SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : -...

96
- 1 Sign of Contractor No of corrections Secretary SPSM SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV RAHURI - 413 722 DIST. AHMEDNAGAR (M. S.) Phone (02426) 243320 B - 1 TENDER ( PERCENTAGE RATE TENDER) No. B - 1/95 2017 2018 NAME OF WORK : - Construction of First Floor of English Medium School for SPSM at Central Campus,MPKV, Rahuri. ISSUED TO : - Office of the Secretary SPSM, MAHATMA PHULE KRISHI VIDYAPEETH RAHURI - 413722, Dist. AHMEDNAGAR (M. S.)

Transcript of SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : -...

Page 1: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 1 –

Sign of Contractor No of corrections Secretary SPSM

SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV RAHURI - 413 722 DIST. AHMEDNAGAR (M. S.)

Phone (02426) 243320

B - 1 TENDER ( PERCENTAGE RATE TENDER)

No. B - 1/95 2017 – 2018

NAME OF WORK : - Construction of First Floor of English Medium

School for SPSM at Central Campus,MPKV, Rahuri.

ISSUED TO : -

Office of the Secretary SPSM, MAHATMA PHULE KRISHI VIDYAPEETH

RAHURI - 413722, Dist. AHMEDNAGAR (M. S.)

Page 2: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 2 –

Sign of Contractor No of corrections Secretary SPSM

INDEX

NAME OF WORK :- Construction of First Floor of English Medium School for SPSM at

Central Campus,MPKV, Rahuri. R NO DESCRIPTION PAGE

FROM

PAGE TO

1

Brief Tender notice 1 2

2

Detailed Tender Notice 3 11

3

Declaration of Contractor 12

4

General Description and Scope of work 13

5

Printed B-1 Agreement Form 14 16

6

Tender for works 17 18

7

Conditions of the contract

19 37

8 Schedule A

38

9

Annexure 39

10 Conditions for materials issued under 40 42

11 Additional General Conditions and

Specifications

43 73

12 Schedule "B"

74 78

13

Drawings 79 80

Secretary SPSM

MPKV, RAHURI

Page 3: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 3 –

Sign of Contractor No of corrections Secretary SPSM

SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

Office of the Secretary, SPSM, MPKV, Rahuri Phone (02426) 243320

No. SPSM/Works/ 95 /of 2017, Dated : 09/05/2017

e-TENDER NOTICE No.3

The on behalf of the Savitribai Phule Shikshan Mandal, the Secretary, SPSM, MPKV, Rahuri

invites online e- tenders in B-1 form from the registered civil contractors in appropriate class

registered in state PWD/Central PWD/Military Engineering services and Railway Department for the

following works at C.C. MPKV, Rahuri. Sr.

No Name of work Approxim

ate

Estimated

cost.

(Rs.

Lakhs)

Earnest

money

Deposit

(Rs.)

Total

SECURI

TY

DEPOSIT

(50 %

cash +

50 %

through

bills)

Completion

period Cost of

blank

tender

form

(Rs.)

Class of

Registra

tion

1 Construction of First Floor of

English Medium School for

SPSM at Central

Campus,MPKV, Rahuri.

42.07 42000.00 105000.00 6 Calendar

Months. 4000.00 Class 6

and

above

Time table for e-Tendering

Sr. No Mahatma Phule

Krishi Vidyapeeth

Stage

Contractor

stage From Date &Time Date &Time up to Envelope /

Remark

1 To publish e-tender --- 11/05/2017

from 10.00 Hrs. 11/05/2017

up to 17.15 Hrs

2. --- Downloading

e-tenders 11/05/2017

from 17.16 Hrs 29/05/2017

up to 17.15 Hrs. Technical

and

commercial

envelope 3. --- Preparation

of e-tenders 11/05/2017

from 17.16 Hrs. 29/05/2017

up to 17.15 Hrs. As above

4. To close sale of

online e-tenders --- 29/05/2017

up to 17.16 Hrs. 30/05/2017

up to 17.00 Hrs.. As above

5. --- Submission

of e-tenders 30/05/2017

up to 17.01 Hrs... 01/06/2017

up to 22.00 Hrs... As above

6. Opening of

Technical envelope --- 02/06/2017

up to 10.00 Hrs... 02/06/2017

up to 17.15 Hrs... Technical

envelope

7. Opening of

commercial

envelope

--- 03/06/2017

up to 10.00 Hrs... 03/06/2017

up to 17.15 Hrs. commercial

envelope

Page 4: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 4 –

Sign of Contractor No of corrections Secretary SPSM

1.The interested and qualified contractors shall download e-tenders and to participate e-tendering procedure, by using

website Portal https//maharashtra.etenders.in./Sub portal :ADF/Location:Mahtma Phule Krishi Vidyapeeth,

Rahuri

2. The interested contractors shall have enrollment with above website and have digital signature certificate. In this

regard if there is any quarries, they may contact telephone number of M/s. Sify Technologies Ltd. Nextender

(India) Pvt. Ltd., Mumbai. On 020-25315555 / 25315556 (Pune).

3. The contractors will have to pay Rs. 1063.00 as a downloading charges of e-tenders for each work directly to the

Sify Technologies Ltd. Nextender (India) Pvt. Ltd., Mumbai.

4. The interested contractors will have to submit all required documents i.e copy of valid registration, PAN No & TIN

No. etc. with Earnest money Deposit, cost of blank tender form should be paid by on line payment mode.

5. The offer will be valid for 120 days from the date of opening of the tender

6. The other terms and condition are available in e-tender form available on above website.

7. The authority reserved the right to reject any all tenders So, received without assigning any reason and no

explanation can be demanded for the rejection of the offer by the person / firm making tender.

8. The office is not responsible for postal delay if any.

9. Royalty charges and permission from concerned Tahashil office will be responsibility of the contractor.

10. No escalation will be paid.

11. Presence of the contractor or his representative is essential for tender opening other wise there tender will not be

considered.

12. As per G.R.B.D.G 2016/prak.2/Ima.2 dated 12.02.2016, the additional security deposit for below rate quoted clause is

applicable.

13. The date of opening of commercial envelop is tentative and subject to change as per date and time finalized by President

SPSM and Hon’ble Vice Chancellor, MPKV, Rahuri.

Secretary (SPSM) MPKV, Rahuri.

NOT TO BE PUBLISHED –

Copy fwcs to : The Editor, Dainik Lokamat,Ahmednagar with a request to publish the above tender notice in your

newspaper in one insertion in minimum space. The bill of the same may please be forwarded in TRIPLICATE in the name of

the Secretary (SPSM) MPKV, Rahuri. for payment. Payment.

Copy fwcs for information to the : 1) Chairman SPSM and Dean Faculty of Agriculture , MPKV, Rahuri 2) Director of

Research, MPKV, Rahuri 3) Director of Extension Education, MPKV Rahuri 4)

Associate Dean (PGI) ,MPKV,Rahuri 5) P.A. to Hon. Vice – Chancellor, MPKV,

Rahuri 6) The Registrar, MPKV Rahuri. 7) The Comptroller, MPKV Rahuri.

Copy for necessary action to : 1)University Engineer MPKV, Rahuri.2) All Directors of SPSM ,MPKV, Rahuri

3) Head Master Higher Secondary School SPSM ,MPKV, Rahuri

4) Head Master Primary School SPSM ,MPKV, Rahuri 5) Head Master English Medium

School SPSM ,MPKV, Rahuri

:

Copy for necessary action to : 1) The I/C Officer ARIS, MPKV, Rahuri. He is requested to publish to above tender notice

on MPKV website. 2) The Director of Communication, MPKV, Rahuri.

Copy to 1) Tender Notice Board , office of the University Engineer, MPKV, Rahuri.

2) Tender Notice Board , office of the Secretary, SPSM, MPKV, Rahuri.

Page 5: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 5 –

Sign of Contractor No of corrections Secretary SPSM

The blank tender form is issued to Shri. / M/s. ……………………………

DETAILED TENDER NOTICE TO CONTRACTORS :

1.1e-tenders in B.1 form on departmental design are invited for the following work, from

contractors Registered in Appropriate class, by Government of Maharashtra, from Class 6

and and above category and will be received in sealed covers, addressed to Secretary SPSM

M.P.K.V., Rahuri in his office up to 22.00 hours on 01.06.2017. Blank Tender and - any

other information will be supplied by the Secretary SPSM M.P.K.V., Rahuri on all working

days except Sundays and Public Holidays declared by Government of Maharashtra, during

working hours from 11.05.2017 to 29.05.2017 on payment of cost of each Blank Tender

form mentioned below and on production of attested copy of valid registration certificate in

the appropriate Class and as per schedule given in the e-tender notice

e-TENDER NOTICE No. 95 / 2017-18 No. SPSM/Works/ 95 /of 2017, dated : 09/05/2017

1. Name of work : Construction of First Floor of English Medium School for SPSM at

Central Campus,MPKV, Rahuri.

2. Cost of blank Tender Form : Rs. 4000.00

3. Estimated cost of work : Rs. 42.07 lakhs

4. Earnest Money Deposit : Rs. 42000.00

5. Initial Security Deposit: Rs. 52500.00

6. and further security : Rs. 52500.00

Deposit. to be deducted

from bills.

7. Last date and time upto : 29.05.2017 up to 17.15Hrs.

which blank tender forms

will be issued.

8. Pre-Tender Conference will be held on ------------------- at --------------- hours at -------

------------------ in the office of the Secretary SPSM, MPKV, Rahuri ------------

------------------------------------------ (Not Applicable)

9. Date and time of receipt :

of Tender. (on line e-tendering ) 01.06.2017 22.00 hrs. 10 Probable date and time :- 03.06.2017 10.00 to 17.15 hrs.

of opening of tender.

11. Validity period :The Offer of the contractor shall remain valid for 120 days from

the date of opening commercial No.2

Page 6: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 6 –

Sign of Contractor No of corrections Secretary SPSM

12. The tender notice shall form a part of the contract agreement.

13. The tenders are invited on the Departmental design only.

14. The blank tender forms will be sold only to the registered contractorss of appropriate

category i.e. Class -5---- and above on production of original or attested copy of

vaild registration or renewal certificate at the time of applying for issue of

blank tender forms. Otherwise Blank tender forms will not be issued to them.

15. The tenderer if firm or company shall in their forwarding letter mention the names of

all the partners of the firm or the company (as the case may be) and the name of the

partner who holds the power of attorney if any, authorising him to conduct

transactions on behalf of the firm or company.

16. Right is reserved to revise or amend the contract documents fully or part thereof prior

to the date notified or amended for the receipt of tender. Such deviations/amendments

if any Shall be communicated in the form of corrigendum or by a letter as may be

considered suitable.

17. Right is reserved to reject any or all tenders without assigning any reason there of.

(2) EARNEST MONEY :

2.1 Earnest money of Rs.42000.00 ( forty two thousand only) along with the

tender should be in the shape of demand draft only issued by Scheduled Nationalized

Bank in favour of the Secretary SPSM, M.P.K.V., Rahuri.

2.2 Tender of those who do not deposit earnest money in one of the acceptable

forms shall be summarily rejected.

2.3 The amount of earnest money will be refunded to the unsuccessful tenderer on

deciding about the acceptance or otherwise of the tender or on expiry of the validity

period whichever is earlier.In case of the successful tenderer it will be refunded on his

paying the initial security deposit and completing the tender documents or will be

transferred towards a part of security deposit to be paid after awarding of the work. If

successful tenderer does not pay the security deposit in the prescribed time limit and

complete the agreement bond, his earnest money deposit will be forfeited to SPSM.,

Rahuri.

(3) TENDERING PROCEDURE :-

3.1 Issue of Bank tender forms :-

Blank tender forms can be purchased from the office of the Secretary SPSM,

M.P.K.V. Rahuri.

3.2 Pre Tender Conference :-

3.2.1 A pre-tender Conference open to all propective Tenderers will be held at --------------

on -----------------at ------------------- hours in the office of the Secretary SPSM,

SPSM., Rahuri where in the prospective tenders will have an opportunity to obtain

clarifications regarding the work and the tender conditions. (Not Applicable)

3.2.2 The prospective tenderers are free to ask for any Additional information or

clarification either in writing or orally and the reply to the same will be given by the

Secretary SPSM, M.P.K.V. in writing and this clarification referred to as Common set

of onditions shall form part of tender documents and which will also be common and

applicable to all tenders.

Page 7: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 7 –

Sign of Contractor No of corrections Secretary SPSM

3.2.3 The tender submitted by tenderer shall be based on the clarification, Additional

facility issued (if Secretary SPSM M.P.K.V., Rahuri any) by the Department and this

tender shall be un conditional. Conditional tenders will be summarily rejected.

3.2.4 All tenders are cautioned that the tenders containing any deviation from the

contractual terms and conditions, specifications or other requirements, and conditional

tenders will be rejected.

2. The Blank- e-Tender form, conditions of contract, specifications and contract Drawings can be had on cash payment of Rs. 4000.00 /- (Rs four thousand only) per set from the office of the Secretary SPSM, MPKV, Rahuri, on any working day from 11.05.2017 to 30.05.2017 during office hours No blank tender form will be supplied by post. Further information regarding the work can be obtained from the above office. 2.1 Joint Venture is not allowed. 3. The e-Tenders will be received online of the Secretary SPSM, MPKV, Rahuri, on or

before 01.06.2017 upto 22.00 hours and will be opened in the office of Secretary SPSM, MPKV, Rahuri, on the same day, if possible, in the presence the such intending tenders or his/their authorized representatives who may be present at the time, Tenders, sent by post, shall be sent in good time by registered post/courier service and must reach by the above time and date. For late delivery or no delivery by postal authority/ courier service the department will not be responsible.

4. EARNEST MONEY AND SECURITY DEPOSIT 4.1 The tenders should be accompanied by Earnest Money Deposit (E.M.D) Which

should be paid in the form of Demand Draft in the name of Secretary, SPSM, MPKV, Rahuri attached or term Deposit, receipt for a period of one year issued by any schedule Bank in favour of the Secretary, SPSM MPKV, Rahuri, separately for each work.

4.2 Earnest Money in any other form of cash or cheque will not be accepted. 4.3 The amount of earnest money will be forfeited, in case a successful contractor does

not pay the amount of initial security deposit within the time specified as stipulated by the Secretary SPSM and complete the contract documents. In all other cases, earnest money will be refundable.

4.4 SECURITY DEPOSIT. The total security deposit to be paid shall be 5 % (Rs. 105000.00) of the amount put to tender.The successful tenderer shall have to pay half of the security deposit in

cash within 10 days of acceptance of tender, and the balance security deposit will be recovered from the running account bills at the percentages as shown in item (d) of the memorandum in printed B-1 form or as may decided by the Secretary SPSM during course of execution of the work looking to the position and circumstances that may prevail, whose orders will be final and binding on the contractor.

The security deposit for the due performance of the contract shall be as detailed in the tender documents else where. Fifty percent of the security deposit will have to be deposited within ten days of the acceptance of the tender and remaining fifty percent will be recovered from the running bills at the rates as specified in the tender form, on the cost of work as per C.S.R. prevailing at the time of acceptance of

Page 8: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 8 –

Sign of Contractor No of corrections Secretary SPSM

tender Amount of total Security deposit to be paid shall be 5% (Five percent) of the cost of work, worked out as per DSR 2016 - 2017.

4.5 Condition for payment of performance security deposit if the offer is received

lower than 10% below.( As per G.R.B.D.G 2016/prak.2/Ima.2 dated 12.02.2016,

the additional security deposit for below rate quoted clause is applicable) In case the tenderer offers the rates lower than 10% below of the estimated cost put to tender, in that case the tenderer will have to pay additional security deposit along with the initial security deposit for performance of work.( for 10% below 1% and further increase of below equal % of below rates quoted). Amount exceeding 10% below offer, in the form of demand draft in the Name of Comptroller for full period of completion of work and it should be extendable up to expiry of valid extension if any, as directed by engineer in charge, failing to which such tender, will be considered as with drawn and their EMD shall be forfeited to SPSM, Rahuri. The additional security deposit shall be refundable after satisfactorily completion of work.

4.6 In the event of the failure of the tenderer to pay cash security deposit within 10 days (unless extended in writing by the Secretary SPSM) from the date of receipt of notice (sent by Registered Post) of acceptance of his tender, the amount of earnest money shall be forfeited to SPSM, Rahuri and the acceptance of his tender, shall be considered withdrawn, Except that in the event of the notice of acceptance of the tender not being issued within 120 days of the date of opening of tender in envelope No. 2 (Financial Bid). The tenderer shall have the option (to be intimated in wiring in good time before the expiry of 120 days period) of withdrawing his tender, in which case the earnest money should be refunded in full. All the tenderers shall remain open for acceptance for 120 days from the date fixed for opening of envelope No.2(financial bid) and thereafter until it is withdrawn by the tenderer by notice in writing as per condition No.2 of the Memorandum.

4.7 Earnest money of the un-successful tenderers will be refunded on their application only after an intimation of rejection of their tender is sent to them or on the expiry of the validity period whichever is earlier.

5. The acceptance of the tender may be intimated to the contractor telegraphically or otherwise, and either by the office completent to accept the tender or any authority in the department including SPSM, Rahuri and such intimation shall be deemed to be an intimation of acceptance of the tender given by the authority competent to accept the tender.

6. In case there is difference between amount written in figures and words, lower offer will be taken as final.

7. No Pages should be removed from, added in or replaced in Tender. 8. Income Tax The income tax @ 2.33% and surcharge there on or at the rates amended from time

to time as intimated by completent income tax authority shall be deducted from bill amount, whether measured bill, advance payment or secured advance.

8.1 VAT Tax

The VAT Tax @ 2.00% shall be deducted from the contractors bill amount who are registered with Maharashtra Value Added Tax 2005 and 5% shall be deducted from contractors bill amount those who are not registered with Maharashtra Value Added Tax 2005 ,Labour cess 1% and Labour insurance 1% and Royalty charges Rs.141.34 per cum are to be recovered in RA bills

Page 9: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 9 –

Sign of Contractor No of corrections Secretary SPSM

9. TENDERING PROCEDURE 9.1 ISSUE OF BLANK TENDE FORMS:

Blank tender forms can be purchased from the office as stipulated in the tender notice on application for blank tender form the contractor shall attach an attested copy of registration in proof of his being a registered contractor of appropriate class, valid on the date purchasing of tender without which the tender form will not be issued. The contractor should note that joint venture is not allowed.

9.2 The tender shall be unconditional. Conditional tender shall be summarily rejected. 9.3 Pre-tender conference i) Pre-tender conference open to all prospective tenderers who have purchased tender

form before the date of pre tender conference will be held at Office of the Secretary SPSM, MPKV, Rahuri on / /200 at 15.00 hr (Phone No. (02426)243320, wherein, prospective tenderers will have an opportunity to obtain clarifications regarding the work and the tender conditions. (Not applicable)

ii) The prospective tenderers are free to ask for any additional information or

clarification iii) either in writing or orally concerning to the work, and the reply to the same will be

given by the Secretary SPSM, MPKV, Rahuri in writing and this clarification refereed to as common set of conditions/

deviations (C.S.D.) shall form a part of tender documents and which will also be

common and applicable to all tenderers. iv) The tender submitted by the tenderer shall be based on the clarification, additional

facility issued (if any) by the Department, this tender shall be unconditional. Conditional tender will be summarily Rejected.

v) All tenderers are cautioned that the tenders containing any deviation form the contractual terms and conditions specifications or other requirements and conditional tender will be rejected as non responsive.

9.3.1 EXAMINATION OF DRAWING AND SITE CONDITIONS.:

The tenderers shall in his own interest carefully examine the drawings, conditions of contract specifications etc. He shall also inspect the site and acquaint himself about the climate, physical and all whether conditions prevailing at site, the nature, magnitude, special features, practicability of the works, all existing and required means of communications and access to site, availability of housing and other facilities, the availability of labour and materials, labour camp site, stores, godown etc. He shall obtain all necessary information as to the risk, contingencies and other circumstances which may affect and influence the tender. No claims on any of the above or any other factors will be entertained by the SPSM, Rahuri, should there be any discrepancy or doubt or obscurity to be observed by him. He shall set forth in writing such discrepancies, doubts, obscurity and submit the same to the Secretary SPSM, MPKV, Rahuri for elucidation as soon as possible.

9.4 MANNER OF SUBMISSION OF TENDER AND IT’S ACCOMPANIMENTS:

Page 10: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 10 –

Sign of Contractor No of corrections Secretary SPSM

The Tenderer shall submit the tender and documents in two separate sealed envelopes as below:

9.4(a) A) ENVELOPE NO. 1 (DOCUMENTS) The first envelope clearly marked as “Envelope No. 1” shall contain the following

documents. a) Demand Draft in the Name of Secretary, SPSM, Rahuri for Earnest Money. b) Certificate in original or an attested copy thereof duly attested by a gazetted Officer

as registered contractor in appropriate (Valid on the date of submission of tender) class as may be applicable.

c) Details of other works tendered for and in hand with the value of work unfinished on the last date of submission of tender, (In the pro forma of statement No. on page No. ) The certificate from the heads of the Office under whom the works are in progress should be enclosed.

d) A list of owned machinery and plants immediately available with tender for use on this work & list of machiney proposed to be utilized on this work, but not immediately available and the manner in which it is proposed, to be procured (in the pro forma of Statement No. II on Page No. )

e) Certified copy of partnership deed and power of attorney in case of a firm, tendering for work (True copy there of duly attested by a Gazetted Officer).

f) Details of works of similar type and magnitude carried out by the contractor. (in the pro forma of Statement No. on Page NO. ). The certificate should be signed by the authority with whom the contractor has executed the work.

g) Details of technical personnel on the roll of the tenderes. (in the pro forma of Statement No. on page No. )

h) valid professional tax reiteration certificated in the form of PTR/PTE under section (1) of section (5) of Maharashtra state tax on profession, trade callings and employment act 1975 Rule 3(2) for Employees including technical personnel from professional tax office of the concerned District in Maharashtra.

i) All Xerox copies submitted in connection with the tender shall be attested by a

gazetted officer only, otherwise their tender will not be considered and envelop No. 2 will not be opened.

j) Valid registration Certification under Maharashtra Value Added Tax act 2005 under rule 8 & 9

k) The envelop No.1 (Technical bid) should reach the office of Secretary SPSMing, SPSM Rahuri on all working days except on Sundays and Holidays before 17.00 Hrs on stipulated date.

l) Even though the bidder meet the above qualifying criteria they are subject to be disqualified if they have made :

ØMisleading or false representations in the forms statements and attachment

submitted in proof of the qualification requirements.And / or ØRecord of poor performance such as abandoning the work, not properly completing

the contract, inordinate delay in completion, litigation history or financial failures etc. 9.4 (b) B) ENVELOPE NO. 2 TENDER : (Financial Bid) The second Envelope clearly marked as “Envelope No. 2” shall contain only the main

tender including the common set of conditions/ stipulations issued by the Department after the pre tender conference. A tender submitted without this would be considered as invalid. The tenderer should not quote his offer on schedule ‘B’of the tender.

Page 11: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 11 –

Sign of Contractor No of corrections Secretary SPSM

The tenderer shall quote his offer duly signed in terms of percentage above or below the estimated rates, at the appropriate place of tender Documents ( on page No.17 ) to be submitted only in Envelope No. 2 ( Financial Bid). He should not quote this offer any where directly or indirectly in Envelope No. 1.

The contractor shall quote for the work as per details given in the main tender and also based on the detailed set of conditions issued/additional stipulations (C.S.D.) duly signed by contractor made by the department as informed to him by a letter from Secretary SPSM after pre-tender conference.

9.4 C ) SUBMISSION OF TENDER i) The two sealed Envelope No. 1 & 2 shall be again put together in one

common cover & sealed. This sealed cover shall be marked on the left hand top corner “Tender for the work of ……………………………………………………………………………………………

ii) The full name and address of the tenderer and the name of the authorized

agent

delivering the sealed cover containing the tender shall be written on the bottom left

hand corner. If submitted by post/ courier service the sealed envelope marked as

above shall enclosed in another cover properly addressed and shall be sent by

registered Post Acknowledgement Due / Courier service. The date and time for

receipt of envelope containing tender shall strictly apply in all cases. The tenderers

should ensure that their tender is received by the Secretary SPSM, MPKV, Rahuri

Telephone No. (02426)243320 before the expiry of the date and time. No delay on

account of any cause will be entertained for the receipt of the tender. Tender offered

or received after this date and time is over, will either not be accepted or if

inadvertently accepted, will not be opened and shall be returned to the tenderer

unopened.

9.4 (D) OPENING OF TENDER

On the date, specified in the tender Notice, following procedure will be adopted for

opening of the tender.

ENVELOPE NO. 1(Documents)

First of all Envelope No. 1 of the Tender will be opened to verify its contents as

per requirements. If the various documents contained in this envelope do no meet

the requirements of the department a note will be recorded accordingly by the

tender opening authority and the said tenderes Envelop No. 2 ( Financial Bid) will

not be considered for further action but the same will be recorded. The decision of

the tender opening authority in this regard will be final and binding on the

contractor.

ii) ENVELOPE NO. 2( Financial Bid)

This envelope shall be opened immediately after opening of envelope No. 1 only if

contents of envelope No. 1 are found to be acceptable to the department. The tendered

rates percentage above/below the estimated rates quoted on Page No.17 shall then be

read out.

Page 12: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 12 –

Sign of Contractor No of corrections Secretary SPSM

9.5 TIME LIMIT

The work is to be completed within time limit as specified in the N.I.T. which shall be

reckoned from the date of written order of commencing the work and shall be

inclusive of monsoon period.

9.6 TENDER RATE

No alteration in the form of tender and the scheduled of tender and no additions in the

scope of special stipulation will be permitted. Rates quoted for the tender shall be

taken as applicable to all leads and lifts.

9.7 TENDER UNITS:

The tender should particularly note the unit mentioned in the schedule “B” on which

the rates are based. NO change in the units shall be allowed. In the case of difference

between the rates written in figure and in words, the correct rate will be the one which

is lower of the two.

9.8 CORRECTION:

No correction shall be made in the tender documents. Any corrections that are to be

made, shall be made by crossing the incorrect portion and writing the correct portion

above with the initials of tenderer.

9.9 TENDER ACCEPTANCE:

Acceptance of the tender will rest with the appropriate Authority of SPSM, Rahuri,

who reserve the right to reject any or all tenders without assigning any reason therefore. The

tenderer whose tenders accepted will have to enter in to a regular B-1 agreement within 10

days of bring notified to do so. In case failure on the part of tenderer to sign the agreement

within the stipulated time, the earnest money paid by him shall stand forfeited to the

Government and the offer or the tenderer shall be considered as withdrawn by him.

9.10 POWER OF ATTORNEY :

If the tenderers are a firm or company, they should in their forwarding letter

mentioning the names of all the partners together with the name of the person who

holds the power of attorney authorizing him to conduct all transactions on behalf of

the body, alongwith the tender.

9.11 The tenderer may in the forwarding letter mention any points he may wish to make

clear but right is reserved to reject the same or the whole of the tenders if the same

become conditional tender there by.

9.12 The contractor or the firms tendering for the work shall inform the Secretary SPSM if

they appoint their authorized Agent on the work.

Page 13: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 13 –

Sign of Contractor No of corrections Secretary SPSM

9.13 No foreign exchange will be released by the Department for the purchase of plants

and Machinery for the work by the contractor.

9.14 Any dues arising out of contract will be recovered form the contractor as arrears of

Land Revenue if not paid amicably. Moreover, recovery of Government dues from the

contractors will be effected form the payment due to the contractor from any other

Government work under execution with them.

9.15 All pages of tender documents, conditions, specifications Corrections slips etc. shall

be initialed by the tenderer. The tender should bear full signature of the tenderer, or

his authorized power of Attorney holder in case of firm.

9.16 The successful tenderer will be required to produce to the satisfaction of the specified

concerned authority a valid concurrent license issued in his favour.

9.17 Validity period:

The offer shall remain open for acceptance for minimum period of 120 days from the

date of opening of Envelope No 2 (Financial Bid) and thereafter until it is withdrawn

by the contractor by notice in writing duly addressed to the authority opening the

tenderer and sent by registered Post Acknowledgement due. (ref. To memorandum on

Page No. 14 to 42, of B-1 form chapter)

10. The contractor will have to sign the original copy of the tenderer paper and the

drawings according to which the work is to be carried out. The contractor shall also

have to give a declaration to the effect that he has fully studies the plans, specification,

local conditions and availability of labour and materials and that he has quoted his

rates with the consideration to all these factors.

11 he right is reserved to revise or amend the contract document prior to the date

notified for the receipt of tender or extended date. Such deviations amendment or

extensions if any shall communicated in the form of corrigendum, by letter and by

notice in news papers as may be considered suitable.

12. The tender submitted by the tenderer remain valid for a period of 120 days from the

date of opening of envelope No. 2(financial bid) tenders also see para 2 of General

Rules etc of contract form.

13. The contractor (s) whose tender is accepted is required to note that no foreign

exchange will be released by the department.

14 Tenders which do not fulfill all or any of the condition or are incomplete in all respect

are liable to summarily rejection.

15. Right to reject any or all tenders without assigning resason therefore is reserved. The

acceptance of the tender lies with the Appropriate Authority of SPSM, Rahuri.

16. The notice inviting tender shall form part of the tender agreement.

17. The successful tenderer will be required to produce to the satisfaction of the

concerned authority a valid and concurrent license issued in his favour under the

Page 14: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 14 –

Sign of Contractor No of corrections Secretary SPSM

provision of the Contract Labour (Regulation and Abolition) Act 1970 before starting

the work. Failure to do so, acceptance to the tender shall be withdrawn and earnest

money deposit will be forfeited.

18. Instruction to Contractor.

1 In case the tender whose offer is found lowest is requested to negotiate and reduce the

offer, does not respond within a period of 7 days the tender accepting without issuing

any reminder reserves the right to reject such tender.

2 In case of the contractor who is informed of acceptance of his tender, does not remit

the initial security deposit within a period of 10 days the tender accepting authority

reserves the right to forfeit the earnest money deposit without issuing any reminder to

take further action to the tender provision.

Page 15: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 15 –

Sign of Contractor No of corrections Secretary SPSM

DECLARATION OF THE CONTRACTORS

—————————————————————————— I /We hereby declare that

I/We have made myself/ourselves thoroughly conversant with the Sub-soil conditions, the

local conditions regarding all materials (such as stone murum sand etc.) and labour

availability of water on which I/We have based my/our rates for this work. The specifications,

conditions bore results and lead of materials on this work have been carefully studied and

understood by me/us before submitting this tender. I/We undertake to use only the best

materials approved by the Secretary SPSM, MPKV, Rahuri or his duly authorized assistant,

before starting the work and to abide by his decision.

Signature of Contractor

Page 16: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 16 –

Sign of Contractor No of corrections Secretary SPSM

4) GENERAL DESCRIPTION AND SCOPE OF

WORK.

The prescribed work is to be under taken at first floor of existing ground floor of English

medium school, work is to executed by the contractor during the school period and it is

necessary to take the necessary precautions for the out of any injuries to the children at

the time school by the contractor. The SPSM would not be responsible if such instant

occurred at that time.

Page 17: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 17 –

Sign of Contractor No of corrections Secretary SPSM

FORM B-1 PERCENTAGE RATE TENDER

AND CONTRACT FOR WORKS

SPSM ,MAHATMA PHULE KRISHI VIDYAPEETH, RAHURI- 413 722,

DIST. A'NAGAR

General Rules and Directions for the Guidance of contractors.

1. All works proposed to be executed by contract shall be notified in a form of invitation

to tender pasted on a board hung up in the office of the Secretary SPSM and signed by

the Secretary SPSM.

This form will state the work to be carried out as well as the date for

submitting and opening tenders, & the time allowed for carrying out the work, also the

amount of earnest money to be deposited with the tender and the amount of security

deposit to be deposited by the successful renderer, and percentage, if any, to be

deducted from bills. It will also state whether a refund of a quarry fees, royalties, dues

and ground rents will be granted. Copies of the specification, designs and drawings,

estimated rates, scheduled rates and any other documents required in connection with

the work shall be signed by the Secretary SPSM for the purpose of identification and

shall also be open for inspection by contractors at the office of the Secretary SPSM

during office hours. Where the works are proposed to be executed according to the

specifications recommended by a contractor and approved by a competent authority

on behalf of the Governor of Maharashtra such

specifications with designs and drawings shall form part of the accepted tender.

2. In the event of the tender being submitted by a firm, it must be signed by each partner

thereof, and in the event of the absence of any partner, it shall be signed on his behalf

by a person holding a power of attorney authorizing him to do so.

2(A) (i)The contractor shall pay alongwith the tender the sum of Rs.42000.00

(Rs. forty two thousand only) as and by way of

earnest money. demand draft only of any scheduled bank Nationalized bank for the

like amount in favour of the Secretary SPSM, M.P.K.V., Rahuri. The said amount of

earnest money shall not Carry interest what so ever

(ii) In the event of his tender being accepted, subject to the provisions of sub

clause below, the said amount of earnest money shall be appropriated towards

the amount of security deposit payable by him under conditions of General

Conditions of Contract.

(iii) If, after submitting the tender, the contractor withdraws his offer, modifies the

same or if after the acceptance of his tender the contractor fails or neglects to

furnish the balance of security deposit without prejudice to any other rights

and powers of the SPSM,M.P.K.V., hereunder, or in law, SPSM, M.P.K.V.

shall be entitled to forfeit the full amount of earnest money deposited by him.

(iv) In the event of his tender not being accepted, the amount of earnest money

deposited bythe contractor, shall unless it is prior thereto forfeited under

provisions of sub- clause (iii) above, be refunded to him on his passing receipt

therefore.

Page 18: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 18 –

Sign of Contractor No of corrections Secretary SPSM

3. Receipts for payments made on account of any work, when executed by a firm,

should also be signed by all the partners except where the contractors are discribed in

their tender as a firm, in which case the receipt shall be signed in the name of the firm

by one of the partners, or by some other person having authority to give effectual

receipt for the firm.

4. Any person who submit a tender shall fill the usual printed form stating at what

percentage above or below the rates specified in the Schedule 'B' (memorandom

showing items of work to be carried out) he is willing to undertake the work. Only

the rate or such percentage of all the estimated rates/ Schedule rates shall be named.

Tenders which propose any alteration in the works specified in the said form of

invitation to tender, or in the time allowed for carrying out the work. or which contain

any other conditions of any sort will be liable to rejection. No printed forms of tender

shall include a tender for more than one work but if contractors who wish to tender

two or more works, they shall submit a separate tender for each. Tender shall have

the name and number of the work to which they refer, written outside the envelope.

5. Secretary SPSM or his duly authorised Assistant shall open tenders in the presence of

contractors who have submitted tenders or their representatives who may be present at

the time, and he will enter the amounts of several tenders in a comparative statement

in a suitable form. In the event of a tender being accepted, the contractor shall for the

purpose of identification, sign copies of the specification and other documents

mentioned in Rule 1. In the event of the tender being rejected, the competent officer

shall authorise the Account Officer concerned to refund the amount of the earnest

money deposited to the contractor making the tender, on his giving a receipt for the

return of the money.

6, The officer competent to dispose of the tenders shall have the right of rejecting all or

any of the tenders.

7. No receipt for any payment alleged to have been made by a contractor in regard to

any matter relating to this tender or the contract shall be valid and binding on SPSM.

unless it is signed by the Secretary SPSM.

8. The memorandum of the work to be tendered for and the Schedule of materials to be

supplied by the SPSM. and their rates shall be filled in and completed by the office of

the Secretary SPSM before the tender form is issued. If a form issued to an intending

tenderer has not been so filled in and completed he shall request the said officer to

have this done before he completes and delivers his tender.

9. All work shall be measured net by standard measure and according to the rules and

customs of the SPSM. and their rates shall be without reference to any local custom.

10, Under no circumstances shall any contractor be entitled to claim enhanced rates for

items in this contract.

Page 19: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 19 –

Sign of Contractor No of corrections Secretary SPSM

11. Every registered contractor should produce along with his tender certificate of

registration as aproved contractor in the appropriate class and renewal of such

registration with date of expiry.

12. All corrections and additions or pasted slips should be initialled.

13. The measurement of work will be taken according to the usual methods in use in the

SPSM. and no proposals to adopt alternative method will be accepted. The

Secretary SPSM's decision as to what is the usual method in use in the SPSM. will

be final.

14. The tendering contractor shall furnish a declaration alongwith the tender showing all

works for which he has already entered into contract and the value of the work that

remains to be executed in each case on the date of submitting the tender.

15. Every tenderer shall furnish alongwith the tender, information regarding the Income

Tax, Circle or Ward of the District in which he is assessed to Income-Tax, the

reference to the number of the assessed and the assessment year, and a valid Income

Tax clearance certificate. 16. In view of the difficult position regarding the availability of foreign exchange no

foreign exchange would be released by the Department for purchase of plant and

machinery required for the execution of the work contracted for

(GCB/PWD/CFM/1058-62517 dated 26.9.1959)

17. The contractor will have to construct shade for storing controlled and valuable

materials issued to him under Schedule 'A' of the agreement at the work site, having

double locking arrangement. The materials will be taken for use in the presence of

the departmental persons. No materials will be allowd to be removed from the site

of works.

18. The contractors shall also give list of machinery in their possession and which they

propose to use on the work.

19. Every unregistered contractor should furnish alongwith tender statement showing

previous experience and staff employed by him.

20. Successful tenderer will have to produce to the satisfaction of the accepting authority

a valid and current licence issued in his favour under the provision of Contract

labour (Regulation and Abolition) Act 1973 before starting work, failing which

acceptance of the tender will be liable for withdrawal and earnest money will be

forfeited. to SPSM.

21. The contractor shall comply with the provision of the Apprentices Act 1962 and the

rules and orders issued there under from time to time. If he fails to do so, his failure

will be a breach of the contract and the Secretary SPSM, may in his descretion cancel

the contract. The contractor shall also be liable for any pecuniary liability arising on

account of any violation by him of the provisions of the Act.

Page 20: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 20 –

Sign of Contractor No of corrections Secretary SPSM

TENDERS FOR WORKS

1. I/We hereby tender for the execution for the Government of Maharashtra

(hereinbefore and hereinafter referred to as “M.P.K.V.”) of the work specified

in the under written memorandum within the time specified in such

memorandum at * ------------------------------

( )

percent Below/above the estimate rate entered in all respects with the

specifications, designs, drawings and instructions, in writing referred to Rule-1

hereof and in Clause-12 of the annexed conditions of the contract and agree

that when material for the work are provided by the M.P.K.V. such materials

and the rate to be paid for them shall be as provided in Schedule ‘A’ hereto.

MEMORANDUM

(a) General Description: Construction of First Floor of English Medium

School for SPSM at Central Campus, MPKV,

Rahuri.

(b) Estimated Cost Rs. 42.07 lakhs

(c) Earnest Money Deposit Rs. 42000/-

(d) Security Deposit

ii) Cash (not less than the Rs. 52500/-

amount of earnest money)

iii) To be deducted from Rs. 52500/-

current bills

Total Security Deposit Rs. 105000/-

(e) Percentage if any to be deducted from bills so as

to make up the Total amount required as security

as security deposit by the time, half the work

at measured by the cost, is done.

(f) Time allowed for the work from the date of written

order to commence. six Calendar months

* In figures as well a in

words.

a) In several Sub works

are included they

should be detailed in a

Separate list.

(b) The amount of

earnest money to be

deposited shall be in

accordance with the

provision of para 204&

205 of the M.P.W.

Manual.

(c) The deposit shall be

in accordance with para

211 of the M.P.W.

Manual.

(d) This percentage

where the security

deposit is taken will

very from 5% to 10%

according to the

requirement of the case

where security deposit

is taken see Note 1 to

Clause-1 of condition

of contact.

(e) Give Schedule

where necessary

showing dates by which

the various items are to

be complete.

Page 21: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 21 –

Sign of Contractor No of corrections Secretary SPSM

Amount to

be

specified in

words and

figures.

Strike out

(a) if on

security

deposit is

to be taken

Signature

of

contractor

before

submission

of tender

Signature

of

contractor

before

submission

of tender

2. I/We agree that the offer shall remain open for acceptance for a minimum period

of 120 days from the date fixed for opening the same and thereafter until it is

withdrawn by me/us by notice in writing duly addressed to the authority opening

the tenders and sent by the registered post A.D. or otherwise delivered at the office

of such authority. Demand draft for a period of one year receipt No. and date ------

--------- in respect to the sum of Rs --------------------- in words Rs.

representing the earnest money is herewith forwarded. The amount of earnest

money shall not bear interest and shall be liable to be forfeited to the SPSM,

should I/We fail to (i) abide by the stipulation to keep the offer open for the period

mentioned above or (ii) sign and complete the contract documents as required by

the Engineer and furnish the authority deposit as specified in item (d) of the

memorandum contained in paragraph I above with in the time limit laid down in

the clause (I) of the annexed General conditions of contract. The amount of earnest

money may be adjusted towards the security deposite or refunded to me/us writing,

unless the same or any part thereof has been forfeited as aforesaid.

3. I/We have secured exemption of earnest money after executing the necessary

bond in favor of Government a true copy of which is enclosed herewith, should

any occasion for forfeiture of earnest money for this work arise due to failure on

my/our part to (i) abide by the stipulations to keep the offer open for the period

mentioned above or (ii) sign and complete the contract documents and furnish the

security deposit as specified in item (d) of the Memorandum contained in

paragraph I above within the time limit laid down in clause (I) of the annexed

General condition of contract the amount payable by me/us may at the option of

the Engineer be recovered out of the amount deposited in the lump sum for

securing exemption in so far as the same may extend in terms of the options said

bond and in the event of the deficiency out of any other contract or payable to

me/us by the Government under any other contract or transaction of any nature

whatsoever or other wise.

4. Should this tender be accepted I/We hereby agree to abide by and fulfill all the

terms and provisions of the conditions of conditions of contract annexed here to so

far as applicable and in default there of to forfeit and pay to Government the sum

of money mentioned in the said conditions.

Receipt No. ---------------- date-------------- from Account Officer at ---------------in

respect of the sum of Rs. --------------------------------------- is herewith forwarded

representing the earnest money (a) the full value of which is to be absolutely

forfeited to SPSM, should I/We not deposit the full amount of security deposit

specified in the above memorandum, in accordance with clause 1 (A) of the said

conditions of contract, otherwise the said sum of Rs.-------------------- shall be

refunded.

Contractor Address

Dated the ---------------------- day of -------------200-----

(Witness) Address

The above tender is hereby accepted by me for and on

behalf of the Governor of Maharashtra / SPSM

Dated -------------------- day of -------------------- 200 ------SPSM M.P.K.V.,

Rahuri

Signature of

Officer by

whom

accepted.

Page 22: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 22 –

Sign of Contractor No of corrections Secretary SPSM

CONDITIONS OF CONTRACT

Clause 1 - The person/persons whose tender may be accepted

(hereinafter called the contractor, which expression shall unless excluded by

or repugnant to the context include his heirs, Executors, administrators, and

assigns) shall (A) (within on day for a contract of Rs.1000/- or less or two

days for contract of more than Rs.1000/- but less than Rs.2000/- and so on

upto a limit of ten days, which may be extended by theVice-Chancellor,

Mahatma Phule Krishi Vidyapeeth concerned up to 15 days, if the Vice

Chancellor thinks it fit to do so far a contract over Rs.10,000/- of the receipt

by him of the notification of the acceptance of his tender) deposit with the

Engineer in Charge (if deposited) for more than 12 months) a sum sufficient

which will make up the full security deposit specified in the tender or (B)

(permit M.P.K.V. at the time of making any payment to him for work done

under the contract to deduct such sum as will amount to * percent of all

moneys so payable such deductions to held by Mahatma Phule Krishi

Vidyapeeth by way of security deposit.) Provided always that in the event

of the contractor depositing a lumpsum by way of security deposit as

contemplated at (A) above then and in such case, if the sum so deposited

shall not amount to percent of the total estimated cost of the work, it shall be

lawful for Mahatma Phule Krishi Vidyapeeth at the time of making of any

payment to the contractor for the work under the contract to makeup the full

amount of four percent by deducting a sufficient sum for every such

payment at last aforsaid until the full amount of the security deposit is

madeup. All compensatation or other sums of money payble by the

contractor Mahatma Phule Krishi Vidyapeeth under the terms of his contract

may be deducted from, or paid by the sale of a sufficient part of his security

deposit or from the interst arising there from, or from any sums which may

by due or may become due by Mahatma Phule Krishi Vidyapeeth to the

contractoe under any other contract or tranction of any nature whatsoever in

the event of his security deposit being reduced by reason of any sush

deductions or sale as aforsaid, the contractor shall, within 10 days thereafter,

make good in case or M.P.K.V. Securities endorsed as aforsaid any sum or

sums which may have been deducted from or raised by sale of his security

deposit or any part thereof. The security deposit refered to when paid in

cash may, at the cost of teh depositor, be converted in to interest bearing

securities provided that the depositor has expressly desired this in writting.

The security deposit will not be accepted in form of Insurance company

bonds.

If the amount of the security deposit to be paid in lumpsum within the

period specified at (A) above is not paid the tender/contract already accepted

shall be considered cancelled and legal steps taken against the contractor for

recovery of the amount. The amount of security deposit lodged the

contractor shall be refunded after expiry of 12 months after payment of final

bill or the expiry of defect liability period. Which ever is latter.

The defect libility period for the work is Twelve months. The defect

Security

Deposit

* This will be

the same

percentage as

that in the

tender at(e).

Page 23: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 23 –

Sign of Contractor No of corrections Secretary SPSM

libility period starts from the date of completion of the work.

Compensation for

delay.

Action when

whole of security

deposit is

forfeited.

Clause 2 - The time allowed for carrying out the work as entered tender

shall be strictly observed by the contractor and shall be reckoned from

the date on which the order to commence work is given to the contractor.

The work shall through the stipulated period of the contract be

proceeded with, with all due diligence (time being deemed to be the

essence of the contract on the part of the contractor) and the contractor

shall pay as compensation an amount equal to one percent or such

smaller amount as the Secretary SPSM (whose decision in writing shall

be final) may decide, of the amount of the estimated cost of the whole

work as shwon by the tender for every day that the work remains

uncommenced or unfinished, after the proper dates. And further to

ensure good progress during execution of the work, the contractor shall

bed bound, in all case in which the time allowed for any work exceeds

one month to complete.

1/6th of the work in 1/4th of the time

1/2 of the work in 1/2 of the time

3/4th of the work in 3/4th of the time

Note - The quantity of the work to be done within a particular time to be

specified above shall be fixed and inserted in the blank space kept for the

purpose by the Office competent to accept the contracts after taking into

consideration the circumstances of each case and abide by the

programme of the detailed progress laid down by the Secretary SPSM.

The following proportion will usually be found suitable :-

In 1/4, 1/2, 3/4 of the time

Reasonable progress of the earth work, 1/6, 1/2, 3/4 of the total value of

the work to be done.

Do Do of masonry work 1/10, 4/10, 8/10 Do

Do

In the event of the contractor failing to comply with this conditions he

shall be liable to pay as compensation an amount equal to one percent or

such smaller amount as the Secretary SPSM (whose decision in writing

shall be final) may decide of the said estimated cost of the whole work

for every day that the due quantity of the work remains incomplete

provided always that the total amount of compensation to be paid under

the provisions of the clause shall not exceed 10 percent of the estimated

cost of the work as shown in the tender Secretary SPSM, should be the

final authority in

this respect, irrespective of the fact that the tender is accepted by the

Secretary SPSM or M.P.K.V., Rahuri.

Clause 3 - In any case in which under any clause of this contract the

contractor shall have rendered himself liable to pay compensation

Page 24: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 24 –

Sign of Contractor No of corrections Secretary SPSM

cmounting to the whole of his security deposit whether paid in one sum

or deducted by instalments or in the case of abandoment of the work

owing to serious illness or death of the contractor or any other cause the

Engineer, on behalf of the M.P.K.V. shall have power to adopt any of the

following

courses, as he may deem best suited to the interest of M.P.K.V. :-

(a) To rescind the contract (for which rescission notice in writing to the

contractor under the hand of Secretary SPSM shall be conclusive

evidence) and in the case the security deposit of the contractor shall stand

forfeited and be absolutely at the disposal of SPSM., Rahuri

(b) To carry out the work or any part of the work departmentally debiting

the contractor with the cost of the work, expenditure incurred on tools and

plant, and charges on additional supervisory staff including the cost of work

charged establishment employed for getting the un-executed part of the

work completed and creding him with the value of the work done....

departmentally in all respects in the same manner and at the same rates as if

it had been carried out by the contractor under the terms of his contract. The

certificate of the Secretary SPSM as to the costs and other allied expenses so

incurred and as to the value of the work so done departmentally shall be

final and conculsive against the contractor.

(c) To order that the work of the contractor be measured up and to take

such part thereof as shall be unexecuted out of his hands, and to give it to

another contractor to complete, in which case all expenses incurred on

advertisement for fixing a new contracting agency, aditional supervisory

staff including the cost of the work charged etablishment and the cost of the

work executed by the new contract agency will be debited to the contractor

and the value of the work done or executed through the new contractor shall

be credited to the contractor in all respects and in the same manner and at

the same rates as if it had been carried out by the contractor under the terms

of his contract. The certificate of the Executive Engineer as to all the cost of

the work and other expenses incurred as aforeaid for or in getting the

unexecuted work done by the new contractor and the value of the work so

done shall be final and conclusive aginst the contractor.

In case the contract shall be rescinded under clause (a) above the

contractor shall not be entitiled to recover or be paid, any sum for any work

therefore actually performed by him under this contract unless and until the

Secretary SPSM shall have certified in writing the performance of such

work and the amount payable to him in respect thereof and he shall only be

entitled to be paid the amount so certified. In the event of either or courses

referred to in clause (b) or (c) being adopted and the cost of the work

executed departmentaly or through a new contractor and other allied

expenses exceeding the value of such work credited to the contractors the

amount of excess shall be deducted from any money due to the contractor,

by M.P.K.V. under the contract or otherwise howsoever or from is security

deposit or the sale proceeds thereof provided, however that contractor shall

have no claim against M.P.K.V. even if the certified value of the work done

departmentally or through a new contractor exceeds the certified cost of

such work and allied expenses, provided always that whichever of the three

Action when the

progress of any

particular portion

Page 25: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 25 –

Sign of Contractor No of corrections Secretary SPSM

courses mentioned in caluse (a), (b) or (c) is adopted by the SPSM.

Engineer, the Contractor shall have no claim to compensation for any loss

sustained by him by reason of his having purchased or procured any

materials, or entered into any engagements, or made any advance on account

of or with a view to the execution of the work or the performance of the

contract.

Clause 4 - If the progress of any particular portion of the work is

unsatisfactory the Secretary SPSM shall notwithstanding that the general

progress of the work is in accordance with the conditions mentioned in

clause 2, be entitled to take action under clause 3 (b) after giving the

contractor 10 days notice in writing. The contractor will have no claim for

compensation, for any loss sustained by him owing to such action.

Clause 5 - In case in which any of the powers conferred upon the

Secretary SPSM by Clause 3 and 4 hereof shall have become exercisable

and the same shall not have been exercised, the non exercise thereof shall

not constitute a waiving of any of the conditions hereof and such powers

shall notwithstanding be exercisable in the event of any future case of

default by the contractor for which under any clause hereof he is declared

liable to pay compensation amounting to the whole of his security deposit

and the liability of the contractor for past and future compensation shall

remain unaffected.

of the work is

unsatisfactory

Contractor

remains liable to

pay compensation

if action not taken

under Clause 3

&4\

Power to take

possession of or

require removal

of or sell

contractor's

plant.

Extension of

time Final certificate

In the event of the Secretary SPSM taking action under sub-claluse (a)

or (c) or clause 3, he may, if he so desires, take possession of all or any tools

any plant, materials and stores in or upon the work of the site thereof or

belonging to the contractor, or procured by him and intended to be used for the

execution of the work or any part thereof paying or allowing for the same, in

account at the contract rates, or in the case of contract rates not being

applicable at current market rates to be certifiedd by the Secretary SPSM

whose certificate thereof shall be final. In the alternative the Secretary SPSM

may, after giving notice in writing to the contractor or his clerk of the work,

foreman or other authorised agent require him to remove such tools and plant,

material, or stores from the premises within a time to be specified in such

notice, and in the event of the contractor failing to comply with any such

requisition, the Secretary SPSM may remove them at the contractor's expenses

or sale them by auction or private sale on account of the contractor and at his

risk in all respects and the certificate and the certificate of the Secretary SPSM

as to the expenses of any such removal and the amount of the proceeds and

expense of any such sale shall be final and conclusive against the contractor.

Clause 6 - If the contractor shall desire an extension of the time for

completion of work on the ground of his having been unavoidably hindered in

its execution or on any other ground he shall apply in writing to the Secretary

SPSM before the expiration of the period stipulated in the tender or before the

expiration of 30 days from the date on which he was hindered as aforesaid or

on which the cause for asking for extension occured, whichever is earlier and

the Secretary SPSM, or in the opinion of SPSM Engineer, as the case may be

if in his opinion, there were reasonable grounds for granting an extension,

grant such extension as he thinks necessary or proper. The decision of the

Secretary SPSM in this matter shall be final.

Page 26: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 26 –

Sign of Contractor No of corrections Secretary SPSM

Payment on

intermediate

certificate to be

regarded as

advances.

Clause 7 - On the completion of the work the contractor shall be

furnished with a certificate by the Secretary SPSM (hereinafter called the

Engineer-in-charge) of such completion, but no such certificate shall be given

nor shall the work be considered to be completed untill the contractor shall

have removed from the premises on which the work shall have been executed,

all scaffolding, surplus materials and rubbish, and shall have cleaned off, the

dirt from all wood work, doors, windows, wall, floor or other parts of any

building in or upon which the work has been executed or of which he may

have had possession for the purpose of executing the work, nor untill the work

shall have been measured by the Engineer-in-charge or where the

measurements have been taken by his subordinate until they have received

aproval of the Engineer-in-charge, the said measurements being binding and

conclusive against contractor. If the contractor shall fail to comply with the

requirements of this clause as to the removal of scaffolding surplus materials

and rubbish and the cleaning of dirt on or before the date fixed for the

completion of the work the Engineer-in-charge may at the expense of the

contractor, remove such scaffolding, surplus materials and rubbish, and

dispose of the same as he thinks fit and clean off such dirt as aforesaid and the

contractor shall forthwith pay the amount of all expense so incurred, but shall

have no claim in respect of any such scaffolding or surplus materials as

aforesaid except for any sum actually realised by the sale thereof.

Clause 8 - No payment shall be made for any work, estimated to cost less

than rupees one thousand till after the whole of work shall have been

completed and a certificate of completion given. But in the case of works

estimated to cost more than rupees one thousand the contractor shall on

submitting a monthly bill therefor be entitled to receive payment proportionate

to the part of the work then approved and passed by the Engineer-in-charge,

whose certificate of such approval and passing of the sum so payable shall be

final and conclusive against the contractor.

All such intermediate payments shall be regarded as payments by

way of advance against the final payments for work actually done

and completed and shall not preclude the unskilful work to be

removed or taken away and reconstructed or re-errected nor shall any

such payment be considered as an admission of the due performance

of the contract or any part thereof in any respect or the accruing of

any claim nor shall it conclude dctermine, or affect in any other way

the powers of the Engineer in charge as to the final settlement and

adjustment of the accounts or otherwise, in any other way very or

affect the contract. The final bill shall be submited by the contractor

within one month of the date fixed for the completion of the work,

otherwise the Engineer-in-charge's certificate of the measurements

and of the total amount payable for the work shall be final and

binding on the parties.

Clause 9 - The rates for several items of work estimated to cost

more than Rs.1000/- agreed to within, shall be valid only when the

item converted is accepted as having been completed fully in

accordance with the sanctioned specifications. In case where the

items of work are not accepted as so completed by the Engineer-in-

charge he may make payment on account of such items at such

Payment at reduced

rates on account of

items of work not

accepted as

completed to be at the

discretion of the

Engineer-in-charge.

Page 27: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 27 –

Sign of Contractor No of corrections Secretary SPSM

reduced rates as he may consider reasonable in the preparation of

final or on account bills.

Caluse 10- A bill shall be submitted by the contractor in each

month on or before the date fixed by the Engineer-in-charge for all

work exectued in the previous month and the Engineer-in-charge

shall take or cause to be taken the requisite measurement for the

purpose of having, the same verified and the claim, so far as it is

admissible shall be adjusted, if possible, within ten days from the

presentation of the bill. If the contractor does not submit the bill

within the time fixed as aforesaid, the Engineer-in-charge may depute

a subordinate to measure up the said work in the presence of the

contractor or his duly authorised agent whose contersignature to the

measurement list shall be sufficient warant, and the Engineer-in-

charge may prepare a bill from such list which shall be binding on

the contractor in all respects.

Clause 11- The contractort shall submit all bills on the printed

forms to be had on application at the office of the Engineer-in-

charge. The charges to be made in the bills shall always be entered at

the rates specified in the tender or in the case of any extra work

ordered in pursuance of these conditions, and not mentioned or

provided for in the tender at the rates hereinafter provided for such

work.

Clause 12- If the specification or estimate of the work provides

for the use of any special description of material to be supplied from

the store to the SPSM. store or if it is required that the contractor

shall use certian stores to be provided by the Engineer-in-charge

(such material and stores and their prices to be charged therefor as

hereinafter mentioned being so far as practicable for the convenience

of the contracor but not so as in any was to control the meaning or

effect of this contract specified in the schedule or memorandum here

to annexed) the contractor shall be supplied with such meterial and

stores as may be required from time to time to be used by him for the

purposes of the contract only, and value of the full quantity of the

materials and stores so supplied shall be set off or deduced from any

sums then due, or thereafter to become due to the contractor under

the contract or otherwise, or from the security deposit or the proceeds

of sele thereof if the security deposit is held in University securities,

the same or a sufficient portion thereof shall in that case be sold for

the purpose.

Bill to be submitted

Monthly

Bills to be on printed

forms.

Stores supplied by

Government.

All materials supplied to the contractor shall remain the absolute property

of University and shall on no account be removed from the site of the work,

and shall at all times be open for inspection by the Engineer-in-charge. Any

such materials unused and in perfectly good condition at the time of

completion or determination of the contract shall be returned to the SPSM.

store if the Engineer-in-charge so requires by a notice in writing given

under his hand but the contractor shall not be entitle to return any such

material except with consent of the Engineer-in-charge and he shall

Page 28: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 28 –

Sign of Contractor No of corrections Secretary SPSM

Works to be

executed in

accordance

with

specification,

drawings, order

etc.

Alterations in

specifications

and designs not

to invalidate

contract.

Rates for, items

not entered in

estimate or

Schedule of

Rates of the

District.

have no claim for compensation on account of any such material supplied to

him as aforesaid but remaining unused by him or for any wastage in or

damage to any such materials.

Clause 12(A)- All stores of controlled materials such as cement, steel etc.

supplied to the contractor by government should be kept by the contractor

under lock and key and will be accessible for inspection by the Secretary

SPSM or his agent at all the times.

Clause 13- The contractor shall execute the whole and every part of the

work in the most substantial and workmanlike manner, and both as regards

materials and every other respect in strict accordance with specifications.

The contractor shall also conform exactly, fully and faithfully to the

designs, drawings and instructions in writing relating to which, the

contractor shall be entitled to have access for the purpose of inspection at

such office, or on the site of the work during office hours. The contractor

will be entitled to receive three sets of contract drawing and working

drawings as well as one certified copy of the accepted tender along with the

work order free of cost. Further copies of the contract drawings and

working drawings if required by him shall be supplied at the rate of Rs. 100

per set of contract drawings and Rs.50 per working drawing except where

otherwise specified.

Clause 14- The Engineer-in-charge shall have power to make any

alteration in or additions to the original specifications, drawings, designs

and instructions that may appear to him to be necesary or advisable during

the progress of the work and the contractor shall be bound to carry out the

work in accordance with any instructions in this connection which may be

given to him in writing signed by the Engineer-in-charge and such

alteration shall not invalidate the contract, and any additional work which

the contractor may be directed to do in the manner above specified as part

of the work shall be carried out by the contractor on the same conditions in

all respects on which he agreed to do the main work. And if the additional

and altered work includes any class of work for which no rate is specified in

this contract, then such class of work shall be carried out at the rates entered

in the Schedule of Rates of the Division or at the rates mutually agreed

upon between the Engineer-in-charge and the contractor, whichever are

lower.

If the aditional or altered work for which no rate is entered in the

schedule of Rates of the Division is ordered to be carried out before the

rates are agreed upon then the contractor shall within seven days of the date

of receipt by him of the order to carry out the work, inform the Engineer-in-

charge of the rate which it is his intension to charge for such class of work,

and if the Engineer-in-charge does not agree to this rate he shall by notice in

writing be at liberty to cancle his order to carry out such class of work and

arrange to carry out in such manner as he may consider adviable provied

always that if the contractor shall commence work or incur any expenditure

in regard thereto before the rates shall have been determind as lastly

hereinbefore mentioned, then in such case he shall only be entitiled to be

paid in respect of the work carried out or expenditure incurred by him prior

Page 29: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 29 –

Sign of Contractor No of corrections Secretary SPSM

to the dat of the determination of the rate as aforesaid according to such rate

or rates as shall be fixed by the Engineer-in-charge. In the event of a

dispute the decision of the University Engineer of the Circle will be final.

Where however, the work is to be executed according to the

designs, drawings and specifications recommended by the contractor

and accepted by the competent authority the alterations above referred to

shall be within the scope of such designs, drawings, and specifications

appended to the tender. The time limit for the completion of the work

shall be extended in the proportion that incurease in its cost occassioned

by alterations or additions bear to the cost of the original contract work,

and the certificate of the Engineer-in-charge as to such proportion shall

be conclusive.

Clause 15- (1) If at any time after the execution of the contract

documents the Engineer shall for any reason what-so-ever (other than

default on the part of the contractor for which the SPSM. is entitled to

rescind and contract) desires the the whole or any part of the work

specified in the tender should be suspended for any period or that the

whole or part of the work should not be carried out at all, he shall give

to the contractor a notice in writing of such desire and upon the receipt

of such notice the contractor shall forthwith suspend or stop the work

wholly or in part as required, after having due regard to the appropriate

stage at which the work should be stopped or suspended so as not to

case any damage or injury to the work already done or endanger the

safety thereof provided that the decision of the Engineer as to the stage

at which the work or any part of it could be or could have been safety

stopped or suspended shall be final and conclusive against the

contractor. The contractor shall have no claim to any payment or

compensation whatsoever by reason of or in persuance of any notice as

aforesaid, on account of any suspension stoppage or curtainlment except

to the extent specified hereinafter.

(2) Where the total suspension of work ordered as aforesaid

continued for a continous period exceeidng 90 days the contractor shall

be at liberty to withdraw from the contractual obligations under the

contract so far as it pertains to the unexectued part of the work by giving

a 10 days prior notice in writing to the engineer, within 30 days of the

expiry of the said period of 90 days, of such intention and requiring the

Engineer to record the final measurement of the work already done and

to pay final bill. Upon giving such notice the contractor shall be

deemed to have been discharged from his obligation to complete the

remaining unexecuted work under his contract. On receipt of such

notice the Engineer shall proceed to complete the measurements and

make such payment as may be finally due to the contractor within a

period of 90 days from the receipt of such notice in respect of the work

already done by the contractor. Such payment shall not in any manner

prejudice the right of the contractor to any further compensation under

the remaining provisions of this clause.

(3) Where the Engineer required the contractor to suspend the

Extension of time

in consequence of

additions or

alterations

No claim to any

payment; or

compensation for

alteration in/or

restriction of work.

Page 30: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 30 –

Sign of Contractor No of corrections Secretary SPSM

work for a period in excess of 30 days at any time or 60 days in the

aggregate, the contractor shall be entitled to apply to the Engineer

within 30 days of the resumption of work after such suspesion for

payment of compensation to the extent of pecuniary loss suffered by

him in respect of working machinery remained idle on the site or on the

account of his having and to pay the salary or wages of labour engaged

by him during the said period of suspension provided always that the

contractor shall not be entitled to any claim in respect of any such

working Machinery, salary or wages for the first 30 days whether

consecutives or in the agreegate of such suspension or in respect of any

suspension whatsoever occasioned by unsatisfactory work or any other

default on his part. The decision of the Engineer in this regard shall be

final and conclusive against the contractor.

No claim to

compensation

on account of

loss due to

delay in supply

of materials

SPSM

4) In the event of -

(i) Any total stoppage of work on notice from Engineer under

sub clause (1) in that behalf.

(ii) Withdrawal of the contractor from the contractural obligations to

complete the remaining unexecutred work under sub-clause (2) on account

of continued suspension of work for a period exceeding 90 days.

or

(iii) Curtailment in the quantity of item or items originally

tendered on account of any alteration, omission or substitution in the

specifications, drawings, designs or instructions under clause (14)-1

where such curtailment exceeds 25% in quantity and the value of the

quantity curtailed beyond 25% at the rates for the item specified in the

tender is more than Rs.5000/-.

It shall be open to the contractor, within 90 days from the service of

(i) the notice of stoppage of work or (ii) the notice of withdrawal from the

contractual obligations under the contract on account of the continued

suspension of work or (iii) notice under clause 14(1) resulting in such

curtainlment to produce to the Engineer satisfactory documentary evidence

that he has purchased or agreed to purchase materials for use in the

countracted work, being receipt by him of the notice of stoppage,

suspension or cutailment and require the Government to take over on

payment such material at the rates determined by the Engineer, provided,

however, such rates shall in no case exceed the rate at which the same was

acquired by the contractor. The SPSM shall thereafter take over the

material so offered, provided the quantities offered, are not in excess of the

requirements of the unexecuted work as specified in the accepted tender and

are of quality and specifications approved by the Engineer.

Clause15-A- The Contractor shall not be entitled to claim any

compensation from Government for the loss suffered by him on account of

delay by SPSM. in the supply of material entered in Schedule A where such

delay is caused by –

Difficulties relating to the supply of railway wagons.

Force majcure.

Act of God.

Page 31: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 31 –

Sign of Contractor No of corrections Secretary SPSM

Time limit for

unforseen

claims.

Action and

compensation

payable in case

of bad work

Act of enemies of the State or any other reasonable cause beyond

the condrol of SPSM.

In the case of such delay in the supply of materials, SPSM. shall grant such

extension of time for the completion of the work as shall appear to the

Secretary SPSM to be reasonable in accorance with the circumstances of

the case. The decision of the Secretary SPSM as to the extension of time

shall be accepted as final by the contractor.

Clause 16- Under no circumstance whatever shall the contractor be

entitled to any compensation from SPSM. on any account unless the

contractor shall have submitted a claim in writing to the Engineer-in-charge

within one month of the case of such claim occuring.

Caluse 17- If any time before the security deposit or any part thereof is

refunded to the contractor is shall appear to the Engineer-in-charge or his

subordinate in charge of the work, that any work has been executed with

unsound, imperfect or unskillful workmanship work has been executed with

unsound, imperfect or that any materials or articles provided by him for the

execution of the work are unsound, or of a quality inferior to that contracted

for, or are otherwise not in accordance with the contract it shall be lawful

for the Engineer-in-charge to intimate this fact in writing to the contractor

and then notwithstanding the fact that the work, materials or articles

complained of may have been inadvertently passed, certified and paid for

the contractor shall be bound forthwith to rectify, or remove and reconstruct

the work so specified in whole or in part as the case may require or

if so required, shall remove the materials or articles so specified and

provide other proper and suitable materials or articles at his own

charge and cost and in the event of his failing to do so within a

period to be specified by the Engineer-in-charge in written

intimation aforesaid, the contractor shall be liable to pay

compensation at the rate of one percent on the amount of the

estimate for every day not exceeding 10 days during which the

failure so continues and in the case of any such failure the Engineer-

in-charge may rectify or remove and re-execute the work or remove

and replace the materials or articles complained of as the case may

be at the risk and expense in all respects of the contractor. Should

the Engineer-in-charge consider that any such inferior work or

materials as described above may be accepted or made use of it shall

be within his discretion to accept the same at such reduced rates as

he may fix therefor.

Clause 18- All work under or in course of execution or excuted

in persunance of the contract shall at all times be open to the

imspection and supervision of the Engineer-in-charge and his

subordinates and the contractor shall at all times during the usual

working hourse, and at all other times at which reasonable notice of

the intendion of the Engineer-in-charge and his subordinate to visit

the work shall have been given to the contractor eirhter himself be

present to receive orders and instructions or have a responsible agent

duly credited in writing present for that purpose. Orders given to the

Work tobe open to

inspection

Contractor or

responsible agent to

be present.

Page 32: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 32 –

Sign of Contractor No of corrections Secretary SPSM

contractor's duly authorised agent shall be considered to have the

same force and effect as if they had been given to the contractor

himself.

Clause 19- The contractor shall give not less than five days

notice in writing to the Engineer-in-charge or his subordinate in

charge of the work before covering up or otherwise placing beyond

the reach of measurement any work in order that the same may be

measured and correct dimensions thereof taken before the same is so

covered up or placed beyond the reach of measurements and shall

not cover up or place beyond the reach of measurment any work

without the consent in writing of the Engineer-in-charge or his

subordinate in charge of the work and if any work shall be covered

up or placed beyond the reach of measurements shall be uncovered

at the contractor's expenses and in default thereof no payment or

allowance shall be made for such work or for the materials with

which the same was executed.

Clause 20- If during the period of -Twelve months from the date

of completion as certified by the Engineer-in-charge persuant to

Clause-7 of the contract or Twelve months after commissioning the

work whichever is earlier in the opinion of the Secretary SPSM; the

said work is defective in any manner whatsover, the contractor shall

forthwith on receipt of notice in that behalf from the Secretary

SPSM, duly commence execution and completely carry out at his

cost in every respect all the work that may be necessary for

rectifying and setting right the defects specified therein including

dismentalling and reconstruction of unsafe portions strictly in

accordance with and in the manner prescribed and under the

supervision of the Secretary SPSM. In the event of the contractor

failling or neglecting to commence execution of the said rectification

work within the period prescribed therefor in the said notice and / or

to complete the same as aforesaid as required by the said notice, the

Secretary SPSM get the same executed and carried out

departmentally or by any other agency at the risk on account and at

the cost of the contractor. The shall forthwith on demand pay to the

Government the amount of such cost, charges and contractor

expenses sustained or incurred by the SPSM.,Rahuri of which the

certificate of the

Notice tobe given

before work is

covered up.

Contractor liable for

damage done and for

imperfections.

P.W.D.Resolution

No.CAT-

1087/CR/94/Bldg.-2

dt. 14.6.89.

Contractor to supply

plant ladder

scaffolding etc.

And is liable for

damages arising

from non

provisions of

light, fencing

etc.

Secretary SPSM shall be final and binding on the contractor. Such cost,

charges and expenses shall be deemed to be arrears of land revenue and in

the event of the contractor failing or neglecting to pay the same on demand

as aforesaid without prejudice to any other rights and remedies of the

SPSM.,Rahuri the same may be recovered from the contractor as arrears of

land revenue. The SPSM. shall also be entitled to deduct the same from

any amount which may then be payable or which may thereafter become

payable by the SPSM. to the contractor either in respect of the said work or

any other work whatsoever or from the amount of security deposits retained

by SPSM. The defect liabilities period in particular for water proofing

Page 33: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 33 –

Sign of Contractor No of corrections Secretary SPSM

treatment (Building works) shall be 7 years.

Caluse 21- The contractor shall supply at his own cost all material

(except such special materials if any as may in accordance with the

contract, be supplied from the SPSM. Stores) plant tools, appliances,

implements, ladders, cordage, tackles, scaffolding and temporary works

requisite or proper for the proper execution of the work, whether in the

original, altered or substituted form and whether included in the

specification or other documents forming part of the contract or referred to

in these conditions or not and which may be cecessary for the purpose of

satisfying or complying with the

requirements of the Engineer-in-charge as to any matter as to which under

these conditions he is entitled to be satisfied, or which he is entitled to

require together with the carriage therefor to and from the work. The

contractor shall also supply without charge the requisite number of persons

with the means and materials necessary for the purpose of setting out works

and counting, weighing and assisting in the measusrement or examination

at any time and from time to time of the work or the materials failing which

the same may be provided by the Engineer-in-charge at the expense of the

contractor and the expenses may be deducted from any money due to the

contractor under the contract or from his security deposit or the proceeds of

sale thereof, or of a sufficient portion thereof. The contractor shall provide

all necessary fencing and lights required to protect the public from accident

and shall also be bound to bear the expenses of fdefence of every suit,

action or other legal proceeding, that may be brought by any person for

injury sustained owing to neglect of the above precautions, and to pay any

damages and cost which may be awarded in any such suit action or

proceeding to any such person or which may with consent of the contractor

be paid for compromising any claim by any such person.

List of machinery in contractor's possession and which they propose

to use on the works should be submitted along with the tender.

Clause 21-A- The contractor shall provide suitable scaffolds and working

platforms gangaways and stairways and shall comply with the following

regulations in connections herewith.

a) Suitable scaffolds shall be provided for workmen for all works that

can not be safely done from a ladder or by other means.

(b) A Scaffold shall not be constructed, taken down or substantially

altered except.

i)under the suprevision of a competent and responsible person and

ii)as far as possible by competent workers possessing adcquate

experience in this kind of work.

(c) All scaffolds and appliances connected there with and ladders shall -

i) be of sound material.

ii) be of adequate strength having regard to the loads and

strains to which they will be subjected and

iii) be maintained in proper condition.

(d) Scafolds shall not be over loaded and so far as practicable the load shall be evenly

distributed.

Page 34: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 34 –

Sign of Contractor No of corrections Secretary SPSM

(e) Scattolds shall be so constructed that no part therof can be displaced in consequent of

normal use.

(f) Before installing lifting gear on scaffolds special precautions shall be taken to ensure

the strength and stability of the scaffolds.

(g) Scaffold shall be periodically inspected by the competent person.

(h) Before allowing a scaffold to be used by his workmen the contractor shall, whether the

scaffold has been erected by his workmen or not, take steps to ensure that it complies fully with

the regulations here-in-specified.

(i) Working platform, goangways stairways shall -

i) be so constructed that no part there of can sag unduly or

unequally.

ii) be so constructed and maintained having regard to the prevailing

conditions as to reduce as far as practicable risks of persons

tripping or slipping, and

be kept free from any unnecessary obstruction.

j) In the case of working platform, gangways, working places and stairways at the height

exceeding 2 metres.

i) every working platform and every gangway shall be closely

boarded unless other adequage measures are taken to ensure safty.

ii) every working platform and gangway shall have adequate width

and

iii) every working platform gangway, working place and stair way

shall be suitably fenced.

k) Every opening in the floor of a building or in a working platform shall except for the

time and to the extent required to allow the excess of persons or the transport or shifting of

materials be provided with suitable means to prevent the fall of persons or material.

l) When persons are employed on roof where there is a danger of falling from a height

exceeding 2 metres suitable precautions shall be taken to prevent the fall of persons or

materials.

(m) Suitable precautions shall be taken to prevent persons being struck by articles which

might fall from scaffold or other working places.

n) Safe means of access shall be provided to all working platforms and other working

places.

o) The Contractor(s) will have to make payments to the labours as per

Minimum Wages Act.

Clause 21-B- The contractor shall comply with the following regulations as regards the

hoisting appliances to be used by him.

a)- Hoisting machine and tacket including their attachements, anchorges and support shall-

(i) be of good mechanical construction, sound material and adequate strength and

free from patent defect.

and

(ii) be kept in good repair and good working order.

b)- Every rope used in hoisting or lowering materials as a means of suspension shall be of

suitable quality and adequate strength and free from patenet defect.

c)- Hoisting machine and tackle shall be examined and adequately tested after erection

on the site and before use and be re-examined in position at intervala to be priscribed by the

Government.

Page 35: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 35 –

Sign of Contractor No of corrections Secretary SPSM

(d)- Every chain, ring, hook, shacle swivel and pulley block used in hoisting or lowering

materials or as a means of suspension shall be periodically examined.

(e)- Every crane driver pr hoissting appliance operator shall be properly qualified.

f)- No person who is below the age of 21 years shall be in control of any hoisting machine

including any scaffold which or give signals to the operator.

Measure for

prevention of fire.

Liability of

contractor for any

damage done in or

out side workarea.

Employment of

female labour.

Work on Sunday.

Work not to sublet

(g)- In the case of every hoisting and of every chain, ring, hook,

shackle, swivel, pully block ysed in hosting or lowering or as means of

suspension the safe working load shall be ascertained by adequate

means.

(h)- Every hoisting machine and all gear referred to in preceding

regulation shall be plainly marked with the safe working load.

i)- In the case of hoisting machine having a variable safe working

load, each safe working load and the conditions under which it is

applicable shall be clearly indicated.

(j)- No part of any hoisting machine or of any gear referred or in

regylation (g) above shall be loaded beyond the safe working load except

for the purpose of testing.

(k)- Motors, gearing, transmisions, electric working and other

dangerous part of hoisting appliances shall be provided with efficient

safaguards.

(l)- Hoising applicances shall be provided with such means as will

reduce to minimum the risk of the accidental descent of the load.

m)- Adequate precaution shall be taken to reduce to a minimum the

risk of any part of a suspended load becoming accidentally displaced.

Clause 22- The contractor shall not set fire to a standing jungle, trees,

brushwoods or grass without a written permit from the Secretary SPSM.

When such permit is given and also in all cases when destroying cut or

dug up trees, brushwoods, grass etc. by fire, the contractor shall take the

necessary measure to prevent such fire spreading to or otherwise

damaging surrounding property. The contractor shall make his own

arrangements for drinking water for the labour employed by him.

Clause 23- Compensation for all dangers done intentionationally or

unintetionally by contractor's labour whether in or beyond the limits of

SPSM. property including any damage caused by the spreading of fire

mentioned in Clause-22 shall be estimated by the Engineer-in-charge or

such other officer as he may appoint and the estimate of the Engineer-in

charge subject to the decision of the Vice Chancellor on appeal shall be

final and the contractor shall be bound to pay the amount of the assessed

compensation on demand, failing which, the same will be recovered

from the contractor as damages in the manner prescribed in clause 1 or

deducted by the Engineer-in-charge from any sums that may be due or

become due from SPSM. to contractor under this contractor or

otherwise.

The contractor shall bear the exoenses of defending any action or

other legal proceeding that may be brought by and person for in jury

sustained by him owing to neglect of precautions to prevent the spread of

Page 36: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 36 –

Sign of Contractor No of corrections Secretary SPSM

contract may be

rescinded and

security deposit

forfeited for

subleting it

without approval

or for

fire and he shall pay damages and cost that may be awarded by the court

in consequence.

Clause 24- The employment of female labours on work in

neighbourhood of soldiers barracks should be avoided as far as possible.

Clause 25- No work shall be done on a Sunday without the sanction

in writing of the Engineer-in-charge.

Clause 26- The Contract shall not be assigned or sublet without the

written approval of the Engineer-in-charge. And if the contractor shall

assign or sublet his contract or attempt so to do or become insolvent or

commence any proceeding to get himself adjudicated and insolvent or

make any composition with his creditors or attempts so to do or if bribe,

gratuity, fift, loan, perquiste, reward or advantage pecuniary or otherwise

shall either directly or indirectly be given, promised or offered by the

contractor of any of his servants or agents to any public officer or person

in the employ of SPSM. in any way relating to his office or employment

or if any such officer or person shall become in any way directly or

indirectly interested in the contract, and the Engineer-in-charge may

thereon by notice in writing rescind the contract, the contract and

the security deposit of the contractor shall there upon stand forfeited

and be absolutely at the disposal of SPSM and the same

consequences shall ensure as of the contract had been rescinded

under clause 3 hereof and in addition the contractor shall not be

entitled to recover or be paid for any work therefore actually

performed under the contract.

Clause 27- All sums payable by a contractor by way of

compensation under any of these conditions shall be considered as a

reasonable compensation to be applied to the use of SPSM. without

reference to the actual loss or damage sustained and whether any

damage has or has not been sustained.

Clause 28- In the case of tender any charge in the constitution of

a firm shall be forthwith notified by the contractor to the Engineer in

charge for his information.

Caluse 29- All works to be executed under the contract shall be

executed direction and subject to the approval in all respect of the

Secretary SPSM of the Circle, for the time being who shall be

entitled to direct at what point or points in what manner they are to

be commenced and from time to time carried on.

Clause 30- (1) Except where there otherwise specified in the

contract and subject to the powers delegated to him by SPSM. under

the Code, rules then in force, the decision of the Secretary SPSM of

the circle for the time being shall be final, conclusive and binding on

all parties to the contract upon all questions relating to the meaning

of the specifications, designs and instructions herein before

mentioned and as to the quality or workship, or material used on the

work or as to any other question, claim right matter or thing what-

so-ever if any way arising out of or relating or otherwise concerning

the works or the executions or failure to execute the same whether

bribing a public

officer or if contractor

becomes insolvent.

Sum payable by way

of compensation to be

considered as

resonable

compensation withour

referance to actual

loss

Change in the

constitution of firm to

be notified.

control of the

Secretary SPSM.

Direction &control of

the Secretary SPSM.

Page 37: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 37 –

Sign of Contractor No of corrections Secretary SPSM

arising during the process of the work or after the completion or

abandoment thereof.

2) The contractor may within thirty days of receipt by him of

any order passed by the Secretary SPSM as aforesaid appeal against

it with the contract work project provided that-

(a) The accepted Value of the Contract exceed Rs.10 Lakhs (Rs.Ten

Lakhs)

(b) Amount of claim is not less than Rs.1.00 Lakh (Rs.One lakh)

(3) If the Contractor so not satisfied with the order passed by the

University Engineer as aforesaid the contractor may within thirty

days of the receipt by him of any such order appeal against it to

the SPSM who if convinced that primaficia the contractor's

claim rejected by Secretary SPSM is not frivouls and that

there is some substances in the claim of contractor as would merit a

detailed examination and decision by the Standing committee shall

put up to the standing committee at Government level for suitable

decision. (as per PW Circular No.CAT 1086 OR 110/Bidg dt.

7-5-86)

Clause 31- The contractors shall obtain from the Departmental

stores, all stores and articals of Europian or in American

manufacturer which may be required for the work or any part thereof

or in making up any articlas required there for inconnection there

with unless he has obtained permission in writing from Engineer-in-

charge to obtain such stores and articles elsewhere.Thevalueof such

store and articals as may be supplied to the contractorbytheEngineer-

in-charge will be debited to the contractor in his

accountattheratesshowninthe schedule, in Form A attached to the

contract and if they are not entered in the said schedule, they shall be

debited to him at cost price which for the purposeof these contract

shall include the cost of carriage &other expenses whatsover, which

shall have been incurred in obtaining delivery of the same

atthestores aforesaid.

Store of European or

American

manufacture to be

obtained from the

Government.

Lump sums in

estimates.

Actions where no

specifications.

Clause 32- When the estimate on which a tender is made

includes lump sum in respect of parts of the work, the contractor

shall be entitled to payment in respect of the items of work involved

or the part of the work in question at the same rates at are payable

under this contract for each items, or if the part of the work

inquestion is not in the opinion of the Engineer-in-charge capable of

measurement, the Engineer-in-charge may at his discretion pay the

lump sum amount entered in the estimate and the certificate in

writing of the Engineer-in-charge shall be final and conclusive

against the contractor with regard to any sum or sums payable to him

under the provision of this clause.

Clause 33- In the case of any class of work for which there is not

such specification as is mentioned in rule 1 such work shall be

carried out in accordance with the Divisional specifications, and in

the event of there being no Divisional specification, then in such

Page 38: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 38 –

Sign of Contractor No of corrections Secretary SPSM

Definition of work

Contractor's

percentage whether

applied net or gross

amount of bill.

Refundof quarry fees

&royalties.

Compensation under

Workmen's

compensation Act.

case the work shall be carried out in all respects in accordance with

all instructions and requirements of the Engineer-in-charge.

Clause 34- The expression "Works" or 'work' used in these

conditions, shall unless there be something in the subject or context

repugnant to such construction, be construed to mean the work or

works contracted to be executed under or in virtue of the contract,

whether temporary or permanent and whether original, altered,

substituted or additional.

Clause 35- The percentage referred to in the tender shall be

deducted from/added to the gross amount of the bill before

deducting the value of any stock issued.

Clause 36- All quarry fees, royalties, octroi dues and ground rent

for stock materials, if any, should be paid by the contractor.

Clause 37- The contractor shall be responsible for and shall pay

any compensation to his workmen payable under the workmen's

Compensations Act, 1926 (VIII of 1923), (herein after called the

said Act) for injuries caused to the workmen. If such compansation

is payable be paid by Government as principle under Sub section (1)

of section 12 of the said. At on behalf of the contractor it shall be

recoverable by Government from the contraqctor under sub section

(2) of the said section. Such Compensation shall be recovered in the

manner laid down in the Clause-1 above.

Clause 37 A- The contractor shall be responsible for and shall pay

the expenses of providing medical aid to any workmen who may

suffer a bodily injury as a result of an accident. If such expenses are

incurred by Government the samd shall be recoverable from the

contractor forthwith and be deducted without projudice to any other

remedy of Government from any amount due to or that may become

due to the contractor.

Clause 37 B- The contractor shall provide all necessary personal

safety equipment and first aid apparatus available for the use of the

persons employed on the site and shall maintain the same in

condition suitable for immediate use at any time &shall comply with

the following regulations in connection therewith.

(a) The workers shall be required to use the equipment so

provided by the contractor and the contractor shall take adequate

steps to ensure proper use of the equipment by those concerned.

(b) When work is carried on in proximity to any place where

there is a risk of drowning all necessary equipment shall be provided

and kept ready for use and all necessary steps shall be taken for the

prompt rescue of any person in danger.

(c) Adequate provision shall be made for prompt first aid

treatment of all injuries likely to be sustained during the course of

the work.

Caluse 37 C- The contractor shall duly comply with the provisions

Page 39: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 39 –

Sign of Contractor No of corrections Secretary SPSM

of The Apprentices Act 1961 (III of 1961) the rules made there

under the orders that may be issued from time to time order the Act

the said rules and on his failure or neglect to do so he shall be

subject to all the liabilities and pentalties provided by the said Act

and said Rules.

Clause 38- (1) Quantities in respect of the several items shown in

the tender are approximate and no revision in the tendered rate shall

be permitted in respect of any of the itmes so long as subject to any

special provision contained in the specifications prescribing different

percentage of permissible variation the quantity of the item does not

exceed the tender quantity by more than 25% and so long as the

value of the excess quantity beyond this limit at the rate of the item

specified in the tender is not more than Rs.5000/-.

2) The contractor shall if ordered in writing by the Engineer so

to do, also carry out any quantities in excess of the limit mentioned

in sub clause (1) hereof on the same conditions as and in accordance

with the specifications in the tender at the rate (i) derived from the

rates entered in the current schedule of rates and in the absence of

such rates, (ii) at the rate prevailing in the market, the said rates

being increased or decreased as the case may be by the percentage

which the total tendered amount bears to the estimated cost of work

as put to tender based upon the schedule of rates applicable to the

year in which the tenders were invited. For the purpose of the

operation of this clause this cost shall be taken to be cost worked out

on the basis of D.S.R.200 - 200

Claims arising out of reduction in the tendered quantity of any item

beyong 25% will be governed by the provision of clause 15 only

when the amount of such reduction beyond 25% at the rate of the

item specified in the tender is more than Rs.5000/-. (The clause is

not applicable to extra items.)

3) The clause is not applicable to extra items.

(4) There is no change in the rate if the excess is more than 25%

of the tendered quantity, but the value of the excess work at the

Trndered rates does not exceed Rs.5000.

(5) The quantities to be paid at tendered rate shall include :-

(a) Tendered quantity plus.

(b) 25% excess of the Tendered quantity or the excess quantity of

the value of Rs.5000/- at the Tendered rates whichever is more.

Clause 39- The contractor shall employ any famine convict or

other labour of a particular kind or class if ordered in writing to do

so by the Engineer-in-charge.

Clause 40- No compensation shall be allowed for any delay

caused in the starting of the work on account of acquisition of land,

or in the case of clearance works on account of anydelay in

according to sanction of estimates.

Clause 41- No compensation shall be allowed for any delay in

the execution of the work in account of water standing in borrow pits

Claim for quantities

entered in the tender

or estimate.

Employment of

famine labour etc.

Claim for

compensation for

delay in starting the

work.

Claim for

compensation for

delay in execution of

work.

Page 40: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 40 –

Sign of Contractor No of corrections Secretary SPSM

or compartments. The rates are inclusive for hard or cracked soil,

excavation in mud, soil water standing in borrow pits and no claim

for extra rate shall be entertained unless otherwise expressly

specified.

Entering upon or

commencing any

portion of work.

Minimum age of

persons employed the

employment of

donkeys and or other

animals and the

payment of fair wages.

Method of Payment.

Acceptance of

conditions compulsory

before tendering for

work

Employment of

Scarcity labour.

Clause 42- The contractor shall not enter upon or commence any

portion of work except with the wirtten authority and instructions of

the Engineer-in-charge or of his subordinate in charge of the work.

Failing such authority the contractor shall have no claim to ask for

measurements of or payment for work.

Clause 43-(i) No contractor shall employ any person who is under

the age of 18 years.

(ii) No contractor shall employ donkeys or other animals with

breeching of string

or thin rope. The breeching must be at least there inches wide and

should be of tape (Newar.)

(iii) No animal suffering from sores, lameness or emaciation or

which is immature shall be comployed on the work.

(iv) The Engineer-in-charge or his Agent is authorised to remove

from the work any person or animal found working which does

not satisfy these conditions and no responsibility shall be accepted

by SPSM for any delay caused in the completion of the work by

such removal.

(v)The contractor shall pay fair and reasonable wages to the

workemen employed by him, in the contract under-taken by him. In

the event of any dispute arising between the contractor and his

workmen on the grounds that the wages paid are not fair and

reasonable the dispute shall be referred without delay to the

Secretary Engineer who shall decide the same. The decision of the

Secretary SPSM shall be conclusive and binding on the contractor

but such decision shall not in any way affect the conditions in the

contract regarding the payment to be made

by Government at the sanctioned tender rates.

(vi) Contractor shall provide drinking water facilities to the workers.

Similar amentities shall be provided to the workers engaged on

large work in urban areas.

(vii) Contractor to take precaution against accidents which takes

place on account of labout using loose garments while working

near machinery.

Clause 44- Payment to contractor shall be made by cheque

drawn on any treasury within the division convenient to them

provided the amount exceeds Rs.10 Amounts not exceeding Rs.10

will be paid in cash.

Clause 45- Any contractor who does not accept these conditions

shall not be allowed to tender for work.

Clause 46- If SPSM. declares a state of scarcity or famine to

exist in the village situated within 10 miles of the work, the

Page 41: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 41 –

Sign of Contractor No of corrections Secretary SPSM

contractor shall employ upon such parts of the works, as are suitable

for unskilled labour, any person certified to him by the Secretary

SPSM, or by any person to whom the Secretary SPSM may have

delegated this duty in writing to be in need of relief and shall be

bound to pay to such person wages not below the minimum which,

SPSM. may have fixed in this behalf. Any disputes which may

arise in connection with the implementation of this clause shall be

decided by the Secretary SPSM whose decision shall be final and

binding on the contractor.

Clause 47- The price quoted by the contractors shall not in any

case exceed the control price if any, fixed by SPSM. or reasonable

price which it is permissible for him to charge a private purchaser

for the same class and description the controlled price or price

permissible under Hoarding and Profiteering Ordinances 1948 as

amended from time to time.

If the price quoted exceeds the controlled price or the price premissible under

Hoarding and Profiteering Prevention ordinance the contractor will specfically

mention this fact in his tender along with the reasons for quoting such higher

prices. The purchaser at his discertion will in such case excerise the right of

revising the price at any stage so as to conform with the controlled price excerise

the right of revising the price at any stage so as to conform with the controlled

This descretion will be exercised without projudice to any other action that may

be taken against the contractor.

Clause 47 A- The tendered rates shall be inclusive of all taxes rates and cesses

and shall also be inclusive of the tax leviable in respect of works contract under

the provision of the Maharashtra Sales tax on transfer of property in goods

involved in the execution of works contract Act 1985 (Maharashtra Act No.XIX

of 1985)

Clause 48- The rates to be quoted by the contractor must be inclusive of

sales tax No extra payment on this account will be made to the contractor.

Clause 49- In case of materials that may remain surplus with the contractor

from those issued for the work contracted for the date of ascertainment of the

materials being surplus will be taken as the date of sale for the purpose of sale

tax and the sales tax will be recovered on such sale.

Clause 50- The Contractor shall employ the unskilled labour to be employed

by him on the said work only from locally available labours &shall give

perference to those persons enrolled under Maharashtra Government

employment &self employment Department's Scheme.

rovided however, that if the required unskilled labours are not available locally,

the contractor shall in the first instance employ such number of persons as is

available &thereafter may with previous permission, in writting of the Secretary

SPSM incharge of the said work, obtain the rest of requirment of unskilled

labour from outside the above scheme.

Clause 51- Wages to be paid to the skilled and unskilled labourers engaged

by the contractor.

The contractor shall pay the labourers skilled and unskilled according to the

wages prescribed by the minimum Wages Act of 1948 applicable to the area in

which the work is located.

The contractor shall comply with the provisions of the apprentices Act 1961 and

Maharashtra Act

XIX of 1985 Clause

regarding Turnover

Tax vide

P.W.D.Circular

Page 42: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 42 –

Sign of Contractor No of corrections Secretary SPSM

Rules and Orders issued thereunder from time to time. If he fails to do so. his

failure will be a breach of the Contract and the Secretary SPSM, may in his

discreation, cancle the Contract. The contractor shall also be liable for any

pecuniary libility arisen on account of any violation by him of the provision of

Act. The contractor shall pay the labourers skilled and Un-skilled according to

wages prescribed by Manimum Wages Act applicable to the area in which the

work lies.

Clause 52- All amounts whatsoever which the contractor is liable to pay to

the SPSM. in connection with the execution of the work including the amount

payable in respect of

(i) materials and or stores supplied/issued hereunder by the SPSM. to the

Contractor (ii) hire charges in respect of heavy plant, machinery and equipment

given on hire by the SPSM. to the contractor for execution by him of the work

and/or on which advances have been given by the SPSM to the contractor shall

be deemed to be arrears of the Land Revenue and the SPSM. may without

prejudice to any other rights and remadies of the SPSM. recover the same from

the contractor as arrears of Revenue.

No.CAT/1086/CR.33

0/Bldg-2 dt.

10/6/1986

P.W.Deptt.No. CAT

1284 (Building-2)

dated 14.8.1985.

Clause 53- The contractor shall duly comply with all the

provisions of the Contract Labour (Regulation and Abolition)

Act, 1970 (37 of 1970) and the Maharashtra Contract Labour

(Regulation and abolition) Rules, 1871 as amended from time

to time and all other relevant statutes and statutory provisions

concerning payment of wages particularly to workmen

employed by the contractor and working on the site of the

work. In particular the contractor shall pay wages to each

worker employed by him on the site of the work at the raes

prescribed under the Maharashtra Contract Labour (Regulation

and Abolition

Rules 1971). If the contractor fails or neglects to pay wages at

the said rates or markes short payment and the SPSM. makes

such payment of wages in full or part thereof less paid the

contractor, as the case may be, the amount so paid by the

SPSM. to such workers shall be deemed to be arrears of land

Revenue and the SPSM. shall be entitled to recover the same as

such from the contractor or deduct same from the amount

payable by the SPSM to the contractor hereunder or from any

other amount payable by the SPSM to the contractor hereunder

or from any other amount/s payable to him by the SPSM

Clause 54- The contractor shall engage apprentices such as

bricks layer, carpeters, wiremen, plumber as well as black

smith as recommended by the State Apprenticeship Advisor

Director of Technical Education, Dhobi Talav, Bombay 1 on

the construction work. (Government of Maharashtra Eductional

Department No.TSA-5170/T-56689 dated 7.7.1972).

Clause 55- (Government of Maharashtra P.W.D. Resolution

No.CAT-1086/CR-243/K/Bidg. 32 dt.11.8.1987).

The anti-malaria and other health measures shall be

as directed by the Joint Director (Malaria and

Page 43: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 43 –

Sign of Contractor No of corrections Secretary SPSM

Filaria) of Health services, Pune.

Contractor shall see that mosquitozenic conditions

are not created so as to keep vactor population to

minimum level.

Contractor shall carry out anti malaria measures in

the area as per guidelines prescribed under National

Malaria Eradication Programme and as directed by

the Joint Director (M &F) of Health Services, Pune.

In case of default in carrying out prescribed anti malaria

measures resulting in increase in malaria incidence, contractor

shall be liable to pay Government the amount spent by

Government on anti malaria measures to control the situation

in addition to fine.

Relations with Public Authorities - The contractor shall

make sufficient arrangements for draining away the sullage

water as well as water coming from the bathing and

washing places and shall dispose of this water in such a

way as not to bause any nuisance. He shall also keep the

premise clean by employing sufficient number of sweepers.

The contractor shall comply with all rules, regulations, bye-

laws and directions, given from time to time by any local or

public authority in connection with this work and shall pay

fees or charges which are leviable on him without any extra

cost to Government.

Clause 56 The tender rates are inclusive of all taxes, rates, cesses and also

inclusive of the leviable tax in respect of sale by transfer of property in

goods involved in the execution of a works contract under the provision of

Rule 58 of Maharashtra Value Added Tax ACT- 2005 for the purpose of levy

of Tax.

Clause 57 Tax Deducted at Source Value added Tax@ 2% of tender cost

from the contractors registered under Maharashtra Value Added Tax ACT-

2005 and @ 5% of tender cost from those contractors who have not registered

under Maharashtra Vaule Added Tax ACT 2005 will be deducted from bills.

Page 44: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 44 –

Sign of Contractor No of corrections Secretary SPSM

SCHEDULE 'A'

Schedule showing (Approxmately) the materials to the supplied from the

departmental stores for work, contracted to be executed and preliminary and ancillary works

and the rates at which they are to be charged for.

Particulars Rates at which the materials will be

charged to the contractor place of

delivery

Unit In figures In words

1 2 3 4 5

Nil

Nil

Nil

Nil

Nil

Page 45: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 45 –

Sign of Contractor No of corrections Secretary SPSM

ANNEXURE Aditional Conditions for procurement of Materials.

1. The contractor shall make his own arrangement for supply of materials including.

bitumen 60/70 grade/cement & steel RCC Pipes collars. The contractor shall be

responsible for all transportation & storage of the materials at site & shall be bear all

the related costs. The Engineer shall be entitled at any time, to inspect or examine all

such materials. The contractor shall provide reasonable assistance for such In

spection or examination as may be required.

2. The contractor shall keep as accurate record of use of material as like bitumen cement

& steel used in the works in a manner prescribed by the Engineer.

3. After receiving the bitumen the authorised challan/gate pass should be obtained from

the rofinary mentioning the quentity of bitumen/grade of bitumen, date time of

delivery etc. & it should be handed over to Department for each consignment.

4. While transportation of bouzer a through transport pass should be obtained from the

corporation/Municipalaty through which the bouzer is passed & same should be

handed over to the authorised person of Department.

5. If there is any doubt regarding the material received the same should be get tested

from the Gove. Laboratory of the cost of the Contractor & is the results are sub-

standard, the material or the work executed with such material will be rejected.

6. The day-today record of the receipt/utility/Balance of material should be kept by the

contractor at plant site/site of work/store & the same will be checked by the Engineer-

in charge of authorised Engineer at any time.

7. The procurement of cement/steel RCC pipe etc. should be from authorised

manufacturing company & the vouchers regarding purbhase thereof shall be

sumbitted to Engineer-In-charge.

8. The testing charges shall be borne by the contractor.

B. Materials for Department works.

1) The contractor shall be entitled to such sum as the Engineer may consider proper to

respect of materials intended for but not yer incorporated in the permanent works

provided that :-

a) The materials are in accordance with the specification for the permanent

works.

b) Such materials have been delivered to site and are properly stored and

protected against loss or damage or deterioration to the satisfaction of the Engineer.

c) The contractor's records of the requirement, order, receipts and use of

materials are kept in a form approved by the Engineer and such records shall be

available for inspection by the Engineer.

d) The contractor shall submit with his monthly statement the estimated value of

the materials on site together with such documents as may be required by the

Engineer for the purpose of valution of the materials and providing evidence of

ownership and payment thereof.

e) Ownership of such mateils shall be deemed to vest in the Employer, and

f) The sum payable for such materials, secured advance loans on site shall not

exceed 75 percent of the

i) extactory, exwarahouse price of locally manufactured materials or

ii) stockpile value of locally produced materials such as Bricks, sand,

Aggrigates and crushed metal.

Page 46: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 46 –

Sign of Contractor No of corrections Secretary SPSM

CONDITIONS FOR MATERIALS ISSUED UNDER SCHEDULE 'A'

The issue of material by the Department under Schedule 'A' of this contract will be

subject to interalia the following conditions :-

1. All the materials shall be made available for delivery on working day only during

working hours, to be arranged mutually by the contractor between himself and the

Storekeeper or the University Engeneers, who so ever shall issue the same. The

material shall be made available at the place of delivery mentioned in Schedule 'A' of

the tender.

2. The contractor shall submit periodically as well as on completion of work, an account

of all materials issued to him in a manner as directed by Engineer-in-charge. The

contractor shall also furnish an account of previous materials issued before placing

demand for further materials. In additions, a separate register shall be maintained on

site for recording daily item-wise cement consumption of cement issued under

Schedule 'A' as directed. This shall be signed daily by contractor or his representative

and representative of Engineer-in-charge.

3. The quantities in Schedule 'A' are approximate and may vary according to actual and

bonafide use as certified by the Engineer-in-charge.

4. All the materials mentioned in Schedule 'A' required for the work shall be taken from

the Department only. The materials from other source in lieu of the materials in

Schedule 'A' shall not be allowed except under written permission from the Secretary

SPSM. In such case, certificate for its quality shall be produced by the contractor and

samples of such materials shall be tested from any Government Laboratory by the

contractor at his own cost and the test results be supplied to the Department. The

materials not conforming to the required standard shall be removed at once from the

site of the work by the contractor at his own cost.

5. The rates mentioned in Schedule 'A' are inclusive of Sales Tax and storage charges.

6. After issue of any material for use on bonafide Government work to contractor if the

Engineer-in-charge ascertians on any particular date that the portion of such supplies

becomes surplus to the requirement of the work, the date of ascertainment will be

taken as the date for sale for the purpose of payment of sales tax on such portion and

recovered from the contractor as per rules.

7. The contractor shall construct shed/sheds as per direction of the Engineer-in-charge of

the work for storing the materials issued to him by the Department and provide

double locking arrangements, one lock shall be with incharge of Departmental person

and materials shall be taken for use in presence of the Departmental persons only.

8. The contractor shall make his own arrangement for the safe custody of the materials

which are supplied to him by the Department.

9. The contractor shall not use cement and other material under Schedule 'A' in items

other than as per this tender except for such ancillary small items as are connected

with and absolutely necessary for execution of this work as may be decided by the

Engineer.

10. All steel issued under Schedule 'A' which remains surplus with the contractor after

use in the work, shall be returned to the Department. Generally, only full length bars

in lenghts supplied by the Department shall be taken back by the Department.

However, the Engineer-in-charge may at his discretion, take back bars of particular

Page 47: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 47 –

Sign of Contractor No of corrections Secretary SPSM

diameter in any other lengths approved by him, if same are required for use in

Government work. The rates for repayment of the surplus acceptable materials

returned by the contract at the godown of issue, shall be at the prevailing market rates

or the rates charged to the contractor, excluding the element of storage charges or

issue rates excluding the element of storage charges at the time of retur, whichever is

lower. The quantity of such surplus steel as is not acceptable to the Department may

be disposed of by the Contractor in any manner he likes and the cost thereof shall

entirely be borne by the contractor. However in cases in which the materials issued to

a contractor become surplus owing to change in the design of the work after materials

were issued to the contractor the materials should be taken back from the contractor at

the same rates, at which they were supplies to him by Government provided, the

materials, at the time of taking over, were not actually needed and are serviceable.

11. Mild steel, Tor steel bars shall be issued to the contractor either in coils or straight, on

actual weighment, However, for the purpose of payment, the weight of steel bars used

on the work shall be calculated on the basis of standard weight per unit length vide

table in B-10, 13 of Standard Specification Book 1972, edition by B. and C.

Department. Hence claims on account of difference in actual weight and calculated

on the basis of standard weight per unit length shall not be entertained. No extra

payment for straightening the bars will be made.

12. The contractor shall make his own arrangement for securing structural steel such as

square bars, flats, rolled steels joints, angles, iron plates, etc. The department is

neither responsible for securing permit nor to supply required structural steel.

However, necessary certificate to the effect that the material is required for the said

bonafide Government work, will be issued of required.

13. The charges for conveyance of materials from the place of delivery to the site of work

and the actual spot on work site shall be entirely borne by the contractor. No claims

on this account shall be entertained.

14. If surplus materials after completion of the work are not returned by the contractor,

recovery of such materials at the penal rate of twice the issue rate of these materials

shall be made from the contractor. Salex Tax and General Tax on the cost of surplus

materials which are not returned, shall be recovered from the contractor as decided by

the Secretary SPSM. However, it is clear that any surplus material returened is in

unserviceable or damaged conditions, the same will not be accepted. In such case the

cost will be recovered from the contractor as stated above in this clause.

15. Empty asphalt drums will have to be returned to the Department in case of non-return

of empty asphalt drumps, recovery at Rs.200/- (Two hundred) per drum will be

charged to the contractor.

16. The person/firm submitting the tenders should see that the rates in the above schedule

'A' are filled-up by the Secretary SPSM-in-charge of the work on the issue of the form

prior to the submission of the tender.

17. The SPSM shall not be responsible for the loss in cement during transit from SPSM.

stores to work site. Cement so delivered to the contractor at the SPSM stores shall

mean 50 Kg./per bag by weight. The rate quoted should correspond to this method of

reckoning. The correction will have to be done by weight basis. While mixing, if

cement is found short in a bag, it will have to be made good by the contractor for

which additional cement would be supplied by the Department at issue rate in

Schedule 'A'. Item or percentage rate quoted for should reckon this.

Page 48: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 48 –

Sign of Contractor No of corrections Secretary SPSM

18. For the purpose of issue rate, the area of a A.C. sheets and ridges shall be the actual

gross size before laying in the roof and each dimension shall be measured at straight

line in plain (neglecting extra length, due to corrugations etc.)

19. The contractor shall furnish unstamped receipts for all material issued under Schedule

'A'.

20. The contractor shall furnish the account of steel cement etc. issued to him at each time

before placing an ident for further supply. Also he should submit on completion of

the work final account of all the materials supplied to him by the Department. This

account will be scrutinised by the Engineer-in-charge, and if any extra use of found,

shortages are seen, and any quantity of material remained unaccounted for, recovery

at penal rates will be effected for such quantities as mentioned in Clause 14 above.

21. A seperate register shall be maintained on site for recording detailed item wise cement

and steel consumption on the work. This register shall be signed by the contractor or

his authorised representative and got signed from the representaive of the Engineer-in-

charge.

Page 49: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 49 –

Sign of Contractor No of corrections Secretary SPSM

Additional General Conditions and specifications ______________________________________________________________________

Sr. INDEX Page No.

No. From To

__________________________________________________________________________

1 General 45 --

2 Contractor to study Site conditions. 45 --

3 Declaration of contractor. 45 --

4 Indemnity 45 --

5 Definitions 45 47

6 Errors, omssions and descrepancies 48 --

7 Working methodology and progress schedule. 48 49

8 Agent and work order book 49

9 Setting out 50 51

10 Levelling instruments. 52 --

11 Authority of representative of Engineer-in-charge 52 --

12 Co-ordination 52 --

13 Assistance in procuring Priorities/permits etc. 53 --

14 Quarries. 53 53

15 Collection of materials 54 56

16 Site office 56 --

17 Treasure-Trove 56 --

18 Patented Device 56 --

19 Explosive. 56 --

20 Damage by flood for accident 57 --

21 Police Protections 57 --

22 Traffice regulations 57 --

23 Inspections and supervision 58 --

24 Initial measurements 58

25 Samples and testing of materials 58 59

26 Change in cement contents etc. 59 --

27 Cement concrete/form work for concrete 60 60

28 Miscellanous 61 62

29 Medical and sanitary arrangement for labour 63

30 Safety code, Demolition 64 66

31 Scope of rates for different items of works 67 --

32 Payments 68 --

33 Handing over of work 68 --

34 Claims 68 --

35 Quality Assurence & Maintenance 64 69

Page 50: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 50 –

Sign of Contractor No of corrections Secretary SPSM

GENERAL CONDITIONS AND SPECIFICATIONS:-

1) These are to apply as aitional condition and specifications unless otherwise already

provided for contradictorily else where in this contract.

2) CONTRACTOR TO STUDY SITE CONDITIONS:-

The contractor shall be deemed to have carefully examined the work and side

condtions including labour, the general and the special conditions, specifications, schedules

and drawings and shall be deemed to have visited the site of the work and to have fully

informed himself regarding the local conditions and carried out his own investigation to

arrive at rates quoted in the tender. In this regard, he will be given necessary information to

the best of knowledge of department but without any guarantee about it.

If he shall have any doubt as to the meaning of any portions of these general

conditions or the special conditions, the scope of work of the specifications and drawings, or

any other matter concerning the contract, he shall in good time, before submitting his tender,

setforth the particulars thereof and submit them to the Secretary SPSM M.P.K.V., Rahuri in

writing in order that such doubts may be clarified authoritatively before tendering once a

tender is submitted, the matter will be decided according to tender conditions in the absence

of such authentic preclarification.

3) DECLARATION OF THE CONTRACTOR :-

The contractor should sign the declaration form on page 12

4) INDEMNITY :-

The contractor shall indemnify the Government against all actions, suits, claims and

demands brought or made against him in respect of anything done or committed to be done

by the contractor in execution of or in connection with the work of this contract and against

any loss or damage to the Government in consequence of any action or suit being brought

against the contractor for anything done or committee to be done in the execution of the

works of this contract.

5) DEFINATIONS :-

Unless excluded by or repugnant to the context.

(a) The expression " SPSM." as used in the tender papers shall mean the Savitribai

Shikshan Mandal,MPKV, Rahuri, Dist. A'nagar.

(b) The expression "Engineer" or "Engineer-in-charge" as used in the tender papers shall

mean the Engineer appointed by the SPSM of the work for the time being.

Page 51: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 51 –

Sign of Contractor No of corrections Secretary SPSM

(c) The expression "Contractor" used in the tender papers shall means the successul

tenderer whose tender has been accepted and who has been authorised to proceed

with the work.

(d) The expression "Contract" as used in tender papers shall mean the deed of contract

together with its original accompaniments and those later icorporated in it by mutual

consent.

(e) The expression "Plant" as used in the tender papers shall mean every temporary and

necessary means necessary or considered necessary by the Engineer to execute,

construct, complete and maintain the works and used in, altered, modified, substituted

and additional work ordered in the time and the manner herin provided and all

temporary materials and special and other articles of appliances of every sort, kind

and description what-so-ever intended or used there of.

(f) "Drawing" shall mean the drawings referred to in the specification and any

modification or such drawings approved in writing by Engineer and such other

drawings as may from time to time the furnished or approved in writing by the

Engineer.

(g) "Engineer's representative" shall mean an assistant of the Engineer notified in writing

to the contrtactor by the Engineer.

(h) Provisional sum or "Provisional lump sum" shall mean a lump sum included by

SPSM in tender documents and shall represent the estimated value of work for which

details are not available at the time of issue of tender.

(i) "Provisional items" shall mean items for which approximate quantities have been

included in the tender documents.

(j) The "Site" shall mean the lands and/or other places, on under in or through which the

work is to be executed under the contract including any other lands or places which

may be alloted by SPSM. or used for the purpose of contract.

(k) The "Work" shall mean the works to be executed in accordance with the contract or

part(s) thereof as the case may be and shallinclude all extra or aditional, altered or

substituted works as required for performance of the contract.

(l) The "Contract sum" shall mean the sum for which the tender is accepted.

(m) The "Accepting Authority" shall mean the officer competant to accept the tender.

(n) The "Day" shall mean a day of 24 hours from midnight to midnight irrespective of the

number of hours worked in any day in that week.

(o) "Temporary works" shall mean all temporary works of every kind required in or

about the execution, completion, or maintenance of the works.

Page 52: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 52 –

Sign of Contractor No of corrections Secretary SPSM

(p) "Urgent works" shall mean any measure which, in the opinion of the Engineer-in-

charge, become necessary during the progress of the works to obviate any risk or

accident or failure or which become necessary for security of the work or the persons

working, theron.

Where the context so requirs, words importing the singular only also include the

plural and vice-versa.

Heading and marginal notes, if any, to the general conditions shall not be deemed to

form pan thereof or be taken into consideration in the interpretation or construction thereof of

the contract.

Wherever there is mention of "Schedule of rates" of the Division or simply D.S.R. in

this tender, it will be taken to mean as "the Schedule of the rate of the Division in whose

jurisdiction the work lies".

a) "Secretary SPSM" means the Secretary SPSM of the Mahatma Phule Krishi Vidyapeeth

Rahuri or his representative.

(b) "Architest" means every partner of the firm appointed for the works or in the event of

their ceasing to be Architect for the work such other firm or person as may be appointed

by the SPSM, as Architect of this work.

The Architect so appointed is required to obtain all necessory permissions viz. N.A.

permission, commencement certificate, completion certificate, certificate from all

departments of Municipal Corporation required for it's lawful execution/Occupation of

the work / building in question.

The contractor shall allow the Architect to inspect the works who will give directives to

the contractor through the Secretary SPSM or his representative at the site during the

progress of the work to observe rules and regulations of the local authorities.

(c) "Secretary SPSM" Means the Comptroller of the SPSM, Rahuri.

(d) "Contractor" means the person or persons, firm or company whose tender has been

accepted by SPSM and includes the contractor's personal representative, successors and

permitted assings.

(f) "Contract price" means the sum name in the tender subject to such additions thereto or

deductions therefrom as may be made in the provisions hereinafter contained.

(g) "Construction Plant" means all appliances or things of whatsoever nature requied in or

about the execution plant or maintenance of the works or temperory works (as

hereinafter defined) but does not include materials or other things intended to for or

forming part of the permenant work.

(h) Services of notice in writing or "Written Notice" means notice of a communication in

written, typed or printed character sent to the last known private or business address or

registered office to which in the ordinary course of post it would have been delivered.

(i) "Virtual Completion" means that the completion as in the opinion of the University is fit

for occupation in every respect including removal and scaffolding plant, surplus

materials and rubbish and cleaning of dirt from works and site.

Page 53: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 53 –

Sign of Contractor No of corrections Secretary SPSM

(j) "Works" means all the works defined by Bill of quantities, drawings, specifications, and

such other works as the contractor may be entrusted with for executing with the contract.

(k) "Act insolvency" means any of insolvency as defined by the Maharashtra insolvency Act

or any amending Statute.

(l) "Site Order Book" means the order book which shall be maintained by the contractor

at the site of the work in which instruction shall be given to the contractor by the university as

and when necessary. These orders shall have to be assigned and complied by the contractor

and nothingelse will be written on it, if the contractor wants to represent anything relating

thereto, he can do so by separate letter.

6) ERRORS, OMMISSIONS AND DISCREPANCIES :- (a) In case of errors, omissions and/or dis-agreement between written an scaled dimentions

on

the drawing or between drawings and specifications etc. the following order of preference

shall apply.

(i) Between actual caled and written dimensions or descriptions on a drawing the

later shall be aopted.

(ii) Between the written or shown description of dimensions in the drawing and

corresponding one in the specifications, the later shall apply.

(iii) Between the quantities shown in schedule of quantities and those arrived at from

the drawings, the later shall be preferred.

(iv) Between the written description of the item in the schedule of quantities and the

detailed description in the specifications of the same item, the later shall be adopted.

(b) In case of discrepancy between percentage rate quoted in figures and words, the

lowest of the two will be consiered for acceptance of tender. (c) In all cases of omission and / or doubts of discrepancies in the dimension or description of

the item or specifications, a reference shall be mae to the Secretary SPSM, M.P.K.V., Rahuri

whose elucidation, elaboration or decision shall be cosidered as authentic. The contractor shall

be held responsible for any errors that may occur in the work through lack of such reference and

precaution.

(d) The special provision in detailed specifications and wording of any item shall gain

precedance over corresponding contradictory provision (if any) in the Standard Specifications of

Public Works Department Hand Book where reference to such specifications is given without

reproducing the details in contract.

7.1 PROGRAMME OF WORK :

The work is require to be completed within a period of ------4---------- months

(including the monsoon period). The tentative programme may be as per the Bar-chart on

Page------------.

7.2 (A) METHODOLOGY OF CONSTRUCTION AND CONSTRUCTION

EQUIPMENTS :

Page 54: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 54 –

Sign of Contractor No of corrections Secretary SPSM

Contractor shall furnish altleast 15 days in advance his programme of commencement of

item or work, the details of actual methods that would be aopted by contractor for the execution

of various items of work such a well sinking, cas-in-situ, super sturcture for Bridge work and

Earth work, W.B.M., Black topping items etc. for Road works supported by necessary detailed

drawing and sketches including those of the plant an Machinery that would be used their

locations, arrangement for conveying and hanling materials etc. and obtain prior approval of the

Engineer-in-charge reserves the right to suggest modifications or make complete changes in the

method proposed by the contractor, whether accepted previously or not at any stage of the work,

to obtain the desired accuracy, quantity and progress of the work which shall be bining on the

contractor, and no claim on account of such change in method of execution will be entertained by

SPSM. so long as specifications of the item remain unaltered. The side responsibility for the

safety and adequacy of the methods adopted by the contractor, will however, rest on the

contractor irrespective of any approval given by the Engineer.

In case of slippage from the approved work programme at any stage, the contractor shall

furnish revised programme to make up the slippage within the stipulated time schedule an obtain

the approval of the engineer to the revised programme.

(b) CONSTRUCTION EQUIPMENT :- The contractor shall be required to give a trial run of the equipments for establishing their

capability to achieve the laid down specifications and tolerance to the satisfaction of the Engineer

before commencement of the work. All equipment provided shall be of proven efficiency and

shall be operated and maintained at all times, in a manner acceptable to the Engineer and no

equipment or personnel will be removed from site without permission of the Engineer.

(c) PROGRESS SCHEDULE :-

The contractor shall furnish within the period of one month of the order to start the

work, the programme of work in CPM/PERT charts in quaruplicate indicating the date of

actual start, the monthly/progress expected to be achieved an the anticipated completion date

of each major item of work to be done by him, also indications dates of procurement and

setting up of materials, plant and machinery. The schedule is to be such as is practicable of

achievement towards the completion of whole work in the time limit, the particulars items, if

any, on the due dates specified in the contract and shall have the approval of the Engineer-in-

charge. No revised scheules hall be operative without such acceptance in writing. The

Engineer is further empowered to ask for more detailed schedule or schedules say; week by

week for any item to items, in case of urgency of work as will be directed by him and the

contractor shall supply the same as and when asked for.

The contractor shall furnish sufficient plant, equipment an labour as may be necessary

to maintain the progress of schedule. The working and shift hours restricted to one shift a day

for operations to be done under the Government supervision shall be such as may be

approved by the Engineer-in-charge. They shall not be varied without the prior approval of

the Engineer. Night work which requires supervison shall not be permitted except when

specifically allowed by Engineer each time if requested by the contractor. The contractor

shall provide necessary lighting arrangements etc. for night work as directed by Engineer

without extra cost.

Page 55: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 55 –

Sign of Contractor No of corrections Secretary SPSM

Further, the contractor shall submit the progress report of work in prescribed from and

charts etc. at periodical intervals, as may be specified by the Engineer-in-charge. Schedule

shall be in the form of progress charts, forms, progress statement and/or reports as may be

approved by the Engineer.

The contractor shall maintain proforma, charts, details regarding machinery,

equipment, labout, materials, personnel etc. as may be specified by the Engineer and submit

periodical returns therof as may be specified by the Engineer-in-charge.

AGENT AND WORK ORDER BOOKS :-

The contractor shall himself manage the work or engage an authorised all time agent

on the work capable of managing and guiding the work and understanding the specifications

and contract condition. A qualified and experienced, Engineer shall be provided by the

contractor as his agent for technical matters in case the Engineer-in-charge consiers this is

essential for the work and so directs contractors. He will take orders as well be given by the

Secretary SPSM or his representative and shall be responsible for carrying them out. this

agent shall not be changed without prior intimation to the Secretary SPSM and his

representative on the work site. The contractor shall supply to the Engineer the details of all

supervisory and other staff employed by the contractor and notify changes when made and

satisfy the Engineer regaring the quantity and sufficiency of the staff, thus employed. The

Engineer will have the unquestionable right to ask for changes in the quality and number of

contractor's supervisory staff and to order removal from work of any of such staff. The

contractor shall comply with such others and effect replacements to the satisfaction of the

Engineer.

A work order book shall be maintained on site and it shall be the property of SPSM.

and the contractor shall promptly sign orders given therein by the Engineer-in- charge or his

representative and his superior officers and comply with them. The complaince shall be

reported by the contractor to the Engineer in good time so that it can be checked. The blank

work order book with machine numbered pages will be provied by the department free of

charge for this purpose. The contractor will be allowed to copy out instructions therein from

time to time.

(9) SETTING OUT : (I) ROAD WORKS :

9.1 The contractor shall establish working bench marks in the area soon after taking

possession of the site. The referance Bench mark for the area shall be as indicated in

the Contract Documents. The working bench marks/shall be at the rate of four per

KM and also at or near all drainage structures, over bridge and underpasses. The

working bench marks/levels should be got approved from the engineer. Checks must

be made on these bench marksonce every month and adjustment if any got agreed

with the Engineer and recorded. An upto date record of all bench marks including

approved adjustment, if any shall be maintaine by the contractor and also a copy

supplied to the Engineer for his record.

Page 56: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 56 –

Sign of Contractor No of corrections Secretary SPSM

9.2 The lines and levels of formation, side slopes, drainage, corriageways and shoulders

shall be carefully set out and frequently checked, care being taken to ensure that

correct gradients and cross sections are everywhere obtained.

9.3 In order to facilitate the setting out of the works, the center line of the carriageway or

highway must be accuraty established by the contractor and approved by the Engineer.

It must then be accuratly referenced in a manner satisfactory to the Engineer every 50

m. intervals in plain and rolling terrain and 20 m. intervals in hilly terrain and in all

curve points as directed by the Engineer, with marker peges chainage boards set in or

near the fence line, and a schedule of referance dimentions shall be prepared and

supplied by the contractor to the engineer. These markers shall be maintained untill

the works reach finished formation level and are accepted by the Engineer.

9.4 On construction reaching the formation levell stage the center line shall again be set

out by the Contractor an when approved by the Engineer shall be accuratly referenced

in a manner satisfactory to the Engineer by marker pegs set at the outer limits of the

formation.

9.5 No referance peg of market shall be moved or withdrawn without the approvel of the

Engineer and no earthwork or structrul work shall be commenced until the centre line

has been referenced.

9.6 The contractor will be the sold responsible party for safeguarding all survey

monuments, bench marks, beacons etc. The Engineer will provie the Contractor with

the data necessory for the setting out of the center line all dimensions and levels

shown on the drawings or mentioned in document forming part of or issued under the

contract shall be verified by the contractor on the site and he shall immediatly inform

the Engineer of any apperent errors or (discrepa-ncies) in such dimentions or levels.

The contractor shall after or in connection with the setting gut of the center line,

survey the terrian along the road and the centreline an cross sections at intervals as

required by the Engineer.

9.7 After obtaining approval of the Engineer, work on earthwork can commence and the

profile an the cross sections shall from the basis for measurements and payment. the

Contractor is responsible for checking that all the basic traverse points are in place at

the commencement of the contract and if any are mission or appear to have been

disturbed, the Contractor shall make rearrengements in reestablish these points. A

"Survey File" containing the necessory data will be made available for this purpose. If

in the opionion of the Engineer, design modifications of the centreline or grade are

advisable the Engineer will issue detailed instructions to the contractor and the

contractor shall perform the modifications in the fielld, as required and modify the

ground levels on the cross sections accordingly as many times as required. There will

be no seperate payment for any survey work performed by the Contractor. The cost

of these services shall be considered as being included in the cost of the items of the

work in the bill of Quantities. 9.8 The work of setting out shall be deemed to be a part of general works preparatury to

the execution of the work and no separate payment shall be made for the same.

(ii) SETING OUT FOR (BRIDGE WORKS):

Page 57: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 57 –

Sign of Contractor No of corrections Secretary SPSM

Immeiatly on receipt of the work order, the Contractor shall at his own expence clean

the site and take up a provisional and final setting out an lining out of the work under the

supervision of his responsible representatives and shall provided necessary material labour,

tools instruments etc. required for the same.

One tentative abutment location will be indicated by Engineer-in-charge and the

center line of the bridge shall be defined by him. The Contractor will then have to fix up the

location of the other abutment. The abutment location will then be verified by the

Department and may be adjusted. Once the final location of the abutment is so finalised it

will be the contracters responsibility to line out and locate the remaining foundations.

The contractor shall be responsible for true and proper setting out of the works an for

the corrections of he positions, level dimentions and agreement of all the parts of works, and

for providing all necessory instruments appliance and labours in connection therewith at his

own cost. Officers may assist the Contractor in proper setting out. Government instruments

may be allowed to be used for setting out of the work for which no cost shall be recovered

from the contractor. If at any time furing the progress of work, any error arise in regard to

levels or dimentions or alignment of any part of the work rectification thereof on being

required to do so will be carried out by the contractor at his own cost, unless such errors are

based on in correct data, supplied in writing by the Engineer or his authorised representative

in which case the expance of the rectification shall be refunded by SPSM.

The checking of any setting out or checking levels by the Engineer or his authorised

representative shall not in any way relieve the contractors of his responsibility for the

correctness thereof. The Contractor shall carefully protect and preserve all bench marks site

rails, pegs an other things used in setting out of works.

SETTING OUT FOR (BUILDING WORKS)

The Engineeringcharge shall furnish the contractor with only the four corners of the

worksite and a level bench mark and the contractor shall set out the works and shall provide

an efficient staff for the purpose and shall be solely responsible for the accuracy of such

setting out.

The Contractor shall provide fix and be responsible for the maintenance of all stackes,

templates, level marks profiles and other similar thuings and shall take all necessary

precautions to prevent there removel or disturbance and shall be responsible for the

consequence of such removel or disturbances should be the same take place and for their

efficient and timely reinstatement. The contractor shall also be responsible for the

maintenance of all existing survey marks boundary marks, distance marks and centre line

marks, either existing or supplied and fixed by the contractor. The work shall be set wut to

the satisfaction of Engineer-in-charge. The approval therefore or joining with the contractor

by the Engineer-in-charge in setting out the work, shall out relieve the contractor of any of

his responsibilities.

Before beginning the work, the contractor shall at his own cot provide all necessary

referance and level posts, pegs, bamboos, flags, ranging rods, strings and other materials for

proper layout of the work in accordance with the scheme for bearing marks acceptable to the

Engineer-in-charge. The centre, longitudinal or face lines and cross line shall be marked by

means of small masonry pillers. Each piller shall have distinct mark at the centre to enable

theodolite to be set over it. No work shall be started until all these points are checked and

approved by the Engineer-in-charge in writing but such approval shall not relieve the

contractor of any of his responsibilities. the contractor shall also provides all labour, material

Page 58: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 58 –

Sign of Contractor No of corrections Secretary SPSM

and other facilities, as necessary for the proper chocking of layout and inspection of the

points during construction.

Pillar bearing geodetic marks located at the sites of units of works under the

construction should be protected and fenced by the contractor.

On complition of works, the contractor must submit the geodetic documents

according to which the work was carried out.

RESPONSIBILITIES FOR LEVEL AND ALIGNMENT :

The contractor shall be entirelly and exclusively responsible for the horizontal and

vertical alignment, the levels and correctness of every part of the work and shall rectify

effectually any errors or imperfections therein, such rectifications shall be carried out by the

contractor at his own cost, when instructions are issued to that effect by the Engineer-in-

charge.

(10) LEVELLING INSTRUMENTS:-

If measurements of items of the work are based on volumetric measurements

calculated from levels taken before and after constructions of the item, a large number of

levelling stayas tapes etc. will have to be kept available by the Contractor at the site of work

for this pupose. Lack of the such levelling staves, tapes etc. in required numbers may cause

delay in measurements and the work. The contractor will have therefore to keep sufficient

number of these readily available at site.

(11) AUTHORITIES OF THE ENGINEER IN CHARGE'S REPRESENTATIVE :-

The duties of the representative of the Engineer-in-chargeare to watch and supervise

the work and to test and examine any material to be used or workmanship employed in

connection with the works.

The Engineer-in-charge may from time to time, in writting delegate to his

representative any powers and authorities vested in the Engineer-in-charge and shall furnish

to the contractor a copy of all such delegations of powers and authorities. Any written

instructions of approval given by the representative of the Engineer-in-charge to the

contractor within the terms of such delegations (but not otherwise) shall bind the contractor

and the department as through it had been given by the Engineer-in-charge, provided always

as follows.

Failure of the representative of the Engineer-in-charge to disapprove any work or

materials shall not prejudice the power of the Engineer-in-charge thereafter to disapprove

such work or materials and so order the putting down, removal of breakin up thereof.

(12) CO-ORDINATION :-

When several agencies for different sub-works of the project are to work

simultaneously on the project site, there must be full co-ordination and co-operation between

contracotrs to ensure timely completion of the whole project smoothly. The scheduled dates

for completion specified in each contract shall therefore, be strictly adhered to. Each

Page 59: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 59 –

Sign of Contractor No of corrections Secretary SPSM

contractor may make his independent arrangement for water, power, housing etc. if they so

desire. On the other hand the contrectors are at liberty of mutual agreement in this behalf and

make joint arrangements with the approval of the Engineer. No single contractor shall take or

cause to be taken any steps or action that may cause, distruption discontent, or disturbance of

work, labour or arrangement etc. of the other contractor which the Engineer in his

unquestioned discretion may consider as infringment of the above code, would be considered

as a breach of the contract conditions and shall be dealth with as such.

In case of any dispute, disagreement between the contractors, the Engineer's decision

regarding the co-ordination, co-operation and facilities to be provided by any of the

contractors shall be final and binding on the contractors concerned and such a decision or

decisions shall not vitiate any contract nor absolve the contractor(s) of his/their obligations

under the contract nor consider for the grant for any claim or compensation.

(13) ASSISTANCE IN PROCURING PRIORITIES, PERMITS, ETC. :-

The Engineer, on a written request by the contractor, will, if in his opinion, the

request is reasonably and in the interest of work and its progress assist the contractor in

securing, the priorities for deliveries transport permits for controlled materials etc. where

such are needed. The SPSM. will not however, be responsitble for the non-availability of

such facilities or delay in this behalf and no claims on account of such failure or delays shall

be allowed by the SPSM.

The Contractor shall have to make his own arrangement for machinery required for

the work. However, such machinery conveniently available with the Department, may be

spared as per rules in force on recovery of necessary Security Deposit and rent with

agreement in the prescribed form. Such an Agreement shall be independent of this contract

and the supply of machinery shall not form a ground for any claim or extension of time limit

for this work.

(14) QUARRIES :-

14.1 No P.W.D. quarries are available with this Department. The contractor(s) shall have

to arrange the same himself/themselves.

14.2 The quarrying operations shall be carried out by the Contractor with proper

equipment such as compressors, Jack-hammers, drill bits, explosives etc. and

sufficient number of workmen shall be employed so as to get the required out-turn.

14.3 The Contractor shall carry out the works in the quarries on conformity with all the

rules and regulations already laid down or that may be laid down from time to time by

SPSM. Any cost incurred by SPSM. due to non-compliance of any rules or

regulations or due to damages by the Contractor shall be the responsibility of the

Contractor. The Engineer-in-charge or his representative shall be given full facilites

by the Contractor for inspection at all times of the working of the quarry, records

maintained, the stocks of the explosives and detonators etc. so as to enable him to

check that the working records and storage are all in accordance with the relevant

rules. The Engineer-in-charge or his representative shall at any times be allowed to

inspect the works, buildings, and equipment at the quarters.

14.4 The Contractor shall maintain at his own cost the books, registers etc. required to be

maintained under the relevant rules and regulatins and as directed by the Engineer-in-

charge. These books shall be open for inspection at all times by the Egnineer-in-

Page 60: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 60 –

Sign of Contractor No of corrections Secretary SPSM

charge or his representative and the contractor shall furnish the copies of extracts of

books or registers as and when required.

14.5 All quarrying operations shall be carried out by the Contractor in orgainsed and

expenditious manner, systematkeally and with proper planning. The Contractor shall

engage licensed blasters and adopt electric blasting and/or any other approved method

which would ensure complete safety to all the men engaged in the quarry and its

surroundings. The Contractor shall himself provide suitable magazines and arranges

to procure and store explosives etc. ar required under the rules at his own cost. The

designs and the location of the magazine shall be got approved in advance from the

Chief Inspector of Explosives and the Rules and Regulations in this connection as laid

down by the Chief Ispector of Explosives from time to time shall be strictly adhered

to by the contractor. It is generally experienced that it takes time to obtain the

necessary licence for blasting and licence for storage of materials from the concerned

authorities. The Contractor must, therefore, take timely advance action for procuring

all such licences so that the work progress may not be humpered.

14.6 The approaches to the quarrying place form the existing public roads shall have to be

arranged by the Contractor at his own cost and the approaches shall be maintained by

the Contractor at his won cost till the work is over.

14.7 The Quarrying operations shall be carried out by the Contractor to the entire

satisfaction of the Engineer-in-charge and the developement of the quarry shall be

made efficiently so as to avoid wastage of stones. Only such stones as are of the

required quality shall be used on the work. Any stone which is in the opinion of the

Engineer-in-charge, not in accordance with the specifications or of required quality

will be rejected at any time, at the quarry or at the site of work. The rejected stones

shall not be used on the work and such rejected materials shall be removed to the

place shown at the Contractors's cost.

14.8 Since all stones quarried from Government quarry (iff made available) by the

Contractor including the excavated over burden are the property of the Government.

No stones or earth shall be supplied by the Contractor to any other agencies or works

or allowed to be taken away for any other works. All such surplus quarried materials

not required for work under this contract shall be the property of the Government and

shall be handed over to the Contractor to Government free of cost at quarry site duly

heaped at the spots indicated by the Engineer-in-charge. The contractor will be

entitled to the refund of royalty if any paid by him for such quantity handed over to

Government for which necessary certificate will be issued by Executive Engineer as

per usual procedure. If however, the SPSM. does not required such surplus material

the Contractor may be allowed to dispose off or use such material else where with

prior written permission of the Engineer-in-charge. Leaving off a quarry face or

opening of a new quarry face shall be done only on the approval of the Engineer-in-

charge.

14.9 Quarrying permission will have to be directly obtained by the contractor from the

Collector of the District concerned for which purpose the Department will render

necessary assistance. All quarry fees, royalty charges, octroi duties, ground rent for

staking material etc. if any to be paid, shall be paid directly by the contractor as per

rules in force. The Contractor will however, be entitled to a refund of part of such

charges as are admissible under rules as mentioned elsewhere in this contract after

Page 61: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 61 –

Sign of Contractor No of corrections Secretary SPSM

obtaining a certificated from the Engineer-in-charge that the material were required

for use on Government works.

14.10 The Contractor will be permitted to earect at his own risk and cost at the quarry site if

suitable vacant space in SPSM. area is available for the purpose his own structures

for stores, offices etc. at places approved by the Engineer-in-charge. On completion

of the work the contractor shall remove all the structures erected by him and restore

the site to its original condition.

14.11 The Contractor shall not use any land in the quarry either for cultivation or for any

other purpose except that required for breaking or transporting stones.

(15) COLLECTION OF MATERIALS :-

i) Where suitable and approved P.W. Department's quarries exist, the contractor or

piece worker will be allowed if otherwise there is no objection to obtian the materials

to the extent required for the work from the quarry. He will be, however, liable to pay

compensation of any damage if caused to the quarry either deliberately or through

neglience or for wastage of materials by himself or his staff or labour. The Contractor

shall pay necessary royalty in advance and claim refund according to rules, if

admissible, and shall submit detailed accounts or materials from quarries as directed.

ii) Where no suitable P.W. Department's quarries exist or when the quantity of the

material required cannot be obtained from a P.W. Department quarry the Contractor

or piece-worker shall make his own arrangements to obtain the material from existing

or a new quarry in Government waste land, private land or land belonging to other

States or talukas etc. After opening the quarry but before starting collection the

quarry shall be got approved by the Engineer-in-charge or his representatives. The

Contractor or piece worker shall pay all royalty charges compensation etc. No claims

or responsibility on account of any of obstructions caused to execution of the work by

difficulties arising out of private owners of the land will be entertained.

iii) The rates in the tender include all incidental charges such as opening of new quarry,

opening out a new portion in an existing quarry, removing top soil and the unsuitable

material, dewatering, quarry, cost of blasting power of fuse, lift lead, repairs to

existing cart tracks, making new cart tacks, control charges, Central/State

Government or Municipal Taxes, Local Board Cess etc.

iv) The rates in the tender are for the delivery of the approved material on road side

properly stacked at the places specified by the Engineer-in-charge and are inclusive of

conveyance charges in respect of the leads and lifts. No claims on account of changes

in lead will be entertained.

v) No material shall be removed from the land within the road boundary or from the land

touching it without the written permission of the Engineer-in-charge or his authorised

agent. If any material is un authorisely obtained from such places, the contractor or

piece workers shall have to make good the damages and Pay such compensation in

addition as may be decided by the Executive Engineer and will have to stop further

collection.

vi) Any material that falls on any P.W.D. Road from the card etc. during conveyance

shall be immediately picked up and removed by the Contractor or piece worker,

failing which it will be got removed Departmentally at his cost. No heap shall be left

Page 62: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 62 –

Sign of Contractor No of corrections Secretary SPSM

prior to stacking even temporarily on the road surface or in any way so as to cause

any obstruction or danger to the traffic. The any claims of compensation etc. arising

out of any accident etc. Any such materials causing obstruction or danger etc. will be

got removed Departmentally at his cost thum removed will be entertained. the

contractor shall also be responsible for the damage or accident etc. arising out of any

material that falls on the road or track, not in charge of the Department and shall

attend to any complaints which may be received.

vii) The materials shall not be stacked in place where it is liable to be damaged or lost due

to traffic passing over it, to be washed away by rain or floods, to be buried under the

land slides etc. of the slip down and embankment or hill side etc. No claims for any

loss due to these and similar causes will be entertained.

viii) Before stacking, the materials shall be free from all earth, rubbish, vegetable matter

and other extraneous substance and in the case of metal, screened to guage if so

directed when ready. It shall be stacked entirely clear of the road way on ground

which has been cleaned of vegetation and levelled. On high banks ghat roads etc.

where it may not be practicable to stack it entirely clear of the roadway it my be

stacked with the permission of the Engineer-in-charge on berms in such a way as to

cause minimum danger and obstruction to the traffic or as may be directed by him.

ix) The size of the stack for materials other than rubble shall be 1.0 m. X 1.0 X 0.5 m. or

such other size as may be directed by the Engineer-in-charge and all but one stack in

furlong shall be of the same uniform size and shall be uniformly distributed over

whole lenghts. One stack (at the end) in each furlong may be of lenght different from

the rest in order to adjust total quantity to be required but its width and height will be

the same as those of the rest.

x) The Secretary SPSM shall supply the contractor with statement showing furlong wise

quantities that will be required and the order in which the collection is to be done. No

materials in excess of requirements in that furlong shall be staced. Any excess

quantity shall be removed at the Expense of the contractor or piece worker to where it

is required before the material in that furlong is finally measured.

xi) In stacking materials the deposition shall commence at the end of the mile furthest

from the quarry and be carried continuously to the other end (unless otherwise

directed by the Secretary SPSM). Stacking in one furlong shall be completed before it

is started in another unless directed otherwise in writing by the Secretary SPSM.

Measurements of the materials stacked in a furlong will not be recorded until the full

quantity required has been stacked unless otherwise authorised by Engineer in writing.

Collecting and spreading shall not be carried out at the same time in one and the same

mile or in two adjoining miles except with the written permission of the Secretary

SPSM.

xii) Unless otherwise directed the materials shall be collected in the following order

according to availability of space. (1) Rubble (if included in tender) (2) metal (3) Soft

murum and (4) Hard murum. Hard murum shall be stacked on the side opposite to

that on which soft murum has been stacked. Similarly, metal collected for petty

repairs shall be stacked on the side opposite to metal for new layer. Where metal for

two layers has to be stacked, as in the case of new roads, the metal for each layer shall

be stacked on the opposite sides of the road.

xiii) All road material shall be examined and measured before it is spread. The labour for

measurements (and check measurements wherever carried out) shall be supplied by

Page 63: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 63 –

Sign of Contractor No of corrections Secretary SPSM

the contractor or piece worker. immediately after the measurements are recorded the

stacks shall be marked by the contractor or piece worker by white wash or otherwise

as may be directed by the Secretary SPSM to prevent from any possibility of the same

material being measured and recorded over again and to prevent any unauthorised

tampering with the stacks. If the contractor or the piece worker fails to attend the

measurements of materials after receiving the notice from the Secretary SPSM or his

subordinate stating date and time of the intention to measure the work, shall be

measured neverthless and no complaint in this respect will be entertained lateron. If

the contractor or piece worker fails to supply sufficient labour for the materials

required at the time to measurements or check measurements, after due notice has

been given to him, the expenses incurred on account of employing departmental

labour or material etc.

xiv) No deduction will be made for voids.

(16) THEMPORARY QUARTERS AND SITE OFFICE :-

i) The contractor shall at his own expense maintain sufficient experienced supervisory

staff etc. required for the work and shall make his own arrangement, provide housing

for them with all necessary arrangements, including fire preventive measures etc. as

directed by the Engineer-in-charge.

ii) The contractor shall provide, furnish, maintain and remove on completion of the work,

a suitable office on the work site for the use of Secretary SPSM's representative. The

Sft. covered area Exclusive of Verandah should not be less than 400. It may have

brick walls and asbestos or corrugated iron roof, paved floor should be 18" above

ground level. He should provide a suitable latrine, urinals and keep them clean daily.

this will be supposed to be included in his rate.

(17) TREASURE TROVE :-

In the event of discovery by the contractor or his employees, during the progress of

the work of any treasure, fossils, minerals or any other articles of value or interest, the

contractor shall give immediate intimation thereof to the Engineer and forthwith hand over to

the Engineer such treasure to things which shall be the property of Government.

(18) PATENTED DEVICE : Whenever the contractor desires to use any designed devices, materials or process

covered by the letter of patent or copy right, the right for such use shall be secured by suitable

legal arrangement and agreement with patent owner and the copy of their agreement shall be

with the Engineer-in-charge if so desired by the later.

(19) EXPLOSIVES :

The contractor shall at his own expense construct and maintain proper magazines, if

such are required for the storage of explosives for use in connection with the work and such

magazine, being situated constructed and maintained in accordance with the Government

Rules applicable in that behalf. The contractor shall at his own expenses obtain such license

or Licenses as may be necessary for storing and using explosives. Notwithstanding that the

location etc. or storage of explosvies are approved by the Engineer, the SPSM. shall not be

incurring any responsibility whatever in connection with storage and use of explosives on the

site

Page 64: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 64 –

Sign of Contractor No of corrections Secretary SPSM

or any accident or occurance what-so-ever in connection, there wtih, all operations in or for

which explosives are employed being at the risk of contractor and upon his sole responsibility

and the contractor hereby gives to SPSM. an absolute indemnity in respect thereof.

(20) DAMAGE BY FLOODS OR ACCIDENTS :-

The contractor shall take all precautions against damage by floods or like or from

accident etc. No compenstaion will be allowed to the Contractor on this account or for

correcting and repairing any such damage to the work during construction. The contractor

shall be liable to make good at his cost any plant or materials belonging to the Government

lost or damaged by floods or from any other cause which is in his charge.

(21) POLICE PROTECTION :

For the Special Protection of camp and of the contractor's works, the Department will

halp the contractor as far as possible to arrange for such protection with the concerned

authorities if so required by the Contractor in writing. the full cost of such protection shall be

borne by the Contractor.

(22) TRAFFIC REGULATION FOR ROAD WORKS :-

22.1 Unless separately provided for in the contract, the Contractor shall have to make all

necessary arrangements for regulating traffic, day to night during the period of

construction to the entire satisfaction of the Engineer. This includes the construction

and maintenance of diversions if necessary. The contractor shall have to provide

necessary caution boads, barricades flags, lights and watchmen etc. so as to comply

with the latest Motor Vehicles Rules and regulation and for traffic safety and he shall

be responsible for all claims from accidents which may arise due to his neglignece

whether in regulating the traffic or in stacking material on the roads, or due to any

other reasons.

22.2 The contractor shall at all times carry out the work on the road in a manner creating

least interference to the flow of traffic, while consistant with the satisfactory

execution of the same. For all works involving improvements to the existing road, the

contractor shall, in accordance with the directives of the Engineer-in-charge, provide

and maintain, during the execution of work a passage for traffic, either along a partof

the existing carriage way under improvement, or along a temporary diversion

constructed close to the road.

22.3 TRAFFIC REGULATION FOR BRIDGES AND C.D.WORKS :-

It is to be clearly understood that whatever work carried out by the Contractor for

construction of diversion road including earthwork, W.B.M. bituminous surface dressing,

R.C.C. pipe drains etc. will be paid for only once if the items of temporary diversion are

included in the Contract and if due to flow of traffic, due to floods or due to any other cause,

this diversion road and/or the R.C.C. drain gets damaged it shall be repaired and mainatined

by the Contractor in good conditions till completion of the whole work at his own expenses.

Page 65: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 65 –

Sign of Contractor No of corrections Secretary SPSM

Traffic safety and control shall be as per cause No.112.4 of M.O.S.T. Specification for Roads

and Bridges (IInd Revision 1990).

(23) SUPERVISION AND INSPECTION OF WORKS AND QUALITY

CONTROL :-

23.1 SUPERVISION :-

The contractor shall either himself supervise the execution of the works or shall

appoint the competent agent approved by the Engineer-in-charge, to act on his behalf. If in

the opinion of the Engineer-in-charge, the contractor has himself no sufficient knowledge and

experience of receiving instructions or cannot give his full attention to the works, the

contractor shall at his own expenses, employ as his accredited agent a qualified Engineer

approved by the Engineer-in-charge.

Orders given to the contractor's agent shall be considered to have the force as if these

had been given to the contractor himself. If the contractor fails to appoint a suitable agent as

directed by the Engineer-in-charge, the Engineer-in-charge shall have full power to suspend

the execution of the work untill such date a suitable agent is appointed and the contractor

shall be responsible for the delay so caused to the works and contractor shall not be entitled

for any compensation on this behalf.

23.2 INSPECTION :-

The contractor shall inform the Engineer-in-charge in writing when any portion of the

work is ready for inspection giving him sufficient notice to enable him to inspect the same

without affecting the further progress of the work. The work shall not be considered to have

been completed in accordence with the terms of the contract un till the Engineer-in-charge

shall have certified in writing to that effect. Approval of materials or workmenship or

approval of part of the work during the progress of execution shall not bind the Engineer-in-

charge or in any way affect him even to reject the work which is alleged to be completed and

to suspend the issue of his certificate of completion untill such alteration and modifications or

reconstruction have been effected at the cost of the contractor as shall enable him to certify

that the work has been completed to his satisfaction.

The contractor shall provide at his cost necessary ladders and such arrangements as to

provide necessary facilities and assistance for proper inspection of all parts of the work at his

own cost.

(24) INITIAL MEANSUREMENTS FOR RECORDS :-

Where, for proper measurement of the work, it is necessary to have and intitial set of

levels or other measurements taken, the same as recorded in the authorised field book or

measurement book of SPSM. by the Engineer or his authorised representative will be signed

by the contractor who will be entitled to have a true copy of same made at his cost. Any

failure on the part of the contractor to get such levels etc. recorded before starting the work

will render him liable to accept the decision of the Engineer as to the basis of taking

measurements. Like-wise the contractor will not cover any work which will render its

subsequent measurements difficult or impossible without first getting the same jointly

measured by himself and the authorised representative of the Secretary SPSM. The record of

such measurements on the SPSM side will be signed by the Contractor and he will be entitled

to have a true copy of the same made at his cost.

(25) SAMPLES AND TESTING OF MATERIALS :-

Page 66: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 66 –

Sign of Contractor No of corrections Secretary SPSM

i) All materials to be used on work shall be got approved in advance from the Engineer-

in-charge and shall pass the test and/or analysis required by him which will be :-

(a) as specified in the specification for the items concerned and/or

(b) I.S.I. specifications (whichever and wherever applicable) or

(c) such recognised specifications acceptable to Engineer-in-charge as equivalent

there

to or absence of such authorised specification.

(d) such requirement test and/or analysis as may be specifed by the Engineer-in-charge in

order

of precedence given above.

ii) The Contractor shall at his risk and cost make all arrangements and/or shall provide

all such facilities as the Engineer-in-charge may require for collecting, preparing

required number of samples for test or analysis at such time and to such places as may

be directed by Engineer and bear all such charges. Such samples shall also be

deposited with Engineer-in-charge.

iii) The contractor shall if and when required submit at his cost the samples of materials

to be tested or analysed and if so directed, shall not make use of or incorporate in the

work any materials represented by the samples until the required tests or analysis

have been made and the materials, finally accepted by the Engineer-in-charge.

iv) The contractor shall not be eligible for any claim or compensation either arising out of

any delay in the work or due to any corrective measure required to be taken on

account of and as a result of testing of the materials.

v) The contractor or his authorised representative will be allowed to remain present in

the departmental alboratory while testing samples furnished by him. However, the

results of all the tests carried out in the departmental laboratory in the presence of

absence of the contractor or his authorised representative will be binding on the

contractor.

vi) The contractor shall at his own cost set up laboratory to carry out the routine tests of

materials which are to be used on the work. The tests will have to be carried out

eighter in his field laboratory or in an approved laboratory. In case tests are carried

out in field laboratory, atleast 50% test should be caried out in nearest quality control

laboratory for the Department.

vii) In case of material procured by the contractor, testing as required by the codes and

specifications shall be arranged by him at his own cost. Testing shall be done in the

presence of authorised representative of the Engineer-in-charge at the nearest

approved laboratory. If additional testing other than as required by specification is

ordered, the testing charges, shall be borne by the Department, if the test results are

satisfactory and by the contractor if the same are not satisfactory.

Page 67: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 67 –

Sign of Contractor No of corrections Secretary SPSM

viii) In case of materials supplied by the SPSM if the contractor demands certain testing,

the charges thereof shall be paid by the contractor if the testing results are satisfactory

and by the Department if the same are not satisfactory.

(26) CHANGE OF CEMENT CONTENTS ETC. :-

The tendered rated for any item, involving the use of cement shall apply to the

quantity of cement specified for the mix for that item in the specifications. If for any reasons,

except those required for compensating the deficencies, in the components, the cement

content and properties are altered by the Engineer (Engineer-in-charge) at any time or from

time to time the tendered rates for the particular item and quantity or quantities, shall be duly

enhanced or reduced only to account for the addition or reduction in cost of the cement

content from that laid down in the specification at the rates specified in the Schedule 'A' of

the contract plus 10% to cover all other incidental charges whatever. Likewise if any

additives compounds water proofing materials etc. are ordered by the Engineer to be added to

the mortar or concrete, no extra rate shall be paybale for this change which shall be carried

out as per direction of the Engineer-in-charge, provided cost of such additives etc. is borne

by SPSM. or these are supplied free of costs to contractor at site by the SPSM.

(27) CEMENT CONCRETE :-

27.1 General :

a) All concrete shall be controlled concrete and machine mix unless otherwise directed

by Engineer-in charge. For controlled or High grade concrete, the grading of

aggregates shall be got approved from the Engineer.

b) The correct proportions and the total amount of water for the mix will be determined

by means of preliminary tests and shall be got approved by the Engineer. However,

such approval does not relieve the Contractor from his responsibility regarding the

minimum works strength requirements. Work test shall be taken in accordance with

relevancodes specifications.

All proportioning of aggregates shall be done by weight if so ordered by the Engineer.

c) All mixing shall be done by mechinical means in approved mixers. the Engineer may

at his discretion, allow in writing hand mixing of concrete for minor items where

small quantities are involved but in that case the Contractor shall increase the cement

content of the mixure by 10% without any extra cost.

d) The form work used shall be made preferably of steel or with lining of steel. Wooden

shuttering may be allowed at the discretion of the Engineer e.g. lintels small slabs and

beams coping etc.

e) The concrete shall be machincally vibrated for proper compaction by the method

approved by the Engineer.

Page 68: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 68 –

Sign of Contractor No of corrections Secretary SPSM

f) The concrete shall be cured only by a sweet potable water for full 21 days after the

time or the period specified in the detailed specification or as may be directed by

Engineer-in-charge.

27.2 FORM WORK AND STAGING FOR BRIDGE STRUCTURES :-

27.2.1 For bridge structure, forms for concrete shall be constructed of mild steel plates or

marine plywood and be of substantial and rigid construction true to shape and dimensions

shown on the drawings. Where metal forms are used all bolts and rivets shall be counter sunk

and well ground to provide a smooth plane surface.

27.2.2 Forms shall be morter tight and shall be sufficiently rigid by the use of ties and

brancings to prevent any displacement or sagging between supports. They shall be strong

enough to withstand all pressure, ramming and vibration, without deflection from the

prescribed lines occuring during and after placing the concrete and shall be tight enough to

prevent any appreciable loss of concrete during vibration.

Screw jacks or hard wood wedges where required shall be provided to make up any

settlement in the form work before or during the placing of concrete. 27.2.3 Schedule cmber shall be provided in horizontal members of structures, specially in

long spans to counter act the effects of any deflection. The form work shall be so fixed as to

provided for such camber.

27.2.4 Forms shall be so constructed as to be removal in sections in the desired sequence,

without damaging the surface of concrete or disturbing other sections.

27.5 NUMBER OF SETS OF STAGING AND SHUTTERING AND EQUIPMENT.

(FOR BRIDGE WORKS ONLY)

In order to ensure completion of bridge within the stipulated period, the contractor

shall have to arrange a minimum number of sets of staging and shuttering as well as

equipment of the required size for different components as stipulated hereunder :-

i) for well (a) Staging and ---------------- sets.

foundations shuttering.

(b) Equipments ---------------- sets.

ii) For other (a) Staging and ---------------- sets.

items of shuttering.

substructure (b) Equipments ---------------- sets.

iii) For super (a) Staging and ---------------- sets.

structure. shuttering.

(b) Equipments ---------------- sets.

Use of slip form shuttering wherever feasible will be preferred.

27.2.6 Forms shall be construced so as to be removable in sections in the desired sequence

without damaging the surface of concrete or distrubing other sections.

Page 69: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 69 –

Sign of Contractor No of corrections Secretary SPSM

(28) MISCELLANEOUS :-

1. Rate shall be inclusive of S.T., General Tax and other Taxes etc.

2. For providing electric wiring or water lines etc. recesses shall be provided if

necessary through walls, slabs, beamss etc. and later refilling up with bricks or stone

chipping, cement mortar without any extra cost.

3. In case it becomes necessary for the due performance of the contract for the

Contractor to occupy land outside the Department limits the Contractor will have to

make his own arrangements with the land owners and to pay such rents if any are

payable as mutually agreed between them.

The Department will afford the Contractor all the reasonable assistance to enable him

to obtain Government land for such purpose on usual terms and conditions as per

rules of Government, if such land is available.

4. The special provision in detailed specifications or wording of any item shall gain

precedence over corresponding contradictory provision (if any) in the standard

specifications of P.W.D. Hand Book, where reference to such specifications is given

without reproducing the details in contract.

5. Suitable separating Barricades and enclosures shall be provided to separate material

brought by contractor and material issued by SPSM to contractor under Schedule 'A'

Same applies for the material obtained from different sources of supply.

6. The stacking and storage of construction material at site shall be in such manner as to

prevent deterioration or infusion of foreign matter and to ensure the preservaion of

their quality, properties and fitness for the work. Suitable precautions shall be taken

by the Contractor to protect the material against atmospheric actions, fire and other

hazards. The materials likely to be carried away by wind shall be stored in suitable

stores or with suitable baricades and where there is likelyhood of subsidence of soil,

such heavey materials shall be store on platforms.

7. For Road and Bridge works the contractor shall in additon to the specifications cited

here comply with requirements of relevent I.R.C. code practice.

8. The Contractor shall be responsible for making good the damages done to the existing

properity during construction by his men.

9. If it is found necessary from safety point of view to test any part of the structure the

test shall by carried out by the Contractor with the help of Department at his own cost.

10. Defective work is liable to be rejected at any stage. The contractor, on no account can

refuse to rectify the defects merely on reasons that further work has been carried out.

No extra payment shall be made for rectification.

11. In the Schedule 'B' the work has been divided in to sections but notwithstanding this,

every part of it shall be deemed supplementary to and complementary of every other

part.

12. General directions or detailed description of work, materials and items coverage of

rates given in the specification are not necessarily repeated in the Bill of Quantities.

Reference is, however, drawn to the appropriate section clause(s) of the General

Specifications in accordance with which the work is to be carried out.

Page 70: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 70 –

Sign of Contractor No of corrections Secretary SPSM

13. In the absence of specific directions to the contrary the rates and prices inserted in the

items are to be considered as the full inclusive rates and prices for the finished work

described thereunder and are to cover all labour, materials, westage, temporary work

plant overhead charges and profits, as well as the general liabilities, obligations and

risks arising out of the General Conditions of Contract.

14. The quantities set down against the item in the Schedule 'B' are only estimated

quantities of each kind of work included in the Contract an are not to be taken as a

guarnatee that the quantities scheduled will be carried out or required or that they will

not be exceeded.

15. All measurements will made in accordance with the methods indicated in the

specification and read in conjunction with the General Conditions of Contract.

16. The details shown on drawings and all other information pertaining to the work shall

be treated a indicative and provisional only and are liable to variation as found

necessary while preparing working drawing which will be supplied by the

Government during execution. The contractor shall not, on account of such variation

be entitled to any increase over the ones quoted in the tender which are on quantity

basis.

17. The recoveries if any due from contractor will be effected as arrears of land revenue

through the Collector of the District.

18. Clause 101 to 107 of Specifications of Road Bridges work adhered herewith will be

applicable to works as per Schedule 'B' unless specified otherwise in the detailed

specifications of the relevant items.

19. All materials used in the construction shall conform to the requirement of

Sepcification Clause under Section 1000 "Materials for Structures" of Specification of

Road and Bridge work M.O.S.T. New Delhi 1990 Edition.

20. Extranous materials and steps to minimise dust nuisance during construction shall be

as per clause 111 of MOST Specification (Second Edition 1990).

PROTECTION OF UNDERGROUND TELEPHONE CABLE & AERIAL

TELEPHONE WIRES & POLES, TRANSMISSION TOWERS, ELEC.

CABLES AND WATER SUPPLY LINES :- During the execution of work it is likely that the contractor may meet with telephone

cables, electrical cable, water supply lines etc. it will, therefore, be the responsibility of the

contractor to protect them carefully. All such cases should be brought to the notice of the

Engineer-in-charge by the contractor and also to the concerned Department. Any damage

what-so-ever done to these cables and pipe lines by the contractor shall be made good by him

at his cost.

29. MEDICAL & SANTITARY ARRANGEMENTS TO BE PROVIDED FOR

LABOUR EMPLOYED IN THE CONSTRUCTION BY THE CONTRACTOR:-

(a) The contractor shall provide an adequate supply of water for the use of labour on

work and in camps.

Page 71: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 71 –

Sign of Contractor No of corrections Secretary SPSM

(b) The contractor shall construct trench or semi-permanent latrines for the use of the

Labours. Seperate latrines shall be provided for men and women.

(c) The Contractor shall build sufficient number of huts on a suitable plot of land for use

of the labourers according to the following specifications :-

1) Huts of Bamboos and Grass may be constructed.

2) A good site not liable to submergence shall be selected on high ground

remote from jungle but well provided with trees, shall be chosen

wherever it is available. The neighbourhood of tank, jungle, grass or

wood should be particularly avoided. Camps should not be established

close to large cutting of earth work.

3) The lines of huts shall have open spaces of atleast ten yards between

rows. When a good natural site cannot be procurred, particular

attention should be given to the drainage.

4) There should be no over crowding. Floor space at the rate of 3- sq. ft.

per head shall be prodived. Care should be taken to see that the huts are

kept clean and in good order.

5) The contractor must find has own land. If he wants Government land,

he should apply for it and pay assessment for it, if made available by

SPSM 6) The contractor shall construct a sufficient number of bathing places.

Washing places should also be provided for the purpose of washing

cloths.

7) The contractor shall make sufficient arrangements for draining away

the surface and sullage water as well as water from the bathing and

washing places and shall dispose off this waste water in such way as

not to cause any nuisance.

(d) The contractor shall engage a Medical Officer with a travelling dispensary for a Camp

containing 500 or more persons if there is no SPSM. of other private dispensary

situated within 8 KMs from the camp. In case of emergency the contractor shall

arrange at his cost of transport for quick medical help to his sick worker.

(e) The contractor shall provide the necessary staff for effecting satisfactory drainage

system and cleanliness of the camp to the satisfaction of the Engineer. Atleast one

sweeper per 200 persons should be engaged.

(f) The Assistant Director of Public Health shall be consulted before opening a labour

camp and his instructions on matters such as water supply, sanitary conveniences, the

camp site accommodation and food supply shall be followed by the contractor.

(g) The contractor shall make arrangements for all antimalaria measures to be provided

for the labours employed on the work. The antimalaria measures shall be provided as

directed by the Assistant Director of Public Health.

(30) SAFTY CODE :-

Page 72: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 72 –

Sign of Contractor No of corrections Secretary SPSM

Suitable scaffolds shall be provided for workmen for all works shat can not safely be

done from the ground, or from soild construction except such short period work as can be

done safely from ladders. When ladder is used an extra mazdoor shall be engaged for

holding the ladder and if the ladder is used for carrying materials as well suitable footholds

and handholds shall be provided on the ladder and the ladder shall be given an inclination not

steeper than 1 to 4 (1 horizontal and 4 vertical).

Scaffolding or staging more than 3.25 metres above the ground or floors, swing or

suspended from an overhead surport or erected with stationary supports, shall have a guard

rail properly attached, bolted braced and otherwise assured at least one metre high above the

floor or platform of such scanffolding or stagging and extending along the entire length of the

outside and ends thereof with only such openings as may be necessary for the delivery of

materilas. Such scaffolding or staging shall be so fastened as to prevent it from swaying from

the building or structure.

Working platform gangways, and stairways shall be so constructed that they do not

sagunduly or is more than 3.25 metres above ground level or floor level, it shall be closely

boarded, have adequate width and be suitably fenced as described in 2 above. Every opening in floor of the building or a working platform shall be provided with

suitable protection to prevednt fall of persons or materials be providing suitable fencing or

railing with minimum height of 1 metre.

Sefe means of access shall be provided to all working platform and other working

places. Every ladder shall be securely fixed No protable single ladder shall be over 9 metres

in length, width between side rails in arung ladder shall in no case be less than 30 cms. for

ladders upto and including 3 metres in length. For longer ladders this width shall be

increased atleast 6 mm for each additional 30 cms. of lenght Uniform step spacing shall not

exceed 30 cms.

Adequate precautions shall be taken to prevent danger from electrical equipment. No

materials on any of the sites shall be stacked or placed as to cause danger or inconvenience to

any person or the public. The Contractor shall provide all necessary fencing and lights to

protect public from accident and shall be bound to bear expenses of defence of every suit,

action or other proceedings as law that may be brought by any person for injury sustained

owing to neglect of the above precaution and to pay any damages and costs which may be

awarded in any such suit action or proceedings to any such person or which may with the

consent of the contractor, to be paid to compromise any claim by any such person.

EXCAVATION AND TRENCHING :-

All trenches, 1.5 meters or more in depth, shall at all times be supplied with at least

one ladder for each 30 metres in length or fraction thereof. Ladder shall be extended from

bottom of trench to at least 1 metre above surface of the ground, sides of a trench which is 1.5

metres or more in depth shall be stepped back to give suitable slope, or security held by

timber bracing, so as to avoid the danger of side collapsing. Excavated materials shall not be

placed within 1.3 meters of edge of trench or half of depth of trench whichever is more.

Page 73: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 73 –

Sign of Contractor No of corrections Secretary SPSM

Cutting shall be done from top to bottom under no circumstances shall undermining or under

cutting be done.

DEMOLITION :-

Before any demolition work is commenced and also during the process of the work :-

a) All roads and open areas adjacent to the work site shall either be closed or suitably

protected.

b) No electric cable or apparatus which is liable to be a source on danger or a cable or

apparatus used by operator shall remain electrically charged.

c) All practical steps, shall be taken to prevent danger to person employed, from risk or

fire or explosion or hooding. No floor, roof or other part of a building shall be so

overloaded with debris of materials as to render it unsafe.

All necessary personal safety equipment as considered adequate by the Engineer-in-

charge shall be available for use of persons employed on the site and maintained in a

condition suitable for immediate use and the contractor shall take adequate step to ensure

proper use of equipment by those concerned.

A) Workers employed on mixing asphaltic materials, cement, lime morters, concrete

shall be provided with protective footwear and protective goggles.

B) Those engaged in handing any materials, which is injurious to eyes shall be provided

with protective goggles.

C) Those engaged in welding works shall be provided with welder's protective

eyeshields.

D) Stone breakers shall be provided with protection roggles and protective clothing and

seated at sufficiently safe intervals.

e) When workers are employed in sewers and menholes which are in use, the contractor

shall ensure that manhole covers are opened and manholes are ventilated at least for

an hour before workers are allowed to get into them. Manholes opened shall be

cordened off with suitable railing and provided with warning signals or boards to

prevent accident to public.

f) The Contractor shall not employ. men below the age of 18 and women on the work

of painting with products containing lead in any form. Wherever men above the age

of 18 are employed on the work of lead painting the following precautions shall be

taken.

(i) No paint containing lead of lead product shall be used except in the

form of paste or ready made paint.

Page 74: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 74 –

Sign of Contractor No of corrections Secretary SPSM

(ii) Suitable face masks shall be supplied for use by workers when paint is

applied in the form of spray or a surface having lead paint dry rubbed

and scraped.

(iii) Over alls shall be supplied by the Contractor to workmen and adequate

facilities shall be provided to enable working painters to wash during

and on cessation of work.

g) When work is done near any place where there is risk of drowning all necessary

equipment shall be provided and kept ready for use and all necessary steps taken for

prompt rescue of any person in danger and adequate provision made for prompt first

aid treatment of all injuries likely to be sustained during the course of the work.

Use of hoisting machines and shackle including their attachments, anchorage supports

shall confirm to the following :-

a) (i) These shall be of good machanical construction round materials and

adequate strength and free from potent defects and shall be kept in good repair

and in good working order.

(ii) Every rope used in hoisting or lowering materials or as a means of

suspension shall be of durable quality and of adequate strength and free from

potent defects.

b) Every crane driver or hoisting appliance operator shall be properly qualified and not

person under the age of 21 years shall be incharge of any hoisting machine including

any scaffolding.

c) In case of every hoisting machine and of every chain ring hook, shackle ownel and

pulley block used in hoisting or lowering or as means of suspension safe working load

shall be ascertained by adequate means. Every hoisting machine and all gear referred

to above shall be painly marked with safe working load.

In case of a hoisting machine having a variable safe working load, each safe working

load and the conditions under which it is applicable shall be clearly indicated. No part

of any machine or any gear referred to above in this paragraph shall be loaded beyond

safe working load except for the pupose of testing.

d) In case of departmental machines safe working load shall be notified by the Engineer-

in-charge. At regards contractor's machines the contractor shall notify safe working

load of each machine to the Engineer-in-charge whenever, he brings it to site of work

and get it verified by the Engineer-in-charge.

Motors, gearing, transmission, electric wiring and other dangerous parts of hoisting

appliances shall be provided with such means as will reduce to the minimum risk of

accidental descent of load. Adequatge prcautions shall be taken to reduce to the minimum

the risk of any part of a suspended load becoming accidentally displaced, when workers are

employed. On electrical installations which are already enargised insulating materials

wearing approved such as gloves, sleaves and coats as may be necessary, shall be provided.

Workers shall not wear any rings, watches and carry keys or other materials which are good

conductors of electicity.

All scaffolds, ladders, and other safety decices mentioned or described hereing shall

be maintained in a safe condition and no scaffold ladder or equipment shall be altered or

removed while it is in use. Adequate washing facilites shall be provided at or near places of

work.

Page 75: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 75 –

Sign of Contractor No of corrections Secretary SPSM

These safety provisions shall be brought to the notice of all concerned by display on a

notice board at a prominent place at the work spot. Persons responsible for ensuring

complaince with the safety code shall be named therin by the contractor.

i) To ensure effective enforcement of the rules and regulations relating to

safety precautions, arrangements made by the contractor shall be open to

inspection by the Engineer-in-charge or his representatives and the inspecting

officers.

ii) Failure to comply with the provision hereunder shall make the

contractor liable to pay to the Department as penalty an amount not exceeding

Rs.50/- for each default and decision of the Engineer-in-charge shall be final

and binding.

Not with standing the above conditions 1 to 14 the contractor is not exempted from

the operation of any other Act or Rules inforce.

31) SCOPE OF RATES FOR DIFFERENT ITEMS OF WORK :-

For item rate contracts, the contract unit rates for differ erent items of work shall be

payment in full for completing the work to the requirements of the specifications including

full compensation for all the operations detailed in the relevant sections of these

Specifications under "Rates". In the absence of any directions to the contrary, the rates are to

be considered as the full inclusive rate for finished work covering all labour, materials,

wastage, temporary work, plant, equipment, overhead charges and profit as well as the

general liabilities, obligations and risks arising out of the General Conditions of Contract.

The item rates quoted by the Contractor shall, unless otherwise specified, also include

compliance with/supply of following :-

i) General works such as setting out, clearance of site before setting out and clearance

of works after completiong.

ii) A detailed programme for the construction and completion of the works (using

CPM/PERT techniques) giving, in addition to construction activities, detailed

network activities for the submission and approval of materials, procuremnt of critical

materials and equipment, fabrication of special production/equipments and their

installation and testing and for all activities of the Employee that are likely to effect

the progress of work, etc. including updating of all such activities on the basis of the

decisions taken at the periodic site review meeting or as directed by the Engineers.

iii) Sample of various materials proposed to be used on the work for conducting tests

thereon as required as per the Provisions of the Contract.

iv) Design of mixes as per the relevant clauses of the Specifications giving proportions of

ingredients, sources of aggregates and binder along with accopanying trial mixes as

per the relevant Clauses of these specifications to be submitted to the Engineer for his

approval before use of the works;

v) Detailed design calculations and drawings for all Temporary Works (such as

formwork, staging, centering, specialised constructional handling and launching

equipment and the like);

Page 76: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 76 –

Sign of Contractor No of corrections Secretary SPSM

vi) Detailed drawings for templates, support and end anchorage, details for prestressing

cable profiles, bar bending and cutting schedules for reinforcement, material lists for

fabrication of structural steel etc.

vii) Mill test reports for all mild and high tensils steel and cast steel as per the relevant

provisions of the Specifications;

viii) Testion of various finished items and materials including bitumen, cement, concrete,

bearings as required under these specifications and furnishing test reports/certificates;

ix) Inspection Reports in respect of formwork, staging reinforcement and other items of

work as per the relevant Specification;

x) Any other data which may be required as per these Specifications or the Conditions of

Contract or any other annexures/schedules forming part of the contract.

xi) Any other item of work which is not specifically provided in the Bill of Quantities but

which is necessary for complying with the provisions of the Contract; and

xii) All temporary works, formwork and false work.

Portions of road works beyond the limits and or any other work may be got constructed by

the Employee directly through other agencies. Accordingly, other agencies employed by the

Emplyer may be working in the vacinity of the work being executed by the Contractor. The

Contracctor shall liaise with such agencies and adjust his construction programme for the

completion of work accordingly and no claim or compensation due to any reason whatsoever

will be entertain on this accout. The Employer will be indemnified by the Contractor for any

claims from other agencies on this account.

32) PAYMENTS :-

a) Running Bills :-

One payment in a month will be granted by the Engineer-in-charge if the progress is

satisfactory. Contractor should submit bill to the Engineer-in-charge in appropriate forms.

b) Final Bill :-

The Contractor should submit final bill within one month after completion of the

work and the same will be paid within 3 months if it is in order. Disputed item and claims if

any shall be excluded from the final bill and settled separately later on.

33) HANDING OVER OF WORK :-

All the works and materials before finally taken over by SPSM., will be the entire

liability of the contractor for guarding, maintaining and making good any damage of any

magnitude. Interim payments made for such work will not alter this position.

34) CLAIMS :-

Page 77: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 77 –

Sign of Contractor No of corrections Secretary SPSM

Bills for extra work for any claim shall be paid seperately apart from the interim bills

for the main work. The payment of bills for the main work shall not be withheld for want of

decision on the extras or claims not covered in the appendices.

Claims for extra work shall be registered within 30 days of occurance of the event.

However, bills for these claims including supporting data/details may be submitted

subsequently.

35) QUALITY ASSURANCE AND MAINTENANCE :-

(for works costing more than 100 lakhs)

1) Ensure the specified quality of work which will also include necessary surveys,

temporary works etc. the contractor shall prepare a quality assurance plan and get the same

approved from the engineer-in-charge with in one month from the date of work order. For the,

the contractor shall submit and organisation chart of his technical personeel to be delayed on

the work alongwith their qualification, job descriptions defining the functions of reporting

supervision inspecting and approving. The contractor shall also submit a list of tools,

equipment and the machinery and instrumentation which he proposes to use for the

construction and for testing in the field and/or in the laboratory and monotoring. The

contractor shall modify/supplement the organisation chart and the list of machinery,

equipment etc. as per the directions of the University Engineer and shall deploy the

personnel and equipment on the field asper the approved chart and list respectively. The

contractor shall submit written method statements detailing his exact proposals of execution

of the work in accordance with the specification. He will have to get these approved from the

Engineer-in-charge. The quality of the work shall be properly documented through certificate,

records, check-lists and log books of results etc., Such records shall be complied from the

beginning of the work and be continuously updated and supplemented and this will be the

responsibility of the contractor. The forms should be got approved from the Engineer-in-

charge.

2) Where the work is to be done on lumpsum basis on contractor's design the

contractor shall also prepare and submit a maintenance manual giving procedure

for maintenance, with the periodicity of maintenance work including inspections,

tools and equipment to be used, means of accessibility for all parts of the structure.

He shall also include in the manual, the specifications for maintenance work that

would be appropriate for his design and technique of construction. This manual

shall be submitted withing the contract period.

Page 78: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 78 –

Sign of Contractor No of corrections Secretary SPSM

SCHEDULE 'B' Memorandum showing items of work to be carried out

Sr.

No. Item of

work Quantities

estimated

but may be

more or less

Estimated rates Unit Total

Amount

according

to

estimated

quantities In figures In

word

s

1 2 3 4

Separately

Attached

5

6 7

As per separate sheets in Chapter No. 10

Note 1: All work shall be carried out as per Public works Department Hand Book and

Standard Specification of the Division or as directed and as per specifications given in

Chapter No. 11

Page 79: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 79 –

Sign of Contractor No of corrections Secretary SPSM

Note 2: Rates quoted include clearance of site(Prior to commencement of work and at its

close) in all respect and hold good for work under all site condition, moisture whether etc.

Page 80: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 80 –

Sign of Contractor No of corrections Secretary SPSM

SCHEDULE-B

Name of Work :

Construction of First Floor of English Medium School for SPSM at Central Campus,MPKV, Rahuri.

I.NO

ITEM OF WORK E Quantities

estimated

but may be

more or

less

Estimated rates UNIT

Total

Amount

according to

estimated

quantities

PWD Specification

No.

In figures In words

,1 ,2 ,3 ,4 ,5 ,6 ,7 ,8

1 Dismantling brick masonry in lime or cement

mortar and stacking the materials as directed with

all leads,lifts, complete.

8.26

153.00 Rs.one hundred fifty

three only

Cu.M. 1263.78 As directed by

Engineer-In-Charge

2 Dismantling the R.C.C. work 1:2:4 and sorting out

the materials such as steel etc. as directed and

stacking them within the specified lead as directed.

Spec. No.: As directed by Engineer in charge.

1.85 753.00 Rs. Seven hundred

fifty three only

Cu.M. 1393.05 As directed by

Engineer-In-Charge

3 Dismantling G.I. and A.C. sheet roof covering and

stacking them as and where directed in the

compound, including scaffolding etc. complete.

Spec. No.: BdW- 8

Page No. 587

25.20 21.00 Rs. Twenty one only Sq.m 529.20 BdW- 8, Page No. 587

4 Removing purlin from room including stacking as

directed etc.complete.

22.50 10.00 Rs. ten one only Rmt 225.00 As directed by

Engineer-In-Charge

Page 81: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 81 –

Sign of Contractor No of corrections Secretary SPSM

5 Providing Gas or Electrical welding for structural

steel section, plates including rebaring of 16mm

dia steel bar for column section as per detailed

drawing. For less than 10 mm thick section. Spec.

No.: B.18, Page No 78

2160.00 8.00 Rs. eight one only Cm. 17280.00 B.18, Page No 78

6 Dismantling doors and windows shutters without

frame and stacking the materials as directed with

all leads, lifts etc. complete. Spec. No.: BdW- 8

Page No. 587

1.00 37.00 Rs. Thirty seven one

only

No 37.00 BdW- 8 Page No. 587

7 Conveying the dismantled material from the work

site of 1km away and including all lead,lift

transportation charges etc.complete

10.11 112.00 Rs. one hundred

twelve only

Cu.M. 1132.32 As directed by

Engineer-In-Charge

8 Providing and casting in situ cement concrete M20

grade, of trap / granite / quartzite / gneiss metal for

R.C.C. columns as per detailed designs and

drawings or as directed, including dewatering,

centering form-work, compacting, finishing the

formed surface with cement mortar 1: 3 of

sufficient minimum thickness to give a smooth

and even surface or roughening if special finish is

to be provided and curing (excluding steel

reinforcement).

21.04 7437.00 Rs. Seven thousand

four hundred thirty

seven only

Cu.M. 156474.48 Bd.F.5 Page No. 300

and B.7, Page.No. 38

9 Providing and casting in situ cement concrete, of

trap / granite / quartzite / gneiss metal for R.C.C.

beams and lintels, as per detailed designs and

drawings or as directed, including dewatering

centering, form-work, compaction finishing the

formed surfaces with cement mortar 1 : 3 of

sufficient minimum thickness to give a smooth

and even surface or roughening if special finish is

to be provided and curing (excluding steel

37.18 7515.00 Rs. Seven thousand

five hundred fifteen

only

Cu.M. 279407.70 Bd.F.6 Page No. 300

and B.7, Page No.38

Page 82: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 82 –

Sign of Contractor No of corrections Secretary SPSM

reinforcement).

10 Providing and casting in situ cement concrete

M20grade, of trap / granite / quartzite / gneiss

metal for R.C.C. slabs and landings as per detailed

designs and drawings including centering, form-

work, compacting, finishing, the formed surfaces

with cement mortar 1 : 3 of sufficient minimum

thickness to give a smooth and even surface or

roughening them if special finish is to be provided

and curing (excluding steel reinforcement).

47.02 7797.00 Rs. Seven thousand

seven hundred

ninety seven only

Cu.M. 366614.94 Bd.F.8 Page No. 302

and B.7, Page No.38

11 Providing and casting in situ cement concrete M

20 grade, of trap / granite / quartzite / gneiss metal

for R.C.C. Waist Slabs as per detailed designs and

drawings including centering, form-work,

compacting, finishing, the formed surfaces with

cement mortar 1 : 3 of sufficient minimum

thickness to give a smooth and even surface or

roughening them if special finish is to be provided

and curing (excluding steel reinforcement).

4.28 7876.00 Rs. Seven thousand

eight hundred

seventy six only

Cu.M. 33709.28 Bd.F.8 Page No. 302

and B.7, Page No.38

Page 83: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 83 –

Sign of Contractor No of corrections Secretary SPSM

12 Providing and casting in situ cement concrete M-

20 grade, of trap / granite / quartzite / gneiss metal

for R.C.C. pardi / wall upto 150 mm. thick,

including centering, formwork, compacting,

finishing the formed surfaces with cement mortar

1 :3 of sufficient minimum thickness to give a

smooth and even surface or roughening them if

special finish is to be provided and curing

(excluding steel reinforcement).

3.26 9492.00 Rs. nine thousand

four hundred ninety

two only

Cu.M. 30943.92 Bd.F.11 Page No. 304

and B.7, Page No. 38

13 Providing and casting in situ cement concrete M20

trap / granite quartzite/ gneiss metal for step

including centering form work, compacting,

covering newly laid concrete by gunny bag,,

plastic or tarpaulin, roughening them if special

finish is to be provided and curing and finishing if

required etc. complete ( The cement mortar 1:3

plaster is considered for rendering uneven and

honeycombed surface only. Wooden planks /

shuttering will not be allowed)

2.27 9492.00 Rs. nine thousand

four hundred ninety

two only

Cu.M. 21546.84 Bd. F. 12 Page No. 304

& B-7, Pg 38

14 Providing and casting in situ cement concrete M-

20 grade, of trap / granite / quartzite / gneiss metal

for R.C.C. chajja as per design including

centering, formwork, compacting, finishing the

formed surfaces with cement mortar 1 :3 of

sufficient minimum thickness to give a smooth

and even surface or roughening them if special

finish is to be provided and curing (excluding steel

reinforcement).

3.24 7876.00 Rs. nine thousand

eight hundred

seventy six only

Cu.M. 25518.24 Bd.F.9 Page No. 303

and B.7, Page No.38

Page 84: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 84 –

Sign of Contractor No of corrections Secretary SPSM

15 Providing and fixing in position mild / TMT steel

of Fe 500/550 bar reinforcement of various

diameters for R.C.C. pile caps, footings,

foundations, slabs, beams, columns, canopies,

staircases, newels, chajjas, lintels, pardis, copings,

fins, arches, etc., as per detailed designs, drawings

and schedules including cutting, bending, hooking

the bars, binding with wires or tack welding and

supporting as required completed.

11.84 56004.00 Rs. Fifty six thousand

four only

M.T. 663087.36 No.: BdF-17 Page No.

306

16 Providing second class Burnt Brick masonry with

conventional / I.S. type bricks in cement mortar 1 :

6 in superstructure, striking joints on unexposed

faces, raking out joints on exposed faces and

watering, etc., complete.

67.76 6710.00 Rs.six thousand

seven hundred ten

only

Cu.M. 454669.60 Bd.G. 1 Page No. 313

17 Providing sand cement, sand faced plaster

exterenally sponged finished in two coats, first

coat in C.M. 1:4 mix, using Kharsalia / Kasaba or

similar type of sand, approx. 15 mm. thick using

waterproofing compound at 1Kg. / cement bag and

second coat in C.M. 1:4 mix., approx. 6 to 8 mm.

thick, including working in door and window

jambs, crevices drip moulds, bands, soffits,

scaffolding, curing, roughening the first coat to

receive second coat, etc., complete.

1049.74 328.00 Rs. three hundred

twenty eight only

Sq.m 344314.72 Bd.L.7 Page No. 369

18 Providing internal cement plaster 20 mm. thick

in two coats in cement mortar 1 : 4 without neeru

finish to concrete or brick surfaces, in all

positions, including scaffolding, curing, etc.,

complete.

1123.05 229.00 Rs. two hundred

twenty nine only

Sq.m 257178.45 Bd.L.4 Page No. 368

Page 85: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 85 –

Sign of Contractor No of corrections Secretary SPSM

19 Providing neeru finish to plastered surfaces in all

positions except ceiling, including scaffolding,

curing, etc., complete.

1123.05 29.00 Rs. twenty nine only SQ.M 32568.45 Bd.L.10, Page No.370

20 Providing internal cement plaster 12 mm. thick

in single coat in cement mortar 1 : 3 without neeru

finish to concrete surfaces, in all positions,

including scaffolding,providing groove at joint of

brick masonry and concrete members if necessary

curing, etc., complete.

368.76 154.00 Rs.one hundred fifty

four only

Sq.m 56789.04 Bd.L.2 Page No. 368

21 Providing neeru finish to plastered surfaces for

ceiling, including scaffolding, curing, etc.,

complete.

368.76 29.00 Rs. twenty nine only SQ.M 10694.04 Bd.L.10, Page No.370

22 Providing and laying polished kotah stone

flooring 25 to 30 mm thick and of a required

width in plain/diamond pattern on abed of 1:6

cement mortar including neat cement float, filling

joints with neat coloured cement slurry, curing,

polishing and cleaning etc.complete.(Including

cost of Mirror polishing)

387.90 1110.00 Rs . One thousand

one hundred ten

only

Sq.m 430569.00 Bd.M.3 Page No. 380

23 Providing and fixing in required positions skirting

of polished Kotah stone slab 25 to 30 mm thick

and of required width on 1:2 lime plaster / 1 : 4

cement plaster including cement float , filling

joints with cement slurry , curing rubbibg

polishing and cleaning complete (Including cost

of Mirror polishing)

31.89 1110.00 Rs . One thousand

one hundred ten

only

Sq.m 35397.90 BdM - 5 Page No. 381

Page 86: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 86 –

Sign of Contractor No of corrections Secretary SPSM

24 Providing and laying polished Kotah stone 20 to

25 mm thk. For treads and risers of steps and

staircases,with rounded nosing for the treads on a

bed of 1:4 cement mortar including cement

float,filling joints with neat cement

slurry,curing,polishing and cleaning

complete.(Including cost of Mirror polishing)

21.33 920.00 Rs . nine hundred

twenty only

Sq.m 19623.60 Bd.M.22 Page No. 390

25 Providing sills of polished kotah stone 40 to 50

mm thk.with machine polished surface on bed of

cement mortar 1:4 including neat cement float

filling joints with neat cement float filling joints

with neat cement slurry tomatch the colour of

slabs,curing,polishing and rounding

edges,cleaning etc.complete.(one side polished)

7.20 920.00 Rs . nine hundred

twenty only

Sq.m 6624.00 Bd.M.22 Page No. 390

26 Providing and fixing black Kadappa stone sill

steps,laboratory platforms of 25 to 30mm mm.

thick machine polished, cutting rounding corners,

laying in position jointing with neat cement slurry

on cement mortar bedding in cement mortar 1:4

proportion, curing etc. complete. Additional Item

Spec. No. : As directed by Engineer in charge.

(both side polished)

28.80 954.00 Rs . nine hundred

fifty four only

Sq.m 27475.20 Bd.M.22 Page No. 390

Page 87: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 87 –

Sign of Contractor No of corrections Secretary SPSM

27 Providing and fixing mild steel grill railing

weighing 20 kg / sqm. with teak wood hand rail of

size 75mm.x 60 mm. and sill of 75mm.x 25 mm.

and newel posts for staircases, including

fabricating, fixtures, erecting, painting the grill

work with one coat of anticorrosive paint and two

coats of oil painting with approved colour and

polishing the sill, hand rail and the newel post with

French polish. Spec. No. : Bd.U.2 Page No. 537

(As detailed design and drawing)

35.65 2039.00 Rs .two thousand

thirty nine only

sqm 72690.35 Bd.U.2 Page No. 537

28 Supplying & fixing in position powder coated

alluminium extruded section three tack sliding

windows upto 1.5 m.height,outer frame made

from section of overall size 92x45 mm,bottom

section with or without drains track section

weighing 0.901 kg/m and top and side section

weighing 0.838 kg/m with shutters of sections

made of 19x40 mm size having average weight of

0.6 kg/m(or as per required size with change in

proportionate weight)with 5.5 mm selected quality

plain sheet glass fixed with nylon encased

stainless rollers,necessary locks and handles etc.

complete.(As detailed design and drawing)

57.60 4335.00 Rs four thousand

thousand three

hundred thirty five

only

sqm 249696.00 As directed by

Engineer-In-Charge

29 Providing and fixing pressed steel door box

frame of Mild steel sheet made of 18 gauge thk.of

required section with rebate of 10 mm for required

thickness of shutters and tie rod of 12 mm square

bar at at bottom as per specifications with or

without ventilators including holdfasts,hinges

weld to frame,filling in cement mortar 1:10 in box

frame and finishing with 2 coats of oil painting

etc.complete Box section of 100x65 mm overall

dimensions.etc.complete

23.04 747.00 Rs . Seven hundred

fourty seven only

sqm 17210.88 As directed by

Engineer-In-Charge

Page 88: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 88 –

Sign of Contractor No of corrections Secretary SPSM

30 Providing and fixing Single/double leaf shutter of

35 mm thick, for solid core flush door, decorative

type of exterior grade as per detailed drawings or

as approved Laminates Formica on both faces

venetians, all necessary beads,moulding and

lipping, brass oxidized / aluminum with power

coating fixture & fastenings _____ chromium

plated handles on both sides and finishing etc.

complete. (without door frame) Spec. No.: Bd-T

34 Page No. 499 ( Sample approved by

Engineer-in-charge )

23.04 2379.00 Rs two thousand

thousand three

hundred seventy nine

only

sqm 54812.16 Bd-T 34 Page No. 499

31 Providing & fixing mild steel grill wrork

weighing 20 Kg/Sqm for windows, ventilators etc.

as per drawing including fixtures, necessary

welding & painting with one coat of anti corrosive

paint and two coats of oil painting complete.(As

detailed design and drawing)

57.60 1679.00 Rs one thousand

six hundred seventy

nine only

sqm 96710.40 As directed by

Engineer-In-Charge

Providing and fixing 15 mm dia.elbow operated 20 cm long arm chomium plated brass cock including necessary sockets,union nut,testing etc.complete.Basic Rate+5%SA+0.75% VAT=296+14.80+2.22=313.02 Rounded Rs.313.00)

32 Providing and fixing collapsible gate in steel in

two leaves with channel pickets , pivoted flat

bars , including top and bottom guides , rollers ,

stoppers, handles , and all fiting acesories locking

arrangement and one coat of red lead primer

complte.(As detailed design and drawing)

9.60 2598.00 Rs two thousand

five hundred ninety

eight only

sqm 24940.80 As directed by

Engineer-In-Charge

Page 89: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 89 –

Sign of Contractor No of corrections Secretary SPSM

33 Providing and applying two coats of water proof

cement paint of approved manufacture and of

approved colour to the plastered surfaces including

scaffolding if necessary, excluding primer coat

cleaning and preparing the surface, watering for

two days complete. (Sample and brand is to be got

approved from Engineer-in-charge before use)

Spec. No. : Bd.O.8 Page No. 406

1049.74 42.00 Rs fourty two only sqm 44089.08 Bd.O.8 Page No. 406

34 Providing &applying primer coat for internal wall

surface and ceilling including scaffolding

etc.complete..

1491.81 18.00 Rs eighteen only sqm 26852.58 As directed by

Engineer-In-Charge

35 Providing and applying washable oil bound

distemper of approved quality, colour and shade

to internal walls and ceiling plastered surfaces,in

two coats. including scaffolding if necessary,

cleaning and preparations of the surface by

applying putty, excluding priming coat, etc.,

complete.( Sample approved by Engineer-in-

charge )

1491.81 38.00 Rs thirty eight only sqm 56688.78

36 Providing and fixing about 30 cm width chicken

mesh of 22 gauge of approved quality over joints

of Reinforced cement concrete member and brick

wall including fixing of mesh,necessary

nailing,drilling tying etc.complete as directed.

30.00 94.00 Rs ninety four only sqm 2820.00 As directed by

Engineer-In-Charge

Page 90: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 90 –

Sign of Contractor No of corrections Secretary SPSM

37 Providing cement based water proofing treatment

to terrace (India water proofing or alike) with

brick bats laid in required slope to drain the water

for any span after cleaning the base surface,

applying a coat of cement slurry and mixed with

approved water proofing compound and laying

the brick bats on bottom layer of c.m. (1:5) and

mixed with approved water proofing compound,

filling upto half depth of brick bats, curing this

layer for 3 days, applying cement slurry over this

layer, jointing of brick bats with c.m. 1:3 and

mixed with approved water proofing compound

and finally top finishing with average 20 mm thick

layer of same mortar including finishing the

surface smooth with cement slurry mixed with

approved water proofing compound, marking the

finished surface with false squares of 300mm x

300mm, making the junctions at the parapets

rounded and tapered towards top for required

height with drip mould at the junction of plaster

and curing etc.covering 7 years guarantee on Court

Fee Stamp paper of Rs.100/- including ponding

test etc. complete.

341.21 703.00 Rs seven hundred

three only

Sq.m 239870.63 As directed by

Engineer-In-Charge

Page 91: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 91 –

Sign of Contractor No of corrections Secretary SPSM

38 Providing and fixing 110 mm diameter UPVC soil

/ vent / waste SWR pipe/Rain water pipe of

required diameter conforming to IS-13592, and IS-

4985 to withstand continuous internal hydraulic

pressure of 4 kg / cm2 including necessary fixtures

and fittings, such as bends, tees, single junctions,

double junctions and joining with rubber rings and

lubricants, on wall by means of clips or in ground

including necessary excavation, laying refilling,

trench testing etc. complete. (Prior approval of

sample and brand by Engineer is necessary before

use) Spec. No.: As directed by Engineer-in-charge.

82.50 201.00 Rs two hundred one

only

Rmt 16582.50 As directed by

Engineer-In-Charge

39 Labour charges for fabricating and errecting

structural steel work in rolled sections like joists,

channels, angles, tees etc. as per detailed designs

and drawing including fixing in position without

connecting plates, braces etc. and one coat of

anticorrosive paint and over it two coat of oil

paintings of approved quality and shade complete.

Spec. No.: Bd.C.2 Page No. 275

0.14 15158.00 Rs fifteen thousand

one hundred fifty

eight only

MT 2122.12

40 Providing and fixing powder coated meta colour

sheets of 0.50 mm thick (22 B.W.G.) for roofing

without wind tiles including fastening with

galvanised / iron screw / bolt and lead / bitumen

washers as per drawing complete Spec. No.:

Bd.R.5, Page No. 453 ( Sample approved by

Engineer-in-charge )

24.75 711.00 Rs seven hundred

eleven only

Sq.m 17597.25 Bd.C.2 Page No. 275

41 Cement-Quality control test report from

Govt.Testing lab. For cement of Standard

Consistancy Fineness, Specific Gravity, Setting

Time ( Initial & Final ),Compressive Strength ,

2.00 3000.00 Rs three thousand

only

Per Set 6000.00 As directed by

Engineer-In-Charge

Page 92: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 92 –

Sign of Contractor No of corrections Secretary SPSM

Soundness.

42 Concrete -Quality control test report from

Govt.Testing lab.Compressive Strength of C.C.

Cube(Set of 3 cubes).For RCC

Slab,Column,Beams

6.00 550.00 Rs five hundred

fifty only

Per Set 3300.00 As directed by

Engineer-In-Charge

Total 4207050.64

Signature of contractor Secretary ,SPSM

MPKV, Rahuri

Page 93: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 93 –

Sign of Contractor No of corrections Secretary SPSM

Page 94: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 94 –

Sign of Contractor No of corrections Secretary SPSM

Page 95: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 95 –

Sign of Contractor No of corrections Secretary SPSM

Page 96: SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV - e Tenders€¦ ·  · 2017-05-14NAME OF WORK : - Construction of ... SAVITRIBAI PHULE SHIKHAN MANDAL,MPKV, RAHURI-413 722, DIST-AHMEDNAGAR

- 96 –

Sign of Contractor No of corrections Secretary SPSM