    WORSHOP ON INNOVATIVE

    FINANCING MODALITIES FOR

    INFRASTRUCTURE DEVELOPMENT

    IN INDIA

    PRESENTATION ON BANGALORE METRO RAIL

    TRANSIT SYSTEM

    AN OVERVIEW

    The views expressed in these presentations are the views of the author and do not necessarily reflect the views or policies of

    the Asian Development Bank (ADB), or its Board of Directors or the governments they represent. ADB does not guarantee the

    source, originality, accuracy, completeness or reliability of any statement, information, data, finding, interpretation, advice,opinion, or view presented, nor does it make any representation concerning the same.

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    2/26

    Bangalore Metro Rail Corporation

    Brief Status of The Project

    N Sivasailam

    Managing Director

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    3/26

    Reach 1

    Reach 3

    Under Ground

    Reach 4

    Reach 2

    South

    Extension

    North

    Extension

    East West Corridor

    Elevated Section 13.02 Km

    Underground Section 4.88 Km

    Elevated Stations 12

    Underground Stations 4

    North South Corridor

    Elevated Section 19.87 Km

    Underground Section 4.00 Km

    Elevated Stations 21

    Underground Stations 3

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    4/26

    EAST WEST CORRIDOR 18.10 KMS

    NORTH-SOUTH CORRIDOR 24.20 KMS

    TOTAL 42.30 KMSELEVATED 33.50 KMS

    UNDERGROUND 08.80 KMS

    GAUGE Standard GaugeTRACTION 750V dc Third Rail

    SPEED Max 80Kmph ; Avg. 34Kmph

    NO. OF STATIONS 40 (33 elevated, 7 UG)TRAVEL TIME 33 / 44 Mins. (end to end)

    HEAD WAY 4 Minutes at start; later 3

    Minutes

    Bangalore Metro Rail Corporation

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    5/26

    Project Cost (Total Network of 42.30kms)

    Bangalore Metro Rail Corporation

    Sl

    No

    Components (Rs Crores) (US $

    Millions)

    Percentage

    of theProject Cost

    1 Land , rehabilitation

    and Utilities

    1760.00 390.00 15

    2 Civil Engineeringworks

    5222.00 1160.00 45

    3 Systems including

    Rails and Rolling

    stock

    4229.00 940.00 36

    4 Others (Consultancy,

    reimbursement of

    taxes)

    398.00 88.00 4

    Total 11,609.00 2,578.00 100

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    6/26

    FUNDINGFUNDING ARRANGEMENTARRANGEMENT

    Equity (Rs Crores) (US $ Millions)

    - GOI 1635 363.00

    - GOK 1635 363.00

    Interest Free Subordinate Debt

    - GOI 1090 242.00

    - GOK 1635 363.00

    Senior Term Debt from JICA

    -1st Sanction 44.704 Billion yen

    -2nd Sanction 19.8 Billion Yen

    2910 646.00

    ADB 1125 250.00

    K EXIM Bank 133 Million Euro 864 192.00

    AFD 715 159.00

    Total ~ 11,609.00 2,578.00

    Estimated Project Cost : US 2.6 Billions (Rs. 11,609 Crore)

    Debt Equity Ratio: 45:55

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    7/26

    Bangalore Metro Rail Corporation

    ReachReachReachReach No.of PropertiesNo.of PropertiesNo.of PropertiesNo.of Properties AreaAreaAreaArea Amount PaidAmount PaidAmount PaidAmount Paid

    Reach - 1 176 402430.63 376.52

    Reach - 2 250 119266.87 225.86

    Reach - 3 233 104585.17 273.76

    Reach - 3A 82 465825.46 163.51

    Reach - 3B 204 171887.62 35.2

    Reach - 4 66 49051.88 85.29

    Reach - 4A 84 54958.94 93.68

    TotalTotalTotalTotal 1095109510951095 1,368,006.571,368,006.571,368,006.571,368,006.57 1253.821253.821253.821253.82

    Land Acquisition and Rehabilitation

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    8/26

    Slum Rehabilitation

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    9/26

    UNIQUE LAND PACKAGE

    Rehabilitation Allowances

    Residential / Commercial PropertiesRESIDENTIAL

    Shifting Allowance* Avg. Rs. 15000/- one time payment

    Inconvenience Allowance* Avg. Rs. 30000/- one time payment

    Transitional Allowance Rs. 75000/- one time payment

    Rental Income Lost Rs. 10/- per sq. ft. lost

    Right to salvage material Full

    TDR As applicable

    COMMERCIAL

    Shifting Allowance* Avg. Rs. 15000/- one time payment

    Loss of Business* Avg. Rs. 75000/- one time payment

    Business Re-establishment* Avg. Rs. 240/- per sq. ft. for area lost

    Rental Income lost Rs. 20/- per sq. ft. lost

    Right to salvage material Full

    TDR As applicable

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    10/26

    AFFORESTATIONAFFORESTATION

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    11/26

    Progress Report

    Bangalore Metro Rail Project

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    12/26

    Bangalore Metro Rail Project

    7 kms of this section is fully completed and awaiting for

    opening to public.

    REACH 1

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    13/26

    Bangalore Metro Rail Project

    7 kms of this section is fully completed and awaiting for opening to public.

    REACH 1

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    14/26

    Bangalore Metro Rail Project

    REACH 2

    71% of Viaduct is completed.

    Remaining work on Viaduct is expected

    to be complete by Aug 2012

    33% of progress is recorded in the

    stations and civil works are estimated

    to be complete by April 2012

    The commencement of trials will

    begin by April 2013

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    15/26

    Bangalore Metro Rail Project

    REACH 3

    Launching is under the progress

    with the help of 4 launching girders.

    82% of the work already has been

    completed and is expected to be

    completed by April 2012

    With regard to stations around 51%

    of progress is completed and

    remaining civil works are estimated

    to complete by April 2012

    The commencement of trials will

    begin by Dec 2012

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    16/26

    Bangalore Metro Rail Project

    REACH 3A & 3B

    33% progress has been achieved.

    26 Spans have been erected.

    About 800 segments have already

    been casted.

    Handing over to track contractor is

    targeted progressively from Nov 2011.

    With regard to stations, civil works is

    expected to be completed by April 2012.

    Overall 24% Progress has been

    achieved in Reach 3B

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    17/26

    Bangalore Metro Rail Project

    REACH 4 and 4A

    Viaduct works have achieved a

    progress of 86%.

    Handing over to track contractor is

    targeted progressively from Aug

    2011.

    All civil works in viaduct is expected

    to be completed by Dec 2011

    Around 65% of progress has been

    achieved in stations. Off road

    structure are under progress.

    Overall 33% has been achieved in

    Reach 4A

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    18/26

    Bangalore Metro Rail Project

    UG East- West Corridor

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    19/26

    Bangalore Metro Rail Project

    Physical Progress up to Aug 2011

    Percentage in terms of work executed 44%

    percentage in terms of tenders

    awarded

    97%

    Financial Progress up to Aug 2011

    In Crore 4853.77

    In Percentage 41.81%

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    20/26

    Bangalore Metro Rail Project

    Baiyappanahalli MG Road October 2011

    Peenya Depot - Yeshwanthpur Sampige Road

    December 2012

    Peenya Depot Nagasandra December 2013

    U/G Section December 2013

    City Station Mysore Rd December 2013

    K.R.Market R.V Road Puttenahallicross

    December 2013

    Commissioning Schedule

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    21/26

    WHAT NEXT

    BANGALORE METRO PHASE 2

    DPR FOR SIX LINES READY FOR APPROVAL

    OBJECTIVE IS TO PROVIDE LINKAGE TO IT

    INDUSTRY

    FOUR EXTENSION LINES

    ONE ARTERIAL LINE

    ONE LINK LINE ARTERIAL AND LINK LINE PROPOSED FOR PPP

    SYSTEMS AND O&M

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    22/26

    Phase II Alignment

    Baiyappanahalli

    Mysore Road

    Hessaraghatta Cross

    PuttenahalliCross

    BIEC

    Anjanapura Township

    Kengeri

    Nagawara

    IIMB

    White Field

    Electronic city

    RV Road

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    23/26

    Sl. No Description Length of the

    line

    Completion cost

    (Rs. In Crores)

    1 Baiyappanahalli to

    Whitefield

    11.60 4483.60

    2 Mysore Road Station to

    Kengeri

    7.70 1851.30

    3 Hesaraghatta Cross to BIEC 4.20 1058.63

    4 Puttenahalli Cross to

    Anjanapura

    6.70 1657.74

    5 R.V Road terminal to

    Bommasandra

    15.60 5102.00

    6 Gottigere IIMB to

    Nagawara

    21.10 9650.88

    Grand Total 66.90 23804.15

    COST ESTIMATE OF PHASE II METRO CORRIDORS(With Central taxes and Without State taxes)

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    24/26

    FUNDINGFUNDING ARRANGEMENTARRANGEMENT

    Description In PC In Crores (US$ in Millions)

    Equity

    - GOI 15 3571 793.5

    - GOK 15 3571 793.5

    SubordinateDebt

    - GOI 10 2380 529.0

    - GOK 15 3571 793.5

    Senior Term

    Debt

    45 10711 2380.0

    Total ~ 100 23804.0 5289.5

    Estimated Project Cost : US$ 5.29 Billions (Rs. 23804 Crore)

    Debt Equity Ratio: 45:55

    Means of Finance

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    25/26

    BANGALORE AIRPORT RAIL LINK

    THE PROJECT HAS BEEN TRANSFERRED TO

    BANGALORE METRO ON 26TH SEP 2011

    DPR PREPARED AND APPROVED UNDER PPP

    20% VGF

    LAND COST BORNE BY STATE GOVT RFP & CA UNDER EXAMINATION

  • 8/3/2019 S3_110930 PPP Presn_N. Sivasailam

    26/26

    Bangalore Metro Rail Project

    Thank You