San Francisco’s City Construction Program: It Needs Work...Civil Grand Jury, 2014-2015 San...

30
San Francisco’s City Construction Program: It Needs Work June 2015 City and County of San Francisco Civil Grand Jury, 2014-2015

Transcript of San Francisco’s City Construction Program: It Needs Work...Civil Grand Jury, 2014-2015 San...

  • San Francisco’s City Construction Program:

    It Needs Work

    June 2015

    City and County of San Francisco

    Civil Grand Jury, 2014-2015

  • SanFrancisco’sCityConstructionProgram 2

    Members of the Civil Grand Jury

    Janice Pettey, Foreperson

    Philip Reed, Foreperson Pro Tem

    Anne M. Turner, Recording Secretary

    Morris Bobrow

    Leonard Brawn

    Daniel Chesir

    Matthew Cohen

    Jerry Dratler

    Herbert Felsenfeld

    Allegra Fortunati

    Mildred Lee

    Marion McGovern

    Fred A. Rodríguez

    Gary Thackeray

    Jack Twomey

    Ellen Zhou

  • SanFrancisco’sCityConstructionProgram

    3

    THE CIVIL GRAND JURY

    The Civil Grand Jury is a government oversight panel of volunteers who serve for one year. It makes findings and recommendations resulting from its investigations. 

     Reports of the Civil Grand Jury do not identify individuals by name. 

    Disclosure of information about individuals interviewed by the jury is prohibited. California Penal Code, section 929 

    STATE LAW REQUIREMENT California Penal Code, section 933.05

    Each published report includes a list of those public entities that are required to respond to the Presiding Judge of the Superior Court within 60 to 90 days as specified. A copy must be sent to the Board of Supervisors. All responses are made available to the public. For each finding, the response must:

    1) agree with the finding , or 2) disagree with it, wholly or partially, and explain why

    As to each recommendation the responding party must report that:

    1) the recommendation has been implemented, with a summary explanation; or 2) the recommendation has not been implemented but will be within a set timeframe as

    provided; or 3) the recommendation requires further analysis. The officer or agency head must define

    what additional study is needed. The Grand Jury expects a progress report within six months; or

    4) the recommendation will not be implemented because it is not warranted or reasonable, with an explanation.

  • SanFrancisco’sCityConstructionProgram 4

    TABLE OF CONTENTS EXECUTIVE SUMMARY ............................................................................................................ 5BACKGROUND ............................................................................................................................ 6METHODOLOGY ......................................................................................................................... 8DISCUSSION ................................................................................................................................. 9The Current Contracting Environment and its Complexity ............................................................ 9

    1. Overview ......................................................................................................................... 92.The Construction Management General Contractor (CMGC) Approach ........................ 93. The Lowest Cost Bid Problem ..................................................................................... 114. The Role of “LBEs” ..................................................................................................... 135. Revisions to Chapter 6 ................................................................................................. 14

    Construction Project Management ................................................................................................ 141. Change Order Management .......................................................................................... 152. Contract Close Outs ...................................................................................................... 17

    Department Interactions ................................................................................................................ 181. The DPW Architecture and Engineering staff ............................................................. 182. Disparate Policies and Systems ................................................................................... 193. Errors and Omissions ................................................................................................... 194. Recreation and Park ...................................................................................................... 19

    Information Technology ............................................................................................................... 20Transparency and Reporting ......................................................................................................... 21Lack of Independent Oversight ..................................................................................................... 23FINDINGS .................................................................................................................................... 25RECOMMENDATIONS .............................................................................................................. 25REQUEST FOR RESPONSES..................................................................................................... 26GLOSSARY ................................................................................................................................. 29ACRONYMS ................................................................................................................................ 29ENDNOTES ................................................................................................................................. 30

  • SanFrancisco’sCityConstructionProgram

    5

    EXECUTIVE SUMMARY

    HowcanSanFranciscomanageaconstructionportfolioofover$25billionwithinconsistentcontrols,insufficientsystems,andaninabilitytoconsolidatecitywidefinancialandmanagementinformation?WhydoesSanFranciscocontinuetooperateacontractingenvironmentthatisoutofstepwithbestpractices?ShouldtheCitybespendingsomuchonconstructionwithouttheoversightoftheBoardofSupervisors?TheCivilGrandJury(CGJ)wantedanswerstothesequestions.InthisreporttheCGJexaminesthesethreecriticalproblemsthathavebeencalledoutinnumerousCityauditreportsoverthelastfewyearsbutremainunaddressed.InourresearchwediscoveredthattheCity’sconstructionprojectportfolioisdiverse,thatsomeprojectsareverycomplex,andthatneighborhoodprojectsinflamethepassionsofSanFranciscocitizens.Sixdepartmentshavepublicworkscontractingauthority.TheCGJchosetofocusprimarilyontheworkofoneofthose,theDepartmentofPublicWorks(DPW).Althougheffortsareunderwaytoaddresssomeoftheproblemareas,muchworkstillneedstobedone.Ourrecommendationsinclude:

    TheCityneedstoreviseChapter6oftheAdministrativeCodetoenablecontractorselectiononpastperformanceinadditiontothelowcostbid.

    Commonconstructionmanagementprocessesaddressingchangeorders,projectcloseoutandcomplianceneedtobeinstituted,monitoredandmeasured.

    Constructionmanagementinformationmustbestandardizedtoproducecitywidereports.Onceconsolidatedinformationisavailable,citywidereportsshouldbepublishedforpublicreview.

    TheCity’soutofdatetechnologyandweakConstructionManagementSystemsinfrastructuremustbeaddressed.

    TheBoardofSupervisors(BOS)musttakeamoreactiveroleintheoversightofconstructionprojects.

  • SanFrancisco’sCityConstructionProgram 6

    BACKGROUND SanFrancisco’s2014–2023ten‐yearcapitalplanis$25billion,astaggeringsumbyanymeasure.Theplanprincipallyfundsinfrastructurelikeroadsandpowersystems,buttherearealsoalargenumberofbuildingprojects.Thecitydifferentiatesbetween“vertical”projects,e.g.buildings,and“horizontal”projects,likeroads.TheverticalprojectscanrangefromthehighlycomplexandmassiverebuildingofSanFranciscoGeneralHospitaltoarelativelysmallproject,liketherenovationofacommunitycenteratMissionPlayground.

    2014‐2023 Capital Plan Summary(Dollars in Millions)

     By Service Category    Plan Total   Public Safety   $1,376 Health and Human Services   $1,306 Infrastructure & Streets   $8,678 Recreation, Culture, and Education   $1,241 Economic & Neighborhood Development   $4,151 Transportation   $8,228 General Government   $91 Total   $25,072 1

    SixCitydepartmentshavepublicworkscontractingauthority.Thesedepartmentsare:‐ ThePortCommission(thePort)‐ TheAirportCommission(theAirport)‐ TheSanFranciscoPublicUtilitiesCommission(PUC)‐ RecreationandParkDepartment(R&P)‐ TheMunicipalTransportationAgency(MTA)‐ TheDepartmentofPublicWorks(DPW)

    Goingforward,thesesixareaswillbereferredtojointlyasthe“sixCitydepartments”.

  • SanFrancisco’sCityConstructionProgram

    7

    InadditiontoDPW’sowndepartmentprojects,DPWmanagesconstructionprojectsforallnon‐Chapter6departmentssuchastheLibrary,FireDepartment(SFFD)andDepartmentofPublicHealth.Constructionprojectsarefundedinmanywaysincludingbondmeasuresthattaxpayersapprove,federalorstatefunding,citygeneralfunds,privatesources,oracombinationofallavailablesources.Whengeneralobligationbondfundsareused,theCitizens’GeneralObligationBondOversightCommittee(CGOBOC)hastheresponsibilityofensuringthatgeneralobligationbondproceedsarespentproperly.AtrecentCGOBOCmeetings,theDirectorofAuditspresentedperformanceauditsofconstructionpracticesintheCity.Theauditsidentifiedcontrolweaknessesintheareasofcontractchangeordermanagementandtheprocessofclosingoutconstructioncontracts.Afterreviewingadditionalconstructionmanagementaudits,theSanFranciscoCGJfeltthetopicwarrantedstudy,giventhedollarmagnitudeandlargenumberofbuildingconstructionprojectsinprocess.AstheCGJbeganitsinvestigationwefoundthattherehavebeen25auditsoverthelastsevenyears,whichhaveexaminedvariousaspectsoftheconstructionmanagementprocess.Someofthesewerecitywideperformanceaudits,whileothersfocusedonspecificprojects.Theseauditsweredonebyemployeesandoutsidefirmswithspecializedexpertiseinsuchassessments.Severalthemesemergedfromthesevariousrigorousaudits.

    Constructionprojectsalwaysinvolvechangeorders,whichauthorizeworktobeaddedtoordeletedfromtheoriginalcontract.Inmanyinstances,thechangeordermanagementprocesswasweakwhichcouldexposetheCitytoincreasedcostand/ordelays.

    Constructioncontractcloseoutproceduresarealsoanareaofconcern;astrongcloseoutprocessensuresthatallcontractualtermsaremet,sodeficienciesinthatprocesscouldmeanarisktothecity,

    IntheprojectsthatDPWmanagesanddesigns,therehavebeendesignerrorsthathaveledtoavoidablecostincreases.

    Cityconstructionprojectslacktransparencyforseveralreasons.Thesystemsthattrackprojectsacrossdepartmentsvaryanddonotsharecommondataelements,preventingtheconsolidationorcomparisonofkeyperformancemetrics.Similarly,nofinalreportispublishedoneachprojectsummarizingthefinancial,functionalandoperationalprojectoutcomes.

    Accountabilityforbothlargeandsmallcityconstructionprojectsresidesinthedepartment,itscommissionortheCityAdministrator,butnotwiththeBOS.WiththeexceptionofDPW,allsixCitydepartmentshavecommissionoversight.

  • SanFrancisco’sCityConstructionProgram 8

    TheinformationsystemsinfrastructureinDPWisnotsufficienttohandlethe535activehorizontalandverticalprojectsthatDPWcurrentlymanagesthatarevaluedat$5.7billion.2

    AnApril2014auditperformedbytheCityServicesAuditorexaminedtheCity’scurrentpracticeofawardingconstructioncontractsusingasinglecriterion,thelowcostbid,apracticethatignorescurrentbestpracticesusedbyotherlargecitiesandgovernmentagencies.

    Manyofthesefactorsalonesuggestedtheneedforfuturestudy,buttakentogether,aninvestigationofCityconstructionmanagementwasclearlywarranted.Tomakethetopicmanageable,wechosetofocusonthebuildingconstructionmanagementprocessofDPW.Weareconfidentthatmanyofourrecommendationswillbeapplicabletoothercitydepartmentsandtheirconstructionprojectsaswell.METHODOLOGY Wereviewedmanycity‐publishedsourcesofinformationinpreparingthisreportincludingdepartmentwebsitesandtheSanFranciscoAdministrativeCode(theCode).TheCityServicesAuditor(CSA)hasaconstructionauditgroupthatauditsCityconstructionprojectsandissuedseveralauditsinthelastsevenyears.Wereviewedtheseauditsindepth,focusingonthosethatdealwithverticalprojects,managementcontrols,andtheCity’scurrentlowestcostbiddercriterionforawardingconstructioncontracts.Wealsoreviewedthe2007ManagementAuditofDPWpreparedbytheSanFranciscoBudgetandLegislativeAnalyst(BLA).AsectionofthatmanagementauditaddressedDPW’sprogramforreportingandpreventingconstructiondesignerrorandomissionchangeorders.Additionally,wereviewedthe2011BLAreportonthecostofchangeordersandthelackofcitywidechangeorderreporting.TheCGJinterviewedrepresentativesofthesixCitydepartmentsandCitydepartmentsthatlackcontractingauthorityinordertounderstandtheirdifferentperspectivesontheeffectivenessoftheprevailingpracticesofmanagingtheCity’sconstructionworkload.Weinterviewedconstructioncontractorsincludingthosewhodobothpublicandprivateconstructionprojects,andcontractorswhohavechosennottobidonCitywork.WeinterviewedseniormanagersatthePublicWorksdepartmentsinotherlargecitiestounderstandthepracticesinplaceintheircommunities,andtherebydiscernwhatissuesmayapplytoallcitiesandwhatmaybeuniquelypertinenttoSanFrancisco.Asaresultoftheseinterviewswewereprovidedwithadditionalmanagementreports,anddataextractsfromthedepartments.

  • SanFrancisco’sCityConstructionProgram

    9

    DISCUSSION OurinvestigationrevealedseveralareasforimprovementinCitymanagementofverticalconstructionprojects.Theseissueareasarediverse,sowewilladdresseachseparately.Theyare:

    TheContractingEnvironment ConstructionProjectManagement DepartmentInteractions InformationTechnology TransparencyinReporting IndependentOversight

    The Current Contracting Environment and its Complexity

    1. Overview

    ThenumberofcranesseenintheSanFranciscoskylineisaclearindicationofthescaleofconstructionprojectsinourcity.Althoughmostprojectsareprivatedevelopments,manyarecityprojectsthatmustcompeteforthesamedesignandconstructionresources.ThemannerinwhichtheCitysecuresdesignandcontractorresourcesforconstructionprojectsisviaacontractingprocessoutlinedinChapter6oftheCode.TheCodespecifiesthattheCitymusttakethelowestcost“responsiblebidder.”Additionally,biddersarerequiredtoincludeLocalBusinessEnterprises(LBEs)aspartoftheirconstructionteam.Thisisa“hardbid”process,wherespecificationsareprovidedtobidderswithnonegotiationofprojectscope,timingordeliverables.Somemajorconstructionfirmswillnotparticipateinahardbidprocess.Theyseethehardbidprocessasstructurallyflawed;aprocesswheretheclientdoesnotchooseacontractorbasedonpastperformanceorthequalityofthecontractor’swork.Thelowcostbidprocesscancreateaperverseincentiveforcontractorstoscrutinizeprojectbidspecificationstodeterminetheexistenceofflawsoromissionsinthebidspecificationsthatwouldneedtobeaddressedthroughlucrativecontractchangeorders.Thepresidentofamajorconstructionfirmthathadhistoricallyavoidedmunicipalcontractingviahardbidssaidin2007,"Theprocessasithasbeenfollowedisafailureeverytime.WhyinGod'snameisthisprocessstillrepeated?"3

    2. The Construction Management General Contractor (CMGC) Approach

    Theconstructionindustrymovedtoalternativecontractingstructurestocounterthe“oldschool,”hardbidenvironment.Privatedevelopersandcontractors,realizingtherewasaneedforgreatercollaborationindesigningandbuildingcomplexconstructionprojects,developedcontractualagreementsthatsupportspecializationandcollaboration.

  • SanFrancisco’sCityConstructionProgram 10

    Ina“Design‐Build“contractonefirmprovidesprojectdesignandconstructionservices.Thisapproachisusedforroutineconstructionprojects,likeparkinglotsorcorrectionalfacilities,wherespecificfirmsspecializeinagiventypeofstructureandofferaturnkeysolution,providingboththeprojectdesignandconstructionmanagementservices.Inthisprocess,writtendesigncriteriaareprovidedalongwithprojectrequirements.Thebiddingfirmcomesbackwiththeprojectdesignandtheconstructioncost.TheCityofSanFranciscohasdoneseveralDesign‐Buildprojects.Forexample,the$255millionRehabilitationDetentionFacilityisadesign‐buildproject.Othermunicipalitieshaveadoptedthisturnkeyoptionaswell.InaConstructionManagementGeneralContractor(CMGC)relationship,thecontractorprovidesinputinthepre‐constructionphaseoftheprojecttosimplifytheconstructionprocess,reducingconstructioncost.Theconstructionmanagerispaidforpre‐constructionplanning,whichincludesvalidatingthebudget,andidentifyingconstructionsavingsthatcouldbeachievedfromtheredesignofcertainelementsoftheproject.Thegoalistocreateamoreefficientandcosteffectiveconstructionproject.Theprivatesectorcontractingcommunityalsoreferstothisasintegratedprojectdesign.CMGCpracticeswereadoptedinSanFranciscoin2007,whenthenMayorGavinNewsom,recognizedtheneedformorecollaborationintheplanningofthenewAcademyofSciences.SeniorleadershipofDPWassistedinpassinganordinancetoenableCMGCpractices.4TheCityaddressedthesenewcontractingstructuresinitsCode:Chapter6.61fordesign‐build,and6.68forCMGCprojects.Subjecttotwoconditions,theseprovisionsgranttheflexibilitytosoliciteitherdesign‐buildorCMGCproposalstodepartmentheadsauthorizedtoexecutecontractsforpublicworksprojects.Theprojectmustbesuitabletoeitherprocess;and,mostsignificantly,approvalmustbeobtainedbytheclient’sdepartmentcommission.Ifadepartmenthasnocommission,theCityAdministratormustapprovethearrangement.DPWhascompletedfiveconstructionprojectsusingCMGCwithanotherfiveprojectsintheactiveconstructionphase.ThefiveactiveprojectsarethePublicSafetyBuilding,SanFranciscoGeneralHospital,theOfficeoftheChiefMedicalExaminerBuilding,theMosconeCenterExpansionandtheVeteransBuilding.ThebenefitsofusingtheCMGCprocesshavebeendemonstratedintheearlyresultsoftheseprojects.TheAcademyofSciencesrebuildwasabig“win”fortheCity,cominginbothontimeandunderbudget.TherebuildingofSanFranciscoGeneralHospitalisbeingcoordinatedbyaspecialisthospitalcontractingfirm.Changeordersonthelargestphaseofthe$882millionproject,the$673millionofnewconstruction,wereapproximately3%oftotalcost,agreatresultforaprojectofitssizeandcomplexity.

    Somestates,includingOregonandWashington,havemovedtoamandatoryuseofCMGCpracticesforlarge‐scaleprojects.Federalprojectsalsousethismethodofcontracting.Aqualifications‐basedcriteriaisestablishedfortheawardoftheCMGCpre‐constructionproject.Priceisnotaselectioncriterion.SanFrancisco,likemanyjurisdictions,includes

  • SanFrancisco’sCityConstructionProgram

    11

    socialpolicygoalsliketheuseofdisadvantagedbusinessenterprisesasaratableelementinthescoringprocess.Afterthehighestscoringbidderhasbeenselected,priceisthennegotiated.TheCGJcommendstheCityonitsuseofCMGCanddesign‐build,processesthatarebeingadoptedasa“BestPractices”intheconstructionindustry.Theincreaseduseofthesetechniquesforlargeand/orcomplexconstructionprojectswillonlyyieldbenefitstotheCity.

    3. The Lowest Cost Bid Problem AlthoughsomecityconstructionprojectsutilizeCMGCanddesign‐buildtechniques,mostprojectsarestillsubjecttothelowestcostbidapproach.Forprojectsequaltoormorethan$400,000,theCoderequirestheCitytoaccept“aresponsiblebidderofferingthelowestresponsive bid.” Forprojectsunder$400,000theCoderequires“aresponsiblebidderofferingthelowestquotation.”5Thosetermsaredefinedasfollows:

    Responsible.Aresponsiblebidderorcontractorisonewho(1)meetsthequalifyingcriteriarequiredforaparticularproject,includingwithoutlimitationtheexpertise,experience,recordofpriortimelyperformance,license,resources,bondingandinsurancecapabilitynecessarytoperformtheworkunderthecontractand(2)atalltimesdealsingoodfaithwiththeCityandCountyandshallsubmitbids,estimates,invoicesclaims,requestsforequitableadjustments,requestsforchangeorders,requestsforcontractmodificationsorrequestsofanykindseekingcompensationonaCitycontractonlyuponagoodfaithhonestevaluationoftheunderlyingcircumstancesandagoodfaith,honestcalculationoftheamountsought.

    Responsive.Aresponsivebidisonethatcomplieswiththerequirementsofthesubjectadvertisementforbidswithoutconditionorqualification.6

    WhileitwouldappearthattheSanFranciscocityrequirementtoacceptaresponsiblebidderofferingthelowestcostresponsivebidwouldincorporateevaluatingcontractorpastperformanceinthebidselectionprocessforfixedbidcontracts,thisisnotthecase.AnApril2014CSAcitywideconstructionauditevaluatedwhetherthesixCitydepartmentseffectivelyevaluatecontractorpastperformanceandutilizecontractorpastperformanceinawardingconstructioncontracts.Theauditfoundthat“citydepartmentsdonotadequatelyassesscontractorperformanceanddonotconsiderpastperformanceintheconstructionawardprocess.”Thereportgoesontosay,“becausetheCitydoesnotrequireevaluationsofcontractors’performanceand,hence,thereisnoformalrecordoformethodbywhichtojudgecontractorresponsibility,poor‐performingcontractors—evencontractorsincapableofperformingtheworkonwhichtheybid—cansecureadditionalcitycontracts.”7Similarly,70%ofthosesampledbytheCSAreportedthatacontractorhadperformedpoorlyonaCityproject.8

  • SanFrancisco’sCityConstructionProgram 12

    Othercitieshavedevelopedextensivevettingcriteriaforpublicworkscontractors.Fiveoftheleadingpracticesaresummarizedinthetablebelow.ThreeofthesixSanFranciscoCitydepartmentshaveacontractorevaluationprocess.However,thethreedepartmentsusedifferentcontractorassessmentcriteriaandthecontractorevaluationsarenotusedinthecontractawardprocess.

    9Adoptionofleadingpracticesincontractorperformanceevaluationdiscouragesthefollowingcontractorpracticesthatincreaseconstructionprojectcosts: Contractorspurposelysubmittingabidthatdoesnotprovideenoughmoneyto

    completeaconstructionprojectknowingthattheCitywillneedtoissueprojectchangeorderstofundtheprojecttocompletion.Projectchangeordersarenotsubjecttocompetitivebiddingandhaveamuchgreaterprofitmarginforcontractors.

    Contractorsevaluatingconstructionprojectsfromtheperspectiveoftheproject’schangeorderpotential.ContractorswhousethisprocessevaluatetheCity’sbidpackagesfromtheperspectiveofwhatdesignelementsaremissingfromthebidpackagethatwillnecessitatefuturechangeorders.

    Contractorsnotcompletingaprojectwhentheyhavereceivedthebulkoftheprojectconstructioncontractpayments,therebyleavingtheCitytofindanewcontractortocompletetheopenitemsontheprojectpunchlist.

    Theuseofpastperformancecriteriaalsoeliminatestherevolvingdoorofbadcontractorssecuringcityworkbyvirtueofalowestcostbid.TheCityofLosAngelesgoesevenfurtherwithits“ContractorResponsibilityOrdinance”:

    Priortoawardingacontract,theCityshallmakeadeterminationthattheprospectivecontractorisonethathasthenecessaryquality,fitnessandcapacitytoperformtheworksetforthinthecontract.Responsibilitywillbedeterminedbyeachawardingauthorityfromreliableinformationconcerninganumberofcriteria,includingbutnotlimitedto:managementexpertise;technicalqualifications;experience;organization,material,equipmentandfacilitiesnecessarytoperformthework;financialresources;satisfactoryperformanceofothercontracts:satisfactoryrecordofcompliancewithrelevantlawsandregulations:andsatisfactoryrecordofbusinessintegrity.10

  • SanFrancisco’sCityConstructionProgram

    13

    Inallthereare18differentcategoriesthatareevaluatedintheLosAngelesfinalreport.Poorresultswillprecludeafirmfromfurtherworkaswillfalsificationofanyofthesurveyanswers.

    4. The Role of “LBEs” TheCityhasspecificsocialpolicygoalsincorporatedintoitscontractingrequirements.Itprovidespreferencepointsinawardingcontractstothosecontractorswhousesubcontractorswhomaybenew,small,orfromdisadvantagedbackgroundsorneighborhoods.Thesediversitygoalsandthecomprehensivestatutoryregulationsthatgovernthem,alterexistingprimecontractorandsubcontractorworkingrelationships.Manycontractorsarerequiredtousesubcontractors,withwhomtheymayneverhaveworked,towinCitycontracts.Thecontractorscannotdependonthecompetencyofthesesubcontractors.AllofthismakescontractingwiththeCityaveydifficultprocess.InparticularChapter14oftheCodeidentifiesthefollowingcategoriesofbusinessesthataregivenpreferenceinthepublicbuildingprocess:

    LBE‐ Local Business Enterprise Small LBEMBE‐Minority Business Enterprise Micro MBEWBE‐Womens Business Enterprise SBA‐LBEOBE‐ Other Business Enterprise Non‐profit LBE 11

    Numerouspreferencecategoriesandtheuniquerequirementsofeachcitydepartmentcreateextraworkandmanagementchallengesforbothcontractorsandsubcontractors.TheContractMonitoringDivision(CMD)oftheGeneralServicesAgency(GSA)ischargedwithenforcementoftherequirementsofChapter14(B)throughtwoseparateunits:acertificationunitthatqualifiesfirmsforcertificationmeetingcertainprescribedcriteria,andacomplianceunitthat“setsgoals”forhiringChapter14businessesinmostCitycontracts.Forexample,thecomplianceunitwilldeterminethepreferencecontentofeachelementoftheconstructionproject.Thereareapproximately1,700firmsthathavebeencertifiedforsome270differentcategoriesofbusinesstypesforeachspecificproject.TheCGJdidnotdetermineifthecertificationprocessincludedcertificationofcontractorperformance.Additionally,thereisChapter12,whichenforcesnon‐discriminationpracticesinthecertificationprocessandundertheCodeisenforcedbytheHumanRightsCommission(HRC).AlthoughtheCodestillplacesthisobligationontheHRC,thisfunctionhasbeentransferredtotheCMD.Finally,thereistheOfficeofEconomic&WorkforceDevelopment,which,underChapter6.22(g)oftheCode,administersandmonitorslocalhiringpolicyforconstructionintheCity.ContractorsdoingworkwiththeCityhavedescribedtheprocessas“byzantine.”Noonequestionsthemeritofthesocialgoal;ratheritisthecomplexityofmeetingitthatcreatesfrustration.SomecontractorsaredauntedbytheCity’sLBErequirement,sincesomeLBE

  • SanFrancisco’sCityConstructionProgram 14

    firmspossessgoodconstructionskillsbutlackconstructionmanagementandadministrativeskills.Whenasubcontractorfailstodeliveracceptableworkontime,itcancausesignificantprojectdelays,whichcanleadtoasignificantincreaseintotalprojectcostandjeopardizetheprimecontractor’sreputation.ThishasledtoareductioninthenumberofcontractorswillingtobidonCitybusiness.R&Patpresenthasonlyfourcontractorswhowillbidonmostoftheirconstructionprojects.

    5. Revisions to Chapter 6 Atpresent,acityworkgrouphasbeenformedtoidentifyadministrativeandsubstantivechangesthatshouldbemadeinChapter6oftheCode.InphaseItheworkgroupproposed43technicalchangestotheBOSthisspring.InphaseIIoftheproject,theworkgroupwillbeproposingthatChapter6oftheCodebemodifiedtoincludecontractorperformanceasanadditionalcriterioninawardingfixedbidconstructioncontracts.Inthecurrentlowestbidenvironment,itispossibleforacontractorwithatrackrecordofpoorqualityworkandfailuretomeetdeliveryschedulestowinnewconstructioncontractsmerelybecauseitwasthelowestbidder.ItisoftendifficultforDPWsupervisorypersonneltocollaboratewithlowbidcontractorsunderthesecircumstances.EventhoughperformanceisnotacriterioninthelowestbidenvironmentinSanFrancisco,theCityhasaprocessforexcludingcontractorsfrombiddingonnewconstruction.Theprocessiscalleddebarment.Acontractorcanbedebarreddueto“willful”misconductinanyaspectofthebiddingprocess,fromsubmittingfalseinformationintheproposaltofailuretocomplywiththetermsofthecontract.12TheCitydebarmentprocessisdifficult,andcurrentlynoCitycontractorsaredebarredorpreventedfrombiddingonnewconstructionprojects,regardlessofhowmanynoticesofnon‐compliancetheyhavereceivedfromtheCity.TheCSAissuedaCitywideConstructionauditreportinMayof2014thatprovidesanecdotalexamplesofCityprojectswhereconstructioncontractorsperformedpoorly.Thereportfoundthatpoor‐performingcontractorshavemorenon‐compliancenotices,higherprojectsoftcost(non‐constructioncosts)andmorechangeordersthanhighperformingcontractors.OneexamplecitedintheauditreportisanAirportcontractorwhoreceived59non‐compliancenoticesforimproperworkona$14millioncontracttoconstructabridgeattheAirport.13Itisnotclearwhysuchacontractorwasnotconsideredfordebarment,aprocessthatdoesnotappeartobeusedtoprotecttheCityfrompoorlyperformingcontractors.WeencouragetheBOStoamendChapter6oftheCodetoincludeconsiderationofcontractorpastperformanceinawardingfixedbidconstructioncontractsandtoimplementthechangeswiftly.Construction Project Management Projectmanagementcontrolsareveryimportantforensuringprojectqualityandformanagingconstructionprojectcosts.Wereviewedtwoimportantareasofconstruction

  • SanFrancisco’sCityConstructionProgram

    15

    projectcontrol:changeordermanagementandprojectconstructioncontractclose‐outprocedures.Additionally,welookedattheconsequencesofnon‐compliancewiththeseandotherpolicies.

    1. Change Order Management Largeconstructionprojectswillhavemanyhundredsofchangeorders.Anillustrativelistappearsbelow.14

    Project Total Cost # Of Change Orders SanFranciscoGeneralHospital

    $887million 607PublicSafetyBuilding $243million 389NorthBeachBranchLibrary $14million 116BayviewBranchLibrary $14million 102PalegaRecreationCenter $14.4million 175MissionDoloresPark $18million 103Thechangeorderprocessgeneratesmanydocumentsthatneedtobemanagedandroutedforapprovalandsignoff.Itstartswithacontractorpreparingaproposedchangeorderwhichleadstoanegotiationprocessandanindependentcostanalysisforchangeordersover$20,000.Onceachangeorderhasbeenapproved,itrequiresacontractmodification.Theserequireauthorizingsignaturesaswellas,insomecases,revisedarchitecturalplansorengineeringspecifications.Allofthechangeorderdocumentsneedtobemanaged,sothatapprovalscanbetracked,contractrevisionscanbenoted,andkeydocumentscanberetrievedasneeded.ThefollowingexamplestakenfrommanyCSAauditreportsdemonstratethatmanagementprocessesforchangeordersaredepartmentspecific,notcitywide,andarefrequentlyignoredinpractice.TheApril2014CSAauditofchangeordersonthe$243millionPublicSafetyBuildingprojectfound:15

    DPWdocumentedproposedchangeorders,but,contrarytodepartmentalprocedures,didnotdocumentthenegotiationsforthoseexceeding$20,000.

    DPWdidnotpreparetherequiredindependentcostestimatesforproposedchangeordersexceeding$20,000,sohadnonegotiatingleveragewhenthecontractorsubmittedrevisedcosts.

    Proposedchangeordersrequestingtimeextensionsdidnotcontainsufficientsupportingdocumentation,increasingtheriskofpossibleapprovalofunwarrantedtimeextensions.

    TheCSAissuedabout20changeorderauditreportsoverthelastfouryears.Theauditshighlightedsignificantproceduralproblemsthatcanbeimprovedwithallcitydepartments

  • SanFrancisco’sCityConstructionProgram 16

    usingthesamechangeorderprocedures,greateradherencetoexistingchangeorderpoliciesandtheimplementationofcitywidechangeordermanagementreports.Theauditsfoundcontrolweaknessesinlargeandmidsizeconstructionprojects.TheCSAApril2013AuditofthePUC$39.2millionAlamedaSiphon#4foundthat40%ofprojectchangeorderswereissuedand47%wereapprovedaftersubstantialcompletionoftheconstructionproject.Approvingchangeordersafterthecontractorhascompletedtheworkiscontrarytotheintentofthechangeordermanagementprocess.Changeordersareafactoflifeinconstruction;someareduetounforeseenbuildingconditionsandregulatoryrequirements,whileotherchangeordersareavoidableTwotypesofavoidablechangeordersaredesignerrorsandomissionsandclientrequestedchangesduringconstruction.Itisimportanttoreportalltypesofchangeordersandtoensurethatavoidablechangeordersreceiveahigherlevelofmanagementscrutiny.DPWhasastatedgoaloflimitingerrorandomissionchangeordersto3%oftotalprojectcost.Theextenttowhichtheyareachievingthat3%standardisnotclear.TheCGJbelievesthisshouldbeacitywidestandardthatshouldbereportedandenforcedforallconstructionprojects.TheAlamedaSiphonprojecthad196changeorderstotaling$6.8millionor21percentoftheoriginalcontractvalue.Asampleof40ofthe196changeordersfoundthatmodificationswererequiredbecauseof:6designerror,6designomission,12differingsiteconditions,8owner‐requested,3regulatoryrequirementandfiveothercategorychangeorders.16ACSAApril2013auditoftwomidsizeconstructionprojects,the$10.8millionChineseRecreationCenterandthe$4.6millionMissionClubhouseandPlaygroundrenovation,foundsignificantdepartmentpolicyviolations.ChangeordersfortheMissionClubhouseandPlaygroundrenovationamountedto$642,103or14percentoftheoriginalcontractvalue.ChangeordersfortheChineseRecreationCenteramountedto$1,587,540or15percentoftheoriginalcontractvalue.17Theauditfoundthefollowingdepartmentalpolicyviolations:

    R&Phasnopublishedchangeorderprocessesorprocedures. DPWdidnotadequatelyrecordpertinentinformationonallchangeorders. DPWdidnotobtainindependentestimatesforchangeordersofmorethan$20,000

    asrequiredbywrittenprocedures. BothR&PandDPWeachallowedanincreasetocontractormarkupswithouta

    contractmodificationascalledforbythecontract. Amajorityofcontractorchangeorderrequeststhatincludedaprojecttime

    extensiondidnotmeetcontractrequirements,andsomechangeorderrequestsweresubmittedlate.

    Insomeinstances,contractorsdidnotadheretochangeorderpricingrequirements.

  • SanFrancisco’sCityConstructionProgram

    17

    AnOctober2011BLAreporttotheBOSevaluatedthefrequencyandcosttotheCityofcontractchangeordersforlargeconstructionandprofessionalservicecontracts.ThereportsurveyedtenCitydepartmentsandreviewed218constructionandprofessionalservicecontractsover$5millionenteredintobetweenFiscalYear2006‐07andSeptember2011.Thereportfindingswerethat107or49.1%ofthelargeconstructionandprofessionalservicecontractshadchangeorderswithatotalcostof$295.2million,astaggeringsum.OneoftherecommendationsinthereportwastohavetheBOSrequestthatallCitydepartmentsmaintaincontractinformationinauniformmannerandthattheinformationbesummarizedandregularlyreportedtotheBOS.Weconcurwiththisrecommendation.

    2. Contract Close Outs CSAauditreportsexaminedasecondimportantconstructionmanagementprocess,theprocessusedtocloseoutcontractorconstructioncontracts.Theconstructioncontractcloseoutformallyendstheconstructionphaseofacapitalprojectandensuresthatallcontractualandlegalobligationshavebeenfulfilledbeforefinalpaymentisreleasedtothecontractor.EnsuringcompliancewithallcloseoutproceduresassurestheCitythatthecontractorusedcityresourcesappropriatelyandcompletedtheworkinaccordancewithcontractterms.TherewereanumberofDPWandnon‐DPWcontractcloseoutauditswhereCitydepartmentswerefoundtohaveskippedsomeofthecontractcloseoutprocedures.Inthecloseoutaudits,tworecurringfindingswerethatthedepartmentsfailedtouseacontractcloseoutchecklist,aconstructionindustrybestpractice,andthedepartmentswereunabletoprovideadequatedocumentationthatspecificaspectsoftheconstructioncontracthadbeenfulfilled.

    TheJuly2013closeoutauditofthecontractforthe$583millionLagunaHondaHospitalReplacementProgramfoundthatDPWwasunabletoverifyitscompliancewitheightof34applicablecloseoutprocedures.Similarly,theJuly2012closeoutauditofthe$332,000contractforChinatownPublicHealthCenterADAImprovementsPhaseIIfoundthatDPWdidnotrequirethecontractortocomplywiththefollowingsixcloseoutprocedures:18

    Submitallchangeordersbeforeworkwas95percentcomplete. AdvisetheCityofpendinginsurancechangeoverrequirements. NotifytheCityinwritingthattheworkwassubstantiallycompleteandreadyfor

    inspection. Submitconsentofsuretytofinalpayment. Submitacertifiedcopyofthepunchlistofremedialitemstobecompletedor

    corrected,statingthateachitemhasbeenotherwiseresolvedforacceptancebytheCity.

    NotifytheCityinwritingthatallpunchlistitemsofremedialworkwerecompletedandtheworkwasreadyforfinalinspection.

    Thatsaid,contractcloseoutscanbeproblematic,becausedepartmentsrelyonthecontractortofulfillallcontractrequirements.Inthecurrentconstruction‐boom

  • SanFrancisco’sCityConstructionProgram 18

    environmentinSanFrancisco,somecontractorsjustwalkawayfromthefinalpaymentandmoveontoanotherproject,ratherthandealwiththefinalpaperwork.Otherjurisdictionshaveexperiencedthissameproblem.Portland,Oregonisevaluatingalargerholdbackprovisioninthecontracttoreducethisbehavior.Department Interactions

    1. The DPW Architecture and Engineering staff Asmentionedearlier,DPW,hasoneofthemostdiverseconstructionportfoliointheCity.Notonlydoesitmanageitsownprojects,italsoworkswithotherCitydepartmentsasneeded.ThePort,MTAandR&PrelyonDPWforgeneralconstruction.DPWhasexpertiseinremodels,seismicretrofitting,hydraulicsandnewconstruction.R&P,SFFDandthePoliceDepartmenthavehundredsofbuildingsthatneedtoberemodeledorreplaced.Theseinclude220cityparks,82recreationcenters,51firestationsand12policestations.ThePUCreliesonDPWforspecificexpertisearoundhydraulics.DPWmanagesbothbuilding(vertical)androadandsewer(horizontal)constructionprojectswithaFY2014‐2015budgetedarchitectureandengineeringstaffof531fulltimeequivalent(FTE)employees.Mostofthesalariesandbenefitsoftheseemployeesarechargedtotheindividualconstructionprojects(capitalized)andnottoDPW’soperatingbudget.DPWmanagesabout41%ofthebudgetedcitywide1,286FTEs.

    Annual Annual Salary Salary

    Ordinance OrdinanceF2014-2015 F2015-2016Budgeted Budgeted

    FTEs FTEs DPW- Architecture Bureau 252.0 258.9 DPW- Engineering Bureau 278.7 287.6 DPW- Total Arch+ Engineers FTEs 530.7 546.5

    41% 41%

    Airport- Bureau of Design and Construction 167.3 181.7 MTA -Capital Programs & Construction 156.4 158.9 Port - Engineering and Environmental 26.5 26.5 PUC- Engineering 389.0 394.0 Recreation and Parks- General Fund work order fund 16.0 16.0 Citywide total 1,285.9 1,323.7 F2015-2016 % increase in FTEs 37.8 F2015-2016 increase in FTEs 2.9% 19

  • SanFrancisco’sCityConstructionProgram

    19

    TheremaybeanopportunityforSanFranciscotobetterutilizethe1,286budgetedFTEswhoarecurrentlyspreadamongthesixCityDepartments.WerecommendtheCityhavetheCSAbenchmarkSanFrancisco’scitywideconstructionmanagementstafforganizationalstructureagainstcomparablecities.DPW’sstaffingstructurecontrastswiththestaffingoflargeconstructionfirms.Historically,constructionfirmsmaintainedadeepstaffoftradespeopleandspecialists.LargecontractingfirmsalongwithcitieslikePortlandobservedthatthevarietyofconstructionprojectscreatesamismatchbetweentheskillsrequiredforcurrentprojectsandtheskillsoftheirstaff.Theresultisduplicatelaborcostswhenoutsidefirmsareretained.Ascompetitiveconditionsdemandedmorecosteffectiveapproachesandnimbleoperations,constructionfirmsandcitieslikePortlandeliminatedinternalspecialistdepartmentsanddevelopedrelationshipswithsubcontractingfirms.Intervieweessharedthatfewmajorcitiesmaintainalargepublicworksstaffofspecialtydesignandengineeringemployees.

    2. Disparate Policies and SystemsSincethesixCityDepartmentsmanagesitsownconstructionprojects,itisnotsurprisingtheyhavedevelopedtheirowndepartment‐specificconstructionprocessesandsystems.Whenmorethanonecitydepartmentworksonaconstructionproject,itisimpossibletocombinedepartmentconstructioninformation,becausedataiscapturedand/ordefineddifferently.Forthatreasonitisdifficulttoproducecitywideconstructionprojectreports.CSAauditsfoundthatDPWandR&Pprojectchangeordersweredifficulttocoordinate,becauseindividualdepartmentalsystemsanddepartmentaloperatingprocedureswerenotaligned.R&PlacksawrittenchangeorderpolicyandDPW’ssystemsareincompatiblewithR&P’sworkflowforprocessingchangeorders.

    3. Errors and Omissions CitydepartmentsthatutilizeDPWforarchitectureanddesignworkassumeariskthattheywouldnototherwisehaveifthecitydepartmentretainedanoutsidefirm.CitydepartmentscannotsueDPWfordesignandomissionerrors.ADPWdesignerrororomissionforcesitsCityclientstoreducethescopeofaprojectorfindadditionalfundingforcompletion.DPWacknowledgesthattherehavebeenissuesonsomeprojects,butmaintainsthatallclientsaremadewhole;someclientdepartmentsinterviewedbytheCGJwoulddisagree.

    4. Recreation and Park OneofthesixCityDepartments,R&P,warrantshighlighting,becauseDPWmanagesallR&PverticalprojectsandbecauseR&Pprojectselicitalotofcitizeninput.AlthoughR&Phasexpertiseinthelandscapeaspectsofconstruction,itoftenneedstorelyonDPWforstructuralprojects,fromplaygroundcenterstotenniscourtstobathrooms.

  • SanFrancisco’sCityConstructionProgram 20

    R&Phasateamofninespecialistsincludingprojectmanagers,seniorplanners,architectsandlandscapearchitects.SomearespecialistsinareaslikeirrigationorADA20access.TheyworkwithDPWonaMemorandumofUnderstandingwheretheR&Pprojectmanageristhepointpersononthejob,responsibleformaintenanceoftheprojectbudgetandschedule.Oftheir70activeprojects,20%areverticalprojectsand80%ofallprojectsareunder$1million.Thesesmallprojectsrequireextensivepublicmeetingsbecausethecommunityismorelikelytobecomeinvolvedwithaneighborhoodparkremodelthanapumpingstation.IndeedarecentSanFranciscoChroniclearticledetailedtherenovationofthe760squarefootrestroominWashingtonSquareParkthathadanextensivecommunityreviewprocessandultimatelycost$1.2million,whichwas20%overbudget.21DPWprovidesthedesignservicesforR&P,howeverthecostisoftenhigherthanwhatanoutsidedesignerwouldcharge.Forsmallprojects,thishigherdesignfeerepresentsasignificantportionoftheprojectbudget.Oncedesigned,DPWmanagestheconstructionusingitsresidentengineerteam.Theyhandlecontractorselection,fromthesmalluniverseofcontractorswillingtodoR&Pprojects.TheDPWengineerandR&Pprojectmanagercoordinatethecompletionoftheproject.Lackofclarityinthissharedrolestructureleadstoproblemsofaccountabilityforvariousaspectsoftheproject. Information Technology DPW’scurrentsystemsenvironmentiscomplicatedandobsolete.Morethan20yearsago,DPWdevelopedanAS400systemtomanageconstructionprojectdataatalevelthatwasmoregranularthanwhatwasavailablefromtheCity’sfinancialsystemFAMIS.DPWusestheElectronicJobOrderAccountingSystem(EJOA)tomanagebudgetsandadherencetotimelinesandinterfaceswithFAMISinarudimentaryway.EJOAcannothandleon‐linechangeordermanagementorprojectupdates.Theselimitationsledonemanagertosaythatthey“needtokeepreallygoodemailtrailsofdecisions.”Thatsaid,it should be noted that several contractors commented on the strong attention to detail of the DPW staff, despite their lack of adequate information systems. ThingsarenobetterinotherareasoftheCity.The Department of Public Health, for example, reports that it does not maintain electronic records of originally approved construction contract amounts at all, thus preventing comparison with amended or modified amounts, unless a manual review of individual contract document files is made. FAMIS,thecitywidefinancialsystem,istargetedforreplacementinFY2018.22DPWrecognizestheneedforcommonconstructionprojectdataarchitectureandimprovedprojectreportingandisdevelopingDPWconstructionmanagementsystemspecificationsaspartoftheFAMISprojectteam.WecommendDPWforrecognizingtheproblemanddevelopingadepartmentplantoaddresstheproblem.IndividualCitydepartmentsrecognizetheneedfornewsystemstobettercontrolaneverincreasingprojectworkload.IftheCitydoesnotprovideleadership,departmentswillberequiredtoactindependentlywhichwillperpetuatetheexistinglackofintegratedcitywideconstructionprojectreporting.

  • SanFrancisco’sCityConstructionProgram

    21

    Theproblemisacitywideproblemthatshouldbeaddressedthroughthedevelopmentofacitywideinformationtechnologyplanthataddresses(i)thecoordinatedreplacementofthecitywidefinancialsystem(FAMIS),and(ii)theadoptionofcitywideconstructionprocedures,includingtheimplementationofacitywideconstructionmanagementsystem.ReplacingFAMISmayimprovesomereporting,butitisafinancialsystem,notaconstructionmanagementapplication.Asdescribedearlier,DPWlacksanelectronicdocumentmanagementsystemtocatalog,storeandretrievetherequisitedocumentationforchangeorders.Asaresult,theengineeringandarchitecturebureauswithinDPWhavetheirowndocumentmanagementprocesses.Similarly,there is no centralized database in the City that provides for monitoring contract change orders. Instead, the information must be obtained from individual departments, each of which records and reports the information differently, making a consolidated roll-up of citywide construction information impossible. WerecommendthattheDepartmentofTechnology(DT)retainaconsultingfirmwithextensiveconstructionmanagementsystemexpertisetodevelopcitywidesystemsrequirementsfortheimplementationofaflexiblesystemthatthousandsofcityconstructionprojectemployeeswillbeabletousetobettermanageconstructionefforts.However,theneedforaconstructionmanagementsystemisnotaddressedinthe2016InformationandCommunicationTechnology(ICT)planforFiscalYears2016‐2020.ItisunacceptablefortheCitytoproposetospendinexcessof$25billiondollarsoverthenexttenyearswhentheCitylacksbothcitywideconstructionproceduresandacitywideconstructionmanagementsystem. Transparency and Reporting Understandably,thelackofintegratedmanagementsystemsandfailuretofollowcommonpoliciesandproceduresinmanagingconstructionprojectsmakesitimpossibletogetanup‐to‐datesnapshotofthecurrentstatusofallactiveconstructionprojectsintheCity.Inthecurrentenvironment,theBLAandtheCSAmustusealabor‐intensivesamplingprocesstogetcitywideinformationinsteadofusingcitywidereports.WefounditdifficulttoworkwithindividualDPWconstructionprojectreportswhenmorethanoneCitydepartmentwasinvolvedinaconstructionproject.ForprojectswhereDPWisprovidingspecificprojectserviceslikeengineeringbutnotmanagingtheentireproject,DPWprojectreportsonlyhaveengineeringprojectcostinformation.DPWreportsthatsummarizemultipleconstructionprojectsaredifficulttousebecauseDPWoftenisnotprovidingthesameclientservicesforallconstructionprojects. Thelackofcitywidepoliciesandtheinconsistentapplicationofexistingpoliciesmakeitimpossibletocreatecitywidereportsthatsummarizekeyconstructionperformancemetricslikenoticesofnon‐compliance,changeorders,actualconstructionsoftcosts

  • SanFrancisco’sCityConstructionProgram 22

    (design,architecture,engineering,etc.)andacomparisonofactualprojectcosttobudgetedprojectcost.ItisimpossibletoprepareacitywidereportofactualconstructionexpensesforallsixCitydepartments,asevidencedbytheinabilityoftheCSAtoincludeactualcitywideconstructioncostsintheirMay2014constructionauditreport.Thecurrentsituationwheretherearenocitywideconstructionreportsthatcompareactualprojectspendingtooriginalbudgetforcompletedprojectsviolatesbothcommonsenseandbasicgoodmanagementpractice.Allowingthecurrentsituationtocontinuewhenthemajorityofthe$25billionten‐yearCapitalPlanspendingisforconstructionisunacceptable.Governmentconstructionprojectsaredifferentfromprivateconstructionprojects,becausetheyarepublicprojectsandsubjecttomanylevelsofoversightthatdonotexistintheprivateworld.PublicprojectsshouldbesubjecttocitizenoversightandtheoversightofmanyCityDepartments.Forexample,theCMD,(asmentionedearlier)reviewstheLBEcomponentofconstructionprojects.ConstructionprojectmanagersneedtodealwithreportingrequirementsthatareuniquetoeachCitydepartmentthatoverseesaspecificaspectofaconstructionproject.Governmentconstructionprojectsalsohavemorestringentprojectdocumentationandapprovalrequirements.TheCityhasallowedeachofthesixCitydepartmentstodefineandimplementdepartmentalsolutionsratherthanestablishingacitywidestandard.Thissiloproblemmirrorsthecity’sinformationtechnologyproblemthatwasaddressedinthe2011‐2012CivilGrandJuryreport,DéjàvuAllOverAgain.Thesolutionforbothproblemsrequiresthecitytodevelopacitywideplanandgiveonecitydepartmenttheresponsibilityfordesigningandimplementingcitywidesolutions.Developingacitywideconstructionreportingsolutionisadifficulttask,becausedepartmentslikethePUCandtheAirporthaveafewverylargeconstructionprojectsthatspanmanyyears.ThePort,MTA,R&P,andDPWhavemanysmallconstructionprojects.376or70%ofthe535activeDPWprojectshaveabudgetoflessthan$3milliondollars.Identifyingandimplementinganenterpriseconstructionmanagementsystemthatfitsdepartmentswithlargeandsmallprojectsisdifficult.Nonetheless,thecurrentlackofcitywideconstructionpoliciesandproceduresandtheinabilitytogenerateaccuratecitywideconstructionreportsneedstobeaddressed.

    DPW active construction projects ‐ November 2014

    Cost of individual projects# of 

    projects% of total

    Over ten million dollars 46 9%Three million to ten million dollars 113 21%Under three million dollars 376 70%

    535 100% Thistheproblemneedstobeaddressedtoenablecitizenoversightofindividualconstructionprojects.Accesstoinformationonindividualconstructionprojectsisnotcurrentlypossible,becausetherearenofinalreportsissuedforeachcompleted

  • SanFrancisco’sCityConstructionProgram

    23

    constructionprojectwhichreportoriginal,budgetedprojectcostandactualprojectcostaswellaskeyperformanceindicatorsliketheactualnumber,typeandcostofprojectchangeorders.Accordingtointerviewees,othercitiesproducereportsand/ormaintainwebsitesthatprovidedetailedinformationonconstructionprojects.ThepeopleofSanFranciscodeservethetoolstomonitorconstructionspendingthatisfundedbybondsthevoterswereaskedtoapprove.UntiltheCityimplementscitywideconstructionpolicesandreportingstandardssupportedbyacitywideconstructionmanagementsystem,meaningfulinformationaboutconstructionprojectswillnotbeavailabletothecitizensofSanFrancisco. Lack of Independent Oversight FiveofthesixCitydepartmentsreporttoanindependentcommission.Forexample,thePUCCommissionandtheR&PCapitalCommitteearerequiredunderChapter6oftheCodetoreviewprojectchangeorderswhenthecumulativecostofchangeordersforanindividualprojectexceeds10%ofbudgetedprojectcost.DPWclientdepartmentprojects,likethoseforSFFDandSFPD,aresubjecttothesamecommissionchangeorderoversight.DPW’sownprojectsarenotsubjecttothesameindependentoversight;thereisnoDPWCommission.TheBOSplaysnoroleintheapproval,ongoingreportingoroversightofanyconstructionproject.ThejurywastoldthattheBOSwasnotgivenaroleinapprovingconstructioncontractstopreventpoliticizingtheprocess.However,thefailureoftheBOStoexerciseregularoversightovercitywideconstructionspendingneedstobeexamined.TheCGJcannotfindanyreasonwhytheBOSshouldnotexerciseoversightauthorityafteracontracthasbeenawarded.ABLAauditnotedthelackofscrutiny:23

    Construction contracts are not subject to BOS approval, whereas professional services contracts over $10 million do require BOS approval. The BOS must approve non-construction change orders greater than $500,000.

    By comparison, in three other large jurisdictions in California, the threshold amount for a governing body approval was from $25,000 to $250,000, with some variances for construction and certain other contracts. Therefore, there is significantly less scrutiny of contracts required by the BOS for contracts with a value of less than $10 million.

    Several BLA recommendations addressed the oversight issue, including (i) lowering the contract approval threshold to a number consistent with other cities, and (ii) changing the change order approval threshold to a cumulative amount as opposed to the current single change order threshold of $500,000.

    Perhaps the most important recommendation, and the one with which the CGJ is in total agreementisthis:

    TheBoardofSupervisorsshouldrequestthatallCitydepartmentsmaintaincontract

  • SanFrancisco’sCityConstructionProgram 24

    informationinauniformmanner,recordingoriginalcontractamounts,eachchangeorderandchangeincontractvalue,andfinalcontractamounts,tobesummarizedandregularlyreportedtotheBoardofSupervisors.24

    Weinterviewedemployeesinotherlargecitiesandfoundthatallofthecitieshadindependentoversightofpublicworksconstructionprojects.Allofthecitiesweresearchedrequiredthatconstructionprojectchangeordersthatexceededaspecificthresholdrequirecitycouncilapproval.OtherlargeU.S.citieshaveimplementedindependentoversightofconstructionprojectsthroughthecreationofanindependentdepartmentofcontractmanagementintheirDPWdepartment.ThisunitmonitorsDPWconstructionprojectadherencetocitypolicies.Inthesecities,thecontractmanagementdepartmentisindependentanddoesnotreporttoDPWarchitects,engineersorprojectmanagers.ThelackofBOSoversightofallCityconstructioncontractsandthelackofindependentoversightofDPWdepartmentconstructionprojectsshouldberemedied.

  • SanFrancisco’sCityConstructionProgram

    25

    FINDINGS

    Basedonthediscussionabove,wehavethefollowingfindings:F1. DPWshouldbecommendedforitsadoptionoftheCMGCanddesign‐buildstructures

    inlarge‐scaleprojectsandtheChapter6workgroupshouldbecommendedforworkingtostreamlinetheconstructioncontractingprocessintheCity.

    F2. Thecurrentlowestbid‐contractingenvironmentisnotoptimalfortheCity,sinceitincreasescostsduetoadditionalprojectchangeorders,anditreducesthenumberofqualitycontractorswillingtobidonCityprojects.

    F3. Thecomplexityofthecontractingenvironment,especiallyasitrelatestoLBEs,reducesthepoolofcontractorswillingtodobusinesswiththeCity,therebylimitingvendorselection.

    F4. Changeordersarenotmanageduniformlyacrossdepartments,whichexposestheCitytoincreasedprojectcosts.

    F5. Constructioncontractcloseoutproceduresarenotfollowed,whichcanresultintheCitynotreceivingtheservicesitcontractedtoreceive.

    F6. ThevarietyofconstructionprojectsintheCitycreatesamismatchbetweenthedesignandengineeringskillsrequiredforcurrentprojectsandtheskillsofthestaff,resultinginduplicatelaborcostswhenoutsidefirmsareretainedandexcesscapacitywhenthereisadeclineinconstructionactivity.

    F7. ThelackofintegratedconstructionmanagementsystemsandthefailuretofollowcentralizedconstructionmanagementpoliciesandprocedurespreventstheCityfromgeneratingcitywideconstructionreports.

    F8. TheCitydoesnothaveanindependentmanagementgroupreviewingcitywideconstructionperformancereportsandmonitoringadherencetochangeordersandconstructioncontractcloseoutpoliciesandprocedures.

    F9. SanFranciscoCitydepartmentsdonotissuefinalreportsonconstructionprojectsthatarereadilyavailabletoitscitizens.

    RECOMMENDATIONS R1. None

    R2. TheBOSshouldamendChapter6oftheAdministrativeCodetorequirecontractorperformanceasanadditionalcriterionforawardingconstructioncontracts.

  • SanFrancisco’sCityConstructionProgram 26

    R3. The CGJ recommends that the proposed Chapter 6 amendment make past performance a construction award criterion for all future City construction contracts including LBE subcontracts.

    R4. The Office of the Controller should implement a standardized change order management policy and require all City departments to adhere to the new change order policy.

    R5. The Office of the Controller should implement a standardized construction contract closeout policy and require all City departments to adhere to any new policy.

    R6. The BOS should request BLA or CSA to benchmark the City’s design and engineering workforce organizational structure against comparable cities and issue a report within a reasonable timeframe.

    R7. The Mayor should allocate financial resources in the current City budget to fund the Department of Technology hiring a consulting firm with extensive construction management expertise to develop citywide system requirements for the implementation of a construction management system.

    R8. Within a reasonable timeframe, the BOS should either request the CSA or BLA, or retain an outside firm, to benchmark the independent construction management structure of other cities and develop recommendations applicable to San Francisco.

    R9. The BOS should require each City department to issue final project construction reports within nine months of project completion for all construction projects and for the reports to be posted on each department’s website.

    REQUEST FOR RESPONSES PursuanttoPenalCodesection933.05,thegrandjuryrequestsresponsesasfollows:

    Findings Recommendations Response Required

    F1.DPWshouldbecommendedforitsadoptionoftheCMGCanddesign‐buildstructuresinlarge‐scaleprojectsandtheChapter6workgroupshouldbecommendedforworkingtostreamlinetheconstructioncontractingprocessintheCity.

    None

    F2.Thecurrentlowestbid‐contractingenvironmentisnotoptimalfortheCity,sinceitincreasescostsdue

    R2.TheBOSshouldamendChapter6oftheAdministrativeCodetorequirecontractorperformanceasanadditional

    BOS

  • SanFrancisco’sCityConstructionProgram

    27

    toadditionalprojectchangeorders,anditreducesthenumberofqualitycontractorswillingtobidonCityprojects.

    criterionforconstructioncontracts.

    F3.Thecomplexityofthecontractingenvironment,especiallyasitrelatestoLBEs,reducesthepoolofcontractorswillingtodobusinesswiththeCity,therebylimitingvendorselection.

    F4.Changeordersarenotmanageduniformlyacrossdepartments,whichexposestheCitytoincreasedprojectcosts.

    R3. The CGJ recommends that the proposed Chapter 6 amendment make past performance a construction award criterion for all future City construction contracts including LBE subcontracts.

    R4.TheOfficeoftheControllershould implement a standardized change order management policy and require all City departments to adhere to any new change order policy.

    BOSMayorBOSMayorOfficeoftheController

    F5.Constructioncontractcloseoutproceduresarenotfollowed,whichcanresultintheCitynotreceivingtheservicesitcontractedtoreceive.

    R5.TheOfficeoftheControllershouldimplementastandardizedconstructioncontractcloseoutpolicyandrequireallCitydepartmentstoadheretoanynewpolicy.

    BOSMayorOfficeoftheController

    F6.ThevarietyofconstructionprojectsintheCitycreatesamismatchbetweenthedesignandengineeringskillsrequiredforcurrentprojectsandtheskillsofthestaff,resultinginduplicatelaborcostswhenoutsidefirmsareretainedandexcesscapacitywhenthereisadeclineinconstructionactivity.

    R6.The BOSshouldrequesttheBLAorCSAtobenchmarktheCity’sdesignandengineeringworkforceorganizationalstructureagainstcomparablecitiesandissueareport.

    BOSMayorOfficeoftheControllerDPW

    F7.Thelackofintegratedconstructionmanagementsystemsandthefailuretofollowcentralizedconstruction

    R7.TheMayorshouldallocatefinancialresourcesinthecurrentCitybudgettofundtheDepartmentofTechnologyhiringaconsultingfirm

    BOS

  • SanFrancisco’sCityConstructionProgram 28

    Reports issued by the Grand Jury do not identify individuals interviewed. Penal Code section 929 requires that reports of the Grand Jury not contain the name of any person or facts leading to the identity of any person who provides information to the Grand Jury.

    managementpoliciesandprocedurespreventstheCityfromgeneratingcitywideconstructionreports

    withextensiveconstructionmanagementexpertisetodevelopcitywidesystemrequirementsfortheimplementationofaconstructionmanagementsystem.

    MayorOfficeoftheControllerDPW

    F8.TheCitydoesnothaveanindependentmanagementgroupreviewingcitywideconstructionperformancereportsandmonitoringadherencetochangeordersandconstructioncontractcloseoutpoliciesandprocedures.

    R8.The BOSshouldeitherrequesttheCSAorBLA,orretainanoutsidefirm,tobenchmarktheindependentconstructionmanagementstructureofothercitiesanddeveloprecommendationsapplicabletoSanFrancisco.

    BOSMayorOfficeoftheController

    F9.SanFranciscoCitydepartmentsdonotissuefinalreportsonconstructionprojectsthatarereadilyavailabletoitscitizens.

    R9.TheBOSshouldrequireallCitydepartmentstoissuefinalprojectconstructionreportswithinninemonthofprojectcompletionforallconstructionprojectsandforthereportstobepostedoneachdepartment’swebsite.

    BOSMayorOfficeoftheController

  • SanFrancisco’sCityConstructionProgram

    29

    GLOSSARY Change Orders – Work that is added or deleted from the original scope of work for a contract Close Out Procedure – The process by which an awarding agency ensures that all provisions of the contract have been fulfilled

    Construction Management General Contractor - A process whereby an owner engages a contractor during the design process to provide input into the constructability of the design

    Design-Build - A method to deliver a construction project where the design and construction are delivered by the same entity

    Punch list - A list of tasks to be completed at the end of a construction project

    Turnkey Solution - An approach that can be immediately implemented in a given business process

    ACRONYMS

    BLA – Budget and Legislative Analyst

    BOS – Board of Supervisors

    CGJ – Civil Grand Jury

    CGOBOC – Citizens’ General Obligation Bond Oversight Committee

    CMD – Contract Monitoring Division

    CSA – City Services Auditor

    DT – Department of Technology

    DPW – Department of Public Works

    FTE – Full-Time Equivalent

    HRC – Human Rights Commission

    LBE – Local Business Enterprise

    MTA - Municipal Transportation Agency

    PUC – San Francisco Public Utilities Commission

    R&P – Recreation and Park Department

    SFFD – San Francisco Fire Department

  • SanFrancisco’sCityConstructionProgram 30

    ENDNOTES 1 One SF – Building Our Future: The City and County of San Francisco Proposed Capital Plan, FY2016 – 2025. 2 Department of Public Works, Project/Client Table, November 2015. 3 J.K. Dineen, “Reinvention as Usual, The San Francisco Business Times, April 27, 2008. 4 Ibid. 5 San Francisco Administrative Code, Chapter 6, Section 20 (A) & (B). 6 San Francisco Administrative Code, Chapter 6, Section 6.1 (K) & (L). 7 City and County of San Francisco, Office of the Controller - City Services Auditor, Citywide Construction: Adopting Leading Practices Could Improve the City’s Construction Contractor Bid Pool, May 20,2014, 3. 8 Ibid., D-2. 9 Ibid., 4. 10 City of Los Angeles, Ordinance #173677, Article 14, Contractor Responsibility Program, Sec 10.40.2. 11 The San Francisco Administrative Code, Section 14B. 12 Grounds for Debarment, Section 28.3, administrative.sanfranciscocode.org. 13Office of the Controller - City Services, Auditor, May 20, 2014, op.cit. 11. 14 City and County of San Francisco, Budget and Legislative Analyst Report, Evaluation of Contract Change Orders for Large Construction and Professional Services Contracts , Oct. 17, 2011. 15 Office of the Controller - City Services Auditor, May 20, 2014, P3. 16 San Francisco Public Utilities Commission: Alameda Siphon Number 4 Construction Management, April 2014, P 10. 17City and County of San Francisco, Office of the Controller – City Services Auditor, Recreation and Park Department: Chinese Recreation Center and Mission Clubhouse and Playground Construction Management- The Change Management Process Requires Some Improvements, April 3, 2013. P 6. 18 Ibid. 19 City and County of San Francisco, Office of the Controller, Annual Salary Ordinance. 20 Americans with Disabilities Act 21 John King, “In Washington Square, no ordinary Restroom”, San Francisco Chronicle, 5/27/2015. 22 City and County of San Francisco, Proposed Information and Communication Technology (ICT) Plan Fiscal Years 2016-2020. 59. 23 City and County of San Francisco, Budget and Legislative Analyst Report, Evaluation of Contract Change Orders, Oct. 17, 2011. P 3. 24 Ibid.