description

SA1 coordination. Maite Barroso, CERN SA1 F2F coordination meeting CERN. Agenda for the day. Track progress since the last meeting Agree plan for Y2 Plan for the next months, till next meeting in September At EGEE09, in Barcelona Prepare EU review, at the end of June. Agenda for the day. - PowerPoint PPT Presentation

Transcript of SA1 coordination

Page 1: SA1 coordination

EGEE-III INFSO-RI-222667

Enabling Grids for E-sciencE

www.eu-egee.org

EGEE and gLite are registered trademarks

SA1 coordination

Maite Barroso, CERN

SA1 F2F coordination meeting

CERN

Page 2: SA1 coordination

Enabling Grids for E-sciencE

EGEE-III INFSO-RI-222667 2

Agenda for the day

• Track progress since the last meeting• Agree plan for Y2• Plan for the next months, till next meeting in

September– At EGEE09, in Barcelona

• Prepare EU review, at the end of June

Page 3: SA1 coordination

Enabling Grids for E-sciencE

EGEE-III INFSO-RI-222667 3

Agenda for the day

• OAT milestones• C-COD and R-COD• EGI update• EGI release and deployment model• User support

Page 4: SA1 coordination

Enabling Grids for E-sciencE

EGEE-III INFSO-RI-222667 4

Country reports

• each country (JRU) directly reports its SA1 related activity – including the country report metrics – including national and international resource use

• The SA1 QR will become the direct assembly of these reports with minimal editing; still quarterly

• Similar to SA1 country reports– Diff format so they can be easily aggregated (instead of digested and

summarized, as they are now)

• reason for this change – NGIs to establish reporting activity of their international and global NGI

tasks– to regularly review the expanding metrics automation work.

• Next: May-June-July– Template by mid-June; filled by the end of July

Page 5: SA1 coordination

Enabling Grids for E-sciencE

EGEE-III INFSO-RI-222667 5

Actions from today

• OAT (James Casey): Define messaging deployment scenario based on early experience, matching scale needed and regional needs– By next meeting, so regions can plan HW and expertise

• COD (Helene Cordier): – Define C-COD model to be prototyped in next 3 months (who will

do it, how many FTEs), by the end of June– Define Key Performance Indicators for R-COD

Format similar to MSA1.3, seed resources metrics, etc To be automated and displayed by the related tools/teams

• Deployment (Antonio Retico): discuss with SA3 and JRA1 to define an implementation to the requirement on production repository always consistent

Page 6: SA1 coordination

Enabling Grids for E-sciencE

EGEE-III INFSO-RI-222667 6

Actions from today

User Support (Torsten Antoni): • CENTRALLY COORDINATED FEW (2-3) FULL-TIME TPM

TEAMS– More automation in ticket assignment to regions– Role of the central TPM teams: ticket assignment (of the few not

automatically routed), escalation, monitoring• Refine and put in place this model in Y2• Discuss and agree mw support with product teams/mw

providers? So it is properly staffed

Country reports: agreement to start with them at next quarter

• Action on Maite to distribute template• To be filled by all partners and grouped by country at

mid July