rs: 215.13

Total cost of Labour Rs: 6066.67

ABSTRACT:A. Cost of Materials Rs: 7079.58B. Hire charges of Machinery Rs: 14891.26C. Cost of Labour Rs: 6066.67

Total Rs: 28037.50Add for Air and Water line @ 1.00% Rs: 280.38Add for Ventilation @ 4.50% Rs: 1261.69Add for Lighting @ 1.60% Rs: 448.60Add for Ele sub-station / Demand charges @ 5.00% Rs: 1401.88Add for other Enabling works @ 2.00% Rs: 560.75 Total cost for 38.50 cum Rs: 31990.79

Rate per cum Rs: 831.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 2

ITEM: Excavation for vertical / inclined shaft in all types of soft / hard rock including cost of allmaterials, machinery, labour, shoring, strutting, scaling excavated surface, ventilation, lighting,drainage, removing and hauling excavated muck outside shaft upto specified dump area andall other ancillary operations etc., complete with initial lead upto 1 km and all lifts.

DATA:Size of shaft assumed : 5.00 m dia Shape of shaft assumed for excavation : CircularDepth of shaft assumed : 75.00 m

9

Page 11: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Pay-line margin assumed : 0.20 mDiameter of shaft upto pay line for excavation : 5.40 mDistance of dump yard from face : within 500 mAverage lift involved for excavation of shaft upto tunnel level : 40 m

1 Checking alignment and marking hole locations :Deploy winch & cradle for 0.5 hour for marking hole locations.

2 Drilling holes :Area of excavation upto payline ( 0.7857 x 5.4 x 5.4 ) : 22.91 sqmDepth of drilling : 1.50 mDepth of pull : 1.30 mNo. of peripheral holes with 0.75 m spacing ( 20 times dia ) : 20 Nos.No. of holes in shaft area @ 2 per sqm : 40 Nos.Depth of drilling for 60 holes : 90 mExtra drilling considered at 5 percent for secondary blasting of large fragments.Total depth of drilling ( 90 x 1.05 ) : 95 mAverage rate of drilling per hour per jack hammer : 6 mDeploy 4 jack hammers for drilling. : 4 hoursDeploy 1 air compressor 15 cmm for air supply to 4 jack hammers : : 4 hoursDeploy 10 hp pump for pumping water to storage tank. : 4 hoursDeploy 20 hp sludge pump for removing drill water from pit : 2 hourTotal time for drilling including preparation for drilling : 5 hours

3 Loading explosive and blasting :Quantity of in-situ excavation per blast ( 22.91 x 1.30 ) : 30 cumQuantity of explosive small dia per blast @ 1.0 kg per cum : 30 kgQuantity of explosive for secondary blasting @ 5 % : 2 kgTotal quantity of explosive : 32 kgQuantity of electric detonators for blasting : 65 Nos.Detonating fuse coil : 50 Rm

4 Defuming shaft: Generally for shafts defuming is carried out by leaving compressed air by air hose for about0.5 hour to remove blasting gases and dust.Deploy air compressor for 0.5 hour.

5 Mucking excavated rock :Winch and 0.5 cum bottom / side opening bucket are considered for removing the muck from shaft and rail mounted tipping tubs are considered for further haulage and disposal.Quantity of muck to be removed per blast considering 50 % bulkage : 45 cumCycle time for operating mucking bucket by winch :Lowering bucket by winch @ 15 m / minute for av. 40 m : 3.00 minLoading muck by work force : 7.50 minLifting by winch @ 15 m / minute for av. 40 m : 3.00 minUnloading to tipping tub : 1.50 mun

Say : 15.00 minQuantity of muck per mucking bucket : 0.50 cumTime required for mucking 45 cum ( 45 x 15 / 0.50 / 60 ) : 22.5 hoursDeploy winch for 28 hours including time for movement of work force in shifts.Deploy 1 mucking bucket for 24 hours for removing muck from shaft.Deploy 1 tipping tub for 24 hours for disposal of muck outside shaft.

6 Overall cycle time :Marking hole locations and preparation for drilling : 1.50 hoursDrilling holes : 4.00 hoursLoading explosive and blasting : 2.00 hoursDefuming by leaving compressed air : 0.50 hoursMucking excavated rock : 24.00 hoursTotal cycle of excavation per blast of 1.3 m depth : 32.00 hours

7 Use rate of materials:Cost of drill rod 1.6 m long @ Rs: 2600.00 / No. Rs: 2600.00

10

Page 12: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Life of drill rod with reconditioning : 150 mUse rate of drill rod per Rm drilling ( cost / life ) Rs: 17.33Length of air and water hose assumed : 100 m eachCost of air hose 100 m each @ Rs: 120.00 / Rm Rs: 12000.00Life of air hose : 800 hoursUse rate of air hose per hour ( cost / life ) Rs: 15Cost of water hose 100 m each @ Rs: 110.00 / Rm Rs: 11000.00Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 13.75Quantity of rails for haulage of tubs Haulage track outside : 2 x 150 mWeigth of 30R rails 300 m length @ 30 kg / Rm : 9 tonnesCost of 30 R rails 300 m @ Rs: 24500.00 / tonne Rs: 220500.00Add for fixtures @ 25% Rs: 55125.00

Total Rs: 275625.00Less salvage value @ 10% ( - ) -27562.50

Total Rs: 248062.50Life of rails under tunnel working conditions : 15 yearsUse rate of rails per year ( cost / life ) Rs: 16537.50Add for repairs & replacement @ 10% Rs: 1653.75

Total Rs: 18191.25Use rate of rails per shift considering 300 working days Rs: 60.64Consider use of rail track for 24 hours.Length of 16 mm dia wire rope for winch assuming 80 m deep shaft : 150 mCost of wire rope 150 m length @ Rs: 150.00 / Rm Rs: 22500.00Life of wire rope for lifting : 2500 hoursUse rate of wire rope per hour ( cost / life ) Rs: 9.00Weight of mucking bucket : 250 kgCost of steel plates @ 75 % @ Rs: 24.00 / kg Rs: 4500.00Cost of steel angles @ 25 % @ Rs: 20.00 / kg Rs: 1250Cost of fabrication @ Rs: 8.00 / kg Rs: 2000.00

Total Rs: 7750.00Add for hooks / door arrangements etc @ 20% Rs: 1550

Total Rs: 9300.00Less salvage value @ 10% ( - ) -930.00

Total Rs: 8370.00Add for repairs / maintenance etc @ 10% Rs: 837.00

Total Rs: 26877.00Life of mucking bucket assumed : 2500 hoursUse rate of mucking bucket per hour ( cost / life ) Rs: 10.75

RATE ANALYSIS UNIT : 30.00 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Small dia explosive kg 32.00 44.00 1408.002 Electric detonator Nos 65.00 8.00 520.003 Detonating fuse coil Rm 50.00 5.00 250.004 Use rate of drill rod 1.6 m long Rm 95.00 17.33 1646.67

Reconditioning charges @ 10% 164.675 Use rate of air hose Hour 18.00 15.00 270.006 Use rate of water hose Hour 16.00 13.75 220.007 Use rate of rail track Shift 3.00 60.64 181.918 Use rate of mucking bucket Hour 24.00 10.75 258.029 Sundries( paint / template etc ) LS 2.00 22.50 45.00

TOTAL Rs: 4964.27

11

Page 13: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Add for small Tools and Plants @ 1% Rs: 49.64Add for Contractor' Profit @ 10% Rs: 496.43Add for Contrators' Overheads @ 5% Rs: 248.21

Total cost of Materials Rs: 5758.55

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Air compressor 15 cmm ( ele ) Hour 4.50 86.00 387.00

Fuel / Energy charges Hour 4.50 511.00 2299.502 Jack hammer ( 4 x 4 hrs ) Hour 16.00 11.00 176.00

Fuel / Energy charges Hour 16.00 3.00 48.003 Pump 10 hp ( ele ) Hour 4.00 4.00 16.00

Fuel / Energy charges Hour 4.00 41.00 164.004 Pump 20 hp electric Hour 2.00 9.00 18.00

Fuel / Energy charges Hour 2.00 82.00 164.005 Winch 35 hp electric Hour 28.00 77.00 2156.00

Fuel / Energy charges Hour 28.00 100.00 2800.006 Tipping tub 1.5 cum Hour 24.00 24.00 576.00

Fuel / Energy charges Hour 24.00 5.00 120.007 Sundries(explosive van / magazine ) LS 2.00 22.50 45.00

TOTAL Rs: 8969.50Add for small Tools and Plants @ 1% Rs: 89.70Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 564.05Add for Contrators' Overheads @ 5% Rs: 448.48 Total hire charges of Machinery Rs: 10071.72

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Air compressor Hour 4.50 34.90 157.052 Crew for Jack hammer Hour 16.00 64.45 1031.203 Crew for Pump 10 hp Hour 4.00 15.60 62.404 Crew for Pump 20 hp Hour 2.00 15.60 31.205 Crew for Winch Hour 28.00 52.65 1474.206 Surveyor Day 0.50 91.20 45.607 Foreman Day 4.00 108.65 434.608 Fitter / Mechanic Day 2.00 93.70 187.409 Blaster ( Licensed ) Day 1.00 84.70 84.70

10 Helper blasting Day 2.00 81.60 163.2011 Hammerman 1 No. in each shift Day 3.00 83.65 250.9512 Maistry 1 in each shift Day 4.00 81.60 326.4013 Khalasi

for mucking 2 Nos in each shift Day 6.00 83.65 501.9014 Heavy mazdoor

for mucking 8 Nos in each shift Day 24.00 80.90 1941.60for other 2 shifts 1 No / shift Day 2.00 80.90 161.80

15 Light mazdoorfor cleaning & miscellaneous Day 2.00 76.40 152.80

TOTAL Rs: 7007.00Add for small Tools and Plants @ 1% Rs: 70.07Add for Contractor' Profit @ 10% Rs: 700.70Add for hidden cost on Labour @ 15% Rs: 1051.05

12

Page 14: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Add for additional hidden cost on labour @ 10% Rs: 700.70Add for Contrators' Overheads @ 5% Rs: 350.35

Total cost of Labour Rs: 9879.87

ABSTRACT:A. Cost of Materials Rs: 5758.55B. Hire charges of Machinery Rs: 10071.72C. Cost of Labour Rs: 9879.87

Total Rs: 25710.14Add for Air and Water line @ 1.00% Rs: 257.10Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 411.36Add for Ele sub-station / Demand charges @ 5.00% Rs: 1285.51Add for other Enabling works @ 2.00% Rs: 514.20 Total cost for 30.00 cum Rs: 28178.31

Rate per cum Rs: 939.50

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 3

ITEM: Excavation for tunnel by tunnelling methods in rock not requiring supports including cost of all materials,machinery, labour, scaling excavated surface, removing under-cuts, ventilation,lighting, drainage, removing and hauling the excavated muck outside tunnel upto specifieddump area and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts.

DATA:Size of tunnel assumed ( finished section ) : 4.50 m dia Shape of tunnel assumed for excavation : D - shapeHeight of tunnel assumed ( finished section ) : 4.50 m Length of tunnel assumed : 1000 mThickness of CC lining : 0.30 mPay-line margin assumed : 0.20 mDiameter of tunnel upto pay line for excavation : 5.50 mDistance of dump yard from face : within 500 mHaulage of excavated muck : By dumpers

Pay line Concrete lining

Minimum excavation line

Excavated profile Finished tunnel line

TYPICAL CROSS SECTION OF TUNNEL 4.50 m dia.

1 Checking alignment and marking hole locations :Deploy drilling jumbo for 1 hour for marking hole locations.

2 Drilling holes :Area of tunnel upto pay-line ( 0.5 x 0.7857x 5.5 x 5.5 )+( 5.5 x 2.75 ) : 27.00 sqmThe number of holes for tunnel excavation will be generally in the range of 2.5 to 3.0 per sqmof cross sectional area for tunnel upto 45 sqm and in the range of 2.0 to 2.5 per sqm of crosssectional area for tunnel exceeding 45 sqm.For rate analysis 2.5 holes per sqm of cross sectional area considered.

13

Page 15: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Number of holes for full face excavation : 68 NosDepth of holes : 2 mExtra drilling considered at 10 percent for inclination of holes and for removal of any under cutsand for secondary blasting of large fragments during mucking.Depth of drilling for 68 holes ( 68 x 2 x 1.10 ) : 150 mAverage rate of drilling per hour per jack hammer : 6 mDeploy 4 jack hammers with pusher leg for drilling. say : 6.5 hoursDeploy 1 air compressor 15 cmm for air supply to 4 jack hammers : : 6.5 hoursDeploy drilling jumbo for drilling : 6.5 hoursDeploy 10 hp pump for water supply to drilling work. : 6.5 hours

3 Loading explosive and blasting :Depth of pull per blast for 2 m deep holes : 1.80 mQuantity of in-situ excavation per blast ( 27.00 x 1.80 ) : 49 cumQuantity of explosive small dia per blast @ 1.00 kg per cum : 49 kgQuantity of explosive for under cuts secondary blasting @ 10 % : : 5 kgTotal quantity of explosive per blast : 54 kgQuantity of delay detonators per blast : 68 Nos.Quantity of electric detonators for secondary blasting LS : 10 Nos.Detonating fuse coil LS : 50 RmDeploy drilling jumbo for 1 hour for loading explosives.

4 Defuming and scaling loose materials: No machinery other than ventilation fans required. For defuming tunnel ventilation fans areinstalled in duct system at about 300 m interval and are run for about 1 hour after each blast.This is equivalent to running 1 fan for 2 hrs. Consider 1 fan 20 hp for 2 hrs.

5 Mucking excavated rock :Quantity of muck to be removed per blast considering 50 % bulkage : 73 cumCapacity of dumper per load : 5.00 cumQuantity of muck per load considered under tunnel working conditions : 4.50 cumLoading cycle time:Moving from turning pocket position and spotting : 1 minutesLoading muck by convey mucker and work force : 20 minutesTime for loaded dumper to pass waiting point say : 1 minutesCycle time of loading dumper per load of 4.50 cum : 22 minutesHaulage cycle time:Running time from loading point to dump yard at av. 12 km / hr : : 5 minutesTurning and unloading : 2 minutesReturn trip to waiting point : 5 minutesWaiting time before spotting : 9 minutesCycle time for haulage per load of 4.5 cum : 21 minutesRound trip cycle time of dumper say : 45 minutesQuantity of muck disposal per hour / dumper : 6.00 cumDeploy 2 dumpers for conveying muck @ 12 cum per hour : : 6 hoursDeploy convey mucker and labour force for loading : 6 hours

6 Overall cycle time :Checking alignment and marking hole locations : 2.00 hoursDrilling holes : 6.50 hoursLoading explosive and blasting : 2.00 hoursDefuming and scaling loose rock fragments : 2.00 hoursMucking excavated rock : 6.00 hoursBed cleaning, support fixing, rock bolting, lighting etc say : 5.50 hoursTotal cycle of excavation per blast of 1.8 m length : 24.00 hoursDeploy drilling jumbo for total 10 hours including time for movement.

7 Use rate of materials:Cost of drill rod 2.5 m long @ Rs: 3500.00 / No. Rs: 3500.00Life of drill rod with reconditioning : 150 m

14

Page 16: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Use rate of drill rod per Rm drilling ( cost / life ) Rs: 23.33Length of air and water hose assumed : 25 m eachCost of air hose 25 m each @ Rs: 120.00 / Rm Rs: 3000.00Life of air hose : 800 hoursUse rate of air hose per hour ( cost / life ) Rs: 3.75Cost of water hose 25 m each @ Rs: 110.00 / Rm Rs: 2750.00Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 3.44

RATE ANALYSIS UNIT : 48.60 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Small dia explosive kg 54.00 44.00 2376.002 Delay detonators Nos 68.00 15.00 1020.003 Electric detonators Nos 10.00 8.00 80.004 Detonating fuse coil Rm 50.00 5.00 250.005 Use rate of drill rod 2.5 m long Rm 150.00 23.33 3500.00

Reconditioning charges @ 10% 350.006 Use rate of air hose Hour 24.00 3.75 90.007 Use rate of water hose Hour 24.00 3.44 82.508 Sundries( paint / template etc ) LS 2.00 22.50 45.00

TOTAL Rs: 7793.50Add for small Tools and Plants @ 1% Rs: 77.94Add for Contractor' Profit @ 10% Rs: 779.35Add for Contrators' Overheads @ 5% Rs: 389.68

Total cost of Materials Rs: 9040.46

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Drilling jumbo Hour 10.00 230.00 2300.00

Fuel / Energy charges Hour 10.00 17.00 170.002 Air compressor 15 cmm ( ele ) Hour 6.50 86.00 559.00

Fuel / Energy charges Hour 6.50 511.00 3321.503 Jack hammer ( 4 x 6.5 hrs ) Hour 26.00 11.00 286.00

Fuel / Energy charges Hour 26.00 3.00 78.004 Pusher leg Hour 26.00 6.00 156.00

Fuel / Energy charges Hour 26.00 2.00 52.005 Convey mucker Hour 6.00 552.00 3312.00

Fuel / Energy charges Hour 6.00 142.00 852.006 Dumper ( 2 x 6 hrs ) Hour 12.00 352.00 4224.00

Fuel / Energy charges Hour 12.00 156.00 1872.007 Pump 10 hp ( ele ) Hour 6.50 4.00 26.00

Fuel / Energy charges Hour 6.50 41.00 266.508 Ventilation fans 20 hp Hour 2.00 5.00 10.00

Fuel / Energy charges Hour 2.00 82.00 164.009 Sundries(explosive van / magazine ) LS 2.00 22.50 45.00

TOTAL Rs: 17694.00Add for small Tools and Plants @ 1% Rs: 176.94Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 682.10Add for Contrators' Overheads @ 5% Rs: 884.70 Total hire charges of Machinery Rs: 19437.74

15

Page 17: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Drilling jumbo Hour 10.00 35.10 351.002 Crew for Air compressor Hour 6.50 34.90 226.853 Crew for Jack hammer Hour 26.00 64.45 1675.704 Crew for Convey mucker Hour 6.00 34.90 209.405 Crew for Dumper Hour 12.00 42.10 505.206 Crew for Pump Hour 6.50 15.60 101.407 Crew for ventilation fans Hour 2.00 5.35 10.708 Surveyor Day 0.50 91.20 45.609 Foreman Day 1.00 108.65 108.65

10 Fitter / Mechanic Day 2.00 93.70 187.4011 Blaster ( Licensed ) Day 1.00 84.70 84.7012 Helper blasting Day 2.00 81.60 163.2013 Hammerman Day 2.00 83.65 167.3014 Maistry 1 in each shift Day 3.00 81.60 244.8015 Khalasi

for mucking shift 4 Nos Day 4.00 83.65 334.6016 Heavy mazdoor

for mucking shift 8 Nos Day 8.00 80.90 647.20for other 2 shifts 1 No each shift Day 2.00 80.90 161.80

17 Light mazdoorfor cleaning & miscellaneous Day 2.00 76.40 152.80

TOTAL Rs: 5378.30Add for small Tools and Plants @ 1% Rs: 53.78Add for Contractor' Profit @ 10% Rs: 537.83Add for hidden cost on Labour @ 15% Rs: 806.75Add for additional hidden cost on labour @ 10% Rs: 537.83Add for Contrators' Overheads @ 5% Rs: 268.92

Total cost of Labour Rs: 7583.40

ABSTRACT:A. Cost of Materials Rs: 9040.46B. Hire charges of Machinery Rs: 19437.74C. Cost of Labour Rs: 7583.40

Total Rs: 36061.60Add for Air and Water line @ 1.00% Rs: 360.62Add for Ventilation @ 4.50% Rs: 1622.77Add for Lighting @ 1.60% Rs: 576.99Add for Ele sub-station / Demand charges @ 5.00% Rs: 1803.08Add for other Enabling works @ 2.00% Rs: 721.23 Total cost for 48.60 cum Rs: 41146.29

Rate per cum Rs: 847.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 4

ITEM: Excavation for tunnel by tunnelling methods including excavation for supports in all types ofsoil / rock strata requiring supports ( excluding cost of providing supports ) including cost ofall other materials, machinery, labour, scaling excavated surface, ventilation, lighting, drainage, removing and hauling the excavated muck outside tunnel upto specified dump area and allother ancillary operations etc., complete with initial lead upto 1 km and all lifts.

DATA:Size of tunnel assumed ( finished section ) : 4.50 m dia Shape of tunnel assumed for excavation : D - shape

16

Page 18: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Height of tunnel assumed ( finished section ) : 4.50 m Length of tunnel assumed : 1000 mThickness of CC lining : 0.30 mExtra excavation for supports : 0.25 mPay-line margin assumed : 0.20 mDiameter of tunnel upto pay line for excavation : 6.00 mDistance of dump yard from face : within 500 mHaulage of excavated muck : By dumpers

1 Checking alignment and marking hole locations :Deploy drilling jumbo for 1 hour for marking hole locations.

2 Drilling holes :Area of tunnel upto pay-line ( 0.5 x 0.7857x 6 x 6 )+( 6 x 2.75 ) : : 30.64 sqmThe number of holes for tunnel excavation will be generally in the range of 2.5 to 3.0 per sqm of cross sectional area for tunnel upto 45 sqm and in the range of 2.0 to 2.5 per sqm of cross sectional area for tunnel exceeding 45 sqm.For rate analysis 2.5 holes per sqm of cross sectional area considered.Number of holes for full face excavation : 77 NosAssuming spacing of supports at 0.75 m the depth of pull is considered at 1.5 m.Depth of holes for 1.5 m pull : 1.7 mExtra drilling considered at 10 percent for inclination of holes and for removal of any under cutsand for secondary blasting of large fragments during mucking.Depth of drilling for 77 holes ( 77 x 1.7 x 1.10 ) : 144 mAverage rate of drilling per hour per jack hammer : 6 mDeploy 4 jack hammers with pusher leg for drilling. : 6 hoursDeploy 1 air compressor 15 cmm for air supply to 4 jack hammers : : 6 hoursDeploy drilling jumbo for drilling : 6 hoursDeploy 10 hp pump for pumping water to storage tank. : 6 hours

3 Loading explosive and blasting :Depth of pull per blast for 1.7 m deep holes : 1.50 mQuantity of in-situ excavation per blast ( 30.64 x 1.50 ) : 46 cumQuantity of explosive small dia per blast @ 0.8 kg per cum : 37 kgQuantity of explosive for secondary blasting @ 10 % : 4 kgTotal quantity of explosive : 41 kgQuantity of delay detonators per blast : 77 Nos.Quantity of electric detonators for secondary blasting LS : 10 Nos.Detonating fuse coil : 50 RmDeploy drilling jumbo for 1 hour for loading explosives.

4 Defuming and scaling loose materials No machinery other than ventilation fans required. For defuming tunnel ventilation fans areinstalled in duct system at about 300 m interval and are run for about 1 hour after each blast.This is equivalent to running 1 fan for 2 hrs. Consider 1 fan 20 hp for 2 hrs.

5 Mucking excavated rock :Quantity of muck to be removed per blast considering 50 % bulkage : 69 cumCapacity of dumper per load : 5 cumQuantity of muck per load considered under tunnel working conditions : 4.5 cumLoading cycle time:Moving from pocket position and spotting : 1 minutesLoading muck by convey mucker and work force : 20 minutesTime for loaded dumper to pass waiting point say : 1 minutesCycle time of loading dumper per load of 4.5 cum : 22 minutesHaulage cycle time:Running time from loading point to dump yard at av. 12 km / hr : : 5 minutesTurning and unloading : 2 minutesReturn trip to waiting point : 5 minutesWaiting time before spotting : 9 minutes

17

Page 19: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Cycle time for haulage per load of 4.5 cum : 21 minutesRound trip cycle time of dumper say : 45 minutesQuantity of muck disposal per hour / dumper : 6 cumDeploy 2 dumpers for conveying muck @ 12 cum per hour : : 6 hoursDeploy convey mucker and labour force for loading : 6 hours

6 Overall cycle time :Checking alignment and marking hole locations : 2.00 hoursDrilling holes : 6.00 hoursLoading explosive and blasting : 2.00 hoursDefuming and scaling loose rock fragments : 2.00 hoursMucking excavated rock : 6.00 hoursBed cleaning, Jumbo movements, rock bolting, lighting etc say : 4.00 hoursErection of temperary / permanent supports : 10.00 hoursTotal cycle of excavation & supporting /blast of 1.5 m length : 32.00 hoursDeploy drilling jumbo for 11 hours for various operations including time for movement.

7 Use rate of materials:Cost of drill rod 2.5 m long @ Rs: 3500.00 / No. Rs: 3500.00Life of drill rod with reconditioning : 150 mUse rate of drill rod per Rm drilling ( cost / life ) Rs: 23.33Length of air and water hose assumed : 25 m eachCost of air hose 25 m each @ Rs: 120.00 / Rm Rs: 3000.00Life of air hose : 800 hoursUse rate of air hose per hour ( cost / life ) Rs: 3.75Cost of water hose 25 m each @ Rs: 110.00 / Rm Rs: 2750.00Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 3.44

RATE ANALYSIS UNIT : 46.00 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Small dia explosive kg 41.00 44.00 1804.002 Delay detonators Nos 77.00 15.00 1155.003 Electric detonators Nos 10.00 8.00 80.004 Detonating fuse coil Rm 50.00 5.00 250.005 Use rate of drill rod 2.5 m long Rm 144.00 23.33 3360.00

Reconditioning charges @ 10% 336.006 Use rate of air hose Hour 24.00 3.75 90.007 Use rate of water hose Hour 24.00 3.44 82.508 Sundries( paint / template etc ) LS 2.00 22.50 45.00

TOTAL Rs: 7202.50Add for small Tools and Plants @ 1% Rs: 72.03Add for Contractor' Profit @ 10% Rs: 720.25Add for Contrators' Overheads @ 5% Rs: 360.13

Total cost of Materials Rs: 8354.90

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Drilling jumbo Hour 11.00 230.00 2530.00

Fuel / Energy charges Hour 11.00 17.00 187.002 Air compressor 15 cmm ( ele ) Hour 6.00 86.00 516.00

Fuel / Energy charges Hour 6.00 511.00 3066.003 Jack hammer ( 4 x 6 hrs ) Hour 24.00 11.00 264.00

Fuel / Energy charges Hour 24.00 3.00 72.00

18

Page 20: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

4 Pusher leg Hour 24.00 6.00 144.00Fuel / Energy charges Hour 24.00 2.00 48.00

5 Convey mucker Hour 6.00 552.00 3312.00Fuel / Energy charges Hour 6.00 142.00 852.00

6 Dumper ( 2 x 6 hrs ) Hour 12.00 352.00 4224.00Fuel / Energy charges Hour 12.00 156.00 1872.00

7 Pump 10 hp ( ele ) Hour 6.00 4.00 24.00Fuel / Energy charges Hour 6.00 41.00 246.00

8 Ventilation fans 20 hp Hour 2.00 5.00 10.00Fuel / Energy charges Hour 2.00 82.00 164.00

9 Sundries(explosive van / magazine ) LS 2.00 22.50 45.00TOTAL Rs: 17576.00

Add for small Tools and Plants @ 1% Rs: 175.76Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 655.20Add for Contrators' Overheads @ 5% Rs: 878.80 Total hire charges of Machinery Rs: 19285.76

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Drilling jumbo Hour 11.00 35.10 386.102 Crew for Air compressor Hour 6.00 34.90 209.403 Crew for Jack hammer Hour 24.00 64.45 1546.804 Crew for Convey mucker Hour 6.00 34.90 209.405 Crew for Dumper Hour 12.00 42.10 505.206 Crew for Pump Hour 6.00 15.60 93.607 Crew for ventilation fans Hour 2.00 5.35 10.708 Surveyor Day 0.50 91.20 45.609 Foreman Day 1.00 108.65 108.65

10 Fitter / Mechanic Day 2.00 93.70 187.4011 Blaster ( Licensed ) Day 1.00 84.70 84.7012 Helper blasting Day 2.00 81.60 163.2013 Hammerman 2 Nos Day 2.00 83.65 167.3014 Maistry 1 in each shift Day 3.00 81.60 244.8015 Khalasi

for mucking shift 4 Nos Day 4.00 83.65 334.6016 Heavy mazdoor

for mucking shift 8 Nos Day 8.00 80.90 647.20for other 2 shifts 1 No each shift Day 2.00 80.90 161.80

17 Light mazdoorfor cleaning & miscellaneous Day 2.00 76.40 152.80

TOTAL Rs: 5259.25Add for small Tools and Plants @ 1% Rs: 52.59Add for Contractor' Profit @ 10% Rs: 525.93Add for hidden cost on Labour @ 15% Rs: 788.89Add for additional hidden cost on labour @ 10% Rs: 525.93Add for Contrators' Overheads @ 5% Rs: 262.96

Total cost of Labour Rs: 7415.54

ABSTRACT:A. Cost of Materials Rs: 8354.90B. Hire charges of Machinery Rs: 19285.76C. Cost of Labour Rs: 7415.54

Total Rs: 35056.20

19

Page 21: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Add for Air and Water line @ 1.00% Rs: 350.56Add for Ventilation @ 4.50% Rs: 1577.53Add for Lighting @ 1.60% Rs: 560.90Add for Ele sub-station / Demand charges @ 5.00% Rs: 1752.81Add for other Enabling works @ 2.00% Rs: 701.12 Total cost for 46.00 cum Rs: 39999.13

Rate per cum Rs: 870.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 5

ITEM: Excavation for tunnel by heading and benching tunnelling methods including excavation for supports in all types of soil / rock strata requiring supports ( excluding cost of providingsupports ) for roof before benching including cost of all other materials, machinery, labour,scaling excavated surface, ventilation, lighting, drainage removing and hauling excavated muckoutside tunnel upto specified dump area and all other ancillary operations etc., complete withinitial lead upto 1 km and all lifts.

DATA:Size of tunnel assumed ( finished section ) : 4.50 m dia Shape of tunnel assumed for excavation : D - shapeHeight of tunnel assumed ( finished section ) : 4.50 m Length of tunnel assumed : 1000 mThickness of CC lining : 0.30 mExtra excavation for supports : 0.25 mPay-line margin assumed : 0.20 mDiameter of tunnel upto pay line for excavation : 6.00 mDistance of dump yard from face : within 500 mHaulage of excavated muck : By dumpers

1 Checking alignment and marking hole locations :Deploy drilling jumbo for 1 hour for marking hole locations.

2 Drilling holes :In case of tunnel where the height is more or where the chances of over excavation due to fullface blasting is more the excavation will be generally carried out by heading and benchingmethod. For week strata arch rib supports are to be erected before benching.Assuming spacing of arch supports at 0.75 m interval the effective depth of pull per blast isconsidered at 1.5 m. The depth of hole for 1.5 m pull is considered at 1.7 m.Extra drilling considered at 10 percent for inclination of holes and for removal of any undercuts and for secondary blasting of large fragments during mucking.

Pay lineHeading portion

Excavated profileMinimum Drill holes Benching portionexcavationline

TYPICAL CROSS SECTION OF TUNNEL FOR HEADING & BENCHINGHeading portion :Area of excavation upto payline : 14.14 sqmDepth of pull : 1.50 mNo. of holes considering 2.5 holes / sqm : 35 Nos.Depth of drilling for 35 holes ( 35 x 1.7 x 1.1 ) : 65.5 m

20

Page 22: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Haunch portion on either side :Area of excavation upto payline : 2.60 sqmDepth of drilling : 1.70 mNo. of holes considering 3 holes / sqm : 8 NosDepth of drilling for 8 holes ( 8 x 1.7 x 1.1 ) : 15 mBenching portion :Area of excavation upto payline ( 6 x 2.75 ) : 16.50 sqmNo. of holes considering 2.5 holes / sqm : 41 Nos.Depth of drilling : 1.70 mDepth of drilling for 41 holes ( 41 x 1.7 x 1.1 ) : 76.5 mTotal depth of drilling ( 65.5 + 15 + 76.5 ) : 157 mAverage rate of drilling per hour per jack hammer : 6 mDeploy 4 jack hammers with pusher leg for drilling. : 6.5 hoursDeploy 1 air compressor 15 cmm for air supply to 4 jack hammers : : 6.5 hoursDeploy drilling jumbo for drilling : 6.5 hoursDeploy 10 hp pump for pumping water to storage tank. : 6.5 hours

3 Loading explosive and blasting :Total area of excavation : 33.24 sqmDepth of pull per blast for 1.7 m deep holes : 1.50 mQuantity of in-situ excavation per blast ( 33.24 x 1.50 ) : 50 cumQuantity of explosive small dia per blast @ 0.8 kg per cum : 40 kgQuantity of explosive for secondary blasting @ 10 % : 4 kgTotal quantity of explosive : 44 kgQuantity of delay detonators per blast ( 35 + 8 + 41 ) : 84 Nos.Quantity of electric detonators for secondary blasting LS : 10 Nos.Detonating fuse coil : 50 RmDeploy drilling jumbo for loading explosives. ( 1 + 0.5 + 0.5 ) : 2 hours

4 Defuming and scaling loose materials No machinery other than ventilation fans required. For defuming tunnel ventilation fans areinstalled in duct system at about 300 m interval and are run for about 1 hour after each blast.This is equivalent to running 1 fan for 2 hrs. However, since excavation is planned in stages1 hour defuming after each of 3 blasts is considered adequate.

5 Mucking excavated rock :Quantity of muck to be removed per blast considering 50 % bulkage : 75 cumCapacityof dumper per load : 5 cumQuantity of muck per load considered under tunnel working conditions : 4.5 cumLoading cycle time:Moving from pocket position and spotting : 1 minutesLoading muck by convey mucker and work force : 20 minutesTime for loaded dumper to pass waiting point say : 1 minutesCycle time of loading dumper per load of 4.5 cum : 22 minutesHaulage cycle time:Running time from loading point to dump yard at av. 12 km / hr : : 5 minutesTurning and unloading : 2 minutesReturn trip to waiting point : 5 minutesWaiting time before spotting : 9 minutesCycle time for haulage per load of 4.5 cum : 21 minutesRound trip cycle time of dumper say : 45 minutesQuantity of muck disposal per hour / dumper : 6 cumDeploy 2 dumpers for conveying muck @ 12 cum per hour : 6.5 hoursDeploy convey mucker and labour force for loading : 6.5 hours

6 Overall cycle time :Checking alignment and marking hole locations : 2.00 hoursDrilling holes : 6.50 hoursLoading explosive and blasting : 2.50 hours

21

Page 23: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Defuming and scaling loose rock fragments : 3.00 hoursMucking excavated rock : 6.50 hoursBed cleaning, Jumbo movements, rock bolting, lighting etc say : 4.00 hoursErection of permanent supports : 7.50 hoursTotal cycle of excavation & supporting /blast of 1.5 m length : 32.00 hours

7 Use rate of materials:Cost of drill rod 2.5 m long @ Rs: 3500.00 / No. Rs: 3500.00Life of drill rod with reconditioning : 150 mUse rate of drill rod per Rm drilling ( cost / life ) Rs: 23.33Length of air and water hose assumed : 25 m eachCost of air hose 25 m each @ Rs: 120.00 / Rm Rs: 3000.00Life of air hose : 800 hoursUse rate of air hose per hour ( cost / life ) Rs: 3.75Cost of water hose 25 m each @ Rs: 110.00 / Rm Rs: 2750.00Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 3.44

RATE ANALYSIS UNIT : 50.00 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Small dia explosive kg 44.00 44.00 1936.002 Delay detonators Nos 84.00 15.00 1260.003 Electric detonator Nos 10.00 8.00 80.004 Detonating fuse coil Rm 50.00 5.00 250.005 Use rate of drill rod 2.5 m long Rm 157.00 23.33 3663.33

Reconditioning charges @ 10% 366.336 Use rate of air hose Hour 26.00 3.75 97.507 Use rate of water hose Hour 26.00 3.44 89.388 Sundries( paint / template etc ) LS 2.00 22.50 45.00

TOTAL Rs: 7787.54Add for small Tools and Plants @ 1% Rs: 77.88Add for Contractor' Profit @ 10% Rs: 778.75Add for Contrators' Overheads @ 5% Rs: 389.38

Total cost of Materials Rs: 9033.55

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Drilling jumbo Hour 12.00 230.00 2760.00

Fuel / Energy charges Hour 12.00 17.00 204.002 Air compressor 15 cmm ( ele ) Hour 6.50 86.00 559.00

Fuel / Energy charges Hour 6.50 511.00 3321.503 Jack hammer ( 4 x 6.5 hrs ) Hour 26.00 11.00 286.00

Fuel / Energy charges Hour 26.00 3.00 78.004 Pusher leg Hour 26.00 6.00 156.00

Fuel / Energy charges Hour 26.00 2.00 52.005 Convey mucker Hour 6.50 552.00 3588.00

Fuel / Energy charges Hour 6.50 142.00 923.006 Dumper ( 2 x 6.5 hrs ) Hour 13.00 352.00 4576.00

Fuel / Energy charges Hour 13.00 156.00 2028.007 Pump 10 hp ( ele ) Hour 6.50 4.00 26.00

Fuel / Energy charges Hour 6.50 41.00 266.50

22

Page 24: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

8 Ventilation fans 20 hp Hour 3.00 5.00 15.00Fuel / Energy charges Hour 3.00 82.00 246.00

9 Sundries(explosive van / magazine ) LS 2.00 22.50 45.00TOTAL Rs: 19130.00

Add for small Tools and Plants @ 1% Rs: 191.30Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 716.40Add for Contrators' Overheads @ 5% Rs: 956.50 Total hire charges of Machinery Rs: 20994.20

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Drilling jumbo Hour 12.00 35.10 421.202 Crew for Air compressor Hour 6.50 34.90 226.853 Crew for Jack hammer Hour 26.00 64.45 1675.704 Crew for Convey mucker Hour 6.50 34.90 226.855 Crew for Dumper Hour 13.00 42.10 547.306 Crew for Pump Hour 6.50 15.60 101.407 Crew for Ventilation fan Hour 3.00 5.35 16.058 Surveyor Day 0.50 91.20 45.609 Foreman Day 1.00 108.65 108.65

10 Fitter / Mechanic Day 2.00 93.70 187.4011 Blaster ( Licensed ) Day 2.00 84.70 169.4012 Helper blasting Day 4.00 81.60 326.4013 Hammerman 2 Nos Day 2.00 83.65 167.3014 Maistry 1 in each shift Day 3.00 81.60 244.8015 Khalasi

for pushing muck in heading portion Day 4.00 83.65 334.60for mucking shift 4 Nos Day 4.00 83.65 334.60

16 Heavy mazdoorfor mucking shift 8 Nos Day 8.00 80.90 647.20for other 2 shifts 1 No each shift Day 2.00 80.90 161.80

17 Light mazdoorfor cleaning &miscellaneous Day 2.00 76.40 152.80

TOTAL Rs: 6095.90Add for small Tools and Plants @ 1% Rs: 60.96Add for Contractor' Profit @ 10% Rs: 609.59Add for hidden cost on Labour @ 15% Rs: 914.39Add for additional hidden cost on labour @ 10% Rs: 609.59Add for Contrators' Overheads @ 5% Rs: 304.80

Total cost of Labour Rs: 8595.22

ABSTRACT:A. Cost of Materials Rs: 9033.55B. Hire charges of Machinery Rs: 20994.20C. Cost of Labour Rs: 8595.22

Total Rs: 38622.97Add for Air and Water line @ 1.00% Rs: 386.23Add for Ventilation @ 4.50% Rs: 1738.03Add for Lighting @ 1.60% Rs: 617.97Add for Ele sub-station / Demand charges @ 5.00% Rs: 1931.15Add for other Enabling works @ 2.00% Rs: 772.46 Total cost for 50.00 cum Rs: 44068.81

Rate per cum Rs: 881.00

23

Page 25: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

NOTE:Where mucking is to be carried out through shaft using winch and mucking tub systemincrease the basic rates for items 3, 4 & 5 by 8 percent.

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 6

ITEM: Removing and hauling muck overfallen due to natural causes such as geological faults etc., out of tunnel including breaking large fragments by blasting if necessary and disposing off the same in specified dump area or as directed including cost of all materials, machinery, labour, ventilation, drainage, lighting and all other ancillary operations etc., complete withinitial lead upto 1 km and all lifts.

DATA:Quantity of overfallen muck considered for analysis : 100 cumLength of tunnel assumed : 1000 mDistance of dump yard from face : 500 mHaulage of excavated muck : By dumperQuantity of overfallen muck requiring blasting assumed @ 20 % : : 20 cumDepth of drilling @ 0.75 m per cum : 15 mDeploy 15 cmm air compressor for 1 hour.Deploy 4 Jack hammers for 1 hour.Cost of drill rod 1.6 m length @ Rs: 2600.00 / No. Rs: 2600.00Life of drill rod with reconditioning : 150 mUse rate of drill rod per Rm drilling ( cost / life ) Rs: 17.33Length of air and water hose assumed : 25 m eachCost of air hose 25 m each @ Rs: 120.00 / Rm Rs: 3000.00Life of air hose : 800 hoursUse rate of air hose per hour ( cost / life ) Rs: 3.75Cost of water hose 25 m each @ Rs: 110.00 / Rm Rs: 2750.00Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 3.44Quantity of explosive @ 0.40 kg / cum : 8 kgQuantity of electric detonators assuming 0.5 m holes : 30 NosQuantity of detonating fuse coil : 20 RmDeploy convey mucker for loading @ 16 cum / hour : 6 hoursDeploy 5 cum dumpers 2 Nos @ 8 cum / hour each : 6 hours

RATE ANALYSIS UNIT : 100.00 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Use rate of drill rod Rm 15.00 17.33 260.00

Reconditioning charges @ 10% 26.002 Explosive small dia. kg 8.00 44.00 352.003 Detonator ( ele ) Nos. 30.00 8.00 240.004 Detonating fuse coil Rm 20.00 5.00 100.005 Use rate of air hose Hour 4.00 3.75 15.006 Use rate of water hose Hour 4.00 3.44 13.757 Sundries LS 1.00 22.50 22.50

TOTAL Rs: 1029.25Add for small Tools and Plants @ 1% Rs: 10.29Add for Contractor' Profit @ 10% Rs: 102.93Add for Contrators' Overheads @ 5% Rs: 51.46

Total cost of Materials Rs: 1193.93

24

Page 26: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Air compressor 15 cmm ( ele ) Hour 1.00 86.00 86.00

Fuel / Energy charges Hour 1.00 511.00 511.002 Jack hammer Hour 4.00 11.00 44.00

Fuel / Energy charges Hour 4.00 3.00 12.003 Pump 10 hp ( ele ) Hour 1.00 4.00 4.00

Fuel / Energy charges Hour 1.00 41.00 41.004 Convey mucker Hour 6.00 552.00 3312.00

Fuel / Energy charges Hour 6.00 142.00 852.005 Dumper 4.5 cum Hour 12.00 352.00 4224.00

Fuel / Energy charges Hour 12.00 156.00 1872.006 Sundries LS 1.00 22.50 22.50

TOTAL Rs: 10980.50Add for small Tools and Plants @ 1% Rs: 109.81Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 331.05Add for Contrators' Overheads @ 5% Rs: 549.03 Total hire charges of Machinery Rs: 11970.38

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Air compressor Hour 1.00 34.90 34.902 Crew for Jack hammer Hour 4.00 64.45 257.803 Crew for Pump Hour 1.00 15.60 15.604 Crew for Convey mucker Hour 6.00 34.90 209.405 Crew for Dumper Hour 12.00 42.10 505.206 Blaster ( Licensed ) Day 0.50 84.70 42.357 Helper blasting Day 0.50 81.60 40.808 Heavy mazdoor Day 4.00 80.90 323.609 Light mazdoor Day 4.00 76.40 305.60

TOTAL Rs: 1735.25Add for small Tools and Plants @ 1% Rs: 17.35Add for Contractor' Profit @ 10% Rs: 173.53Add for hidden cost on Labour @ 15% Rs: 260.29Add for additional hidden cost on labour @ 10% Rs: 173.53Add for Contrators' Overheads @ 5% Rs: 86.76

Total cost of Labour Rs: 2446.70

ABSTRACT:A. Cost of Materials Rs: 1193.93B. Hire charges of Machinery Rs: 11970.38C. Cost of Labour Rs: 2446.70

Total Rs: 15611.01Add for Air and Water line @ 1.00% Rs: 156.11Add for Ventilation @ 4.50% Rs: 702.50Add for Lighting @ 1.60% Rs: 249.78Add for Ele sub-station / Demand charges @ 5.00% Rs: 780.55Add for other enabling works @ 2.00% Rs: 312.22 Total cost for 100.00 cum Rs: 17812.17

Rate per cum Rs: 178.00

25

Page 27: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 7

ITEM: Dewatering tunnel by pumping out water collected by natural drainage inside tunnel includingproviding sump wherever necessary, cost of all materials, machinery, labour, drainage, lighting,ventilation and all other ancillary operations etc., complete.

DATA:Consider 20 hp electric pump installed near junction of adit / channel with tunnel.100 mm dia B Class G.I. Delivery pipe 250 m length.Daily average 8 hours pumping.Energy consumption per hour running of pump ( 20 x 0.746 ) : 14.92 kwhrMiscellaneous such as indicator lamps etc : 00.08 kwhr

Total / hour : 15.00 kwhrUse rate of delivery pipe:Cost of 100 mm dia pipe 250 m @ Rs: 395.00 / Rm Rs: 98750.00Add for fixtures @ 5% Rs: 4937.50

Total Rs: 103687.50Less salvage value @ 10% Rs: -10368.75

Total Rs: 93318.75Life of G.I. pipe : 20000 hrsUse rate of delivery pipe per hour: ( cost / life ) Rs: 4.67

RATE ANALYSIS UNIT : 15.00 KwhrA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Use rate of G.I.pipe 100 mm dia Hour 1.00 4.67 4.672 Sundries LS 0.10 22.50 2.25

TOTAL Rs: 6.92Add for small Tools and Plants @ 1% Rs: 0.07Add for Contractor' Profit @ 10% Rs: 0.69Add for Contrators' Overheads @ 5% Rs: 0.35

Total cost of Materials Rs: 8.02

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Electric pump 20 hp Hour 1.00 9.00 9.002 Fuel / Energy charges Hour 1.00 82.00 82.003 Sundries(Starter/Switches ete) LS 0.10 22.50 2.25

TOTAL Rs: 93.25Add for small Tools and Plants @ 1% Rs: 0.93Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 8.43Add for Contrators' Overheads @ 5% Rs: 4.66 Total hire charges of Machinery Rs: 107.27

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew charges for Pump Hour 1.00 15.60 15.602 Laying & dismantling pipe LS 0.05 22.50 1.133 Heavy mazdoor Day 0.10 80.90 8.09

TOTAL Rs: 24.82Add for small Tools and Plants @ 1% Rs: 0.25Add for Contractor' Profit @ 10% Rs: 2.48

26

Page 28: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Add for hidden cost on Labour @ 15% Rs: 3.72Add for additional hidden cost on labour @ 10% Rs: 2.48Add for Contrators' Overheads @ 5% Rs: 1.24

Total cost of Labour Rs: 34.99

ABSTRACT:A. Cost of Materials Rs: 8.02B. Hire charges of Machinery Rs: 107.27C. Cost of Labour Rs: 34.99

Total Rs: 150.28Add for Air and Water line @ 1.00% Rs: 1.50Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 2.40Add for Ele sub-station / Demand charges @ 5.00% Rs: 7.51Add for other Enabling works @ 2.00% Rs: 3.01 Total cost for 15.00 Kwhr Rs: 164.71

Rate per Kwhr Rs: 11.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 8

ITEM: Providing 25 mm thick guniting to sides and arch of tunnel in cement mortar 1 : 3 proportion by weight including cost of all materials, machinery, labour, ventilation, lighting, drainageand all other ancillary operations etc., complete with lead upto 1 km and all lifts.

DATA:Thickness of guniting : 25 mmMortar mix proportion by weight : 1 : 3Water to cement ratio by weight : '0.35Unit weight of mortar 1 : 3 proportion by weight in kg / cum : '2300Cement per cum of mortar : 530 kgSand per cum of mortar : 0.96 cumDuring guniting a portion of the mortar mix is wasted due to rebounding of mainly sand particles. The extend of rebound varies from 20 to 25 percent. In view of very rich mix the extent of rebound is considered at 20 percent for analysis.For 25 mm thick guniting the rate of progress will be 4 to 5 sqm per hour.For analysis rate of progress is considered at 4.5 sqm per hour.For shift of 8 hours the progress will be 36 sqm.Quantity of mortar for 36 sqm with 20 % rebound ( 36 x 1.2 x 0.025 ) : 1.08 cumAdd for filling crevices / joints in exposed rock etc @ 5% 0.05 cumTotal quantity of mortar for 36 sqm 1.13 cumQuantity of cement with 1 % wastage for 36 sqm : 605 kgQuantity of sand with 2 % wastage for 36 sqm : 1.11 cumDeploy Guniting equipment with accessories for 8 hours.Deploy 8.5 cmm air compressor for 8 hours.Deploy Drilling jumbo for 4 hours during guniting of arch portion.Deploy 10 hp pump for 1 hour for pumping water to storage tank for mixing and curing.Use rate of materials :Cost of grout hose 25 m @ Rs: 120.00 / m Rs: 3000.00Life of grout hose : 800 hoursUse rate of grout hose per hour ( cost / life ) Rs: 3.75Cost of water hose 25 m @ Rs: 110.00 / m Rs: 2750.00Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 3.44Cost of guniting nozzle @ Rs: 250.00 / m Rs: 250.00Life of guniting nozzle : 200 hoursUse rate of guniting nozzle per hour ( cost / life ) Rs: 1.25

27

Page 29: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

RATE ANALYSIS UNIT : 36.00 sqmA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Cement icluding wastage kg 605.00 2.90 1754.502 Sand ( screened ) cum 1.11 114.00 126.543 Use rate of grout hose 20 m Hour 8.00 3.75 30.004 Use rate of water hose 20 m Hour 8.00 3.44 27.505 Use rate of guniting nozzle Hour 8.00 1.25 10.006 Sundries LS 2.00 22.50 45.00

TOTAL Rs: 1993.54Add for small Tools and Plants @ 1% Rs: 19.94Add for Contractor' Profit @ 10% Rs: 199.35Add for Contrators' Overheads @ 5% Rs: 99.68Add for royalty charges on sand ( Included in material cost ) Rs: 0.00

Total cost of Materials Rs: 2312.51

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Guniting equipment Hour 8.00 67.00 536.00

Fuel / Energy charges Hour 8.00 5.00 40.002 Air compressor 8.5 cmm ( ele ) Hour 8.00 87.00 696.00

Fuel / Energy charges Hour 8.00 230.00 1840.003 Pump 10 hp ( ele ) Hour 1.00 4.00 4.00

Fuel / Energy charges Hour 1.00 41.00 41.004 Drilling jumbo Hour 4.00 230.00 920.00

Fuel / Energy charges Hour 4.00 17.00 68.005 Sundries LS 2.00 22.50 45.00

TOTAL Rs: 4190.00Add for small Tools and Plants @ 1% Rs: 41.90Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 203.40Add for Contrators' Overheads @ 5% Rs: 209.50 Total hire charges of Machinery Rs: 4644.80

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Guniting equipment Hour 8.00 43.00 344.002 Crew for Air compressor Hour 8.00 32.70 261.603 Crew for pump Hour 1.00 15.60 15.604 Crew for Drilling jumbo Hour 4.00 35.10 140.405 Mason Cl I Day 1.00 94.15 94.156 Heavy mazdoor Day 4.00 80.90 323.607 Light mazdoor Day 2.00 76.40 152.80

TOTAL Rs: 1332.15Add for small Tools and Plants @ 1% Rs: 13.32Add for Contractor' Profit @ 10% Rs: 133.22Add for hidden cost on Labour @ 15% Rs: 199.82Add for additional hidden cost on labour @ 10% Rs: 133.22Add for Contrators' Overheads @ 5% Rs: 66.61

Total cost of Labour Rs: 1878.33

28

Page 30: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

ABSTRACT:A. Cost of Materials Rs: 2312.51B. Hire charges of Machinery Rs: 4644.80C. Cost of Labour Rs: 1878.33

TOTAL Rs: 8835.64Add for Air and Water line @ 1.00% Rs: 88.36Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 141.37Add for Ele sub-station / Demand charges @ 5.00% Rs: 441.78Add for other enabling works @ 2.00% Rs: 176.71

TOTAL Rs: 9683.86Add for 1 km rehandling charges :For cement 605 kg @ Rs: 81.30 / tonne Rs: 49.19For sand 1.11 cum @ Rs: 55.10 / cum Rs: 61.16 Total cost for 36.00 sqm Rs: 9794.21

Rate per sqm Rs: 272.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 9

ITEM: Providing and fixing 25 mm diameter steel rock bolts with mechanical / wedge type anchorage including drilling 35 mm dia holes, providing 15 cm long 20 mm thick steel taperedwedge, 10 mm thick plate washers and nuts, tightening bolt by torque wrench, cost of allmaterials, machinery, labour, ventilation, lighting, drainage and all other ancillary operationsetc., complete with lead upto 1 km and all lifts.

DATA:Diameter of ribbed steel rock bolt : 25 mmLength of rock bolt including threaded portion : 2.15 mPlate washers 200 x 200 x 10 mm thick : 2 Nos.Wedge 25 mm wide 20 mm thick at one end 150 mm long : 1 No.M S Nuts for bolts : 2 Nos.Diameter of hole for fixing rock bolt : 35 mmDepth of hole for fixing rock bolt : 2.00 mConside 10 bolts for analysis:Length of rock bolt excluding threaded portion : 20.00 mQuantity of 25 mm dia bars for 10 bolts with 2.5 % wastage ( 10 x 2.15 x 3.85 x 1.025 ) : 85 kgQuantity of washer for 10 bolts with 2.5 % wastage ( 10 x 2 x 0.2 x 0.2 x 78.5 x 1.025 ) : 64 kgQuantity of steel for wedge for 10 bolts with 2.5 % wastage ( 10 x 0.15 x 0.025 x 157 x 1.025 ) : 6 kgQuantity of nuts for 10 bolts ( 10 x 2 x 0.2 ) : 4 kgQuantity of drilling for 10 bolts : 20 mRate of drilling for rock bolts including shifting : 4 m / hrDeploy 1 Air compressor 15 cmm for 1.5 hours with 50 minutes per hour working.Deploy 4 Jack hammers / Stooper drills for 1.5 hours with 50 minutes per hour working.Deploy Drilling jumbo for 4 hours including fixing bolts.Deploy 10 hp pump for 1 hour for pumping water to storage tank.Use rate of materials :Cost of drill rod 2.5 m long @ Rs: 3500.00 / No. Rs: 3500.00Life of drill rod with reconditioning : 150 mUse rate of drill rod per m drilling ( cost / life ) Rs: 23.33Cost of air hose 25 m / jack hammer @ Rs: 120.00 / m Rs: 3000.00Life of air hose : 800 hoursUse rate of air hose per hour ( cost / life ) Rs: 3.75

29

Page 31: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Cost of water hose 25 m/ jack hammer @ Rs: 110.00 / m Rs: 2750.00Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 3.44Requirement of labour other tham crew:Gas cutter for preparing washers and wedges : 1 No.Blacksmith for slitting rods and tapering wedges : 1 No.Turner for threading bolts : 1 No.Hammerman : 0.5 No.Fitter for fixing bolts : 0.5 No.Khalasis for handling 2 Nos for 0.5 day : 1 No.Heavy mazdoor for assisting in cutting / fabrication / fixing : 2 No.

RATE ANALYSIS UNIT : 20.00 RmA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Rein.Steel with 2.5 % wastage kg 85.00 18.00 1530.002 Steel plate for washers kg 64.00 24.00 1536.00

Steel plate for wedges kg 6.00 24.00 144.003 M S Nuts for bolts kg 4.00 45.00 180.004 Use rate of drill rod Rm 20.00 23.33 466.67

Reconditioning charges @ 10% 46.675 Use rate of air hose 4 Nos Hour 6.00 3.75 22.506 Use rate of water hose 4 Nos Hour 6.00 3.44 20.637 Sundries ( gas for cutting / heating etc ) LS 5.00 22.50 112.50

TOTAL Rs: 4058.96Add for small Tools and Plants @ 1% Rs: 40.59Add for Contractor' Profit @ 10% Rs: 405.90Add for Contrators' Overheads @ 5% Rs: 202.95

Total cost of Materials Rs: 4708.39

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Air compressor 15 cmm ( ele ) Hour 1.50 86.00 129.00

Fuel / Energy charges Hour 1.50 511.00 766.502 Pump 10 hp ( ele ) Hour 1.00 4.00 4.00

Fuel / Energy charges Hour 1.00 41.00 41.003 Jack hammer Hour 6.00 11.00 66.00

Fuel / Energy charges Hour 6.00 3.00 18.004 Pusher leg Hour 6.00 6.00 36.00

Fuel / Energy charges Hour 6.00 2.00 12.005 Drilling jumbo Hour 4.00 230.00 920.00

Fuel / Energy charges Hour 4.00 17.00 68.006 Sundries ( lathe, blower etc ) LS 5.00 22.50 112.50

TOTAL Rs: 2173.00Add for small Tools and Plants @ 1% Rs: 21.73Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 101.80Add for Contrators' Overheads @ 5% Rs: 108.65 Total hire charges of Machinery Rs: 2405.18

30

Page 32: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Air compressor Hour 1.50 34.90 52.352 Crew for pump Hour 1.00 15.60 15.603 Crew for Jack hammer Hour 6.00 64.45 386.704 Crew for Drilling jumbo Hour 4.00 35.10 140.405 Fitter Day 0.50 93.70 46.856 Gas cutter Day 1.00 93.70 93.707 Turner Day 1.00 93.70 93.708 Blacksmith Day 1.00 81.65 81.659 Khalasi ( 2 x 0.5 ) Day 1.00 83.65 83.65

10 Hammerman Day 0.50 83.65 41.8311 Heavy mazdoor Day 2.00 80.90 161.80

TOTAL Rs: 1198.23Add for small Tools and Plants @ 1% Rs: 11.98Add for Contractor' Profit @ 10% Rs: 119.82Add for hidden cost on Labour @ 15% Rs: 179.73Add for additional hidden cost on labour @ 10% Rs: 119.82Add for Contrators' Overheads @ 5% Rs: 59.91

Total cost of Labour Rs: 1689.50

ABSTRACT:A. Cost of Materials Rs: 4708.39B. Hire charges of Machinery Rs: 2405.18C. Cost of Labour Rs: 1689.50

TOTAL Rs: 8803.07Add for Air and Water line @ 1.00% Rs: 88.03Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 140.85Add for Ele sub-station / Demand charges @ 5.00% Rs: 440.15Add for other enabling works @ 2.00% Rs: 176.06

TOTAL Rs: 9648.16Add for 1 km rehandling charges :For steel 155 kg @ Rs: 81.30 / tonne Rs: 12.60 Total cost for 20.00 Rm Rs: 9660.77

Rate per Rm Rs: 483.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 10

ITEM: Providing and fixing 25 mm diameter steel rock bolts with resin bond cement capsuleanchorage including drilling 35 mm dia holes, inserting grout capsule, driving bolt,fixing 10 mm thick plate washers and nuts and tightening the same by torque wrench after hardening ofcement grout, cost of all materials, machinery, labour, ventilation, lighting, drainage and otherancillary operations etc., complete with lead upto 1 km and all lifts.

DATA:Diameter of ribbed steel rock bolt : 25 mmLength of rock bolt including threaded portion : 2.15 mPlate washers 200 x 200 x 10 mm thick : 2 Nos.Resin bond cement grout capsule : 2 Nos.M S Nuts for bolts : 2 Nos.Diameter of hole for fixing rock bolt : 35 mmDepth of hole for fixing rock bolt : 2.00 mConside 10 bolts for analysis:

31

Page 33: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Length of rock bolt excluding threaded portion : 20.00 mQuantity of 25 mm dia bars for 10 bolts with 2.5 % wastage ( 10 x 2.15 x 3.85 x 1.025 ) : 85 kgQuantity of washer for 10 bolts with 2.5 % wastage ( 10 x 2 x 0.2 x 0.2 x 78.5 x 1.025 ) : 64 kgQuantity of nuts for 10 bolts ( 10 x 2 x 0.2 ) : 4 kgQuantity of drilling for 10 bolts : 20 mRate of drilling for rock bolts including shifting : 4 m / hrDeploy 1 Air compressor 15 cmm for 1.5 hours with 50 minutes per hour working.Deploy 4 Jack hammers / Stooper drills for 1.5 hours with 50 minutes per hour working.Deploy Drilling jumbo for 4 hours including fixing bolts.Deploy 10 hp pump for 1 hour for pumping water to storage tank.Use rate of materials :Cost of drill rod 2.5 m long @ Rs: 3500.00 / No. Rs: 3500.00Life of drill rod with reconditioning : 150 mUse rate of drill rod per m drilling ( cost / life ) Rs: 23.33Cost of air hose 25 m / jack hammer @ Rs: 120.00 / m Rs: 3000.00Life of air hose : 800 hoursUse rate of air hose per hour ( cost / life ) Rs: 3.75Cost of water hose 25 m/ jack hammer @ Rs: 110.00 / m Rs: 2750.00Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 3.44Requirement of labour other tham crew:Gas cutter for preparing washers : 1 No.Turner for threading bolts : 1 No.Hammerman : 0.5 No.Fitter for fixing bolts : 0.5 No.Khalasis for handling 2 Nos for 0.5 day : 1 No.Heavy mazdoor for assisting in cutting / fabrication / fixing : 2 No.

RATE ANALYSIS UNIT : 20.00 RmA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Rein.Steel with 2.5 % wastage kg 85.00 18.00 1530.002 Steel plate for washers kg 64.00 24.00 1536.003 Resin bond cement grout capsule Nos. 2.00 24.00 48.004 M S Nuts for bolts kg 4.00 45.00 180.005 Use rate of drill rod Rm 20.00 23.33 466.67

Reconditioning charges @ 10% 46.676 Use rate of air hose 4 Nos Hour 6.00 3.75 22.507 Use rate of water hose 4 Nos Hour 6.00 3.44 20.638 Sundries(gas for cutting etc) LS 3.00 22.50 67.50

TOTAL Rs: 3917.96Add for small Tools and Plants @ 1% Rs: 39.18Add for Contractor' Profit @ 10% Rs: 391.80Add for Contrators' Overheads @ 5% Rs: 195.90

Total cost of Materials Rs: 4544.83

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Air compressor 15 cmm ( ele ) Hour 1.50 86.00 129.00

Fuel / Energy charges Hour 1.50 511.00 766.50

32

Page 34: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

2 Pump 10 hp ( ele ) Hour 1.00 4.00 4.00Fuel / Energy charges Hour 1.00 41.00 41.00

3 Jack hammer Hour 6.00 11.00 66.00Fuel / Energy charges Hour 6.00 3.00 18.00

4 Pusher leg Hour 6.00 6.00 36.00Fuel / Energy charges Hour 6.00 2.00 12.00

5 Drilling jumbo Hour 4.00 230.00 920.00Fuel / Energy charges Hour 4.00 17.00 68.00

6 Sundries ( lathe, etc ) LS 3.00 22.50 67.50TOTAL Rs: 2128.00

Add for small Tools and Plants @ 1% Rs: 21.28Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 97.30Add for Contrators' Overheads @ 5% Rs: 106.40 Total hire charges of Machinery Rs: 2352.98

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Air compressor Hour 1.50 34.90 52.352 Crew for pump Hour 1.00 15.60 15.603 Crew for Jack hammer Hour 6.00 64.45 386.704 Crew for Drilling jumbo Hour 4.00 35.10 140.405 Fitter Day 0.50 93.70 46.856 Gas cutter Day 1.00 93.70 93.707 Turner Day 1.00 93.70 93.708 Khalasi ( 2 x 0.5 ) Day 1.00 83.65 83.659 Hammerman Day 0.50 83.65 41.83

10 Heavy mazdoor Day 2.00 80.90 161.80TOTAL Rs: 1116.58

Add for small Tools and Plants @ 1% Rs: 11.17Add for Contractor' Profit @ 10% Rs: 111.66Add for hidden cost on Labour @ 15% Rs: 167.49Add for additional hidden cost on labour @ 10% Rs: 111.66Add for Contrators' Overheads @ 5% Rs: 55.83

Total cost of Labour Rs: 1574.37

ABSTRACT:A. Cost of Materials Rs: 4544.83B. Hire charges of Machinery Rs: 2352.98C. Cost of Labour Rs: 1574.37

TOTAL Rs: 8472.18Add for Air and Water line @ 1.00% Rs: 84.72Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 135.55Add for Ele sub-station / Demand charges @ 5.00% Rs: 423.61Add for other enabling works @ 2.00% Rs: 169.44

TOTAL Rs: 9285.51Add for 1 km rehandling charges :For steel 150 kg @ Rs: 81.30 / tonne Rs: 12.20 Total cost for 20.00 Rm Rs: 9297.71

Rate per Rm Rs: 465.00

33

Page 35: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 11

ITEM: Providing, fabricating and fixing in position permanent structural steel supports as per details including cost of all materials, machinery, labour, cutting, bending, welding, grinding, lighting,ventilation, drainage and all other ancillary operations etc., complete with initial lead upto1 km and all lifts.

DATA:Clear diameter of tunnel : 4.50 mAssuming 30 cm thick concrete lining and about 25 cm extra excavation for fixing permanentstructural steel supports and further 20 cm pay line margin the over all width of tunnel for excavation will be 6.00 m.Permanent steel supports are generally provided in the form of quarter / half / full rib dependingon the condition of rock and mode of excavation and size of sections. For the purpose of rateanalysis quarter arch rib fabrication is considered.

Arch rib

Rib joint

Tie rod

Vertical support

TYPICAL SKETCH SHOWING TUNNEL SUPPORTS

Generally, the depth of rib will be considered at 25 mm per metre width of tunnel and thespacing of ribs depends on the condition of strata to be supported. Average spacing of 5 timesthe depth of rib ( generally 2 ribs per blast ) is considered for analysis.For 6 m wide tunnel the depth of rib required will be 150 mm.Further, to provide adiquate bearing for lagging sectoins wide flanged structural steel beams areused for tunnel supporting ribs.Consider ISWB 150 x 100 sections @ 0.75 m c / c.Consider 10 mm plate for fabrication of end plates.Consider 25 mm dia bars for anchorage and tie rods with washers and nuts @ 1 m c/c.Arch ribs 4 Nos of 2.25 m length each @ 17 kg / m : 153.00 kgVertical ribs 2 Nos of 2.75 m length each @ 17 kg / m : 94.00 kgEnd plates 12 Nos 0.2 x 0.2 m each @ 78.5 kg / sqm : 38.00 kgTie rods 14 Nos 25 mm dia 0.9 m length @ 3.85 kg / m : 49.00 kgBolts / Nuts / Washers for connections : 15.00 kgTotal weight / set of support excluding wastage say : 350.00 kgFor 1 tonne of permanent supports requirement of materials is considered as under includingwastage in cutting and fabrication at 3 percent.ISWB 150 sections for ribs : 760 kg10 mm thick plates for end connections : 115 kg25 mm dia bars for anchors and tie rods : 150 kgBolts / Nuts / Washers for fitting : 50 kgNo.of welding electrodes for 8 m welding / support @ 5 / Rm. : 125 Nos.Oxygen gas for cutting sections : 2.4 cumAcetylene gas for cutting sections : 0.8 cumDeploy bending machine for 8 hours for bending arch ribs.Deploy welding machine for 16 hours for welding end plates.Assuming requirement of 2 supports per blast length of 1.5 m and considering 4 hours time for

34

Page 36: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

erection of each support, the time required for erection of 1.00 tonne steel supports will be ( 1000 x 4 / 350 ) say : 11.5 hoursDeploy drilling jumbo for 12 hours for erection of 1 tonne supports.

RATE ANALYSIS UNIT : 1.00 tonneA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Structural steel beams kg 760.00 20.00 15200.002 Structural steel plates kg 115.00 24.00 2760.003 Steel bars for tie rods & anchors kg 150.00 18.00 2700.004 For cutting sections:

Oxygen gas @ 2.4 cum / t cum 2.40 40.00 96.00Acetylene gas @ 0.8 cum / t cum 0.80 185.00 148.00

5 For welding sections:Electrodes 4 x 300 mm @ 125 Nos / t Nos. 125.00 4.00 500.00

6 For field connections:M.S.Bolts / Nuts & Washers kg 50.00 45.00 2250.00

7 Sundries LS 5.00 22.50 112.50TOTAL Rs: 23766.50

Add for small Tools and Plants @ 1% Rs: 237.67Add for Contractor' Profit @ 10% Rs: 2376.65Add for Contrators' Overheads @ 5% Rs: 1188.33

Total cost of Materials Rs: 27569.14

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Bending machine Hour 8.00 31.00 248.00

Fuel / Energy charges Hour 8.00 61.00 488.002 Welding set Hour 16.00 9.00 144.00

Fuel / Energy charges Hour 16.00 49.00 784.003 Drilling Jumbo Hour 12.00 230.00 2760.00

Fuel / Energy charges Hour 12.00 17.00 204.004 Sundries ( lathe / drilling / grinder ) LS 30.00 22.50 675.00

TOTAL Rs: 5303.00Add for small Tools and Plants @ 1% Rs: 53.03Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 215.10Add for Contrators' Overheads @ 5% Rs: 265.15 Total hire charges of Machinery Rs: 5836.28

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Drilling Jumbo Hour 12.00 35.10 421.202 Crew fir Bending machine Hour 8.00 26.70 213.603 For cutting & preparing sections:

Structural steel Marker Day 1.00 93.70 93.70Gas cutter Day 2.00 93.70 187.40Fitter Day 2.00 93.70 187.40Turner / Driller Day 3.00 89.70 269.10Khalasi Day 2.00 83.65 167.30Helper fabrication Day 4.00 81.60 326.40

4 For welding sections:Welder Day 2.00 93.70 187.40

35

Page 37: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Helper fabrication Day 2.00 81.60 163.20Khalasi Day 2.00 83.65 167.30

5 For erection of supports:Foreman Day 1.00 108.65 108.65Structural steel Erector Day 2.00 93.70 187.40Helper erector Day 2.00 81.60 163.20Khalasi Day 4.00 83.65 334.60

TOTAL Rs: 3177.85Add for small Tools and Plants @ 1% Rs: 31.78Add for Contractor' Profit @ 10% Rs: 317.79Add for hidden cost on Labour @ 15% Rs: 476.68Add for additional hidden cost on labour @ 10% Rs: 317.79Add for Contrators' Overheads @ 5% Rs: 158.89

Total cost of Labour Rs: 4480.77

ABSTRACT:A. Cost of Materials Rs: 27569.14B. Hire charges of Machinery Rs: 5836.28C. Cost of Labour Rs: 4480.77

Total Rs: 37886.19Add for Air and Water line @ 1.00% Rs: 378.86Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 606.18Add for Ele sub-station / Demand charges @ 5.00% Rs: 1894.31Add for other enabling works @ 2.00% Rs: 757.72

TOTAL Rs: 41523.26Add for 1 km rehandling charges :For steel 1000 kg @ Rs: 81.30 / tonne Rs: 81.30 Total cost for 1.00 tonne Rs: 41604.56

Rate per tonne Rs: 41600.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 12

ITEM: Providing, fabricating and fixing in position temperary structural steel supports as per detailsand dismantling the same before concreting including cost of all materials, machinery, labour,cutting, bending, welding, grinding, ventilation, lighting, drainage and all other ancillaryoperations etc.,complete with initial lead upto 1 km and all lifts.

DATA:As the temperary supports are dismantled before concreting and reused else where the cost ofmaterials including fabrication will be per use of supports.As per the data under Item-11 consider 1 tonne suppots for analysis. Consider 20 uses for support materials.Requirement of materials for supports per tonne : Same as in item- 11Structural beams : 760 kgStructural plates : 115 kgTie rods and anchors : 150 kgMS bolts / nuts / washers : 50 kgOxygen gas per tonne fabrication : 2.40 cum Acetylene gas per tonne fabrication : 0.80 cumWelding electrodes per tonne fabrication : 125 NumbersRequirement of machinery for supports per tonne : Same as in item- 11 except drilling jumbo.For 20 uses of supports the drilling jumbo will be used for 18 hours each time.Bending machine : 8 hoursWelding set : 8 hoursDrilling jumbo ( for each use 12 hours for erection and 6 hours for dismantling ) : 18 hours

36

Page 38: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Requirement of labour for supports per tonne : Same as in item- 11 except for erection and dismantling of supports. For erection and dismantling the requirement of labour will be for eachuse of supports.Labour charges for dismantling : @ 50 percent of labour charges for erection.Rehandling charges for 1 km are considered both at erection and dismantling stages.

RATE ANALYSIS UNIT : 1.00 tonneA. MATERIALS ( for 20 uses ) : Sl No Perticulars Unit Quantity Rate/ use Amount

in Rs. in Rs.1 Structural steel beams kg 760.00 20.00 15200.002 Structural steel plates kg 115.00 24.00 2760.003 Tie rods & anchors kg 150.00 18.00 2700.004 For cutting sections:

Oxygen gas @ 2.40 cum / t cum 2.40 40.00 96.00Acetylene @ 0.8 cum / t cum 0.80 185.00 148.00

5 For welding sections:Electrodes @ 125 Nos / t Nos. 125.00 4.00 500.00

6 For field connections:M.S.Bolts / Nuts / Washers kg 50.00 45.00 2250.00

7 Sundries LS 20.00 22.50 450.00TOTAL Rs: 24104.00

Add for small Tools and Plants @ 1% Rs: 241.04Add for Contractor' Profit @ 10% Rs: 2410.40Add for Contrators' Overheads @ 5% Rs: 1205.20 Total cost of Materials for 20 uses of supports Rs: 27960.64 Cost per use considering 20 uses Rs: 1398.03

B. MACHINERY ( for fabrication ) : Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Bending machine Hour 8.00 31.00 248.00

Fuel / Energy charges Hour 8.00 61.00 488.002 Welding set Hour 16.00 9.00 144.00

Fuel / Energy charges Hour 16.00 49.00 784.003 Sundries LS 30.00 22.50 675.00

TOTAL Rs: 2339.00Add for small Tools and Plants @ 1% Rs: 23.39Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 194.70Add for Contrators' Overheads @ 5% Rs: 116.95 Total hire charges of Machinery Rs: 2674.04 Cost per use considering 20 uses Rs: 133.70

C. MACHINERY ( for erection and dismantling ) : Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Drilling Jumbo Hour 18.00 230.00 4140.00

Fuel / Energy charges Hour 18.00 17.00 306.002 Sundries LS 10.00 27.70 277.00

TOTAL Rs: 4723.00Add for small Tools and Plants @ 1% Rs: 47.23Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 58.30Add for Contrators' Overheads @ 5% Rs: 236.15 Total hire charges of Machinery Rs: 5064.68

37

Page 39: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

D. LABOUR ( for fabrication ): Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Bending machine Hour 8.00 26.70 213.602 For cutting & preparing sections:

Structural steel Marker Day 1.00 93.70 93.70Gas cutter Day 2.00 93.70 187.40Fitter Day 2.00 93.70 187.40Turner / Driller Day 3.00 89.70 269.10Khalasi Day 2.00 83.65 167.30Helper fabrication Day 4.00 81.60 326.40

3 For welding sections:Welder Day 2.00 93.70 187.40Helper fabrication Day 2.00 83.65 167.30Khalasi Day 2.00 81.60 163.20

TOTAL Rs: 1962.80Add for small Tools and Plants @ 1% Rs: 19.63Add for Contractor' Profit @ 10% Rs: 196.28Add for hidden cost on Labour @ 15% Rs: 294.42Add for additional hidden cost on labour @ 10% Rs: 196.28Add for Contrators' Overheads @ 5% Rs: 98.14

Total cost of Labour Rs: 2767.55 Cost per use considering 20 uses Rs: 138.38

E. LABOUR ( for erection and dismantling ): Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Drilling jumbo Hour 8.00 35.10 280.802 For erection of supports:

Foreman Day 1.00 108.65 108.65Structural steel Erector Day 2.00 93.70 187.40Helper erector Day 2.00 81.60 163.20Khalasi Day 4.00 83.65 334.60

3 For dismantling of supports:Foreman Day 0.50 108.65 54.33Structural steel Erector Day 1.00 93.70 93.70Helper erector Day 1.00 81.60 81.60Khalasi Day 2.00 83.65 167.30

TOTAL Rs: 1471.58Add for small Tools and Plants @ 1% Rs: 14.72Add for Contractor' Profit @ 10% Rs: 147.16Add for hidden cost on Labour @ 15% Rs: 220.74Add for additional hidden cost on labour @ 10% Rs: 147.16Add for Contrators' Overheads @ 5% Rs: 73.58

Total cost of Labour Rs: 2074.92

ABSTRACT:A. Cost of Materials Rs: 1398.03B. Hire charges of Machinery for fabrication Rs: 133.70C. Hire charges of Machinery for erection and dismantling Rs: 5064.68D. Cost of Labour for fabrication Rs: 138.38E. Cost of Labour for erection and dismantling Rs: 2074.92

Total Rs: 8809.71Add for Air and Water line @ 1.00% Rs: 88.10

38

Page 40: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 140.96Add for Ele sub-station / Demand charges @ 5.00% Rs: 440.49Add for other enabling works @ 2.00% Rs: 176.19

TOTAL Rs: 9655.44Add for 1 km rehandling charges ( 2 times ) :For steel 1000 kg for erection @ Rs: 81.30 / tonne Rs: 81.30For steel 1000 kg after dismantling @Rs: 81.30 / tonne Rs: 81.30 Total cost for 1.00 tonne Rs: 9818.04

Rate per tonne Rs: 9818.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 13

ITEM: Providing and fixing hard variety cut jungle wood for lagging / blocking locations in tunnel wherever required including cost of all materials, machinery, labour, fixing in position, lighting,ventilation, drainage etc complete with all leads and lifts.

DATA:Generally 50 to 65 mm thick cut jungle wood planks are placed behind supports as lagging /blocking to prevent loosening and over falling of weak / highly jointed rock formations duringdaily blasting for excavation of tunnel.20 to 25 sqm area can be covered by 1 cum of cut jungle wood sections.1 carpenter Cl II and 2 heavy mazdoors are considered for cutting and fixing / cum.5 percent extra wood assumed for wedges / wastage etc.Use of drilling jumbo assumed for 2 hours.

RATE ANALYSIS UNIT: 1.00 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Cut jungle wood cum 1.05 16000.00 16800.002 Sundries LS 2.00 22.50 45.00

TOTAL Rs: 16845.00Add for small Tools and Plants @ 1% Rs: 168.45Add for Contractor' Profit @ 10% Rs: 1684.50Add for Contrators' Overheads @ 5% Rs: 842.25

Total cost of Materials Rs: 19540.20

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Drilling jumbo Hour 2.00 230.00 460.00

Fuel / Energy charges Hour 2.00 17.00 34.00TOTAL Rs: 494.00

Add for small Tools and Plants @ 1% Rs: 4.94Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 3.40Add for Contrators' Overheads @ 5% Rs: 24.70 Total hire charges of Machinery Rs: 527.04

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Drilling jumbo Hour 2.00 35.10 70.202 Carpenter Cl II Day 1.00 86.15 86.153 Heavy mazdoor Day 2.00 80.90 161.80

TOTAL Rs: 318.15

39

Page 41: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Add for small Tools and Plants @ 1% Rs: 3.18Add for Contractor' Profit @ 10% Rs: 31.82Add for hidden cost on Labour @ 15% Rs: 47.72Add for additional hidden cost on labour @ 10% Rs: 31.82Add for Contrators' Overheads @ 5% Rs: 15.91

Total cost of Labour Rs: 448.59

ABSTRACT:A. Cost of Materials Rs: 19540.20B. Hire charges of Machinery Rs: 527.04C. Cost of Labour Rs: 448.59

Total Rs: 20515.83Add for Air and Water line @ 1.00% Rs: 205.16Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 328.25Add for Ele sub-station / Demand charges @ 5.00% Rs: 1025.79Add for other enabling works @ 2.00% Rs: 410.32 Total cost for 1.00 cum Rs: 22485.35

Rate per cum Rs: 22490.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 14

ITEM: Providing and constructing un-coursed rubble stone masonry with approved stones from tunnel excavated muck in cement mortar 1 : 6 proportion for backfilling over cuts / slips ontunnel sides due to geological faults etc., including cost of all materials, machinery, labour,cleaning,scaffolding, packing mortar, wedging stone chips, curing, ventilation, lighting, drainagecomplete with lead upto 1 km and all lifts.

DATA:For 1 cum masonry :- Rubble stones : 0.83 cum Stone chips : 0.13 cum.Sand : 0.40 cum. Cement : 95 kg. Wastage : 1 % for cement & 2 % for stones & sand.Cement mortar preparation : ManualOutput of 1 Mason : 5.00 cum per day

RATE ANALYSIS UNIT: 10.00 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Cement kg 960.00 2.90 2784.002 Rubble stones cum 8.50 85.00 722.503 Stone chips cum 1.25 100.00 125.004 Sand ( screened ) cum 4.10 114.00 467.40

TOTAL Rs: 4098.90Add for small Tools and Plants @ 1% Rs: 40.99Add for Contractor' Profit @ 10% Rs: 409.89Add for Contrators' Overheads @ 5% Rs: 204.95Add for scaffolding @ 2.5% Rs: 102.47Add Royalty charges on Rubble @ Rs: ( Included in material rate ) Rs: 0.00Add Royalty charges on Sand @ Rs: ( Included in material rate ) Rs: 0.00

Total cost of Materials Rs: 4857.20

40

Page 42: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 10 hp pump ( ele ) Hour 1.00 4.00 4.00

Fuel / energy charges Hour 1.00 41.00 41.00TOTAL Rs: 45.00

Add for small Tools and Plants @ 1% Rs: 0.45Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 4.10Add for Contrators' Overheads @ 5% Rs: 2.25 Total hire charges of Machinery Rs: 51.80

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.2 Crew for Pump Hour 1.00 15.60 15.603 Maistry Day 1.00 81.60 81.604 Mason Class-I Day 1.00 94.15 94.155 Mason Class-II Day 2.00 86.15 172.306 Heavy mazdoor

for sorting out rubble in dump yard Day 1.00 80.90 80.90for conveying rubble Day 2.00 80.90 161.80for preparing mortar Day 2.00 80.90 161.80for loading mortar pans Day 1.00 80.90 80.90for laying & packing mortar Day 4.00 80.90 323.60

7 Light mazdoor for washing rubble / finishing / curing Day 1.00 76.40 76.40for conveying mortar / chips Day 3.00 76.40 229.20

TOTAL Rs: 1478.25Add for small Tools and Plants @ 1% Rs: 14.78Add for Contractor' Profit @ 10% Rs: 147.83Add for hidden cost on Labour @ 15% Rs: 221.74Add for additional hidden cost on labour @ 10% Rs: 147.83Add for Contrators' Overheads @ 5% Rs: 73.91Add for labour for scaffolding @ 2.50% Rs: 36.96

Total cost of Labour Rs: 2121.29

ABSTRACT:A. Cost of Materials including royalty charges Rs: 4857.20B. Hire charges of Machinery Rs: 51.80C. Cost of Labour Rs: 2121.29

Total Rs: 7030.29Add for Air and Water line @ 1.00% Rs: 70.30Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 112.48Add for Ele sub-station / Demand charges @ 5.00% Rs: 351.51Add for other enabling works @ 2.00% Rs: 140.61

Total Rs: 7705.19Add for 1 km rehandling charges :For cement 960 kg @ Rs: 81.30 / tonne Rs: 78.05For sand 4.10 cum @ Rs: 55.10 / cum Rs: 225.91For stones and chips 9.75 cum @ Rs: 77.45 / cum Rs: 755.14 Total cost for 10.00 cum Rs: 8764.29

Rate per cum Rs: 876.50

41

Page 43: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 15

ITEM: Providing, fabricating and placing in position reinforcement steel for tunnel RCC worksincluding cleaning, straightening, cutting, bending, hooking, lapping / welding joints wherever required, tying with 1.25 mm dia.soft annealed steel wire, including cost of all materials, labour, machinery, ventilation, lighting, drainage etc.,complete with initial lead upto 1 km and all lifts.

DATA:No welding of reinforcement bars is considered since the diameter of bars for tunnel RCC workswill be generally less than 32 mm.As concrete will be placed by pneumatic placer, the reinforcement bars have to be held regidlyin place to prevent displacement due to shooting effect of concrete. This requires about50 percent more binding wire compared to locations where concrete placement is by manuallabour.Quantity of binding wire for works other than tunnel : 9 kg / tonneQuantity of binding wire for reinforcement in tunnel ( 1.5 x 9 ) : 13.5 kg / tWastage of steel : 2.5 percentLabour requirement per tonne:In view of restricted head room between shuttering and excavation line placing reinforcementwill be slow compared to open area.Further bars in transverse direction are to be bent to matchthe profile of tunnel. This requires more labour for bending at fabrication yard and for placingbars in position in tunnel.Labour requirement per tonne:Cleaning and straightening : 2 Bar benders & 2 Heavy mazdoorsMarking, bending and stacking : 3 Bar benders & 6 Heavy mazdoorsPlacing in position and tying : 3 Bar benders & 6 Heavy mazdoorsChecking, correcting & misc. works : 1 Bar benders & 1 Heavy mazdoors

RATE ANALYSIS UNIT : 1.00 tonneA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Rein.Steel with 2.5 % wastage tonne 1.025 18000.00 18450.002 Binding wire 1.25 mm dia kg 13.50 27.00 364.503 Sundries ( chairs / spacers etc ) LS 5.00 22.50 112.50

TOTAL Rs: 18927.00Add for small Tools and Plants @ 1% Rs: 189.27Add for Contractor' Profit @ 10% Rs: 1892.70Add for Contrators' Overheads @ 5% Rs: 946.35

Total cost of Materials Rs: 21955.32

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 NIL 0.00 0.00 0.00

0.00 0.00 0.00TOTAL Rs: 0.00

Add for small Tools and Plants @ 1% Rs: 0.00Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 0.00Add for Contrators' Overheads @ 5% Rs: 0.00 Total hire charges of Machinery Rs: 0.00

42

Page 44: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Bar bender Day 9.00 94.15 847.352 Heavy mazdoor Day 15.00 80.90 1213.50

TOTAL Rs: 2060.85Add for small Tools and Plants @ 1% Rs: 20.61Add for Contractor' Profit @ 10% Rs: 206.09Add for hidden cost on Labour @ 15% Rs: 309.13Add for additional hidden cost on labour @ 10% Rs: 206.09Add for Contrators' Overheads @ 5% Rs: 103.04

Total cost of Labour Rs: 2905.80

ABSTRACT:A. Cost of Materials Rs: 21955.32B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2905.80

TOTAL Rs: 24861.12Add for Air and Water line @ 1.00% Rs: 248.61Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 397.78Add for Ele sub-station / Demand charges @ 5.00% Rs: 1243.06Add for other enabling works @ 2.00% Rs: 497.22

Total Rs: 27247.79Add for 1 km rehandling charges :For steel 1.025 tonne @ Rs: 81.30 / tonne Rs: 83.33 Total cost for 1.00 tonne Rs: 27331.12

Rate per tonne Rs: 27331.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 16

ITEM: Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,graded aggregates crushed from tunnel excavated muck for filling and levelling over-cutsin bed due to geological faults etc., including cost of all materials, machinery, labour, cleaning bed, batching, mixing, conveying and laying, levelling, compacting, finishing, curing, lighting,ventilation, drainage etc., complete with initial lead upto 1 km and all lifts. ( Cementcontent : 220 kg / cum )

DATA:For 1 cum CC :- Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20Fine aggregate : 0.40 cum Cement content : 220 kg Super plasticizer : 0.70 ltrWastage : 1 % for cement and 2 % for coarse & fine aggregates.Requirement of materials per cum of CC: Cement 43 Gr with 1 % wastage : 222 kgFine aggregate with 2 % wastage : 0.41 cumCoarse aggregate with 2 % wastage 40 to 20 mm size : 0.46 cum 20 to 10 mm size : 0.28 cum 10 to 4.75 mm size : 0.18 cumConcrete admixture ( Super plasticiser ) : 0.66 ltrConsider 2 cum capacity agitator car for conveying concrete.Cycle time for one round trip:Turning and spotting : 2 minLoading 4 mixes of 0.5 cum @ 5 min per mix : 20 minRunning time from BP to placing point av. 1 km : 10 min

43

Page 45: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Unloading concrete : 15 minReturn trip to BP : 10 minTotal cycle time for round trip : 57 minDeploy 2 Agitator cars for conveying concrete.The rate of concreting for 2 agitator cars with 50 min / hr working : 3.50 cum / hrDeploy 2 x 1.00 cum rated capacity non-tilting type batching plant for 8 hours.Deploy 10 hp pump for 8 hours for pumping water to storage tank for concreting / curing waterrequirements.Progress per shift of 8 hours: ( 8 x 3.50 ) : 28 cumLoading cement to BP bin : ManualNo shuttering is required for over excavations in bed.

RATE ANALYSIS UNIT: 28.00 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Cement for mix kg 6222.00 2.90 18043.802 Coarse aggregate 40-20 mm cum 12.90 263.00 3392.70

Coarse aggregate 20-10 mm cum 7.85 358.00 2810.30 Coarse aggregate 10 mm below cum 5.05 461.00 2328.05

3 Fine aggregate ( screened ) cum 11.50 114.00 1311.004 Super Plasticizer ltr 19.00 55.00 1045.005 Sundries LS 2.00 22.50 45.00

TOTAL Rs: 28975.85Add for small Tools and Plants @ 1% Rs: 289.76Add for Contractor' Profit @ 10% Rs: 2897.59Add for Contrators' Overheads @ 5% Rs: 1448.79Add Royalty charges on CA @ Rs:( Included in material rate ) Rs: 0.00Add Royalty charges on FA @ Rs:( Included in material rate ) Rs: 0.00

Total cost of Materials Rs: 33611.99

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Batching plant 2 x 1 cum Hour 8.00 236.00 1888.00

Fuel / Energy charges Hour 8.00 184.00 1472.002 Agitator car 2 cum Hour 16.00 486.00 7776.00

Fuel / Energy charges Hour 16.00 340.00 5440.003 10 hp pump ( ele ) Hour 8.00 4.00 32.00

Fuel / Energy charges Hour 8.00 41.00 328.004 Needle vibrator 40 mm dia Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 4.00 32.005 Sundries LS 2.00 22.50 45.00

TOTAL Rs: 17061.00Add for small Tools and Plants @ 1% Rs: 170.61Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 731.70Add for Contrators' Overheads @ 5% Rs: 853.05 Total hire charges of Machinery Rs: 18816.36

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Batching plant Hour 8.00 62.80 502.402 Crew for Agitator car Hour 16.00 52.65 842.40

44

Page 46: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

3 Crew for Pump Hour 8.00 15.60 124.804 Crew for Needle vibrator Hour 8.00 30.85 246.805 Mason Class-I Day 1.00 94.15 94.156 Maistry Day 1.00 81.60 81.607 Heavy mazdoor

for cleaning bed Day 2.00 80.90 161.80for loading material bin ( Cement ) Day 3.00 80.90 242.70for miscellaneous works at BP Day 2.00 80.90 161.80for laying concrete Day 7.00 80.90 566.30

8 Light mazdoor for conveying laying concrete Day 14.00 76.40 1069.60for cleaning bed Day 2.00 76.40 152.80for washing CA / curing Day 2.00 76.40 152.80

TOTAL Rs: 4399.95Add for small Tools and Plants @ 1% Rs: 44.00Add for Contractor' Profit @ 10% Rs: 440.00Add for hidden cost on Labour @ 15% Rs: 659.99Add for additional hidden cost on labour @ 10% Rs: 440.00Add for Contrators' Overheads @ 5% Rs: 220.00

Total cost of Labour Rs: 6203.93

ABSTRACT:A. Cost of Materials including royalty charges Rs: 33611.99B. Hire charges of Machinery Rs: 18816.36C. Cost of Labour Rs: 6203.93

Total Rs: 58632.28Add for Air and Water line @ 1.00% Rs: 586.32Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 938.12Add for Ele sub-station / Demand charges @ 5.00% Rs: 2931.61Add for other enabling works @ 2.00% Rs: 1172.65 Total cost for 28.00 cum Rs: 64260.97

Rate per cum Rs: 2295.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 17

ITEM: Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,graded aggregates crushed from tunnel muck for kerb and bed lining including cost of allmaterials, machinery, labour, formwork, batching, mixing, conveying upto placing point inagitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts. ( Cement content 270 kg / cum for use of super plasticiser )

Cost of shuttering : Annexure: A

Consider one shutter and one soldier set :Shutter size : 900 mm x 1200 mm Length of soldier : 2.3 m Shutter area : 1.20 sqm4 mm thick plate 1.08 sqm @ 31.4 kg/ sqm : 33.91 kg50x50x6 mm angle 6.6 m length @ 3.8 kg/ m : 25.08 kg50x6 mm flat 1.8 m length @ 2.35 kg/ m : 4.23 kgISLC 100 2.3 m length @ 7.9 kg / m : 18.17 kg6 mm plate 0.03 sqm @ 47.1 kg/ sqm : 1.41 kg

45

Page 47: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Cost of 4 mm plate 33.91 kg @ Rs: 24.00 / kg Rs: 813.84Cost of 6.6 m angle 25.08 kg @ Rs: 20.00 / kg Rs: 501.60Cost of 1.8 m flat 4.23 kg @ Rs: 20.00 / kg Rs: 84.60Cost of 2.3 m soldier 18.17 kg @ Rs: 20.00 / kg Rs: 363.40Cost of 6mm plate 1.41 kg @ Rs: 24.00 / kg Rs: 33.84

Total Rs: 1797.28Add for wastage @ 2.5 % Rs: 44.93Add for bolts & nuts @ 0.5 kg/ sqm Rs: 45.00 / kg Rs: 22.50Add for fabrication of shutter @ Rs: 8.00 / kg Rs: 662.40

Total Rs: 2527.11Less salvage value @ 10% Rs: -252.71

Total Rs: 2274.40Use rate of shutters:Use rate of shutters considering average 40 uses Rs: 56.86Add for repairs/ replacements/ catwalks etc., @ 15 % Rs: 8.53Add for binding wire/ temperary supports etc., @ 5 % Rs: 2.84Add for shutter oil at 0.2 ltr/ sqm @ Rs: 15.00 / ltr Rs: 3.00

Total Rs: 71.23Effective area of shutter & soldier with 10 cm margin at top and bottom : 1.00 sqmCost of shuttering for concrete / use/ sqm Rs: 71.23( Excluding T & P / Profit / Overheads)

Erection & dismantling shuttering : Annexure: B

2 Fitters, 1 Carpentor Cl-II and 5 mazdoors erect 50 sqm shuttering / day.Cost of dismantling assumed at 50 % of erection charges.Area of shuttering with supports considered. : 100 sqmCleaning, conveying, erecting and oiling:Fitter shuttering 4 Nos. @ Rs: 86.15 Rs: 344.60Carpentor Cl -II 2 Nos. @ Rs: 86.15 Rs: 172.30Heavy mazdoor 10 Nos. @ Rs: 80.90 Rs: 809.00Dismantling and stacking: Fitter shuttering 2 Nos. @ Rs: 86.15 Rs: 172.30Carpentor Cl -II 1 Nos. @ Rs: 86.15 Rs: 86.15Heavy mazdoor 5 Nos. @ Rs: 80.90 Rs: 404.50

Total Rs: 1988.85Labour charges for erecting and dismantling shuttering per sqm Rs: 19.89( Excluding T & P / Profit / Overheads / Hidden costs )

DATA:Concrete mix details for 50-70 mm slump: For 1 cum CC :- Coarse aggregates : 0.90 cum(1300 kg) Blending ratio : 50 :30 : 20Fine aggregate : 0.40 cum ( 700 kg ) Cement : 270 kg Super plasticizer : 0.80 ltrWastage : 1 % for cement and 2 % for coarse & fine aggregates.Requirement of materials per cum of CC: Cement 43 Gr with 1 % wastage : 273 kgFine aggregate with 2 % wastage : 0.45 cumCoarse aggregate with 2 % wastage 40 to 20 mm size : 0.47 cum 20 to 10 mm size : 0.27 cum 10 to 4.75 mm size : 0.17 cumConcrete admixture( Super plasticiser ) : 0.80 ltrConsider 2 cum capacity agitator car for conveying concrete.Cycle time for one round trip:Turning and spotting : 2 minLoading 4 mixes of 0.5 cum @ 5 min per mix : 20 minRunning time from BP to placing point av. 1 km : 10 min

46

Page 48: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Unloading concrete : 15 minReturn trip to BP : 10 minTotal cycle time for round trip : 57 minDeploy 2 Agitator cars for conveying concrete.The rate of concreting for 2 agitator cars with 50 min / hr working : : 3.50 cum / hrDeploy 2 x 1.00 cum rated capacity non-tilting type batching plant for 8 hours.Deploy 10 hp pump for 8 hours for pumping water to storage tank for concreting / curing waterrequirements.Progress per shift of 8 hours: ( 8 x 3.50 ) : 28 cumLoading cement to BP material bin : ManualFor kerb / bed concreting average 1 sqm shuttering is required per cum of concrete. Requirement of shuttering for 28 cum concrete : 28 sqm

RATE ANALYSIS UNIT : 28.00 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Cement 43 Gr kg 7644.00 2.90 22167.60

Cement for incidentals @ 1 kg / cum kg 28.00 2.90 81.202 Fine aggregate ( screened ) cum 12.60 114.00 1436.403 Coarse aggregate 40-20 mm cum 13.15 263.00 3458.45

Coarse aggregate 20-10 mm cum 7.55 358.00 2702.90Coarse aggregate 10-4.75 mm cum 4.75 461.00 2189.75

4 Super plasticiser ltr 23.00 55.00 1265.005 Use rate of shuttering for kerb / bed sqm 28.00 71.23 1994.506 Sundries LS 2.00 22.50 45.00

TOTAL Rs: 35340.80Add for small Tools and Plants @ 1% Rs: 353.41Add for Contractor' Profit @ 10% Rs: 3534.08Add for Contrators' Overheads @ 5% Rs: 1767.04Add Royalty charges on CA @ Rs: ( Included in material rate ) Rs: 0.00Add Royalty charges on FA @ Rs: ( Included in material rate ) Rs: 0.00

Total cost of Materials Rs: 40995.32

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Batching plant 2 x 1.00 cum Hour 8.00 236.00 1888.00

Fuel / Energy charges Hour 8.00 184.00 1472.002 Agitator car 2 cum ( 2 Nos ) Hour 16.00 486.00 7776.00

Fuel / Energy charges Hour 16.00 340.00 5440.003 Needle Vibrator Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 4.00 32.004 Pump 10 hp ( Ele ) Hour 8.00 4.00 32.00

Fuel / Energy charges Hour 8.00 41.00 328.005 Sundries LS 5.00 22.50 112.50

TOTAL Rs: 17128.50Add for small Tools and Plants @ 1% Rs: 171.29Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 738.45Add for Contrators' Overheads @ 5% Rs: 856.43 Total hire charges of Machinery Rs: 18894.66

47

Page 49: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Batching plant Hour 8.00 62.80 502.402 Crew for Agitator car Hour 16.00 52.65 842.403 Crew for vibrator Hour 8.00 30.85 246.804 Crew for pump Hour 8.00 15.60 124.805 For scaling & cleaning bed

Hammerman Day 2.00 83.65 167.30 Heavy mazdoor Day 4.00 80.90 323.60

Light mazdoor Day 2.00 76.40 152.806 For loading cement to BP bin

Heavy mazdoor Day 3.00 80.90 242.707 For miscellaneous work at BP

Heavy mazdoor Day 2.00 80.90 161.808 For wetting C.A & curing

Light mazdoor Day 2.00 76.40 152.809 Laying concrete for kerb/ invert

Masom Cl I Day 2.00 94.15 188.30Mason Cl II Day 2.00 86.15 172.30Heavy mazdoor Day 7.00 80.90 566.30Light mazdoor Day 14.00 76.40 1069.60Maistry Day 1.00 81.60 81.60

10 Labour charges for shuttering sqm 28.00 19.89 556.88TOTAL Rs: 5552.38

Add for small Tools and Plants @ 1% Rs: 55.52Add for Contractor' Profit @ 10% Rs: 555.24Add for hidden cost on Labour @ 15% Rs: 832.86Add for additional hidden cost on labour @ 10% Rs: 555.24Add for Contrators' Overheads @ 5% Rs: 277.62

Total cost of Labour Rs: 7828.85

ABSTRACT:A. Cost of Materials including royalty charges Rs: 40995.32B. Hire charges of Machinery Rs: 18894.66C. Cost of Labour Rs: 7828.85

Total Rs: 67718.84Add for Air and Water line @ 1.00% Rs: 677.19Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 1083.50Add for Ele sub-station / Demand charges @ 5.00% Rs: 3385.94Add for other enabling works @ 2.00% Rs: 1354.38 Total cost for 28.00 cum Rs: 74219.85

Rate per cum Rs: 2651.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 18

ITEM: Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,graded aggregates crushed from tunnel muck for sides and arch lining including cost of allmaterials, machinery, labour, formwork, batching, mixing, conveying upto placing point inagitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.( Cement content 300 kg / cum with super plasticiser ).

48

Page 50: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

DATA:Concrete mix details per cum for 80-100 mm slump: Cement 43 Gr : 300 kgFine aggregate : 700 kgCoarse aggregate 40 mm down : 1250 kgBlending ratio : 50 : 30 : 20Requirement of materials per cum of CC: Cement 43 Gr with 1 % wastage : 306 kgFine aggregate with 2 % wastage : 0.450 cumCoarse aggregate with 2 % wastage 40 to 20 mm : 0.455 cum 20 to 10 mm : 0.265 cum 10 to 4.75 mm : 0.170 cumConcrete admixture( Super plasticiser ) : 0.90 ltr

Excavated line

Gantry shuttering

Concrete lining

Gantry frame

Gantry track

TYPICAL ARRANGEMENT FOR ARCH / SIDE CONCRETING

Consider 2 cum capacity agitator cars for conveying concrete.Cycle time for one round trip:Turning and spotting : 2 minLoading 4 mixes of 0.5 cum @ 5 min per mix : 20 minRunning time from BP to placing point av. 1 km : 10 minUnloading concrete to placer drum : 24 minReturn trip to BP : 10 minTotal cycle time for round trip : 66 minDeploy 2 Agitator cars for conveying concrete.The rate of concreting for 2 agitator cars with 50 min / hr working : : 3.0 cum / hrDeploy 2 x 1.00 cum rated capacity non-tilting type batching plant for 12 hours.Deploy 10 hp pump for 8 hours for pumping water to storage tank for water requirement forconcreting and curing.Progress per shift of 8 hours: ( 8 x 3.00 ) : 24 cumLoading BP material bins : ManualPlacing concrete for sides and arch : Placer pumpDeploy 8.5 cmm air compressor ( ele ) for air supply to placer pump.Track mounted collapsible gantry considered for supporting sides and arch concrete.Assume 9 m long collapsible type steel gantry Diameter of tunnel ( finished ) considered : 5.00 mHight of tunnel ( finished ) considered : 5.00 mQuantity of concrete / gantry considering 30 cm thick lining : 32.75 cum( considering 60 cm hight kerb above bed level already laid )Concrete for filling support reaches & pay line margin @ 45 % : : 14.75 cum ( for av. 10 cm pay line margin filling & 10 % length with supports )Average quantity of concrete / gantry length of lining ( say ) : 48.00 cumSurface area of gantry for sides and arch portion ( say ) : 105 sqm

49

Page 51: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Weight of gantry @ 150 kg / sqm ( say ) : 16 tonnesCost of gantry including cost of steel, fabrication, painting, transportation and erection:Cost of beams/angles/channels at 50 % @ Rs: 20000.00 / tonne Rs: 160000.00Cost of plates @ at 40 % @ Rs: 24000.00 / tonne Rs: 153600.00Cost of wheels/Jacks/Fixtures at 10 % @ Rs: 45000.00 / tonne Rs: 72000.00Cost of fabrication & painting @ Rs: 10000.00 / tonne Rs: 160000.00

Total Rs: 545600.00Add for transportation, erection & dismantling @ 12% Rs: 65472.00

Total Rs: 611072.00Less salvage value @ 10% ( - ) Rs: -61107.20

Total Rs: 549964.80Considering 100 uses cost per use of gantry Rs: 5499.65Add for repairs/ replacements etc., @ 25% Rs: 1374.91Add for rails / fixtures etc., @ 15% Rs: 824.95Add for shutter oil at 0.2 ltr/ sqm @ Rs: 15.00 / ltr Rs: 315.00

Total Rs: 8014.51Use rate of gantry / sqm / use considering 100 sqm effective area Rs: Rs: 80.15Requirement of end shutter : 6 sqmUse rate of end shutter per sqm ( Annexure-A Item-17 ) Rs: 71.23Erecting & dismantling end shutter / sqm ( Annexure-B Item-17 ) Rs: 19.89Cycle time of various operations for concreting:Cleaning / scaling bed for laying track line : 2.00 hoursDismantling & extending track line : 4.00 hoursReleasing / moving / aligning gantry : 4.00 hoursCleaning & Oiling gantry / Bulk head fixing : 4.00 hoursPlacer pipe assembling for different positions : 6.00 hoursConcreting 48 cum @ 3.00 cum per hour : 16.00 hoursMiscellaneous / Break downs / pipe clogging etc : 4.00 hoursSetting time before release of gantry : 12.00 hoursConsidering cleaning / scaling bed / track dismsntling and erection are carried out as parallelactivities during setting time of concrete, the total cycle time for one gantry length concretingwill be about 48 hours. Out of 6 shifts ( 48 hours ) 3 shifts are considered as concreting shifts and 3 shifts areconsidered as preparatory shifts.

RATE ANALYSIS UNIT : 48.00 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Cement 43 Gr kg 14544.00 2.90 42177.60

Cement for incidentals @ 1 kg / cum kg 48.00 2.90 139.202 Fine aggregate ( screened ) cum 22.00 114.00 2508.003 Coarse aggregate 40-20 mm cum 22.30 263.00 5864.90

Coarse aggregate 20-10 mm cum 13.00 358.00 4654.00Coarse aggregate 10-4.75 mm cum 8.30 461.00 3826.30

4 Super plasticiser ltr 44.00 55.00 2420.005 Use rate of end shuttering sqm 6.00 71.23 427.396 Use rate of steel gantry sqm 100.00 80.15 8014.517 Sundries ( placer pipe etc ) LS 5.00 22.50 112.50

TOTAL Rs: 70144.40Add for small Tools and Plants @ 1% Rs: 701.44Add for Contractor' Profit @ 10% Rs: 7014.44Add for Contrators' Overheads @ 5% Rs: 3507.22Add Royalty charges on CA @ Rs: ( Included in material rate ) Rs: 0.00

50

Page 52: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Add Royalty charges on FA @ Rs: ( Included in material rate ) Rs: 0.00Total cost of Materials Rs: 81367.50

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Air compressor ( Ele ) 8.5 cmm Hour 16.00 87.00 1392.00

Fuel / Energy charges @ 75 % load Hour 12.00 230.00 2760.002 Batching plant 2 x 1.00 cum Hour 12.00 236.00 2832.00

Fuel / Energy charges Hour 12.00 184.00 2208.003 Agitator car 2 cum ( 2 Nos ) Hour 32.00 486.00 15552.00

Fuel / Energy charges Hour 32.00 340.00 10880.004 Concrete placer pump Hour 16.00 102.00 1632.00

Fuel / Energy charges Hour 16.00 2.00 32.005 Needle Vibrator / Shutter vibrator Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 4.00 32.006 Pump 10 hp ( Ele ) Hour 8.00 4.00 32.00

Fuel / Energy charges Hour 8.00 41.00 328.007 Sundries LS 5.00 22.50 112.50

TOTAL Rs: 37840.50Add for small Tools and Plants @ 1% Rs: 378.41Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 1635.25Add for Contrators' Overheads @ 5% Rs: 1892.03 Total hire charges of Machinery Rs: 41746.18

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew charges for Air compressor Hour 16.00 32.70 523.202 Crew charges for Batching plant Hour 16.00 62.80 1004.803 Crew charges for Agitator car Hour 32.00 52.65 1684.804 Crew charges for placer pump Hour 16.00 16.80 268.805 Crew charges for vibrator Hour 8.00 30.85 246.806 Crew charges for Pump Hour 8.00 15.60 124.807 For scaling & cleaning

Stone chiseller Cl II Day 0.50 84.20 42.10 Heavy mazdoor Day 0.50 80.90 40.45

Light mazdoor Day 0.50 76.40 38.208 For dismantling / Laying track

Surveyer Day 0.50 91.20 45.60Fitter shuttering Day 0.50 86.15 43.08Helper shuttering 2 x 0.5 Day 1.00 81.60 81.60Khalasi 6 x 0.5 Day 3.00 83.65 250.95Heavy mazdoor 2 x 0.5 Day 1.00 80.90 80.90

9 For Moving / Positioning gantry Surveyer Day 0.50 91.20 45.60Foreman Day 0.50 108.65 54.33Fitter shuttering Day 0.50 86.15 43.08Helper shuttering 2 x 0.5 Day 1.00 81.60 81.60Khalasi 6 x 0.5 Day 3.00 83.65 250.95Heavy mazdoor 2 x 0.5 Day 1.00 80.90 80.90

10 For loading cement to BP binHeavy mazdoor Day 5.00 80.90 404.50

11 For miscellaneous works of BPHeavy mazdoor Day 2.00 80.90 161.80

51

Page 53: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

12 For Erection/Dismantling bulk head sqm 6.00 19.89 119.3313 For Laying concrete by placer

Masom Cl I Day 3.00 94.15 282.45Heavy mazdoor Day 6.00 80.90 485.40Light mazdoor Day 3.00 76.40 229.20Maistry Day 3.00 81.60 244.80

14 For wetting C.A / Curing etc Light mazdoor Day 3.00 76.40 229.20

TOTAL Rs: 7189.21Add for small Tools and Plants @ 1% Rs: 71.89Add for Contractor' Profit @ 10% Rs: 718.92Add for hidden cost on Labour @ 15% Rs: 1078.38Add for additional hidden cost on labour @ 10% Rs: 718.92Add for Contrators' Overheads @ 5% Rs: 359.46

Total cost of Labour Rs: 10136.78

ABSTRACT:A. Cost of Materials including royalty charges Rs: 81367.50B. Hire charges of Machinery Rs: 41746.18C. Cost of Labour Rs: 10136.78

Total Rs: 133250.46Add for Air and Water line @ 1.00% Rs: 1332.50Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 2132.01Add for Ele sub-station / Demand charges @ 5.00% Rs: 6662.52Add for other enabling works @ 2.00% Rs: 2665.01 Total cost for 48.00 cum Rs: 146042.51

Rate per cum Rs: 3043.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 19

ITEM: Drilling 32 mm diameter grout holes in concrete / rock by percussion drilling using jackhammer or stooper drills as directed to specified depth for consolidation / contact groutingincluding cost of all materials, machinery, labour, cleaning holes, ventilation, lighting, drainageand all other ancillary operations etc., complete.

DATA:Diameter of hole for consolidation / contact grouting : 32 mmConsider 100 m drilling for analysis:Rate of drilling by jack hammer in open area 8 m / hourThe rate of drilling for consolidation / contact grouting will be slow in view of frequent shifting ofdrilling jumbo / air and water hoses from place to place.Average rate of drilling considering 50 % time for shifting : 4 m / hourDeploy 1 Air compressor 15 cmm for 8 hours with 50 minutes per hour workingDeploy 4 Jack hammers / Stooper drills for 8 hoursDeploy Drilling jumbo for 8 hours.Deploy 10 hp pump for 4 hours for pumping water to storage tank.Cost of jack hammer drill rod 2.5 m long @ Rs: 3500.00 Each Rs: 3500.00Life of drill rod with reconditioning : 150 mUse rate of drill rod per m drilling ( cost / life ) Rs: 23.33Cost of air hose 25 m / jack hammer @ Rs: 120.00 / m Rs: 3000.00Life of air hose : 800 hoursUse rate of air hose per hour ( cost / life ) Rs: 3.75Cost of water hose 25 m / jack hammer @ Rs: 110.00 / m Rs: 2750.00Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 3.44

52

Page 54: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

In view of shallow holes and wet drilling regular flushing is not required.

RATE ANALYSIS UNIT : 100.00 RmA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Use rate of drill rod Rm 100.00 23.33 2333.33

Reconditioning charges @ 10% 233.332 Use rate of air hose 4 Nos Hour 32.00 3.75 120.003 Use rate of water hose 4 Nos Hour 32.00 3.44 110.004 Sundries LS 3.00 22.50 67.50

TOTAL Rs: 2864.17Add for small Tools and Plants @ 1% Rs: 28.64Add for Contractor' Profit @ 10% Rs: 286.42Add for Contrators' Overheads @ 5% Rs: 143.21

Total cost of Materials Rs: 3322.43

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Air compressor 15 cmm ( ele ) Hour 8.00 86.00 688.00

Fuel / Energy charges Hour 8.00 511.00 4088.002 Pump 10 hp ( ele ) Hour 4.00 4.00 16.00

Fuel / Energy charges Hour 4.00 41.00 164.003 Jack hammer Hour 32.00 11.00 352.00

Fuel / Energy charges Hour 32.00 3.00 96.004 Pusher leg Hour 32.00 6.00 192.00

Fuel / Energy charges Hour 32.00 2.00 64.005 Drilling jumbo Hour 8.00 230.00 1840.00

Fuel / Energy charges Hour 8.00 17.00 136.006 Sundries LS 5.00 22.50 112.50

TOTAL Rs: 7748.50Add for small Tools and Plants @ 1% Rs: 77.49Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 466.05Add for Contrators' Overheads @ 5% Rs: 387.43 Total hire charges of Machinery Rs: 8679.46

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Air compressor Hour 8.00 34.90 279.202 Crew for pump Hour 4.00 15.60 62.403 Crew for Jack hammer Hour 32.00 64.45 2062.404 Crew for Drilling jumbo Hour 8.00 35.10 280.805 Heavy mazdoor Day 2.00 80.90 161.80

TOTAL Rs: 2846.60Add for small Tools and Plants @ 1% Rs: 28.47Add for Contractor' Profit @ 10% Rs: 284.66Add for hidden cost on Labour @ 15% Rs: 426.99Add for additional hidden cost on labour @ 10% Rs: 284.66Add for Contrators' Overheads @ 5% Rs: 142.33

Total cost of Labour Rs: 4013.71

53

Page 55: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

ABSTRACT:A. Cost of Materials Rs: 3322.43B. Hire charges of Machinery Rs: 8679.46C. Cost of Labour Rs: 4013.71

TOTAL Rs: 16015.60Add for Air and Water line @ 1.00% Rs: 160.16Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 256.25Add for Ele sub-station / Demand charges @ 5.00% Rs: 800.78Add for other enabling works @ 2.00% Rs: 320.31 Total cost for 100.00 Rm Rs: 17553.10

Rate per Rm Rs: 175.50

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 20

ITEM: Grouting cement slurry in grout holes under specified pressure for consolidation / contactgrouting including cost of all materials, machinery, labour, redrilling wherever necessary,ventilation,lighting, drainage and other ancillary operations etc., complete with lead upto 1 kmand all lifts.

DATA: In contact zones, perticularly in crown portion, the grout intake will be heavy due to inadequatepacking of concrete during placement of concrete by placer pump. The average grout intake in the contact zone is considered at 75 kg per metre. Beyond contactzone the grout intake may vary from 25 kg per metre to 50 kg per metre depending on theextent of opening of joints in rock during / after excavation.The average gruot intake for consilidation /contact grouting is considered at 50 kg per metre.The average progress of grouting per shift is considered at 1500 kg. Deploy Grout pump with accessories for 8 hours.Deploy Drilling jumbo for 2 hours during grouting of top holes.Deploy 10 hp pump for 2 hours for pumping water to storage tank.Cost of grout hose 50 m @ Rs: 110.00 / Rm Rs: 5500.00Life of grout hose : 800 hoursUse rate of grout hose per hour ( cost / life ) Rs: 6.88Cost of water hose 50 m @ Rs: 110.00 / Rm Rs: 5500.00Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 6.88

RATE ANALYSIS UNIT : 1.50 tonneA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Cement including 1 % wastage tonne 1.52 2900.00 4408.002 Use rate of grouting hose 50 m Hour 8.00 6.88 55.003 Use rate of water hose 50 m Hour 8.00 6.88 55.004 Sundries LS 2.00 22.50 45.00

TOTAL Rs: 4563.00Add for small Tools and Plants @ 1% Rs: 45.63Add for Contractor' Profit @ 10% Rs: 456.30Add for Contrators' Overheads @ 5% Rs: 228.15

Total cost of Materials Rs: 5293.08

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Grouting machine Hour 8.00 16.00 128.00

54

Page 56: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Fuel / Energy charges Hour 8.00 20.00 160.002 Pump 10 hp ( ele ) Hour 2.00 4.00 8.00

Fuel / Energy charges Hour 2.00 41.00 82.003 Drilling jumbo Hour 2.00 230.00 460.00

Fuel / Energy charges Hour 2.00 17.00 34.004 Sundries LS 2.00 22.50 45.00

TOTAL Rs: 917.00Add for small Tools and Plants @ 1% Rs: 9.17Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 32.10Add for Contrators' Overheads @ 5% Rs: 45.85 Total hire charges of Machinery Rs: 1004.12

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Grout pump Hour 8.00 51.55 412.402 Crew for pump Hour 2.00 15.60 31.203 Crew for Drilling jumbo Hour 2.00 35.10 70.204 Heavy mazdoor Day 2.00 80.90 161.80

TOTAL Rs: 675.60Add for small Tools and Plants @ 1% Rs: 6.76Add for Contractor' Profit @ 10% Rs: 67.56Add for hidden cost on Labour @ 15% Rs: 101.34Add for additional hidden cost on labour @ 10% Rs: 67.56Add for Contrators' Overheads @ 5% Rs: 33.78

Total cost of Labour Rs: 952.60

ABSTRACT:A. Cost of Materials Rs: 5293.08B. Hire charges of Machinery Rs: 1004.12C. Cost of Labour Rs: 952.60

TOTAL Rs: 7249.80Add for Air and Water line @ 1.00% Rs: 72.50Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 116.00Add for Ele sub-station / Demand charges @ 5.00% Rs: 362.49Add for other enabling works @ 2.00% Rs: 145.00

Total Rs: 7945.78Add for 1 km rehandling charges :For cement 1.50 tonne @ Rs: 81.30 / tonne Rs: 121.95 Total cost for 1.50 tonne Rs: 8067.73

Rate per tonne Rs: 5378.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 ITEM No: 21

ITEM: Drilling 75 mm diameter drainage holes vertical or inclined in rock / concrete in tunnel bypercussion drilling using waggon drill or other suitable drilling equipment including cost of allmaterials, machinery, labour, ventilation, lighting, drainage etc., complete.

DATA:Generally rate of drilling in rock or concrete inside tunnel will be less compared to drilling inopen area.Rate of drilling by waggon drill in open area : 12 m / hourConsidering about 25 percent reduction in efficiency the hourly progress of drilling by waggon drill will be about 7.5 m considering 50 minutes per hour working.Progress of drilling per shift by one waggon drill is considered at 60 m for analysis.

55

Page 57: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Deploy 1 air compressor 15 cmm and 2 waggon drills for 8 hours.Deploy 10 hp pump for 6 hours for pumping water to storage tank.Progress of drilling per shift for 2 waggon drills : 120 mCost of 75 mm dia T.C cross bit @ Rs: 6200.00 / Each Rs: 6200.00Life of T.C cross bit 75 mm dia in rock : 80 m Use rate of T.C cross bit per m drilling (cost / life) Rs: 77.50Cost of 6 m extn rod with sleeve @ Rs: 1000.00 / Rm Rs: 6000.00Life of extension rods : 1500 mUse rate of 6 m extn rod per m drilling (cost / life) Rs: 4.00Cost of air hose 20 m @ Rs: 120.00 / Rm Rs: 2400.00Life of air hose : 800 hoursUse rate of air hose 20 m per hour (cost / life) Rs: 3.00Cost of water hose 20 m @ Rs: 110.00 Rs: 2200.00Life of water hose : 800 hoursUse rate of water hose 20 m per hour (cost / life) Rs: 2.75

RATE ANALYSIS UNIT: 120.00 RmA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Use rate of cross bit 75 mm dia Rm 120.00 77.50 9300.002 Use rate of air hose 20 m Hour 16.00 3.00 48.003 Use rate of water hose 20 m Hour 16.00 2.75 44.004 Use rate of extension rods Rm 120.00 4.00 480.00

TOTAL Rs: 9872.00Add for small Tools and Plants @ 1% Rs: 98.72Add for Contractor' Profit @ 10% Rs: 987.20Add for Contrators' Overheads @ 5% Rs: 493.60

Total cost of Materials Rs: 11451.52

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Waggon drill Hour 16.00 166.00 2656.00

Fuel / Energy charges Hour 16.00 5.00 80.002 Air compressor 15 cmm ( ele ) Hour 8.00 86.00 688.00

Fuel / Energy charges Hour 8.00 511.00 4088.003 Pump 10 hp ( ele ) Hour 6.00 4.00 24.00

Fuel / Energy charges Hour 6.00 41.00 246.004 Sundries LS 2.00 22.50 45.00

TOTAL Rs: 7827.00Add for small Tools and Plants @ 1% Rs: 78.27Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 445.90Add for Contrators' Overheads @ 5% Rs: 391.35 Total hire charges of Machinery Rs: 8742.52

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Waggon drill Hour 16.00 51.55 824.802 Crew for Air compressor Hour 8.00 34.90 279.203 Crew for Pump Hour 6.00 15.60 93.604 Heavy mazdoor Day 2.00 80.90 161.80

TOTAL Rs: 1359.40Add for small Tools and Plants @ 1% Rs: 13.59

56

Page 58: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Add for Contractor' Profit @ 10% Rs: 135.94Add for hidden cost on Labour @ 15% Rs: 203.91Add for additional hidden cost on labour @ 10% Rs: 135.94Add for Contrators' Overheads @ 5% Rs: 67.97

Total cost of Labour Rs: 1916.75

ABSTRACT:A. Cost of Materials Rs: 11451.52B. Hire charges of Machinery Rs: 8742.52C. Cost of Labour Rs: 1916.75

Total Rs: 22110.79Add for Air and Water line @ 1.00% Rs: 221.11Add for Ventilation @ 0.00% Rs: 0.00Add for Lighting @ 1.60% Rs: 353.77Add for Ele sub-station / Demand charges @ 5.00% Rs: 1105.54Add for other enabling works @ 2.00% Rs: 442.22 Total cost for 120.00 Rm Rs: 24233.43

Rate per Rm Rs: 202.00

57

Page 59: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 Annexure-1

ITEM: Data for percentage provisions towards cost of air and water lines:

DATA:Consider 100 mm dia GI pipe for air line and 80 mm dia GI pipe for water line.For 1 km tunnel consider 1250 m length air line including pipe line from air compressor shedshed to tunnel / adit portal.For 1 km tunnel consider 1500 m length water line including pipe line from pumping point to starage water tank and from storage water tank to tunnel / adit portal.Air and water lines are extended inside the tunnel as the excavation progresses and are dismantled progressively during concreting. Considering 24 months as the construction period for 1 km tunnel the weighted average use of air and water lines will be for 18 months.

a. Cost of 1250 m 100 mm dia pipe @ Rs: 395.00 / Rm Rs: 493750.00Add for fittings / specials / valves etc @ 10% Rs: 49375.00

Total Rs: 543125.00Add for repair / replacements @ 15% Rs: 81468.75

Total cost of air line Rs: 624593.75As the air and water lines are laid in open and are prone to damage due blasting / rock fallsetc., the life of pipes is assumed at 6 years ( 4 uses ) with 20 percent salvage value.Use rate of air line per year ( 0.8 x 624593.75 / 6 ) Rs: 83279.17

b. Cost of 1500 m 80 mm dia pipe @ Rs: 280.00 / Rm Rs: 420000.00Add for fittings / specials / valves etc @ 10% Rs: 42000.00

Total Rs: 462000.00Add for repair / replacements @ 15% Rs: 69300.00

Total cost of air line Rs: 531300.00Use rate of water line per year ( 0.8 x 531300.00 / 6 ) Rs: 70840.00For laying / maintaining / dismantling air and water lines 1 pipe fitter and 2 heavy mazdoors are assumed for 2 years with 50 percent utilisation for air / water lines.

RATE ANALYSIS UNIT: 1000.00 Rm tunnelA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Use rate of 100 mm dia GI pipe Year 1.50 83279.17 124918.752 Use rate of 80 mm dia GI pipe Year 1.50 70840.00 106260.003 Sundries( sealing compound etc ) LS 20.00 22.50 450.00

TOTAL Rs: 231628.75Add for small Tools and Plants @ 1% Rs: 2316.29Add for Contractor' Profit @ 10% Rs: 23162.88Add for Contrators' Overheads @ 5% Rs: 11581.44

Total cost of Materials Rs: 268689.35

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 NIL 0.00 0.00 0.00

0.00 0.00 0.00TOTAL Rs: 0.00

Add for small Tools and Plants @ 1% Rs: 0.00Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 0.00Add for Contrators' Overheads @ 5% Rs: 0.00 Total hire charges of Machinery Rs: 0.00

58

Page 60: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Pipe fitter ( 2 x 12 x 26 x 0.5 x 1 ) Day 312.00 89.20 27830.402 Heavy mazdoor ( 2x12x26 x 0.5 x 2) Day 624.00 80.90 50481.60

TOTAL Rs: 78312.00Add for small Tools and Plants @ 1% Rs: 783.12Add for Contractor' Profit @ 10% Rs: 7831.20Add for hidden cost on Labour @ 15% Rs: 11746.80Add for additional hidden cost on labour @ 10% Rs: 7831.20Add for Contrators' Overheads @ 5% Rs: 3915.60

Total cost of Labour Rs: 110419.92

ABSTRACT:A. Cost of Materials Rs: 268689.35B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 110419.92

Total Rs: 379109.27Cost of air and water lines is chargeable to all items requiring use of water.Approximate basic cost of 1 km tunnel:Excavation ( 1.8 m / Blast ) : 1000 x 36061.60 / 1.8 ( Item - 3 ) 20034223.89Concreting ( 7.7 cum / Rm ) : 1000 x 133250.46 x 7.7 / 48 ( Item - 15 ) 21375595.22All other items at 20 % of cost of excavation and concreting. 8281963.82

Total basic cost / km Rs: 49691782.93Cost of air and water lines as percentage of basic cost of all items : 0.76%

say : 1.00%

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 Annexure-2

ITEM: Data for percentage provisions towards cost of ventilation system :

DATA:Length of ventilation duct 0.78 m dia for 1 km length of tunnel : 900 mGenerally twin fans of 20 hp each are installed at 300 m interval and are run for about 1 hourfor each blast to clear off blasting fumes and dust.Requirement of materials for fabrication of 900 m duct:Plain GI sheet 1 mm thick Class II @ 22.5 kg per Rm : 20250 kgMS angle 30 x 30 x 4 mm for ring @ 2 kg per Rm : 1800 kgMS flats 50 x 4 mm for supporting pipes @ 2 kg per Rm : 1800 kgRivets for joints @ 0.4 kg per Rm : 360 kgGI bolts and nuts for connecting pipes @ 0.25 kg per Rm : 225 kgShalimastic sealing compound for joints @ 0.2 kg per Rm : 180 kgBinding wire @ 0.2 kg per Rm : 180 kgAnchors @ 2.5 m interval for supporting duct & 4 for each fans : : 732 Nos32 mm dia 1 m deep holes for anchors for duct & fans : 732 m20 mm dia 1.2 m long rods for anchors & 2 m long rods for fans : : 2250 kgResin bond cement capsules for fixing anchors : 750 NosCost of drilling 32 mm dia. hole ( Item 19 ) per Rm Rs: 175.50

RATE ANALYSIS FOR COST OF DUCT UNIT: 900.00 RmA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Plain GI sheet kg 20250.00 32.00 648000.002 MS angle 30 x 30 x 5 mm kg 1800.00 20.00 36000.003 MS flats kg 1800.00 24.00 43200.00

59

Page 61: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

4 Rivets kg 360.00 45.00 16200.005 GI bolts and nuts kg 225.00 55.00 12375.006 Sundries ( gas / electrodes etc ) LS 50.00 22.50 1125.00

TOTAL Rs: 756900.00Add for small Tools and Plants @ 1% Rs: 7569.00Add for Contractor' Profit @ 10% Rs: 75690.00Add for Contrators' Overheads @ 5% Rs: 37845.00

Total cost of Materials Rs: 878004.00

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Bending machine Hour 360.00 31.00 11160.00

Fuel / Energy charges Hour 360.00 61.00 21960.002 Sundries ( welding / drilling etc ) LS 50.00 22.50 1125.00

TOTAL Rs: 34245.00Add for small Tools and Plants @ 1% Rs: 342.45Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 2308.50Add for Contrators' Overheads @ 5% Rs: 1712.25 Total hire charges of Machinery Rs: 38608.20

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Fabricator @ 0.1 / Rm Day 90.00 93.70 8433.002 Gas cutter / Welder @ 0.1 / Rm Day 90.00 89.70 8073.003 Helper fabricator @ 0.2 / Rm Day 180.00 81.60 14688.004 Tinsmith @ 0.2 / Rm Day 180.00 81.65 14697.005 Heavy mazdoor @ 0.2 / Rm Day 180.00 80.90 14562.00

TOTAL Rs: 60453.00Add for small Tools and Plants @ 1% Rs: 604.53Add for Contractor' Profit @ 10% Rs: 6045.30Add for hidden cost on Labour @ 15% Rs: 9067.95Add for additional hidden cost on labour @ 10% Rs: 6045.30Add for Contrators' Overheads @ 5% Rs: 3022.65

Total cost of Labour Rs: 85238.73

ABSTRACT:A. Cost of Materials Rs: 878004.00B. Hire charges of Machinery Rs: 38608.20C. Cost of Labour Rs: 85238.73 Total cost for 900.00 Rm Rs: 1001850.93

ERECTION / DISMANTLING OF DUCT & FANS: UNIT: 900.00 RmA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Shalimastic sealing compound kg 180.00 53.00 9540.002 20 mm dia steel for anchors kg 2250.00 18.00 40500.003 Resin bond cement capsule Nos 750.00 24.00 18000.004 Binding wire kg 180.00 5.00 900.005 Sundries LS 25.00 22.50 562.50

TOTAL Rs: 69502.50Add for small Tools and Plants @ 1% Rs: 695.03Add for Contractor' Profit @ 10% Rs: 6950.25

60

Page 62: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Add for Contrators' Overheads @ 5% Rs: 3475.13Add for drilling holes 732 m @ Rs: 175.50 / Rm Rs: 128466.00

Total cost of Materials Rs: 209088.90

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Drilling jumbo Hour 480.00 230.00 110400.00

Fuel / Energy charges Hour 480.00 17.00 8160.002 Tipper Hour 60.00 240.00 14400.00

Fuel / Energy charges Hour 60.00 117.00 7020.003 Sundries LS 25.00 22.50 562.50

TOTAL Rs: 140542.50Add for small Tools and Plants @ 1% Rs: 1405.43Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 1574.25Add for Contrators' Overheads @ 5% Rs: 7027.13 Total hire charges of Machinery Rs: 150549.30

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 For erection of duct & fans:

Crew for Drilling jumbo Hour 240.00 35.10 8424.00Crew for Tipper Hour 30.00 32.90 987.00Bar bender Day 30.00 94.15 2824.50Erector @ 30 m / day Day 30.00 93.70 2811.00Helper erection Day 60.00 81.60 4896.00Khalasis Day 60.00 83.65 5019.00Heavy mazdoor Day 70.00 80.90 5663.00

2 For dismantling of duct & fans:Crew for Drilling jumbo Hour 240.00 35.10 8424.00Crew for Tipper Hour 30.00 32.90 987.00Erector @ 60 m / day Day 30.00 93.70 2811.00Helper erection Day 60.00 81.60 4896.00Khalasis Day 60.00 83.65 5019.00Heavy mazdoor Day 70.00 80.90 5663.00

TOTAL Rs: 58424.50Add for small Tools and Plants @ 1% Rs: 584.25Add for Contractor' Profit @ 10% Rs: 5842.45Add for hidden cost on Labour @ 15% Rs: 8763.68Add for additional hidden cost on labour @ 10% Rs: 5842.45Add for Contrators' Overheads @ 5% Rs: 2921.23

Total cost of Labour Rs: 82378.55

ABSTRACT:A. Cost of Materials Rs: 209088.90B. Hire charges of Machinery Rs: 150549.30C. Cost of Labour Rs: 82378.55 Total cost for 900.00 Rm Rs: 442016.75

ABSTRACT FOR COST OF VENTILATION SYSTEM:Cost of ventilation duct 900 m length Rs: 1001850.93Deduct salvage value of duct @ 10% Rs: -100185.09

Total Rs: 901665.84

61

Page 63: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Use rate of duct per use assuming 2 uses Rs: 450832.92Erection & dismantling of duct & fans Rs: 442016.75

Total Rs: 892849.66Add for maintenance & replacements @ 5% Rs: 44642.48Total cost of ventilation system for 1000 m tunnel Rs: 937492.15Cost of ventilation system /blast of 1.80 m length ( 49 cum ) Rs: 1687.49 ( excluding hire charges of fans )Entire cost of ventilation system is chargeable to excavation item as the requirement of defuming the tunnel for other activities is negligible.Basic cost of excavation per blast ( 49 cum ) as per item-3 Rs: 36061.60Cost of ventilation system ( excluding hire charges of fans ) as percentage of basic cost of excavation : 4.68%

say : 4.50%

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 Annexure-3

ITEM: Data for percentage provisions towards cost of Electric sub-station & Demand charges:

DATA:Estimation of electric power load for sub-station:Aggregate crushing plant 1 No. : 30 hpBatching & mixing plant 1 No. : 40 hpVibrators 2 Nos. : 6 hpAir compressor 15 cmm 1 No. : 150 hpAir compressor 8.5 cmm 1 No. : 75 hpWater supply / Dewatering pumps : 50 hpConvey mucker 1 No. : 60 hpVentilation fans : 60 hpFabrication / Repair / Maintenance units : 20 hpMajor electric power consuming equipment is 15 cmm capacity air compressor.Air compressor 15 cmm 1 No. : 150 hpOther equipments running simultaneously:Aggregate crushing plant 1 No. : 30 hpWater supply / Dewatering pumps : 30 hpFabrication / Repair / Maintenance units : 20 hp

Total : 230 hpRequirement of power in Kw 230 x 0.746 : 171.58 kwAdd for lighting & miscellaneous requirements : 10.00 kwAdd for reserve capacity @ 10 % : 17.16 kw

Total ( say ): 200.00 kwCapacity of sub-station required 200 / 0.85 : 250 KVADemand for power requirement is assumed to vary from 250 KVA to 150 KVA duringconstruction period of about 3 years.Average demand for electric power for 3 years is considered @. : : 200 KVAConsider 2 Transformers of 250 KVA including 1 spare unit.Capital cost of other sub-station equipments & distribution lines:HT / LT Circuit breaker 2 Nos @ Rs: 25000.00 Rs: 50000.00Poles with fixtures 30 Nos @ Rs: 2500.00 Rs: 75000.00HT / LT Line conductor 5 km @ Rs: 19000.00 Rs: 95000.00Controls and Miscellaneous LS Rs: 28125.00

Total Rs: 248125.00Life of sub-station equipments : 15 yearsSalvage value : 10 percentAverage capital cost 248125.00 x ( 15+1 ) / 30 Rs: 132333.33

62

Page 64: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Hire charges of sub-station equipments:Depreciation per year 248125.00 x 0.9 / 15 Rs: 14887.50Maintenance & repairs @ 25 % of depreciation Rs: 3721.88Miscellaneous charges @ 10 % of repair charges Rs: 372.19Interest on av. Capital cost @ 13 % Rs: 17203.33

Total hire charges / year Rs: 36184.90Cables & Fittings:PVC armoured cable 70 sqmm 100 m @ Rs: 250.00 / Rm Rs: 25000.00PVC armoured cable 25 sqmm 100 m @ Rs: 110.00 / Rm Rs: 11000.00PVC armoured cable 16 sqmm 1250 m @ Rs: 75.00 / Rm Rs: 93750.00PVC arm.cable 10 sqmm & below 2000 m @ Rs: 25.00 / Rm Rs: 50000.00Miscellaneous fittings LS Rs: 5625.00

Total Rs: 185375.00Assume use of cables for 3 years with 50 percent salvage value.Use rate of cables per year with 50 % salvage value Rs: 30895.83

RATE ANALYSIS UNIT: 1000.00 RmA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Use rate of cables Year 3.00 30895.83 92687.502 Anchors / supports for cables / lights LS 150.00 22.50 3375.003 Sundries ( tapes & consumeables ) LS 50.00 22.50 1125.00

TOTAL Rs: 97187.50Add for small Tools and Plants @ 1% Rs: 971.88Add for Contractor' Profit @ 10% Rs: 9718.75Add for Contrators' Overheads @ 5% Rs: 4859.38

Total cost of Materials Rs: 112737.50

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Sub-station equipments Year 3.00 36184.90 108554.692 Transformer 250 KVA 2 Nos. Month 72.00 1916.00 137952.003 Demand charges for 3 years for 200 kVA

@ 85 % PF ( 200 x 3 x 12 x 0.85 ) KVA 6120.00 200.00 1224000.004 Sundries LS 50.00 22.50 1125.00

TOTAL Rs: 1471631.69Add for small Tools and Plants @ 1% Rs: 14716.32Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 122512.50Add for Contrators' Overheads @ 5% Rs: 73581.58 Total hire charges of Machinery Rs: 1682442.09

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Lineman 2 Nos. x 3 x 12 x 26 days Day 1872.00 81.60 152755.202 Electrician 2 Nos. x 3 x 12 x 26 days Day 1872.00 82.65 154720.803 Heavy mazdoor 2 Nos x 3 x 12 x 26 days Day 1872.00 80.90 151444.80

TOTAL Rs: 458920.80Add for small Tools and Plants @ 1% Rs: 4589.21Add for Contractor' Profit @ 10% Rs: 45892.08Add for hidden cost on Labour @ 15% Rs: 68838.12

63

Page 65: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Add for additional hidden cost on labour @ 10% Rs: 45892.08Add for Contrators' Overheads @ 5% Rs: 22946.04

Total cost of Labour Rs: Rs: 647078.33ABSTRACT:A. Cost of Materials Rs: 112737.50B. Hire charges of Machinery Rs: 1682442.09C. Cost of Labour Rs: 647078.33 Total cost for 1000.00 Rm Rs: 2442257.92Cost of electric sub-station and distribution lines is chargeable to all items as except transportequipments all other equipments are operated using electric power.Approximate basic cost of 1 km tunnel:Excavation ( 1.8 m / Blast ) - 1000 x 36061.60 / 1.8 ( Item - 3 ) 20034223.89Concreting ( 7.7 cum / Rm ) - 1000 x 133250.46 x 7.7 / 48 ( Item - 15 ) 21375595.22All other items @ 20 % of excavation and concreting. 8281963.82

Total basic cost / km Rs: 49691782.93Cost of electric sub-station and distribution lines ( excluding energy charges ) as percentage of basic cost of all items : 4.91%

say : 5.00%

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 Annexure-4

ITEM: Data for percentage provisions towards cost of Lighting :

DATA:Lighting facilities are to be provided inside the tunnel round the clock till completion.Provision of flood lights near work areas and tube lights at other locations is assumed.Fluorescent tube lights are assumed at 30 m interval inside tunnel.Number of tube lights inside tunnel assuming 900 m length requires lighting : 30 Nos.Number of hours of use and energy requirement for 1 year during excavation for average 50percent sets utilisation and 24 hours use ( since the lights are installed progressively as thetunnel excavation advances ) :Number of hours of usage ( 0.5 x 30 x 24 x 360 ) : 129600.00Energy requirement in Kwhr ( 0.5 x 30 x 22 x 360 x 40 / 1000 ) : : 4252.00Number of hours of use and energy requirement for 2 year during other works for 75 percentsets utilisation and 24 hrs use:Number of hours of usage ( 0.75 x 30 x 24 x 360 x 2 ) : 388800.00Energy requirement in Kwhr ( 0.75 x 30 x 22 x 360 x 2 x 40 / 1000 ) : 14256.00Number of tube lights for approach / BP / Crusher / Material yard etc (say) : 20 Nos.Number of hours of use and energy requirement for 3 year during night time for 75 percent sets utilisation and 12 hours use:Number of hours of usage ( 0.75 x 20 x 12 x 360 x 3 ) : 97200.00Energy requirement in Kwhr ( 0.75 x 20 x 11 x 360 x 3 x 40 / 1000 ) : 3564.00Number of flood lights inside tunnel : : 3 Nos.Number of hours of use and energy requirement for 3 year for 100 percent sets utilisation and average 16 hours use daily:Number of hours of usage ( 3 x 16 x 360 x 3 ) : 51840.00Energy requirement in Kwhr ( 3 x 15 x 360 x 3 x 500 / 1000 ) : : 24300.00Number of flood lights for BP / Crusher / Switch yards etc (say) : 4 NosNumber of hours of use and energy requirement for 3 year during night time for 100 percent sets utilisation and 11 hrs use:Number of hours of usage ( 4 x 12 x 360 x 3 ) : 51840.00Energy requirement in Kwhr ( 4 x 11 x 360 x 3 x 500 / 1000 ) : : 23760.00Flood / Tube light fittings:Flood light sets 7 Nos @ Rs: 1050.00 / set Rs: 7350.00Tube light set inside tunnel 30 Nos @ Rs: 195.00 / set Rs: 5850.00

64

Page 66: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Tube light set outside tunnel 20 Nos@Rs: 195.00 / set Rs: 3900.00Accessories for light fittings / repairs / replacements etc LS Rs: 3375.00

Total Rs: 20475.00Assume use of light fittings for 3 years with 50 percent salvage value.Use rate of light fittings per year with 50 % salvage value Rs: 3412.50 ( 20475.00 x 0.5 / 3 )Cost of flood lights 500 W @ Rs: 250.00 / No. Rs: 250.00Life of flood light in hours : 1500.00Use rate of flood lights per hour ( cost / life ) Rs: 0.17Cost of tube lights 40 W @ Rs: 47.00 / No. Rs: 47.00Life of fluorescent tube light in hours : 1500.00Use rate of tube lights per hour ( cost / life ) Rs: 0.03Running of 30 KVA DG set with 50 percent utilisation for tunnel lighting is assumed for 2 hours running daily to ensure lighting for tunnel works during break down of main power supply frompower supply grid.

RATE ANALYSIS UNIT: 1000.00 RmA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Use rate of flood/ tube light sets Year 3.00 3412.50 10237.502 Use rate of flood lights Hour 103680.00 0.17 17280.00

Energy charges Kwhr 48060.00 4.57 219634.203 Use rate of fluorescent tubes Hour 712800.00 0.03 22334.40

Energy charges Kwhr 27436.00 4.57 125382.524 Sundries ( tapes & starter etc ) LS 50.00 22.50 1125.00

TOTAL Rs: 395993.62Add for small Tools and Plants @ 1% Rs: 3959.94Add for Contractor' Profit @ 10% Rs: 39599.36Add for Contrators' Overheads @ 5% Rs: 19799.68

Total cost of Materials Rs: 459352.60

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 DG set 30 KVA @ 50 % for lighting Hour 1920.00 23.00 44160.00

Fuel / Energy charges Hour 1920.00 124.00 238080.002 Sundries LS 50.00 22.50 1125.00

TOTAL Rs: 283365.00Add for small Tools and Plants @ 1% Rs: 2833.65Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 23920.50Add for Contrators' Overheads @ 5% Rs: 14168.25 Total hire charges of Machinery Rs: 324287.40

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for DG set Day 1920.00 13.10 25152.00

( 50 % for tunnel lighting ) 0.00 0.00 0.00TOTAL Rs: 25152.00

Add for small Tools and Plants @ 1% Rs: 251.52Add for Contractor' Profit @ 10% Rs: 2515.20Add for hidden cost on Labour @ 15% Rs: 3772.80

65

Page 67: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Add for additional hidden cost on labour @ 10% Rs: 2515.20Add for Contrators' Overheads @ 5% Rs: 1257.60

Total cost of Labour Rs: 35464.32

ABSTRACT:A. Cost of Materials Rs: 459352.60B. Hire charges of Machinery Rs: 324287.40C. Cost of Labour Rs: 35464.32 Total cost for 1000.00 Rm Rs: 819104.32Cost of lighting work area inside and outside tunnel is chargeable to all items.Approximate basic cost of 1 km tunnel as per data in Annexure-3: Rs: 49691783Cost of lighting tunnel including energy chargesas percentage of basic cost cost of all items works : 1.65%

say : 1.60%

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2003-2004 Annexure-5

ITEM: Additional rate for mucking through vertical / inclined shaft :

DATA: A . Cost of disposal of muck using convey mucker for loading and dumper for conveying through approach channel / adit.All data same as in Item - 3.

RATE ANALYSIS UNIT : 49.00 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 NIL 0.00 0.00 0.00

0.00 0.00 0.00TOTAL Rs: 0.00

Add for small Tools and Plants @ 1% Rs: 0.00Add for Contractor' Profit @ 10% Rs: 0.00Add for Contrators' Overheads @ 5% Rs: 0.00

Total cost of Materials Rs: 0.00

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Convey mucker Hour 6.00 552.00 3312.00

Fuel / Energy charges Hour 6.00 142.00 852.002 Dumper ( 2 x 6 hrs ) Hour 12.00 352.00 4224.00

Fuel / Energy charges Hour 12.00 156.00 1872.00TOTAL Rs: 10260.00

Add for small Tools and Plants @ 1% Rs: 102.60Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 272.40Add for Contrators' Overheads @ 5% Rs: 513.00 Total hire charges of Machinery Rs: 11148.00

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Convey mucker Hour 6.00 34.90 209.402 Crew for Dumper Hour 12.00 42.10 505.203 Khalasi

for mucking shift 2 Nos. Day 2.00 83.65 167.30

66

Page 68: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

4 Heavy mazdoorfor mucking shift 8 Nos. Day 8.00 80.90 647.20

TOTAL Rs: 1529.10Add for small Tools and Plants @ 1% Rs: 15.29Add for Contractor' Profit @ 10% Rs: 152.91Add for hidden cost on Labour @ 15% Rs: 229.37Add for additional hidden cost on labour @ 10% Rs: 152.91Add for Contrators' Overheads @ 5% Rs: 76.46

Total cost of Labour Rs: 2156.03

ABSTRACT:A. Cost of Materials Rs: 0.00B. Hire charges of Machinery Rs: 11148.00C. Cost of Labour Rs: 2156.03

Total Rs: 13304.03Add for Air and Water line @ 1.00% Rs: 133.04Add for Ventilation @ 5.00% Rs: 665.20Add for Lighting @ 1.50% Rs: 199.56Add for Ele sub-station / Demand charges @ 5.00% Rs: 665.20Add for other Enabling works @ 2.00% Rs: 266.08 Total cost for 49.00 cum Rs: 15233.12

Rate per cum Rs: 311.00

B. Cost of disposal of muck using convey mucker for loading and loco with tipping tub forconveying through vertical / inclined shaft.All data same as in Item - 3 except mode of disposal of muck.Winch and tipping tubs are considered for mucking through shaft.Movement of tubs on the rail track can be by manual labour or by deploying loco.Use of diesel loco inside tunnel and manual haulage outside tunnel assumed.Quantity of muck to be disposed per blast ( Item - 3 ) : 73 cumCycle time for disposal of muck by winch :Aligning & hooking tub : 0.50 minLifting by winch @ 15 m / minute for 75 m : 5.00 minDehooking & aligning loaded tub on outside track : 1.00 munHooking / Lowering / Dehooking / aligning empty tub on inside track : 5.50 min

Say : 12.00 minQuantity of muck per tipping tub : 1.50 cumTime require for mucking 73 cum ( 73 x 12 / 1.50 / 60 ) Say : 10 hoursDeploy loco & 8 mucking tubs for 10 hours.Deploy winch for 12 hours including use for movement of work force.Quantity of rails for haulage of tubs Main track inside tunnel : 2 x 1000 m

Siding near shaft : 2 x 50 mSiding near excavation face : 2 x 50 mHaulage track outside : 2 x 150 mTotal length of rails : 2500 m

Weigth of 30R rails 2500 m length @ 30 kg / Rm : 75 tonnesCost of 30 R rails 2500 m @ Rs: 24500.00 / tonne Rs: 1837500.00Add for fixtures @ 25 % Rs: 459375.00

Total Rs: 2296875.00Life of rails under tunnel working conditions : 15 yearsUse rate of rails per year with 10 % salvage value Rs: 137812.50Add for repairs & replacement @ 10 % Rs: 13781.25

Total Rs: 151593.75Use rate of rails per shift considering 300 working days Rs: 505.31

67

Page 69: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

Consider use of loco track for 12 hours.Length of 16 mm dia wire rope for winch assuming 75 m deep shaft : : 100 mCost of wire rope 150 m length @ Rs: 150.00 / Rm Rs: 22500.00Life of wire rope for lifting : 2500 hoursUse rate of wire rope per hour ( cost / life ) Rs: 9.00

RATE ANALYSIS UNIT : 49.00 cumA. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount

in Rs. in Rs.1 Use rate of rails Shift 1.50 505.31 757.972 Use rate of wire rope for winch Hour 12.00 9.00 108.003 Sundries LS 1.00 22.50 22.50

TOTAL Rs: 888.47Add for small Tools and Plants @ 1% Rs: 8.88Add for Contractor' Profit @ 10% Rs: 88.85Add for Contrators' Overheads @ 5% Rs: 44.42

Total cost of Materials Rs: 1030.62

B. MACHINERY: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Loco 45 hp Hour 10.00 182.00 1820.00

Fuel / Energy charges Hour 10.00 209.00 2090.002 35 hp Winch Hour 12.00 77.00 924.00

Fuel / Energy charges Hour 12.00 100.00 1200.003 Mucking tub 1.5 cum Hour 80.00 24.00 1920.00

Fuel / Energy charges Hour 80.00 5.00 400.004 Sundries LS 1.00 22.50 22.50

TOTAL Rs: 8376.50Add for small Tools and Plants @ 1% Rs: 83.77Add for Contractor' Profit on DPOL/ Energy @ 10% Rs: 371.25Add for Contrators' Overheads @ 5% Rs: 418.83 Total hire charges of Machinery Rs: 9250.34

C. LABOUR: Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for loco Hour 10.00 32.90 329.002 Crew for Winch Hour 12.00 52.65 631.803 Foreman Day 2.00 108.65 217.304 Khalasi

for mucking Day 4.00 83.65 334.605 Heavy mazdoor

for mucking Day 12.00 80.90 970.80for hauling & unloading outside Day 8.00 80.90 647.20for signalling & miscellaneous Day 8.00 80.90 647.20

TOTAL Rs: 3777.90Add for small Tools and Plants @ 1% Rs: 37.78Add for Contractor' Profit @ 10% Rs: 377.79Add for hidden cost on Labour @ 15% Rs: 566.69Add for additional hidden cost on labour @ 10% Rs: 377.79Add for Contractor' Overheads @ 5% Rs: 188.90Add for laying & dismantling loco track @ 15% Rs: 566.69

Total cost of Labour Rs: 5893.52

68

Page 70: SCHEDULE OF RATES - Karwaterresources.kar.nic.in/scheduleofrates/Tunnel-1-21.pdf · only between quarry/ source of supply and batching plant / fabrication site. Further conveyance

TUNNEL AND ALLIED WORKS

ABSTRACT:A. Cost of Materials Rs: 1030.62B. Hire charges of Machinery Rs: 9250.34C. Cost of Labour Rs: 5893.52

Total Rs: 16174.49Add for Air and Water line @ 1.00% Rs: 161.74Add for Ventilation @ 5.00% Rs: 808.72Add for Lighting @ 1.50% Rs: 242.62Add for Ele sub-station / Demand charges @ 5.00% Rs: 808.72Add for other Enabling works @ 2.00% Rs: 323.49 Total cost for 49.00 cum Rs: 18519.79

Rate per cum Rs: 378.00Additional cost for mucking through shaft per cum ( A - B ) Rs: 67.00Basic rate for excavation / cum for use of dumpers ( Item-3 ) Rs: 847.00

Extra rate as percentage of basic rate for mucking through shaft : 7.91% say : 8.00%