Sanitary Pump Station Rehabilitation

32
How to Drag a 1960s Lift Station Leaking & Squeaking into the 21 st Century Presented at the Arkansas Water Environment Federation 2008 Conference in Hot Springs Arkansas April 29, 2008 David E. Mizell, P.E. Jon A. Kremer, P.E. Burns & McDonnell - St. Louis, MO David Moss, P.E. Paragould Light Water & Cable

Transcript of Sanitary Pump Station Rehabilitation

Page 1: Sanitary Pump Station Rehabilitation

How to Drag a 1960s Lift

Station Leaking & Squeaking

into the 21st Century

Presented at the Arkansas Water Environment Federation

2008 Conference in Hot Springs Arkansas April 29, 2008

David E. Mizell, P.E.

Jon A. Kremer, P.E.

Burns & McDonnell - St. Louis, MO

David Moss, P.E.

Paragould Light Water & Cable

Page 2: Sanitary Pump Station Rehabilitation

Agenda

� Pump Station History

� Project Objectives

� Project Challenges� Project Challenges

Page 3: Sanitary Pump Station Rehabilitation

Agenda

� Pump Station History

� Project Objectives

� Project Challenges� Project Challenges

� Design Factors

� Construction

� Lessons Learned

� Operational Experience Apr 07 – Mar 08

Page 4: Sanitary Pump Station Rehabilitation

History, Part 1

� Built 1965

� Concrete cast-in-place

� All-Brick above grade � All-Brick above grade

� Wet well 12’ W by 8’ L by 34’ D

� Dry well 12’ W by 12’ L by 34’ D

� 3 pumps, vertical shaft, motors at surface

� Discharge out east and west walls!!

Page 5: Sanitary Pump Station Rehabilitation

Service Area

� This Lift Station Serves:

• 4 other pump stations

• 486 acres total

• 814 homes and businesses• 814 homes and businesses

• Avg. Flow = 0.375 MGD

• Peak Flow = 1.75 MGD est

Page 6: Sanitary Pump Station Rehabilitation

Project Objectives – 1

� Fix leaks at wall of

wet well

� Wall pipe with leaded

seal seal

� Replace intake piping

to pumps

Page 7: Sanitary Pump Station Rehabilitation

Project Objectives – 2

� Replace old water pumps

� Replace old pump motors & pump motors & eliminate shafts

� Valves & couplings for future repairs

Page 8: Sanitary Pump Station Rehabilitation

Project Objectives – 3

� Stop leaks at wall

discharge points

� This leak was

suspected ground suspected ground

water infiltration

� Actually was a

crack in the pipe!

Page 9: Sanitary Pump Station Rehabilitation

Project Objectives – 4

� Convert to VFD

control

� Install pressure

transducer in wet transducer in wet

well for primary

level control

� Floats as

secondary control

Page 10: Sanitary Pump Station Rehabilitation

Project Challenges

� Maintain Service

at all times

• Short breaks OK

� Tight cramped � Tight cramped

vertical space

View down Dry Well

Page 11: Sanitary Pump Station Rehabilitation

Design Objectives

� Create single discharge line

• Old pumps 1 & 2 discharged out West side

• One pump 3 discharged out East side

Page 12: Sanitary Pump Station Rehabilitation

Design Objectives

� Create single discharge line

• Old pumps 1 & 2 discharged out west side

• One pump 3 discharged out east side

� Improve reliability and redundancy� Improve reliability and redundancy

Page 13: Sanitary Pump Station Rehabilitation

Design Objectives

� Create single discharge line

• Old pumps 1 & 2 discharge out west side

• One pump 3 discharges out east side

� Improve reliability and redundancy� Improve reliability and redundancy

� Keep Station in service during

construction

• Bypass wet well to existing 12-inch force main

• Replace 3 pumps in 2 phases

Page 14: Sanitary Pump Station Rehabilitation

3 Replacement Pumps

One New Pump 1

� 400 gpm

� 115 feet total

dynamic head

� 8-inch suction

� 4-inch discharge

� 30 HP motor

� 1,800 rpm

� 480 V, 3 Ph

Page 15: Sanitary Pump Station Rehabilitation

3 Replacement Pumps

New Pumps 2 & 3

� 1,000 gpm each

� 115 feet total

dynamic head

One New Pump 1

� 400 gpm

� 115 feet total

dynamic head

� 8-inch suction

� 6-inch discharge

� 50 HP motor

� 1,800 rpm

� 480 V, 3 Ph

� 8-inch suction

� 4-inch discharge

� 30 HP motor

� 1,800 rpm

� 480 V, 3 Ph

Page 16: Sanitary Pump Station Rehabilitation

Use 3-D Design

Looking Southeast Looking South

Page 17: Sanitary Pump Station Rehabilitation

Pre-Bypass #1 Activities

� Expose Force Main &

install tapping sleeve &

valve

� Set up bypass pumps � Set up bypass pumps

and piping

• Pump out of manhole upstream of lift station

• Feed force main through tapping sleeve & valve

Page 18: Sanitary Pump Station Rehabilitation

During Bypass #1

� Pump out wet well

� Turn off Pump 3 & close

valves to isolate

� Remove Pump 3 & piping

Core drill into wet well for

Phase 2Phase 1

� Core drill into wet well for

new intake

� Install new suction elbow,

pipe spool & valve for

Pump 3

� Re-activate Pumps 1 & 2

P-3 P-2 P-1

Page 19: Sanitary Pump Station Rehabilitation

After Bypass #1 Activities - 1

� Core drill North wall for new discharge pipe

� Install Pump 3 base & vibration isolatorsvibration isolators

� Install new Pump 3 & Motor

� Install new conduit, wiring, etc.

Page 20: Sanitary Pump Station Rehabilitation

After Bypass #1 Activities - 2

� Install piping & valves to outside

� Outside: install meter vault & bypass piping vault & bypass piping & valves

� Install wet well water level transducer & redundant floats

Page 21: Sanitary Pump Station Rehabilitation

Meter Vault

� Dismantling Coupling

� Mag. Flow Meter

� Tee

� Full Size Valve

Air release valve

� Air Release Valve

• If future emergency occurs,

remove air release valve,

install connector, bring in portable pump, and discharge at Tee into force main

� Full Size Valve

Page 22: Sanitary Pump Station Rehabilitation

During Bypass #2

� Turn off Pumps 1 & 2,

close valves to isolate

� Pump out wet well

� Disassemble piping &

remove Pumps 1 & 2remove Pumps 1 & 2

� Core drill into wet well for

intakes 1 & 2

� Install new suction elbows, pipe, & valves

� End bypass #2

Page 23: Sanitary Pump Station Rehabilitation

After Bypass #2

� Install Pumps 1 & 2, motors & wiring

� Install piping and valves to new discharge headerdischarge header

� Start up Pumps 1 & 2

� Demolish Old Piping Outside

Page 24: Sanitary Pump Station Rehabilitation

Actual Construction

� Contractor did one LONG

Bypass Period

• Elec Feeds

• Two portable pumps

� Tackle all pump & piping � Tackle all pump & piping

replacements at once!

� All Core Drilling 1 mob

� Weather cooperated,

No big storms!

Page 25: Sanitary Pump Station Rehabilitation

New Pump Station Operations

� April 2007 – March 2008

• Total Pump Cycles = 42,749 (Avg. 118/day)

•• Total Flow = 137 MG (377,000 gpd)

Page 26: Sanitary Pump Station Rehabilitation

Pump Cycles Apr-07 to Mar-08

200

250

300

350

400

Pu

mp

Cycle

s /

Day

0

50

100

150

200

Apr-

07

May-

07

Jun-

07

Jul-

07

Aug-

07

Sep-

07

Oct-

07

Nov-

07

Dec-

07

Jan-

08

Feb-

08

Mar-

08

Date

Pu

mp

Cycle

s /

Day

Page 27: Sanitary Pump Station Rehabilitation

Daily Flow Apr-07 to Mar-08

800

1,000

1,200

1,400

Daily F

low

(000 g

al)

0

200

400

600

Apr-

07

May-

07

Jun-

07

Jul-

07

Aug-

07

Sep-

07

Oct-

07

Nov-

07

Dec-

07

Jan-

08

Feb-

08

Mar-

08

Date

Daily F

low

(000 g

al)

Page 28: Sanitary Pump Station Rehabilitation

Dry Day Operation 5/28/2007

800

1,000

1,200

1,400

Flo

w R

ate

(g

pm

)

0

200

400

600

0:00 3:00 6:00 9:00 12:00 15:00 18:00 21:00 0:00

Time of Day

Flo

w R

ate

(g

pm

)

Page 29: Sanitary Pump Station Rehabilitation

Flows on 5/28/07 from 6:00 to 8:00 AM

800

1,000

1,200

1,400

Flo

w R

ate

(gpm

)

0

200

400

600

6:00 6:15 6:30 6:45 7:00 7:15 7:30 7:45 8:00

Time of Day

Flo

w R

ate

(gpm

)

Page 30: Sanitary Pump Station Rehabilitation

Wet Day Operation 11/25/07

800

1,000

1,200

1,400

Flo

w R

ate

(g

pm

)

0

200

400

600

0:00 3:00 6:00 9:00 12:00 15:00 18:00 21:00 0:00

Time of Day

Flo

w R

ate

(g

pm

)

Page 31: Sanitary Pump Station Rehabilitation

Conclusion

� 1960s era Pump Station was an O&M nightmare

� Many ways to modernize this facility

� 3-D design was effective tool� 3-D design was effective tool

� Over-core of pipe penetrations was key

� Bypass pumping successful

� Nightmares Over!

Page 32: Sanitary Pump Station Rehabilitation

Questions?Questions?