Santa Margarita Conjunctive Use Project, Phase I August 2, 2016

Transcript of Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield...

Page 1: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

Santa Margarita Conjunctive Use Project, Phase I

August 2, 2016

Page 2: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

United States Versus Fallbrook

• United States Government sues all water users in Fallbrook

• Final Judgment Requires a Physical Solution between U.S. and FPUD

Page 3: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

United States Versus Fallbrook

• United States Government sues all water users in Fallbrook

• Final Judgment Requires a Physical Solution between U.S. and FPUD

United States Government

Fallbrook

Page 4: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

History of Waters of the Santa Margarita River

US. Versus Fallbrook

Two Dam Project

4 Party Agreement

Santa Margarita Conjunctive Use Project

Page 5: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

Santa Margarita

River Conjunctive Use Project

Average Annual Yield (10,800 AFY)

Page 6: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

IRWM Project Includes• Environmental Permitting

(CEQA/NEPA)

• Hydrological Modeling, Water Rights Petitions and Settlement.

• Feasibility and Final Design of FPUD Facilities

Page 7: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

Santa Margarita Conjunctive Use Project

Page 8: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

Proposed Improvements to Diversion Facilities

Page 9: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

Proposed Improvements to Groundwater Facilities

Page 10: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

Proposed Treatment/Delivery Facilities for FPUD

New Groundwater Treatment Plant

New Reservoir and Pump Station

Page 11: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

Water Supply/Environmental Benefits

Water Cutbacks• Provides a local

supply to buffer cutbacks of the imported supplies

• Provides imported water supplies for the base during extended droughts

Water Supply • Locally available

groundwater that has lower energy requirements than alternative supplies

• Reduces demands on the Delta

• Resolves outstanding water rights litigation on the river

Environment• Permanently

Preserved 1,400 acres of high value habitat as open space

• Modify diversion dam to facilitate passage

• Maintain flows and groundwater levels required for riparian habitat and species

Page 12: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

Changes Made to Project to Reduce Environmental Impacts

Reduced Maximum Diversion Rate

Provide Fish Passage Facilities and Diversion Operating Plan

Develop Adaptive Management Plan based on real time groundwater data

and modeling

Replace Sheet Pile Weir with Inflatable Weir to Restore Sediment

Transport

Page 13: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

Changes Made to Project to Reduce Environmental Impacts

Reduced Maximum Diversion Rate

Provide Fish Passage Facilities and Diversion Operating Plan

Develop Adaptive Management Plan based on real time groundwater data

and modeling

Replace Sheet Pile Weir with Inflatable Weir to Restore Sediment

Transport

Page 14: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

Lessons for Other Project Sponsors

• Federal Matching Funds

• Consultations on Steelhead (2+ years)– Species Recovery in Marginal Habitat

Page 15: Santa Margarita Conjunctive Use Project, Phase I · 2017-10-05 · Use Project Average Annual Yield (10,800 AFY) IRWM Project Includes •Environmental Permitting (CEQA/NEPA) •Hydrological

Next Steps• Construction of Camp Pendleton

Facilities (Underway)

• Construction of FPUD Facilities (2017).