SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

62
SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1 Addendum #1 Wiedeman and Singleton, Inc. August 14, 2020 ADDENDUM NO. 1 TO CONTRACT, BONDS AND SPECIFICATIONS SAXON STREET WATER TREATMENT PLANT STORAGE BUILDING RE-PURPOSING FOR THE COMMISSION OF PUBLIC WORKS OF THE CITY OF LAURENS, SOUTH CAROLINA Bids Received until 2:00 PM, Local Time, August 20, 2020 ACKNOWLEDGE RECEIPT OF THIS ADDENDUM BY INSERTING ITS NUMBER IN THE PROPOSAL; FAILURE TO DO SO MAY SUBJECT BONA FIDE BIDDER TO DISQUALIFICATION. THIS ADDENDUM FORMS A PART OF THE PROJECT DOCUMENTS; IT MODIFIES THEM AS FOLLOWS: TECHNICAL SPECIFICATIONS SECTION 00 01 00 TABLE OF CONTENTS Page 1 of 4 and Page 4 of 4 Modify the Table of Contents to include: 02 65 00 – Underground Storage Tank Removaland “Asbestos Abatement Plan” prepared by Terracon dated August 4, 2020 into Appendix A SECTION 02 65 00 UNDERGROUND STORAGE TANK REMOVAL Page 1 to 5 Add Specification 02 65 00 – Underground Storage Tank Removal SECTION 05 51 50 LADDERS Paragraph 2.5.H Page 4 of 6 Replace the paragraph of this Section with the following: “H. Rail and Harness Fall Arrest System: Permanently mounted to ladder rungs and complete with necessary components as follows: 1. All fixed ladders shall be equipped with a flexible cable ladder fall prevention system designed to provide protection against falling for persons connected to the system while climbing the fixed ladder and shall be 3M DBI-SALA Lad-Saf Cable Vertical Safety System. 2. Fall prevention system shall be complete including top and bottom brackets, 3/8-inch diameter carrier cable and non-metallic “L” shaped cable guides. 3. The system when installed shall meet the OSHA and ANSI requirements, including ANSI A14.3. 4. Fall prevention system shall be the products of a single manufacturer and a complete system. Substitution of equipment

Transcript of SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Page 1: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Addendum #1 Wiedeman and Singleton, Inc. August 14, 2020

ADDENDUM NO. 1

TO CONTRACT, BONDS AND SPECIFICATIONS

SAXON STREET WATER TREATMENT PLANT STORAGE BUILDING RE-PURPOSING FOR

THE COMMISSION OF PUBLIC WORKS OF

THE CITY OF LAURENS, SOUTH CAROLINA

Bids Received until 2:00 PM, Local Time, August 20, 2020

ACKNOWLEDGE RECEIPT OF THIS ADDENDUM BY INSERTING ITS NUMBER IN THE PROPOSAL; FAILURE TO DO SO MAY SUBJECT BONA FIDE BIDDER TO DISQUALIFICATION. THIS ADDENDUM FORMS A PART OF THE PROJECT DOCUMENTS; IT MODIFIES THEM AS FOLLOWS:

TECHNICAL SPECIFICATIONS

SECTION 00 01 00 TABLE OF CONTENTS Page 1 of 4 and Page 4 of 4

Modify the Table of Contents to include: “02 65 00 – Underground Storage Tank Removal” and “Asbestos Abatement Plan” prepared by Terracon dated August 4, 2020 into Appendix A

SECTION 02 65 00 UNDERGROUND STORAGE TANK REMOVAL Page 1 to 5

Add Specification 02 65 00 – Underground Storage Tank Removal

SECTION 05 51 50 LADDERS Paragraph 2.5.H Page 4 of 6

Replace the paragraph of this Section with the following: “H. Rail and Harness Fall Arrest System: Permanently mounted to ladder rungs and complete with necessary components as follows:

1. All fixed ladders shall be equipped with a flexible cable ladder fall prevention system designed to provide protection against falling for persons connected to the system while climbing the fixed ladder and shall be 3M DBI-SALA Lad-Saf Cable Vertical Safety System.

2. Fall prevention system shall be complete including top and bottom brackets, 3/8-inch diameter carrier cable and non-metallic “L” shaped cable guides.

3. The system when installed shall meet the OSHA and ANSI requirements, including ANSI A14.3.

4. Fall prevention system shall be the products of a single manufacturer and a complete system. Substitution of equipment

Page 2: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-2

Addendum #1 Wiedeman and Singleton, Inc. August 14, 2020

from multiple manufacturers is not permitted.

5. Provide installation and service labels for each fall prevention system installed.

6. Fall prevention system including cable for exterior applications shall be galvanized.

7. Top brackets and bottom shall allow for direct connection to the ladder.

8. Top brackets shall include internal shock absorber assembly and shall extend 4' above the top ladder rung.

9. Cable guides shall be positioned along the carrier cable between the top and bottom brackets and at any point along the system where the cable may abrade against the structure.

10. Provide a ladder safety sleeve. “

SECTION 05 60 00 MISCELLANEOUS METALS Paragraph 2.1.D Page 3 of 9

Modify the paragraph of this Section as follows: “D. Fall Prevention

1. The fall prevention system shall be 3M DBI-SALA Lad-Saf Cable Vertical Safety System.

2. Substitutions: Section 01 60 00 - Product Requirements”

SECTION 05 60 00 MISCELLANEOUS METALS Paragraph 2.2.F Page 4 of 9

Replace the paragraph of this Section with the following: “F. Fall Prevention System:

1. All fixed ladders shall be equipped with a flexible cable ladder fall prevention system designed to provide protection against falling for persons connected to the system while climbing the fixed ladder and shall be 3M DBI-SALA Lad-Saf Cable Vertical Safety System.

2. Fall prevention system shall be complete including top and bottom brackets, 3/8-inch diameter carrier cable and non-metallic “L” shaped cable guides.

3. The system when installed shall meet the OSHA and ANSI requirements, including ANSI A14.3.

4. Fall prevention system shall be the products of a single manufacturer and a complete system. Substitution of equipment from multiple manufacturers is not permitted.

5. Provide installation and service labels for each fall prevention system installed.

6. Fall prevention system including cable for exterior applications shall be galvanized.

7. Top brackets and bottom shall allow for direct connection to the ladder.

8. Top brackets shall include internal shock absorber assembly

Page 3: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-3

Addendum #1 Wiedeman and Singleton, Inc. August 14, 2020

and shall extend 4' above the top ladder rung.

9. Cable guides shall be positioned along the carrier cable between the top and bottom brackets and at any point along the system where the cable may abrade against the structure.

10. Provide a ladder safety sleeve. “

QUESTIONS AND ANSWERS

In response to questions that have been formally submitted by bidders, responses are provided as follows and form a part of the Contract Documents:

Page 4: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Bid Date: THURSDAY AUGUST 20, 2020 @ 2:00 PM8/14/2020 14:06

Question # Question Answer

1 Can you give me a brief description of the work?

This project consists of re-purposing an existing masonry maintenance shop (approximate 1640 sf) at the Saxon Street Water Treatment Plant to an Administrative Building, including interior upfit, electrical, HVAC, plumbing, concrete retaining walls, site improvements, utility relocation, etc.

2 Can you give me an estimated value of this project? The budget is $550,000 to $650,000.

3 Could you please let me know where I could download bid documents The bid documents can be viewed and ordered online from Duncan-Parnell's online bid room: www.dpibidroom.com

4 Checking to see if there’s a need for shoring gear and if yes, how to get the list of interested bidders regarding your Saxon Street Water Treatment Plant Building project

Refer to the Duncan-Parnell online bid room for a list of plan holders and the drawings for the utility and excavation requirements for the project.

5 Will there be a pre-bid conference for this project....if so can you please tell me what date and time....and also if the pre-bid is mandatory There will not be a pre-bid meeting for this project.

6 Please provide specifications for Glazing requirements Refer to Specification 08 85 13 for requirements for Glazing Sealants.

7 Please provide clarification and specifications for Fire Alarm work that is required in the building. A fire alarm system is not required.

8 Are specifications available for the aluminum doors Refer to Specification 08 41 13 for requirements for Aluminum-framed Entrances & Storefront.

9 I would like to propose a RidgeRock retaining wall system in lieu of the designed concrete retaining wall system for this project. The project should be bid per the drawings with the concrete retaining wall.

10 I wanted to follow up with you in regards to the Fall Protection Plan (Lad Saf Ladder Lifeline). I would like to provide a proposal for these items if possible.

Refer to Specification 05 51 50 for requirements for cable type fall prevention system for the ladder for the project. Specification 05 60 00 will be revised by Addenda to include a cable type fall prevention system.

QUESTIONS FROM BIDDERS

Update:

Saxon Street Water Treatment Plant Storage Building Re-purposing

W&S Project No. 049-19-120

FORLCPW, Laurens, SC

NOTES:

1. Company Names and Trade Names have been removed from the questions. The answers contain trade names only to refer to existing installations. These inclusions do not represent an endorsement of the product or the company.2. Questions from sales representatives have been edited where appropriate for brevity.3. Questions from General Contractors have been left untouched.4. Significant Changes in answers previously posted are marked in red.

Page 5: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

SAXON STREET WTP STORAGE BUILDING RE-PURPOSING SECTION 02 65 00 LAURENS COMMISSION OF PUBLIC WORKS UNDERGROUND STORAGE TANK REMOVAL

Wiedeman and Singleton, Inc. Page 1 of 5

SECTION 02 65 00

UNDERGROUND STORAGE TANK REMOVAL

1.1 SUMMARY

A. The Contractor will be responsible for the removal of the following tank system(s) 1. An underground 1,000-gallon petroleum/fuel oil storage tank. The presence of the tank has

not been confirmed but is presumed to exist because of a visible vent pipe. The vent/presumed tank are located within the excavation for the retaining wall. If required, the Contractor shall completely remove and dispose of the existing underground storage tank system. Removal work shall include demolition and removal of underground tank, associated oil and petroleum products, and all other incidentals to complete the work as required.

2. Contractor shall remove and dispose of oil and petroleum contaminated soils as designated by the Owner.

3. The tank is expected to be empty but may include fuel residues, sludges, and other solids or liquids. The Contractor shall remove and dispose of these materials whether flammable or not, and whether existing or generated by Contractor’s cleaning activities. Contractor shall provide all labor, material, equipment, and services to completely empty, clean, and transport all tank contents in accordance with Federal, State and local regulations, and in such a manner that contents are not discharged to the local environment. Contractor shall perform pump-out, recovery, removal, legal disposal, and clean-up of all fuel residues remaining in the existing tank.

4. Contractor shall be responsible for backfilling and compaction testing of the excavation to remove the tank/soils and restoring the excavation to pre-existing conditions for construction of the retaining walls.

5. The Contractor shall obtain and pay for all local and state permits required for removal and disposal of the tank and soils.

B. Related Sections: 1. Section 02 41 16 - Structure Demolition: Demolition of utilities and other underground

items. 2. Section 31 00 00 – Earthwork

1.2 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Written plan describing in detail the procedures used to remove and dispose of any remaining liquid from the underground storage tank; cleaning, removing and disposing of the underground storage tank; and disposal of oil and petroleum contaminated soils as designated by the Owner.

C. Certification documents that personnel are qualified for UST closures. Submit documentation of past UST closures successfully completed by the Contactor.

1.3 CLOSEOUT SUBMITTALS

A. Section 01 70 00 - Execution and Closeout Requirements: Requirements for submittals.

Page 6: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

SAXON STREET WTP STORAGE BUILDING RE-PURPOSING SECTION 02 65 00 LAURENS COMMISSION OF PUBLIC WORKS UNDERGROUND STORAGE TANK REMOVAL

Wiedeman and Singleton, Inc. Page 2 of 5

B. After completion of the tank removal, provide a final report documenting removal, transportation and disposal activities. The document shall include the following: 1. Photographic documentation of the work. 2. Lab and field results. 3. Copies of all certifications and permits for the disposal facilities required by State and

Federal regulatory agencies to receive and dispose of the liquid and solid wastes resulting from the performance of the work

4. Documentation/manifest of disposal of tank at an approved disposal site. 5. Documentation/manifest of disposal of liquid material, if any, to an approved disposal site. 6. Documentation/manifest of disposal of contaminated soil at an approved disposal site.

1.4 PRE-DEMOLITION MEETINGS

A. Section 01 30 00 - Administrative Requirements: Pre-demolition meeting.

B. Convene minimum one week prior to commencing work of this section.

1.5 QUALITY ASSURANCE

A. Underground storage tank removal and disposal shall comply with the following: 1. American Petroleum Institute (API) recommended Practice 1604. 2. United States Environmental Protection Agency (EPA), 40 CFR Part 280. 3. United States Environmental Protection Agency (EPA), Test Methods for Petroleum

Hydrocarbons, SW-846. 4. OSHA Standards 29 CFR Part 1910 and 1926. 5. South Carolina DHEC Regulation 61-92, Underground Storage Tank Control Regulations

1.6 SEQUENCING

A. Section 01 10 00 - Summary: Requirements for sequencing.

1.7 SCHEDULING

A. Section 01 30 00 - Administrative Requirements and 01 32 16 - Construction Progress Schedule: Requirements for scheduling.

B. Schedule work to coincide with new construction.

1.8 MEASURENT AND PAYMENT

A. See the Bid Form.

B. Measurement and payment shall be by the unit price for the work item completed. 1. If so directed by the Engineer, the Contractor shall remove and dispose of the underground

1,000-gallon petroleum/fuel oil storage tank and oil and petroleum contaminated soils as designated by the Owner. a. Reimbursement for the removal and disposal of the underground 1,000-gallon

petroleum/fuel oil storage tank shall be via extra work and shall include the complete removal and disposal of the existing underground storage tank system and other

Page 7: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

SAXON STREET WTP STORAGE BUILDING RE-PURPOSING SECTION 02 65 00 LAURENS COMMISSION OF PUBLIC WORKS UNDERGROUND STORAGE TANK REMOVAL

Wiedeman and Singleton, Inc. Page 3 of 5

incidentals and for backfilling and compaction testing of the excavation to pre-existing conditions for construction of the retaining walls. As required, includes the recovery, removal, legal disposal, and clean-up of all fuel residues remaining in the existing tank.

b. Reimbursement for the removal and disposal of petroleum impacted soils, where designated by the Engineer and Owner, shall be via extra work and shall include removal, proper disposal and replacement of the soils with compacted and tested backfill.

1.9 SAFETY AND PRECAUTION

A. The Contractor shall determine the appropriate level of personal protection for all workers associated with work performed under this section to ensure health and safety of all personnel, including subcontractors, engaged in the tank removal activities.

B. The Contractor shall provide Personal Protective Equipment (protective suits, gloves, boots, hard hats, respiratory equipment etc.) for all workers as required for protection against exposure to contamination. Contractor shall determine the required level of personal protective equipment during each phase of the work. Contractor shall ensure his/her personnel are properly trained to use these items. Contractor shall follow all OSHA requirements.

C. Personnel working in the general vicinity of the USTs shall be trained and thoroughly familiar with the safety precautions, procedures, and equipment required for controlling the potential hazards associated with this work. Personnel shall use proper protection and safety equipment during work around the storage tank.

D. The area surrounding the tank and/or tank excavation shall be secured by temporary fence to protect building occupants, visitors and workers.

E. The Contractor shall eliminate all potential sources of ignition from the area, including but not limited smoking materials, nonexplosion proof tools, electrical equipment, and internal combustion equipment.

F. The Contractor shall provide and maintain an adequate supply of fire extinguishers and other required safety equipment in close proximity to all tank cleaning and removal activities.

G. The Contractor shall test interior UST spaces and surrounding excavation areas to detect dangerous vapor levels until the USTs are removed from the project site.

H. Prior to ending operations on any work day or at any time the Contractor is not on site, the Contractor shall secure all areas of work in a safe manner to the satisfaction of the Engineer and Owner.

1.10 COORDINATION

A. Section 01 30 00 - Administrative Requirements: Requirements for coordination.

B. Conduct demolition to minimize interference with adjacent and occupied structures and areas.

C. Coordinate demolition work with new construction.

Page 8: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

SAXON STREET WTP STORAGE BUILDING RE-PURPOSING SECTION 02 65 00 LAURENS COMMISSION OF PUBLIC WORKS UNDERGROUND STORAGE TANK REMOVAL

Wiedeman and Singleton, Inc. Page 4 of 5

D. Coordinate and sequence demolition so as not to cause shutdown of operation of surrounding areas.

PART 2 PRODUCTS Not Used

PART 3 EXECUTION

A. All work shall be conducted in accordance with the applicable standards of the latest edition of the American Petroleum Institute (API) Recommended Practice 1604 “Closure of Underground Petroleum Storage Tanks.

3.2 DEMOLITION

A. Contractor shall locate and identify the tank to be closed; Contractor is responsible for determining exact location of underground work

B. The Contractor shall remove all flammable or combustible liquids, petroleum-impacted liquids, wash water, and/or sludge remaining in the tank. The Contractor is responsible for the collection, transfer, storage, transportation, and disposal of all materials removed from the tank.

C. All flammable or combustible liquids, petroleum-impacted-liquids, and/or sludge removed from the system by the Contractor shall be disposed of by the Contractor in accordance of all applicable Federal, State, and local codes and regulations.

D. The Contractor shall avoid spilling any petroleum/fuel oil during the tank removal process. The Contractor is responsible for the cleanup and remediation of any and all releases of petroleum/fuel oil to the environment that occur during that tank removal process.

3.3 UNDERGROUND STORAGE TANK CLEANING AND REMOVAL

A. Perform frequent combustible gas meter readings of the tank interior atmosphere during preparation, cleaning, storage, and removal. Monitor atmosphere as required to ensure that there is never the potential for fire or explosion. Prevent vapors from accumulating at ground level. Keep all tanks properly vented until ready to remove them from the excavation.

B. Clean and remove all flammable vapors from the tank to levels suitable for the safe removal of the tank. Once the tank is cleaned and inert then carefully excavate around the tank, exposing as much of the tank as possible, to allow for a visual inspection of the tank surface to identify possible holes, cracks, etc. and other evidence that a leak may have occurred. Remove the tank out of the excavation, place on a level surface, and block the tank to prevent movement. The exterior of each tank and pipe shall be cleaned, and if contaminated soil or groundwater conditions exist, the cleaning wastes contained for proper disposal.

C. Continue to excavate soils around the tank to permit removal. Petroleum-impacted soils and non-impacted soils must be segregated into separate piles. All excavated materials shall be placed on

Page 9: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

SAXON STREET WTP STORAGE BUILDING RE-PURPOSING SECTION 02 65 00 LAURENS COMMISSION OF PUBLIC WORKS UNDERGROUND STORAGE TANK REMOVAL

Wiedeman and Singleton, Inc. Page 5 of 5

double layers of 6-mil or thicker polyethylene sheeting. Cover and securely anchor with polyethylene sheeting all soils at the end of the work day.

D. The tank shall be rendered unusable and shall be removed from the site and disposed of in accordance with all applicable regulations at an approved disposal facility. All cutting shall be done in such a way, and using such tools and equipment as to prevent generation of sparks of flame.

3.4 PETROLEUM IMPACTED SOIL

A. If during the tank removal, evidence of a past or ongoing release is discovered, notify the Engineer and Owner.

B. The extent of contaminated soil removal by the Contractor shall be determined by a testing firm to be retained by the Owner. Soils will be sampled and analyzed by the Owner. Contractor shall exercise care to preserve the material below and beyond the limits of excavation. Where excavation is carried out, through error, below indicated grade or beyond the lines of excavation, the Contractor shall backfill to the indicated grade and compact with approved fill at no additional cost to the Owner.

C. All petroleum or petroleum saturated soils identified from the tank excavation by the Owner shall be removed and disposed of by the Contractor in accordance with all Federal, State and local regulations and requirements. The Contractor is responsible for the proper transportation and proper disposal of the soils at an approved disposal facility.

D. Pending analysis by the Owner, segregated soils shall be maintained on-site on impermeable plastic sheeting and covered with plastic sheeting so as to prevent run-off or run-on of rainwater. Stockpiled materials shall be inspected daily to assure integrity of the plastic liner and cover

3.5 PROTECTION OF FINISHED WORK

A. Section 01 70 00 - Execution and Closeout Requirements: Requirements for protecting finished Work.

END OF SECTION

Page 10: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan

LAURENS CPW MAINTENANCE BUILDING

201 SAXON STREET

LAURENS, SOUTH CAROLINA

August 4, 2020

Terracon Project No. 86207131

Prepared for:

Wiedeman and Singleton, Inc.

Rock Hill, South Carolina

Prepared by:

Terracon Consultants, Inc.

Greenville, South Carolina

_________________________

Jeffrey A. Gurrie, CIH

SCDHEC Asbestos Designer #22728

Page 11: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

TABLE OF CONTENTS

WORK REQUIREMENTS Page Number

1.0 GENERAL REQUIREMENTS ............................................................................ 1

1.1. Background Information............................................................................... 1 1.2. Scope of Work ............................................................................................. 1 1.3. Contractor Use of Premises ......................................................................... 3 1.4. Coordination ................................................................................................ 4 1.5. Pre-Construction Conference ...................................................................... 6

1.6. References .................................................................................................. 6 1.7. Definitions .................................................................................................... 7 1.8. Submittals .................................................................................................. 11

1.9. Daily Reports ............................................................................................. 12 2.0 PRODUCTS ..................................................................................................... 13

2.1. Materials .................................................................................................... 13 2.2. Equipment ................................................................................................. 14

3.0 EXECUTION .................................................................................................... 16 3.1. Construction of Worker/Equipment Decontamination Systems ................. 16

3.2. Asbestos Work Area Preparation (General) .............................................. 16 3.3. Asbestos Work Area Preparation (Non-Friable Materials) ......................... 17 3.4. Asbestos Removal (Window Glazing Compound) ..................................... 17

3.5. Asbestos Removal (Roofing) ..................................................................... 18 3.6. Decontamination of Work Areas ................................................................ 18

3.7. Disposal of Asbestos Material and Contaminated Debris .......................... 19 3.8. OSHA Required Air Monitoring .................................................................. 20

3.9. Clearance Air Monitoring ........................................................................... 20

APPENDIX A - Asbestos Survey Report

Page 12: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 1

1.0 GENERAL REQUIREMENTS

1.1. Background Information

Terracon Consultants, Inc. (Terracon) conducted an asbestos and lead-based paint survey

on the Laurens CPW Maintenance Building located at 201 Saxon Street in Laurens, South

Carolina. This structure is planned for renovation. The following Plan outlines work

practices required by South Carolina Department of Health and Environmental Control

(SC DHEC) Asbestos Regulation 61-86.1 to meet the requirements for an asbestos project

design. Other federal and state regulations are included by reference and shall also apply.

General provisions of the Contract, including General and Supplementary Conditions and

other Specification sections prepared by Wiedeman and Singleton, Inc. or Laurens CPW,

apply to Work of this section. In case of conflict between this plan and the contract

documents the more explicit or stringent shall apply.

The Owner for this project is Laurens CPW and is referred to throughout this Plan as

“Owner.” Wiedeman and Singleton, Inc. may also fulfill the role of Owner for the purpose

of this Plan.

The Owner’s authorized representative for the purposes of asbestos abatement is referred

to as Engineer, Designer, or Air Monitoring Firm throughout the Plan. The Engineer,

Designer, or Air Monitoring Firm (Terracon) will advise and consult with the Owner.

The Contractor is the person or entity identified as such in the Owner-Contractor

Agreement and is referred to throughout the Plan as “Contractor.” The term Contractor

means the Asbestos Abatement Contractor for the purposes of this Plan. The Owner will

contract with a qualified abatement Contractor.

1.2. Scope of Work

1.2.1. The scope of work includes the cleaning, removal, and disposal of identified

asbestos-containing materials (ACM) that are affected by renovations at this site.

Asbestos was detected or assumed in samples of the following materials:

▪ Pink and white window glazing compound (1.1% anthophyllite) on the windows

throughout; and,

▪ Flashing and gray roof sealant (5% chrysotile) on the roof.

A copy of Terracon’s Asbestos Survey Report is attached for additional details.

Page 13: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 2

All quantities estimated in the inspection report shall be field verified by

the Contractor.

1.2.2. The following removal work practices are required for the identified ACM.

Additional requirements are provided in Section 3.0.

Material Full

Containment

Non-

Friable

Removal

Notes

Window Glazing

Compound

No Yes

(See

notes)

Damaged material shall be HEPA

vacuumed initially. Removal of window

glazing compound may be removed as a

component if other renovation

specifications allow for the complete

removal of windows.

Roof Flashing No Yes The removal of asbestos-containing

roofing materials shall be coordinated with

the roofer to limit water infiltration into the

building. The entire roof system will be

replaced.

1.2.3. The Contractor shall stage work in a clear and organized manner.

1.2.4. Authorized workers: All workers performing work within asbestos work areas at

this site must be licensed by SC DHEC with an appropriate asbestos credential.

1.2.5. Asbestos-containing material found to extend from the designated areas into,

through, above, or below walls, ceilings, roofs, behind paneling, above ceilings, or

other barriers is also included in this specification.

1.2.6. Discovery of other hazardous materials. If hazardous materials, such as

chemicals, or other hazardous materials are discovered during the course of the

work other than asbestos debris, the Contractor shall cease work in affected area

and immediately assess the area. The Owner shall be notified within the work shift

of discovery.

1.2.7. The Contractor shall assume full responsibility and liability for the compliance with

all applicable federal, state and local regulations pertaining to work practices,

hauling, disposal, and protection of workers, visitors to the site, and persons

occupying areas adjacent to the site. The Contractor is responsible for providing

medical examinations and maintaining medical records of personnel as required

by the applicable federal, state, and local regulations. The Contractor shall hold

the Owner, Architect, and Engineer/Air Monitoring Firm harmless for failure to

comply with any applicable work, hauling, disposal, safety, health or other

regulation on the part of himself, his employees, or his subcontractors.

Page 14: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 3

1.2.8. Contractor must furnish all permits, labor, material, services, insurance, tools,

equipment (including, but not limited to, power and water), and notifications in

accordance with EPA, OSHA, State, and all other applicable agencies to complete

removal of asbestos containing materials from the structures. It is the Contractors’

responsibility to be aware of and obtain all permits necessary to complete the

scope of work.

1.2.9. Where in the performance of the Work, workers, supervisory personnel,

subcontractors, or consultants may encounter, disturb, or otherwise function in the

immediate vicinity of any identified asbestos-containing materials, take appropriate

continuous measures as necessary to protect all building occupants from the

potential hazard of exposure to airborne asbestos. Such measures will include the

procedures and methods described herein, and compliance with regulations of

applicable federal, state and local agencies.

1.2.10. The Contractor is responsible for all costs, including additional visits, should the

Air Monitoring Firm determine that the Contractor failed a final inspection.

Notification and scheduling of the final inspection during the project is the

responsibility of the Contractor. The Contractor will allow a minimum notice of 48

hours unless the designer and the Contractor agree upon a different time frame.

1.2.11. In event of any apparent conflict among codes, standards, or this Plan, the

Contractor shall refer the conflict to the Owner or Engineer for written resolution.

1.3. Contractor Use of Premises

1.3.1. The Contractor shall limit their use of the premises to the work indicated. The

Contractor is responsible for securing all points of ingress/egress to the buildings.

1.3.2. Use of Site: Confine operations at the site to the areas permitted under contract.

Portions of the site beyond areas on which work is indicated are not to be

disturbed. Conform to site rules and regulations affecting the work while engaged

in project construction.

1.3.3. Driveways and Entrances: Keep driveways and entrances adjacent to the

premises clear and available to the Owner. Do not use these areas for parking or

storage of materials. Schedule deliveries to minimize space and time

requirements for storage of materials and equipment on-site. All vehicles must be

parked in areas approved by the Owner.

Page 15: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 4

1.3.4. The Contractor at all times shall keep the premises free from accumulation of

waste materials or rubbish caused by his operations. At the completion of the work

the Contractor shall leave the Project in a clean and orderly condition, including

removing all his waste materials and rubbish from and about the Project as well as

all his tools, construction equipment, machinery, and surplus materials.

1.3.5. Title to Materials: All materials resulting from demolition work, except as specified

otherwise, shall become the property of the Contractor and shall be disposed of as

specified herein.

1.4. Coordination

1.4.1. Coordinate construction operations included in various Sections of these

Specifications to assure efficient and orderly completion of each part of the Work.

Coordinate construction operations included under different Sections that depend

on each other for proper installation, connection, and operation.

1.4.2. Develop a directory of all entities involved in the project. Include the Contractor's

principal staff assignments, including the Superintendent and other personnel in

attendance at the site. Identify individuals, their duties and responsibilities. List

business name, contact person, normal business and emergency telephone,

pager and fax numbers and addresses.

1.4.2.1. Supervisor. All supervisors on the project shall have a minimum of two years

experience in the administration and supervision of asbestos abatement

projects including work practices, protective measures for building and

personnel, disposal procedures, etc. One supervisor shall be provided for

every 10 workers inside each containment. A minimum of one supervisor

shall be provided per asbestos abatement work area.

1.4.2.2. The Contractor shall have at least one employee on the jobsite in either a

foreman, supervisor, and/or competent person position that is fluent in

English and also fluent in any necessary languages to effectively

communicate with abatement personnel who do not fluently speak

English. That person must be on site at all times as long as non-English

speaking personnel are working on site.

1.4.2.3. A competent person, as defined in the OSHA asbestos standard 29 CFR

1926.1101, employed by the Contractor must be outside each work area at

all times to monitor activity, ensure containment security, provide information

to visitors, and provide access to the work area. The competent person,

Page 16: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 5

employed by the Contractor, shall be bilingual in the appropriate languages

when employing workers who do not speak fluent English.

1.4.3. Notify other entities at the job site of the nature of the asbestos abatement

activities, location of asbestos-containing materials (ACM), requirements relative

to asbestos set forth in these specifications and applicable regulations. Advance

notification will be made to: the Owner; employees who will perform asbestos

abatement work or related activities or who will be in the work area during the

course of the work of this contract; and, employers of employees who work and/or

will be working in adjacent areas during the course of the work of this contract.

1.4.4. Notify emergency service agencies (not less than 10 days prior to start) including

fire, ambulance, police or other agency that may service the abatement work site

in case of an emergency. Notification is to include methods of entering work area,

emergency entry and exit locations, modifications to fire notification or fire-fighting

equipment, and other information needed by agencies providing emergency

services.

1.4.5. Contingency Plan: Prepare a contingency plan for emergencies or any other event

that may require breaching of work area containment or modification or

abridgement of decontamination or work area isolation procedures. Include in this

plan procedures for performing electrical and mechanical repairs inside

containment after abatement work has begun. Include in plan specific procedures

for decontamination or work area isolation. Note that nothing in this specification

should impede safe exiting or providing of adequate medical attention in the event

of an emergency. Items to be addressed in the plan include, but are not limited to

the following:

1. Fire

2. Accident

3. Life threatening injury

4. Non-life threatening injury

5. Rescue

6. Power Failure

7. Pressure differential system failure

8. Breach of containment

9. Electrical faults or shock

10. Excessive heat / cold (if/when such limits are specified)

11. Supplied air system failure

12. Water leaks

13. Waste spills

14. Unauthorized entry into work area

Page 17: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 6

15. Elevated air samples outside of containment

16. Repairs inside containment

17. Toxic releases

1.5. Pre-Construction Conference

1.5.1. A separate progress meeting, recognized as "Pre-Construction Conference" will

be convened by the Owner prior to start of any asbestos abatement. The

preconstruction conference will be scheduled before start of asbestos abatement,

at a time convenient to the Owner Meet at the project site, via teleconference, or

as otherwise directed, with General Superintendent, Owner, and other entities

concerned with the asbestos abatement work.

1.5.2. Attendees: Authorized representatives of the Owner and their consultants may be

in attendance. An authorized representative of the Contractor and its

superintendent; major subcontractors; manufacturers; suppliers; and other

concerned parties shall attend the conference. All participants at the conference

shall be familiar with the Project and authorized to conclude matters relating to the

Work.

1.6. References

1.6.1. Except to the extent that more explicit or more stringent requirements are written

directly into the contract documents and abatement plan, all applicable codes,

regulations, and standards have the same force and effect (and are made a part

of the central documents by reference) as if copied directly into the contract

documents, or as if published copies are bound herewith.

1.6.2. The current issue of each regulation, code and standard shall govern. Where

conflict among requirements or with these specifications exists, the more stringent

requirements shall apply.

1.6.3. U.S. Department of Labor, Occupational Safety and Health Administration,

(OSHA), including but not limited to:

1. Occupational Exposure to Asbestos, Tremolite, Anthophyllite, and Actinolite:

Final Rules Title 29, Part 1910, Section 1001 and Part 1926, Section 1101, of

the Code of Federal Regulations.

2. Respiratory Protection: Title 29, Part 1910, Section 134 and Title 29, Part

1926, Section 103 of the Code of Federal Regulations.

3. Construction Industry: Title 29, Part 1926, of the Code of Federal Regulations.

4. Access of Employee Exposure and Medical Records: Title 29, Part 1910,

Page 18: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 7

Section 20 and Title 29, Part 1926, Section 33 of the Code of Federal

Regulations.

5. Specifications for Accident Prevention Signs and Tags: Title 29, Part 1910,

Section 145 of the Code of Federal Regulations.

6. Personal Protective Equipment: Title 29, Part 1910, Section 132 and Title 29,

Part 1926, Sections 95 through 107 of the Code of Federal Regulations.

7. Hazard Communication: Title 29, Part 1910, Section 1200 and Title 29, Part

1926, Section 59 of the Code of Federal Regulations.

8. Lead in Construction; Title 29, Part 1926, Section 62.

1.6.4. U.S. Environmental Protection Agency (EPA) including but not limited to:

1. Asbestos Abatement Project Rule: 40 CFR Part 763 Subpart G; as of July 1,

1991.

2. Regulations for Asbestos: Title 40, Part 61, Subpart A of the Code of Federal

Regulations.

3. National Emissions Standard for Asbestos: Title 40, Part 61, Subpart M

(Revised Subpart B); Code of Federal Regulations.

4. Hazardous Wastes: Title 40, Part 260-265.

1.6.5. American National Standards Institute (ANSI):

1. ASTM D1331 - 1989: Surface and Interfacial Tension of Solution of Surface-

Active Agents.

2. American National Standard for Respiratory Protection - Respirator Use-

Physical Qualifications for Personnel, Publication Z88.6-1984

3. Practices for Respiratory Protection - Publication Z88.2-1992

1.6.6. American Society for Testing and Materials (ASTM):

1. ASTM D-1331 - 1989: Surface and Interfacial Tension of Solution of Surface

Active Agents.

1.6.7. Underwriters Laboratories, Inc. (UL):

1. UL 586 - 1985 (Rev 1988): High-Efficiency Particulate, Air Filter Units.

2. E1368-90: Standard Practice for Visual Inspection of Asbestos Abatement

Projects

1.6.8. South Carolina Dept. of Health and Environmental Control (SCDHEC)

1. Regulation 61-86.1 Standards of Performance for Asbestos Projects.

1.7. Definitions

Page 19: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 8

1.7.1. Air Filtration Units: A local exhaust unit, utilizing high-efficiency particulate air

(HEPA) filtration and capable of maintaining a minimum negative pressure

differential of 0.02 inches of water within the containment barrier with respect to

that of the environment surrounding the containment barrier. The unit also cleans

recirculated air or generates a constant air flow from adjacent areas into the

abatement work area through the decontamination enclosure.

1.7.2. Air Pressure Monitoring: The process of measuring the air pressure differential

between the containment barrier and the surrounding area using inches of water

unit.

1.7.3. Amended Water: Water to which a surfactant (wetting agent) has been added to

increase the ability of the liquid to penetrate asbestos-containing materials (ACM).

1.7.4. Area Monitoring: Sampling of asbestos fiber concentrations within the asbestos

control area and outside the asbestos control area which is representative of the

airborne concentrations of asbestos fibers that may reach the breathing zone of

personnel potentially exposed to asbestos.

1.7.5. Asbestos: A group of naturally occurring minerals that separate into fibers. There

are six asbestos minerals used commercially: chrysotile; amosite; crocidolite;

tremolite; anthophyllite; and actinolite.

1.7.6. Asbestos Control Area: An area where asbestos removal operations are

performed which is isolated by physical boundaries to prevent unauthorized entry

of personnel and to prevent the spread of asbestos dust, fibers, or debris.

1.7.7. Asbestos-Containing Material (ACM): Any material containing more than 1%

asbestos by volume of any type or mixture of types.

1.7.8. Asbestos Fibers: Asbestos fibers having a length to diameter ratio of at least 3:1

and is 5 micrometers long or longer, as analyzed by Phase Contrast Microscopy

utilizing NIOSH Method 7400.

1.7.9. Asbestos Permissible Exposure Limit: The limit is 0.1 fibers per cubic centimeter

of air as an 8-hour time weighted average as determined by 29 CFR 1926.1101.

1.7.10. Competent Person: One who is capable of identifying existing asbestos, tremolite,

anthophyllite, or actinolite hazards in the work place and who has the authority to

take prompt corrective measures to eliminate them.

1.7.11. Critical Barrier: Those portions of the containment barrier which represent the

Page 20: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 9

minimum structural components necessary to maintain the asbestos removal area

in airtight isolation from the surrounding areas. Critical barriers shall be placed at

floors, windows, ventilation louvers and other openings as necessary to achieve

abatement work area isolation before putting up the double-layer plastic sheeting

containment enclosure within which abatement work is performed. If a temporary

plastic sheeting/stud wall must be erected, it shall be treated as a critical barrier.

The double-layer plastic sheeting containment enclosure shall then be erected on

that wall. Wrappings on lights, control boxes, etc., do not constitute part of the

critical barrier.

1.7.12. Encapsulant: A material applied after the removal of ACM or to the ACM-edges of

partially abated substrates which surrounds or embeds residual asbestos fibers in

an adhesive matrix to prevent their release into the atmosphere.

1.7.13. Equipment Decontamination and Waste Load Out System: A decontamination

area for waste materials and equipment, typically consisting of a designated area

of work area for HEPA vacuuming and wet wiping.

1.7.14. Friable Asbestos Material: Material that contains more than one percent asbestos

as determined using the method specified in Appendix A, Subpart F, 40 CFR Part

763 Section 1, Polarized Light Microscopy, that when dry can be crumbled,

pulverized, or reduced to powder by hand pressure.

1.7.15. Glove Bag: A pouch, typically constructed of a minimum 6 mil thick, 45 inches x

45 inches, transparent polyethylene or polyvinylchloride plastic, with inward

projecting sleeve gloves to abate ACM in a sealed micro-environment with

designated inlets for amended water and sealant application, and a HEPA filtered

vacuum unit attachment. The pouch has capacity for tool storage and to hold

removed ACM.

1.7.16. GFCI (Ground Fault Circuit Interrupter): A type of ground fault protection in areas

where personnel are at high risk of receiving electrical shocks (for example, in

damp locations); makes use of a device designed to trip at a ground current in the

milliampere range, i.e., very much below currents that are normally harmful.

1.7.17. HEPA Vacuum Equipment: High efficiency particulate air (HEPA) filtered

vacuuming equipment with a UL 586 filter system capable of collecting and

retaining asbestos fibers. Filters shall be of 99.97 percent efficiency for retaining

fibers of 0.3 micrometers or larger.

1.7.18. Impermeable Waste-Disposal Containers: Suitable to receive and retain any

asbestos-containing or contaminated material until disposal at an approved site.

Page 21: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 10

The containers shall be labeled in accordance with OSHA Regulation 29 CFR

1910.1001 and 29 CFR 1926.1101. Containers must be both water-tight and air-

tight.

1.7.19. Lockdown: Lockdown is the procedure of applying a protective coating or sealant

to a surface from which asbestos-containing material has been removed. Its

primary function is to control and minimize airborne asbestos fiber generation that

might result from any asbestos-containing residue on the substrate.

1.7.20. Negative Pressure System: A system in which static pressure in an enclosed

control area is lower than that of the environment outside the control area, as

specified herein.

1.7.21. Non-friable Asbestos Material: Material that contains more than one percent

asbestos as determined by the method specified in Appendix A, Subpart F, 40

CFR Part 763 Section 1, in which the fibers have been locked in by a bonding

agent, coating, binder, or other material so that the asbestos is well bound and

may not release fibers in excess of the asbestos permissible exposure limit during

any appropriate use, handling, storing, transporting, or processing. Non-friable

asbestos material may be hazardous and rendered friable during removal and

disposal procedures. Cutting, crushing, grinding and sanding will render non-

friable materials into a friable state.

1.7.22. Personnel Decontamination Unit System: A decontamination unit consisting of a

clean room, shower room, and equipment room separated by airlocks, thus making

a 5-stage system. This unit is attached to the regulated area.

1.7.23. Personal Monitoring: Sampling of asbestos fiber concentrations within the

breathing zone of an employee to determine the 8-hour time weighted average in

accordance with Appendix A of 29 CFR 1926.1101. The samples shall be

representative of the employee's work tasks. The breathing zone shall be

considered an area within 12 inches of the nose or mouth of an employee.

1.7.24. Regulated Area: An area established to demarcate areas where airborne

concentrations of asbestos, tremolite, anthophyllite, actinolite, or a combination of

these minerals exceed or can be expected to exceed the permissible exposure

limits. The regulated area may take the form of an enclosed control area or an area

demarcated to prohibit occupants from the vicinity of the area and prevent potential

exposure to asbestos, tremolite, anthophyllite, or actinolite.

1.7.25. Surfactant (Wetting Agent): A chemical wetting agent added to water to improve

penetration. The surfactant shall be a 50/50 mixture of polyoxyethylene ether and

Page 22: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 11

polyoxyethylene ester, or equivalent, mixed in a proportion of one fluid ounce to 5

gallons of water or as specified by the manufacturer. An equivalent surfactant shall

be understood to mean a material with a surface tension of 29 dynes/cm as tested

in accordance with ASTM D 1331.

1.7.26. Time Weighted Average (TWA): The TWA is an 8-hour time weighted average of

airborne concentration of fibers (5 micrometers or longer) per cubic centimeter of

air which represents the employee's 8-hour workday exposure as determined by

Appendix A of 29 CFR 1926.1101.

1.8. Submittals

1.8.1. The Contractor shall be responsible for obtaining and maintaining all permits and

certifications for the work. All permits and certifications shall be maintained onsite.

The Contractor shall submit permits and certifications to the Owner for

recordkeeping prior to final payment. Final payment will not be made until all

requested submittals have been reviewed and approved by the Owner.

1.8.2. Affidavits: Contractor’s affidavit of payment of debts and claims, affidavit of release

of liens, and consent of surety company to final payment.

1.8.3. Notification: Notify the Owner's Representative and SC DHEC Asbestos Section.

Obtain and post the asbestos removal permit onsite. The Contractor shall notify

SC DHEC by telephone and follow up in writing as soon as possible, but not later

than, the following working day when a project has been canceled. Notification is

also required for any changes in work schedule. Submit notification and permit

copies to the Owner not less than 10 days prior to commencing any work.

Contractor is responsible for obtaining any work practice variances.

1.8.4. All work practice variances must be approved in writing by both the Designer and

SC DHEC. Contractor shall submit written variances for review. Allow one week

for initial review.

1.8.5. Hazard Communication Program: The Contractor will submit evidence, if

requested, of a written Hazard Communication Program as required by 29 CFR

1910.1200.

1.8.6. Respirator Program: Establish and implement a respirator program as required by

ANSI Z88.2, 29 CFR 1910.134, and 29 CFR 1926.1101. Submit evidence of

program, if requested.

1.8.7. Training: Submit to the Owner not less than 10 days prior to commencing any

Page 23: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 12

work documentation that the required EPA, OSHA and State training has been

conducted. Prior to or at time of initial assignment to asbestos work, and at least

annually thereafter, each employee shall be instructed with regard to the hazards

of asbestos, safety and health precautions, the use and requirements for protective

clothing, equipment, and respirators, and the association of cigarette smoking and

asbestos-related disease, and the additional requirements of 29 CFR 1926.1101.

Training shall fully cover engineering and other hazard control techniques and

procedures.

1.8.8. Logs: Submit to the Owner a daily sign in sheet, a record of all employees and

visitors who enter the asbestos control area, daily reports of the abatement activity

compiled by the onsite abatement supervisor, reports of unusual events, and

accident reports.

1.8.9. Landfill Receipts: Submit to the Owner receipts from the approved landfill and

transport manifest recording the transportation and disposal of the asbestos and

demolition waste. Submit detailed delivery tickets, prepared signed, and dated by

an agent of the landfill, certifying the amount of asbestos materials delivered to the

landfill. All asbestos waste shall be disposed of at the location designated on the

SCDHEC abatement permit.

1.9. Daily Reports

1.9.1. The Contractor shall maintain daily logs and reports of job-site activities and

personnel exposure monitoring at the site and shall provide copies to the Owner

prior to final payment.

1.9.2. Reporting Unusual Events: When an event of unusual and significant nature

occurs at site (examples: failure of pressure differential system, rupture of

temporary enclosures, equipment or power failure, high airborne fiber reading),

prepare and submit a special report listing chain of events, persons participating,

response by Contractor's personnel, evaluation of results or effects, and similar

pertinent information.

1.9.3. Accident Reporting: Report all accidents to onsite safety representative. Prepare

reports of significant accidents, at site and anywhere else work is in progress.

Record and document data and actions; comply with industry standards. For this

purpose, a significant accident is defined to include events where personal injury

is sustained, property loss of substance is sustained, or where the event posed a

significant threat of loss or personal injury. Contractor shall be responsible for the

investigation of accidents, the generation of documentation, and the resolution of

Page 24: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 13

issues within its control.

2.0 PRODUCTS

2.1. Materials

2.1.1. Encapsulant: Product shall be rated as acceptable for use intended when field

tested in accordance with ASTM Proposed Specification P-189 “Specification for

Encapsulants for Friable Asbestos Containing Building Materials". Use only

materials that have a flame spread index of 25 or less when dry, when tested in

accordance with ASTM E-84.

2.1.2. Glove-Bag: Transparent polyethylene or polyvinylchloride plastic with long sleeve

gloves, designated inlets for HEPA vacuum attachment, and storage pouch. Use

in accordance with manufacturer’s instructions.

2.1.3. Impermeable Waste-Disposal Containers: Suitable to receive and retain any

asbestos-containing or contaminated material until disposal at an approved site.

The containers shall be labeled in accordance with OSHA Regulation 29 CFR

1910.1001 and 29 CFR 1926.1101. Containers must be both water-tight and air-

tight.

2.1.4. Plastic Sheeting: Polyethylene plastic sheeting material typically 6-mil thickness

for covering floors and walls, providing air locks, and sealing doors and windows;

supply in appropriate widths to minimize seams.

2.1.5. Surfactant (Wetting Agent): 50% polyoxyethylene ester and 50% polyoxyethylene

ether, or approved equal, shall be mixed with water to provide a concentration of

2 ml surfactant to 1 liters of water, or manufacturer's recommended concentration.

2.1.6. Tape: Glass fiber or other tape capable of sealing joints of adjacent sheets of

plastic sheeting and for attachment of plastic sheets to finished or unfinished

surfaces of dissimilar materials under both dry and wet conditions, including use

of amended water.

2.1.7. Warning Signs and Labels: Provide caution signs printed in English at approaches

to asbestos control areas. Locate signs at such a distance that personnel may

read the sign and take the necessary precautions before entering the area.

Provide caution labels printed in English. Affix labels to asbestos materials, scrap,

waste, debris, sealed impermeable bags, asbestos waste drums, and other

asbestos-contaminated products.

Page 25: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 14

1. Warning Signs: The warning signs required by 29 CFR 1926.1101,

paragraph (k)(7), shall bear the following information:

DANGER

ASBESTOS

MAY CAUSE CANCER

CAUSES DAMAGE TO LUNGS

AUTHORIZED PERSONNEL ONLY

In addition, where the use of respirators and protective clothing is required

in the regulated areas, the warning signs shall include the following:

WEAR RESPIRATORY PROTECTION AND PROTECTIVE CLOTHING

IN THIS AREA

2. Warning Labels: Provide label with sufficient print size to be clearly legible

with bold print on a contrasting background, displaying the following

legend:

DANGER

CONTAINS ASBESTOS FIBERS

MAY CAUSE CANCER

CAUSES DAMAGE TO LUNGS

DO NOT BREATHE DUST

AVOID CREATING DUST

2.2. Equipment

2.2.1. The Contractor shall make available three complete sets of personal protective

equipment daily, as required herein, for entry to and inspection of the asbestos

control area by the Owner's Representative or other appointed authorized safety

or health personnel. The items furnished by the Contractor shall include

disposable protective whole body covering, head covering, gloves, foot coverings,

eye protection, and use of the Contractor's staging/decontamination area. The

personal protective equipment shall remain the property of the Contractor.

2.2.2. Respirators: Select respirators approved by the National Institute for Occupational

Safety and Health (NIOSH), Department of Health and Human Services, for use in

atmospheres containing asbestos fibers. Respirator selection shall be in

Page 26: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 15

accordance with OSHA Regulation 29 CRF 1910.134.

2.2.3. Eye Protection: Furnish eye protection for personnel engaged in asbestos

operations when the use of a full face respirator is not required.

2.2.4. Protective Clothing: Personnel exposed to airborne concentrations of asbestos

fibers shall wear disposable protective whole body clothing, head coverings,

gloves, and foot coverings. Cloth gloves may be worn for comfort, but shall not be

used alone. Secure sleeves at the wrists and secure foot coverings at the ankles

with duct tape.

2.2.5. Work Clothing: Cloth or nylon undergarments may be worn under the disposable

protective coveralls.

2.2.6. Decontamination Systems: Provide a personnel decontamination staging area

and an equipment decontamination staging area as described herein. Personnel

entry/exit procedures shall be located adjacent to the regulated area as described

in 29 CFR 1926.1101. Wastewater shall be disposed of as asbestos waste or shall

be filtered through a filter of at least 0.5 micron particle size collection capability

before disposal into the sanitary sewer system. Handle and dispose of filters as

asbestos contaminated waste.

2.2.7. Tools and Exhaust Systems: Provide the local exhaust in accordance with ANSI

Z9.2 and as specified herein. Filters on vacuums and exhaust equipment shall be

absolute HEPA filters and UL 586 labeled. Replace filters as required to maintain

the efficiency of the system.

2.2.8. Scaffolding: Provide scaffolding, ladders and/or staging, etc. as necessary to

accomplish the work of this contract. Scaffolding may be of suspension type or

standing type such as metal tube and coupler, tubular welded frame, pole or

outrigger type or cantilever type. The type, erection and use of scaffolding shall

comply with applicable OSHA provisions.

2.2.9. Electrical Power Cords: Provide grounded extension cords. Use hard-service

cords where exposed to abrasion and traffic. Provide waterproof connectors to

connect separate lengths of electric cords if single lengths will not reach areas

where construction activities are in progress. Do not exceed safe length-voltage

ratio.

2.2.10. Lamps and Light Fixtures: Provide general service incandescent lamps or

fluorescent lamps of wattage indicated or required for adequate illumination as

required by the work or this section. Protect lamps with guard cages or tempered

Page 27: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 16

glass enclosures, where fixtures are exposed to breakage by construction

operations. Provide vapor tight fixtures in work area and decontamination units.

Provide exterior fixtures where fixtures are exposed to the weather or moisture.

2.2.11. First Aid Supplies: Comply with governing regulations and recognized

recommendations within the construction industry.

2.2.12. Fire Extinguishers: Provide hand-carried, portable, UL-rated, Class A fire

extinguishers for temporary offices and similar spaces. In other locations, provide

hand-carried, portable, UL-rated, Class ABC, dry-chemical extinguishers or a

combination of extinguishers of NFPA-recommended classes for the exposures.

Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and

size required by location and class of fire exposure.

3.0 EXECUTION

3.1. Construction of Worker/Equipment Decontamination Systems

3.1.1. Contractor shall establish an equipment room or area that is adjacent to the work

area for the decontamination of workers and equipment contaminated with

asbestos. The decontamination area shall consist of an area covered by an

impermeable drop cloth on the floor or horizontal working surface and be of

sufficient size as to accommodate cleaning of equipment and removing personal

protective equipment without spreading contamination beyond the area when

acceptable by OSHA asbestos regulations. A water hose and bucket shall also be

available to decontaminate equipment.

3.1.2. Filtered Waste Water Drainage: Provide cascaded disposable filter units on drain

lines from showers or any other fluid source carrying ACM. Connect so that

discharged water passes primary filter and output of primary (particles 20 microns

and smaller) filter passes through secondary (particles 5 microns and smaller)

filter. Filtered water shall be discharged into a sanitary sewer. The Contractor

shall not place water in storm drains, onto lawns, or into ditches, creeks, streams,

rivers or oceans.

3.2. Asbestos Work Area Preparation (General)

The Work Area is the location where asbestos abatement work occurs. It is a variable of the

extent of Work of the contract. For this project a "Work Area" is defined as the area in which

asbestos removal is being performed. A "Work Area" is considered contaminated during the

Work, and must be isolated from the balance of the building, and decontaminated at the

completion of the asbestos-abatement work.

Page 28: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 17

3.2.1. The Work Area is the location where asbestos abatement work occurs. It is a

variable of the extent of Work of the contract. For this project a "Work Area" is

defined as the area in which asbestos removal is being performed. A "Work Area"

is considered contaminated during the Work, and must be demarcated from the

balance of the building, and decontaminated at the completion of the asbestos-

abatement work.

3.2.2. Prior to the start of any asbestos related activities, the Contractor shall have a

locked waste container on site.

3.3. Asbestos Work Area Preparation (Non-Friable Materials)

3.3.1. Post Warning signs and barrier tape in and around work area as required by all

applicable regulatory agencies and restrict access to work area to personnel

approved by Contractor or Owner’s Representative.

3.3.2. Damaged ACM shall be HEPA vacuumed during the work area preparation to

prevent spread of ACM.

3.3.3. All building ventilation air systems connected to the work area shall remain off and

sealed during preparation and until the area has passed final visual inspection and

final air sampling when required.

3.3.4. The Contractor shall implement an electrical practice protocol that includes, but is

not limited to, lockout and GFCI shutdown as described in OSHA Construction

Standard 29 CFR 1926.417. All electrical powered equipment utilized during the

project shall have ground-fault protection as described in OSHA Construction

Standards. All equipment and wiring shall be in compliance with National Fire

Protection Association Standard 70, and the National Electrical Code.

3.4. Asbestos Removal (Window Glazing Compound)

3.4.1. Prior to asbestos removal, the Contractor’s equipment, work area and

decontamination area will be reviewed by the Contractor’s Onsite Supervisor to

ensure compliance with regulations. The Owner’s Representative may also review

the work area prior to start.

3.4.2. Place a 6-mil polyethylene sheeting on the wall and floor/ground below the window.

3.4.3. Wet non-friable material with amended water and remove with appropriate

equipment. Spray the asbestos material during the removal to maintain a wet

Page 29: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 18

condition and minimize asbestos fiber dispersion. The asbestos material shall be

removed by means which do not render the material friable or prevent dust from

being released during the removal. Do not subject the material to grinding,

sanding, chipping or abrading. Placing polyethene or tape over the window glazing

compound will also assist in keeping the ACM contained if the window will be

removed as a component.

3.4.4. Remove material in small sections. As it is removed place material in sealable 6

mil polyethylene bags or equivalent and place in appropriately labeled container

for transport. IF window is removed as a component wrap the window in two

separate layers of 6-mil polyethylene. Label and dispose of as specified

elsewhere.

3.5. Asbestos Removal (Roofing)

3.5.1. Prior to asbestos removal, the Contractor’s equipment, work area and

decontamination units will be reviewed by the Contractor’s Onsite Supervisor to

ensure compliance with regulations. The Owner’s Representative may also review

the work area prior to start.

3.5.2. Place a 6-mil polyethylene sheeting approximately 10 feet wide on the ground at

the perimeter of the structure if the parapet wall cannot contain debris from falling

off roof.

3.5.3. Wet non-friable material with amended water and remove with appropriate

equipment. Additional considerations for roof safety and water shall also be taken

in account. Spray the asbestos material during the removal to maintain a wet

condition and minimize asbestos fiber dispersion. Asbestos flashing/mastic may

be cut into sections using axes, hatchets, or power slicers (use of saws or other

dust-generating tools is not allowed) or may be removed intact. Waste will be

placed directly into 6-mil poly-lined waste containers (or wrapped in two layers of

6-mil poly), labeled with asbestos waste labels, and carefully lowered to the

ground. Any debris on the roof or adjacent ground will be HEPA vacuumed.

Dispose of as specified elsewhere.

3.6. Decontamination of Work Areas

3.6.1. Equipment shall be cleaned and all contaminated materials removed before

removing poly from the walls and floors. After polyethylene sheets have been

removed from walls and floors, the Contractor shall clean all surfaces in the work

area, including ducts, electrical conduits, steel beams, roof deck, etc., with

Page 30: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 19

amended water and/or HEPA filtered vacuum. After cleaning the work area, the

Contractor shall allow the area to thoroughly dry and then wet clean and/or HEPA

vacuum all surfaces in work area again. At the completion of the second cleaning

operation, the Contractor's supervisor shall perform a complete visual inspection

of the work area to insure that the work area is dust and fiber free. Final air

sampling shall not commence until the visual inspection is completed and passed.

3.6.2. Notify the Owner and Air Testing firm 48 hours in advance of requiring a final

inspection.

3.6.3. If the Owners representative finds that the work area has not been adequately

decontaminated, cleaning and/or air monitoring shall be repeated until the work

area is in compliance. All repeat visual inspections and air monitoring will be

conducted only after all surfaces are dry.

3.6.4. A lock-down material shall be applied to porous surfaces after the work area has

be visually observed to be dust and fiber free. The lock-down shall be tinted to

visually identify coverage.

3.6.5. After the work area is found to be in compliance from final air monitoring results,

all entrances and exits shall be unsealed and the plastic sheeting, tape, and any

other trash and debris shall be disposed of in sealable plastic bags (6-mil

minimum) and buried in the approved waste disposal site.

3.7. Disposal of Asbestos Material and Contaminated Debris

3.7.1. All waste removal from the work area/containment shall be transported to the load

vehicle/dumpster in sealed containers or bags. Monitor the path for any debris or

broken bags. Fully clean area if accidental spill occurs.

3.7.2. All asbestos materials and miscellaneous contaminated debris shall be properly

sealed and protected, and the loadout vehicle/dumpster shall be locked, while

located on the facility site and then transported to a predesignated disposal site in

accordance with 40 CFR 61.150 and DOT 49 CFR Parts 100-399. All asbestos

waste shall be disposed of at the location designated on the SCDHEC removal

permit.

1. An enclosed vehicle will be used to haul waste material to the disposal site.

No rental vehicles or trailers shall be used. Vehicle selection, vehicle

covers, and work practices shall assure that no asbestos becomes airborne

during the loading, transport, and unloading activity, and that material is

Page 31: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 20

placed in the waste site without breaking any seals.

2. Waste disposal bags: Polyethylene bags (6-mil) with labels.

3. Containers: Non-porous (steel/plastic) drums or equivalent appropriate for

holding waste disposal bags during transportation to the disposal site.

3.7.3. The Contractor shall transport the containers and bags of waste material to the

approved waste disposal site. The sealed plastic bags shall be placed into the

burial site unless the bags have been broken or damaged. Upon the landfill's

approval damaged bags shall be placed in the non-porous containers and the

entire contaminated package shall be buried. Uncontaminated containers may be

recycled.

3.7.4. Workers unloading the asbestos will wear appropriate personal protective

equipment when handling material at the disposal site. Asbestos warning signs

shall be posted during loading and unloading of asbestos waste.

3.7.5. The Contractor shall use the Waste Shipment Record for disposal records as per

40 CFR 61.150 and distribute a copy of all waste shipment records to the Owner

after the completion of the project.

3.8. OSHA Required Air Monitoring

3.8.1. The Contractor is responsible for OSHA required monitoring and shall be

conducted in accordance with OSHA sampling requirements.

3.8.2. The Contractor shall conduct air sampling that is representative of both the 8-hour

time weighted average and 30-minute short-term exposures to indicate compliance

with the permissible exposure and excursion limits. If a negative exposure

assessment is valid monitoring may not be necessary.

3.8.3. Results of personnel air sample analyses shall be available, verbally, within twenty-

four (48) hours of sampling and shall be posted upon receipt.

3.9. Clearance Air Monitoring

3.9.1. The industrial hygiene firm (Terracon) will perform clearance air monitoring and

will contract directly with the Owner. The cost for initial clearance air monitoring

only will be the responsibility of the Owner. All other work, monitoring and services

are the responsibility of the contractor. The industrial hygiene firm shall also offer

Page 32: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos Abatement Plan Laurens CPW Maintenance Building ■ Laurens, South Carolina August 4, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 21

expertise to the designer and Contractor but is not directly responsible for the

performance of the job. The industrial hygiene firm will not supervise, direct,

control or have authority over or be responsible for Contractor’s or its

subcontractors’ means, methods, techniques, sequences or procedures. As such,

the industrial hygiene firm will not issue any “stop-work” notifications to the

Contractor or its subcontractors as the industrial hygiene firm is not in a position to

direct or control the work of the Contractor or its subcontractors. The Contractor

remains solely responsible for handling asbestos-containing materials and

administering its health and safety programs in accordance with applicable local,

state, and federal regulations.

3.9.2. Monitoring During Asbestos Work: Not required by SC R. 61-86.1

3.9.3. Clearance Monitoring After Final Cleanup of Materials.

3.9.3.1. Air samples will be analyzed by Phase Contrast Microscopy (PCM) in general

accordance with NIOSH 7400 Method and shall be analyzed by a laboratory

proficient in the American Industrial Hygiene Association's (AIHA) Proficiency

Analytical Testing Program.

3.9.3.2. A minimum of five samples shall be collected inside the building. A

clearance criterion of not to exceed in any sample of 0.01 f/cc will be

required. If the air results exceed the clearance criteria, cleaning shall be

repeated until the work area is in compliance.

3.9.4. All repeat air monitoring will be conducted only after all surfaces are dry. If an area

fails clearance sampling the Contractor shall re-clean work area. Additional

clearance testing will be at the expense of the Contractor.

Page 33: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

APPENDIX A

ASBESTOS SURVEY REPORT

Page 34: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Responsive ■ Resourceful ■ Reliable

June 16, 2020

Wiedeman and Singleton, Inc. 131 East Main Street, Suite 300 Rock Hill, South Carolina 29730 Attn: Mr. Troy Began, PE

Re: Asbestos and Lead-Based Paint Survey

Laurens CPW Maintenance Shop

201 Saxon Street

Laurens, South Carolina

Terracon Project No. 86207131

Dear Mr. Began:

Terracon Consultants, Inc. (Terracon) is pleased to present the results of the asbestos and lead-

based paint survey performed on the Laurens CPW Maintenance Building located at 201 Saxon

Street in Laurens, South Carolina. We understand that this survey was requested due to the

proposed renovations to the structure. Our services were performed in general accordance with

our Proposal No: P86207131 dated May 26, 2020.

Asbestos-containing materials (ACM) were identified in samples of suspect materials collected

during our survey. Lead was identified in the samples collected during this assessment. Please

refer to the report for further details.

Terracon appreciates the opportunity to provide environmental consulting services to you on

this project. If you should have any questions regarding this report, please contact the

undersigned at (864) 292-2901.

Sincerely,

Terracon Consultants, Inc.

Stephen N. Ellis Jeffrey A. Gurrie, CIH

Staff Industrial Hygienist Senior Industrial Hygienist

Page 35: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Asbestos and Lead-Based Paint

Survey Report

LAURENS CPW MAINTENANCE BUILDING 201 SAXON STREET

LAURENS, SOUTH CAROLINA

June 16, 2020

Terracon Project No. 86207131

Prepared for: Wiedeman and Singleton, Inc.

Rock Hill, South Carolina

Prepared by: Terracon Consultants, Inc.

Greenville, South Carolina

Inspected by:

Stephen N. Ellis

Inspected on June 3, 2020

Page 36: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Responsive ■ Resourceful ■ Reliable

TABLE OF CONTENTS EXECUTIVE SUMMARY ........................................................................................................ I 1.0 INTRODUCTION ....................................................................................................... 1 2.0 BUILDING DESCRIPTION ........................................................................................ 1 3.0 ASBESTOS SURVEY ............................................................................................... 1

3.1 Regulatory Overview ......................................................................................1 3.2 Visual Assessment .........................................................................................2 3.3 Physical Assessment .....................................................................................2 3.4 Sample Collection ..........................................................................................3 3.5 Sample Analysis.............................................................................................3 3.6 Findings and Recommendations ....................................................................3

4.0 LEAD-BASED PAINT SURVEY ................................................................................ 4 4.1 Regulatory Overview ......................................................................................4 4.2 Sampling and Analytical Protocol ...................................................................4 4.3 Sample Collection ..........................................................................................4 4.4 Findings and Recommendations ....................................................................5

5.0 GENERAL COMMENTS ........................................................................................... 5

APPENDICES

A - FIGURE 1 – ACM RESULTS SAMPLE SUMMARY B - TABLE 1 – ACM RESULTS SAMPLE SUMMARY TABLE 2 – LEAD IN PAINT SUMMARY C - LABORATORY REPORTS D – INSPECTOR’S CREDENTIAL

E - PHOTOGRAPHS

Page 37: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

ACM and LBP Survey Report Laurens CPW Maintenance Building ■ Laurens, South Carolina June 16, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable I

EXECUTIVE SUMMARY

Terracon Consultants, Inc. (Terracon) conducted an asbestos and lead-based paint survey

performed on the Laurens CPW Maintenance Building located at 201 Saxon Street in Laurens,

South Carolina. Our survey was conducted on June 3, 2020, in support of planned renovation

activities and in general accordance with the terms of our Proposal No: P86207131 dated May

26, 2020. This Executive Summary is intended as an overview for the convenience of the

reader. The complete report must be reviewed in its entirety prior to making decisions

regarding this site.

ASBESTOS

The asbestos-containing material (ACM) survey was conducted by Mr. Stephen Ellis, a South

Carolina Department of Health and Environmental Control (SCDHEC)-licensed asbestos

inspector. The survey was conducted in general accordance with the sample collection

protocols outlined in South Carolina Regulation 61-86.1 Standards of Performance for Asbestos

Projects. A total of eighteen (18) bulk samples were collected from the structure. A general

layout with sample locations is included as Figure 1 in Appendix A. Sample descriptions,

locations, analytical results, classification and estimated quantities are summarized in Table 1

in Appendix B. Copies of the asbestos laboratory analytical reports are included in Appendix C

and photographs are provided in Appendix E.

Asbestos was detected (greater than 1%) in the following materials:

▪ Pink and white window glazing compound (1.1% anthophyllite) on the windows

throughout; and,

▪ Flashing and gray roof sealant (5% chrysotile) on the roof.

LEAD

The lead-based paint survey was conducted by Mr. Stephen Ellis, an EPA accredited lead

inspector. A total of six (6) samples were collected of paint chips from the subject structure.

The results are summarized in Table 2 in Appendix B. Two (2) of the samples submitted for

analysis detected lead:

▪ White paint (0.84%) on a wooden door frame; and,

▪ Green paint (0.83%) on a wooden door.

Page 38: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Responsive ■ Resourceful ■ Reliable 1

ASBESTOS AND LEAD-BASED PAINT SURVEY REPORT

LAURENS CPW MAINTENANCE BUILDING

201 SAXON STREET

LAURENS, SOUTH CAROLINA

Terracon Project No. 86207131

1.0 INTRODUCTION

Terracon Consultants, Inc. (Terracon) conducted an asbestos and lead-based paint survey

performed on the Laurens CPW Maintenance Building located at 201 Saxon Street in Laurens,

South Carolina. Our survey was conducted on June 3, 2020, in support of planned renovations

and in general accordance with the terms of our Proposal No: P86207131 dated May 26, 2020.

2.0 BUILDING DESCRIPTION

The maintenance building is constructed of brick and concrete on a concrete foundation and

covers approximately 1,200 square feet. The interior of the building is primarily without finishes

on the floors, ceilings, and walls except for a small area of plaster. Heating was previously

provided by a coal or wood stove and no cooling systems were present. Piping in the building

appeared to be un-insulated. Window glazing compound was noted on windows throughout the

building. Roofing consisted of a built-up roofing system on a concrete deck with suspect residual

sealants on the parapet walls.

3.0 ASBESTOS SURVEY

The asbestos survey was conducted by Mr. Stephen Ellis, an SC DHEC licensed Asbestos Building

Inspector (License No. BI-01211). A copy of Mr. Ellis’ license is provided in Appendix D. The survey

was conducted June 3, 2020, in general accordance with the sample collection protocols outlined

in South Carolina Regulation 61-86.1 Standards of Performance for Asbestos Projects.

3.1 Regulatory Overview

An ACM is defined as any material containing asbestos of any type in an amount greater than one

percent (1%). The asbestos NESHAP (40 CFR Part 61, Subpart M) regulates asbestos fiber

emissions and asbestos waste disposal practices. It also requires the identification and

classification of existing building materials prior to demolition or renovation activity. Under

NESHAP, asbestos-containing building materials are classified as either friable, Category I non-

friable or Category II non-friable ACM. Friable materials are those that, when dry, may be crumbled,

pulverized or reduced to powder by hand pressure. Category I non-friable ACM includes packing

materials, gaskets, resilient floor coverings and asphalt roofing products containing more than 1

percent (%) asbestos. Category II non-friable ACM are non-friable materials other than Category I

materials that contain more than 1% asbestos.

Page 39: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

ACM and LBP Survey Report Laurens CPW Maintenance Building ■ Laurens, South Carolina June 15, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 2

Friable ACM, Category I and Category II non-friable ACM which is in poor condition and has become

friable or which will be subjected to drilling, sanding, grinding, cutting or abrading and which could

be crushed or pulverized during anticipated renovation/demolition activities are considered

regulated ACM (RACM). RACM must be removed prior to renovation or demolition activities.

In the State of South Carolina, asbestos activities are regulated by the SC DHEC under SC DHEC

Regulation 61-86.1 Standards of Performance for Asbestos Projects. SC DHEC requires that

asbestos-related activities conducted in a public building be performed by personnel licensed by

SC DHEC. The owner or operator must provide the SC DHEC with written notification of planned

abatement and removal activities prior to the commencement of those activities. The SC DHEC

requires a four (4) day notification for non-friable projects and 10-day notification for RACM projects.

Asbestos abatement must be performed by SC DHEC-licensed asbestos abatement contractors.

A SC DHEC-licensed Project Designer shall prepare a written abatement design for each

abatement renovation project involving the removal of greater than 3,000 square, 1,500 linear, or

656 cubic feet of RACM. Third-party air monitoring must be conducted during the abatement of

friable (regulated) ACM. The SC DHEC asbestos regulations can be found at http://www.SC

DHEC.gov.

The Occupational Safety and Health Administration (OSHA) Asbestos Standard for Construction

Industry (29 CFR 1926.1101) regulates workplace exposure to asbestos. The OSHA standard

requires that employee exposure to airborne asbestos fibers be maintained below 0.1 asbestos

fibers per cubic centimeter of air (0.1 f/cc) for an eight-hour time weighted average. The OSHA

standard classifies construction and maintenance activities, which could disturb ACM, and specifies

work practices and precautions which employers must follow when engaging in each class of

regulated work. A full copy of the OSHA asbestos standard for general industry may be found at

OSHA’s website (www.osha.gov) and should be referenced for specific information.

3.2 Visual Assessment

Our survey activities began with visual observation of the interior and exterior of the building to

identify apparent homogeneous areas of suspect ACM. A homogeneous area consists of building

materials, which appear similar throughout in terms of color, texture and date of application.

Building materials which were not identified as concrete, glass, wood, masonry, metal or rubber

were considered suspect ACM.

3.3 Physical Assessment

A physical assessment of each homogeneous area of suspect ACM was conducted to assess the

friability and condition of the materials. A friable material is defined by the EPA as a material, which

can be crumbled, pulverized or reduced to powder by hand pressure when dry. Friability was

assessed by physically touching suspect materials.

Page 40: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

ACM and LBP Survey Report Laurens CPW Maintenance Building ■ Laurens, South Carolina June 15, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 3

3.4 Sample Collection

Based on the results of the visual sampling, bulk samples of suspect ACM were collected in general

accordance with SC DHEC Regulation 61-86.1 Standards of Performance for Asbestos Projects.

Random samples of suspect materials were collected in each homogeneous area. Bulk samples

were collected using wet methods as applicable to reduce the potential for fiber release. Samples

were placed in sealable containers and labeled with unique sample numbers using an indelible

marker. A summary of the suspect ACM samples collected during the survey is presented in Table

1 in Appendix B.

3.5 Sample Analysis

Bulk samples were submitted using chain-of-custody procedures to Scientific Analytical Institute,

Inc. (SAI) of Greensboro, North Carolina. SAI is accredited under the National Voluntary

Laboratory Accreditation Program NVLAP (#200664-0). The samples were submitted for a

“positive stop” analysis which means once a sample is detected with asbestos the remainder of

the samples in the same homogenous set are not analyzed and are presumed to be of similar

asbestos content. Asbestos analysis was performed by PLM with dispersion staining techniques

per EPA EPA/600/R-93/116. The percentage of asbestos, where applicable, was determined by

microscopical visual estimation. Per the SC DHEC Regulation 61-86.1 Standards of Performance

for Asbestos Projects, negative results for non-friable organically bound (NOB) materials such as

flooring, mastics, or roofing shall be verified with at least one analysis by transmission electron

microscopy (TEM). The additional analysis was performed by TEM in accordance with EPA

Chatfield SOP 1988-02 Rev. 1.

3.6 Findings and Recommendations

A total of eighteen (18) bulk samples were collected from the structure. A general layout with

sample locations is included as Figure 1 in Appendix A. Sample descriptions, locations, analytical

results, classification and estimated quantities are summarized in Table 1 in Appendix B. Copies

of the asbestos laboratory analytical reports are included in Appendix C and photographs are

provided in Appendix E.

Asbestos was detected (greater than 1%) in the following materials:

▪ Pink and white window glazing compound (1.1% anthophyllite) on the windows throughout;

and,

▪ Flashing and gray roof sealant (5% chrysotile) on the roof.

The window glazing compound is currently damaged. This material should be repaired or removed

by an SC DHEC-licensed asbestos abatement contractor. If the above ACMs have the potential of

being disturbed during renovations, they should be removed by an SC DHEC-licensed asbestos

Page 41: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

ACM and LBP Survey Report Laurens CPW Maintenance Building ■ Laurens, South Carolina June 15, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 4

abatement contractor in accordance with SC DHEC Asbestos Regulation 61-86.1 prior to

renovation.

It should be noted that suspect materials, other than those identified during the June 3, 2020, survey

may exist within the work area. Should suspect materials other than those which were identified

during this survey be uncovered prior to or during the upcoming renovation activities, those

materials should be assumed to be asbestos-containing until sampling and analysis demonstrates

otherwise. Federal, state, and local regulations should be consulted before initiating any action on

an ACM.

4.0 LEAD-BASED PAINT SURVEY

4.1 Regulatory Overview

The US Environmental Protection Agency (EPA) defines lead-based paint (LBP) as paint, varnish,

stain, or other applied coating that contain lead equal to or greater than 1.0 milligrams per square

centimeter (mg/cm2), 5,000 mg/kg, or 0.5% by dry weight as determined by laboratory analysis.

As applicable to this project, lead is regulated by South Carolina Department of Health and

Environmental Control (SC DHEC) for disposal. The SC DHEC regulations require that painted

demolition debris with a lead concentration greater than 0.7 mg/cm2, or 0.06% by dry weight be

disposed in a permitted Class II landfill. However, coatings that are de-laminated, deteriorated,

or flaking must be evaluated against the Toxicity Characteristic under state and federal hazardous

waste management regulations. Lead-based paint is defined in SC Regulation 61-107.9, “Solid

Waste Landfills and Structural Fill.” The hazardous waste Toxicity Characteristic is defined in the

SC Hazardous Waste Management Regulation 61-79, at § 261.24, “Toxicity Characteristic.”

4.2 Sampling and Analytical Protocol

4.3 Sample Collection

The lead-based paint survey was conducted by Mr. Stephen Ellis, an EPA accredited lead inspector.

Bulk samples of suspect lead paint were collected from the building. Samples were placed in

sealable containers and labeled with unique sample numbers using an indelible marker. A summary

of the suspect lead paint collected during the survey is presented in Table 2 in Appendix B.

4.3.1 Lead Analysis via Flame Atomic Absorption Spectroscopy

Bulk samples were submitted using chain-of-custody procedures to Scientific Analytical Institute,

Inc. (SAI) of Greensboro, North Carolina. SAI’s Environmental Lead Laboratory is fully accredited

by the American Industrial Hygiene Association Laboratory Accreditation Program, LLC (AIHA-

LAP, LLC) and is recognized by the Environmental Lead Laboratory Accreditation Program

(ELLAP) (#173190). ELLAP is an approved lead laboratory accreditation program under the

Environmental Protection Agency (EPA) National Lead Laboratory Accreditation Program

Page 42: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

ACM and LBP Survey Report Laurens CPW Maintenance Building ■ Laurens, South Carolina June 15, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 5

(NLLAP). Lead paint analysis was performed by Flame Atomic Absorption Spectroscopy per EPA

SW-846 3050B/6010C/7000B.

4.4 Findings and Recommendations

A total of six (6) samples were collected of paint chips from the subject structure. The results are

summarized in Table 2 in Appendix B. Two (2) of the samples submitted for analysis detected lead:

▪ White paint (0.84%) on a wooden door frame; and,

▪ Green paint (0.83%) on a wooden door.

The lead content of the above listed paints meets the EPA definition of lead-based paint (>0.5%)

and also exceeds the SC DHEC regulation criteria (>0.06%). Intact paint on building components

may be disposed in an approved landfill and metal components may be recycled without removing

paint.

The OSHA lead-in-construction standard was intended to apply to detectable concentrations of

lead in paint, as even small concentrations of lead can result in unacceptable employee

exposures depending upon the method of removal and other workplace conditions. All paints

tested contained detectable amount of lead, and therefore, OSHA’s lead-in-construction standard

is applicable. OSHA does not consider methods that rely solely on the analysis of bulk materials

or surface content of lead (or other toxic material) to be acceptable for safely predicting employee

exposure to airborne contaminants. Without air monitoring results or without the benefit of

historical or objective data (including air sampling which clearly demonstrates that the employee

cannot be exposed above the action level during any process, operation, or activity) the analysis

of bulk or surface samples cannot be used to determine employee airborne exposure. A full copy

of the OSHA lead standard for construction industry may be found at OSHA’s website

(www.osha.gov) and should be referenced for specific information.

5.0 GENERAL COMMENTS

This limited ACM and LBP survey was conducted in a manner consistent with the level of care and

skill ordinarily exercised by members of the profession currently practicing under similar conditions

in the same locale. The results, findings, conclusions and recommendations expressed in this

report are based on conditions observed during our survey of the building. The information

contained in this report is relevant to the date on which this survey was performed and should not

be relied upon to represent conditions at a later date.

This report has been prepared on behalf of and exclusively for use by Wiedeman and Singleton,

Inc., Laurens CPW, and Contractors approved by Laurens CPW working onsite for specific

application to their project, as discussed herein. Terracon does not warrant the work of regulatory

agencies, laboratories or other third parties supplying information, which may have been used in

the preparation of this report. No warranty, express or implied is made.

Page 43: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

ACM and LBP Survey Report Laurens CPW Maintenance Building ■ Laurens, South Carolina June 15, 2020 ■ Terracon Project No. 86207131

Responsive ■ Resourceful ■ Reliable 6

This report is not a bidding document. Contractors or consultants reviewing this report must draw

their own conclusions regarding further investigation or remediation deemed necessary.

Page 44: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

APPENDIX A

FIGURE

Page 45: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

FigureGeneral Layout / Sample Locations

Laurens CPW Maintenance Building201 Saxon Street

Laurens, South Carolina72 Pointe Circle Greenville, SC 29615

PH. (864) 292-2901 FAX. (864) 292-6361

1Building layout and

sample locations are

approximated.Date:

6/10/2020

Project Manager:

JAG

Drawn By:

SNE

Checked By:

JAG

Approved By:

Project No.

86207131

Scale:

N.T.S.

File Name:

B3

C1

Maintenance Area

Service Bay Area

Back Storage

Area

A1

A2

C3

C2

Sample Sets D-F were

collected from the roof and

are not depicted here.

A3

B2 B1

Page 46: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

APPENDIX B

TABLES

Page 47: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

A1 PLM

A2 PLM

A3 PLM

B1 PLM

B2 PLM

B3 TEM

C1 PLM

C2 PLM

C3 PLM

D1 PLM

D2 PLM

D3 TEM

E1 PLM

E2 PLM

E3 PLM

F1 PLM

F2 PLM

F3 TEM

Notes:

Base - NAD

Finish - NAD

1.1% Anthophyllite

NAD

NAD

5% Chrysotile

NAD Roof

Roof

Roof

Building Throughout

LPD 140 SF

Flashing and Gray Roof

SealantE Miscellaneous

Category II

Non-FriableGood LPD 225 SF

Residual Roof Mastic on Parapet

WallsF Miscellaneous Non-Friable Good

LPD 1,100 SF

D Miscellaneous Non-Friable Good LPD

TABLE 1

ASBESTOS RESULTS SAMPLE SUMMARY

201 SAXON STREET

LAURENS, SOUTH CAROLINA

Sample

Number

Analysis

Method

Estimated

QuantitySample Location

TERRACON PROJECT NO. 86207131

Sample DescriptionHomogeneous

AreaClassification

Current

Condition

Potential for

Disturbance

Friable /

Non-FriableAnalytical Results

LPD - Low potential for disturbance

PD - Potential for disturbance

PSD - Potential of significant disturbance

SF - square feet

LF - linear feet

CF - cubic feet

LAURENS CPW MAINTENANCE BUILDING

NA - Not Analyzed

NAD - No Asbestos Detected

PLM - Polarized Light Microscopy

TEM - Transmission Electron Microscopy

PACM - Presumed Asbestos Containing Material

SFBack Storage Room Plaster A Surfacing Friable

Windows ThroughoutPink and White

Window Glazing CompoundB Miscellaneous Friable

Damaged PD 180

SF

1) Quantities listed above are estimates to be used for inspection purposes only and should be field-verified for all other uses.

2) A general overview of the site is depicted on Figure 1.

Damaged PD 55

1,200 SFBuilt-Up Roofing

Brick Mortar C Miscellaneous Friable Good

Page 1 of 1

Page 48: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Sample ID

No.Area Substrate Component Color

Lead

Concentration

(%)

LP-1 Interior Wood Door Frame Gray <0.0056

LP-2 Interior Wood Door Gray <0.0058

LP-3 Exterior Metal Door Frame Gray <0.0068

LP-4 Exterior Metal Door Gray <0.0072

LP-5 Interior Wood Door White 0.84

LP-6 Interior Wood Door Frame Green 0.83

Notes:

1) Values above the analytical method detection limit are indicated in bold type

2) Values equal to or greater than 0.060 percent are bolded and shaded

TABLE 2

LEAD IN PAINT SAMPLE SUMMARY (PAINT CHIP)

LAURENS CPW MAINTENANCE BUILDING

LAURENS, SOUTH CAROLINA

TERRACON PROJECT NO. 86207131

201 SAXON STREET

Page 1 of 1

Page 49: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

APPENDIX C

LABORATORY REPORTS

Page 50: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Bulk Asbestos AnalysisBy Polarized Light Microscopy

EPA Method: 600/R-93/116 and 40 CFR, Part 763, Subpart E,App.E

Laurens CPW Maintenance Bldg 86207131Project:

Sample ID

Lab Sample ID

Description

Lab Notes AsbestosFibrous

ComponentsNon-FibrousComponents

Attributes

Treatment

Stephen EllisJeffrey Gurrie

Attn:Customer: Terracon72 Pointe CircleGreenville, SC 29615

Analysis ID: 71943537_PLM

Date Reported: 6/4/2020

Date Received: 6/4/2020

Lab Order ID: 71943537

None DetectedA1 - A

Plaster

finish

WhiteNon FibrousHeterogeneous

Crushed71943537PLM_1

Other 100%

None DetectedA1 - B

Plaster

base

GrayNon FibrousHeterogeneous

Crushed71943537PLM_19

Cellulose Other 5% 95%

None DetectedA2 - A

Plaster

finish

WhiteNon FibrousHeterogeneous

Crushed71943537PLM_2

Other 100%

None DetectedA2 - B

Plaster

base

GrayNon FibrousHeterogeneous

Crushed71943537PLM_20

Cellulose Other 5% 95%

None DetectedA3 - A

Plaster

finish

WhiteNon FibrousHeterogeneous

Crushed71943537PLM_3

Other 100%

None DetectedA3 - B

Plaster

base

GrayNon FibrousHeterogeneous

Crushed71943537PLM_21

Cellulose Other 5% 95%

None DetectedB1

Pink and White WindowGlazing Compound

White, PinkNon FibrousHeterogeneous

Crushed, Dissolved71943537PLM_4

Other 100%

None DetectedB2

Pink and White WindowGlazing Compound

White, PinkNon FibrousHeterogeneous

Crushed, Dissolved71943537PLM_5

Other 100%

Disclaimer: Due to the nature of the EPA 600 method, asbestos may not be detected in samples containing low levels of asbestos. We strongly recommend that analysis of floor tiles, vermiculite, and/orheterogeneous soil samples be conducted by TEM for confirmation of “None Detected” by PLM. This report relates only to the samples tested and may not be reproduced, except in full, without the writtenapproval of SAI. This report may not be used by the client to claim product endorsement by NVLAP or any other agency of the U.S. government. Analytical uncertainty available upon request. ScientificAnalytical Institute participates in the NVLAP Proficiency Testing program. Unless otherwise noted blank sample correction was not performed. Estimated MDL is 0.1%.

Page 1 of 3

Approved SignatoryAnalyst

Scientific Analytical Institute, Inc. 4604 Dundas Dr. Greensboro, NC 27407 (336) 292-3888

Megan Javonovich (21)

P-F-002 r15 1/16/2021

Page 51: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Bulk Asbestos AnalysisBy Polarized Light Microscopy

EPA Method: 600/R-93/116 and 40 CFR, Part 763, Subpart E,App.E

Laurens CPW Maintenance Bldg 86207131Project:

Sample ID

Lab Sample ID

Description

Lab Notes AsbestosFibrous

ComponentsNon-FibrousComponents

Attributes

Treatment

Stephen EllisJeffrey Gurrie

Attn:Customer: Terracon72 Pointe CircleGreenville, SC 29615

Analysis ID: 71943537_PLM

Date Reported: 6/4/2020

Date Received: 6/4/2020

Lab Order ID: 71943537

Not AnalyzedB3

Pink and White WindowGlazing Compound

TEM71943537PLM_6

None DetectedC1

MortarGrayNon FibrousHeterogeneous

Crushed71943537PLM_7

Other 100%

None DetectedC2

MortarGrayNon FibrousHeterogeneous

Crushed71943537PLM_8

Other 100%

None DetectedC3

MortarGrayNon FibrousHeterogeneous

Crushed71943537PLM_9

Other 100%

None DetectedD1

Built-Up Roofing

built up roofing

Black, GrayNon FibrousHeterogeneous

Dissolved71943537PLM_10

Cellulose Fiber Glass

Other 20% 20%

60%

None DetectedD2

Built-Up Roofing

built up roofing

Black, GrayNon FibrousHeterogeneous

Dissolved71943537PLM_11

Cellulose Fiber Glass

Other 20% 20%

60%

Not AnalyzedD3

Built-Up Roofing

TEM71943537PLM_12

5% Chrysotile

E1Flashing and Gray Sealant

built up roofing

BlackNon FibrousHeterogeneous

Dissolved71943537PLM_13

Cellulose Fiber Glass

Other 20% 20%

55%

Disclaimer: Due to the nature of the EPA 600 method, asbestos may not be detected in samples containing low levels of asbestos. We strongly recommend that analysis of floor tiles, vermiculite, and/orheterogeneous soil samples be conducted by TEM for confirmation of “None Detected” by PLM. This report relates only to the samples tested and may not be reproduced, except in full, without the writtenapproval of SAI. This report may not be used by the client to claim product endorsement by NVLAP or any other agency of the U.S. government. Analytical uncertainty available upon request. ScientificAnalytical Institute participates in the NVLAP Proficiency Testing program. Unless otherwise noted blank sample correction was not performed. Estimated MDL is 0.1%.

Page 2 of 3

Approved SignatoryAnalyst

Scientific Analytical Institute, Inc. 4604 Dundas Dr. Greensboro, NC 27407 (336) 292-3888

Megan Javonovich (21)

P-F-002 r15 1/16/2021

Page 52: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Bulk Asbestos AnalysisBy Polarized Light Microscopy

EPA Method: 600/R-93/116 and 40 CFR, Part 763, Subpart E,App.E

Laurens CPW Maintenance Bldg 86207131Project:

Sample ID

Lab Sample ID

Description

Lab Notes AsbestosFibrous

ComponentsNon-FibrousComponents

Attributes

Treatment

Stephen EllisJeffrey Gurrie

Attn:Customer: Terracon72 Pointe CircleGreenville, SC 29615

Analysis ID: 71943537_PLM

Date Reported: 6/4/2020

Date Received: 6/4/2020

Lab Order ID: 71943537

5% Chrysotile

E2Flashing and Gray Sealant

built up roofing

BlackNon FibrousHeterogeneous

Dissolved71943537PLM_14

Cellulose Fiber Glass

Other 20% 20%

55%

5% Chrysotile

E3Flashing and Gray Sealant

built up roofing

BlackNon FibrousHeterogeneous

Dissolved71943537PLM_15

Cellulose Fiber Glass

Other 20% 20%

55%

None DetectedF1

Residual Roof MasticBlackNon FibrousHomogeneous

Dissolved71943537PLM_16

Other 100%

None DetectedF2

Residual Roof MasticBlackNon FibrousHomogeneous

Dissolved71943537PLM_17

Other 100%

Not AnalyzedF3

Residual Roof Mastic

TEM71943537PLM_18

Disclaimer: Due to the nature of the EPA 600 method, asbestos may not be detected in samples containing low levels of asbestos. We strongly recommend that analysis of floor tiles, vermiculite, and/orheterogeneous soil samples be conducted by TEM for confirmation of “None Detected” by PLM. This report relates only to the samples tested and may not be reproduced, except in full, without the writtenapproval of SAI. This report may not be used by the client to claim product endorsement by NVLAP or any other agency of the U.S. government. Analytical uncertainty available upon request. ScientificAnalytical Institute participates in the NVLAP Proficiency Testing program. Unless otherwise noted blank sample correction was not performed. Estimated MDL is 0.1%.

Page 3 of 3

Approved SignatoryAnalyst

Scientific Analytical Institute, Inc. 4604 Dundas Dr. Greensboro, NC 27407 (336) 292-3888

Megan Javonovich (21)

P-F-002 r15 1/16/2021

Page 53: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

6/4/2020Project: Laurens CPW Maintenance Bldg 86207131

Lab Order ID: 71943538

Lab Notes

Description

Lab Sample ID

Sample ID

Semi-QuantitativeChatfield SOP 1988-02 Rev. 1

Asbestos LCL-UCL

(Wt. %)

Bulk Asbestos Analysisby Transmission Electron Microscopy

Date Received:

6/9/2020Date Reported:

Terracon72 Pointe CircleGreenville, SC 29615

Customer:

Analysis ID: 71943538_TB

Attn: Stephen EllisJeffrey Gurrie

AcidSol.

Organic

(Wt. %)(Wt. %) (Wt. %)

87%7.9%

B3

71943538TBS_1

Pink and White Window GlazingCompound

1.0% - 1.2%Anthophyllite1.1 %

None Detected-91%

D3

71943538TBS_2

Built-Up Roofing

None Detected-51%

F3

71943538TBS_4

Residual Roof Mastic

Daniel Schwartz (1)

Scientific Analytical Institute, Inc. 4604 Dundas Dr. Greensboro, NC 27407 (336) 292-3888

Approved Signatory

Page 1 of 1tem_2.2.001

Analyst

Disclaimer: This report relates only to the samples tested and may not be reproduced, except in full, without the written approval of SAI. This report may not be used by the client to claim product endorsementby NVLAP or any other agency of the U.S. government.

T-F-010 r15 1/15/2018

Page 54: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Client: Contact: Addres$: Phone: Fax: Email:

Project:

Client Notes:

P.O.#. Date Submitted:

Analysis: TurnAroundTime: '

l!ample-N-um6er << A1 A2. A3 B1 B2 B3 C1 C2 C3 01 02 D3 E1 E2 E3 F1 F2 F3

Terrac;on Stephen Ellis

*lnstriict1ons: Use Column "B" for your contact info

72 Pointe Circle, Greenville, SC 29615 423-426-2164 To See an Example Click the

bottom Example Tab. [email protected] [email protected] Laurens CPW Maintenance Bldg

86207131

6/3/2020 0:00

PLM EPA 600 / TEM Chatfield 3 DavTAT -1EM Concurrent

Data 1

Enter samples between "«" and ">>" Begin Samples with a "« "above the first sample

and end wit#J a ">>" below the last sample. Only Enter your data on the first sheet "Sheet1"

Sample Des9ri:BVon

Plaster Plaster Plaster Pink and White Window Glazing Compound Pink and White Window Glazing Compound Pink and White Window Glazing Compound Mortar Mortar Mortar Built-Up Roofing Built-Up Roofing Built-Up Roofing Flashing and Gray Sealant Flashing and Gray Sealant Flashing and Gray Sealant Residual Roof Mastic Residual Roof Mastic Residual Roof Mastic

1\qy;S7:)f

Scientific Analytical Institute ,,,,,.

Version 1-15-2012

0~ 4604 Dundas Drive

Greensboro, NC 27407 Phone: 336.292.3888

Fax: 336.292.3313 Email: [email protected]

Data2

Accepted EtJ

~..,.

PLM PLM PLM PLM PLM TEM PLM PLM PLM PLM PLM TEM PLM PLM TEM PLM PLM TEM - R~ected 0 ~ ~,~ ll ~t;V~

Page 55: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Terracon72 Pointe CircleGreenville, SC 29615

Customer:

Analysis ID: 71943540_PBP

Attn: Stephen Ellis

Date Reported: 6/8/2020

Date Received: 6/4/2020

Project: Laurens CPW Maintenance Bldg

Lab Order ID: 71943540

Lab Notes

Description

Lab Sample ID

Sample ID

Analysis for Lead Concentrationin Paint Chips

by Flame Atomic Absorption SpectroscopyEPA SW-846 3050B/6010C/7000B

Concentration

(ppm)(g)

Mass Concentration

(% by weight)

71943540PBP_1

Gray on woodLP-1< 560.0711 < 0.0056%

71943540PBP_2

Gray on woodLP-2< 580.0694 < 0.0058%

71943540PBP_3

Gray on metalLP-3< 680.0587 < 0.0068%

71943540PBP_4

Gray on metalLP-4< 720.0557 < 0.0072%

71943540PBP_5

White on woodLP-584000.0964 0.84%

71943540PBP_6

Green on woodLP-683000.0960 0.83%

Unless otherwise noted blank sample correction was not performed on analytical results. Scientific Analytical Institute participates in the AIHA ELPAT program. ELPAT Laboratory ID: 173190. This reportrelates only to the samples tested and may not be reproduced, except in full, without the written approval of SAI. Analytical uncertainty available upon request. The quality control samples run with thesamples in this report have passed all EPA required specifications unless otherwise noted. RL: (Report Limit for an undiluted 50ml sample is 4µg Total Pb).

Sara Shaut (6)

Scientific Analytical Institute, Inc. 4604 Dundas Dr. Greensboro, NC 27407 (336) 292-3888

Analyst Laboratory Director

Page 1 of 1pbRpt_4.0.01_pbp001

L-F-021 r17 2/14/2020

Page 56: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1
Page 57: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

APPENDIX D

INSPECTOR’S CREDENTIAL

Page 58: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1
Page 59: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

APPENDIX E

PHOTOGRAPHS

Page 60: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Laurens CPW Maintenance Building 201 Saxon Street, Laurens, South Carolina Photos Taken On: June 3, 2020 Project No. 86207131

Page 1 of 3

Photo #1 General view of the front of the building.

Photo #2 General view of the rear of the building.

Photo #3 General view of the right side of the building.

Photo #4 General view of the left side of the building.

Photo #5 General view of the garage bay. Photo #6 General view of the maintenance area.

Page 61: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Laurens CPW Maintenance Building 201 Saxon Street, Laurens, South Carolina Photos Taken On: June 3, 2020 Project No. 86207131

Page 2 of 3

Photo #7 General view of the back-storage area.

Photo #8 General view of the basement storage area.

Photo #9 General view of the roof over the building.

Photo #10 View of plaster (HA-A) over brick in the back-storage area.

Photo #11 View of pink/white window glazing compound (HA-B) on windows throughout. Contains Asbestos.

Photo #12 View of mortar (HA-C) on brick walls throughout.

Page 62: SAXON STREET WTP STORAGE BUILDING RE-PURPOSING ADD-1-1

Laurens CPW Maintenance Building 201 Saxon Street, Laurens, South Carolina Photos Taken On: June 3, 2020 Project No. 86207131

Page 3 of 3

Photo #13 View of built-up roofing (HA-D) on the roof.

Photo #14 View of flashing and gray sealant (HA-E) on the roof. Contains Asbestos.

Photo #15 View of residual roof mastic (HA-F) on the parapet walls.

Photo #16 View of wooden door and door frame. Both have Lead-Based Paint.