Date: 09/02/2 016 CEO: Nguyen Xuan Thi Minh Group No: 3 Group Members: Ankit Singhvi Rashmee Raghu Shrey Dahlan Virangi Desai Key points discussed: 1. What is the throughput time? A1. The throughput time for the process will be 26 minutes. 2. What will be the cycle time? A2. The cycle time is 10 minutes. 3. What will be the total number of batches produced in the working hours? A3. The total number of batches that would be produced in the working hours is 21 batches.

description

kirsten cookey

Transcript of SBR1 Kirsten Cookey

Page 1: SBR1 Kirsten Cookey

 

1. What is the throughput time?

A1. The throughput time for the process will be 26 minutes. 

2. What will be the cycle time?

A2. The cycle time is 10 minutes.

3. What will be the total number of batches produced in the working hours?

A3. The total number of batches that would be produced in the working hours is 21 batches.

Date:  09/02/2016 CEO: Nguyen Xuan Thi Minh

Group No: 3 Group Members:

Ankit SinghviRashmee RaghuShrey DahlanVirangi Desai

Key points discussed: