SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

28
SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

Transcript of SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

Page 1: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

S A N M A R C O S U N I F I E D S C H O O L D I S T R I C T

A U G U S T 1 9 , 2 0 1 4

FACILITIES UPDATEGOVERNING BOARD MEETING

Page 2: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

2

Facilities Update: In Planning/Design

• Proposition 39: Energy Jobs Act• “Kick-off” meeting• Conduct campus analyses• Create proposed project list• Submit proposals to CEC for approval• Construct projects

• Proposition K: Campus Modernization Projects• Preliminary master plans• Preliminary site surveys• Special Board Meeting “Workshop”

8/19/2014

Page 3: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

3

Facilities Update: In Construction

• Woodland Park MS Modernization Project

• Professional Learning Center (PLC) – NCREC – S

• Shade Shelters – MHHS, SEMS, DSC, SME

• Facilities Needs for 2014-2015 – AD, DSC, SEMS

• New Classroom Buildings – CAR, DSC, SME

• Technology Infrastructure Projects

• San Marcos K-8 School

8/19/2014

Page 4: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

4

Facilities Update: In Construction

• Woodland Park MS Modernization Project: Aug. 2014• Completed final accessible ramp, casework (cabinets), and A/V equipment

8/19/2014

New Front Entry

Page 5: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

5

Facilities Update: In Construction

• Professional Learning Center (PLC) at NCREC – S• Professional Development

8/19/2014

Page 6: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

6

Facilities Update: In Construction

• Professional Learning Center (PLC) at NCREC – S• Professional Development - TOSAs

8/19/2014

Page 7: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

7

Facilities Update: In Construction

• Professional Learning Center (PLC) at NCREC – S• Centralized Kitchen

8/19/2014

Page 8: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

8

Facilities Update: In Construction

• Facilities Needs for 2014-2015• Discovery ES• New Shade Shelter and reconstruct Walkway Cover

8/19/2014

Page 9: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

9

Facilities Update: In Construction

• Facilities Needs for 2014-2015• Discovery ES• New Shade Shelter and reconstruct Walkway Cover

8/19/2014

Page 10: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

10

Facilities Update: In Construction

• Discovery ES• 1 temporary Portable Building• Until SMK8 opens

8/19/2014

Page 11: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

11

Facilities Update: In Construction

• San Elijo MS: Support for temporary enrollment growth for 2014-15 school year

School• 3 lunches• Large P.E. classes

Facilities• Shade Shelter for PE/Lunch

• Additional Basketball Courts

• Upper Field Power/Communications

8/19/2014

Page 12: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

12

Facilities Update: In Construction

• Facilities Needs for 2014-2015• San Elijo MS• New shade shelter, new basketball courts, new track perimeter

8/19/2014

Page 13: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

13

Facilities Update: In Construction

• Facilities Needs for 2014-2015• San Elijo MS• New shade shelter, new basketball courts, new track perimeter

8/19/2014

Page 14: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

14

Facilities Update: In Construction

• Facilities Needs for 2014-2015• Mission Hills HS• New shade shelter for art and outdoor classroom

8/19/2014

Page 15: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

15

Facilities Update: In Construction

• Facilities Needs for 2014-2015• San Marcos ES• New shade shelter for Kindergarten area

8/19/2014

Page 16: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

16

Facilities Update: In Construction

• Facilities Needs for 2014-2015• Alvin Dunn ES• New perimeter fence

8/19/2014

Page 17: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

17

Facilities Update: In Construction

• New Classroom Buildings• Anticipated enrollment growth

at CAR and SME

8/19/2014

Page 18: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

18

Facilities Update: In Construction

• Carrillo ES: 5-Classroom Permanent Building

8/19/2014

Page 19: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

19

Facilities Update: In Construction

• Carrillo ES: 5-Classroom Permanent Building

8/19/2014

Page 20: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

20

Facilities Update: In Construction

• San Marcos ES: 4-Classroom Permanent Building

8/19/2014

Page 21: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

21

Facilities Update: In Construction

• San Marcos ES: 4-Classroom Permanent Building

8/19/2014

Page 22: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

22

Facilities Update: In Construction

• San Marcos ES: 4-Classroom Permanent Building

8/19/2014

Page 23: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

23

Facilities Update: In Construction

• Prop K: Technology Infrastructure Projects: • Mission Hills HS, La Costa Meadows ES, Paloma ES – Completed• Knob Hill ES, Richland ES, Twin Oaks ES, San Elijo MS – Jul. – Oct. 2014• Remaining campuses – Oct. 2014 – Spring 2015

8/19/2014

Page 24: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

24

Facilities Update: In Construction

• Prop K: Technology Infrastructure Projects

8/19/2014

Page 25: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

25

Facilities Update: In Construction

• Prop K: Technology Infrastructure Projects

8/19/2014

Page 26: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

26

Facilities In Construction: SMK-8

8/19/2014

Page 27: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

27

Facilities In Construction: SMK-8

8/19/2014

Fields

ParkingParking

Buildings

Buildings

Central

Courtyard

Page 28: SAN MARCOS UNIFIED SCHOOL DISTRICT AUGUST 19, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING.

G O V E R N I N G B O A R D M E E T I N G

A U G U S T 1 9 , 2 0 1 4

FACILITIES UPDATE:THANK YOU!