Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of...

34
AFRICAN DEVELOPMENT FUND PROJECT : SCALING UP ENERGY ACCESS PROJECT COUNTRY : RWANDA APPRAISAL REPORT ONEC DEPARTMENT June 2013 Appraisal Team Regional Director : Mr. G. NEGATU, Director, EARC Sector Director : Mrs. H. CHEIKHROUHOU, Director, ONEC Division Manager: Mr. E. NEGASH, Division manager, ONEC.2 Team Leader : Mr. A. WUBESHET, Chief Power Engineer, ONEC.2

Transcript of Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of...

Page 1: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

AFRICAN DEVELOPMENT FUND

PROJECT : SCALING UP ENERGY ACCESS PROJECT

COUNTRY : RWANDA

APPRAISAL REPORT

ONEC DEPARTMENT

June 2013

Appraisal Team

Regional Director : Mr. G. NEGATU, Director, EARC

Sector Director : Mrs. H. CHEIKHROUHOU, Director, ONEC

Division Manager: Mr. E. NEGASH, Division manager, ONEC.2

Team Leader : Mr. A. WUBESHET, Chief Power Engineer, ONEC.2

Page 2: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

TABLE OF CONTENTS

I. STRATEGIC THRUST AND RATIONALE ............................................................................................................. 1

1.1 PROJECT LINKAGES WITH COUNTRY STRATEGY AND OBJECTIVES .............................. 1

1.2 RATIONALE FOR BANK’S INVOLVEMENT ..................................................................... 2

1.3 DONOR COORDINATION .............................................................................................. 2

II. PROJECT DESCRIPTION .......................................................................................................................................... 3

2.1 PROJECT COMPONENTS ............................................................................................... 3

2.2 TECHNICAL SOLUTIONS ADOPTED AND ALTERNATIVES CONSIDERED ........................ 3

2.3 PROJECT TYPE ............................................................................................................. 4

2.4 PROJECT COST AND FINANCING ARRANGEMENTS ....................................................... 5

2.5 PROJECT’S TARGET AREA AND POPULATION .............................................................. 6

2.6 PARTICIPATORY APPROACH ........................................................................................ 7

2.7 BANK GROUP EXPERIENCE AND LESSONS REFLECTED IN PROJECT DESIGN ................ 7

2.8 PROJECT’S PERFORMANCE INDICATORS ...................................................................... 8

III. PROJECT FEASIBILITY............................................................................................................................................. 9

3.1 ECONOMIC AND FINANCIAL PERFORMANCE ................................................................ 9

3.2 ENVIRONMENTAL AND SOCIAL IMPACTS ................................................................... 10

IV. PROJECT IMPLEMENTATION ............................................................................................................................. 13

4.1 IMPLEMENTATION ARRANGEMENTS .......................................................................... 13

4.2 PROJECT MONITORING AND EVALUATION ................................................................. 15

4.3 GOVERNANCE ........................................................................................................... 15

4.4 SUSTAINABILITY ....................................................................................................... 16

4.5 RISK MANAGEMENT .................................................................................................. 17

4.6 KNOWLEDGE BUILDING ............................................................................................ 19

5 LEGAL FRAMEWORK ............................................................................................................................................ 19

5.1 LEGAL INSTRUMENT.................................................................................................. 19

5.2 CONDITIONS ASSOCIATED WITH BANK’S INTERVENTION .......................................... 19

5.3 COMPLIANCE WITH BANK POLICIES .......................................................................... 20

6 RECOMMENDATION .............................................................................................................................................. 20

APPENDIX I: COUNTRY’S COMPARATIVE SOCIOECONOMIC INDICATORS....................................................... I

APPENDIX II: AFDB’S ONGOING PORTFOLIO IN RWANDA ................................................................................. III

APPENDIX III: SIMILAR PROJECTS FINANCED BY THE BANK AND OTHER DEVELOPMENT

PARTNERS ........................................................................................................................................................................... IV

Page 3: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

CURRENCY EQUIVALENTS

Exchange Rate as of March 2013

UA 1 = USD 1.51483

UA 1 = RWF 974.50

USD 1 = RWF 643.3065

Bank’s Fiscal Year

1 January – 31 December

Borrower’s (Rwanda) Fiscal Year

1 July – 30 June

Weights and Measures

m meter KOE kilogram of oil equivalent

cm centimeter = 0.01 meter kV kilovolt = 1,000 volts

mm millimeter = 0.001 meter KVA kilovolt ampere (1,000 Va)

km kilometer = 1,000 meters KW kilowatt = 1,000 watts

m² square meter GW gigawatt (1,000,000 kW or 1000 MW)

cm² square centimeter MW megawatt (1,000,000 W or 1 000 kW)

km² square kilometer = 1,000,000 m² KWh kilowatt hour (1,000 Wh)

ha hectare = 10,000 m² MWh megawatt hour (1,000 KWh)

t (t) metric tonne (1,000 kg) GWh gigawatt hour (1,000,000 KWh)

Acronyms and Abbreviations

AfDB African Development Bank LC Local costs

ADF African Development Fund LV Low voltage

Adm. Administration M&E Monitoring and evaluation

AFD Agence Française de

Développement

MINECOFI

N

Ministry of Finance and

Economic Planning

ARAP Abbreviated Resettlement

Action Plan

MININFRA Ministry of Infrastructure

BADE

A

Banque Arabe pour le

Développement de l’Afrique

MOU Minutes of understanding

BSHG Budget Support

Harmonization Group

MV Medium voltage

BTC Belgian Technical

Cooperation

MVA Megavolt-ampere

CFL Compact fluorescent lamp NBI Nile Basin Initiative

CSP Country Strategy Paper NELSAP Nile Equatorial Lakes Subsidiary

Action Plan

DPCG Development Partners NPV Net present value

Page 4: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

Coordination Group

CPAF Country’s Common

Performance Assessment

Framework

p.a. Per annum

CTB Coopération Technique Belge PIU Project Implementation Unit

DoL Division of labor PRSP Poverty Reduction Strategy Paper

DFID Department for International

Development (UK)

RAP Resettlement Action Plan

EA Executing agency RFP Request for proposal

EARP Electricity Access Rollout

Program

RPPA Rwanda Public Procurement

Authority

EDPRS Economic Development and

Poverty Reduction Strategy

RURA Rwanda Utility Regulatory

Agency

EIRR Economic internal rate of

return

RWF Rwandan francs

ENPV Economic net present value RWFO Rwanda Field Office

ESIA Environmental and Social

Assessment

SEA Strategic Environmental

Assessment

ESMP Environmental and Social

Management Plan

SBD Standard Bidding Documents

EWSA Electricity, Water and Energy

Authority

SME Small or medium enterprise

FAPA

FC

Fund for African Private

Sector Assistance

Foreign exchange costs

SPN Specific Procurement Notice

FIRR Financial internal rate of

return

SWAp Sector-wide approach

FNPV Financial net present value SWG Sector Working Group

GDP Gross domestic product TA Technical assistance

GoR Government of Rwanda UA Units of account

GPN General Procurement Notice UN United Nations

HDI Human Development

Indicator

UNIDO United Nations Industrial

Development Organization

ICT Information and

communication technology

USD United States dollar

IMF International Monetary Fund VAT Value-added tax

IRR Internal rate of return WB World Bank

Page 5: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

PROJECT INFORMATION SHEET

CLIENT’S INFORMATION

Borrower Republic of Rwanda

Executing agency Energy, Water and Sanitation Authority (EWSA)

FINANCIAL PLAN

Sources Description

Instrument and

amount (UA million)

Loan Grant Total

African Development

Fund (ADF)

Scaling Up Energy Access Program (initial ADF-12

allocation as in CSP 2012–2016) 10.270 8.910 19.180

Savings to be applied to the project (from previously

completed/closed projects) 1.864 0.261 2.125

Additional ADF-12 resources to be applied to the

project 3.360 2.700 6.060

Subtotal 15.494 11.871 27.365

Government of Rwanda Counterpart fund 2.596

Total financing 29.961

ADB’s KEY FINANCIAL INFORMATION

Loan/grant currency Unit of account (UA)

Commitment fee 0.50% yearly on the undisbursed portion of the loan starting 120

days after the signing of the loan agreements

Service charge 0.75% yearly on the disbursed and outstanding

Tenor 50 years

Grace period 10 years

KEY FINANCIAL AND ECONOMIC OUTCOMES

IRR NPV

Project—financial [FNPV @ 10% real (base case)] 21.5% USD 40.15 million

Project—economic [ENPV @ 12% real (base case)] 39.0% USD 143.28 million

TIMEFRAME – MAIN MILESTONES (expected)

Concept note approval 23 January 2013

Project approval 26 June 2013

Effectiveness January 2014

Last disbursement 31 August 2018

Completion August 2017

Last repayment September 2068

Page 6: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- i -

PROJECT SUMMARY

Project

overview

The proposed Scaling-Up Energy Access project covers the Northern and Western provinces of

Rwanda. The project will: (i) upgrade and rehabilitate two existing substations in Northern

Province, the Gifurwe substation to 10MVA capacity and the Rulindo substation (also to be

relocated) to 20MVA capacity; (ii) build about 464 km of medium voltage (MV) and 710 km of

low-voltage (LV) distribution networks in both provinces; and (iii) connect 25,438 households

and priority institutions (179 schools, 29 health centers and 25 sector administration offices) to

the grid along the constructed distribution network areas. Construction is expected to be

implemented over a period of 24 months after contract effectiveness and to be completed by

August 2017. The project’s cost is estimated at UA 29.961 million. Its beneficiaries are mainly

rural Rwandans, who will gain access to cheaper, reliable and sustainable electricity and related

improved services.

Project

outcomes

The overarching goal of the proposed project is to support the long-term and short-term

development strategy and program of the government of Rwanda (GoR). The expected outcomes

are (i) improved access to electricity for households and priority public institutions in the

proposed project area and (ii) sustained reliable electricity supply.

The project will support scaling up “inclusive and green” connections through the free

distribution and installation of “ready-boards,” which come with two sockets and one lamp

holder, targeting the most vulnerable households (around 10% of the total number of

households), and the use of compact fluorescent lamps (CFL) bulbs by each newly connected

household.

The project will ultimately improve the well-being, living conditions, and diversification of

income-generating activities of the population and contribute to promoting sustainable economic

growth and reducing poverty in Rwanda.

Needs

assessment

Lack of electricity is a key constraint hampering economic development and the improvement of

livelihoods in Rwanda. About 80% of all households rely on traditional biomass for their

cooking and heating needs, which has led to deforestation and soil erosion. The country’s

continuing high population growth also poses a significant challenge. To alleviate this situation,

the Economic Development and Poverty Reduction Strategy (EDPRS), in line with the GoR,

identified the energy sector as a key strategic sector for the development of the national

economy and accelerate poverty reduction. The GoR has set targets for 2017: (i) increasing

generation capacity from 90 MW to 1,000 MW and (ii) increasing household connections to

electricity from 110,000 (6%) to 1,451,855 (70%); with a special emphasis on connecting social

infrastructure: health facilities, schools, and administrative offices.

Bank’s

added value

The project will be an effective means by which to advance implementation of the government-

led, sector-wide approach and ongoing harmonization process in the energy sector. In addition,

the project will complement and benefit from the synergy with the Bank’s recent interventions in

the sector, specifically the interconnection of regional power grids (NELSAP Interconnection),

the Kivu-Watt methane gas power generation project and the Rusumo hydro projects. The Bank

will also be able to further consolidate its leadership role in the development of Rwanda’s

economic infrastructure, and increase its collaboration with other financing institutions and

partners that are supporting the energy sector. The provision of African Development Fund

(ADF) financing for the project will reinforce the Bank’s cooperation with and support for the

GoR’s development programs and the implementation of the pillars of the Bank’s Country

Strategy Paper (CSP) and Energy Sector Policy.

Institutional

development

and

knowledge

building

The project at hand supports Phase 2 of Rwanda’s Electricity Access Rollout Program (EARP).

The midterm evaluation of Phase 1 indicated a greater need for increased capacity building and

knowledge sharing within EWSA in general and EARP in particular. In consequence, the

technical assistance subcomponent included in the project will strengthen the institutional

capacity of: (i) the Ministry of Infrastructure (MININFRA) in the areas of energy policy and

strategy review; and (ii) EWSA and EARP to build and enhance in-house capacity in the areas

of project planning capabilities, preparation of project documents, and project implementation.

This knowledge will improve quality at entry for future energy projects. Analytical knowledge

building will also be promoted through the preparation of the Project Completion Report (PCR)

and through the Bank’s participation in joint analytical work with other development partners

supporting the GoR electricity access program.

Page 7: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- ii -

RESULTS-BASED LOGICAL FRAMEWORK

Country and project name: Rwanda, Scaling-Up Energy Access Project

Purpose of the project: Support to improve access to reliable and cost-effective electricity services for households and priority public

institutions

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATION

RISKS/MITIGATION

MEASURES Indicator

(including CSI) Baseline Target

IMP

AC

T

Sustainable

economic

growth;

improved

living

conditions

and well-

being of the

population,

including

freeing

women’s

time for

income

generation

opportunitie

s and

education

- Gross domestic

product (GDP)

growth

- % of population

below the poverty

level

- Increased welfare

of households

- Access to

electricity

- 7.7% in 2012

- 44.9% in 2011

HDI = 0.429 in

2001

By 2012:

- 16.5%

(330,000

households)

- Health centers

53%

- Schools 34%

- Sector adm.

offices 56%

- Within or

above 11.9%1

in 2017

- 33% in 2017

HDI = 0.466 in

2017

By 2017:

- 70% (1,451,855

households)

- Health centers

100%

- Schools 90%

- Sector adm.

offices 100%

- Human

Development

Report

- National

economic

statistics

- IMF country

review report

- Baseline survey

for electrified

zones/villages/to

wns

- Macroeconomic risk will be

mitigated by the involvement

of many donors and partners

in the development of the

country and strong

commitment of the GoR.

- East African governments

remain committed to the

regional integration and

development of the region.

- Change in level of political

support, or political risk, will

be mitigated by government

support for the EARP

program and the involvement

of the international

community in Rwanda.

OU

TC

OM

ES

Improved

access to

electricity

for

households

and priority

public

institutions

in the

proposed

project area

- Households

connected to

national electricity

grid

- Public institutions

with access to

electricity from

national grid

By 2012:

- 0

- 0 health centers

- 0 schools

- 0 sector adm.

offices

By 2017:

- 25,438 (of

which 3,446 are

women-headed

households)

and 66,910

women out of

127,190 people

- 29 health

centers

- 179 schools

- 25 sector adm.

offices

- National statistics

- Ministry of

Infrastructure and

EWSA annual

reports and

records

- Joins sector

review report of

energy sector

working group

- Bank’s energy

sector review

reports

- Project progress

reports

- Project annual

and quarterly

reports

- Project

monitoring and

post-evaluation

report

- The risk of failure to achieve

operating efficiencies will be

mitigated through

efficiencies factored into the

cost of the access program in

the form of gradual

reductions in technical losses

and operating expenses (per

unit of electricity supplied)

and gradual improvements in

collection efficiencies.

Projected improvements are

conservative and are

consistent with widely

accepted incentive-based

regulation of natural

monopolies.

- The risk posted to

EWSA/EARP’s

implementation capacity,

which is stretched due to the

sheer load of projects under

their management, will be

mitigated through an

extensive program of

capacity building; the

government will undertake

an appropriate restructuring

of the EARP office.

Sustained

reliable

electricity

supply

- System losses

- Rolling average of

monthly

interruption per km

of MV lines

By 2012:

- 19%

- 0.545

interruption/km

(based on 1,762

interruptions

per month and

3,231.4 km of

MV line)

By 2017:

- 14%

- 0.07

interruption/km

(based on 1,012

interruptions

per month and

14,450 km of

MV line)

1 Source: Draft EDPRS-2, February 2013

Page 8: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- iii -

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATIO

N

RISKS/MITIGATION

MEASURES Indicator (including CSI)

Baseline Target

OU

TP

UT

S

Component A

- Rehabilitation

and upgrading

of Gifurwe

110/30kV

substation

- Construction of

new 110/30 kV

Rulindo

substation

- Number of

substations

rehabilitated and

upgraded

By 2012:

- 0 MVA from

Gifurwe

substation

- 3 MVA from

Rulindo

substations

By 2017:

- Gifurwe substation

rehabilitated and

capacity upgraded to

10 MVA

- Rulindo substation

relocated and

capacity upgraded to

20 MVA

- Progress

reports from

the executing

agency and

supervision

and

management

consultant

- Executing

agency

(EWSA)

annual report

- Project

completion

report

- Supervision

mission

reports from

AfDB

- Disbursement

and financial

reports from

the executing

agency

- Number of

ESMP/ARAP

implementation

and compliance

reports

- Inadequate power supply to

meet demand due to new

connections will be

mitigated by the sufficient

supply of electricity from

new hydro and methane gas

sources that have already

begun construction;

assistance provided to the

public utility for domestic

energy resource

development; completion

of cross-border power

interconnections (NELSAP

project for five NBI

countries); and

implementation of energy

efficiency program through

use of compact fluorescent

lamp (CFL) bulbs for new

customers.

- Risk of completion delay

and cost overruns will be

mitigated by the hiring of

experienced and reputable

contractors on the basis of

turnkey, fixed-price, and

time-certain contracts as

well as the involvement of

the supervision consultant

to augment project staff as

needed in order to ensure

delivery efficiency

(Component C).

- Operation (both technical

and financial) and

maintenance risks will be

mitigated by the technical

assistance subcomponent

to be provided to the staff

of EWSA/EARP

(Component C).

- The risk of delay and

unsatisfactory completion

of ESMP/ARAP due to

inadequate number of

skilled staff will be

mitigated by recruiting

additional safeguard staff

through the Bank’s

financing.

Component B

MV line and LV

distribution

network

construction for

access scale-up

- Km of 30 kV

distribution lines

- Km of 0.4 kV

low voltage

network

- Number of direct

jobs created

during

construction

By 2012:

0

0

N/A

By 2017:

- 464 km of 30 kV

lines constructed

- 710 km of 0.4 kV

network constructed

- 800 (600 semi/low-

skilled), of which 120

will go to women

(15%)

Component C

- Project

supervision and

management

- Technical

assistance for

institutional

capacity

strengthening

- Project audit

- Number of

reports

- Number of staff

trained

- Time to complete

audit report

(months)

N/A

N/A

Six months in

2012

- 4 progress reports per

year prepared by the

supervision and

management

consultant

- 20 staffs from

MININFRA, EWSA

and EARP trained by

end of 2016

- One audit report each

year, completed in

less than six months

Component D

Execution of the

ESMP and

Abbreviated

Resettlement

Action Plan

(ARAP)

- Number of

people

compensated and

resettled

- Number of

HIV/AIDS

awareness and

prevention

sessions

N/A

N/A

- 100% compensation

and resettlement plan

executed

- 4 progress

reports/year prepared

by the supervision

and management

consultant until

complete

implementation of

ESMP & ARAP

- 100% of contractor

workers sensitized

about HIV/AIDS

prevention.

KE

Y A

CT

IVIT

IES

COMPONENTS INPUTS

A. Upgrading and rehabilitation of substations

B. Access scale-up

C. Project administration and management

D. Implementation ESMP and ARAP

A. UA 4.644 million

B. UA 20.408 million

C. UA 3.489 million

D. UA 1.420 million

Total cost: UA 29.961 million

Page 9: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- iv -

PROJECT IMPLEMENTATION SCHEDULE

Major

Activities

2013 2014 2015 2016 2017

Ju

ne

Ju

ly

Au

gu

st

Sep

t.

Oct

.

No

v.

Dec

.

Ja

n.

Feb

.

Ma

r.

Ap

ril

Ma

y

Ju

ne

Ju

ly

Au

gu

st

Sep

t.

Oct

.

No

v.

Dec

.

Ja

n.

Feb

.

Ma

r.

Ap

ril

Ma

y

Ju

ne

Ju

ly

Au

gu

st

Sep

t.

Oct

.

No

v.

Dec

.

Ja

n.

Feb

.

Ma

y

Ju

ne

Ju

ly

Au

gu

st

Loan approval

Loan signature

Loan

effectiveness

Issue of GPN &

SPN

Procurement of

consultant

Review and

updating of

design and bid

documents

Bidding period

Bid evaluation

and contract

award

Construction

implementation

period

Page 10: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 1 -

REPORT AND RECOMMENDATION OF THE MANAGEMENT TO THE BOARD

OF DIRECTORS ON PROPOSED FINANCING TO RWANDA FOR SCALING-UP

ENERGY ACCESS PROJECT

Management submits the following report and recommendations on a proposed ADF loan for

UA 15.494 million and ADF grant for UA 11.871 million to finance the Scaling-Up Energy

Access project in Rwanda.

I. STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Country Strategy and Objectives

1.1.1 The Bank’s Country Strategy Paper (CSP) for Rwanda (2012–2016) seeks to support

two strategic pillars: (i) infrastructure development through interventions to address the

country’s energy and transport bottlenecks, and (ii) enterprise and institutional capacity

development by supporting institutions that implement Rwanda’s policy on small and medium

enterprises (SMEs). The GoR’s long-term development strategy (Vision 2020) and medium-

term Economic Development and Poverty Reduction Strategy (EDPRS) focus on rapidly

expanding access to electricity as the key means to achieving the country’s vision of rescuing

itself from poverty. This will alleviate infrastructure bottlenecks in urban areas and improve

limited access in rural areas.

1.1.2 Rwanda has been moving towards a liberalized energy market ruled by an independent

regulator. The country has formulated clear objectives for the development of the energy

sector: (i) increase access to energy; (ii) introduce cost-reflective tariffs and revision of tariff

structure; (iii) diversify energy sources and ensure energy security; and (iv) establish a

favorable institutional, legal, and regulatory framework and build local capacity. Energy

prices have been increasingly adjusted towards a cost-reflective tariff, most recently by 20%

in 2012. A revision of the energy subsidy system is currently under way, which is in turn

expected to lead to a revision of the current generation-based subsidies in favor of income-

based consumption subsidies.

1.1.3 The proposed Scaling-Up Energy Access Project is a direct response to one of the

three flagship programs called for in the EDPRS-1—“economic transformation to create

employment and generate exports”—and responds to its key priority, rapidly expanding

access to electricity. The EDPRS-2 is designed to accelerate the progress already achieved

through the EDPRS-1 and will sustain a focus on infrastructure development for economic

transformation. Moreover, the project will contribute to the revised GoR target for the

electricity sector to reach an access ratio of 70% by 2017. The project is also consistent with

the Bank’s energy sector policy approved in October 2012, as well as with the joint

AfDB/Government of Rwanda Energy Sector Review and Action Plan (2012), whose core

principle is “ensuring energy security and increasing access for all.”

1.1.4 The CSP is in line with the country’s long-term development strategy (Vision 2020),

which targets increase in access to electricity by households, and its medium-term EDPRS-1

(2008-2012) and EDPRS-2 (2013-2018) plan, in which energy is a key strategic sector.

Increasing energy access is a basic requirement for the development of the national economy,

which in turn is a prerequisite for the acceleration of poverty reduction.

Page 11: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 2 -

1.2 Rationale for Bank’s Involvement

1.2.1 Lack of electricity is a key constraint hampering economic development and

livelihood improvement in Rwanda. To alleviate this situation, the GoR has given priority of

investment to infrastructure development, particularly in the energy sector. The Bank has

indicated its willingness to support the sector in line with its CSP for Rwanda and the GoR’s

policy on division of labor among different financing institutions and partners. The proposed

project, is thus in line with both the GoR’s development strategy and the Bank’s operational

strategy in Rwanda, as articulated in the CSP and the Bank’s energy sector policy.

1.2.2 The Bank’s intervention under the proposed project is part of the broader program of

electricity rollout in Rwanda, which among other goals aims to contribute to a reduction in the

cost of doing business, improve competitiveness, spur economic growth and transformation,

and catalyze the achievement of Rwanda’s Vision 2020 goal of becoming a middle-income

country. The project will provide effective means to advance implementation of the

government-led, sector-wide approach and ongoing harmonization process in the electricity

sector. In addition, the project will complement and benefit from the synergy with the Bank’s

recent interventions in the sector, specifically the interconnection of regional power grids

(NELSAP Interconnection Project), the Kivu-Watt methane gas power generation project and

the Rusumo hydro projects. The Bank will also benefit from further consolidating its

leadership role in the development of Rwanda’s economic infrastructure, and increase its

collaboration with other financing institutions and partners that are supporting the electricity

sector.

1.2.3 In light of the above, the GoR officially requested that the Bank consider financing

this important energy access project.

1.3 Donor Coordination

1.3.1 The GoR has an aid policy that focuses on a sector-wide approach (SWAp). The

arching objective is well known: to increase aid effectiveness by reducing fragmentation of

donors flows to the energy sector. The GoR, in view of the recent policy on division of labor,

has asked each donor to actively participate in only three sectors to comply with the Paris

Declaration and the Accra Agenda for Action. In line with the aid policy, the government has

asked the Bank to focus its future operations in Rwanda in the following three sectors: (i)

energy, (ii) transport (including ICT), and (iii) water and sanitation, as well as some

crosscutting areas such as economic governance and private-sector development. The key

development partners supporting the energy sector in Rwanda are the World Bank, AfDB,

Arab Bank for Economic Development in Africa (BADEA), UNIDO, Coopération Technique

Belge (CTB), the Netherlands, France, and Japanese International Cooperation Agency

(JICA). The Bank collaborates with other development partners through the Budget Support

Harmonization Group (BSHG), which provides a platform for members to coordinate high-

level policy dialogue on broad economic management/governance with the government, and

the Development Partners Coordination Group (DPCG), which coordinates thematic

subgroups through various sector working groups (SWGs).

1.3.2 According to the MINECOFIN Review 2012, the introduction of SWAps to energy

has had a positive impact on coordination, harmonization and alignment as well as

strengthening of the sector strategic dialogue compared to the non-SWAp sectors. The review

also notes that there is need to sustain and improve coordination among the various

stakeholders in order to enhance their ownership of the process.

Page 12: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 3 -

1.3.3 The project will provide effective means by which to advance implementation of the

government-led SWAp and ongoing donor harmonization process in the electricity sector.

II. PROJECT DESCRIPTION

The project’s development objectives are to support “improvement of access to reliable and

cost effective electricity services for households and priority public institutions and sustain

the reliability of electricity supply in Rwanda and strengthen the institutional capacity of

key sector players in the project.”

2.1 Project Components

The project has four main components: (A) upgrading and rehabilitation of substations,

(B) access scale-up, (C) consultancy services and technical assistance, and (D) the

Environmental and Social Management Plan (ESMP) and Abbreviated Resettlement Action

Plan (ARAP).

Table 2.1

Project components

N° Component name

Estimated

cost

(UA million)

Component description

A)

Upgrading and

rehabilitation of

substations

4.644

Rehabilitation and upgrading of 110/30 kV Gifurwe

substation

Upgrading and relocation of 110/30 kV Rulindo substations

to new site

B) Access scale-up 20.408

Construction of 464 km of MV distribution lines, 710 km of

LV network, and connection to 25,438 households, and

prioritized sector connection (health centers, schools and

sector administration offices)

C) Project administration and management

C1) Consultancy

services for

project

supervision and

management

1.622 Review and update of design and bidding documents,

supervision of construction, and supervision of the

implementation of ARAP

C2) Technical

assistance and

capacity-building

1.120

Technical assistance to EARP, EWSA and MININFRA

Training for EARP, EWSA and MININFRA to strengthen

institutional investment planning, technical, operational,

finance and support services functions

Electricity danger sensitization program for newly connected

households

C3) Audit 0.020 Annual audit service for the project account

C4) Project

administration 0.727

The project team will be reinforced through recruitment of

additional staff (engineers, an accountant, a procurement

specialist, an environmentalist and a social expert).

D) Environmental and

social management 1.420 Implementation of ESMP and ARAP

2.2 Technical Solutions Adopted and Alternatives Considered

2.2.1 In regard to the access scale-up component, the plan is to expand the national grid

through construction of MV and LV distribution networks. The best off-grid option for

decentralized electrification (diesel, micro hydro, or solar photovoltaic) was compared with

the national grid expansion option. Small-scale generation (stand-alone mini-grids) requires

Page 13: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 4 -

longer implementation time, and the cost is higher than for national grid expansion. The diesel

generator mini-grid option is not in line with the high-level government objective of

“improvement of access to reliable and cost-effective electricity services for households and

priority public institutions and sustain the reliability of electricity supply in Rwanda” and

will not make electricity more affordable for customers.

2.2.2 Concerning the substations component, the chosen solution is that of rehabilitation and

upgrading. The option of instead relying on existing capacity was considered and rejected,

that would have jeopardized the government’s targets to meet the target of 70% access by

2017; the Gifurwe substation has not been functional since 1994 due to damage to power

transformers and Rulindo substation’s capacity is almost saturated, meaning new customers

could not be connected. In addition, existing customers connected via these substations

continue to suffer from voltage drop, and the executing agency will not able to improve the

power losses and in turn its financial situation without new capacity.

Table 2.2:

Project alternatives considered and reasons for rejection

Alternative Brief description Reason for rejection

Component A

“Substations”

No rehabilitation

and upgrading of

Gifurwe substation

Continue supplying

existing customers in

Gifurwe area from

the more remote

substations and

generation plant.

No additional

connection of

customers on the

existing MV and LV

networks.

Without upgrading and rehabilitation of this substation,

targeted electricity access improvements in the area

cannot be achieved

Existing customers will continue to suffer from voltage

drop and fluctuation because of very far-off supply

points.

Existing customers would not be able to develop further

economic activities that require additional power supply.

Relying on existing capacity cannot improve power losses

and reliability of supply.

Component A

“Substations”

No upgrading or

relocation of

Rulindo substation

No additional

connection of

customers on the

existing MV and LV

networks.

Continue the

operation of the

substation at its

current location.

The existing substation is in a swampy area that puts its

operation at risk.

Relying on existing capacity cannot support the country’s

electricity access program or improve power losses and

reliability of supply.

New extension of the MV and LV networks and

connection to households would not be possible because

of capacity saturation of this substation.

Existing customers would not be able to develop further

economic activities that require additional power supply.

Component B

“Access Scale-Up”

Off-grid, mini-grid

solutions

Sizable off-grid

micro hydro

development or diesel

generators to provide

power to rural

villages and towns.

Renewable off-grid

installations.

There is a limited availability of hydro sites in the project

areas. Consequences would include higher investment

cost for construction and longer implementation time.

The use of diesel generators would lead to increased

electricity costs and negative CO2 emissions.

Renewable off-grid solutions have not been proven to be

cost-efficient within Phase 1 of EARP. Costs are higher

compared to grid connection, severe capacity and

electricity storage constrains limit the benefits of

electrification, particularly for health centers. In addition,

maintenance poses a severe challenge, making off-grid a

rather temporary solution.

2.3 Project Type

Page 14: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 5 -

The proposed project is part of the GoR’s program to expand access to electricity and is a

standalone project that will be financed through a loan and grant from the ADF. The project

will extend the national grid through MV and LV networks to connect new households and

priority institutions along the constructed distribution network areas. The upgrading and

rehabilitation of Gifurwe and Rulindo substations will enhance the reliability and quality of

supply of power to distribution networks and support expansion of electricity access.

2.4 Project Cost and Financing Arrangements

2.4.1 The total project cost, including physical contingency of 8% and price contingency of

5% (excluding all taxes, duties, levies, and VAT in Rwanda), is estimated to be USD 45.384

million (UA 29.961 million), comprising foreign exchange costs of USD 35.128 (UA 23.189

million) and local costs of USD 10.256 million (UA 6.772 million). Table 2.3 presents the

foreign and local currency project cost by component.

Table 2.3:

Project cost by component

Component USD million UA million

FC LC Total FC LC Total

A) Upgrading and rehabilitation of

substations 5.447 0.778 6.226 3.596 0.514 4.110

B) Access scale-up 22.181 5.117 27.358 14.643 3.418 18.060

C) Project administration and management

C1) Project supervision and

management 1.956 0.217 2.174 1.291 0.143 1.435

C2) Technical assistance 1.502 0.000 1.502 0.992 0.000 0.992

C3) Audit 0.000 0.027 0.027 0.000 0.018 0.018

C4) Operating expenses 0.000 0.974 0.974 0.000 0.643 0.643

D) ESMP /ARAP 0.000 1.903 1.903 0.000 1.256 1.256

Total base cost 31.087 9.076 40.163 20.552 5.992 26.513

Physical contingency (8%) 2.487 0.726 3.213 1.642 0.479 2.121

Price contingency (5%) 1.554 0.454 2.008 1.026 0.300 1.326

Total project cost 35.128 10.256 45.385 23.189 6.772 29.961

2.4.2 The project will be financed by the Bank and the GoR. The sources of financing of the

project are illustrated in Table 2.4. The Bank’s financing will be used to cover 100% of the

total foreign cost and 61.7% of local costs of the project excluding all taxes, duties, levies,

and VAT in Rwanda.

Table 2.4:

Sources of financing for foreign and local costs

Component UA million % of

total Foreign costs Local costs Total

ADF 23.189 4.176 27.365 91.34%

Government of Rwanda 0.000 2.596 2.596 8.66%

Total project costs 23.189 6.772 29.961 100%

Page 15: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 6 -

Table 2.5:

Project cost by category of expenditure

Category of expenditure UA million % foreign

costs Foreign costs Local costs Total

Works

Upgrading and rehabilitation of substations 4.063 0.581 4.644 87.51%

Access scale-up (six lots of MV and LV lines) 15.448 3.862 19.310 80%

Goods

Access scale-up (supply of energy meters) 1.098 0.000 1.098 100%

Services

Project supervision and management 1.460 0.162 1.622 90%

Technical assistance and capacity building 1.120 0.000 1.120 100%

Audit service 0.000 0.020 0.020 0%

Operating costs

Project administration and operating expenses 0.000 0.727 0.727 0%

Others

ESMP / ARAP 0.000 1.420 1.420 0%

Total project cost 23.189 6.772 29.961 100%

2.4.3 The financing expenditure schedule by component is provided in Table 2.6.

Table 2.6:

Expenditure schedule by component

Component Expenditure per year (UA million)

2014 2015 2016 2017 Total

A) Upgrading and rehabilitation of substations 0.000 0.929 3.019 0.697 4.644

B) Access scale-up 0.000 6.122 11.224 3.061 20.408

C) Project administration and management 0.698 0.698 1.570 0.523 3.489

D) ESMP / ARAP 0.426 0.426 0.426 0.142 1.420

Total 1.124 8.175 16.239 4.423 29.961

Cumulative 1.124 9.299 25.538 29.961

2.5 Project’s Target Area and Population

2.5.1 The key project beneficiaries will be an estimated 25,438 rural households living in

both Northern Province (Rulindo and Gicumbi districts) and Western Province (Ngororero,

Rusizi, Nyamasheke, Nyabihu and Karongi districts), representing around 127,000 people.2 In

addition, public infrastructure will be significantly improved, as the project will provide

access to modern, reliable energy to 179 schools, 29 health centers, and 25 sector

administration offices. Finally, markets, business centers, and other major consumers will be

given priority in the routing as per the program design. It is therefore expected that small-

scale businesses and the few large commercial and industrial clients located in the area will

benefit from the program.

2.5.2 According to a 2012 survey, in the Northern and Western provinces, 42.8% and 48.2%

of households, respectively, were defined as poor and 23.5% and 27.4% as extremely poor,

respectively. The main economic activity in both provinces is agriculture, with more than

47% of people living on small-scale agriculture, primarily subsistence. The main cash crops in

2 Estimated five people per household (INS).

Page 16: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 7 -

both regions are coffee and tea, usually managed as cooperatives, as well as the production of

cassava, banana, and beans in the Northern Province.

2.6 Participatory Approach

2.6.1 There were intensive consultations among development partners during the

preparation of the GoR’s electricity rollout program and on the investment prospectus. The

GoR and development partners had roundtable discussions on 23 March 2009 during which

support for the rollout program was reaffirmed, and together they pledged contribution

totaling USD 228 million for the first phase of implementation (2009–2013).

2.6.2 In the framework of specific activities related to this project, consultations were

conducted with communities, affected people, civil society, and key sector and local

administrative officials during the preparation of the Strategic Environmental Assessment

(SEA), covering all activities pertaining to the second phase of EARP and finalized in

September 2012. While the consultations involved stakeholders concerned with the entire

program, the assessment covered the specific activities financed under this project. The SEA

involved different consultation techniques, such as public hearings based on occupation and

location (e.g., with farmers, sector executive secretaries, or traders) as well as focus groups

(e.g., women, youth, or the elderly). Moreover, additional consultations were conducted with

affected people in the preparation of the Abbreviated Resettlement Action Plan (ARAP)

prepared for the relocation of the Rulindo substation. At project launch, the EARP team will

inform communities about its activities and educate people about how to use electricity safely.

During implementation, the contractor will be contractually required to continue consultations

and carry out awareness activities outlined in the EARP Environmental Safety and Social

Guidelines.

2.7 Bank Group Experience and Lessons Reflected in Project Design

2.7.1 As of the end of January 2013, the Bank’s portfolio comprised 20 operations (see

Appendix II). These included 16 sovereign loans and grants and four private-sector

operations, amounting to a total commitment of UA 280.7 million. The Bank’s portfolio

distribution by sector shows that infrastructure (energy, transport, and water) accounts for

62% of the total commitments, followed by agriculture, 18%; private sector, 12%; human

development, 5%; and multi-sector, 2%. The Country Portfolio Performance Review (CPPR

of 2012) clearly demonstrated that the portfolio performance has improved from an overall

rating of 2.4 in 2011 to 2.53 in 2012. There have also been remarkable improvements in the

disbursement rate, from 18.1% in 2011 to 31.8% in 2012. There were no problematic or

potentially problematic projects as of the end of March 2013. The active sovereign portfolio

has an average age of 3.5 years with no aging projects.

2.7.2 The AfDB’s preparation and appraisal of the proposed project have incorporated

lessons learned from the Bank’s past interventions in Rwanda, as well as other development

partners’ interventions in electrification programs, particularly in the first phase of EARP.

The lessons learned from the Bank’s past intervention, as well as other development partners’

interventions, are detailed in Annex B1.

2.7.3 The lessons learned from the Bank’s past interventions mainly relate to: (i) project

readiness and quality at entry; (ii) project startup and implementation delays due to ineffective

institutional arrangements and delays in fulfilling all the conditions precedent to the loans,

grant effectiveness and the first disbursement; (iii) delays in submitting bidding documents

Page 17: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 8 -

and evaluation reports due to the lack of expertise of the executing agency; (iv) poor quality

and inconsistent procurement documents (bidding documents, bid evaluation report, contract

documents, etc.) prepared by the executing agencies causing delays in the issuance of no-

objection; and (v) delays in the preparation of ESIA and RAP studies by the executing

agencies. The proposed project takes these lessons into account by: (i) ensuring that the

proposed project is supported by appropriate design, feasibility, ESMP, and ARAP studies;

(ii) providing training and support to the executing agency through the technical assistance

subcomponent, (iii) ensuring strong implementation agency arrangement; and (iv)

implementing the proper procurement process.

Strong implementing agency improves results: Effective projects require strong capacity

from the implementing entity. EARP has handled several projects and the first phase of

the rollout program and will be further strengthened through appropriate staffing,

implementation arrangements, and technical assistance.

Lack of procurement capacity causes delays: A longer procurement process can be

attributed to: (i) inconsistent technical specifications, (ii) inadequate procurement staffing,

and (iii) an inadequate recordkeeping system. The proposed project will minimize such

delays through the selection of experienced consulting firms for the preparation of design,

specifications, and bidding documents. In addition, the technical assistance subcomponent

under the project will strengthen the ability of EARP in these areas, building its capacity.

2.7.4 The proposed project incorporates good international practice and experience in

several essential ways: (i) the prospectus investment program is anchored by a well-

prioritized and planned spatial least cost rollout plan, driven by the EDPRS targets and guided

by Rwanda’s multi-sectoral development priorities; (ii) the overall financing policy strikes a

measured and workable balance between affordability for beneficiaries and the limited

availability and opportunity cost of funds for investment in Rwanda, while also ensuring the

commercial viability of the EWSA and overall program sustainability; (iii) a midterm review

of EARP, conducted by an independent consultant, has evaluated the progress of key

activities and targets, with the ultimate intention to provide an impetus for adjustments that

may be required in order to keep the program relevant to the broader sectoral goal; and (iv)

the second phase of EARP is supported by a well-designed and prioritized study, taking into

account the lessons from the prospectus and the midterm review.

2.8 Project’s Performance Indicators

2.8.1 The key outcome indicators will be increased access to electricity and sustained

reliable electricity supply in the project areas. The main deliverables and outcome indicators

of the project are:

Access: (a) 25,438 households connected to national electricity and (b) 179 schools, 29

health centers, and 25 sector and cell administration offices gaining access to electricity in

the project area by constructing: (i) 464 km of MV distribution lines and (ii) 710 km of

LV networks.

Quality: Sustained reliability of electricity supply for existing and new consumers by: (i)

reducing power losses and (ii) reducing monthly average power interruption through

rehabilitation and upgrading of the Gifurwe substation to 10 MVA capacity and building a

new Rulindo substation with 20 MVA capacity.

Page 18: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 9 -

In-house capacity: (i) increased number of staff trained and improved sector project

planning and design preparation, as well as improved financial management system and

procurement handling in the executing agency; and (ii) reviewed energy sector policy and

strategy.

2.8.2 Statistical reports produced by EWSA and MININFRA will verify the performance

indicators. The progress during implementation will be measured by the timely

commencement of the work, regular disbursements, consultations with the Project

Management Teams, timely submission of quarterly progress reports and implementation of

the ESMP/ARAP, and annual audit reports. After completion of the project, its effectiveness

will be assessed via monitoring of productive use of electricity in the targeted project areas,

which will be done in close cooperation with the Ministry of Agriculture and concerned

government institutions.

2.8.3 The technical assistance component will provide the EWSA/EARP with technical

support and know-how to build the in-house capacity for preparation of project planning,

feasibility study, design documents, proper financial management and procurement handling;

to MININFRA, it will provide help with the preparation and revision of energy policy and

strategy. The source of data to confirm these indicators will be time-to-time assessments of

the effectiveness of the technical assistance. This effectiveness will be monitored, after

completion of the project, through the quality of projects and documents prepared in the

future by the executing agency.

III. PROJECT FEASIBILITY

3.1 Economic and Financial Performance

3.1.1 The Bank and EARP jointly developed the project’s financial model, basing it

primarily on data from the EARP midterm review, EWSA’s corporate financial model, and

project technical feasibility studies. In order to determine the impact of the proposed

investment, the model adopts an incremental analysis, which entails comparing the “with the

project” scenario to the “without the project” scenario.

3.1.2 The results of the analysis show that the project is financially sustainable and

economically viable. Its financial internal rate of return (FIRR) is estimated at 21.5% (real)

while the financial net present value (FNPV) discounted at a real rate of 10% is USD 40.15

million. These figures were obtained on the basis of a flat electricity tariff of RWF 134.40

(exclusive of VAT) per KWh charged to residential consumers since August 2012.

3.1.3 The economic benefits of the project are computed by considering the willingness to

pay of the targeted end users. According to the data available from the EARP Socioeconomic

Baseline Study, carried out by Kabonos Consulting during the midterm review of the first

phase of EARP, the total amount spent by non-electrified households for lighting and

telephone charging is RWF 3,100 (around USD 4.91) per month. Assuming an average

consumption of 10 KWh per month for non-electrified households, their energy cost is

estimated at around RWF 310/KWh (around USD 0.491/KWh). Connecting these non-

electrified households to the grid will thus reduce energy costs from RWF 310 to RWF

134.40 per KWh. The project will yield a high economic internal rate of return (EIRR) of

39% (real) and an economic net present value (ENPV) discounted at the opportunity cost of

capital of 12% (real), estimated at USD 143.28 million.

Page 19: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 10 -

3.1.4 The main financial and economic results are summarized in Table 3.1 below. The

detailed calculations and assumptions are presented in Annex B7.

Table 3.1:

Key financial and economic results

Base case

FIRR (%, real) 21.5%

FNPV (@10% real, million USD) 40.15

EIRR (%, real) 39.0%

ENPV (@12% real, million USD) 143.28

3.1.5 A sensitivity analysis was also performed against the key risk variables of the project

to test the robustness of its financial and economic cash flows. The identified key risks

include an increase in investment costs, an increase in operating costs, and a reduction in

revenues. The results of the sensitivity analysis show that the financial and economic results

are robust under adverse conditions. Details of the financial and economic analysis, as well as

the sensitivity analysis, are provided in Annex B7.

3.2 Environmental and Social Impacts

The project is classified as Category-II because it is a small-scale power development and

rural electrification project that would require the relocation of four households comprising

eight people, due to the relocation of the Rulindo substation The Strategic Environmental

Assessment (SEA), ESMP, and ARAP were compiled in September 2012, September 2010,

and January 2013, respectively. The ESMP and ARAP summaries were posted on the Bank’s

website since 2 May 2013.

3.2.1 Environment

The positive impacts of this project are numerous and wide-ranging. They include creation of

employment opportunities, improved socioeconomic status of the affected communities,

opportunity to develop sectors other than agriculture, reduced deforestation to some extent

and improvement in service delivery. Negative impacts include permanent loss of residential

and agricultural land belonging to private individuals. There will be permanent loss of crops

because the site for the new Rulindo substation is mostly farmland (growing avocadoes,

grevillea, peppers, ficus trees, eucalyptus, potatoes, and beans). It is anticipated that

construction activities, including frequent entry and movement of vehicles, will disrupt daily

living. Noise resulting from access road and substation construction may disturb neighboring

communities and local fauna. Dust will be an issue because it is recommended that

construction takes place during the dry season. Stripping, grading, soil removal, backfilling,

compacting, disposal of surplus, and surface excavation to make way for the installation of

the substations and erection of the towers will lead to localized soil erosion. Solid waste

materials during the construction will include paper wrapping, scrap metal, excavated soils,

polythene, plastic, and metal; these will cause pollution of and littering in the immediate

environment.

3.2.2 Mitigation

Mitigation of the impacts will include the engagement of a refuse handling company to

remove waste from the site to recommended disposal and recycling areas where possible.

Page 20: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 11 -

Inert waste will be used for backfilling. Local authorities will be consulted in advance

regarding provision of construction schedules to the community to ensure minimum

disruptions. Heavy vehicles will make use of the existing access roads and in cases where

private roads are to be used; this will be negotiated with property owners before construction

begins. Vehicles will keep to the speed limit and avoid busy roads as far as possible.

Construction will not go on after hours or over weekends and will preferably not take place

during the harvest season. The executing agency will also ensure that affected people are

given advice and encouraged to secure other land as opposed to using their financial

compensation on non-sustainable activities such as moving to cities without clear plans for

finding employment.

3.2.3 Climate Change

3.2.3.1 As per the climate change action plan (2010), average annual rainfall may increase by

up to 20% over 1970 levels by the 2050s. As described in its Rwanda Green Growth and

Climate Resilient Strategy (2012–2017), the country follows a climate-resilient pathway,

incorporating adaptation to climate change into policy and planning. Therefore, given the risk

of flooding, the rehabilitation and construction works to be undertaken for the project must

include climate-proofing of the infrastructure. In this regard, the Rulindo substation, which

will be relocated from the marshy area where it is currently situated, must be located outside

the 1:100 year flood line.

3.2.3.2 Rwanda has one of the lowest per capita greenhouse gas (GHG) emission levels in the

world, estimated at 0.4 tCO2e/person, compared to a global average of 6.7 tCO2e/person. In

this regard, the contribution of this project to GHG is insignificant; particularly considering

that half of the power in the targeted area is hydro and that most households connected will be

using energy-efficient CFL bulbs. Moreover, the relocation of the Rulindo substation will

offset carbon emissions, as it will allow the restoration of the wetland it now sits on, which

can then act as a carbon sink. Providing electricity to Rwanda’s rural and peri-urban

population will reduce dependency on wood and fuel. The grid expansion component of this

project should also be seen as benefitting climate change.

3.2.4 Gender

3.2.4.1 It is expected that the project will benefit an estimated 66,910 women and 3,446

female-headed households living in the project area. Electricity can facilitate cooking, as it

allows for refrigeration, reduces constraints on time allocation, and cuts down on the risk of

accidents such as cuts and burns. Additionally, it reduces the burden of collecting fuel wood,

which has become an increasingly tedious task in certain areas, requiring traveling longer

distances due to forest overexploitation. However, the impact of electricity access is limited in

key ways. While electricity will replace the use of firewood used for lighting, given the lack

of a cheaper alternative it is unlikely to replace in a significant manner the use of wood for

cooking, which is currently used by more than 90% of households in both provinces.

3.2.4.2 Electrification can increase the time women can allocate to income-generating

activities as well as their probability of employment in the community’s businesses. In the

Northern and Western provinces, around 78% and 68% of women, respectively, work in

small-scale farming activities (compared to 47% and 50% of men).3 Wage-farm activities

represent the second most important source of income, employing around 12% of women in

3 EICV3—Thematic Report—Gender.

Page 21: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 12 -

both provinces. Access to electricity will diversify income-generating opportunities for

women, allowing them to work in sectors not constrained by daylight hours, such as sales and

commerce, which are the dominant occupations for women outside farming.4 This in turn will

lead to greater financial independence and improved child welfare, as extra income earned by

women is likely to be invested in children.

3.2.5 Social

3.2.5.1 Improved day-to day welfare of households: Connecting households to the grid will

considerably and immediately improve their welfare via more reliable and quality lighting, as

well as an increased use of ICT. In the project area on average, only around 7.5% of

households use electricity as a source of lighting. The most important sources of lighting used

currently instead of electricity are batteries (35%), fuel lanterns (27.6%), and firewood

(11.7%). Access to the grid will not only provide a more reliable and cheaper source of

energy, but will also reduce indoor air pollution from fuels such as firewood and kerosene.

By allowing for more efficient time allocation and extended total time available, lighting will

not only free up time for productive economic activities but also for leisure, with

opportunities to listen to the radio, read, or socialize. Another important use of electricity will

be to operate radios and phones, already owned by more than 50% and 40% of households,

respectively, in both provinces. The literature points out that access to information through

ICT plays an important role in increasing knowledge about health practices and awareness of

rights and diminishing gender barriers. Moreover, EARP provides low-income households

that cannot afford their own electrical installation with “ready boards,” which include lights

and sockets, free of charge.

3.2.5.2 Improved public services: A key impact will be the improved quality of public

services, foremost among which are health and education services. The project is expected to

connect to the grid 29 health centers that currently use generators for lighting and fuel

refrigerators for vaccines. This will allow the use of electric biomedical refrigeration

equipment for laboratories and the possibility of keeping stocks of vaccines in remote areas.

Providing electricity to these health centers will also facilitate medical consultations,

surgeries, and hospitalizations (such as for childbirth) in their villages, thus reducing health

risks and costs incurred if a patient needs to be evacuated to a hospital elsewhere. On the

education front, the project is expected to electrify 129 primary and secondary schools. This

will allow for extended hours of schooling and extracurricular activities and attract more and

better-qualified teachers. Finally, 25 local administration offices will be connected to the grid,

allowing for more efficient use of time, resources, and data management.

3.2.5.3 Direct employment: Based on the current experience with distribution and similar

activities conducted to this day in Northern Province, it is expected that the project will

directly create an estimated 800 temporary jobs during construction activities, of which 600

would be unskilled to semi-skilled labor. Similar experience shows that at least 80% of the

semi-skilled and unskilled jobs will be filled by local people. It also suggests that around 15%

of jobs for locals will be filled by women, and EARP will make active efforts to sensitize the

contractor on this issue in order to increase their participation. Local capacity will also be

increased as apprentices are hired as engineers and technicians. During construction, the

project will also generate indirect employment through the use of vendors and contractors, as

well as local small-trade and restoration services.

4 Ibid.

Page 22: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 13 -

3.2.5.4 Business development opportunities: The project will support the long-term

development of the private sector, particularly for small and medium agricultural businesses

(e.g. flour mills, coffee processing centers, sugarcane juice makers) prominent in the project

area. It will support the expansion of existing businesses through the use of electric machinery

and longer opening hours, as well as the development of new businesses (e.g. photocopy

shops, restaurants, and tourism-related activities). Grid electricity will lower the operational

costs of businesses that are currently using the next best alternative, such as stand-alone diesel

generators for large power usage or batteries for low power usage. Findings from the

evaluation of the first phase of EARP showed that electrification cut businesses’ energy cost

by 50% to 75%.

3.2.6 Involuntary Resettlement:

3.2.6.1 Among all project activities, the relocation of the Rulindo substation (Component A)

and the extension of the distribution network (Component B) will generate physical and

economic displacement. EARP has elaborated an Abbreviated Resettlement Action Plan

(ARAP) for the Rulindo substation and a Resettlement Framework for Component B. The

ARAP identified four households comprising eight people whose houses, trees, and crops will

be affected by the relocation of the substation.

3.2.6.2 Moreover, it is expected that the MV and LV distribution lines (Component B) will

damage additional crops and trees. Given that the exact routing of the lines will be determined

by the contractor once on board, more specifics of the RAP of each lot will have to be

developed during implementation.

IV. PROJECT IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 Institutional Arrangements: The borrower of the proposed ADF loan and grant will

be the Government of the Republic of Rwanda through its Ministry of Finance and Economic

Planning (MINECOFIN). The executing agency (EA) of the project will be EWSA. For the

purpose of implementing the national electricity access program, the GoR and EWSA have

established an EARP Implementing Unit under EWSA to facilitate project implementation

regardless of the source of funding. The EARP will report to EWSA and will bear oversight

responsibility. It will be primarily responsible for facilitating, monitoring, evaluating, and

reporting on project activities and progress.

4.1.2 In assessing the capacity of the EAs to implement the project, it is noted that EWSA

and EARP have gained technical and managerial experience through implementation of

donor-funded projects. However, as the EARP program coordinator is managing all projects

regardless of the source of funding and faces a huge burden to control, monitor, and supervise

the projects as required, further strengthening of the existing EARP implementation unit is

needed. For the proposed project, the project implementation team will be established within

the implementation unit, comprising a focal point person to manage and coordinate the project

under the supervision of the EARP program coordinator, and sufficient staff to run the

proposed project. EWSA/EARP will submit the CVs of the focal point, one environmentalist,

one procurement specialist, one social expert, two engineers, and one accountant to be

assigned to the project for the Bank’s approval. The profiles of the focal point and other staff

members are given in Annex B.3. The EARP project team will be assisted by a consultant

procured under this project, who will review and update the design and bid documents, assist

Page 23: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 14 -

during the bid evaluation, review and approve the contractor’s detailed engineering design,

and supervise and monitor the project implementation, including of the ESMP. The

involvement of the consultant will reinforce the capacity of the EARP project team. EARP

will be responsible for compiling and transmitting quarterly progress reports and audit reports

to the Bank and implementing the ARAP. The implementation arrangements are detailed in

Annex B.3.

4.1.3 Procurement Arrangements: All procurement of goods, works, and acquisition of

consulting services financed by the Bank will be in accordance with the Bank’s rules and

procedures: “Rules and Procedures for the Procurement of Goods and Works” (May 2008)

and “Rules and Procedures for the Use of Consultants” (May 2008), as amended from time to

time, using the relevant Bank standard bidding documents and the provisions stipulated in the

Legal Agreement. EARP, under the supervision of EWSA, will be responsible for the

procurement of goods, works, and consultancy services. The resources, capacity and expertise

of EARP are adequate to carry out procurement. The overall project risk for procurement is

moderate. Detailed procurement arrangements are provided in Technical Annex B5.

4.1.4 Financial Management: The financial management’s system of EWSA, through its

EARP implementation unit, is considered to be adequate to carry out the budgeting

accounting and capable of recording accurate and complete transactions; delivering timely

financial reports; maintaining internal controls, funds flow management, and financial

reporting; and facilitating external auditing according to the Bank’s requirements. EARP has

proper structures in place as well as adequate staff to carry out the FM responsibilities of the

project. The annual project financial statements will be prepared in accordance with

International Public Sector Accounting Standards (IPSAs) by 30 September 2013. In addition,

the Project will provide an update on financial performance of the project as part of the

Quarterly Progress Report (QPR) as required by the Bank not later than 45 days after the end

of the quarter. EARP keeps its own books of accounts and separates the different donors’

financial statements and reporting in accordance with the IPSA’s modified cash basis of

accounting, in the context of Ministerial Order No. 002/07 of 9 February 2007 relating to

financial regulations. A supervision mission will be conducted at least twice every year based

on the risk assessment of the project. The mission’s objectives will include that of ensuring

that strong financial management systems are maintained for the project throughout its life.

Reviews will be carried out regularly to ensure that expenditures incurred by the project

remain eligible for ADF funding. The initial risk assessment is set at moderate at this stage.

A detailed assessment of the financial management is provided in Annex B.4.

4.1.5 Disbursement: The executing agency will utilize the Bank’s four disbursement

methods as prescribed in the Disbursement Handbook; the direct payment method will be the

preferred one for payments to contractors, suppliers, consultants and service providers upon

the recommendations of the implementing agency and project-authorized consultant of their

satisfactory performance. The project will operate one foreign special account into which the

proceeds of the loan and grant will be deposited and further to a local currency special

account. The executing agency will open both special accounts at the National Bank of

Rwanda. The opening of foreign and local currency special accounts will be made a condition

precedent to first disbursement of the loan and grant. A detailed assessment of the financial

management and disbursement arrangements is provided in Annex B.4.

4.1.6 Audit: The internal control system at EWSA is satisfactory. EARP has an Internal

Audit Unit and a Fraud and Investigation Unit whose duties include overseeing the activities

handled by EARP internal controls as detailed in the Financial Management Manual; this will

Page 24: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 15 -

apply to the project. The auditor general is primarily responsible for the auditing of all

government projects and in line with the Paris Declaration; Rwanda’s Supreme Audit

Institution will be the auditor for the project. The auditor general will audit the project

accounts annually and at the end of the project in line with the Terms of Reference agreed

with the Bank. The audit report, complete with a management letter and management

responses, will be presented annually to the Bank within six months of the end of each fiscal

year. The annual audit will be done in accordance with International Standards on Auditing. A

detailed assessment of the audit system is provided in Annex B.6.

4.2 Project Monitoring and Evaluation

4.2.1 Monitoring of and reporting on the project implementation progress will be the

responsibility of EWSA’s project implementing unit (EARP). EARP will have the

responsibility to supply current data on the set of agreed performance indicators at least: (i) on

an annual basis for project outcome indicators, (ii) on a quarterly basis for performance

targets based on the output of each components of the project and propose corrective actions;

and (iii) on an annual basis for audit reports. These reports shall cover all aspects of project

implementation, including the status of progress against agreed implementation and

disbursement schedules for all components; implementation of environmental and social

mitigation measures; and the status of fulfillment of the loan conditions. The audit report will

be prepared by EWSA. Via the Bank’s supervision missions—at least twice a year—and

reviews of annual audit reports, the Fund will closely monitor the project implementation.

4.2.2 The Bank will undertake a midterm review of the project approximately 24 months

after the effectiveness of the loan and grant. The execution of the ESMP and ARAP will also

be monitored during all stages of the project by EARP and through the Bank’s supervision

missions. The consultant shall also prepare and submit to the implementing agency and the

Bank final commissioning reports at the completion of their assignments. Within six months

of the completion of the project, the Bank, together with the implementing agency, will

prepare and submit a Project Completion Report (PCR).

4.3 Governance

4.3.1 The financial management arrangements at EWSA and EARP are adequate to ensure

that project resources are used for only the purposes for which they were granted, with due

consideration for efficiency and economy. This project will be implemented following

Rwanda’s Public Financial Management (PFM) system to a large extent. The EWSA’s

director general will be the accounting officer, with EWSA’s Board of Directors providing

general guidance and direction to the EARP. Project operations will be guided by all existing

procedures and manuals, such as the finance manual. The project will adopt all Rwanda’s

governance and anticorruption policies and guidelines. Details on how to report and penalize

corruption are well laid out. The EARP internal audit responsibility lies with EWSA’s

Internal Audit Department, which is headed by a chief internal auditor who reports to the

Board of Directors and administratively to the director general of EWSA. The internal audit

function will play an important role in conducting regular audits for the project, as it is

currently doing. On a monthly basis, EARP accounts are also pre-audited by this directorate

before approval by the director general. The department’s reports will be shared with the

Bank as needed. External oversight will be provided by the Auditor General. The Bank will

provide some oversight, especially during supervision missions. All the anticorruption

measures that pertain to government will apply to this project. There will be at least one

value-for-money audit at midterm.

Page 25: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 16 -

4.3.2 The financial management arrangements of the program implementing unit, EARP,

have been found to be adequate to provide, with reasonable assurance, accurate and timely

accounts/information on the status of the project as required by the Bank. Follow-up will be

made to ensure actions taken on the items detailed in the Financial Management Action Plan

as provided in Annex B.4.

4.4 Sustainability

4.4.1 The project is technically, economically, and financially sustainable. The

sustainability of the electricity access program rests on several key factors: (i) GoR

commitment and total alignment with the project development objective, (ii) development

partners’ commitment to the implementation of EARP, (iii) strengthening the financial

management capabilities within EWSA, the key implementing agent, (iv) near-term actions to

strengthen EWSA, including targeted capacity-building—technical, commercial, managerial

capability for operation, and maintenance of the extended network; and (v) the simplicity of

project technical design, which uses proven technologies.

4.4.2 Government commitment to the project and program. The GoR’s commitment to

EARP and to its objective is strong and is anchored by pillars and targets of the EDPRS,

Rwanda Vision 2020, and the intermediate targets in the 2015 Millennium Development

Goals (MDGs). The proposed project, which is part of the GoR electricity rollout program,

will improve access to reliable and cost-effective electricity services for households and

priority public institutions per the GoR’s commitment.

4.4.3 Development partners’ commitment to the program. The commitment of

development partners is positive and was found strong in the implementation of the first phase

of the program. In the second quarter of 2013, a stakeholder and donor roundtable meeting is

proposed to discuss the Phase 2 rollout plan to help mobilize resources to meet the national

targets that will be set in the EDPRS-2. Development partners have expressed their intent to

provide additional parallel financing to scale up Phase-2 activities of the EARP. The World

Bank approved additional financing of USD 60 million in March 2013. DFID approved an

additional funding of USD 12 million in September 2012, and discussions for funding from

BTC (EUR 17.0 million) and the Netherlands (EUR 21.0 million) are ongoing and expected

to be concluded by July 2013.

4.4.4 The executing agency financial capability and commercial viability. EWSA is a

revenue-earning entity whose financial performance is improving; it has gradually been

transitioning from a loss-making to a profitable operation. To make EWSA a self-sufficient

utility, it must be put on a path towards becoming a credible entity capable of corporate

borrowing from commercial sources (commercial banks and possibly issuance of bonds to be

sold to domestic investors). The steps on this path are: (i) within its current structure, EWSA

should ensure a transparent performance of each segment of the supply chain by separating

the financial accounts of various business units including: generation, transmission, and core

services, (ii) EWSA should be converted into a corporation that could then become an

independent (fully government-owned) company that would be legally able to borrow on its

own account; and (iii) EWSA should gradually improve its creditworthiness. To put EWSA

on this path, it is necessary to establish the performance benchmarks and the legal framework

needed for the medium-term developments.

Page 26: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 17 -

4.4.5 Capacity to operate and maintain the facilities: EWSA has both the technical and

managerial capacity to operate and maintain the substations and distribution network

infrastructure. EWSA has a large pool of well-qualified personnel from which the utility can

readily replenish its manpower requirements over the project life. However, as the network

extends rapidly to meet the government’s target of access, EWSA needs further institutional

strengthening going forward to effectively and efficiently implement the ambitious EARP

targets and operate the facilities. In this regard, the capacity-building component of this

project will strengthen the technical skills necessary to implement projects and successfully

manage the energy infrastructure under the staff’s authority. Stakeholders in the energy sector

will also benefit from the technical assistance provided jointly by AfDB and the Fund for

African Private Sector Assistance (FAPA) in order to support skills development in the

energy sector and thus improve the sustainability of the built infrastructure

4.4.6 Project technical design. All the technologies applied in the project have been widely

used in other countries with similar conditions and in the region.

4.5 Risk Management

The project involves some degree of risks at implementation level and during the life of the

facilities (after project completion). The major risks and mitigation measures are discussed in

Table 4.1 below. Overall, the project risk is low to moderate.

Table 4.1:

Risk and mitigation measures

Risk Risk description Rating Mitigation

Risks at implementation level

Political risk

and

stakeholders

a) Borrower relations: (i)

The project prioritization of

the grid rollout may not be

in synchronized with the

GoR-targeted areas,

considering social-political

aspects, (ii) GoR target of

70% coverage by 2018

unlikely to be met.

b) Partner relations: There

may be a lack of

harmonization and approach

between the various

development partners

involved in the sector.

c) Interagency

cooperation: A lack of

clarity of roles and

responsibilities of the

various government agencies

may impede on the

harmonized implementation.

M a) (i) GoR has showed a continuous effort for

energy access rollout. The project fits well

with the country’s energy sector strategy and

is a high priority for the government.

(ii) EARP has carried out a grid zoning and is

based on transparent indicators for

prioritization, the most dominant one being

cost-effectiveness.

(iii) EARP is complementing with selected off-

grid installations, which will focus on socially

important institutions such as health centers

and schools wherever it is more cost-effective

than grid connection.

b) (i) Strengthen the sector working group

secretariat and the EARP project unit to take

leadership in streamlining development

partners’ support to the access scale-up

program;

(ii) Expand the program steering committee to

include other development partners

supporting the access rollout program.

c) Continue with the current implementation

arrangements, where the EARP is responsible

for implementation with guidance from

MININFRA.

Completion

delay and cost

overrun

Risk of completion delay

and/or that the cost of the

project might escalate during

implementation.

L Meticulous preparation of design and technical

specifications, as well as evaluation and

qualification requirements, should ensure

minimum variance in costs.

Page 27: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 18 -

Risk Risk description Rating Mitigation

Selection of experienced and reputable

contractors through competitive bidding process

with fixed price and time bounded contracts will

minimize delays in completion.

Selection and employment of experienced

project management and supervision consultant

to augment project staff will ensure project’s

delivery efficiency.

Delay on

starting and

completion of

procurement

process

The risk associated with

delay on starting and

longtime of procurement

process due to limited

human resources in

EWSA/EARP will delay the

implementation period of the

project.

L Implementation of the advance

contracting/procurement option.

Selection of an experienced project management

and supervision consultant to prepare the design,

specifications and biding documents.

Environmental

and social

The project is classified as

environmental Category II.

There are risks to

satisfactory implementation

due to inadequate number of

skilled staff.

M The project unit capacity will be enhanced with

two additional safeguard staff, with Bank funding,

to ensure that there is sufficient capacity to ensure

close monitoring and implementation of the ESMP

and ARAP. The project team will monitor closely

during the course of project implementation to

ensure safeguard compliance.

Risks after completion of the project

Inadequate

power supply

to meet

demand

stemming

from new

connection

There is a risk associated

with rapid increase of

demand from the households

electrified in the first phase

of EARP and delay of

ongoing generation projects

and NELSAP

interconnection.

L In regards to overloading of networks, the recent

Electricity Network Planning & Design study

carried out at the end of 2012 has reviewed

supply/demand modeling based on the 10-year

load forecast to identify possible bottleneck

areas. Accordingly, the study has recommended

upgrading and extending the network.

The new hydro and methane gas power

generation projects under construction and the

NELSAP interconnection project will meet the

increased demand for electricity.

Early identification of supply constraints will

facilitate timely mitigation measures, including

additional use of rental diesel generators and

lowering the pace of additional connections for

shorter periods until supply is available.

An energy efficiency program will be

implemented through use of compact fluorescent

lamp (CFL) bulbs for new connections.

capacity and

technical risks

Risks related to the capacity

of the public utility (EWSA)

in operating and maintaining

the facilities in terms of

technical and financial

performance.

M The technical assistance and capacity building

support by the Bank under this project and also

by other development partners will strengthen

EWSA’s capacity.

Continuous human resource development on

operational and maintenance activities supported

by other development partners.

L: Low M: Moderate H: High

Page 28: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 19 -

4.6 Knowledge Building

4.6.1 The contract with the project supervision and management consultant will include

specific provisions to ensure the training of EWSA/EARP staff. This knowledge transfer

mechanism, especially regarding project management and supervision, is important to build

the in-house capacity of the utility, as it will manage other similar projects to meet the

government’s targets for access to electricity. During implementation of the project, the

captured knowledge will be monitored during Bank supervision missions, in quality and time

assessments of the procurement process, and in audit reports.

4.6.2 Technical assistance activities included in the project will support EWSA/EARP

project planning, preparation of feasibility studies, and design and technical specifications.

This in-house knowledge building will enable the utility to prepare projects on time and

ensure quality at entry to development partners for future projects. This training and capacity

building component will, in the short to medium term, reduce the technical and capacity risks

that could particularly be perceived by potential private investors interested in opportunities in

Rwanda. Indeed, in order to achieve its target to provide energy access for all, Rwanda will

need to attract private-sector participation in building the generation capacity of the country.

As such, building the in-house technical capacity of the power utility in areas such as

financial management and procurement will help in improving the efficiency of EWSA and

preparing it to work with private-sector counterparts.

5 LEGAL FRAMEWORK

5.1 Legal Instrument

The legal instruments for the project are an ADF loan and ADF grant, which will be given to

the Republic of Rwanda and the proceeds of the loan and grant on-lent to EWSA on terms

acceptable to the Bank.

5.2 Conditions Associated with Bank’s Intervention

5.2.1 Conditions Precedent to Entry into Force

a) The entry into force of the Loan Agreement shall be subject to the fulfillment by the

borrower of the provisions of Section 12.01 of the General Conditions Applicable to the

African Development Fund Loan Agreements and Guarantee Agreements.

b) The Protocol of Agreement shall enter into force on the date of its signature by the Fund

and the grant recipient under Section 10.1 of the General Conditions Applicable to

Protocols of Agreement for Grants of the African Development Fund.

5.2.2 Conditions precedent to first disbursement of the ADF Loan and Grant: The first

disbursement of the loan and grant shall be subject to the borrower having:

(i) submitted evidence that a subsidiary financing agreement, with terms and conditions

acceptable to the Fund, has been executed between the borrower and EWSA for

the purpose of on-lending the proceeds of the loan and grant;

(ii) provided evidence satisfactory to the Fund of the establishment of the project

implementation team, within the existing EARP implementation unit in order to

strengthen the unit, comprising a focal point for the project, two engineers, a

Page 29: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

- 20 -

procurement specialist, an accountant, an environmentalist, and a social expert whose

qualifications and experience shall be acceptable to the Fund (Paragraph 4.1.2 here

above);

(iii) provided evidence to the Fund of the opening of a designated special account for the

foreign currency and a designated special account for the local currency at the

National Bank of Rwanda (Paragraph 4.1.4 here above);

(iv) provided evidence to the Fund that all project-affected persons have been compensated

in accordance with the Rulindo Substation Abbreviated Resettlement Action Plan

(ARAP) (Paragraph 3.2.6.1 here above).

5.2.3 Conditions Precedent to Further Disbursements under the project component

“Access Scale-Up”

i) Submission to the Fund of a Resettlement Action Plan (RAP), full or abbreviated, as

applicable, under the Project component “Access Scale Up”, in form and substance

satisfactory to the Fund; and

ii) Submission to the Fund of proof of effective payment of PAPs according to the RAP, full

or abbreviated, as applicable, prior to the commencement of construction works on each

lot financed under the project component “Access Scale Up”. (Paragraph 3.2.6.2 here

above);

5.2.4 Undertakings

i) The borrower undertakes to implement and report to the Fund on the implementation

of the Environment and Social Management Plan (ESMP) for the Project annually and

on the implementation of the ARAPs/RAPs quarterly (Para 3.2.6 here above); and

ii) The borrower shall submit to the Fund quarterly progress reports, in a form and

substance acceptable to the Fund, on the implementation of the project.

5.3 Compliance with Bank Policies

This project complies with all applicable Bank policies. In particular, it is consistent with the

Bank’s Energy Sector Policy, approved in October 2012.

6 RECOMMENDATION

Management recommends that the Board of Directors approve the proposed ADF loan not

exceeding an amount of UA 15.494 million and ADF grant not exceeding an amount of UA

11.871 million from the resources of ADF-12 to the Republic of Rwanda for the purposes and

subject to the conditions stipulated in this report, the loan and grant agreements.

Page 30: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

I

Appendix I: Country’s Comparative Socioeconomic Indicators5

Selected Economic and Financial Indicators, 2008–17

Est. Country

Report

No.

12/152

Proj. Country

Report

No. 12/152

2008 2009 2010 2011 2012 2012 2013 2013 2014 2015 2016 2017

Output and prices

Real GDP growth 13.4 6.2 7.2 8.3 7.7 7.7 7.5 7.6 7.2 7.0 7.0 7.0

Real GDP (per

capita)

11.1 4.0 5.0 6.0 5.5 5.5 5.3 5.4 5.0 4.8 4.8 4.8

GDP deflator 10.4 9.5 2.5 7.7 7.7 7.7 7.8 7.2 6.4 5.3 5.3 5.5

Consumer prices

(period average)

15.4 10.3 2.3 5.7 7.9 7.9 7.0 7.0 6.3 5.8 5.3 5.0

Consumer prices

(end of period)

22.3 5.7 0.2 8.3 7.5 7.5 6.5 6.5 6.0 5.5 5.0 5.0

Money and credit1

Domestic credit2 20.5 3.8 9.4 5.0 18.5 12.8 19.6 29.0 16.0 11.4 15.0 12.5

Government2 -18.1 0.2 2.4 -13.2 6.7 -5.8 3.3 16.1 -4.4 4.6 0.0 0.0

Economy2 38.6 3.6 7.0 18.2 11.8 18.6 16.3 12.9 20.5 6.8 15.0 12.5

Broad money (M2) 24.2 13.1 16.9 26.8 17.0 16.5 16.9 16.3 15.6 13.7 13.7 13.8

Reserve money 23.5 0.3 12.5 23.4 17.0 16.5 16.9 16.3 15.6 13.7 13.7 13.8

Velocity

(GDP/M2; end of

period)

5.5 5.6 5.3 4.9 4.8 4.9 4.8 4.8 4.8 4.7 4.7 4.6

National income accounts

National savings 9.1 5.1 4.1 3.1 2.2 2.8 4.1 3.3 5.3 6.9 8.1 8.8

Gross investment 23.5 22.3 21.7 22.1 23.8 23.7 23.0 23.0 21.5 20.0 19.7 19.4

Of which: private

(including public

enterprises)

13.1 12.4 10.8 9.2 9.5 9.5 9.8 9.8 10.1 10.4 10.7 11.0

Government

finance3

Total revenue

(excl. grants)

12.6 14.9 12.5 13.6 13.8 14.3 14.0 14.9 14.9 15.1 14.9 15.2

Total expenditure

and net lending

22.6 26.3 25.7 27.7 26.9 26.6 28.0 32.3 28.4 24.4 23.3 22.9

Capital expenditure 8.2 11.0 10.1 12.3 12.4 11.7 13.5 13.7 13.1 10.1 9.4 9.0

Current

expenditure

15.1 14.5 14.7 14.8 14.5 14.9 14.3 14.0 14.6 14.1 13.9 13.4

5 IMF (2013). “IMF Executive Board Concludes 2012 Article IV Consultation with Rwanda.” Public

Information Notice No. 13/30, 19 March 2013.

Page 31: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

II

Overall fiscal

balance (payment

order)

After grants -0.2 -2.2 -0.1 -3.4 -1.9 -1.2 -2.6 -6.9 -2.9 -2.3 -1.6 -1.6

Before grants -10.0 -11.5 -13.2 -14.1 -13.2 -12.3 -14.0 -17.4 -13.5 -9.3 -8.5 -7.8

External sector

External current account balance

Including official

transfers

-4.9 -7.3 -5.9 -7.3 -10.0 -11.3 -9.7 -10.2 -9.0 -6.8 -5.9 -5.4

Excluding official

transfers

-14.4 -17.2 -17.5 -19.0 -21.5 -20.9 -19.0 -19.7 -16.3 -13.0 -11.5 -10.6

External debt (end

of period)

14.7 14.9 14.8 18.4 18.7 21.3 19.1 20.4 20.3 20.1 19.5 18.7

Net present value of external debt

(Percent of exports

of goods and

services)

… … 86.9 108.6 111.2 136.8 114.8 129.5 127.6 119.1 110.6 102.0

Scheduled debt service ratio

(Percent of exports

of goods and

services)

2.1 2.6 3.1 2.6 13.0 22.9 13.1 11.5 8.9 8.5 7.6 6.8

Gross reserves

(months of imports

of goods and

services)4

4.7 5.4 4.5 5.1 5.0 5.2 4.4 4.6 4.6 4.6 4.2 4.0

Gross reserves 596.4 742.2 814.2 1051.2 1042.0 1144.2 950.4 989.0 978.8 1030.1 1006.2 1047.6

Memorandum item:

Nominal GDP

(billions of Rwanda

francs)

2,565 2,985 3,280 3,826 4,409 4,437 5,109 5,118 5,839 6,578 7,412 8,364

Sources: Rwandan authorities and IMF staff estimates and projections. 1 Projections are based on the program exchange rate of RWF 604.14 per U.S. dollar. 2 As a percent of the beginning-of-period stock of broad money. 3 On a fiscal-year basis (July–June). For example, the column ending in 2011 refers to FY2010/11. 4 Data from 2009 onward includes SDR allocation.

Page 32: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

III

Appendix II: AfDB’s Ongoing Portfolio in Rwanda

No. Sector and project name Type of

instrument

Total

amount

(UA)

% disb.

as of

Jan. 2013

Approval

date

1.0 AGRICULTURE

1.1 Bugesera Agriculture Development Support

Project—PADAB ADF grant 10,000,000 73.1% 24-Jul-06

1.2 Livestock Infrastructure Support Program—

LISP (SBS) ADF loan 21,810,000 100% 29-Jun-11

TOTAL APPROVALS 31,810,000 91.6%

2.0 TRANSPORT

2.1 Butare-Kitabi-Ntendezi Road Project ADF grant 16,000,000 61.7% 25-Mar-09

TOTAL APPROVALS 16,000,000 61.7%

3.0 WATER SUPPLY & SANITATION

3.1 Rural Water and Sanitation—Phase II

(AEPA)

ADF grant

RWSSI 16,000,000 58.1% 1-Jul-09

TOTAL APPROVALS 16,000,000 58.1%

4.0 SOCIAL

4.1 Support to Skills Development in Science &

Technology ADF grant 6,000,000 20.3% 11-Nov-08

4.2 Regional ICT Centre of Excellence ADF loan 8,600,000 0.6% 14-Dec-10

TOTAL APPROVALS 14,600,000 8.7%

5.0 MULTI – SECTOR

5.1 Competitiveness & Enterprise Development ADF grant 5,000,000 51.8% 29-Dec-08

5.2 Support for Policy and Strategy Development ADF grant 1,000,000 96.4% 18-Sep-09

TOTAL APPROVALS 6,000,000 59.2%

6.0 PRIVATE SECTOR

6.1 Support to Rwanda Private Sector Federation FAPA grant 1,000,000 59.8% 27-Aug-08

6.2 KivuWatt AfDB loan 15,892,693 81.5% 3-Feb-11

6.3 BRD (LOC & FAPA) AfDB loan

FAPA grant 5,881,798 0% 19-Nov-10

6.4 BK (LOC & FAPA) AfDB loan

ADF loan 7,955,460 0% 19-Nov-10

TOTAL APPROVALS 30,729,951 44.1%

7.0 MULTINATIONAL OPERATIONS

7.1 Isaka-Kigali Railway Study (Phase 2) ADF grant 1,670,000 35% 17-Nov-09

7.2 Nyamitanga-Ruhwa-Ntendezi-Mwityazo

Road ADF grant 50,620,000 37.3% 16-Dec-08

7.3 NELSAP Interconnection ADF grant 30,470,000 0.8% 27-Nov-08

7.4 Bugesera Multinational Project ADF grant 14,980,000 16% 25-Sep-09

7.5 Rubavu-Gisiza Road Project ADF loan

ADF grant

45,050,000 0% 25-Jul-12

7.6 Sustainable management of woodlands and

restoration of natural forests of Rwanda

Congo

Basin Fund

(grant)

4,015,424 13.6% 29-Nov-11

7.7 Lake Victoria Water & Sanitation Program ADF grant 15,110,000 0.3% 17-Feb-10

7.8 Payment and Settlement Systems Integration

Project ADF grant 3,690,000 0% 5-Dec-12

TOTAL APPROVALS 165,605,424 13.7%

GRAND TOTAL APPROVALS 280,745,375 31.8%

Page 33: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

IV

Appendix III: Similar Projects Financed by the Bank and Other Development Partners

Country/Agency Sector Project

Development

Partners finance

(millions)

Completion

Date

World Bank Transmission Urgent Energy Development

Project (UERP) PO90 194 USD 25 2010

BADEA + Saudi

Fund Electricity access

Increase electricity access in

three areas in Rwanda USD 24.388

2012

Rwanda

Government

Transmission and

Electricity access

Electrification of six districts

in Eastern Province USD 68.6 2013

European Union Electricity access

Increase Rural Energy

Access in Rwanda

through Public

Electrification Project for

the Rural Population through

Renewable Energy

(EPRER)

Euro 18 2013

OFID Electricity access

Electricity Access Scale-Up

Project Loan Agreement

N°1293P”

USD 10 2013

World Bank IDA Electricity access

Electricity Access Scale-Up

and Sector-Wide Approach

(EASSDP), CR N° 4651-

RW

USD 70 2016

JICA Transmission and

Electricity access

Project for improvement of

sub stations and Kigali

distribution lines

USD 25 2014

Government of

the Netherlands

Generation and

electricity access

Rwanda Electricity Sector

Programme—Investment

Prospectus

USD 39 2014

AFD Electricity access Convention AFD No. CRW

3000 01 Euro 4.6 2014

OFID Transmission Additional funds for

EASSDP USD 12 2015

World Bank IDA Electricity access Additional funds for

EASSDP USD 60 2016

Belgian Technical

Cooperation

Generation and

electricity access

Private Partnerships—

IREARPPP Euro 17.5 2016

CTB Generation Rukarara II HPP Euro 5.741 2013

EX-IM Bank Generation Nyabarongo hydropower

project USD 80 2014

Belgian Technical

Cooperation Generation

Geothermal resource

development Euro 27 2017

BADEA / OFID Generation

Rehabilitation of three

hydroelectric power plants

(Mukungwa-Gihira-Gisenyi)

Euro 3 2014

AfDB Transmission NELSAP Rwanda-Uganda

Interconnection

UA 30.47

2014

KfW Transmission

NELSAP Rwanda-Burundi

Interconnection and

NELSAP Rwanda-DRC

Interconnection

Euro 36.25 2015

Page 34: Rwanda - Scaling Up Energy Access Project - Appraisal Report · distribution and installation of “ready-boards,” which come with two sockets and one lamp holder, targeting the

Appendix IV: Map of Project Area

V