Scandic Hotel Project

download Scandic Hotel Project

of 81

Transcript of Scandic Hotel Project

  • 7/25/2019 Scandic Hotel Project

    1/81

    wwww

    Final ProjectProject B42, S11

    Scandic Hotel in Aarhus

    6/9/2011

    Marta Marton

    Sophie Eyler

    Supervisor: Kirsten Malte Iversen

    2011

  • 7/25/2019 Scandic Hotel Project

    2/81

    Scandic Hotel in Aarhus2011

    1 | P a g e

    Contents

    1. Introduction ............................................................................................................................. 3

    2. Geological description ............................................................................................................. 5

    2.1. Book: Engineering geology in Denmark ............................................................................... 5

    2.2. Per Smed maps .................................................................................................................... 6

    2.3. Contour lines map ................................................................................................................ 8

    2.4. Pre quaternary surface map ................................................................................................ 8

    2.5. Book: Underground studies in Arhus area ........................................................................... 9

    2.6. GEUS map........................................................................................................................... 10

    2.7. Danish area information .................................................................................................... 11

    2.8. Drawing .............................................................................................................................. 13

    3. Geotechnical description ....................................................................................................... 14

    3.1. Informationonexistingbuildings ......................................................................................... 15

    3.2. Soil conditions .................................................................................................................... 15

    3.2.1. Groundwater conditions ................................................................................................ 17

    3.2.2. Plasticity ......................................................................................................................... 17

    3.2.3. Soil profiles ..................................................................................................................... 19

    3.2.4. Strength, deformation parameters and unit weights .................................................... 20

    3.3. Conclusion .......................................................................................................................... 22

    4. Risk assessment ..................................................................................................................... 23

    5. Excavation of the soil ............................................................................................................. 27

    5.1. Demolition ......................................................................................................................... 27

    5.2. Excavation of the soil ......................................................................................................... 28

    5.2.1. The excavation process .................................................................................................. 31

    5.3. Temporary dewatering ...................................................................................................... 33

    5.4. Safety ................................................................................................................................. 34

    6. Retaining walls ....................................................................................................................... 37

  • 7/25/2019 Scandic Hotel Project

    3/81

    Scandic Hotel in Aarhus2011

    2 | P a g e

    6.1. Sheet pile walls .................................................................................................................. 39

    6.1.1. Timber sheet pile walls .................................................................................................. 39

    6.1.2. Concrete sheet pile walls ............................................................................................... 40

    6.1.3. Steel sheet pile walls ...................................................................................................... 41

    6.1.4. Berlin wall ....................................................................................................................... 42

    6.1.5. Diaphragm wall .............................................................................................................. 43

    6.1.6. Secant pile walls ............................................................................................................. 44

    6.2. Conclusion .......................................................................................................................... 46

    7. The design of the retaining walls ........................................................................................... 47

    7.1. Steel sheet pile walls .......................................................................................................... 50

    7.2. Secant pile walls ................................................................................................................. 54

    7.2.1. Calculation of the reinforcement ................................................................................... 55

    7.3. Conclusion .......................................................................................................................... 57

    8. Ground anchors ..................................................................................................................... 58

    8.1. Anchors for the steel sheet pile walls ................................................................................ 63

    8.2. Secant pile walls ................................................................................................................. 64

    8.3. Installation of the ground anchors .................................................................................... 65

    9. Calculation of the foundations .............................................................................................. 68

    9.1. Calculation of the reinforcement of the footings .............................................................. 72

    10. Calculation of the bottom concrete plate ......................................................................... 73

    11. Conclusion .......................................................................................................................... 78

    Bibliography .................................................................................................................................. 79

  • 7/25/2019 Scandic Hotel Project

    4/81

    Scandic Hotel in Aarhus2011

    3 | P a g e

    1. Introduction

    The aim of this project is to construct the parking basement of a hotel in Aarhus, placed in an

    urban area, in the heart of the city.

    The parking basement will be provided for the Scandic Arhus City, which will be finished in

    2012. To make way for the new hotel the city demolished some of the old buildings.

    First of all a geological description of the building sites ground has to be made in order to ha ve

    a guess of what kind of soil can be expected in the area of the excavation. It will also give any

    special precaution that has to be taken regarding the pollution or the ground water for

    example. The second step is to do a geotechnical description. Basically this will precise the

    geological description and show what the soil is composed of, its strength, plasticity

    The risk assessment is written in order to list each and every danger that can appear while

    erecting the building.

  • 7/25/2019 Scandic Hotel Project

    5/81

    Scandic Hotel in Aarhus2011

    4 | P a g e

    Then the excavation of the soil will be studied. First the existing buildings have to be

    demolished in order to make place for the new hotel. The demolition method will be explained

    in that part. Finally the excavation part will include the excavation process with the machinery,

    the phase plan of the excavation in two levels, the dewatering and the dangers that can appear

    all along the duration of the excavation work.

    The next topic will be about retaining walls. Indeed the different types of retaining walls will be

    compared and the best solution(s) will be chosen to insure that the ground is retained and the

    excavation pit is dry. The design of the chosen solution(s) will be studied. For example the

    reinforcement of the secant pile wall will be calculated and the sheet piles will be chosen

    regarding the possible and available dimensions, the calculation of the anchors, the anchors

    capacity, the soil conditions The reinforcement of the secant pile wall will be studied and the

    steel section in the piles will be determined. Finally the lengths of the anchors in sheet piles and

    secant piles walls will be calculated and the installation of the anchors will be explained.

    After that comes a reinforced concrete calculation. The footings of the foundations will be

    defined by using the loads from the upper levels of the building. The bottom concrete plate of

    the parking basement at the level - 2 will be designed as well according to the imposed load

    from the parking lot and the swelling pressing the other way from the bottom of the concrete

    plate.

  • 7/25/2019 Scandic Hotel Project

    6/81

    Scandic Hotel in Aarhus2011

    5 | P a g e

    2. Geological description

    -by Sophie-

    Before starting the excavation work, a geological description has to be made in order to get a

    first overview of what the ground is made of. Once the different layers, thicknesses and

    strengths that can be expected are known, then a first choice of retaining walls can be made.

    Different maps showing the Danish underground and two books about the geology in Denmark

    and the underground in the area of Arhus were used to make this geological description. Step

    by step the different information are found starting with the general ones and ending with the

    specific ones.

    2.1. Book: Engineering geology in Denmark

    The chapter 9 of the "Engineering geology in Denmark" book is used to find the type of soil that

    can be generally expected in the area of the building site. However this chapter only gives

    global information and the investigation needs to be pushed further to have specific datas

    about the building site.

    The shape of the level curves in this area are used to determine the type of landscape without

    taking in account the changes brought by the human being.

  • 7/25/2019 Scandic Hotel Project

    7/81

    Scandic Hotel in Aarhus2011

    6 | P a g e

    For example the "valley" in the lower left corner is not taken into account in the determination

    of the landscape because it has been built for the railway of the train.

    The contour lines are irregular and the surface is undulating. This shows a moraine landscape.

    This type of landscape, formed by melting of ice, is the most common in Denmark. It consists ofmaterial that has melted free of the glaciers and has been released from the ice. In this

    situation, moraine clay can be expected in the upper bed.

    The contour lines are also closely spaced and the curves are closed corresponding to high

    situated hills in the landscape. This shows that there was an ice marginal hill in this area. It's

    been formed in front of a gradually advancing glacier where ice acted like a bulldozer on the

    soil. The beds are disturbed that's why it is difficult to predict the nature of the soil.

    To conclude, the information given by this chapter gives a moraine landscape. Moraine clayis

    expected in the upper bed. The beds are also expected disturbed meaning that several

    materialscan be expected in the same layer.

    2.2. Per Smed maps

    This map (Per Smed map number 2) shows the general type of soil that is usually found in the

    area of Arhus in the period which goes from 1978 to 1982. This map will confirm the type of soil

    found with the chapter 9 and specify it for the location of the building site.

    It gives a good overview of the quaternary geological features in the landscape and shows the

    relationship between the large valley systems and other landscape forms. It has to be taken

    into account that this map only shows an interpretation of the landscape-forming processes.

    That's why this map can be used to determinate the type of soil that can generally be expected

    but without being specific about what layers will be found.

  • 7/25/2019 Scandic Hotel Project

    8/81

    Scandic Hotel in Aarhus2011

    7 | P a g e

    The map is taken for the area of Arhus and a zoom is made on the location of the building site.

    A thin red grid is found at that place. According to the legend, "moraine landscapes from

    Weichsel glaciation, mainly with clayey soil" is expected at the building site.

  • 7/25/2019 Scandic Hotel Project

    9/81

    Scandic Hotel in Aarhus2011

    8 | P a g e

    It does confirm the type of landscape found previously in the chapter 9. The building site is a

    part of a moraine landscapewith clayey soiland it comes from a glaciation period, meaning

    that meltwater materialscan be found in the ground.

    2.3. Contour lines map

    This map shows the contour line of the area nowadays. Associated with theorthophoto map of

    the city, it gives the level of the ground surface exactly at the point of the building site.

    2.4. Pre quaternary surface map

    The Pre quaternary surface topography of Denmark map is the result of the landscape-forming

    geological processes throughout the Tertiary and up to the present day. The contour lines are

    the present topographical contour lines. Basically this map shows the ground surface level that

    can be studied for the geological description.

  • 7/25/2019 Scandic Hotel Project

    10/81

    Scandic Hotel in Aarhus2011

    9 | P a g e

    According to the pre quaternary surface map the colour found in the area of the building site

    light green. The legend says that the corresponding level is between -25 and 0 m below the

    sea level.

    2.5. Book: Underground studies in Arhus area

    This book gives a lot of information concerning the background, the groundwater and the type

    of soil that can be found in the area of Arhus. Several typical soil profiles in this area had been

    compared to finally draw the soil profile that we can expect for the building site.

    Unfortunately the whole book and maps are in Danish so this only page below had been

    studied.

  • 7/25/2019 Scandic Hotel Project

    11/81

    Scandic Hotel in Aarhus2011

    10 | P a g e

    The picture above shows the different soil profiles that had been compared and themselves

    compared with the rest of the information that have been gathered. That means that only the

    type of soil that agree with the other information have been taken into account to draw the

    hypothetic soil profile of the building site. The result is shown in point:8. Drawing.

    2.6. GEUS map

    The geological surface map from GEUS shows the dominant soils in 1m depth just below the

    top soil. The technical boreholes will help to find the ground water level at the building site.

  • 7/25/2019 Scandic Hotel Project

    12/81

    Scandic Hotel in Aarhus2011

    11 | P a g e

    As no technical boreholes had been found at the same place of the

    building site two boreholes have been studied to determine the

    ground water level.

    The first borehole (the one shown as an example above) gave aground water level at + 5.4 and the second one (where is the star

    above the building site) gave it at + 11.2. A calculation has been made

    in order to interpolate the ground water level at the building site

    itself. This gave the ground water at the level approximately+ 9m

    above the sea level.

    2.7. Danish area information

    This web site displaysa lot of information about the environmental and planning datas in

    specified locations. It shows also background maps, terrain conditions and contour line maps.

    Basically this web site will help to find out if there are special care that has to be taken

    regarding to the building site.

    Activation / deactivation ofthe different layers

    Building site

  • 7/25/2019 Scandic Hotel Project

    13/81

    Scandic Hotel in Aarhus2011

    12 | P a g e

    First, the area of the building site is found so the scale is good enough and the informationis

    clearly seen. Then every layer is checked in order to see what environmental and planning

    parameter have to be taken into account while building the hotel.

    The building site takes place at the parcel 333a. Just across the street there is a monumentprotection line but not close enough to be relevant for the building site itself. There are no

    particular preservation for the nature

    because the hotel is situated in an urban

    area. The area has limited water interests

    meaning that there are no specific

    problems with the groundwater. This

    picture shows the areas where the soil is

    contaminated around the building site.

    The soil shouldn't be especiallycontaminated at the building site area

    but thatinformation should still be kept in

    mind.

    Finally the web site offers the opportunity to have a look at historical maps showing the

    neighborhood from 1842 to 2008. All those maps show the same building at the exact same

    place of the building site. This means that there was no former construction at that place. There

    is no "construction material" below the existing building.

    To conclude, except regarding the soil contamination, there is no specific preservationthat hasto be taken care off at the building site.

  • 7/25/2019 Scandic Hotel Project

    14/81

    Scandic Hotel in Aarhus2011

    13 | P a g e

    2.8. Drawing

  • 7/25/2019 Scandic Hotel Project

    15/81

    Scandic Hotel in Aarhus2011

    14 | P a g e

    3. Geotechnical description

    -by Marta-

    In this projectit is very important to have the geotechnical description ofthe building site, which

    summarizes and evaluates all results obtained during investigation in the siteand in the

    laboratories.In order to calculate the retaining walls, anchors and also the bottom plate some

    parameters will be needed. For thisit were given all theall boring logs, laboratory test results

    from the different drillings. With theseboringsit is be possible to draw the cross sections of the

    soil, and to determine the strength and deformation properties of the soil in the specific area.

    The borings are divided in two phases. The first phase includes 7 borings which performed

    before the demolition of the existing buildings. The second phase includes 3 borings which

    worked only after demolishing the existing buildings.

    The report covers the results of the second investigation phase above construction: 3

    geotechnical boreholes.

    Figure 1 Place of the drillings

  • 7/25/2019 Scandic Hotel Project

    16/81

    Scandic Hotel in Aarhus2011

    15 | P a g e

    3.1. Informationonexistingbuildings

    While the future hotel will be located in an urban area, in the heart of Aarhus, it is really

    important to have an overview on the surrounding buildings. For the new building there were

    performed some surveys of the existing conditions of the area where it will be placed: in

    stergade, between Hans HartvigSeedorffs StreetandSndergade. It is expected that the new

    hotel will be built with a large car park below the hotel. The purpose of these studies is to give

    historical data to such an extent that the existing building conditions around the proposed

    building can be assessed, including age of the buildings, basement, the possible type of the

    foundation, and the depth of the foundation.

    The building has its border on the north up to stergade, on the west up to Hans Hartvig

    Seedorffs Street, and to the east it borders up to the buildings on Sndergade.

    The new buildings area is surrounded by other buildings, and roads, located next to the area

    which will be excavated, possibly causing danger to these roads and buildings as a result of the

    excavation and/or dewatering.

    Many of the buildings in the surrounding are old, and they dont have a good ground in

    accordance to the applicable rules and standards.

    Because of the basement and car park below the new hotel, the excavation has to be done

    below or on a level with the existing building foundation level.

    The expected water level is about 3-4 meters from the ground. So it will be probably necessary

    to perform a temporary dewatering for the excavation. Dewatering should then be arranged so

    that the water table is lowered at least 0.5 meters below the excavation level.There will

    probably be a dug in clay or moraine clay, in which case the dewatering of the excavation

    possibly will be done by simple drainage.

    3.2. Soil conditions

    The studies in the second phase include drilling no. 3 and no. 10 to 25 m below ground and

    drilling no. 8 to 11 m below ground. In the 3 new wells from ground level between 1.3 and 1.8m has been taken fill and between 4.2 up to approximately 11 m glacial deposits - mainly in the

    form of moraine clay. Glacial deposits are found underneathof very fat tertiary clay from 4 to 11

    meters depth (from 1.9 to 6.1 in elevation), with glacial sediments; however, this is not present

    in drilling no. 8.In both bore no. 3 and 10, the upper zone of the Tertiary clay moved from its

  • 7/25/2019 Scandic Hotel Project

    17/81

    Scandic Hotel in Aarhus2011

    16 | P a g e

    deposition siteduring the last ice age and now covers the static tertiary clay either as loose

    flakes orpossibly as folded structures.

    The static Tertiary succession is: at the top Viborg clay (upper Septarie clay),then Kysing marl

    (upper Svind marl) and at the bottom Moesgrd clay (lower Septarie clay).

    1. Fill layer

    From the terrain is generally taken a coating and underlying base course.

    2. Glacial deposits

    Glacial deposits consist predominantly of clay, as in boring 10 it can be observed

    alternationofrelatively thin flakes with very fat Septarie clay or micaand in boring 8 it can be

    observed alternationwith relatively thin layers of glacial sand and silt.

    Clay is mostly pretty cool, sporadic fat. Moreover, locally it was found embedded layer of very

    fat local moraine of Septarie clay.

    The strength of the clay increases with depth. As in most of the previous wells were right soft

    clay deposits (cv700 kN/m2.

    3. The Tertiary clay deposits

    The static Tertiary deposits, which are only taken in hole 3 and 10, consists of top Viborg clay

    (Septarie clay), then 0.9 to 2.2 m Kysing marl (Svind marl) and at the bottomMoesgrd clay

    (Septarie clay), which is not penetrated 25 m below the ground, but having Svind marl in

    slightly greater depth.

    The new wells give rise to only minor adjustments to the chart below from the report of the

    first phase.

    Updated overview of vane tests and classification properties of Tertiary clay

    Soil type Wing strength

    cv[kN/m2]

    Watercontent

    w [%]

    Unitweight

    [kN/m3]

    Flake of Tertiary clay 170 - 450 27 - 34 18.519.6

    Mica >700 18

  • 7/25/2019 Scandic Hotel Project

    18/81

    Scandic Hotel in Aarhus2011

    17 | P a g e

    3.2.1. Groundwater conditions

    The depth to groundwater level is measured immediately after completion of the drilling. In

    boring 8 the height of the water table was 10.1 meter, which corresponds 3.0 meters below

    ground level. The drilling no. 10 was dry. In the boring no. 3 the water surface elevation was

    measured 8.8 meter which is equivalentto 1.5 meters below ground.

    In the project it will be considered a normal water table for the uplift calculations, which is

    located in elevation 8.5 m along stergade and on the southerly direction in elevation approx.

    9.5 m.

    3.2.2. Plasticity

    1. Viborg clay

    Updated overview of plasticity forViborg clay

    Drilling Test Ip[%]

    32766/1 23 51

    32766/2 21 77

    3 31 70

    32766/4 25 50

    32766/4 26 61

    32766/5 33 61

    32766/6 19 55

    32766/6 20 61

    32766/7 31 51

    32766/7 35 67

    10 22 53

    Viborgclay 180 - 690 28 - 37 18.019.2

    Kysingmarl 350 - >700 27 - 38 19.019.5

    Moesgrdclay 210 - >700 31 - 38 18.5 - 20

  • 7/25/2019 Scandic Hotel Project

    19/81

    Scandic Hotel in Aarhus2011

    18 | P a g e

    10 32 69

    COWI/B1 22 70

    COWI/B1 30 74

    Plasticity index is in the middle: 62%, i.e. significantly lower than for the lower Septarie

    clay,Moesgrd clay.

    2. Kysing marl (upper Svind marl)

    Plasticity forKysing clay

    Drilling Test Ip[%]

    1 33 28

    2 31 88

    6 33 43

    Plasticity index is in the middle: 53 %

    3. Moesgrd clay (lower Septarie clay)

    Updated overview of plasticity in Moesgrd clay

    Drilling Test Ip[%]

    32766/1 49 79

    32766/2 42 84

    3 49 73

    32766/4 49 71

    COWI/B1 38 131

    COWI/B1 46 110

    Plasticity index is in the middle 91%, i.e. significantly higher than the upper Septarie clay,Viborg

    clay.

  • 7/25/2019 Scandic Hotel Project

    20/81

    Scandic Hotel in Aarhus2011

    19 | P a g e

    3.2.3. Soil profiles

    One useful method compiling subsurface

    data is to draw the vertical cross-sections

    across the site. These sections are most

    easily developed when they intersect the

    borings.

    In the geotechnical report it was given all

    the boring logs which were performed on

    the site. By using these logs, and also by

    adding some interpretation, when the

    conditions between these borings were

    not given, the soil profiles could be made.

    Because of the lack of information

    between the borings, the soil profiles are

    not the exact mirror of the reality, and

    because of the interpretation these soil

    profiles are unique.

    Figure 2 Example of a boring log

    The method which was used drawing these profiles:

    1. Determining the depth of the different drillings.

    2. Drawing each boring in his exact place.

    3. Drawing the different layers of the soil on each boring.

    4. Connecting the same layers from one boring to another (where it is obvious).

    5. Drawing the layers between two consecutive boring (estimation).

    For this project two soil cross-sections were made: one where the borings no. 3, 6 and 10 were

    performed and the other one where the borings no. 1, 4, 7 and 8 were performed.(See

    Appendix no.2)

  • 7/25/2019 Scandic Hotel Project

    21/81

    Scandic Hotel in Aarhus2011

    20 | P a g e

    3.2.4. Strength, deformation parameters and unit weights

    For the later calculations it was important to determine some important parameters:undrained

    shear strength, friction angle, effective cohesion, saturated unit weight, dry unit weight.

    Some of these parameters could be determinedusing the boring logs: wing strength or shear

    strength measured by vane test (cv), water content (w), and also the unit weight ().

    To determine the wing strength in the different layers of the soils it was calculated the

    arithmetic mean (average) of the wing strengths for each layer in each boring. Where the

    difference was very big between twoconsecutive values, (like from cv=100 it changed to cv=370

    and then again to cv=70) the very different value was disregarded. In some layers the values

    differed quite much, thanks to the increase of the strength by the depth, because of this, the

    layers were divided in an upper and a lower level (like the Viborg- and the moraine clay). First

    the averages of the soil types were determined for each drilling, then for each soil profile, and

    in the end the wing strengths were determined for the soil in the construction area.

    To have a better security, in most of the cases for the wing strength it was taken a value lower

    than the average, but never higher.(See Appendix no.2)

    The undrained shear strength (cu) (or triaxial certain values of pressure) is determined using the

    vane tests where

    , unless if it is cracked clay or gyttja.

    Another parameter which is important to be determined is the unit weight. For the future

    calculations two types of unit weight will be needed: the saturated unit weight ( m), which is a

    parameter characteristic for the layers situated under the water level, and the dry unit weight

    (d), which is used for the layers situated above the water level.

    From the Danish Technical Handbook (TekniskStbi) the different parameters for the typical

    Danish natural soil deposits could be read, like the saturated unit weight (m), friction angle

    (pl), effective cohesion (c).

  • 7/25/2019 Scandic Hotel Project

    22/81

    Scandic Hotel in Aarhus2011

    21 | P a g e

    Figure 3 Classification-, strength- and deformation parameters for typical Danish natural soil deposits (from

    TekniskStabi)

    The effective cohesion (c)is a mathematical factor to represent the use of breaking the

    condition of the form=c+*tan (Coulombs failure condition). Normally, one can assess (

  • 7/25/2019 Scandic Hotel Project

    23/81

    Scandic Hotel in Aarhus2011

    22 | P a g e

    In order to calculate the dry unit weight the value of the void ratio was needed. In the project

    an estimation of the void ratio was made due to the lack of information.

    After the calculations all the parameters which will be needed in the later calculations are

    shown in the following table for all the layers which are present in the specific area.

    Parameters for the different type of soils

    Soil typecu

    [kN/m2]c

    [kN/m2]

    pl

    []

    m[kN/m3]

    d[kN/m3]

    Fill 0 0 0 16 13

    Moraine clay (upper level) 120 15 30 20 17

    Moraine clay (lower level) 360 16 32 22 -

    Moraine sand 0 0 40 22 -

    Meltwater clay 140 10 26 20 -

    Meltwater sand 0 0 37 19 -

    Meltwater silt 160 10 26 20 -

    Viborg clay 280 0 28 19 -

    Mica (Glimmer clay) >702 0 25 19 -

    Flakes (Glacial clay) 210 0 25 19 -

    Kysing marl 380 0 25 18 -

    Moesgrdclay 480 0 26 18 -

    3.3. Conclusion

    To conclude, comparing the geotechnical description with the geological one, it can be stated

    that the expected soil conditions and groundwater level was demonstrated by the results from

    the drillings executed on the site.

  • 7/25/2019 Scandic Hotel Project

    24/81

    Scandic Hotel in Aarhus2011

    23 | P a g e

    4. Risk assessment

    -by Marta-

    The piling works for the construction of the new hotel include performance-related factors,

    which threaten to cause damage on the surrounding buildings. The risk assessment covers only

    existing buildings and structures located outside the neighbouring boundaries.

    The greatest risks are associated with dewatering and the excavation work. During the

    excavation close to the existing buildings, it will be hard to avoid the emergence of cracks and

    small gaps in them resulted by the deformations of dewatering. It is a must to be prepared of

    this, and to repair the damages.

    The project includes a building with double basement and plate foundation. The bottom platewill be anchored with vertical anchors to avoid the heave. The lowest excavation level in

    elevation is +4.2.

    The retaining walls will consist of sheet pile walls and secant pile walls because there is

    necessary to get close to the existing buildings i.e. along the adjacent boundary to the south

    and along a ca. 22 m stretch of the southern part of neighbouring boundaries to the east.

    Dewatering has to be placed so deeply that all the permeable layers to be are cut off.

    To minimize the noise and vibrations at the steel sheet piles the sheet pile profiles must beforced down by hydraulic pressure with Crush Arrows. If it is required the sheet piles should be

    supplemented with hosing/drilling so that the sheet piles achieve the projected toe level. Pre-

    drilling will be done on the inside of the building pit and the eventual drilling during future

    excavation levels will be done after injecting with cement stabilized bentonite.

    The establishment of the secant pile walls will begin with building a guiding wall cast of

    concrete so that the centre distance between each pile correspond to the desired overlap. The

    secant pile walls are constructed with 80 cm diameter bore piles, which are provided with 8 cm

    overlap.

    Dewatering close to the buildings must be monitored for example by inclinometer

    measurements.

    Dewatering is anchored with drilled, temporary ground anchors. The anchors are placed in

    different anchoring level and are installed at varying angles. The ground anchors are injected

  • 7/25/2019 Scandic Hotel Project

    25/81

    Scandic Hotel in Aarhus2011

    24 | P a g e

    again (normally 24 hour after the first injection). It wont be taken into account any sewer lines

    or other wiring by placing the anchor levels.

    Risk factors

    The piling works for the planned structure contains the following potentially risky moments on

    the neighbouring buildings:

    1. Demolition of existing buildings

    2. Reducing steel sheet pile walls

    3. Drilling down and casting of secant pile walls

    4. Establishment of ground anchors for dewatering (drilling, injecting and holding it)

    5. Temporary ground water lowering

    6. Excavation

    7. Establishment of ground anchors for bottom plate

    Demolition of existing buildings

    The risks associated with the demolition work have not been assessed.

    Reducing steel sheet piles

    It is reported that the steel sheet piles are forced down by hydraulic pressure, with Crush

    Arrows. If it will be managed to reduce the steel sheet piles only by hydraulic pressure it will be

    possible to meet even the most stringent vibration limitscompared to neighbouring buildings.

    It will be a necessary extent to do hosing and/or drilling. Both of them potentially involve

    substantial risks for neighbouring buildings and structures. The drilling will be performed only

    inside of the sheet piles. The drilling occurs during sheet pile tip and liner and the liner is also

    not close, so the effect of possible erosion damage, distortion from clamping, etc. must be

    considered carefully.A risk of hosing and drilling thus requires a detailed description of

    methodology and application, with reference to past assignments.

    Drilling down and casting of secant pile walls

    It would probably be impossible to keep even the most stringent vibration limits in relation to

    neighbouring buildings. The greatest risk of vibration may occur if they hit bigger stones or

    structural parts during drill work.

  • 7/25/2019 Scandic Hotel Project

    26/81

    Scandic Hotel in Aarhus2011

    25 | P a g e

    There must be developed for this work a description of the work explaining detailed

    performance of the drilling works, more specifically, how to ensure to avoid the surrounding

    soil erosion damage from the inflowing water to thoroughly bore baths during drilling and

    casting.

    Establishment of ground anchors for dewatering

    There must be developed for this work a description of the work explaining installation

    performance, particularly how to ensure to avoid the surrounding soil erosion damage. In

    addition should be explained the risk phrases of the anchors free length which is not injected.

    Finally, it is important the presentation of the documentation that the anchors do not hit

    underground structures and equipment - including wiring systems.

    Excavation

    Excavation leads to deformations of dewatering and hence deformation (vertical as well as

    horizontally) of land and buildings, etc. behind the walls.

    There must therefore be performed calculations explaining deformations size.

    Deformations should be compared with limit values which must be already established for each

    neighbouring building. There must also be prepared a job description that outlines that in which

    stages must be excavated, and in what tempos to be installed stabilizing anchors or other form

    of bracing.

    Finally, it is estimated that the most vulnerable buildings will be monitored with benchmarks so

    that excavation work can be stopped if the assumed values against the expected thingsare

    exceeded. Furthermore inclinometer measurements (slope measurements) will be performed

    on selected walls so that the walls current buckling mode can be evaluated in relation to

    expectations.

    It is scarcely possible to avoid the nearest neighbouring buildings cosmetic damage. Even very

    small deformations are in danger of causing damage that might not otherwise have been

    obtained at a later date. The limit for how big movementsbuildings can withstand before any

    significant damage to their static system is building-dependent. There must be approved and

    controlled retail calculations of all dewatering and anchorages in all relevant fracture and

    serviceability limit state.

  • 7/25/2019 Scandic Hotel Project

    27/81

    Scandic Hotel in Aarhus2011

    26 | P a g e

    Temporary ground water lowering

    It is expected that it will probably be executed without risk to neighbouring buildings. In the

    event of a finding substantial leaks - e.g. due to locking skip tests or other variations - the

    situation can be reassessed.

    Establishment of ground anchors for bottom plate

    It is possible to install ground anchors for flat foundations without risk of significant nuisance

    for neighbouring buildings.

  • 7/25/2019 Scandic Hotel Project

    28/81

    Scandic Hotel in Aarhus2011

    27 | P a g e

    5. Excavation of the soil

    -by Marta-

    Deep excavations are needed e. g. for foundations,underground traffic routes and other

    infrastructurefacilities. The dimensions of theexcavation are determined by the drawings from

    the architects.The design of the excavation depends on several factors: like thelocal situation,

    the conditions of the ground and thegroundwater and other circumstances. In urban areasthe

    excavations must be done due to the adjacentbuildings by underpinnings or by retaining walls.

    Nowadays, the land prices are high, and only small areas are available, therefore the investors

    plan more and more basements. To solve the traffic problems new lines areplanned

    underneath the existing ones. So the depthof the excavations increases and reaches values, for

    which no local experiences exist.

    The bottom and the walls of the excavations mustguarantee - with a certain factor of safety -

    the structuralclearance and a certain amount of water impermeabilityif necessary. The ground

    movement,which is unavoidable especially in cases with softand loose soils, has to be restricted

    to such an extent,that no greater damages occur in the neighbourhood.Here the first

    movements occur by establishing thewalls and the sealing of the ground.

    5.1. Demolition

    To make way for the new hotel,the

    first thing which has to be done is

    the demolition of the existing

    buildings. For this the non-

    explosive method will be used,

    which means hydraulic excavators

    will be brought to the construction

    site to do the undermining process.

    The demolition project manager

    has to determine where the

    undermining will be done. He also

    has to take into account the safety

    and clean-up considerations in order

    to determine how the building will be undermined and ultimately demolished.

    Figure 4The building site after the demolition

  • 7/25/2019 Scandic Hotel Project

    29/81

    Scandic Hotel in Aarhus2011

    28 | P a g e

    Loaders or bulldozers may also be used to demolish the building. They are typically equipped

    with "rakes" (thick pieces of steel that could be an I-beam or tube), so they will be used to ram

    the building walls.

    After the demolishing the construction site has to be cleaned, thanks to this the excavation itcan be made.

    5.2. Excavation of the soil

    Before any excavation work is undertaken, a risk assessment must be carriedoutfirst to assess

    the degree of hazard (See Chapter no.4).

    To excavate the soil it is necessary to estimate the amount of soil which is going to be

    removed.By analysing the drawings, two plans were done for this process. To find the better

    solution, the following aspects were compared:

    Volume of soil removed;

    The excavators operating time;

    Cost;

    Aesthetics.

    Volume of soil removed

    It depends on the excavated area and the depth of the

    excavation. The geotechnical description says that the lowest excavation level is +4.2 meters,

    which means that the height of the excavation will be 8.8 meters.

    The excavators operating time

    The chosen excavator which is going to work on the site is: CAT 336D L Hydraulic excavator

    (Caterpillar), with a 2.55 m3 maximum bucket capacity. The cycle time is estimated to 0.50

    minute. To calculate the effective cycles per hour the following are taken into account:

    Cycle time 0.50 minute

    Cycles/60 minute hour 60 / 0.50 = 120

    Operator Skill/Efficiency 0.9 (90%)

    Machine Availability 0.95 (95%)

    Gen Operational Efficiency 0.83 (50 min/hr)

    Effective Cycles per Hour 125 x 0.9 x 0.95 x 0.83 = 85

    Figure 5The chosen excavator: CAT 336D L

  • 7/25/2019 Scandic Hotel Project

    30/81

    Scandic Hotel in Aarhus2011

    29 | P a g e

    Therefore in an hour the amount of soil which it can be removed: 2.55* 85 = 216 m3/hour.

    The cost of the rent of the excavator is estimated to 4000 DKK/day.

    1stsolution

    In this solution the excavation will be done until the Hans Hartvig Seedorffs Street, which will

    have anexcavated areaof 2958 m2. Therefore the volume of the excavated soil will be:

    For this amount of soil the excavator has to work:

    By 8 hours working per day the excavator has to be rented for 15 days, costing 60000 DKK.

  • 7/25/2019 Scandic Hotel Project

    31/81

    Scandic Hotel in Aarhus2011

    30 | P a g e

    2ndsolution

    With this solution the neo-classicist buildings faade on Hans Hartvig Seedorffs Street wont be

    demolished, because it is very characteristic on that area. This will reduce the excavated area:

    2724 m2, the volume of soil:

    and the excavators operating time:

    These 110 hours of work means 13.75 days, therefore the cost of the rent for this period of the

    excavator will be estimated to 55000 DKK.

    This solution needs more attention in the demolition because of the old faade, which will be

    supported during these works.

  • 7/25/2019 Scandic Hotel Project

    32/81

    Scandic Hotel in Aarhus2011

    31 | P a g e

    Conclusion

    Comparing the results of the first two aspects, it

    can be noticed that there is not so big

    difference, but still the second solution is more

    likely, because it has less removed soil, and the

    excavator will work 14 days instead of 15. The

    cost also will be lower, but this doesnt really

    count in a big construction like this.

    The decisive aspect why the 2nd

    solution was

    chosen was the aesthetics.

    5.2.1. The excavation process

    For the excavation it was made a phase plan which shows the activities done for each day. (See

    Appendix no.4 and no.5)Because of the two levels under the ground, the excavation will be

    done during two phases: the first oneincludes the excavation works until the second level and

    the other one is for the second level. Excavating one level takes 7 day. The area which is going

    to be excavated per each day is:

    By making this drawing the aim was to dividethe area in equal pieces. Of course this couldnt be exact: the smallest excavated area for one

    day being 375 m2

    and in the other hand the largest one 409 m2

    .A ramp was made for eachphase from the Hans HartvigSeedorffs Street because of the access of the excavator. (See

    Appendix no.3)

    Regarding to the calculation of the ground

    anchors (See Chapter no. 8) the following

    drawing shows the number of anchors which

    are going to be placed for each excavated area

    for one level.

    The numbers 1,2,3 7 show the order of theexcavated areas.

    It is assumed that the drilling machine can drill

    the hole for 5-6 anchors per day. This means

    installing the anchors for one area can take

    more days up to 7 days. Also it can be noticed

    Figure 6The neo-classicist facade

    Figure 7 Excavated areas and number of anchors per level

  • 7/25/2019 Scandic Hotel Project

    33/81

    Scandic Hotel in Aarhus2011

    32 | P a g e

    that in the area no.5 no anchors will be placed.

    In some of the corners was not possible to place anchors therefore in those placed inner

    bracing will be used. The anchors are put in the ground the day after the soil has been

    excavated. The secant pile walls will be placed where the present soil type is clay. Thanks to this

    reinjection will be done in 24 hours after the drilling and injection of the anchors. On some days

    lots of activities are done in the same time. Installing anchors can be possible while excavating

    another area. The anchors resistance is tested 7 days after their implementation. For this

    reasons, at the end of the excavation work, the last days are taken to test the anchors put the

    week before. Testing and reinjection doesnt take a lot of time, so this wasnt a factor which has

    to be considered carefully while planning the excavation. This is also shown on the detail below

    made for two consecutive days. (See Appendix no.5)

    Figure 8 Detail of the phase plan

    The table gives the information about the week, and the day when the specific activities will be

    done. The number in brackets shows the activity number for each set of installed anchors. This

    meansfor one set of anchorsthe number(32) will be the number for each type of activity done:

    installing (5 anchors), reinjection (if there is a case) and testing. Thanks to this will be easier to

    follow which works have to be done on the specific day.

    As a result the whole excavation works including the installation of the anchors will take 64

    working days, starting from Day 1 until Day 89 with 13 weeks duration.

  • 7/25/2019 Scandic Hotel Project

    34/81

    Scandic Hotel in Aarhus2011

    33 | P a g e

    5.3. Temporary dewatering

    For the excavation it is necessary to perform a temporary dewatering. Dewatering should then

    be arranged so that the water table is lowered at least 0.5 meters below the excavation level.

    In principle there are four different methods for controlling groundwater in connection with a

    building or construction project below the groundwater table:

    Water is allowed to seep into the excavation and is removed by bilge pumping (possibly

    with drain)

    A temporary or permanent dewatering is established, whereby the groundwater table is

    drawn down to below the construction/excavation level

    The groundwater movement is cut off with tight walls, for example sheet pile walls, slot

    walls, freezing, injection

    The water pressure is withheld with air pressure, for instance in tunnels and caissons.

    Figure 9 Selection method

    There will probably be a dug in clay or moraine clay, in which case the dewatering of the

    excavation will be done by simple drainage. This is the simplest and cheapest form of

    groundwater drawdown which is pumping from a system of drains and pumping wells at thebottom of the excavation.

  • 7/25/2019 Scandic Hotel Project

    35/81

    Scandic Hotel in Aarhus2011

    34 | P a g e

    Figure 10 Simple drainage

    By simple drainage, the water is allowed to seep into the building pit and is subsequentlypumpedaway through a well point pump. The method is commonly applied by smaller/modest

    wateramounts and when there is no risk of soil fractures.

    The pump sump can be shaped as a 315 mm corrugated plastic well with slits, which is placed in

    anexcavation filled with pearl stones and connected to the drain flow.

    For a pump, an electrically powered, well point pump, sized as required (available with

    capacitiesof up till approximately 100 m3/h) is chosen.

    The method can be applied to excavation to moderate depth under the groundwater level in

    freegroundwater depots, where the water-bearing beds consist of sand and gravel.Furthermore, themethod can be applied to excavation below the groundwater level in for

    example moraine clay,where water-bearing beds of sand and gravel are often found.

    5.4. Safety

    During excavation works can be present the following hazards:

    operator falling off from excavation machine

    running over a pedestrian when travelling backing

    destroy underground electrical cables

    contact with overground electrical cables

    collision with other vehicles

    operation the machine by unauthorized person

    machine upset

    soil collapse

  • 7/25/2019 Scandic Hotel Project

    36/81

    Scandic Hotel in Aarhus2011

    35 | P a g e

    getting caught in the pinch points of the bucket arms or the pivot area of an articulated

    machine

    spilling a load on others

    falling over an edge

    a raised bucket falling.

    In order to prevent accidents, all the persons present on the site have to respect the following

    instructions:

    To avoid falling off during climbing or descent from machine they have to wear safety

    shoes and clean the stairs.

    To avoid running over a pedestrian, they have to check before starting the machine if all

    the back-up alarm is working, to use properly adjusted rear view mirrors, and when

    lighting is poor, use both front and rear lights, take care for any distance. They should

    never throw the engine into reverse without looking behind them. No one, other than the operator, should ride the equipment. The bouncing and jarring

    can cause passengers to be thrown off. The usual result is, the passenger is run over

    Before starting excavation they have to ask a chart of underground cables. It is

    forbidden to use the excavation machine near/ above the underground cables. In this

    case excavation has to be done manually.

    To avoid contact with overground electrical cables they have to respect the minimal

    distance to the electrical cables (3 m)

    To avoid collision with other vehicles have to be organised the internal transport on the

    site. To avoid operation of the machine by unauthorised person, the operator has to take out

    the key before leaving the machine.

    In order to prevent machine upset, the operator have to be familiar with the

    instructions described in the machine manual, and have to respect all the limits

    described on it.

    During manual excavation the operators have to take care of soil collapse. To prevent

    this all the walls on the dig have to be protected with supports, have to be inspected

    daily and after raining. The excavated soil has to be stored at the minim 70 cm distance

    from excavation site. Articulated loaders have a very nasty pinch point at the pivot. Operators should always

    check both sides of the machine before moving it, to make sure no one is in this

    dangerous area.

    In order to prevent spilling a load on others, if someone ventures into the danger zone

    around where someone else is working, sounding a warning blast and stopping would

  • 7/25/2019 Scandic Hotel Project

    37/81

    Scandic Hotel in Aarhus2011

    36 | P a g e

    certainly be in order. All the peoples from the site have to be instructed to have

    cautions if they are around, between, or under a raised bucket or its arms.

    The cage is designed to protect the operator in the event of rollover. In order to provide

    this protection, the operator must be inside the cage, using his seat belt.

    Have the bucket lowered to the ground unless the work they plan to do requires that itbe raised. Install jacks or blocks under raised buckets or arms so they cannot fall on

    them if something goes wrong.

  • 7/25/2019 Scandic Hotel Project

    38/81

    Scandic Hotel in Aarhus2011

    37 | P a g e

    6. Retaining walls

    -by Marta-

    The building site is located in an urban area; therefore the excavation has to be approximately

    the same size as the building, in order not to disturb the surrounding buildings. While the future

    building will have in the basement a parking place, it has to be done a deep excavation. The

    solution for supporting this deep excavation is to place retaining walls in the specific area.

    In order to find the best solution for this project, which means to choose the type of the

    retaining walls which will be used, it isuseful to have an overview on the different type of the

    walls.

    A retaining wall is a structure that retains (holds back) any material (usually earth) and preventsit from sliding or eroding away. It is designed so that to resist the material pressure of the

    material that it is holding back.

    The retaining walls are used where it is not possible to

    excavate in open pit due to:space, stability, and ground

    water.The scopes of these walls are:

    To restrict the deflection;

    To restrict the bending moment and thus

    weight ; To restrict the height of wall (driving depth);

    Preventive measures by inadequate driving

    depth;

    To ensure structures against uplift (by

    anchorage).

    Figure 11 Retaining wall cross section

    Before choosing the type of the retaining walls some conditions should be taken into

    consideration:

    The substrata

    The soil layers that occur on the site:

  • 7/25/2019 Scandic Hotel Project

    39/81

    Scandic Hotel in Aarhus2011

    38 | P a g e

    Moraine clay

    Meltwater sand

    Flakes (glacial clay)

    Viborg clay

    Kysing marl

    Moesgrdclay

    Tolerances

    Risk of damage

    Some damages can occur during the foundation works. Therefore it has to be prepared for

    damages due to incorrect evaluation of the substrata and/or incorrect calculations, due to the

    ground water-table or seeping in water, and damages caused by the excavation process.

    Conditions pertaining to neighbours

    The building is located in the centre of Aarhus, so it is important to take into account some

    considerations like noise, dust vibrations, permanent- and temporary ground water-table

    lowering in connection with the neighbouring buildings.

    Noise: The noise coming from the building site is disturbing, for example from the

    vehicles which transport the materials, from the installation of the pile walls, especially

    in an urban area, where the buildings are really close to each other. Therefore the work

    should be done by trying to use methods which do not generate a lot of noise.

    Dust: It is impossible to avoid the dust from a building site, but it can be minimized. The

    best solution for this to spray the area at regular intervals using a watering system that

    can correspond to evaporation

    Vibration: Another annoying factor which can cause damage to the existing buildings. To

    avoid the unexpected subsidence in the existing buildings all surrounding constructions

    foundations should be examined before the work is started.

    Temporary ground water-table lowering: It can be a serious problem too, it has to be

    done with attention, but in the project it is expected that it will probably be executed

    without risk to neighbouring buildings

    For more detailed explanation about the risks in connection with the retaining walls (See

    Chapter no. 4)

  • 7/25/2019 Scandic Hotel Project

    40/81

    Scandic Hotel in Aarhus2011

    39 | P a g e

    In order to choose the best solution for the future building it should be listed the advantages

    and disadvantages of the different type of walls.

    There are several types of retaining walls, from these some of them cant be chosen because

    they dont fulfil from the start some considerations: for example the gravity- and the cantileverare used for lower constructions.

    There are 4 types of walls which will be discussed more detailed:

    6.1. Sheet pile walls

    -by Marta-

    Sheet piling is used on a large scale for retaining walls in excavation pits. Sheet piling can be

    supplemented with up to several anchor levels in order to stabilize and fix a sheet pile wall in

    large deep excavations. Sheet pile walls are constructed by driving prefabricated sections into

    the ground. Soil conditions may allow for the sections to be vibrated into ground instead of it

    being hammer driven. The full wall is formed by connecting the joints of adjacent sheet pile

    sections in sequential installation. Sheet pile walls provide structural resistance by utilizing the

    full section. Steel sheet piles are most commonly used in deep excavations, although reinforced

    concrete sheet piles have also being used successfully.

    The materials which can be used for sheet piling is primarily wood, concrete and steel.

    6.1.1. Timber sheet pile wallsThis type of piling should be restricted to short to moderate wallheights (less than 3 meters)

    and used only for temporary structures. The most common types oftimber sheet piles are

    wooden planks and Wakefield piles. Wakefield piles are constructed bynailing three planks

  • 7/25/2019 Scandic Hotel Project

    41/81

    Scandic Hotel in Aarhus2011

    40 | P a g e

    together in an offset manner. Wooded pile walls may be consideredpermanent if the wall is

    permanent submerged underwater or if treated with preservatives.

    Advantages:

    Low cost;

    Readily available;

    Good aesthetics;

    Easy of handling.

    Disadvantages:

    Difficult to install into dense or gravelly

    soils;

    Limited to short duration retaining wallsat construction sites;

    Limited height of structures;

    Decay of structures may be hidden.

    6.1.2. Concrete sheet pile walls

    Concrete piles are typically made with steel reinforcing and prestressing tendons to obtain the

    tensile strength required, to survive handling and driving, and to provide sufficient bending

    resistance.Long piles can be difficult to handle and transport. Pile joints can be used to join twoor more short piles to form one long pile. Pile joints can be used with both precast and

    prestressed concrete piles.

    Advantages:

    Rigid and incur larger earth pressure and

    greater bending stresses than a flexible

    wall;

    Longer service life than other walls;

    Good aesthetics;

    Advantageous in marine environments;

    Capable of supporting significant axial

    loads.

  • 7/25/2019 Scandic Hotel Project

    42/81

    Scandic Hotel in Aarhus2011

    41 | P a g e

    Disadvantages:

    Heavily and bulky and require larger equipment to deliver, handle and drive;

    Higher material cost;

    Large displacement piles and consideration must be given to adjacent structures; May cause settlement in soft soils;

    6.1.3. Steel sheet pile walls

    Steel is the preferred sheet pile material and represents over 95% of all sheet pile

    constructions. The steel sheet pile is used both as a temporary and as a permanent

    construction.

    Advantages:

    Provides high resistance;

    Relatively light weight and easy to handle;

    Can be used repeatedly;

    Long service life;

  • 7/25/2019 Scandic Hotel Project

    43/81

    Scandic Hotel in Aarhus2011

    42 | P a g e

    Less expensive;

    Eliminate or reduce water;

    Easy to increase pile length by welding or bolting.

    Disadvantages:

    Corrosion of steel sheet pile;

    Not aesthetically pleasing in high profile situation;

    Not good in hard soils;

    Driving may cause neighborhood disturbance (noise, vibration);

    Less tight;

    Problems with the interlocks: they can break.

    6.1.4. Berlin wall-by Sophie-

    A Berlin wall, also called a soldier pile wall, is a temporary (in case of timber panels) or a

    permanent (in case of concrete panels) retaining wall mostly used in case of urban area

    constructions. It's one of the oldest methods known for establishing retaining walls in

    connection with deep excavations. The Berlin wall, called in Denmark Copenhagener wall, is the

    front runner for sheet

    pile wall. The method

    of implementation ofthat type of walls is still

    very used today,

    simple and durable.

    This method is used for

    large excavation which

    is made along an

    existing construction.

    The method of

    implementation is very

    simple. First HEB-steel

    profiles are driven or

    vibrated into the

    ground. The distance

  • 7/25/2019 Scandic Hotel Project

    44/81

    Scandic Hotel in Aarhus2011

    43 | P a g e

    between them is going from 0.5 to 2m. To link the steel profile several materials can be used:

    wooden panels, HEB steel profiles, fiber concrete or finally but very rarely, sheet pile profiles.

    The panels are pressed down in stage between the HEB-steel profiles as the excavation goes

    down. Generally, this type of wall can only support small soil pressures.

    Advantages:

    This method is for large excavation;

    Berlin wall is often used along an existing building;

    It's very convenient to urban areas;

    The implementation is simple.

    Disadvantages:

    The Berlin wall is only used for small depth; This method can't be used in case of a high water-table level.

    It mostly used for temporary structures.

    6.1.5. Diaphragm wall

    -by Sophie-

    Diaphragm wall, also called slurry wall in United States, is a continuous retaining wall formed

    and cast in a trench. The terms

    "diaphragm" and "slurry wall'

    come from the final step of the

    implementation. The slurry is

    replaced by concrete which acts

    like structural system for

    temporary retaining wall or as a

    part of a permanent structure.

    Diaphragm walls are mainly used

    for deep excavations basements /parking and tunnels. They can

    also be used as the future

    foundations of the construction

    above.

  • 7/25/2019 Scandic Hotel Project

    45/81

    Scandic Hotel in Aarhus2011

    44 | P a g e

    The method of implementation is suitable for urban areas because it doesn't generate a lot of

    noise or vibration compared to sheep pile driving. First a guide-wall made from in-situ cast

    concrete, concrete elements, guide rail constructions will be placed on the ground to make sure

    that the future will be straight. Then panels will be driven and filled in with bentonite so the

    drilling will stay opened and not collapsed. After that, the traditionally bounded reinforcementis placed in the drilling. Finally the concrete is poured in the drilling as the bentonite is forced

    out of the trenches. This fluid will be after cleaned and reused.

    Advantages:

    This method allows retaining walls of great depth (up to 100m);

    It can be used in case of high water-table level;

    Excavations can be made in difficult conditions of the soil;

    The implementation can be made very close to existing construction;

    The retaining wall can be a part of the final foundation of the construction.

    Disadvantages:

    There is a risk of variation in the thickness of the wall;

    The implementation takes quite a long time;

    This method is very expensive;

    The construction of this type of wall requires the use of heavy construction

    equipment;

    It also takes a lot of space on the construction site and above it;

    The excavated soil has to be moved somewhere else.

    6.1.6. Secant pile walls

    -by Marta-

    Secant pile walls are formed by constructing interlocked concrete piles reinforced with either

    steel rebar or steel beams. Used extensively in dense population areas due to the minimal

    disturbance they cause to adjacent structures, secant walls are a form of top down construction

    used for environmental remediation and soil retention.

  • 7/25/2019 Scandic Hotel Project

    46/81

    Scandic Hotel in Aarhus2011

    45 | P a g e

    Figure 12 Scheme of principles

    Primary piles are installed first with secondary piles constructed in between primary piles once

    the latter gain sufficient strength. Pile overlap is typically in the order of 8 centimetres.

    Advantages:

    Can be used close to existing buildings (no noise and vibration);

    Increased construction alignment flexibility;

    Increased wall stiffness compared to sheet piles;

    Can be installed in difficult ground (cobbles/boulders);

    Can be used as a permanent construction;

    Good a load bearing construction;

    Can be used in very deep excavation (more 8m);

    Gentle installation method (drilling).

    Disadvantages:

    Increased cost compared to sheet pile walls;

    Takes a long time to install;

    Using a lot of materials (steel and concrete);

    Verticality tolerances may be hard to achieve for deep piles;

    Total waterproofing is very difficult to obtain in joints.

  • 7/25/2019 Scandic Hotel Project

    47/81

    Scandic Hotel in Aarhus2011

    46 | P a g e

    6.2. Conclusion

    -by Marta-

    Comparing the mentioned retaining walls the timber- and concrete sheet pile walls could be

    disregarded as an option quite easily. That is because the timber sheet pile walls were not an

    option considering the height of the construction and the concrete pile walls are too heavy and

    too expensive.

    The implementation of the diaphragm walls takes quite a long timeand also it is very expensive,

    so in this way this type of wall was also not a good option.

    The main reason why the berlin wall was not chosen is that it is not completely waterproof.

    The steel sheet pile walls have also some disadvantages, but comparing with the other type of

    walls they are still the best solution which could be used for this construction.

    The secant pile walls were chosen from the start because there was a need to get close to the

    existing buildings in one part of the building; therefore it was really important to choose a type

    of wall which it can be implemented without noise and vibration.

    The table below shows summarizes the advantages and disadvantages for the chosen wall

    types:

    Steel sheet pile wall Secant pile wall

    Resistance + +

    Stiffness of wall - +

    Duration of installation + -

    Installation in hard soils - +

    Gentleness in installation method - +

    Lifetime + +

    Weight + -

    Cost + -

  • 7/25/2019 Scandic Hotel Project

    48/81

    Scandic Hotel in Aarhus2011

    47 | P a g e

    7. The design of the retaining walls

    -by Marta-

    The design of pile retaining walls requires several successive operations: evaluation of the

    forces and lateral pressures that act on the wall, determination of therequired depth of piling

    penetration, computation of the maximum bending momentsin the piling, computation of the

    stresses in the wall and selection of the appropriatepiling section and the design of the walling

    and anchorage system.

    Before these operationscould be initiated some preliminary information must be obtained.

    These include the elevation of the topof the wall, the elevation of the ground surface in front of

    the wall, the maximum water level. It

    was essential that a subsurface

    investigation has beenperformed with

    exploratory borings and laboratory

    tests of representative samples. Onthis

    basis, a soil profile could be drawn and

    the engineering properties of the

    different soilstrata could be accurately

    determined. These properties should

    reflect the field conditionsunder which

    the wall is expected to operate. Onlyafter these preliminary steps could the

    final design have done.

    Now, by having all these necessary

    information the calculation of the

    retaining walls it can be made.

    The picture shows where the sheet-

    and secant pile walls placed. The blue

    line indicates the place of the steel

    sheet pile walls, and the red onethe

    place of the secant pile walls.

    Figure 13The place of the different type of retaining walls

  • 7/25/2019 Scandic Hotel Project

    49/81

    Scandic Hotel in Aarhus2011

    48 | P a g e

    The dimensioning of the walls was examined in ultimate limit state. This limit state ensures

    sufficient safety against failure, and as a basis of the calculation it uses the plasticity theory /

    failure theory (Coulombs failure condition):=c+*tan .

    To satisfy the ultimate limit state, the structure must not collapse when subjected to the peakdesign load for which it was designed. A structure is deemed to satisfy the ultimate limit state

    criteria if all factored bending, shear and tensile or compressive stresses are below the factored

    resistance calculated for the section under consideration.

    The soil parameters taken from the geotechnical description are characteristic values; therefore

    it is important to define the partial coefficients for these parameters and to determine the

    design value of them.

    The Danish National Annex (EN 1997-1 DK NA:2008) set up the following values for the

    different parameters:

    Figure 14 Partial coefficients for soil parameters (m)

    The Danish National Annex it also says that depending on the structure whether it is a

    permanent or a temporary one partial coefficients shall be used with values taken as (M)

    where is a number for which the following applies: 0 <

  • 7/25/2019 Scandic Hotel Project

    50/81

    Scandic Hotel in Aarhus2011

    49 | P a g e

    The long term stateuses the parameters cand , which are referred to as the drained

    (effective) strength parameters. The clay now its rough, so in the calculations the effective

    friction angle was going to be used.

    The sand both in short and long term state is treated as a rough soil layer.

    To calculate the sheet and the secant pile walls it was used Brinch Hansens general theory

    about lateral soil pressure, which forms the basis for the calculation of traditional sheet piling in

    Denmark. The fundamental principle of Brinch Hansens theory is that the lateral soil pressure

    on a given wall is dependent on the walls direction of movement and the location of the point

    around which the wall rotates.

    It is important to mention here that because of the lack of information about how to calculate

    the water pressure caused by the difference in water-tables between the back and the front

    sides of the wall, it was considered that the water level on both side of the wall is in the samelevel.

    It was important to choose the most economical solution; therefore more methods were used

    in the calculations.

    Through dimensioning, the walls total height is determined, as well the pull force in the

    anchorand the maximal moment in the wall.

    Because of the depth of penetration, the anchor force and the maximal moment are different

    for thecalculation methods; it means that there will be different price levels for the different

    walls. It ispossible, through a comparison of the calculations, to choose the most economic wall

    ifconsideration must not be taken to a specific depth of penetration, a given anchorage or a

    specificprofile.

    Brinch Hansen has shown that a retaining wall that is correctly dimensioned under thecondition

    of a specific fracture mode will not be able to fail in any other way.

    With the calculations it was determined the following:

    Toe level

    Lengthof wall

    Maximum bendingmoment

    Horizontalanchorload

  • 7/25/2019 Scandic Hotel Project

    51/81

    Scandic Hotel in Aarhus2011

    50 | P a g e

    There were performed both hand and computer calculation in order to have more secure

    results. For this it was used the Danish software SPOOKS, which also uses the basis for the

    calculation of sheet piling described by Brinch Hansen.

    7.1. Steel sheet pile walls-by Marta-

    The steel shite pile walls will be placed in the whole contour line of the excavation, except the

    line along the adjacent boundary to the south and along a ca. 22 m stretch of the southern part

    of neighbouring boundaries to the east.

    Figure 15The different type of layers and their parameters used for the calculations

    In order to find the best and cheapest solution the calculation was done by using 4 methods.

    According to BrinchHansens soil pressure theory, one can choose different fracture methods,

    which have an influence on thesheet piles final hammering depth and dimensions.

  • 7/25/2019 Scandic Hotel Project

    52/81

    Scandic Hotel in Aarhus2011

    51 | P a g e

    The retaining walls are penetrated in clay so both the short term state (STS) and long term state

    (LTS) was checked.

    The steel sheet pile walls were designed

    with:

    1. One anchor with

    a. 0 yield hinge

    b. 1 yield hinge

    c. 2 yield hinges

    2. Two anchors

    After all the calculations (See Appendix no.6)the results are shown in the following tables:

    The results by using 1 anchor with 0, 1 or 2 yield hinges:

    UNDRAINEDCONDITION

    Toe level

    Length (m)

    Mmax (kNm/m)

    A (kN/m)

    0 yield hinge

    +3.28

    9.72

    -8.25

    547.52

    1 yield hinge

    +3.21

    9.79

    -92.66

    558.26

    2 yield hinges

    +3.05

    9.95

    2.77

    543.49

    DRAINEDCONDITION

    Toe level

    Length (m)

    Mmax (kNm/m)

    A (kN/m)

    0 yield hinge

    +2.49

    10.51

    16.52

    176.81

    1 yield hinge

    +3.09

    9.91

    56.55

    120.50

    2 yield hinges

    +1.15

    11.85

    59.00

    126.26

    Figure 16 Anchored wall with 0, 1 and 2 yield hinges

  • 7/25/2019 Scandic Hotel Project

    53/81

    Scandic Hotel in Aarhus2011

    52 | P a g e

    The results by using 2 anchors:

    All these solutions are correct, but they will have big impact on the price of the wall.The

    following can change the results:

    The installation method of the sheet Soil conditions

    The possible dimensions of the available sheet

    The anchor capacity

    Is this the final excavation level or is it only a temporary excavation level

    Steel prices in different qualities

    Comparing the results from both short and long term it seems that the long term solution used

    for all of the methods should be used to make the calculation of the sheet walls.

    To find the best price, first the length of the wall was considered. If the wall is shorter the price

    can be reduced importantly.By designing the sheet pile walls with one anchor the results show

    that using one yield hinge gives the shortest wall: 10.11 meters.Introducing one more anchor

    the height of the wall will be reduced to +9.3 meters.

    After this, the horizontal anchor loads give the result that the wall with two anchors has smaller

    or more or less the same anchor pull than the one with just only one anchor.

    The last thing was to compare the maximum bending moments. The values indicates that the

    difference between the bending moments is not that big, so the appropriatesteel qualitywhichis going to be used can be the same for all of the methods.

    As a final conclusion the cheapest method is the one with two anchors, thanks to its shorter

    height and lower anchor pulls.

    Toe level

    Length (m)

    Mmax (kNm/m)

    A1(kN/m)

    A2(kN/m)

    UNDRAINEDCONDITION

    +3.5

    9.5

    78.40

    46.72

    93.72

    DRAINEDCONDITION

    +3.7

    9.3

    135.73

    60.73

    74.9

  • 7/25/2019 Scandic Hotel Project

    54/81

    Scandic Hotel in Aarhus2011

    53 | P a g e

    Now with these results, the steel quality has to be chosen. Because the bending moment in the

    wall is quite small, the steel quality S 240 GPfrom the German HOESCH company was selected:

    The value 240is the characteristic value of the yield strength: fyk= 240 MPa. The safety factor of

    steel is equal to: f,steel=1.1. Therefore the design strength can be calculated as:

    So: MPa.Now the steel quality is chosen, the next step is to find the most appropriate sheet type. For

    this the necessary moment of resistance will be calculated with the following formula:

    The last thing in the selection of the steel sheet pile walls is the shape of the walls, the profile.

    The steel sheet piles are typically made of rolled steel U or Z profiles that have folded

    lengthwise edges that lock together with the neighbouring profile and steer the profile whilst it

    isbeing hammered down into the ground. For this construction the Z-shaped steel sheet pile is

    going to be installed: they feature the joints located outside in the right and left when fit with

    each other.

  • 7/25/2019 Scandic Hotel Project

    55/81

    Scandic Hotel in Aarhus2011

    54 | P a g e

    Figure 17Thechosen profile and its dimnesions

    7.2. Secant pile walls

    -by Sophie-

    Secant pile walls will be placed on the line along the adjacent boundary to the south and along

    a ca. 22 m stretch of the southern part of neighbouring boundaries to the east.

    Figure 18The different type of layers and their parameters used for the calculations

  • 7/25/2019 Scandic Hotel Project

    56/81

    Scandic Hotel in Aarhus2011

    55 | P a g e

    The secant pile walls are placed mostly on clay which has a result that the calculation of them in

    undrained condition wasnt working. Therefore these retaining walls were designed only in long

    term state (LTS).

    Two methods were used by designing these walls:

    1. One anchor without yield hinge

    2. Two anchors

    Because the present layers are stiff it is not necessary to use any yield hinges.

    After all the calculations (See Appendix no.7) the results are shown in the following table:

    Comparing the results, first of all,they show that the shortest wall is given by the wall with two

    anchors by the second solution. The maximum bending moment is the smallest in the wall

    without yield hinge but the difference is not too big so the Solution 2 using 2 anchors is againthe winning method. Then it is noticed that the anchor pull (the summarized one) is almost the

    same in each solution. The first solution of the secant pile wall with 2 anchors can be

    disregarded easily because the Solution 2 in each aspect is the better solution. In the end, the

    decisive aspect was the height of the wall, therefore the cheapest solution is considered to be

    the Solution 2.

    7.2.1. Calculation of the reinforcement

    For this construction site, one of two secant pile is reinforced. (See Figure 12) This means thatthe reinforcement in the anchor has to be considered for one entire pile and two half of them.

    Basically for the calculations two wall elements will be taken into account when determining

    the reinforcement in the secant pile wall.

    DRAINED

    CONDITION

    Toe level

    Length (m)

    Mmax (kNm/m)

    A1(kN/m)

    A2(kN/m)

    0 yield hinge

    +1.37

    10.63

    190.55

    547.52

    -

    2 anchors

    Solution 1

    +3.0

    9.0

    342.80

    510.6

    48.2

    2 anchors

    Solution 2

    +3.7

    8.3

    224.50

    258.04

    298.54

  • 7/25/2019 Scandic Hotel Project

    57/81

    Scandic Hotel in Aarhus2011

    56 | P a g e

    The secant pile wall takes the load coming from the earth pressure corresponding to the

    calculation of the retaining wall. Each wall element acts like a vertical beam with its bottom end

    fixed in the ground. The diaphragms formed by the two levels of parking are not considered in

    the calculations because the wall has to stand the earth pressure before the implementation of

    the rest of the building. Thats why the earth pressure has a triangular distribution and themoment which is considered is quite big.

    First the concrete strength, diameter of the pile and strength of steel are picked and those will

    be verified with the calculations. In this case:

    Concrete: C25/30

    Fcd= 25 MPa

    Steel: B550

    Fyd= 458 MPa

    Diameter of secant pile: d = 80 cm

    Then, an assumption is made to start the calculations with z (which is the hight between the

    centre of gravity of the reinforced part and the centre of gravity of the compression part.)

  • 7/25/2019 Scandic Hotel Project

    58/81

    Scandic Hotel in Aarhus2011

    57 | P a g e

    The formula written above gives the exact dimensions of the compressed area. The centre of

    gravity of the compressed area has to be calculated to find the exact z. after the same

    calculation are done again to shows that the theoretical result found before was approaching

    and of course to find the exact section of steel that has to be put in the pile.

    The steel cage is placed all around the wall element even if in

    the end, it will be really relevant only in the tensed part.

    Finally the diameter of 80 cm is sufficient. The steel section found is:

    As= 30.1 cm2

    The solution that has been decided is 10 steel bars with a diameter of 32 each placed all around

    the wall element. (See sketch below)

    7.3. Conclusion

    On the site will be installed two different types of retaining walls: in one hand steel sheet pile

    walls and in the other hand secant pile walls. More methods were done in order to find the

    most economical solution, and thiswas given in both cases by using two anchors. The steel

    sheet pile walls will have a length of 9.3 meters and the secant pile walls will be with one meter

    shorter: 8.3 meters. To show how these retaining walls will be placed on the site a drawing was

    made. (See Appendix no.9)

  • 7/25/2019 Scandic Hotel Project

    59/81

    Scandic Hotel in Aarhus2011

    58 | P a g e

    8. Ground anchors

    -by Marta-

    A ground anchor is defined as a steel bar or multi-strand tendon grouted in a drilled hole

    inclined at an angle below horizontal, whichis capable of transmitting an applied tensile load to

    a load bearing stratum, for the specifiedduration of the structure in which it is required to

    withstand the design load.

    Considering the type of the anchor which will be installed to the walls, the inclined anchors will

    bring the best solution. The other option was the horizontal ones, but because of the problems

    which would have been appeared during the installation, this solution was disregarded.

    The retaining walls were designed, so the values for the anchor pulls are known. The type of theground anchors was also chosen so the next step is to calculate them.

    To calculate the anchors it means to find out their length. The length of the anchors is formed

    by the external-, free-, and the fixed length.

    External length

    It is approximated to 1 meter.

    Free length

    This is that length of the tendon which transmits no

    load to the surrounding strata.

    Coulombs theory says that potential failure plane

    behind the wall forms an angle with the

    horizontal: (See the picture).

    Figure 19 Calculation of anchor length

  • 7/25/2019 Scandic Hotel Project

    60/81

    Scandic Hotel in Aarhus2011

    59 | P a g e

    In order to make the calculations the partial coefficients have to be considered. The Danish

    National Annex says that these coefficients for the ground anchors (Piles and anchors) are not

    relevant in Denmark:

    Figure 20 Partial coefficients for soil parameters (m)

    It is important to note: because the retaining walls will be installed as permanent construction,

    together with them the ground anchors will be permanent too. Therefore the same rule will be

    applied here too: the value for in (M) is set to 1.0.

    Different layers of soil are faced when calculating the anchors for the steel sheet pile wallswhich means it has to be taken into account that the layers have different friction angles. To

    stay on the safe side, the lowest friction angle (30) was used in order to determine the free

    length of the anchors.

    As a normal procedure, the inclined anchors will have a 20 inclination; this of course can

    change up to 2 because the drilling machines cannot be that precise.

    To calculate the fixed length it can be used the figure shown above. From the triangle thelength of the c is known, which is the distance from the foot point of the wall to the anchor

    point.

    First, by dividing the triangle in two ones, the common leg of them could be expressed as:

  • 7/25/2019 Scandic Hotel Project

    61/81

    Scandic Hotel in Aarhus2011

    60 | P a g e

    The ccan be calculated by summarizing the two adjacent legs of the triangles:

    Then,bis determ