Transcript of RWA, 15/6/2007 1 R. Assmann, AB LHC MAC June 15 th, 2007 Collimation System Update.
RWA, 15/6/2007 1
R. Assmann, ABR. Assmann, AB
LHC MACLHC MAC
June 15June 15thth, 2007, 2007
Collimation System UpdateCollimation System Update
RWA, 15/6/2007 2
The LHC Collimation System
• System is powerful but complex:
– 160 locations160 locations in the ring.
– 28 locations28 locations in the transfer line.
– 8 types of collimators8 types of collimators plus various types of masks and absorbers.
– A path is defined from initial to nominal and ultimate intensities (upgradesupgrades).
– Different interfacesDifferent interfaces depending on neighboring equipment and on level of induced radioactivity.
Phase # elements
Initial 9494
Upgrade 1 4444 (all prepared)
Upgrade 2 22
RWA, 15/6/2007 3
System Overview
MomentumCleaning
BetatronCleaning
“Phase 1”
“Final” system: Layount is 100% frozen!
RWA, 15/6/2007 4
Functional Description
• Two-stage cleaning (robust CFC primary and secondary collimators).
• Catching the cleaning-induced showers (Cu/W collimators).
• Protecting the warm magnets against heat and radiation (passive absorbers).
• Local cleaning and protection at triplets (Cu/W collimators).
• Catching the p-p induced showers (Cu collimators).
• Intercepting mis-injected beam (TCDI, TDI, TCLI).
• Intercepting dumped beam (TCDQ, TCS.TCDQ).
• Scraping and halo diagnostics (primary collimators and thin scrapers).
RWA, 15/6/2007 5
The LHC “TCSG” Collimator
360 MJ proton beam360 MJ proton beam
1.2 m1.2 m
3 mm beam passage with RF contacts for guiding image currents
Designed for maximum robustness:
Advanced CC jaws with water cooling!Advanced CC jaws with water cooling!
Other types: Mostly with different jaw Mostly with different jaw materials. Some very different with 2 materials. Some very different with 2 beams!beams!
For design see TS seminar A. Bertarelli.
RWA, 15/6/2007 6
Hardware Procurement...
Major contracts:Major contracts:
Collimators (FR)Collimators (FR)
Motors and sensors (D)Motors and sensors (D)
Position sensors (FR/China)Position sensors (FR/China)
CFC (J)CFC (J)
Supports (Bulgaria)Supports (Bulgaria)
Vacuum pumping ports (Italy)Vacuum pumping ports (Italy)
Material/screws (Switzerland)Material/screws (Switzerland)
Glidcop material (US)Glidcop material (US)
PXI low level controls (H/US)PXI low level controls (H/US)
Motor drivers + supplies (Italy)
RWA, 15/6/2007 7
Status of Collimator Procurement
• The 118 collimators and absorbers for the initial phase must be procured:
• Series production ongoing for the initial phase:
– Industry: 108 in total (including 6 upgrade collimators)
80 ring collimators (+12 spares) and 14 transfer line collimators (+ 2 spares).
– CERN: 32 in total (including 8 collimators taken over from
CERCA)
18 ring collimators/absorbers (+ 4 spares) and 10 transfer line masks
Phase # elements
Initial 94 (ring) + 24 (TL)94 (ring) + 24 (TL)
Upgrade 1 4444 (all prepared)
Upgrade 2 22
(including 2 TCDD, 2 TCLIM, 8 TCAP)
(including 4 TCLP, 8 TCHS, 2 TCLA)
RWA, 15/6/2007 8
Industrial Production
0
2
4
6
8
10
12
De
liv
ere
d C
oll
ima
tors
Time
Planning
Delivered (TL)
Delivered bad (ring)
Delivered good (ring)
Production has just reached its peak rate of 12 collimators per month!
The production crisis during the second half of 2006 has been overcome!
RWA, 15/6/2007 9
Industrial Production (Integrated)
0
20
40
60
80
100
120
Date
# co
llim
ato
rs
We have received 1/3 of the collimators1/3 of the collimators from industry.
October 2007October 2007: All collimators for installation can be available, if no other crisis!
There was a production crisis from July to December 2006!
spares
Crisis
RWA, 15/6/2007 10
Problem Collection I
Brazing
Ni-Cu coating RF fingersVacuum feedthroughs
Coating
TS/MME analysis of problems
RWA, 15/6/2007 11
Production Collection 2TCS010 after bake-out (8 Sep 2006)
0.00E+00
1.00E-08
2.00E-08
3.00E-08
4.00E-08
5.00E-08
6.00E-08
7.00E-08
8.00E-08
9.00E-08
1.00E-07
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105
Mass
Pa
rtia
l Pre
ss
ure
[u
nc
alib
rate
d]
Oil Pollution
Welding
RF fingers
AT/VAC and TS/MME analysis of problems
RWA, 15/6/2007 12
Overcoming the Crisis...
• Production of conform collimators stopped in August 2006 due to severe quality problems in the production company. Main problems:
– Machining of UHV parts with oil-based cooling fluids.
– Insufficient UHV cleaning.
– Non-conform surface coating and brazing problems.
– Lack of quality control from contractor.
• Problems appeared when production rate was supposed to go up.
• Status August 2006: 14 collimators produced, 8 only acceptable.
• Strong TS involvement starting in September 2006 to correct situation together with AB and AT:
– Review, documentation and transfer of all detailed CERN procedures, as used for construction of prototype collimators in TS.
– Some critical production steps done at CERN while contractor corrects problems.
– TS/MME leading production control on site of contractor and sub-contractors.
– AT/VAC program to establish UHV: 15 tests of collimators components made between 6/11/06 and 6/12/06 + assistance in Romans to CERCA.
• Quite some effort required: 1600 TS staff hours from Oct-Dec 2006 plus important AB/AT resources. TS/MME and AT/VAC presence at CERCA during Christmas holidays.
RWA, 15/6/2007 13
Achievements
• All technical issues solved and production was restarted.
• Collimator quality acceptable but not perfect for first 2007 collimators (e.g. only partial tank cooling for some collimators) handled without impact on collimation performance (e.g. locating first collimators at low power locations or repairing at CERN).
• Peak production rate of 12 collimators in 1 month was achieved in May.
• Collimator production is in industrial mode.
• The full minimal system is at CERN (basic two-stage betatron and momentum cleaning) ready for originally foreseen 450 GeV run and up to ~15 nominal bunches at 7 TeV.
• Production now focuses on W collimators. In September 2007:
– cleaning performance reach at ~20% of nominal intensity.
– triplet protection collimators available.
RWA, 15/6/2007 14
Production Process
TanksJaw supports
BellowsCleaning
Parts
Pressure tests
Company has built a stock of pre-assembled parts. Procedures in place.
RWA, 15/6/2007 15
Production Process
Jaw assembly
Assembled collimator Mechanical table
Brazing controlAlignment & calibration
Collimators are handled in parallel at their different stages higher rate!
RWA, 15/6/2007 18
Completion Other Components I
• Supports and quick plug-ins:
– All phase 1 standard supports installed. Allmost all completed with plug-in: final work in LSS7R ongoing (waiting for completion of warm magnet tests).
– Alignment campaign planned (next week LSS1 then LSS7).
– Phase 2 base supports are at CERN but installation to be completed.
– Cabling electrical plug-in: 100 out of 112 are ready.
– Cooling water: All tappings with valves installed. Special flexibles are at CERN, standard flexibles from TS/CV. Connection, adjustment, final pressure test to be done.
• Radiation hard stepping motors and resolvers (50 MGy):
– All ~550 at CERN. Rejection for ~50, due to insufficient insulation of resolvers.
• Position sensors LVDT‘s:
– 750/750 produced and tested. 5 rejected. Ready for mounting.
• Microswitches:
– 1500/1500 produced and tested.
RWA, 15/6/2007 19
Completion Other Components II
• Cabling:
– Long cables all ordered in standard campaign. All installed except LSS2.
– Final ~5 m cable connections (radiation hard) all ordered by TS/EL. Installed in LSS3 and few other positions (LSS8 and TI8).
– Cables of interconnection among racks (interlocks, triggers, timing, ...) all ordered (TS/EL) but not installed yet.
• Racks:
– Racks all installed in the 7 IR‘s with collimators.
• Stepping motor drivers:
– 10/510 ready. 100 more will arrive next Tuesday. Not critical (all there in September)
– Delay due to EM emission and long cable required modifications. Now fixed.
• PXI low level controls:
– All delivered by NI.
Outside of m
ain tunnel
RWA, 15/6/2007 20
Other Procurement
First series production of stepping motors with 50 MGy radiation-hardness. High
numbers now available for mounting on collimators.
Design based on ITER R&D and early prototyping. Solution was adapted to CERN
needs and transformed into industrial process (9 month effort AB/ATB + industry).
RWA, 15/6/2007 21
Cooling Water Issues
• Manifolds for water connection at collimator support were found to have bad welding: No issue for the early years but we must replace them to avoid problems in some years. Try to do it before 2008 startup but not required..
• Cooling water in the collimator must be regulated with an accuracy of about 10%:
– Water velocity must be high enough to handle heat loads from the beam (up to 7kW – is a function of beam intensity and loss rates).
– Water velocity must be lower than 3 m/s to avoid erosion/corrosion.
– Water loads will change after any change in collimator complement (upgrade).
• Prototype tests for radiation-hard regulation valves are ongoing. Procurement in August - October and installation in October/November (no impact on vacuum integrity).
• No showstopper (can always implement a temporary solution) but we are watching this carefully…
RWA, 15/6/2007 22
Final Assembly at CERN
Final assembly restarted with full speed end of April.Final assembly restarted with full speed end of April. Major effort AB/ATB group.
Collimators can be installed after leaving the final assembly hall in B.252!
So far 10 collimators installed10 collimators installed!
0
20
40
60
80
100
120
Date
# c
oll
ima
tors
spares
Final assembly completed!
Industrial production
RWA, 15/6/2007 25
Support & Plug-In Installation
LSS5
Almost all ready in the 7 IR‘s with collimators.
Survey and alignment done with quick-plugin supports and without collimator (precise reference from plug-in and alignment tool).
RWA, 15/6/2007 28
Ring Collimators Installed in IR6
IR6 collimators are part of the dump protection system of the LHC.
Special installationSpecial installation due to space constraints with the dump line.
These 2 like some others with only partial tank coolingpartial tank cooling (welding problem on tank: predicted to be no problem as low heat load expected).
RWA, 15/6/2007 29
Collimator Transport Vehicle
Start of training for collimator installation with upgraded vehicle (K. Kershaw et al).
RWA, 15/6/2007 30
Collimator Installation
• All required installation tools are operational.
• Collimators are being produced at higher rate now. May was a very important milestone. Most difficult collimator design (8 two-beam collimators) likely transferred to CERN production.
• A detailed production planning up to the end will be provided by the company by mid-June (difficult). Somehow mixed with contractual negotiations.
• Planning for not-completed in-house production is being established with TS (depends on decisions with CERCA).
• Optimized collimator installation planning is being worked out with the LHC installation planning group:
– Install the collimators we receive up to January 2008 to have complete collimation system for 2008 run. Compatibility with production progress.
– Minimize interference with other work: group by vacuum sectors, synchronize with vacuum workflow, synchronize with alignment, HWC constraints, ….
RWA, 15/6/2007 31
Production Priorities Draft ICERCA -> Bld 252TCP TCS G/M TCLIB TCT H/VA TCLA TCL TCDI TCTVB TCLIA
10 82 2 12 20 4 24 4 2PHASE I (1st run 7TeV) 8 32 2 12 18 4 24 4 2Upgrade 1 30 2Upgrade 2 2 20
InstalledTCSG.4L6.B2 TCTH.4L8.B1 ?TCSG.4R6.B1 TCTH.4R8.B2
AVAILABILITY FOR THE TRANSPORTTCSG.A5L3.B2
TCSG.4L3.B2
TCP.B6R7.B2 TCSG.4R3.B1
TCP.C6R7.B2 TCSG.A5R3.B1
TCSG.A4L7.B1
TCSG.A4R7.B1
TCSG.A4L7.B2
TCP.D6R7.B2
TCSG.A4R7.B2
TCP.D6L7.B1
TCSG.A6R7.B2
TCSG.6L7.B2
TCSG.A5R7.B2
TCP.C6L7.B1
TCSG.5R3.B2
TCSG.B5R3.B1
TCSG.5L3.B1
TCSG.6R7.B1
TCP.B6L7.B1 TCSG.A6L7.B1
TCSG.A5L7.B1
TCP.6R3.B2
TCP.6L3.B1
TCTVA.4R5.B2
TCTH.4R5.B2
TCTVA.4L5.B1
TCTH.4L5.B1TCDI.TCDI.
1st target --> mid-July : the first 30 collimators must be ready to be installed
under approval
29
CERCA -> TS-MME
30
28
27
26
25
24
A4L3
A4R3
B5L3
B5R3
A5R3
A5L7
A6L7
B5L7
B5R7
A5R7
A6R7
Test of the Warm
Magnets Point7
IP7
B4L5
B4R5
sectors with chamber supports which could be closed :
A4L1A4L2A7L3B4L5A7L7A4L8A4R1A4R2A7R3B4R5A4L7A4R8A5R1A6R2________A4R7____
IN WORK...JUN
EJU
LY
J. Coupard et al
RWA, 15/6/2007 32
Production Priorities Draft IICERCA -> Bld 252TCP TCS G/M TCLIB TCT H/VA TCLA TCL TCDI
TCTVA.4R5.B2
TCTH.4R5.B2
TCTVA.4L5.B1
TCTH.4L5.B1TCDI.TCDI.TCDI.TCDI.TCDI.TCDI.
TCLA.A7L7.B2
TCLA.A7R7.B1
TCLA.D6L7.B2
TCLA.C6L7.B2
TCLA.B6L7.B2
TCLA.A6L7.B2
TCLA.A6R7.B1
TCLA.B6R7.B1
TCLA.C6R7.B1
TCLA.D6R7.B1
TCSG.D4L7.B1
TCSG.D4R7.B2
TCSG.B4L7.B1
TCSG.B4R7.B2
TCSG.E5L7.B2
TCSG.D5L7.B2
TCSG.B5L7.B1
TCSG.B5L7.B2
TCSG.E5R7.B1
TCSG.D5R7.B1
32
33
34
35
1st target --> mid-July : the first 30 collimators must be ready to be installed
2nd target --> mid-September : 6 TCDI and 14 TCT/TCLA must be ready to be installed
36
37
38
29
30
31
A7L7
A7R7
A4L7
A4R7
IP7
A5L7
B4L5
B4R5 IN WORK...
JULY
AUG
UST
SEPT
EMBE
R
J. Coupard et al
RWA, 15/6/2007 33
Draft Sequence: Optimized Installation-Readiness
TI2/LSS8(May - Jul 06)
LSS6(Feb 07)
LSS3/7(Jan - Jun 07)
LSS3/7(Aug - Oct 07)
LSS5(Jul 07)
TI8(Jul - Aug 07)
LSS2/8(Oct 07)
LSS1(Oct - Nov 07)
LSS2(Nov 07)
LSS5(Nov 07)
LSS1(Nov 07)
LSS2(Nov 07)
LSS8(Nov - Dec 07)
LSS3/7(Jan 08)
January 2008: Goal is full phase 1 completion. Ready for high activation, high luminosity, non-standard *.
Present status:The minimal system is there.
Ready for high intensities but not high activation.Planning quite uncertain: detailed planning from CERCA needed, including material status.
Ongoing work. Being optimized further… Sequence of vacuum sectors exists.
RWA, 15/6/2007 34
Conclusion I
• The collimator production crisis has been overcome. Production reached a peak value of 12
per month. Must work hard to keep it there…
• Procurement of extensive auxiliary equipment (sensors, motors, local infrastructure, …) is in
good shape.
• Increased pressure on CERN work: Final assembly at CERN has restarted and is going full
speed for 3 collimators per week (~8 persons full time).
• Full minimal system is at CERN and is being prepared for installation (ready for up to 15
nominal bunches at 7 TeV). 8 collimators stored for installation (IR3 and IR7).
• All quick-plugin supports available/installed (final LSS7R ongoing).
• Collimator alignment campaign will start next week in LSS1 and then move to LSS7.
• High rate collimator installation is being prepared (installation training). 10 already installed.
IR7 installation starts in July…
RWA, 15/6/2007 35
Conclusion II
• Many tests without and with beam show that LHC collimators are robust, reliable (20,000
cycles) and precisely controllable. The 118 initial LHC collimators/absorbers should advance
the state-of-the-art by ~2 orders of magnitude.
• Goals: Have almost the full phase 1 system ready for the 2008 run.
Full passive protection, high cleaning efficiency (> 99.99%) will then be there.
Last collimators for installation ready in January 2008.
• These goals are achievable if we can keep the present pace. We still have a way to go and
there are always risks… We will work hard to make these goals.
• Requires some effort to integrate late collimator installation with other activities.
• Optimized installation planning is being worked out with the LHC installation planning group.
Detailed schedules still in flux (negotiations affect schedule and in-house work).
• Ongoing work in other areas not discussed here: hardware commissioning, controls system,
preparation for beam commissioning and operation, accelerator physics studies, radiation
tests, cascade modeling, preparations for upgrades (performance, remote handling, …).