  • 8/17/2019 Sched Logasd

    1/34

    Scheduling/Leveling Report - 11-May-16 - PM.exe===============================================

    Default Project..................................................UP#30-2

    Projects:UP#30-2.........................................................

    .Completion Plan 5 August 2015 Rev 02 (Update -06 May 2016)

    Scheduling/Leveling Settings:-----------------------------

    General-------Scheduling ......................................................YesLeveling ........................................................NoIgnore relationships to and from other projects .................NoMake open-ended activities critical .............................NoUse Expected Finish Dates .......................................YesSchedule automatically when a change affects dates ..............NoLevel resources during scheduling ...............................NoRecalculate assignment costs after scheduling ...................NoWhen scheduling progressed activities use .......................Retaine

    d LogicCalculate start-to-start lag from ...............................Early S

    tart Define critical activities as ...................................Longest Path

    Compute Total Float As ..........................................FinishFloat

    Calculate float based on finish date of .........................Each project

    Calendar for scheduling Relationship Lag ........................Predecessor Activity Calendar

    Advanced--------Calculate multiple float paths...................................Yes

    Calculate multiple float paths using.............................Free FloatNumber of paths to calculate.....................................10

    Statistics:-----------

    # Projects.......................................................1# Activities.....................................................833# Not Started....................................................301# In Progress....................................................72# Completed......................................................460# Relationships..................................................1197# Activities with Constraint.....................................27

    Project: UP#30-2 Activity: GEN0001020 ReceiveInstruction from ADAC to procure additional MJF Pipe fittings & Valves

    Project: UP#30-2 Activity: GEN0001030 Stage 1Completion

    Project: UP#30-2 Activity: GEN0001040 Stage 2Completion

    Project: UP#30-2 Activity: GEN0001050 Stage 3Completion

    Project: UP#30-2 Activity: GEN0001060 Stage 4Completion

  • 8/17/2019 Sched Logasd

    2/34

    Project: UP#30-2 Activity: GEN0001110 Access to Area (For Remaining Fire Fighting Work)

    Project: UP#30-2 Activity: GEN0001120 Access in Fuel Farm Control Room

    Project: UP#30-2 Activity: GEN0001160 Approval of VO 37

    Project: UP#30-2 Activity: GEN0001180 Road diversion by HLG to its final position

    Project: UP#30-2 Activity: GEN0001200 Availability of Fuel Farm (Installation of instruments)

    Project: UP#30-2 Activity: GEN0001210 Availability of Fuel in Fuel Farm

    Project: UP#30-2 Activity: SEC2S11620 Access to Runways

    Project: UP#30-2 Activity: SEC2S22420 Access to SS 1164

    Project: UP#30-2 Activity: SEC2S22430 Cable Duct Civil Work Completion Section 2

    Project: UP#30-2 Activity: SEC2S22460 Cable Duct Civil Works Completion Section 3

    Project: UP#30-2 Activity: SEC2S22490 Cable Duct Civil Works Completion Section 4

    Project: UP#30-2 Activity: SEC2S22510 Cable Duct Civil Work Completion (New Aprons)

    Project: UP#30-2 Activity: SEC2S22540 Cable Duct Civil Work Completion Section 1Project: UP#30-2 Activity: SEC2S22560 Cable Du

    ct Civil Work Completion (VO)Project: UP#30-2 Activity: SEC2S22590 Cable Du

    ct Civil Work Completion Section 5Project: UP#30-2 Activity: SEC2S22620 Cable Du

    ct Civil Work Completion Section 6Project: UP#30-2 Activity: SEC2S22640 Cable Du

    ct Civil Work Completion Section 7Project: UP#30-2 Activity: SEC2S31000 CH101A -

     Trench Civil Work CompletionProject: UP#30-2 Activity: SEC2S31250 CH156 -

    Trench Civil Work CompletionProject: UP#30-2 Activity: SEC2S31550 CH155 -Trench Civil Work Completion

    Project: UP#30-2 Activity: SEC2S32430 Fuel Farm and Control Room Availability

    Project: UP#30-2 Activity: SEC2S41000 Fuel Farm Availability

    Errors:-------Warnings:---------

    Activities without predecessors..................................1

    Project: UP#30-2 Activity: GEN0001000 ProjectStart

    Activities without successors....................................1Project: UP#30-2 Activity: GEN0001060 Stage 4

    Completion

    Out-of-sequence activities.......................................63Project: UP#30-2 Activity: ASBULT1000 Submissi

    on of As Built Drawing for Storm water works

  • 8/17/2019 Sched Logasd

    3/34

    Project: UP#30-2 Activity: ASBULT1020 Submission of As Built Drawing for Electrical works

    Project: UP#30-2 Activity: ASBULT1040 Submission of As Built Drawing for Fire Fighting works

    Project: UP#30-2 Activity: ASBULT1060 Submission of As Built Drawing for AGL works

    Project: UP#30-2 Activity: ASBULT1120 Submission of As Built Drawing for Aprons - Concrete Pavement

    Project: UP#30-2 Activity: ASBULT1140 Submission of As Built Drawing for Substations

    Project: UP#30-2 Activity: ASBULT1150 Approval of As Built Drawing for Substations

    Project: UP#30-2 Activity: ASBULT1160 Submission of As Built Drawing for Air Side Road A3

    Project: UP#30-2 Activity: ASBULT1170 Approval of As Built Drawing for Air Side Road A3

    Project: UP#30-2 Activity: ASBULT1200 Submission of As Built Drawing for Taxi ways - Asphalt works

    Project: UP#30-2 Activity: ASBULT1210 Approval  of As Built Drawing for Taxi ways - Asphalt works

    Project: UP#30-2 Activity: GEN0001220 ProjectNOCs

    Project: UP#30-2 Activity: O&MMNL1000 Opeartion and Maintanance Manual for AGL Network - Submission

    Project: UP#30-2 Activity: O&MMNL1010 Opeartion and Maintanance Manual for AGL Network - ApprovalProject: UP#30-2 Activity: SEC2S11310 ADAC AGL

     Inspection and Handoover -AGL SSProject: UP#30-2 Activity: SEC2S11580 Installa

    tion of Traffic Signal SystemProject: UP#30-2 Activity: SEC2S11890 Snagging

     and Desnagging - Taxiway D (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S12020 Snagging

     and Desnagging - Connecting TaxiwayProject: UP#30-2 Activity: SEC2S21090 Sand sur

    round - New Apron LoopProject: UP#30-2 Activity: SEC2S21120 Final ba

    ckfilling - New Apron LoopProject: UP#30-2 Activity: SEC2S21630 CH155 -Top slab installation

    Project: UP#30-2 Activity: SEC2S21780 CH101A - Internal finishing

    Project: UP#30-2 Activity: SEC2S21900 Leak detection pipe installation - West End (CH101A)

    Project: UP#30-2 Activity: SEC2S22150 CH-143 - Torquing of Bolts/Nuts

    Project: UP#30-2 Activity: SEC2S22270 HPV-36,HPV-37 & HPV-38 - Installation

    Project: UP#30-2 Activity: SEC2S22290 Tie-In Works to CH-22

    Project: UP#30-2 Activity: SEC2S22500 E&I Cable Laying in Section 4 (Main Cables)

    Project: UP#30-2 Activity: SEC2S22630 E&I Cable Laying in Section 6 (Main Cables)

    Project: UP#30-2 Activity: SEC2S22650 E&I Cable Laying in Section 7

    Project: UP#30-2 Activity: SEC2S22910 Nitrogen Purging Loop 5.1 & 5.2 - T&C Preparation All HPs/LPs

    Project: UP#30-2 Activity: SEC2S22950 Nitrogen Purging Loop 5.1 & 5.2 - Pneumatic, Air Blowing & Drying - Loop 5.2

  • 8/17/2019 Sched Logasd

    4/34

    Project: UP#30-2 Activity: SEC2S22980 Nitrogen Purging Loop 2.1 & 2.2 - CH-133 T&C Spools Instln RRC

    Project: UP#30-2 Activity: SEC2S22990 Nitrogen Purging Loop 2.1 & 2.2 - Pneumatic, Air Blowing & Drying - Loop 2.1

    Project: UP#30-2 Activity: SEC2S23010 Nitrogen Purging Loop 2.1 & 2.2 - Pneumatic, Air Blowing & Drying - Loop 2.2

    Project: UP#30-2 Activity: SEC2S31400 CH156 -24" Spool Preparation

    Project: UP#30-2 Activity: SEC2S31420 CH156 -RT Works

    Project: UP#30-2 Activity: SEC2S31430 CH156 -Drain & Vent Installation

    Project: UP#30-2 Activity: SEC2S31470 CH156 -Platform Installation

    Project: UP#30-2 Activity: SEC2S31590 CH155 -24" Pipe Welding

    Project: UP#30-2 Activity: SEC2S31680 CH155 -24" Spool Preparation

    Project: UP#30-2 Activity: SEC2S31700 CH155 -RT Works

    Project: UP#30-2 Activity: SEC2S31710 CH155 -Drain & Vent Installation

    Project: UP#30-2 Activity: SEC2S31750 CH155 -Platform Installation

    Project: UP#30-2 Activity: SEC2S31940 CH154 -Assembly of Flanges with DBB ValvesProject: UP#30-2 Activity: SEC2S32010 CH154 -

    24" Welding WorksProject: UP#30-2 Activity: VO20 DVOR Monitor Ant

    enna RelocationProject: UP#30-2 Activity: VO33 MJF - Security G

    ate ObstructionProject: UP#30-2 Activity: VO35 MART AGL Primary

     Cable JointsProject: UP#30-2 Activity: VO37 AJF/MJF Interfac

    eProject: UP#30-2 Activity: VO38 MJF Hydrant Cont

    rol Work Pk. 1 Project: UP#30-2 Activity: VO40 B2 Road Underpass Fence Removal

    Project: UP#30-2 Activity: VO43 Surface Protection Omission

    Project: UP#30-2 Activity: VO48 MV & FOC Modifications

    Project: UP#30-2 Activity: VO50 Taxiway F4 Remarking

    Project: UP#30-2 Activity: VO53 Cargo Stands Barriers

    Project: UP#30-2 Activity: VO55 Foreman DayworksProject: UP#30-2 Activity: VO63 Barrier Preparat

    ion for HLGProject: UP#30-2 Activity: VO69 Stop Bar TWY C (

    Near TWY H)Project: UP#30-2 Activity: VO76 FATO Additional

    DesignProject: UP#30-2 Activity: VO85 AGL Primary Cabl

    e Laying ConstraintsProject: UP#30-2 Activity: VO87 Taxiway D6 AGL R

    eroutingProject: UP#30-2 Activity: VO90-1 Optional Items D

  • 8/17/2019 Sched Logasd

    5/34

    escopeProject: UP#30-2 Activity: VO92 Stop bar at Taxi

    way D

    Activities with Actual Dates > Data Date.........................5Project: UP#30-2 Activity: VO06 FATO RelocationProject: UP#30-2 Activity: VO06-1 FATO RelocationProject: UP#30-2 Activity: VO14-1 MART MJF Redesig

    nProject: UP#30-2 Activity: VO14-2 MART MJF Redesig

    nProject: UP#30-2 Activity: VO28 Fire Main Tie -

    in Points

    Milestone Activities with invalid relationships..................0

    Finish milestone and predecessors have different calendars.......43Project: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    Completion Project: UP#30-2 Activity: GEN0001030 Stage 1Completion

    Project: UP#30-2 Activity: GEN0001030 Stage 1Completion

    Project: UP#30-2 Activity: GEN0001030 Stage 1Completion

    Project: UP#30-2 Activity: GEN0001030 Stage 1Completion

    Project: UP#30-2 Activity: GEN0001030 Stage 1Completion

    Project: UP#30-2 Activity: GEN0001030 Stage 1Completion

    Project: UP#30-2 Activity: GEN0001030 Stage 1CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

  • 8/17/2019 Sched Logasd

    6/34

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

    CompletionProject: UP#30-2 Activity: GEN0001050 Stage 3

    CompletionProject: UP#30-2 Activity: GEN0001050 Stage 3

    CompletionProject: UP#30-2 Activity: GEN0001060 Stage 4

    CompletionProject: UP#30-2 Activity: GEN0001060 Stage 4

    Completion Project: UP#30-2 Activity: GEN0001060 Stage 4Completion

    Project: UP#30-2 Activity: GEN0001060 Stage 4Completion

    Project: UP#30-2 Activity: GEN0001060 Stage 4Completion

    Project: UP#30-2 Activity: GEN0001060 Stage 4Completion

    Project: UP#30-2 Activity: GEN0001060 Stage 4Completion

    Project: UP#30-2 Activity: GEN0001060 Stage 4Completion

    Project: UP#30-2 Activity: GEN0001060 Stage 4CompletionProject: UP#30-2 Activity: SEC2S22420 Access t

    o SS 1164Project: UP#30-2 Activity: SEC2S41000 Fuel Far

    m Availability

    Scheduling/Leveling Results:----------------------------

    # Projects Scheduled/Leveled.....................................1# Activities Scheduled/Leveled...................................833# Relationships with other projects..............................0Data Date........................................................06-May-

    16Earliest Early Start Date........................................06-May-

    16Latest Early Finish Date.........................................31-Jan-

    17Number of float paths............................................10

    Exceptions:-----------

    Critical Activities..............................................64Project: UP#30-2 Activity: GEN0001060 Stage 4

  • 8/17/2019 Sched Logasd

    7/34

    CompletionProject: UP#30-2 Activity: PRCMT1130 Procurem

    ent 36" DBB ValvesProject: UP#30-2 Activity: PRCMT1175 Procurem

    ent 24" DBB ValvesProject: UP#30-2 Activity: PRCMTSD1170 Site Del

    ivery 36" DBB valvesProject: UP#30-2 Activity: PRCMTSD1175 Site Del

    ivery 24" DBB valvesProject: UP#30-2 Activity: SEC2S31410 CH156 -

    Piping Installation with DBB valvesProject: UP#30-2 Activity: SEC2S31460 CH156 -

    Insulation Gasket Kit Installation & TourquingProject: UP#30-2 Activity: SEC2S31690 CH155 -

    Piping Installation with DBB valvesProject: UP#30-2 Activity: SEC2S31740 CH155 -

    Insulation Gasket Kit Installation & TourquingProject: UP#30-2 Activity: SEC2S32290 CH-133 t

    o CH-135 Nitrogen Purging - Setting-up & PreparationProject: UP#30-2 Activity: SEC2S32300 CH-133 t

    o CH-135 Nitrogen Purging - Pneumatic TestingProject: UP#30-2 Activity: SEC2S32310 CH-133 t

    o CH-135 Nitrogen Purging - Air BlowingProject: UP#30-2 Activity: SEC2S32320 CH-133 t

    o CH-135 Nitrogen Purging - DryingProject: UP#30-2 Activity: SEC2S32330 CH-133 to CH-135 Nitrogen Purging - Nitrogen Purging

    Project: UP#30-2 Activity: SEC2S41010 Loop 1B- Preparation & Set-up

    Project: UP#30-2 Activity: SEC2S41020 Loop 1B- Installation of Temporary Flushing Loops in CH-133 & CH-151

    Project: UP#30-2 Activity: SEC2S41030 Loop 1B- Installation of BFs & Fuel Filling Loop in CH-139

    Project: UP#30-2 Activity: SEC2S41040 Loop 1B- Installation of Christmas Trees on HPs & LPs

    Project: UP#30-2 Activity: SEC2S41050 Loop 1B- Installation of Blind Flanges with Goose Neck Connection on HRs

    Project: UP#30-2 Activity: SEC2S41060 Loop 1B- Fuel Filling in Loop 1B & Loop 1AProject: UP#30-2 Activity: SEC2S41070 Loop 1B

    - Soak Testing of Loop 1B & Loop 1AProject: UP#30-2 Activity: SEC2S41090 Loop 1B

    - Soak Test Sample & ApprovalProject: UP#30-2 Activity: SEC2S41120 Loop 1B

    - Flushing & Filtration for Mainline & Millipore TestProject: UP#30-2 Activity: SEC2S41130 Loop 1B

    - Flushing & Filtration of Risers & Millipore TestProject: UP#30-2 Activity: SEC2S41140 Loop 1B

    - API FiltrationProject: UP#30-2 Activity: SEC2S41270 Loop 1A

    - Flushing & Filtration for Mainline & Millipore TestProject: UP#30-2 Activity: SEC2S41280 Loop 1A

    - Flushing & Filtration of Risers & Millipore TestProject: UP#30-2 Activity: SEC2S41290 Loop 1A

    - API FiltrationProject: UP#30-2 Activity: SEC2S41330 Loop 2A

    - Preparation & Set-upProject: UP#30-2 Activity: SEC2S41340 Loop 2A

    - Installation of Temporary Flushing Loop in CH-110 & CH-113Project: UP#30-2 Activity: SEC2S41350 Loop 2A

  • 8/17/2019 Sched Logasd

    8/34

    - Installation of BFs in CH-112Project: UP#30-2 Activity: SEC2S41360 Loop 2A

    - Installation of Christmas Trees on HPs & LPsProject: UP#30-2 Activity: SEC2S41370 Loop 2A

    - Transfer of Fuel from Section Between CH-133 & CH-154 to Loop 2AProject: UP#30-2 Activity: SEC2S41380 Loop 2A

    - Removal of Temporary Flushing Loop in CH-133 and Installation of BFsProject: UP#30-2 Activity: SEC2S41390 Loop 2A

    - Installation of Temporary Flushing Loop in CH-133Project: UP#30-2 Activity: SEC2S41400 Loop 2A

    - Fuel Filling in Loop 2A through Loop 1AProject: UP#30-2 Activity: SEC2S41410 Loop 2A

    - Soak Testing of Loop 2AProject: UP#30-2 Activity: SEC2S41440 Loop 2A

    - Soak Test Sample & ApprovalProject: UP#30-2 Activity: SEC2S41450 Loop 2A

    - Flushing & Filtration for Mainline & Millipore TestProject: UP#30-2 Activity: SEC2S41460 Loop 2A

    - Flushing & Filtration of Risers & Millipore TestProject: UP#30-2 Activity: SEC2S41470 Loop 2A

    - API FiltrationProject: UP#30-2 Activity: SEC2S41510 Loop 2B

    - Preparation & Set-upProject: UP#30-2 Activity: SEC2S41520 Loop 2B

    - Installation of Christmas Trees on HPs & LPsProject: UP#30-2 Activity: SEC2S41530 Loop 2B- Fuel Filling in Loop 2B & 2C through Loop 2A

    Project: UP#30-2 Activity: SEC2S41540 Loop 2B- Soak Testing of Loop 2B & 2C

    Project: UP#30-2 Activity: SEC2S41550 Loop 2B- Pressure Testing of Loop 2B & 2C

    Project: UP#30-2 Activity: SEC2S41570 Loop 2B- Removal of Blind Flanges in DBB Valve from CH-110

    Project: UP#30-2 Activity: SEC2S41580 Loop 2B- l of Flushing Loop & Installation permanent connecting Spool between 2B & 2A

    Project: UP#30-2 Activity: SEC2S41590 Loop 2B- Flushing & Filtration for Mainline & Millipore Test

    Project: UP#30-2 Activity: SEC2S41770 Loop 3B- Fuel FillingProject: UP#30-2 Activity: SEC2S41780 Loop 3B

    -Soak TestingProject: UP#30-2 Activity: SEC2S41800 Loop 3B

    - Soak Test Sample ApprovalProject: UP#30-2 Activity: SEC2S41810 Loop 3B

    -Draining of SectionProject: UP#30-2 Activity: SEC2S41820 Loop 3B

    -Flip Spectacle Blind, Install Reducer and ValveProject: UP#30-2 Activity: SEC2S41830 Loop 3B

    -Flushing of Mainline & Millipore TestProject: UP#30-2 Activity: SEC2S41840 Loop 3B

    -Draining of SectionProject: UP#30-2 Activity: SEC2S41850 Loop 3B

    -Installation of VentsProject: UP#30-2 Activity: SEC2S41860 Loop 3B

    -Re-Pressurizing to System PressureProject: UP#30-2 Activity: SEC2S42040 Testing

    and Commissioning - PAKSCAN/EFSD Software calibrationProject: UP#30-2 Activity: SEC2S42050 Testing

    and Commissioning - Automation of valvesProject: UP#30-2 Activity: SEC2S42060 Testing

  • 8/17/2019 Sched Logasd

    9/34

    and Commissioning - Emergency fuel shutdownProject: UP#30-2 Activity: SEC2S42070 Testing

    and Commissioning - LDS software set-upProject: UP#30-2 Activity: SEC2S42080 Testing

    and Commissioning - Calibration of TCS and LDSProject: UP#30-2 Activity: SEC2S42090 Snag and

     Desnagging of MJF line

    Activities with unsatisfied constraints..........................11Project: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

    CompletionProject: UP#30-2 Activity: GEN0001050 Stage 3

    CompletionProject: UP#30-2 Activity: GEN0001060 Stage 4

    CompletionProject: UP#30-2 Activity: GEN0001210 Availabi

    lity of Fuel in Fuel FarmProject: UP#30-2 Activity: SEC2S22420 Access t

    o SS 1164Project: UP#30-2 Activity: SEC2S22560 Cable Du

    ct Civil Work Completion (VO)Project: UP#30-2 Activity: SEC2S22640 Cable Du

    ct Civil Work Completion Section 7Project: UP#30-2 Activity: SEC2S31000 CH101A - Trench Civil Work Completion

    Project: UP#30-2 Activity: SEC2S32430 Fuel Farm and Control Room Availability

    Project: UP#30-2 Activity: SEC2S41000 Fuel Farm Availability

    Activities with unsatisfied relationships........................0

    Activities with external dates...................................7Project: UP#30-2 Activity: SEC2S22410 E&I Cabl

    e laying in Section2 - Cables connected to SS 1164

    Project: UP#30-2 Activity: SEC2S22450 E&I Cable Laying in Section 3 (Except Main Cables)Project: UP#30-2 Activity: SEC2S22480 E&I Cabl

    e Laying in Section 4 (except new Apron chambers)Project: UP#30-2 Activity: SEC2S22530 E&I Cabl

    e Laying in Section 1 (Except Main Cables)Project: UP#30-2 Activity: SEC2S22580 E&I Cabl

    e Laying in Section 5 (Except Fuel Farm Control Room)Project: UP#30-2 Activity: SEC2S22650 E&I Cabl

    e Laying in Section 7Project: UP#30-2 Activity: SEC2S32120 New Apro

    n Loop - Continuity & Loop Checking

    Activities that are not on any float paths.......................760Project: UP#30-2 Activity: ASBULT1000 Submissi

    on of As Built Drawing for Storm water worksProject: UP#30-2 Activity: ASBULT1010 Approval

     of As Built Drawing for Storm water worksProject: UP#30-2 Activity: ASBULT1020 Submissi

    on of As Built Drawing for Electrical worksProject: UP#30-2 Activity: ASBULT1030 Approval

     of As Built Drawing for Electrical worksProject: UP#30-2 Activity: ASBULT1040 Submissi

  • 8/17/2019 Sched Logasd

    10/34

    on of As Built Drawing for Fire Fighting worksProject: UP#30-2 Activity: ASBULT1050 Approval

     of As Built Drawing for Fire Fighting worksProject: UP#30-2 Activity: ASBULT1060 Submissi

    on of As Built Drawing for AGL worksProject: UP#30-2 Activity: ASBULT1070 Approval

     of As Built Drawing for AGL worksProject: UP#30-2 Activity: ASBULT1080 Submissi

    on of As Built Drawing for S1 - Section 1Project: UP#30-2 Activity: ASBULT1090 Approval

     of As Built Drawing for S1 - Section 1Project: UP#30-2 Activity: ASBULT1100 Submissi

    on of As Built Drawing for MS1 - Milestone 1Project: UP#30-2 Activity: ASBULT1110 Approval

     of As Built Drawing for MS1 - Milestone 1Project: UP#30-2 Activity: ASBULT1120 Submissi

    on of As Built Drawing for Aprons - Concrete PavementProject: UP#30-2 Activity: ASBULT1130 Approval

     of As Built Drawing for Aprons - Concrete PavementProject: UP#30-2 Activity: ASBULT1140 Submissi

    on of As Built Drawing for SubstationsProject: UP#30-2 Activity: ASBULT1150 Approval

     of As Built Drawing for SubstationsProject: UP#30-2 Activity: ASBULT1160 Submissi

    on of As Built Drawing for Air Side Road A3Project: UP#30-2 Activity: ASBULT1170 Approval of As Built Drawing for Air Side Road A3

    Project: UP#30-2 Activity: ASBULT1180 Submission of As Built Drawing for Temporary Road R3

    Project: UP#30-2 Activity: ASBULT1190 Approval of As Built Drawing for Temporary Road R3

    Project: UP#30-2 Activity: ASBULT1200 Submission of As Built Drawing for Taxi ways - Asphalt works

    Project: UP#30-2 Activity: ASBULT1210 Approval  of As Built Drawing for Taxi ways - Asphalt works

    Project: UP#30-2 Activity: EN00001000 Design Concept - VO37 (AJF/MJF INterface)

    Project: UP#30-2 Activity: EN00001010 QA/QC Documents - VO37 (AJF/MJF INterface)Project: UP#30-2 Activity: ENMTAP1000 Material

     Approval of Insulation Gasket kitProject: UP#30-2 Activity: ENMTAP1010 Material

     Approval of 24" Ball ValvesProject: UP#30-2 Activity: ENMTAP1020 Material

     Approval of CNAF GasketProject: UP#30-2 Activity: ENMTAP1030 Material

     Approval of CS Spectacle BlindProject: UP#30-2 Activity: ENMTAP1040 Material

     Approval - VO37 (AJF/MJF INterface)Project: UP#30-2 Activity: ENMTSB1000 Material

     Submittal of Insulation Gasket kitProject: UP#30-2 Activity: ENMTSB1010 Material

     Submittal of 24" Ball ValvesProject: UP#30-2 Activity: ENMTSB1020 Material

     Submittal of CNAF GasketProject: UP#30-2 Activity: ENMTSB1030 Material

     Submittal of CS Spectacle BlindProject: UP#30-2 Activity: ENMTSB1040 Material

     Submittal- VO37 (AJF/MJF INterface)Project: UP#30-2 Activity: ENSD001000 Shop Dra

  • 8/17/2019 Sched Logasd

    11/34

    wings Submitted and Approved till 5th AugustProject: UP#30-2 Activity: ENSDAP1000 Shop Dra

    wign Approval - Parking & FencingProject: UP#30-2 Activity: ENSDAP1010 Function

    al Design Specification (FDS) Approval - VO37 (AJF/MJF Interface)Project: UP#30-2 Activity: ENSDAP1020 Design D

    rawings - VO37 (AJF/MJF Interface) - ApprovalProject: UP#30-2 Activity: ENSDSB1000 Shop Dra

    wing Submission - Parking & FencingProject: UP#30-2 Activity: ENSDSB1010 Function

    al Design Specification (FDS) SubmissionProject: UP#30-2 Activity: ENSDSB1020 Design D

    rawings - VO37 (AJF/MJF Interface) - SubmissionProject: UP#30-2 Activity: GEN0001000 Project

    StartProject: UP#30-2 Activity: GEN0001010 Receive

    final MJF IFC-06 from ADACProject: UP#30-2 Activity: GEN0001020 Receive

    Instruction from ADAC to procure additional MJF Pipe fittings & ValvesProject: UP#30-2 Activity: GEN0001030 Stage 1

    CompletionProject: UP#30-2 Activity: GEN0001040 Stage 2

    CompletionProject: UP#30-2 Activity: GEN0001050 Stage 3

    Completion Project: UP#30-2 Activity: GEN0001070 Access to F3 in the GCAA Area

    Project: UP#30-2 Activity: GEN0001080 Access to CH147 - East end in the GCAA Area

    Project: UP#30-2 Activity: GEN0001090 Access to West end

    Project: UP#30-2 Activity: GEN0001100 Access to Presidential Flight area

    Project: UP#30-2 Activity: GEN0001110 Access to Area (For Remaining Fire Fighting Work)

    Project: UP#30-2 Activity: GEN0001120 Access in Fuel Farm Control Room

    Project: UP#30-2 Activity: GEN0001130 Receiptof NTP with Procurement (VO38)Project: UP#30-2 Activity: GEN0001140 Submitta

    l of VO 072 - IFC 33 Cost ProposalProject: UP#30-2 Activity: GEN0001150 Approval

     of VO 072 - IFC 33 Cost ProposalProject: UP#30-2 Activity: GEN0001160 Approval

     of VO 37Project: UP#30-2 Activity: GEN0001170 Kick-off

     Meeting - VO37 (AJF/MJF INterface)Project: UP#30-2 Activity: GEN0001180 Road div

    ersion by HLG to its final positionProject: UP#30-2 Activity: GEN0001190 Completi

    on of Substation 1164 by Other ContractorProject: UP#30-2 Activity: GEN0001200 Availabi

    lity of Fuel Farm (Installation of instruments)Project: UP#30-2 Activity: GEN0001210 Availabi

    lity of Fuel in Fuel FarmProject: UP#30-2 Activity: GEN0001220 Project

    NOCsProject: UP#30-2 Activity: GEN0001230 Contarct

    ual SubmissionProject: UP#30-2 Activity: GEN0001240 Mobilisa

  • 8/17/2019 Sched Logasd

    12/34

    tion and DemobilisationProject: UP#30-2 Activity: MS10001000 Mileston

    e 1Project: UP#30-2 Activity: O&MMNL1000 Opeartio

    n and Maintanance Manual for AGL Network - SubmissionProject: UP#30-2 Activity: O&MMNL1010 Opeartio

    n and Maintanance Manual for AGL Network - ApprovalProject: UP#30-2 Activity: O&MMNL1020 Opeartio

    n and Maintanance Manual for MJF Network - SubmissionProject: UP#30-2 Activity: O&MMNL1030 Opeartio

    n and Maintanance Manual for MJF Network - ApprovalProject: UP#30-2 Activity: O&MMNL1040 Operatio

    n and Maintanance Manual for Telecommunication Network - SubmissionProject: UP#30-2 Activity: O&MMNL1050 Operatio

    n and Maintanance Manual for Telecommunication Network - ApprovalProject: UP#30-2 Activity: PRCMT1000 Procurem

    ent Stud BoltsProject: UP#30-2 Activity: PRCMT1010 Procurem

    ent Heat Shrink SleeveProject: UP#30-2 Activity: PRCMT1020 Procurem

    ent Link SealProject: UP#30-2 Activity: PRCMT1030 Procurem

    ent End SealProject: UP#30-2 Activity: PRCMT1040 Procurem

    ent CS Pipes Project: UP#30-2 Activity: PRCMT1050 Procurement CS Fittings

    Project: UP#30-2 Activity: PRCMT1060 Procurement CS WNR Flanges

    Project: UP#30-2 Activity: PRCMT1070 Procurement CS Blind Flanges

    Project: UP#30-2 Activity: PRCMT1080 Procurement HP Vent Assembly

    Project: UP#30-2 Activity: PRCMT1090 Procurement Puddle Flanges

    Project: UP#30-2 Activity: PRCMT1100 Procurement Pipe Supports

    Project: UP#30-2 Activity: PRCMT1110 Procurement Valve Operating PlatformsProject: UP#30-2 Activity: PRCMT1120 Procurem

    ent Manhole CoverProject: UP#30-2 Activity: PRCMT1140 Procurem

    ent Insulation Gasket KitsProject: UP#30-2 Activity: PRCMT1150 Procurem

    ent CNAF GasketProject: UP#30-2 Activity: PRCMT1160 Procurem

    ent Ball ValvesProject: UP#30-2 Activity: PRCMT1170 Procurem

    ent CS Spectacle BlindProject: UP#30-2 Activity: PRCMT1180 Procurem

    ent of additional Pipe Fittings (VO-38)Project: UP#30-2 Activity: PRCMT1185 Procurem

    ent Leak Detection SystemProject: UP#30-2 Activity: PRCMT1190 Procurem

    ent Instruments CablesProject: UP#30-2 Activity: PRCMT1200 Procurem

    ent Earthing MaterialProject: UP#30-2 Activity: PRCMT1210 Procurem

    ent Power CablesProject: UP#30-2 Activity: PRCMT1220 Procurem

  • 8/17/2019 Sched Logasd

    13/34

    ent Earth CablesProject: UP#30-2 Activity: PRCMT1230 Procurem

    ent Junction BoxProject: UP#30-2 Activity: PRCMT1240 Procurem

    ent SDB & FDBProject: UP#30-2 Activity: PRCMT1250 Procurem

    ent Tightness Control SystemProject: UP#30-2 Activity: PRCMT1260 Procurem

    ent Temperature TransmitterProject: UP#30-2 Activity: PRCMT1270 Procurem

    ent ThermowellsProject: UP#30-2 Activity: PRCMT1280 Procurem

    ent Pressure TransmitterProject: UP#30-2 Activity: PRCMT1290 Procurem

    ent Pressure GaugeProject: UP#30-2 Activity: PRCMT1300 Procurem

    ent Level TransmitterProject: UP#30-2 Activity: PRCMT1310 Procurem

    ent MOV Isolator SwitchProject: UP#30-2 Activity: PRCMT1320 Procurem

    ent Cathodic Protection SystemProject: UP#30-2 Activity: PRCMT1330 Procurem

    ent Cable Trays & AccessoriesProject: UP#30-2 Activity: PRCMT1340 Procurem

    ent Cable Glands, Glands & TiesProject: UP#30-2 Activity: PRCMTSD1000 Site Delivery Stud Bolts

    Project: UP#30-2 Activity: PRCMTSD1010 Site Delivery Heat Shrink Sleeve

    Project: UP#30-2 Activity: PRCMTSD1020 Site Delivery Insulation Gasket Kit

    Project: UP#30-2 Activity: PRCMTSD1030 Site Delivery Link Seal

    Project: UP#30-2 Activity: PRCMTSD1040 Site Delivery End Seal

    Project: UP#30-2 Activity: PRCMTSD1050 Site Delivery CNAF Gasket

    Project: UP#30-2 Activity: PRCMTSD1060 Site Delivery CS PipesProject: UP#30-2 Activity: PRCMTSD1070 Site Del

    ivery CS FittingsProject: UP#30-2 Activity: PRCMTSD1080 Site Del

    ivery CS WNR FlangesProject: UP#30-2 Activity: PRCMTSD1090 Site Del

    ivery CS Blind FlangesProject: UP#30-2 Activity: PRCMTSD1100 Site Del

    ivery HP Vent AssemblyProject: UP#30-2 Activity: PRCMTSD1110 Site Del

    ivery Puddle FlangesProject: UP#30-2 Activity: PRCMTSD1120 Site Del

    ivery Pipe SupportsProject: UP#30-2 Activity: PRCMTSD1130 Site Del

    ivery Valve Operating PlatformsProject: UP#30-2 Activity: PRCMTSD1140 Site Del

    ivery CS Spectacle BlindProject: UP#30-2 Activity: PRCMTSD1150 Site Del

    ivery Manhole CoverProject: UP#30-2 Activity: PRCMTSD1160 Site Del

    ivery Ball ValvesProject: UP#30-2 Activity: PRCMTSD1180 Site Del

  • 8/17/2019 Sched Logasd

    14/34

    ivery Cable Trays & AccessoriesProject: UP#30-2 Activity: PRCMTSD1190 Site Del

    ivery Cable Glands, Glands & TiesProject: UP#30-2 Activity: PRCMTSD1200 Site Del

    ivery Leak Detection SystemProject: UP#30-2 Activity: PRCMTSD1210 Site Del

    ivery Instruments CablesProject: UP#30-2 Activity: PRCMTSD1220 Site Del

    ivery Earthing MaterialProject: UP#30-2 Activity: PRCMTSD1230 Site Del

    ivery Power CablesProject: UP#30-2 Activity: PRCMTSD1240 Site Del

    ivery Earth CablesProject: UP#30-2 Activity: PRCMTSD1250 Site Del

    ivery Junction BoxProject: UP#30-2 Activity: PRCMTSD1260 Site Del

    ivery SDB & FDBProject: UP#30-2 Activity: PRCMTSD1270 Site Del

    ivery Cathodic Protection SystemProject: UP#30-2 Activity: PRCMTSD1280 Site Del

    ivery Tightness Control SystemProject: UP#30-2 Activity: PRCMTSD1290 Site Del

    ivery Temperature TransmitterProject: UP#30-2 Activity: PRCMTSD1300 Site Del

    ivery Pressure TransmitterProject: UP#30-2 Activity: PRCMTSD1310 Site Delivery Pressure Gauge

    Project: UP#30-2 Activity: PRCMTSD1320 Site Delivery Level Transmitter

    Project: UP#30-2 Activity: PRCMTSD1330 Site Delivery MOV Isolator Switch

    Project: UP#30-2 Activity: PRCMTSD1340 Site Delivery Thermowells

    Project: UP#30-2 Activity: PRCMTSD1345 Procurement and Site Delivery- Required for LV Panel Modification

    Project: UP#30-2 Activity: PRCMTSD1350 Procurement and Site Delivery Addtionaol Work - 400Hz Cable

    Project: UP#30-2 Activity: PRCMTSD1360 Procurement and Site Delivery BollardProject: UP#30-2 Activity: PRCMTSD1370 Procurem

    ent and Site Delivery Generators for MV SubstationsProject: UP#30-2 Activity: PRCMTSD1380 Procurem

    ent and Site Delivery Doors for AGL SubstationProject: UP#30-2 Activity: PRCMTSD1390 Procurem

    ent and Site Delivery Windows for AGL SubstationProject: UP#30-2 Activity: PRCMTSD1400 Procurem

    ent and Site Delivery Crash Gate - A3 RoadProject: UP#30-2 Activity: PRCMTSD1410 Procurem

    ent and Site Delivery Stop Bar Light - A3 Link RoadProject: UP#30-2 Activity: PRCMTSD1420 Procurem

    ent and Site Delivery CCTV System - A3 link RoadProject: UP#30-2 Activity: PRCMTSD1430 Procurem

    ent and Site Delivery Traffic Signal System - A3 Link RoadProject: UP#30-2 Activity: PRCMTSD1440 Procurem

    ent and Site Delivery Guard Rail - A3 Link RoadProject: UP#30-2 Activity: PRCMTSD1450 Procurem

    ent and Site Delivery Additional SIgns - Taxiway CProject: UP#30-2 Activity: PRCMTSD1460 Procurem

    ent and Site Delivery Roman NumeralsProject: UP#30-2 Activity: PRCMTSD1490 Procurem

  • 8/17/2019 Sched Logasd

    15/34

    ent and Site Delivery of Fire Extinguishers for Cargo Apron (VO-65)Project: UP#30-2 Activity: PRCMTSD1500 Procurem

    ent and Site Delivery RVR Gantries and Field box (VO-61)Project: UP#30-2 Activity: PRCMTSD1520 Procurem

    ent and Site Delivery (AJF/MJF Interface)Project: UP#30-2 Activity: PRCMTSD1530 Procurem

    ent and Site Delivery of SCADA System (VO-32)Project: UP#30-2 Activity: SEC1001000 Section

    1Project: UP#30-2 Activity: SEC2001000 South Ru

    nway And Taxiways (Package 2) as on 5th August 2015Project: UP#30-2 Activity: SEC2001010 East Mid

    field Cargo Apron PAL 2Project: UP#30-2 Activity: SEC2001020 New Fuel

     Hydrant SystemProject: UP#30-2 Activity: SEC2001030 AOA Peri

    meter FenceProject: UP#30-2 Activity: SEC2S11000 Bollard

    Installation -EMCAProject: UP#30-2 Activity: SEC2S11010 Snagging

     and Desnagging -EMCAProject: UP#30-2 Activity: SEC2S11020 Permit t

    o Work - ATCT ConnectionProject: UP#30-2 Activity: SEC2S11030 Fiber Op

    tic Cabling - EMCAProject: UP#30-2 Activity: SEC2S11040 Connections and Termination with ATCT

    Project: UP#30-2 Activity: SEC2S11050 400Hz Cable Installation - EMCA

    Project: UP#30-2 Activity: SEC2S11060 Testingand Commissioning of VDGS

    Project: UP#30-2 Activity: SEC2S11070 Testingand Commissioning of CCTVs

    Project: UP#30-2 Activity: SEC2S11080 Testingand Commissioning - EMCA

    Project: UP#30-2 Activity: SEC2S11090 Stand Energisation

    Project: UP#30-2 Activity: SEC2S11100 Remaining Civil Works - MV SSProject: UP#30-2 Activity: SEC2S11110 Snagging

     and Desnagging - MV SSProject: UP#30-2 Activity: SEC2S11120 Generato

    r Installation - MV SSProject: UP#30-2 Activity: SEC2S11130 LV Panel

     Modification - MV SSProject: UP#30-2 Activity: SEC2S11140 Fiber Op

    tic Panel Installation - MV SSProject: UP#30-2 Activity: SEC2S11150 Fiber Op

    tic Connection to ATCTProject: UP#30-2 Activity: SEC2S11160 Fire Fig

    hting System - Testing and Commissioning - MV SSProject: UP#30-2 Activity: SEC2S11170 ADDC LV

    Inspection - MV SSProject: UP#30-2 Activity: SEC2S11180 ADDC MV

    Inspection - MV SSProject: UP#30-2 Activity: SEC2S11190 ADAC Ins

    pection and Handover - MV SSProject: UP#30-2 Activity: SEC2S11200 Installa

    tion of Door (Remaining) - AGL SSProject: UP#30-2 Activity: SEC2S11210 Installa

  • 8/17/2019 Sched Logasd

    16/34

    tion of Window (Remaining) - AGL SSProject: UP#30-2 Activity: SEC2S11220 Snagging

     and Desnagging - AGL SSProject: UP#30-2 Activity: SEC2S11230 Generato

    r Installation - AGL SSProject: UP#30-2 Activity: SEC2S11240 Chiller

    Unit Installation - AGL SSProject: UP#30-2 Activity: SEC2S11250 Sound At

    tenuator Installation - AGL SSProject: UP#30-2 Activity: SEC2S11260 Fiber Op

    tic Connection to ATCTProject: UP#30-2 Activity: SEC2S11270 Fire Fig

    hting System - Testing and Commissioning - AGL SSProject: UP#30-2 Activity: SEC2S11280 Generato

    r Testing and Commissioning - AGL SSProject: UP#30-2 Activity: SEC2S11290 Software

     Modification - AGL SSProject: UP#30-2 Activity: SEC2S11300 Switchin

    g from Temporary to Permanent A/C - AGL SSProject: UP#30-2 Activity: SEC2S11305 Testing

    and Commissioning of Fire AlarmProject: UP#30-2 Activity: SEC2S11310 ADAC AGL

     Inspection and Handoover -AGL SSProject: UP#30-2 Activity: SEC2S11320 GCAA Ins

    pection and Handoover - AGL SSProject: UP#30-2 Activity: SEC2S11330 Complete Storm Water Chamber - East End - A3 Road

    Project: UP#30-2 Activity: SEC2S11340 AOA Fence East End

    Project: UP#30-2 Activity: SEC2S11350 Completion of Work by HLG

    Project: UP#30-2 Activity: SEC2S11360 SL DuctBank North of EMCA

    Project: UP#30-2 Activity: SEC2S11370 SL DuctBank Landside to SS PU-3

    Project: UP#30-2 Activity: SEC2S11380 InstallRoad Studs

    Project: UP#30-2 Activity: SEC2S11390 SS PU-5Parking & Fencing (SS1205)Project: UP#30-2 Activity: SEC2S11400 Crash Ga

    te InstallationProject: UP#30-2 Activity: SEC2S11410 SS PU-4

    Parking & Fencing (SS1204)Project: UP#30-2 Activity: SEC2S11420 AOA Fenc

    e SS PU-4 to HLG UnderpassProject: UP#30-2 Activity: SEC2S11430 SS PU-3

    Parking & Fencing (SS1206)Project: UP#30-2 Activity: SEC2S11440 Relocate

     Gate A2 (by others)Project: UP#30-2 Activity: SEC2S11450 Snagging

     and Desangging - A3 RoadProject: UP#30-2 Activity: SEC2S11460 Police A

    pproval of New Insatlled FenceProject: UP#30-2 Activity: SEC2S11470 LV Cable

     into SS PU-5Project: UP#30-2 Activity: SEC2S11480 LV Cable

     into SS PU-4Project: UP#30-2 Activity: SEC2S11490 Street L

    ight Cabling - North of EMCAProject: UP#30-2 Activity: SEC2S11500 Fedder P

  • 8/17/2019 Sched Logasd

    17/34

    illar InstallationProject: UP#30-2 Activity: SEC2S11510 LV Cable

     into SS PU-3Project: UP#30-2 Activity: SEC2S11520 Storm Wa

    ter Chamber Internal Finishing - A3 Link RoadProject: UP#30-2 Activity: SEC2S11530 Guard Ra

    il Installation - A3 Link RoadProject: UP#30-2 Activity: SEC2S11540 Backfill

    ing Work Completion in Aviation AreaProject: UP#30-2 Activity: SEC2S11550 A3 Road

    Widening @ Stand 222Project: UP#30-2 Activity: SEC2S11560 Design S

    ubmission - Traffic Signal SystemProject: UP#30-2 Activity: SEC2S11570 Design A

    pproval - Traffic Signal SystemProject: UP#30-2 Activity: SEC2S11580 Installa

    tion of Traffic Signal SystemProject: UP#30-2 Activity: SEC2S11590 Installa

    tion of Stop Bars F3 - F5Project: UP#30-2 Activity: SEC2S11600 Installa

    tion of CCTV to F3 & F5Project: UP#30-2 Activity: SEC2S11610 Testing

    and CommissioningProject: UP#30-2 Activity: SEC2S11620 Access t

    o Runways Project: UP#30-2 Activity: SEC2S11630 AGL Chamber Stencilling (Ch 4+100 - Ch2+810) - Taxiway C (East of Taxiway G&H)

    Project: UP#30-2 Activity: SEC2S11640 Roman Numerals Installation - Taxiway C (East of Taxiway G&H)

    Project: UP#30-2 Activity: SEC2S11650 Snagging and Desnagging - Taxiway C (East of Taxiway G&H)

    Project: UP#30-2 Activity: SEC2S11660 GCAA Inspection - Taxiway C (East of Taxiway G&H)

    Project: UP#30-2 Activity: SEC2S11670 HandingOver - Taxiway C (East of Taxiway G&H)

    Project: UP#30-2 Activity: SEC2S11680 Tunnel Area Fence

    Project: UP#30-2 Activity: SEC2S11690 Primary& Secondary Cabling - West of Taxiway G&HProject: UP#30-2 Activity: SEC2S11700 AGL Ligh

    st Installation - West of Taxiway G&HProject: UP#30-2 Activity: SEC2S11710 AGL Chma

    ber Stencilling (Ch 2+810 - Ch1+460) - Taxiway CProject: UP#30-2 Activity: SEC2S11720 Addition

    al Signs Installation - Taxiway C (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11730 Roman Nu

    merals Installation - Taxiway C (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11740 Testing

    and Commissioning - Taxiway C (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11750 Snagging

     and Desnagging - Taxiway C (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11760 GCAA Ins

    pection - Taxiway C (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11770 Handing

    Over - Taxiway C (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11780 AGL Chma

    ber Stencilling (Ch 4+100 - Ch2+810) - Taxiway D (East of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11790 Roman Nu

    merals Installation - Taxiway D (East of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11800 Snagging

  • 8/17/2019 Sched Logasd

    18/34

     and Desnagging - Taxiway D (East of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11810 GCAA Ins

    pection - Taxiway D (East of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11820 Handing

    Over - Taxiway D (East of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11830 Remainin

    g Work - Fire Fighting Duct ConstrcutionProject: UP#30-2 Activity: SEC2S11840 Testing

    and Commissioning - Fire Fighting NetworkProject: UP#30-2 Activity: SEC2S11850 AGL Chma

    ber Stencilling (Ch 2+810 - Ch1+460) - Taxiway D (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11860 Stop Bar

     Lights Installation - Taxiway DProject: UP#30-2 Activity: SEC2S11870 Roman Nu

    merals Installation -Taxiway D (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11880 Testing

    and Commissioning -Taxiway D (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11890 Snagging

     and Desnagging - Taxiway D (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11900 GCAA Ins

    pection -Taxiway D (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11910 Handing

    Over - Taxiway D (West of Taxiway G&H)Project: UP#30-2 Activity: SEC2S11920 Cabling,

     Lights and Transformer Installation- Connecting Taxiway D1Project: UP#30-2 Activity: SEC2S11930 Cabling, Lights and Transformer Installation- Connecting Taxiway D2

    Project: UP#30-2 Activity: SEC2S11940 Testingand Commissioning - Taxiway D1

    Project: UP#30-2 Activity: SEC2S11950 Cabling, Lights and Transformer Installation- Connecting Taxiway D3

    Project: UP#30-2 Activity: SEC2S11960 Testingand Commissioning - Taxiway D2

    Project: UP#30-2 Activity: SEC2S11970 Cabling, Lights and Transformer Installation- Connecting Taxiway D4

    Project: UP#30-2 Activity: SEC2S11980 Testingand Commissioning - Taxiway D3

    Project: UP#30-2 Activity: SEC2S11990 Cabling, Lights and Transformer Installation- Connecting Taxiway D5Project: UP#30-2 Activity: SEC2S12000 Testing

    and Commissioning - Taxiway D4Project: UP#30-2 Activity: SEC2S12010 Testing

    and Commissioning - Taxiway D5Project: UP#30-2 Activity: SEC2S12020 Snagging

     and Desnagging - Connecting TaxiwayProject: UP#30-2 Activity: SEC2S12030 GCAA Ins

    pection - Connecting TaxiwaysProject: UP#30-2 Activity: SEC2S12040 Handing

    Over - Connecting TaxiwaysProject: UP#30-2 Activity: SEC2S21000 E&I Duct

    s Installation (MART)Project: UP#30-2 Activity: SEC2S21010 Modifica

    tion of SDB and FDBProject: UP#30-2 Activity: SEC2S21030 Backfill

    ing - West End (CH101A)Project: UP#30-2 Activity: SEC2S21040 Concrete

     P&I Duct banks and EDP chambers installation - West End (CH101A)Project: UP#30-2 Activity: SEC2S21050 Final ba

    ckfilling - West End (CH101A)Project: UP#30-2 Activity: SEC2S21060 Concrete

  • 8/17/2019 Sched Logasd

    19/34

     P&I Duct banks and EDP chambers installation - Additional Cable Ducts Near Fuel Depot

    Project: UP#30-2 Activity: SEC2S21070 Final backfilling - Additional Cable Ducts Near Fuel Depot

    Project: UP#30-2 Activity: SEC2S21080 Excavation - New Apron Loop

    Project: UP#30-2 Activity: SEC2S21090 Sand surround - New Apron Loop

    Project: UP#30-2 Activity: SEC2S21100 Backfilling - New Apron Loop

    Project: UP#30-2 Activity: SEC2S21110 Concrete P&I Duct banks and EDP chambers installation - New Apron Loop

    Project: UP#30-2 Activity: SEC2S21120 Final backfilling - New Apron Loop

    Project: UP#30-2 Activity: SEC2S21130 Excavation - CH147 - East End

    Project: UP#30-2 Activity: SEC2S21140 Sand surround - CH147 - East End

    Project: UP#30-2 Activity: SEC2S21150 Backfilling - CH147 - East End

    Project: UP#30-2 Activity: SEC2S21160 Concrete P&I Duct banks and EDP chambers installation - CH147 - East End

    Project: UP#30-2 Activity: SEC2S21170 Final backfilling - CH147 - East End

    Project: UP#30-2 Activity: SEC2S21180 Pavement reinstatement - CH147 - East EndProject: UP#30-2 Activity: SEC2S21190 Excavati

    on - F3 to CH148Project: UP#30-2 Activity: SEC2S21200 Sand sur

    round- F3 to CH148Project: UP#30-2 Activity: SEC2S21210 Backfill

    ing - F3 to CH148Project: UP#30-2 Activity: SEC2S21220 Concrete

     P&I Duct banks and EDP chambers installation - F3 to CH148Project: UP#30-2 Activity: SEC2S21230 Final ba

    ckfilling - F3 to CH148Project: UP#30-2 Activity: SEC2S21240 CH147 -

    Excavation Project: UP#30-2 Activity: SEC2S21250 CH147 -Base concreting

    Project: UP#30-2 Activity: SEC2S21260 CH147 -Wall -1st Lift concreting

    Project: UP#30-2 Activity: SEC2S21270 CH147 -Wall - 2nd Lift concreting

    Project: UP#30-2 Activity: SEC2S21280 CH147 -Water proofing

    Project: UP#30-2 Activity: SEC2S21290 CH147 -Backfilling

    Project: UP#30-2 Activity: SEC2S21300 CH147 -Internal finishing

    Project: UP#30-2 Activity: SEC2S21310 CH147 -Top slab installation

    Project: UP#30-2 Activity: SEC2S21320 CH148 -Excavation

    Project: UP#30-2 Activity: SEC2S21330 CH148 -Base concreting

    Project: UP#30-2 Activity: SEC2S21340 CH148 -Wall -1st Lift concreting

    Project: UP#30-2 Activity: SEC2S21350 CH148 -Wall - 2nd Lift concreting

  • 8/17/2019 Sched Logasd

    20/34

    Project: UP#30-2 Activity: SEC2S21360 CH148 -Water proofing

    Project: UP#30-2 Activity: SEC2S21370 CH148 -Backfilling

    Project: UP#30-2 Activity: SEC2S21380 CH148 -Internal finishing

    Project: UP#30-2 Activity: SEC2S21390 CH148 -Top slab installation

    Project: UP#30-2 Activity: SEC2S21400 CH149 -Excavation

    Project: UP#30-2 Activity: SEC2S21410 CH149 -Base concreting

    Project: UP#30-2 Activity: SEC2S21420 CH149 -Wall -1st Lift concreting

    Project: UP#30-2 Activity: SEC2S21430 CH149 -Wall - 2nd Lift concreting

    Project: UP#30-2 Activity: SEC2S21440 CH149 -Water proofing

    Project: UP#30-2 Activity: SEC2S21450 CH149 -Backfilling

    Project: UP#30-2 Activity: SEC2S21460 CH149 -Internal finishing

    Project: UP#30-2 Activity: SEC2S21470 CH149 -Top slab installation

    Project: UP#30-2 Activity: SEC2S21480 CH154 -ExcavationProject: UP#30-2 Activity: SEC2S21490 CH154 -

    Base concretingProject: UP#30-2 Activity: SEC2S21500 CH154 -

    Wall -1st Lift concretingProject: UP#30-2 Activity: SEC2S21510 CH154 -

    Wall - 2nd Lift concretingProject: UP#30-2 Activity: SEC2S21520 CH154 -

    Water proofingProject: UP#30-2 Activity: SEC2S21530 CH154 -

    BackfillingProject: UP#30-2 Activity: SEC2S21540 CH154 -

    Internal finishingProject: UP#30-2 Activity: SEC2S21550 CH154 -Top slab installation

    Project: UP#30-2 Activity: SEC2S21560 CH155 -Excavation

    Project: UP#30-2 Activity: SEC2S21570 CH155 -Base concreting

    Project: UP#30-2 Activity: SEC2S21580 CH155 -Wall -1st Lift concreting

    Project: UP#30-2 Activity: SEC2S21590 CH155 -Wall - 2nd Lift concreting

    Project: UP#30-2 Activity: SEC2S21600 CH155 -Water proofing

    Project: UP#30-2 Activity: SEC2S21610 CH155 -Backfilling

    Project: UP#30-2 Activity: SEC2S21620 CH155 -Internal finishing

    Project: UP#30-2 Activity: SEC2S21630 CH155 -Top slab installation

    Project: UP#30-2 Activity: SEC2S21640 CH156 -Excavation

    Project: UP#30-2 Activity: SEC2S21650 CH156 -Base concreting

  • 8/17/2019 Sched Logasd

    21/34

    Project: UP#30-2 Activity: SEC2S21660 CH156 -Wall -1st Lift concreting

    Project: UP#30-2 Activity: SEC2S21670 CH156 -Wall - 2nd Lift concreting

    Project: UP#30-2 Activity: SEC2S21680 CH156 -Water proofing

    Project: UP#30-2 Activity: SEC2S21690 CH156 -Backfilling

    Project: UP#30-2 Activity: SEC2S21700 CH156 -Internal finishing

    Project: UP#30-2 Activity: SEC2S21710 CH156 -Top slab installation

    Project: UP#30-2 Activity: SEC2S21720 CH101A - Excavation

    Project: UP#30-2 Activity: SEC2S21730 CH101A - Base concreting

    Project: UP#30-2 Activity: SEC2S21740 CH101A - Wall -1st Lift concreting

    Project: UP#30-2 Activity: SEC2S21750 CH101A - Wall - 2nd Lift concreting

    Project: UP#30-2 Activity: SEC2S21760 CH101A - Water proofing

    Project: UP#30-2 Activity: SEC2S21770 CH101A - Backfilling

    Project: UP#30-2 Activity: SEC2S21780 CH101A - Internal finishingProject: UP#30-2 Activity: SEC2S21790 CH101A -

     Top slab installationProject: UP#30-2 Activity: SEC2S21800 CH138 (V

    O46) - Additional Wall concretingProject: UP#30-2 Activity: SEC2S21810 CH138 (V

    O46) - Water proofingProject: UP#30-2 Activity: SEC2S21820 CH138 (V

    O46) - BackfillingProject: UP#30-2 Activity: SEC2S21830 CH138 (V

    O46) - Internal finishingProject: UP#30-2 Activity: SEC2S21840 CH138 (V

    O46) - Top slab installationProject: UP#30-2 Activity: SEC2S21850 Installation of Fire Extinguishers

    Project: UP#30-2 Activity: SEC2S21860 Testing/Commissioning and hand over of Fire Extinguishers

    Project: UP#30-2 Activity: SEC2S21870 Installation of Gantries

    Project: UP#30-2 Activity: SEC2S21880 Hand over of Gantries

    Project: UP#30-2 Activity: SEC2S21890 Steel pipe/fittings installation and welding - West End (CH101A)

    Project: UP#30-2 Activity: SEC2S21900 Leak detection pipe installation - West End (CH101A)

    Project: UP#30-2 Activity: SEC2S21910 New Apron Loop - Steel pipe/fittings installation and welding - New Apron Loop

    Project: UP#30-2 Activity: SEC2S21920 New Apron Loop - Leak detection pipe installation - New Apron Loop

    Project: UP#30-2 Activity: SEC2S21930 CH-107 - Insulation Gaskets & Torquing

    Project: UP#30-2 Activity: SEC2S21940 CH-110 - Torquing & Platform Works

    Project: UP#30-2 Activity: SEC2S21950 CH-108 - Insulation Gaskets & Torquing

  • 8/17/2019 Sched Logasd

    22/34

    Project: UP#30-2 Activity: SEC2S21960 CH-150 - Mechanical Installation Works

    Project: UP#30-2 Activity: SEC2S21970 CH-151 Torquing, Support & Platform Works

    Project: UP#30-2 Activity: SEC2S21980 CH-134 - Insulation Gaskets & Torquing

    Project: UP#30-2 Activity: SEC2S21990 CH-135 - Insulation Gaskets & Torquing

    Project: UP#30-2 Activity: SEC2S22000 LPD-26 & LPD-27 Installation

    Project: UP#30-2 Activity: SEC2S22010 CH-140 - Insulation Gaskets & Touruing

    Project: UP#30-2 Activity: SEC2S22020 CH-137 - Insulation Gaskets & Torquing

    Project: UP#30-2 Activity: SEC2S22030 CH-135A- Insulation Gaskets & Torquing

    Project: UP#30-2 Activity: SEC2S22040 CH-136 - Insulation Gaskets & Torquing

    Project: UP#30-2 Activity: SEC2S22050 CH-138 - Insulation Gaskets & Torquing & Platform Works

    Project: UP#30-2 Activity: SEC2S22060 CH-139 - Torquing & Platform Reinstallation Works

    Project: UP#30-2 Activity: SEC2S22070 HPV-09,HPV-10 & HPV-11 - Installation

    Project: UP#30-2 Activity: SEC2S22080 LPD-09 & LPD-10 - InstallationProject: UP#30-2 Activity: SEC2S22090 LPD-11 &

     LPD-12 - InstallationProject: UP#30-2 Activity: SEC2S22100 CH-113 -

     Insulation Gaskets & TorquingProject: UP#30-2 Activity: SEC2S22110 CH-146

    - MOV installation, Insulation Gaskets & TourquingProject: UP#30-2 Activity: SEC2S22120 LPD-34 &

     LPD-35 - InstallationProject: UP#30-2 Activity: SEC2S22130 CH-145 -

     MOV installation, Insulation Gaskets & TourquingProject: UP#30-2 Activity: SEC2S22140 Chainage

     8+705 to 8+805 - Pipe Laying and Fitting InstallationProject: UP#30-2 Activity: SEC2S22150 CH-143 - Torquing of Bolts/Nuts

    Project: UP#30-2 Activity: SEC2S22160 CH-144 - Torquing of Bolts/Nuts

    Project: UP#30-2 Activity: SEC2S22170 Chainage 8+805 to 8+905 Pipe Laying and Fitting Installation

    Project: UP#30-2 Activity: SEC2S22180 Chainage 9+105 to 9+205 Pipe Laying and Fitting Installation

    Project: UP#30-2 Activity: SEC2S22190 Chainage 8+905 to 9+005 Pipe Laying and Fitting Installation

    Project: UP#30-2 Activity: SEC2S22200 CH-141 - Insulation Gaskets & Torquing

    Project: UP#30-2 Activity: SEC2S22210 Chainage 9+205 to 9+250 Pipe Laying and Fitting Installation

    Project: UP#30-2 Activity: SEC2S22220 CH-147- MOV installation, Insulation Gaskets & Tourquing

    Project: UP#30-2 Activity: SEC2S22230 CH-148- MOV installation, Insulation Gaskets & Tourquing

    Project: UP#30-2 Activity: SEC2S22240 CH-142 - Insulation Gaskets & Torquing

    Project: UP#30-2 Activity: SEC2S22250 Chainage 9+005 to 9+105 Pipe Laying and Fitting Installation

  • 8/17/2019 Sched Logasd

    23/34

    Project: UP#30-2 Activity: SEC2S22260 LPD-36 & LPD-37 - Installation

    Project: UP#30-2 Activity: SEC2S22270 HPV-36,HPV-37 & HPV-38 - Installation

    Project: UP#30-2 Activity: SEC2S22280 Tie-In Works to CH-21

    Project: UP#30-2 Activity: SEC2S22290 Tie-In Works to CH-22

    Project: UP#30-2 Activity: SEC2S22300 CH-149- MOV installation, Insulation Gaskets & Tourquing

    Project: UP#30-2 Activity: SEC2S22310 CH-102 - Insulation Gaskets & Torquing

    Project: UP#30-2 Activity: SEC2S22320 LPD-01 & LPD-02 - Mechanical Installation Works

    Project: UP#30-2 Activity: SEC2S22330 CH-104 - Insulating Gasket, Torquing & Platform Works

    Project: UP#30-2 Activity: SEC2S22340 Blanking at Chainage 0+040

    Project: UP#30-2 Activity: SEC2S22350 HPV-03 & HPV-04 - Mechanical Installation Works

    Project: UP#30-2 Activity: SEC2S22360 Reinstall DBB Valves

    Project: UP#30-2 Activity: SEC2S22370 Communication Establishment (SCADA System)

    Project: UP#30-2 Activity: SEC2S22380 Signal Testing, Integration and Modification Works of Existing SCADA SystemProject: UP#30-2 Activity: SEC2S22390 SAT and

    PTP TEST (SCADA System)Project: UP#30-2 Activity: SEC2S22400 E&I Cabl

    e Laying in Section 2 (except Cables connected to SS 1164)Project: UP#30-2 Activity: SEC2S22410 E&I Cabl

    e laying in Section2 - Cables connected to SS 1164Project: UP#30-2 Activity: SEC2S22420 Access t

    o SS 1164Project: UP#30-2 Activity: SEC2S22430 Cable Du

    ct Civil Work Completion Section 2Project: UP#30-2 Activity: SEC2S22440 E&I Cabl

    e laying in Section 2 - Main CablesProject: UP#30-2 Activity: SEC2S22450 E&I Cable Laying in Section 3 (Except Main Cables)

    Project: UP#30-2 Activity: SEC2S22460 Cable Duct Civil Works Completion Section 3

    Project: UP#30-2 Activity: SEC2S22470 E&I Cable Laying in Section 3 (Main Cables)

    Project: UP#30-2 Activity: SEC2S22480 E&I Cable Laying in Section 4 (except new Apron chambers)

    Project: UP#30-2 Activity: SEC2S22490 Cable Duct Civil Works Completion Section 4

    Project: UP#30-2 Activity: SEC2S22500 E&I Cable Laying in Section 4 (Main Cables)

    Project: UP#30-2 Activity: SEC2S22510 Cable Duct Civil Work Completion (New Aprons)

    Project: UP#30-2 Activity: SEC2S22520 E&I Cable Laying in Section 4 - New Apron Chambers

    Project: UP#30-2 Activity: SEC2S22530 E&I Cable Laying in Section 1 (Except Main Cables)

    Project: UP#30-2 Activity: SEC2S22540 Cable Duct Civil Work Completion Section 1

    Project: UP#30-2 Activity: SEC2S22550 E&I Cable Laying in Section 1 (Main Cables)

  • 8/17/2019 Sched Logasd

    24/34

    Project: UP#30-2 Activity: SEC2S22560 Cable Duct Civil Work Completion (VO)

    Project: UP#30-2 Activity: SEC2S22570 E&I Cable Laying in Section 1 (VO)

    Project: UP#30-2 Activity: SEC2S22580 E&I Cable Laying in Section 5 (Except Fuel Farm Control Room)

    Project: UP#30-2 Activity: SEC2S22590 Cable Duct Civil Work Completion Section 5

    Project: UP#30-2 Activity: SEC2S22600 E&I Cable Laying in Section 5 (Fuel Farm Control Room)

    Project: UP#30-2 Activity: SEC2S22610 E&I Cable Laying in Section 6

    Project: UP#30-2 Activity: SEC2S22620 Cable Duct Civil Work Completion Section 6

    Project: UP#30-2 Activity: SEC2S22630 E&I Cable Laying in Section 6 (Main Cables)

    Project: UP#30-2 Activity: SEC2S22640 Cable Duct Civil Work Completion Section 7

    Project: UP#30-2 Activity: SEC2S22650 E&I Cable Laying in Section 7

    Project: UP#30-2 Activity: SEC2S22660 E&I Cable Laying in Section 7 (Main Cables)

    Project: UP#30-2 Activity: SEC2S22670 Nitrogen Purging Loop 4.1 & 4.2 - T&C Preparation All HPs/LPs/VCs

    Project: UP#30-2 Activity: SEC2S22680 Nitrogen Purging Loop 4.1 & 4.2 - CH-103 T&C Spools Instln RRCProject: UP#30-2 Activity: SEC2S22690 Nitrogen

     Purging Loop 4.1 & 4.2 - Pneumatic, Air Blowing & Drying - Loop 4.1Project: UP#30-2 Activity: SEC2S22700 Nitrogen

     Purging Loop 4.1 & 4.2 - Nitrogen Filling - Loop 4.1Project: UP#30-2 Activity: SEC2S22710 Nitrogen

     Purging Loop 4.1 & 4.2 - Pneumatic, Air Blowing & Drying - Loop 4.2Project: UP#30-2 Activity: SEC2S22720 Nitrogen

     Purging Loop 4.1 & 4.2 - Nitrogen Filling - Loop 4.2Project: UP#30-2 Activity: SEC2S22730 Nitrogen

     Purging Loop 3.1 & 3.2 -T&C Preparation All HPs/LPsProject: UP#30-2 Activity: SEC2S22740 Nitrogen

     Purging Loop 3.1 & 3.2 - CH-103 T&C Spools Instln RRCProject: UP#30-2 Activity: SEC2S22750 Nitrogen Purging Loop 3.1 & 3.2 - Pneumatic, Air Blowing & Drying - Loop 3.1

    Project: UP#30-2 Activity: SEC2S22760 Nitrogen Purging Loop 3.1 & 3.2 - Nitrogen Filling - Loop 3.1

    Project: UP#30-2 Activity: SEC2S22770 Nitrogen Purging Loop 3.1 & 3.2 - Pneumatic, Air Blowing & Drying - Loop 3.2

    Project: UP#30-2 Activity: SEC2S22780 Nitrogen Purging Loop 3.1 & 3.2 - Nitrogen Filling - Loop 3.2

    Project: UP#30-2 Activity: SEC2S22790 Nitrogen Purging Loop 1.3 & 1.4 - T&C Preparation All HPs/LPs

    Project: UP#30-2 Activity: SEC2S22800 Nitrogen Purging Loop 1.3 & 1.4 - CH-133 T&C Spools Instln RRC

    Project: UP#30-2 Activity: SEC2S22810 Nitrogen Purging Loop 1.3 & 1.4 - Pneumatic, Air Blowing & Drying - Loop 1.3

    Project: UP#30-2 Activity: SEC2S22820 Nitrogen Purging Loop 1.3 & 1.4 - Nitrogen Filling - Loop 1.3

    Project: UP#30-2 Activity: SEC2S22830 Nitrogen Purging Loop 1.3 & 1.4 - Pneumatic, Air Blowing & Drying - Loop 1.4

    Project: UP#30-2 Activity: SEC2S22840 Nitrogen Purging Loop 1.3 & 1.4 - Nitrogen Filling - Loop 1.4

    Project: UP#30-2 Activity: SEC2S22850 Nitrogen Purging Loop 1.1 & 1.2 - T&C Preparation All HPs/LPs/VCs

  • 8/17/2019 Sched Logasd

    25/34

    Project: UP#30-2 Activity: SEC2S22860 Nitrogen Purging Loop 1.1 & 1.2 - CH-139 T&C Spools Instln RRC

    Project: UP#30-2 Activity: SEC2S22870 Nitrogen Purging Loop 1.1 & 1.2 - Pneumatic, Air Blowing & Drying - Loop 1.1

    Project: UP#30-2 Activity: SEC2S22880 Nitrogen Purging Loop 1.1 & 1.2 - Nitrogen Filling - Loop 1.1

    Project: UP#30-2 Activity: SEC2S22890 Nitrogen Purging Loop 1.1 & 1.2 - Pneumatic, Air Blowing & Drying - Loop 1.2

    Project: UP#30-2 Activity: SEC2S22900 Nitrogen Purging Loop 1.1 & 1.2 - Nitrogen Filling - Loop 1.2

    Project: UP#30-2 Activity: SEC2S22910 Nitrogen Purging Loop 5.1 & 5.2 - T&C Preparation All HPs/LPs

    Project: UP#30-2 Activity: SEC2S22920 Nitrogen Purging Loop 5.1 & 5.2 - CH-140 T&C Spools Instln RRC

    Project: UP#30-2 Activity: SEC2S22930 Nitrogen Purging Loop 5.1 & 5.2 - Pneumatic, Air Blowing & Drying - Loop 5.1

    Project: UP#30-2 Activity: SEC2S22940 Nitrogen Purging Loop 5.1 & 5.2 - Nitrogen Filling - Loop 5.1

    Project: UP#30-2 Activity: SEC2S22950 Nitrogen Purging Loop 5.1 & 5.2 - Pneumatic, Air Blowing & Drying - Loop 5.2

    Project: UP#30-2 Activity: SEC2S22960 Nitrogen Purging Loop 5.1 & 5.2 - Nitrogen Filling - Loop 5.2

    Project: UP#30-2 Activity: SEC2S22970 Nitrogen Purging Loop 2.1 & 2.2 - T&C Preparation All HPs/LPs

    Project: UP#30-2 Activity: SEC2S22980 Nitrogen Purging Loop 2.1 & 2.2 - CH-133 T&C Spools Instln RRCProject: UP#30-2 Activity: SEC2S22990 Nitrogen

     Purging Loop 2.1 & 2.2 - Pneumatic, Air Blowing & Drying - Loop 2.1Project: UP#30-2 Activity: SEC2S23000 Nitrogen

     Purging Loop 2.1 & 2.2 - Nitrogen Filling - Loop 2.1Project: UP#30-2 Activity: SEC2S23010 Nitrogen

     Purging Loop 2.1 & 2.2 - Pneumatic, Air Blowing & Drying - Loop 2.2Project: UP#30-2 Activity: SEC2S23020 Nitrogen

     Purging Loop 2.1 & 2.2 - Nitrogen Filling - Loop 2.2Project: UP#30-2 Activity: SEC2S31000 CH101A -

     Trench Civil Work CompletionProject: UP#30-2 Activity: SEC2S31010 CH101A -

     Main Pipe Line Laying & Fit UpProject: UP#30-2 Activity: SEC2S31020 CH101A - Main Pipe Line Welding

    Project: UP#30-2 Activity: SEC2S31030 CH101A - RT Works / Painting/Wrap

    Project: UP#30-2 Activity: SEC2S31040 CH101A - Puddle Flange & Link Seal Insulation

    Project: UP#30-2 Activity: SEC2S31050 CH101A - Concrete Casting Surrounding the Puddle Flange

    Project: UP#30-2 Activity: SEC2S31060 CH101A - LDS conduit Installation

    Project: UP#30-2 Activity: SEC2S31070 CH101A - Installation of End Seal

    Project: UP#30-2 Activity: SEC2S31080 CH101A - Chamber Backfilling

    Project: UP#30-2 Activity: SEC2S31090 CH101A - Chamber Handover for Mechanical Work

    Project: UP#30-2 Activity: SEC2S31100 CH101A - Pipe Fabrication & Installation of DBB Valves

    Project: UP#30-2 Activity: SEC2S31110 CH101A - Pipe Welding

    Project: UP#30-2 Activity: SEC2S31120 CH101A - RT Works

  • 8/17/2019 Sched Logasd

    26/34

    Project: UP#30-2 Activity: SEC2S31130 CH101A - Drain / Vent Installation

    Project: UP#30-2 Activity: SEC2S31140 CH101A - Painting/Wrap

    Project: UP#30-2 Activity: SEC2S31150 CH101A - Pipe Support Installation & Anchor Bolts

    Project: UP#30-2 Activity: SEC2S31160 CH101A - Insulation Gasket Kit Installation & Tourquing

    Project: UP#30-2 Activity: SEC2S31170 CH101A - Platform Installation

    Project: UP#30-2 Activity: SEC2S31180 CH101A - Grating Installation

    Project: UP#30-2 Activity: SEC2S31190 CH101A - Manhole Cover installation with Top Slab Cover

    Project: UP#30-2 Activity: SEC2S31200 CH101A - Cable Tray & Support Installation

    Project: UP#30-2 Activity: SEC2S31210 CH101A - Installation of Junction Boxes

    Project: UP#30-2 Activity: SEC2S31220 CH101A - Instruments Installation

    Project: UP#30-2 Activity: SEC2S31230 CH101A - Installation of Earthling Material

    Project: UP#30-2 Activity: SEC2S31240 CH101A - MOV Isolator Installation

    Project: UP#30-2 Activity: SEC2S31250 CH156 -Trench Civil Work CompletionProject: UP#30-2 Activity: SEC2S31260 CH156 -

    36" Tee InstallationProject: UP#30-2 Activity: SEC2S31270 CH156 -

    36" Tee WeldingProject: UP#30-2 Activity: SEC2S31280 CH156 -

    24" Pipe Fit-upProject: UP#30-2 Activity: SEC2S31290 CH156 -

    6" Weldolet Joints Fit-upProject: UP#30-2 Activity: SEC2S31300 CH156 -

    24" Pipe WeldingProject: UP#30-2 Activity: SEC2S31310 CH156 -

    RT Works Project: UP#30-2 Activity: SEC2S31320 CH156 -6" Weldolet Joints Welding

    Project: UP#30-2 Activity: SEC2S31330 CH156 -Painting/Wrap

    Project: UP#30-2 Activity: SEC2S31340 CH156 -Puddle Flange & Link Seal Insulation

    Project: UP#30-2 Activity: SEC2S31350 CH156 -Concrete Casting Surrounding the Puddle Flange

    Project: UP#30-2 Activity: SEC2S31360 CH156 -LDS conduit Installation

    Project: UP#30-2 Activity: SEC2S31370 CH156 -Installation of End Seal

    Project: UP#30-2 Activity: SEC2S31380 CH156 -Chamber FInal Backfilling

    Project: UP#30-2 Activity: SEC2S31390 CH156 -Chamber Handover for Mechanical Works

    Project: UP#30-2 Activity: SEC2S31420 CH156 -RT Works

    Project: UP#30-2 Activity: SEC2S31440 CH156 -Painting/Wrap

    Project: UP#30-2 Activity: SEC2S31450 CH156 -Pipe Support Installation & Anchor Bolts

  • 8/17/2019 Sched Logasd

    27/34

    Project: UP#30-2 Activity: SEC2S31470 CH156 -Platform Installation

    Project: UP#30-2 Activity: SEC2S31480 CH156 -Grating Installation

    Project: UP#30-2 Activity: SEC2S31490 CH156 -Manhole Cover installation with Top Slab Cover

    Project: UP#30-2 Activity: SEC2S31500 CH156 -Cable Tray & Support Installation

    Project: UP#30-2 Activity: SEC2S31510 CH156 -Installation of Junction Boxes

    Project: UP#30-2 Activity: SEC2S31520 CH156 -Instruments Installation

    Project: UP#30-2 Activity: SEC2S31530 CH156 -Installation of Earthling Material

    Project: UP#30-2 Activity: SEC2S31540 CH156 -MOV Isolator Installation

    Project: UP#30-2 Activity: SEC2S31550 CH155 -Trench Civil Work Completion

    Project: UP#30-2 Activity: SEC2S31560 CH155 -36" Tee Installation

    Project: UP#30-2 Activity: SEC2S31570 CH155 -24" Pipe Fit-up

    Project: UP#30-2 Activity: SEC2S31580 CH155 -36" Tee Welding

    Project: UP#30-2 Activity: SEC2S31590 CH155 -24" Pipe WeldingProject: UP#30-2 Activity: SEC2S31600 CH155 -

    RT WorksProject: UP#30-2 Activity: SEC2S31610 CH155 -

    Painting/WrapProject: UP#30-2 Activity: SEC2S31620 CH155 -

    Puddle Flange & Link Seal InsulationProject: UP#30-2 Activity: SEC2S31630 CH155 -

    Concrete Casting Surrounding the Puddle FlangeProject: UP#30-2 Activity: SEC2S31640 CH155 -

    LDS conduit InstallationProject: UP#30-2 Activity: SEC2S31650 CH155 -

    Installation of End SealProject: UP#30-2 Activity: SEC2S31660 CH155 -Chamber Final Backfilling

    Project: UP#30-2 Activity: SEC2S31670 CH155 -Chamber Handover for Mechanical Work

    Project: UP#30-2 Activity: SEC2S31700 CH155 -RT Works

    Project: UP#30-2 Activity: SEC2S31720 CH155 -Painting/Wrap

    Project: UP#30-2 Activity: SEC2S31730 CH155 -Pipe Support Installation & Anchor Bolts

    Project: UP#30-2 Activity: SEC2S31750 CH155 -Platform Installation

    Project: UP#30-2 Activity: SEC2S31760 CH155 -Grating Installation

    Project: UP#30-2 Activity: SEC2S31770 CH155 -Manhole Cover installation with Top Slab Cover

    Project: UP#30-2 Activity: SEC2S31780 CH155 -Cable Tray & Support Installation

    Project: UP#30-2 Activity: SEC2S31790 CH155 -Installation of Junction Boxes

    Project: UP#30-2 Activity: SEC2S31800 CH155 -Instruments Installation

  • 8/17/2019 Sched Logasd

    28/34

    Project: UP#30-2 Activity: SEC2S31810 CH155 -Installation of Earthling Material

    Project: UP#30-2 Activity: SEC2S31820 CH155 -MOV Isolator Installation

    Project: UP#30-2 Activity: SEC2S31830 CH154 -Chamber Handover for Mechanical Work

    Project: UP#30-2 Activity: SEC2S31840 CH154 -Cutting of Pipes

    Project: UP#30-2 Activity: SEC2S31850 CH154 -Installation of Link Seal

    Project: UP#30-2 Activity: SEC2S31860 CH154 -Puddle Flange Installation

    Project: UP#30-2 Activity: SEC2S31870 CH154 -Tempoaray Installation of Spool Piece

    Project: UP#30-2 Activity: SEC2S31880 CH154 -Concrete Casting Surrounding the Puddle Flange

    Project: UP#30-2 Activity: SEC2S31890 CH154 -Installation of End Seal

    Project: UP#30-2 Activity: SEC2S31900 CH154 -Anchor Bolts for Pipe Support

    Project: UP#30-2 Activity: SEC2S31910 CH154 -Final Backfilling

    Project: UP#30-2 Activity: SEC2S31920 CH154 -Pipe Support Installation

    Project: UP#30-2 Activity: SEC2S31930 CH154 -PIpe Spool PreparationProject: UP#30-2 Activity: SEC2S31940 CH154 -

    Assembly of Flanges with DBB ValvesProject: UP#30-2 Activity: SEC2S31950 CH154 -

    36" Piping Installation with DBB Valves InstallationProject: UP#30-2 Activity: SEC2S31960 CH154 -

    36" Welding WorksProject: UP#30-2 Activity: SEC2S31970 CH154 -

    Radiography TestingProject: UP#30-2 Activity: SEC2S31980 CH154 -

    Installation of Ball Valve With FlangesProject: UP#30-2 Activity: SEC2S31990 CH154 -

    Drain/Vent InstallationProject: UP#30-2 Activity: SEC2S32000 CH154 -24" Pipe Installation

    Project: UP#30-2 Activity: SEC2S32010 CH154 -24" Welding Works

    Project: UP#30-2 Activity: SEC2S32020 CH154 -Painting/Wrap

    Project: UP#30-2 Activity: SEC2S32030 CH154 -Insulation Gasket Kit Installation

    Project: UP#30-2 Activity: SEC2S32040 CH154 -Torquing

    Project: UP#30-2 Activity: SEC2S32050 CH154 -Platform Installation

    Project: UP#30-2 Activity: SEC2S32060 CH154 -Manhole Cover installation with Top Slab Cover

    Project: UP#30-2 Activity: SEC2S32070 CH154 -Cable Tray & Support Installation

    Project: UP#30-2 Activity: SEC2S32080 CH154 -Installation of Junction Boxes

    Project: UP#30-2 Activity: SEC2S32090 CH154 -Instruments Installation

    Project: UP#30-2 Activity: SEC2S32100 CH154 -Installation of Earthling Material

  • 8/17/2019 Sched Logasd

    29/34

    Project: UP#30-2 Activity: SEC2S32110 CH154 -MOV Isolator Installation

    Project: UP#30-2 Activity: SEC2S32120 New Apron Loop - Continuity & Loop Checking

    Project: UP#30-2 Activity: SEC2S32130 New Apron Loop - Installation of Earthing Material

    Project: UP#30-2 Activity: SEC2S32140 New Apron Loop - Cathodic Protection System Works

    Project: UP#30-2 Activity: SEC2S32150 New Apron Loop - FDB & SDB Installation

    Project: UP#30-2 Activity: SEC2S32160 New Apron Loop - Cable Ducts Civil Work Completion

    Project: UP#30-2 Activity: SEC2S32170 New Apron Loop - LD Sensor Cable Laying

    Project: UP#30-2 Activity: SEC2S32180 New Apron Loop - LDS Sensor Cable termination

    Project: UP#30-2 Activity: SEC2S32190 New Apron Loop - LD Jumper Cable Laying

    Project: UP#30-2 Activity: SEC2S32200 New Apron Loop - LDS Jumper Cable termination

    Project: UP#30-2 Activity: SEC2S32210 New Apron Loop - Instrument & Control Cable Laying

    Project: UP#30-2 Activity: SEC2S32220 New Apron Loop - Instrument & Control Cable Termination

    Project: UP#30-2 Activity: SEC2S32230 New Apron Loop - Power Cable LayingProject: UP#30-2 Activity: SEC2S32240 New Apro

    n Loop - Earth Cable LayingProject: UP#30-2 Activity: SEC2S32250 New Apro

    n Loop - Power Cable TerminationProject: UP#30-2 Activity: SEC2S32260 New Apro

    n Loop - Earth Cable TerminationProject: UP#30-2 Activity: SEC2S32270 New Apro

    n Loop - Instrument & Control Cable Loop TestingProject: UP#30-2 Activity: SEC2S32280 New Apro

    n Loop - Testing and Commissioning of Field Instruments, ESD and MOV after Field Modification

    Project: UP#30-2 Activity: SEC2S32340 CH-102 to CH-101 Nitrogen Purging - Setting-up & PreparationProject: UP#30-2 Activity: SEC2S32350 CH-102 t

    o CH-101 Nitrogen Purging - Pneumatic TestingProject: UP#30-2 Activity: SEC2S32360 CH-102 t

    o CH-101 Nitrogen Purging - Air BlowingProject: UP#30-2 Activity: SEC2S32370 CH-102 t

    o CH-101 Nitrogen Purging - DryingProject: UP#30-2 Activity: SEC2S32380 CH-102 t

    o CH-101 Nitrogen Purging - Nitrogen PurgingProject: UP#30-2 Activity: SEC2S32390 Software

     Development - VO37 (AJF/MJF INterface)Project: UP#30-2 Activity: SEC2S32400 System B

    uilt - VO37 (AJF/MJF INterface)Project: UP#30-2 Activity: SEC2S32410 Sytem Te

    sting - VO37 (AJF/MJF INterface)Project: UP#30-2 Activity: SEC2S32420 Integrat

    ed FAT- VO37 (AJF/MJF INterface)Project: UP#30-2 Activity: SEC2S32430 Fuel Far

    m and Control Room AvailabilityProject: UP#30-2 Activity: SEC2S32440 Installa

    tion and Testing Works Related to AJF/MJF InterfaceProject: UP#30-2 Activity: SEC2S32450 Pre-Comm

  • 8/17/2019 Sched Logasd

    30/34

    issioning - VO37 (AJF/MJF INterface)Project: UP#30-2 Activity: SEC2S32460 Commissi

    oning - VO37 (AJF/MJF INterface)Project: UP#30-2 Activity: SEC2S41000 Fuel Far

    m AvailabilityProject: UP#30-2 Activity: SEC2S41080 Loop 1B

    - Pressure Testing of Loop 1B & Loop 1AProject: UP#30-2 Activity: SEC2S41100 Loop 1B

    - Removal of BFs from DBB in CH-139 & Connection to Pump SkidProject: UP#30-2 Activity: SEC2S41110 Loop 1B

    - Rearrangements as part of 1B Flushing CommencementProject: UP#30-2 Activity: SEC2S41150 Loop 1B

    - Draining of Sections Between VCs & Installation of HP/LP AssembliesProject: UP#30-2 Activity: SEC2S41160 Loop 1A

    - Preparation & Set-upProject: UP#30-2 Activity: SEC2S41170 Loop 1A

    - Installation of Christmas Trees on HPs & LPsProject: UP#30-2 Activity: SEC2S41180 Loop 1A

    - Fuel Filling in Loop 1B & Loop 1AProject: UP#30-2 Activity: SEC2S41190 Loop 1A

    - Soak Testing of Loop 1B & Loop 1AProject: UP#30-2 Activity: SEC2S41200 Loop 1A

    - Pressure Testing of Loop 1B & Loop 1AProject: UP#30-2 Activity: SEC2S41210 Loop 1A

    - Soak Test Sample & ApprovalProject: UP#30-2 Activity: SEC2S41220 Loop 1A- Partial Draining between CH-134 & CH135A

    Project: UP#30-2 Activity: SEC2S41230 Loop 1A- Removal of BFs from Hydrant Risers & Installation of 6x4 Isolation Valve

    Project: UP#30-2 Activity: SEC2S41240 Loop 1A- Partial Draining between CH-136 & CH137

    Project: UP#30-2 Activity: SEC2S41250 Loop 1A- Removal of BFs from Hydrant Risers & Installation of 6x4 Isolation Valve

    Project: UP#30-2 Activity: SEC2S41260 Loop 1A- Installation Christmas Trees on All HRs at 2 Cargo Loops

    Project: UP#30-2 Activity: SEC2S41310 Loop 1A- Removal & Relocation of Flushing Equipments from CH-139 to CH-112

    Project: UP#30-2 Activity: SEC2S41420 Loop 2A- Pressure Testing of Loop 2AProject: UP#30-2 Activity: SEC2S41430 Loop 2A

    - Removal of Blind Flanges in DBB from CH-112 & Connection to Pump SkidProject: UP#30-2 Activity: SEC2S41480 Loop 2A

    - Partial Draining of Sections Between CH-111 & CH-133Project: UP#30-2 Activity: SEC2S41490 Loop 2A

    - Removal of Christmas Trees Between CH-111 & CH-133Project: UP#30-2 Activity: SEC2S41500 Loop 2A

    - Installation of HP/LP Assemblies Between CH-111 & CH-133Project: UP#30-2 Activity: SEC2S41600 Loop 2B

    - Flushing & Filtration of Risers & Millipore TestProject: UP#30-2 Activity: SEC2S41610 Loop 2B

    - API FiltrationProject: UP#30-2 Activity: SEC2S41620 Loop 2B

    - Partial Draining of Sections Between CH-111 & CH-133Project: UP#30-2 Activity: SEC2S41630 Loop 2B

    - Removal of Christmas Trees Between CH-111 & CH-133Project: UP#30-2 Activity: SEC2S41640 Loop 2B

    - Installation of HP/LP Assemblies Between CH-111 & CH-133Project: UP#30-2 Activity: SEC2S41650 Loop 2C

    - Preparation & Set-upProject: UP#30-2 Activity: SEC2S41660 Loop 2C

  • 8/17/2019 Sched Logasd

    31/34

    - Installation of Christmas Trees on HPs & LPsProject: UP#30-2 Activity: SEC2S41670 Loop 2C

    - Fuel Filling in Loop 2B & 2C through Loop 2AProject: UP#30-2 Activity: SEC2S41680 Loop 2C

    - Soak Testing of Loop 2B & 2CProject: UP#30-2 Activity: SEC2S41690 Loop 2C

    - Pressure Testing of Loop 2B & 2CProject: UP#30-2 Activity: SEC2S41700 Loop 2C

    - Soak Test Sample & ApprovalProject: UP#30-2 Activity: SEC2S41710 Loop 2C

    - Flushing & Filtration for Mainline & Millipore TestProject: UP#30-2 Activity: SEC2S41720 Loop 2C

    - Flushing & Filtration of Risers & Millipore TestProject: UP#30-2 Activity: SEC2S41730 Loop 2C

    - API FiltrationProject: UP#30-2 Activity: SEC2S41740 Loop 2C

    - Partial Draining of SectionsProject: UP#30-2 Activity: SEC2S41750 Loop 2C

    - Removal of Christmas TreesProject: UP#30-2 Activity: SEC2S41760 Loop 2C

    - Installation of HP/LP AssembliesProject: UP#30-2 Activity: SEC2S41870 Loop 3A

    - Fuel FillingProject: UP#30-2 Activity: SEC2S41880 Loop 3A

    - Soak Testing Project: UP#30-2 Activity: SEC2S41890 Loop 3A- Pressure Testing

    Project: UP#30-2 Activity: SEC2S41900 Loop 3A- Soak Test Sample Approval

    Project: UP#30-2 Activity: SEC2S41910 Loop 3A- Draining of Line 1

    Project: UP#30-2 Activity: SEC2S41920 Loop 3A- Flip Spectacle Blind and Install Flushing Manifold

    Project: UP#30-2 Activity: SEC2S41930 Loop 3A- Flushing of Mainline & Millipore Test of Line 1

    Project: UP#30-2 Activity: SEC2S41940 Loop 3A- Draining of Line 1

    Project: UP#30-2 Activity: SEC2S41950 Loop 3A- Flip Spectacle Blind and Remove Flushing ManifoldProject: UP#30-2 Activity: SEC2S41960 Loop 3A

    - Install Permanent PipingProject: UP#30-2 Activity: SEC2S41970 Loop 3A

    - Draining of Line 2Project: UP#30-2 Activity: SEC2S41980 Loop 3A

    - Flip Spectacle Blind and Install Flushing ManifoldProject: UP#30-2 Activity: SEC2S41990 Loop 3A

    - Flushing of Mainline & Millipore Test of Line 2Project: UP#30-2 Activity: SEC2S42000 Loop 3A

    - Draining of Line 2Project: UP#30-2 Activity: SEC2S42010 Loop 3A

    - Flip Spectacle Blind and Remove Flushing ManifoldProject: UP#30-2 Activity: SEC2S42020 Loop 3A

    - Install Permanent PipingProject: UP#30-2 Activity: SEC2S42030 Loop 3A

    - Re-Pressurizing to System PressureProject: UP#30-2 Activity: VO01 Backfill Trenche

    s MV & FO East & West LinesNew ActivityProject: UP#30-2 Activity: VO02 Code E Islands D

    escopeProject: UP#30-2 Activity: VO03 Hydrant Fuel Cas

  • 8/17/2019 Sched Logasd

    32/34

    ingsProject: UP#30-2 Activity: VO04 AGL TransformersProject: UP#30-2 Activity: VO05 MV substations R

    esizeProject: UP#30-2 Activity: VO06 FATO RelocationProject: UP#30-2 Activity: VO06-1 FATO RelocationProject: UP#30-2 Activity: VO07 Zones 1 & 2 Leve

    l DifferencesProject: UP#30-2 Activity: VO08 Fire Hydrant Pit

    sProject: UP#30-2 Activity: VO09 EMCA - RC Pipe C

    oncrete Surround ReinforcementProject: UP#30-2 Activity: VO10 Primary Cable Co

    nnectorsProject: UP#30-2 Activity: VO11 2 Additional CCR

     rated 30kWProject: UP#30-2 Activity: VO12 AGL F900 Chamber

    sProject: UP#30-2 Activity: VO13 AGL Pits Type 1

    - 1000x1000mmProject: UP#30-2 Activity: VO14-1 MART MJF Redesig

    nProject: UP#30-2 Activity: VO14-2 MART MJF Redesig

    n

    Project: UP#30-2 Activity: VO15 AOA Gate HouseProject: UP#30-2 Activity: VO15-1 AOA Gate HouseProject: UP#30-2 Activity: VO16 AGL CATIIIBProject: UP#30-2 Activity: VO17 Site AmbulancesProject: UP#30-2 Activity: VO18 MJF Control Room

     & TMSProject: UP#30-2 Activity: VO19 Not UsedProject: UP#30-2 Activity: VO20 DVOR Monitor Ant

    enna RelocationProject: UP#30-2 Activity: VO22 MART Stormwater

    & Firefighting LinesProject: UP#30-2 Activity: VO23 Flush KerbProject: UP#30-2 Activity: VO24 MJF Concrete Col

    lars Project: UP#30-2 Activity: VO25 AOA Temp Fence - Patrol Road

    Project: UP#30-2 Activity: VO26 Taxiway F - AGLLights Replacement

    Project: UP#30-2 Activity: VO27 A-SMGCS DescopeProject: UP#30-2 Activity: VO28 Fire Main Tie -

    in PointsProject: UP#30-2 Activity: VO29 Fire Fighting at

     D4Project: UP#30-2 Activity: VO30 MV Network & Sta

    ndby PowerProject: UP#30-2 Activity: VO31 Optional Item -

    Bill 3 - Fencing BarriersProject: UP#30-2 Activity: VO32-1 SCADA System - A

    dditional BudgetProject: UP#30-2 Activity: VO32-2 SCADA System - A

    dditional BudgetProject: UP#30-2 Activity: VO33 MJF - Security G

    ate ObstructionProject: UP#30-2 Activity: VO34 External Access

    Roads - SubstationsProject: UP#30-2 Activity: VO35 MART AGL Primary

  • 8/17/2019 Sched Logasd

    33/34

     Cable JointsProject: UP#30-2 Activity: VO36 Not UsedProject: UP#30-2 Activity: VO37 AJF/MJF Interfac

    eProject: UP#30-2 Activity: VO38 MJF Hydrant Cont

    rol Work Pk. 1Project: UP#30-2 Activity: VO39 Not UsedProject: UP#30-2 Activity: VO40 B2 Road Underpas

    s Fence RemovalProject: UP#30-2 Activity: VO41 Pavement Marking

    s - ThermoplasticProject: UP#30-2 Activity: VO42 Not UsedProject: UP#30-2 Activity: VO43 Surface Protecti

    on OmissionProject: UP#30-2 Activity: VO44 Step Irons AGL C

    hambersProject: UP#30-2 Activity: VO45 Generators 4 Sta

    ndsProject: UP#30-2 Activity: VO46 MJF CH-0138 Wall

     ModificationsProject: UP#30-2 Activity: VO47 Not UsedProject: UP#30-2 Activity: VO48 MV & FOC Modific

    ationsProject: UP#30-2 Activity: VO49 Not Used

    Project: UP#30-2 Activity: VO50 Taxiway F4 RemarkingProject: UP#30-2 Activity: VO51 Earthworks - 31LProject: UP#30-2 Activity: VO52 Not UsedProject: UP#30-2 Activity: VO53 Cargo Stands Bar

    riersProject: UP#30-2 Activity: VO54 Leak Detection C

    able Redundancy WorksProject: UP#30-2 Activity: VO55 Foreman DayworksProject: UP#30-2 Activity: VO56 Cable Ducts Near

     New Fuel DepotProject: UP#30-2 Activity: VO57 Pavement Marking

    s

    Project: UP#30-2 Activity: VO58 Signage AdditionalProject: UP#30-2 Activity: VO59 Signage Amendmen

    tsProject: UP#30-2 Activity: VO60 Earthworks at Ta

    xiways E13 & E14Project: UP#30-2 Activity: VO61 RVR Gantry TowerProject: UP#30-2 Activity: VO62 Not UsedProject: UP#30-2 Activity: VO63 Barrier Preparat

    ion for HLGProject: UP#30-2 Activity: VO64 Generators 9 Sta

    ndsProject: UP#30-2 Activity: VO65 Fire Extinguishe

    rs for Cargo Apron StandsProject: UP#30-2 Activity: VO66 Not UsedProject: UP#30-2 Activity: VO67 Not UsedProject: UP#30-2 Activity: VO68 Not UsedProject: UP#30-2 Activity: VO69 Stop Bar TWY C (

    Near TWY H)Project: UP#30-2 Activity: VO70 A3 Road Stormwat

    er line realignmentProject: UP#30-2 Activity: VO71 Not UsedProject: UP#30-2 Activity: VO72 MJF Hydrant Cont

  • 8/17/2019 Sched Logasd

    34/34

    rol Work CH101, CH21, CH22 & 700 StandsProject: UP#30-2 Activity: VO73 Not UsedProject: UP#30-2 Activity: VO74 Not UsedProject: UP#30-2 Activity: VO75 Not UsedProject: UP#30-2 Activity: VO76 FATO Additional

    DesignProject: UP#30-2 Activity: VO77 EMCA - Generator

    s 12 Stands (MAY - AUG)Project: UP#30-2 Activity: VO78 TWY G&H AGL Duct

     CrossingProject: UP#30-2 Activity: VO79 ADAC Stoppage of

     WorkProject: UP#30-2 Activity: VO80 Lead-on Lighting

     Taxiway D9Project: UP#30-2 Activity: VO81 TWY H AGLProject: UP#30-2 Activity: VO82 TWY H CL Marking

    sProject: UP#30-2 Activity: VO83 A3 Road Formatio

    nProject: UP#30-2 Activity: VO84 Not UsedProject: UP#30-2 Activity: VO85 AGL Primary Cabl

    e Laying ConstraintsProject: UP#30-2 Activity: VO86 Not UsedProject: UP#30-2 Activity: VO87 Taxiway D6 AGL R

    erouting Project: UP#30-2 Activity: VO88 11kV Cable Identification

    Project: UP#30-2 Activity: VO89 Distribution Boxes Relocation

    Project: UP#30-2 Activity: VO90-1 Optional Items Descope

    Project: UP#30-2 Activity: VO90-2 Optional Items Descope

    Project: UP#30-2 Activity: VO90-3 Optional Items Descope

    Project: UP#30-2 Activity: VO91 Not UsedProject: UP#30-2 Activity: VO92 Stop bar at Taxi

    way D Project: UP#30-2 Activity: VO93 AGL Primary Cable Duct Rerouting

    Project: UP#30-2 Activity: VO94 400 Hz Cable