Safety and Suitability for Service (S3)...
Transcript of Safety and Suitability for Service (S3)...
|
Safety and Suitability for
Service (S3) AssessmentDefence
13
December,
2017
1
|
Project initiators
Cite the members of the team (between 2 and 10 persons, the sponsor
of your project and their job titles).
Indicate and detail the synergies between BU and sectors, if any, and
the different skills needed to prepare the project. Do not hesitate to
highlight collaborative work.
13
December,
2017
2
Vincent BadaProject Manager
Daniel GilisAmmunition Engineering
Manager
Philippe LangenaekenEVP - Ammunition Dpt.
Sponsor
David SmithPyrotechnics Engineer
The technical skills neededDevelopment, Industrialization and Production under a very specific framework:
Ammunition containing explosives and pyrotechnic compositions
Associated with mechanical and electronic safety systems
International requirements defined and recognized (required by NATO) authorizing the operational commissioning
|
Earning of an “S3 – Safety and Suitability for Service” assessment of the missile of Ukrainian origin
Prerequisite for the training phase, including the firing of missiles by the final user,
Knowledge of the product delivered to the customer under the Anti-tank version of the AB programme,
Challenges:
Classified test reports, no documentation was accessible justifying or showing in a probative manner the safety aspects of the
material,
Missile was developed and certified according to the GOST standard (former Soviet block) under the supervision of the Ukrainian
minister for defence,
Innovation provided:
Establishment and implementation of a method to assess the level of safety and use of a product/system developed according to a
non Western standard (for GOST) or for a Western standard (NATO)
This type of activity has never been carried out by CMID and, to our knowledge, no company situated in any NATO country…
Implementation actions:
Identification of partners that can provide us the necessary experience,
Identification of applicable NATO standards,
Preparation of a test plan:
sufficient and necessary, reasonable in terms of budget, minimising the risks
Describe the initial situation of your project in detail, the
actions carried out by the group and the results achieved, by
stressing the innovative aspect and intellectual property, if
applicable. How did the initial idea come about? How is it an
innovation? What has it led to?
13
December,
2017
3
What has been done /
put in place
|
Objective(s) of the project
This project addresses above all the Environment, Health and Safety (EHS) policy of CMI:
“We consider it of fundamental importance to place products and services on the market that give preference to environmental performance and safety from the point of view of their use, in cooperation with our customers and suppliers.”
This S3 assessment of the missile is necessary under the AB Programme in order to meet the following needs:
Information required so as to obtain authorization to conduct training of firing ranges in the UK
Information required on the safety of the missile to be included in the user manuals provided to the customer.
It is indispensable to obtain elements of proof (test reports, etc.) that enable CMID to respond formally to these needs..
This project improves our knowledge of the S3 methodology and knowledge of the safety level of the AB missile;
It addresses the following CMID 2022 strategic lines:
Def 1: Deliver AB program on time
Def 3: Ensure that 30% of turnover is achieved/maintained through recurrent business
Def 4: Secure and develop the talent needed to achieve our ambition
Def 5: Define and defend our product know how and IP
13
December,
2017
4
What objective does your project address? What will it
provide that did not exist before? What does it improve or
what is it going to improve? Under which PROP does your
project fall and what strategic line does it meet?
|
Public affected/concerned
The first direct beneficiary of the project is the AB programme,
both for the Support part, by enabling the firing of missiles in
training courses, and the Supply part, by providing the information
necessary for drawing up technical manuals relating to the
missiles provided to the end customer.
The organization opposite was put in place for the execution of
the test plan.
Ordnance Test Solutions (OTS) is the main provider of the
contract.
Frazer-Nash Consultancy (FNC) acts as a consultant and third
party, ensures that the tests and data collected meet the
standards required and draws up the final S3 authorization report
from the UK authorities.
The tests are carried out by BAE Systems (BAE), OTS and
various laboratories (for certain specific tests).
13
December,
2017
5
Ammunition DptProject Management
OTSS3 Prime Contractor
BAETest Facilities
OTSTest execution
Other Test Houses
FNCAssessment
Advisor
AB Supply – AT
Program Management
AB Support
Program Management
Who will be the beneficiaries of your project? How will they
benefit from it?
Who are the persons involved in the implementation of the
project? In what way?
|
Maturity level:
This plan is in the process of execution at present and enables us to contemplate with ease the training provided under
the AB programme and to deliver the ammunition whose limits of use we know in complete safety.
Geographic scope:
Worldwide: every customer/user who needs an S3 assessment according to NATO standards
13
December,
2017
6
Describe the time frame and the different stages of your
project in detail, as well as the geographic scope concerned.
When did it start? What remains to be done? How mature is
your project? What is the extent of the geographic scope
concerned?
Main steps:
Q1 2015 Start up of the activities
In 2015 and 2016, many discussions and
meetings were organized between the UK
authorities, OTS, FNC and CMID to define and
validate a programme of tests.
Q3 2016 Start of programme of tests
Q3 2018 Expected end of project
Organizational chart of complete test plan:
3 phases, > 40 tests, 14 reports
Date and scope of achievement /
implementation
|
Project promotion/media
coverage method
Internal promotion:
Through the project management and internal reporting process (Program, Codir)
Complementary promotion through CMI Awards 2018
External promotion:
Through the different stakeholders of the project (OTS, BAE, FNC, …)
Promotion among potential prospects (Patria, BAE, …) for the acquisition of the missile system
13
December,
2017
7
What have you put in place to promote your project
internally and externally? What efforts have you deployed?
What means have you implemented? What was your
dissemination plan for the project?
|
Allocated budget
Overall budget of €4.5 million, supported by the AB programme and comprising 500 hours of CMID
services.
The CMID effort is composed of:
A member of the team, residing in the United Kingdom, who provides technical assistance and
daily project monitoring.
A project manager at Loncin according to the procedures in force.
At present, a little more than 4000 hours were put in on the project and the realized total amounted to
more than €3.1 million
13
December,
2017
8
What efforts have been made to develop the solution
presented? What financial and/or human resources have
been deployed?
|
Sustainable/reproducible
nature of the projects
The expertise acquired in S3 assessment can naturally also be re-used for other weapon systems
and will help reduce the cost of future assessments.
The assessment of the AB missile makes it easier to sell it to other customers who require S3
certification.
This S3 assessment shows it is possible to use products developed according to other standards
by any client who requires safety according to NATO standards.
13
December,
2017
9
Does your project address a punctual need or does it offer a
sustainable response in time? Could the solution be used
several times? Does it lead to the addition of a new product
in the Group’s portfolio or the improvement of an existing
project?
|
Measured impact
This project meets the:
Environment, Hygiene and Safety (EHS) policy of CMI.
AB contractual obligations, first supply of a complete weapons system (weapons + ammunition) by CMID.
Success indicators:
Earning of final UN Classification (necessary for transport authorizations)
Carried out in Q4 2016
Obtaining of the authorization to conduct training in the firing ranges of the English army
Q2 2018
Final report – Safety characteristics of the AB missile
Q4 2018
13
December,
2017
10
What effects are produced or expected from the
implementation of your project? How can they be
measured? Itemise them through (at least) one indicator.
|
The project in images
Fire resistance test 800 °C
11
First event at
18’ on the video
Falling test from 12 m
UN tests of active missiles
27.11.17
|
www.cmigroupe.com
13
December,
2017
12