Safety Evaluation Review of Topical Report for PWSCC ... · – for Alloy 82/182 DMWs, a...
Transcript of Safety Evaluation Review of Topical Report for PWSCC ... · – for Alloy 82/182 DMWs, a...
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Materials Reliability Program (MRP)
NRC Public Meeting - Rockville, MD
January 21, 2015
Safety Evaluation Review of Topical
Report for PWSCC Mitigation by Peening
(MRP-335, Revision 1)
2© 2015 Electric Power Research Institute, Inc. All rights reserved.
Introduction and Purpose
Richard Clemens - Wolf Creek
3© 2015 Electric Power Research Institute, Inc. All rights reserved.
Purpose
Present Industry’s positions that:
The technical basis already in the topical report and references is sufficient
for SE
• Additional confirmatory testing is not needed to support SE
Will be performed under Appendix B process controls
• Min/max essential variables not needed for standardization
• Performance criteria approach combined with 10 CFR 50 Appendix B
Criterion IX are appropriate and follow ASME Code Case precedent
SE desired mid-2015 to support industry application in 2016
• Originally scheduled to be completed by April 2015
4© 2015 Electric Power Research Institute, Inc. All rights reserved.
Basis for conclusion that the technical basis
for efficacy is sufficient for SE
Glenn White - Dominion Engineering, Inc.
5© 2015 Electric Power Research Institute, Inc. All rights reserved.
Sufficiency of Existing Technical Basis
Data and Research
Operating Experience
Nuclear Risk and Leakage Risk Met Conservatively
6© 2015 Electric Power Research Institute, Inc. All rights reserved.
Sufficiency of Existing Technical BasisData and Research
Extensive vendor testing of peening effectiveness, including
– Stress measurements of mockups
– Corrosion tests including in simulated primary water
• With and without pre-existing flaws
– Long-term sustainability testing
• Thermal stress relaxation
• Load cycling
Independent confirmatory testing sponsored by EPRI
– Stress measurements
– Long-term sustainability testing
7© 2015 Electric Power Research Institute, Inc. All rights reserved.
Sufficiency of Existing Technical BasisData and Research - Testing Documented in MRP-267R1 Demonstrating Peening Effectiveness
Performance criteria are applied to assess peening mitigation:– The residual stress in the surface region following peening is compressive to a
specified depth
– The total stress (residual plus operating) is within limits to prevent PWSCC
initiation in service
– The full area of material considered susceptible is effectively mitigated
– Analyses and testing confirm the resistance to PWSCC initiation on the treated
surface
– Analyses and testing demonstrate that the specified stress condition is maintained
for the remaining component operating life
8© 2015 Electric Power Research Institute, Inc. All rights reserved.
Stress measurements by XRD with progressive electropolishing and strain gauge adjustment
The measured samples represented a wide range of initial residual stress conditions prior to
peening
Flat plate samples of nickel-based alloys (Alloy 600, Alloy 132, Alloy 182) and stainless steels
(304 and 316L) were peened with ULP, ALP, or WJP
– Plate and welded plate samples
– Residual stress was compressive to a depth of at least 1.0 mm
Mock ups of BMNs were constructed of Alloy 600/82/182 and the BMN ID, OD, and J-groove
weld were peened with ULP or WJP
– Residual stress was compressive to a depth of at least 1.0-1.5 mm in most cases
– For WJP of the inner surface of BMNs, the residual stress was compressive to a depth of
about 0.5 mm
Sufficiency of Existing Technical BasisData and Research - Residual Stress Measurement
9© 2015 Electric Power Research Institute, Inc. All rights reserved.
Sufficiency of Existing Technical BasisData and Research - SCC Testing
Testing was performed by the LP and WJP vendors, as well as by an independent
lab (AREVA) sponsored by EPRI
Various samples with no pre-existing flaws were tested in various corrosive
environments
– SCC was detected in unpeened samples but not peened samples
Various pre-cracked coupons were peened and subjected to various SCC
environments
– Shallow cracks located in the compressive stress zone were effectively mitigated
– Cracks significantly deeper than the compressive zone tended to grow at a rate
similar to that for unpeened samples
WJP was applied to temper-colored, pre-cracked coupons
– No growth of the pre-existing cracks due to the WJP application itself was
observed
10© 2015 Electric Power Research Institute, Inc. All rights reserved.
Sufficiency of Existing Technical BasisData and Research - SCC Testing Mitigation of Growth of Pre-Existing Cracks (Data provided by MHI)
Alloy 600/316SS Weld Plate Samples Treated by WJP
USP
11© 2015 Electric Power Research Institute, Inc. All rights reserved.
Sufficiency of Existing Technical Basis Data and Research - Thermal Exposure and Load Cycling Testing (NRI) - Independent Testing Sponsored by EPRI
Evaluated the stress relaxation of a peening-induced compressive stress layer at and close to
the sample surface under the influence of load cycling and operating temperature
Samples manufactured at NRI from Alloy 600 plate material supplied by EPRI
Samples subject to different peening procedures by different vendors, with one set tested in
as-manufactured condition
Tested in an autoclave loop filled with simulated PWR water at 300°C for different numbers of
cycles
– Each cycle consists of a slow ramp-up to three fourths of yield strength, 10 day holding
period, and slow ramp-down to a load of zero
12© 2015 Electric Power Research Institute, Inc. All rights reserved.
Sufficiency of Existing Technical BasisData and Research - Corrosion Testing (AREVA) - Independent Testing Sponsored by EPRI
Alloy 182 weld deposits on Alloy 600
specimens were used to make U-bends
U-bends were treated with WJP, ULP, or ALP
U-bends were exposed to simulated PWR
water at 360°C for 3000 hours over two
phases of experimentation
U-bends treated with ULP, ALP, or WJP did
not have any cracks detected following PWR
water exposure
Spring Loaded U-Bend
ULP, WJP, and ALP are effective for mitigating PWSCC in heavily cold worked weld metal
13© 2015 Electric Power Research Institute, Inc. All rights reserved.
Sufficiency of Existing Technical BasisOperating Experience
Over a decade of implementation in BWRs and PWRs for mitigating PWSCC in Alloy 600/82/182/132
– Water Jet Peening
– Laser Peening
Extensive additional PWR experience with other peening methods
– Abrasive water jet (AWJ) peening
– Shot peening of steam generator tubing
– Pressurizer heater sheaths
– Alloy 718 fuel assembly screws
Applied in other industries for safety critical components, asset
management, and material performance improvement
14© 2015 Electric Power Research Institute, Inc. All rights reserved.
Sufficiency of Existing Technical BasisOperating Experience - Peening Mitigation in Japanese PWRs and BWRs
Japanese PWRs (starting in 2001)
– At least 23 out of 24 PWR units have applied WJP or ULP to BMNs and/or RV inlet/outlet
nozzle DMWs
– WJP and ULP have also been applied to RV safety injection nozzles
– Ultrasonic Shot Peening (USP) has been applied to
Steam generator inlet or outlet nozzles at more than 10 PWRs
9 replacement RV heads with Alloy 690 nozzles
Japanese BWRs (starting in 1999)
– WJP and ULP have extensively been applied to core shrouds and bottom head
penetrations (i.e., CRD stud tubes)
– Applying to new ABWR units during the fabrication and construction phases
15© 2015 Electric Power Research Institute, Inc. All rights reserved.
Sufficiency of Existing Technical BasisNuclear Risk and Leakage Risk Met Conservatively
Deterministic and probabilistic analyses were used to determine
appropriate inspection requirements for Alloy 82/182 piping butt welds
and RPVHPNs mitigated by peening
Deterministic analyses assess the effect of peening on crack growth as
a function of time for various crack types at different locations
Probabilistic analyses assess the effect of peening on the probability of
pressure boundary leakage or rupture assuming reduced frequency of
inspection– Component loading including effect of peening on residual stress field
– PWSCC crack initiation
– PWSCC crack growth
– Simulation of various inspections including UT, ET, and direct visual exam (VE)
Main probabilistic cases do not take any credit for ET exams
16© 2015 Electric Power Research Institute, Inc. All rights reserved.
Sufficiency of Existing Technical BasisNuclear Risk and Leakage Risk Met Conservatively - Conclusions
Deterministic analysis shows that peening eliminates or slows
growth for cracks that are sufficiently shallow
Probabilistic analyses show that peening mitigation with the
recommended inspection requirements and intervals results in:– for Alloy 82/182 DMWs, a probability of leakage that is greatly reduced compared to that for no
mitigation and standard intervals, demonstrating a much reduced probability of a flaw reaching its
critical size
– for RPVHPNs, an acceptably low nozzle ejection frequency (per the approach of MRP-105), and
also a nozzle ejection frequency that is close to that calculated for no mitigation and standard
intervals (i.e., risk neutral)
Probabilistic analyses include significant conservatisms such
that benefits of peening tend to be under predicted
No safety issues associated with peening
17© 2015 Electric Power Research Institute, Inc. All rights reserved.
ASME Code and Standards
Richard Gimple - Wolf Creek
18© 2015 Electric Power Research Institute, Inc. All rights reserved.
ASME Code and Standards
Performance Based Standard vs Prescriptive Standard:
– A performance based standard focuses on desired characteristics
of the final product, service or activity rather than requirements for
the processes to produce it
Performance criteria specify the objectives that when met assure
the final outcome is sufficient
Appropriate for activities where proprietary information is involved
Encourages innovation and allows adaptation to improvements
and alternative processes/techniques
– Initially identified for the appropriate approach in N-770 for MSIP
19© 2015 Electric Power Research Institute, Inc. All rights reserved.
ASME Code and Standards
Code Case N-770-4 integrated peening mitigation performance criteria
appropriate for reduced inspection requirements
Performance criteria approach similar to that taken for MSIP was used
Japanese experience, Japanese JANTI VIP-03 and presentations by
representatives of MHI and Hitachi provided International input for ASME
Technical basis provided through MRP-267 and MRP-335 and PVP papers
Peening performance criteria and pre- and post-peening examinations
evaluated and approved through the consensus process
Approved by the ASME Code as Code Case N-770-4 on May 7, 2014
Significant International experience and review in Japan by JANTI
Strong fully vetted technical basis by EPRI and PVP
Take-away from ASME process: significant technical basis with over 10 years of application
experience, ASME determined this is not a Repair/Replacement activity requiring codification of the
process, performance criteria is the appropriate approach for proprietary peening techniques
20© 2015 Electric Power Research Institute, Inc. All rights reserved.
ASME Code and Standards
Draft Code Case N-729-5 highlights:
– Maintains the performance criteria approach used in Code Case N-770-4
– Utilizes the same technical basis for the process with additional analysis
specific to the impact of the RVH penetration inspection
– Adjusts performance criteria where needed to account for different
configurations of RVH penetrations
Same approach as ASME Code as Code Case N-770-4
Strong technical basis (same as CC N-770-4)
Location specific analysis of peening application on inspection requirements to ensure no
increase in safety risk relative to the current inspections of unmitigated penetrations
Take-away: significant Industry support, strong technical basis, an improved safety (risk of
failure) position, not an ASME Repair/Replacement activity
21© 2015 Electric Power Research Institute, Inc. All rights reserved.
Implementation Guidance for Consistency
Jeff Wilson - Exelon
22© 2015 Electric Power Research Institute, Inc. All rights reserved.
Peening Process – Development to Implementation
COMPRESSIVE
DEPTH
COVERAGE
AREA
IMPLEMENT PEENING UNDER
SPECIAL PROCESS CONTROLS
(10 CFR 50 APPENDIX B
CRITERION IX)
---
QUALITY RECORDS VALIDATE
PROCESS WITHIN ESSENTIAL
VARIABLE LIMITS
---
LICENSEE REVIEWS /
APPROVES PEENING
EFFECTIVENESS
---
PROCESS / RESULTS SUBJECT
TO NRC INSPECTION
DEVELOP PEENING TECHNICAL
BASIS
---
ESTABLISH PROCESS
SPECIFIC ESSENTIAL
VARIABLES
---
CONFIRM "PERFORMANCE
CRITERIA" MET (i.e. PROCESS
EFFECTIVE)
---
DEVELOP SPECIAL PROCESS
CONTROLS / PROCEDURES
(10 CFR 50 APPENDIX B
CRITERION IX)
---
LICENSEE REVIEWS /
APPROVES PROCESS
PROCESS
DEVELOPMENT /
VALIDATION
INFIELD PROCESS
IMPLEMENTATION
PERFORMANCE CRITERIA
COMPRESSIVE
STRESS
23© 2015 Electric Power Research Institute, Inc. All rights reserved.
Implementation Guidance for ConsistencyPeening Process Control
Peening vendors will be required to meet stress magnitude and depth
requirements, and peening coverage requirements
Peening vendors will be required to establish and provide essential
variables and associated ranges of acceptable application-specific values
– Part of the controlled special process procedures submitted for licensee pre-
implementation approval
– Will ensure that specified stress and coverage requirements are met
– Essential variables will be unique to the peening technology offered and specific
to each vendor and type of component being peened
Control by the peening vendor of the essential variables particular to the
peening technology utilized and the satisfaction of the performance
criteria result in a robust mitigation process
24© 2015 Electric Power Research Institute, Inc. All rights reserved.
Implementation Guidance for ConsistencyPeening Process Control
Evaluation of peening application to RCS pressure boundary locations under 10 CFR 50.59
found:
No analysis or procedure identified in the Safety Analysis Report is expected to be adversely
affected
No accident condition or scenario in Safety Analysis Report is expected to be adversely
affected
• If anything, loss of pressure boundary conditions or scenarios are in a better safety
position following the application of peening.
Control of the Peening Process is not a safety issue and should be treated consistent with other
maintenance and repair activities at the Site under 10 CFR 50 Criterion IX. Control of Special
Processes
Other activities typically performed under this criterion are Freeze Sealing, Welding,
Soldering, Leak Stop Injection of Gasketed Joints to name a few
25© 2015 Electric Power Research Institute, Inc. All rights reserved.
Implementation Guidance for ConsistencyKey Peening Process Control Variables
Water Jet Peening
Nozzle Diameter
Jet stand-off distance and nozzle offset in ID
applications
Water flow rate
Application time
Impingement angle
Stationary nozzle time
Water level and water temperature
Laser Peening
Laser type
Pulse energy
Pulse repetition rate
Pulse duration
Laser spot footprint dimensions
Pulse layer count
• These lists of key variables are for WJP and LP processes that participated in EPRI’s R&D program
• Other, new or optimized surface stress improvement processes will have other key process control variables
• Essential variables are usually only a subset of the of the key process variables
• Performance criteria such as those in ASME Code are appropriate, sufficient and follow precedent for defining
the generic “end state” requirements that a surface stress process must achieve (e.g., depth, coverage, stress)
26© 2015 Electric Power Research Institute, Inc. All rights reserved.
Implementation Guidance for ConsistencyPerformance Parameters
Component
ASME
Code Case
Surface Stress
Magnitude
Nominal Compressive
Residual Stress Depth Coverage Zone
Peened
Alloy 82/182
DMWs
N-770-4
Appendix I
Residual stress plus
nominal operating stress
on peened surface shall
be compressive
at least
0.04 in. (1.0 mm)
Entire wetted surface of
PWSCC susceptible
material including the
weld, butter, and base
material, as applicable
Peened
RPVHPNs
Draft
N-729-5
Appendix II
Residual stress plus
nominal operating stress
on peened surface shall
not exceed +10 ksi
Nozzle ID: at least
0.01 in. (0.25 mm)
Nozzle OD/weld: at
least 0.04 in. (1.0 mm)
Wetted surface of
attachment weld, butter,
and nozzle base
material (OD and ID)
that is susceptible to
PWSCC
27© 2015 Electric Power Research Institute, Inc. All rights reserved.
Process Implementation
Gary Poling - AREVA
Note: Slides #28-33 are an EXAMPLE. Requirements are plant, process
and geometry specific. Processes other than AREVA’s will have different
essential variables and approaches for process qualification.
Application of UHP Cavitation Peening
Implementation as a Controlled Special Process Under an Appendix B Program
EXAMPLE
January 21, 2015
p.29
UHP Cavitation PeeningSpecial Process
Both qualification and implementation will be performed in
accordance with the AREVA Inc Quality Assurance Program
(QAP) for special processes
Complies with Criterion IX of 10 CFR 50, Appendix B, Control
of Special Processes and Requirement 9, Control of
Processes, of ASME NQA-1
p.30
UHP Cavitation PeeningQualification
The peening process effectiveness shall be demonstrated on
full scale representative mockups at the nominal, max and min
ranges of essential variables used for site implementation
Full scale nozzle mockups include material and geometry
constraints
X-ray diffraction will be used to determine the residual stress
on peened full scale representative mockups
Confirm the desired peening coverage has been achieved
Confirm the desired depth of compression has been achieved
A qualification report will be provided to the utility that
documents how all requirements are met for the Topical
Report / Relief Request / ASME Code
Essential Variable Range for Qualification Mockups and
Site Implementation are the same
p.31
UHP Cavitation PeeningEssential Variables
Nozzle
Water pressure
Standoff distance
Position
Velocity
Backpressure
Application specific
Essential Variables are Controlled and Monitored
p.32
UHP Cavitation PeeningImplementation
Essential variables are controlled/monitored to
ensure acceptable results are achieved
The tooling control system will record the value
of each essential variable
The electronic data will be reviewed/verified
post-process
Will be part of the archived record
The operator will have a real-time display of all
essential variables
If an essential variable gets outside of qualified
limits the operator is immediately alerted
Noise alarm
Flashing light
In – Process Verification / Post – Process Verification
p.33
UHP Cavitation PeeningSummary
The UHP Cavitation Peening process will be qualified and
implemented in accordance with the AREVA Inc., Quality
Assurance Program for special processes as approved by
the licensee
Essential variables will be ‘bounded’ during process
qualification on representative full scale nozzle mockups
Essential variables will be controlled/monitored during
implementation
Both in-process and post-process verification will be used to
confirm the desired results are achieved
A final report will be provided to the utility that documents
how all requirements were met
34© 2015 Electric Power Research Institute, Inc. All rights reserved.
Exelon Application of Appendix B
Jack Feimster - Exelon
35© 2015 Electric Power Research Institute, Inc. All rights reserved.
Exelon Application of Appendix B
Specification – Specify to meet the technical requirements of
MRP-335, ASME Code Case N-729-5, ASME Section XI and
Exelon implementation of Appendix B Criterion IX Special
Processes
Procurement – Contract will be Safety Related ensuring the
use of Vendor’s 10CFR50 Appendix B program
Oversight – Exelon will use contractor oversight procedure for
Safety Related work
Controls and Management – Vendor to manage critical
parameters and supply data that demonstrates compliance to
the specification
36© 2015 Electric Power Research Institute, Inc. All rights reserved.
Topical Report Review Process:
Schedule
Paul Crooker - EPRI
37© 2015 Electric Power Research Institute, Inc. All rights reserved.
NRC Schedule Evolution for MRP-335R1 Topical Report SE
Timeline
MRP submitted the topical report for review in February 2013
Fee exemption approved in April 2013
Acceptance Review started in August 2013
Acceptance Review completed in November 2013
In June 2014 Confirmatory Research was added on the SE
critical path delaying the SE by about 3 years
RAIs Issued
– Draft – June 30, 2014
– Final – September 2014
A public meeting was held on September 9, 2014, that
covered many issues including; confirmatory research, RAIs,
vendor meetings, performance parameters, inspection
requirements, and 50.59 implementation requirements
MRP submitted written RAI responses on October 10, 2014
Begin Acceptance Review – August 5
Acceptance Review or Denial Letter – Nov 15, 2013
RAI’s issues to EPRI – Apr 4, 2014
RAI responses back from EPRI – Jun 30, 2014
Draft SE issued to EPRI – Nov 21, 2014
Draft SE comments / draft update to TR – Jan 2, 2015
Final SE issued to EPRI – Apr 24, 2015
Final TR-A from EPRI – Jul 20, 2015
Final validation letter to EPRI – Aug 25, 2015
(~1 year between Issuing RAIs and Issuing Final SE)
NRC’s Schedule at Start of Acceptance Review in August 2013
September 2014 – EPRI to submit responses to NRC RAIs
NRC to review supplemental information
November 2014 – Follow up or new RAIs to EPRI
Summer 2017 – Draft SE for MRP-335 (~3 year delay)
NRC’s Schedule at Public Meeting in September 2014
38© 2015 Electric Power Research Institute, Inc. All rights reserved.
Conclusions and Next Steps
William Sims - Entergy
39© 2015 Electric Power Research Institute, Inc. All rights reserved.
Conclusions
It is the Industry’s position that:
The technical basis already in the topical report and references is sufficient for SE
Additional confirmatory testing is not needed to support SE
Will be performed under Appendix B process controls
Min/max essential variables not needed for standardization
Performance criteria approach combined with 10 CFR 50 Appendix B Criterion IX are appropriate and follow ASME Code Case precedent
It is impractical and inappropriate for NRC to specify acceptable ranges of essential process variables for each process
Vendor visits are encouraged for NRC staff
SE needed by mid-2015
Implementation begins in 2016
40© 2015 Electric Power Research Institute, Inc. All rights reserved.
Next Steps
Close Open Actions
– NRC to establish a process and date when they will provide
requirements for inspection relief (due by end of 2014)
– NRC to provide updated schedule for SE (due by end of 2014)
– Schedule for peening vendor meetings
– Status and expedite review and response on RAIs
NRC feedback and response to Industry conclusions of
today’s public meeting
41© 2015 Electric Power Research Institute, Inc. All rights reserved.
Closing
Richard Clemens - Wolf Creek
42© 2015 Electric Power Research Institute, Inc. All rights reserved.
Closing Remarks
PWSCC is time sensitive
– Peening should be encouraged for asset protection, regulatory
schedule delays discourage timely, proactive mitigation
Industry made decisions based on the NRC’s August 2013
schedule
The current NRC schedule will force lead plant projects in
2016/17 to mitigate without knowing the NRC’s requirements
43© 2015 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity