Run 10 Status

16
Run 10 Status http://www.cadops.bnl.gov/AP/RHIC2 010/ http://www.cadops.bnl.gov/AP/RHIC2 010/

description

Run 10 Status. http://www.cadops.bnl.gov/AP/RHIC2010/ http://www.cadops.bnl.gov/AP/RHIC2010/. Status. Running with 111x111, >1.3e9 ions/bunch With rebucketing, 4.8 MV in Yellow, 4.8 MV Blue ZDC rates >40kHz peak Stochastic Cooling status Vacuum spiked at Blue Longitudinal, BL now off - PowerPoint PPT Presentation

Transcript of Run 10 Status

Page 1: Run 10 Status

Run 10 Status

http://www.cadops.bnl.gov/AP/RHIC2010/

http://www.cadops.bnl.gov/AP/RHIC2010/

Page 2: Run 10 Status

Status• Running with 111x111, >1.3e9 ions/bunch

– With rebucketing, 4.8 MV in Yellow, 4.8 MV Blue– ZDC rates >40kHz peak

• Stochastic Cooling status– Vacuum spiked at Blue Longitudinal , BL now

off– Transverse cooling alternating, Blue / Yellow

• Rebucketing & ZDC rates– Latest store, try 4.6 MV (600 kV on “colored”

cavities, 700 kV on common cavities.)

Page 3: Run 10 Status
Page 4: Run 10 Status
Page 5: Run 10 Status
Page 6: Run 10 Status
Page 7: Run 10 Status
Page 8: Run 10 Status
Page 9: Run 10 Status
Page 10: Run 10 Status

Run 1062.4 GeV Setup

Page 11: Run 10 Status

31.2 GeV/N

19.5 GeV/N

Page 12: Run 10 Status

Preparations• 2 days for setup (hopefully less)• Shift schedule is posted• storage rf system can be used above 19.5 GeV/nucleon

– We will use it for the 31.2 GeV run– (We may be able to use it for the 19.5 GeV run)– Expect to work on rebucketing the evening on 1st day

• Beta* ~ 2.5m, all crossing angles are 0.• Basic configuration is same at injection through transition• Develop checklists for energy change

Page 13: Run 10 Status
Page 14: Run 10 Status
Page 15: Run 10 Status

Basic Plan• Injection doesn’t change

– RF setup at injection (synchro) remains the same

• Ramp changes slightly even before transition– Keep gamma jumps as they are (time changes slightly)– Beta-squeeze after transition changes– Yellow dipole feedback – timing will change– Brho loop timing will change

• Use tune/coupling and orbit feedback for ramp – 3 ramps• Rebucketing setup = 1 shift (new frequency, new phases)• Collimation and orbit setup

Page 16: Run 10 Status

Schedule:• Thurs. March 18

– 8 am: end 200 GeV run– Switch to new ramp (modify scripts/sequences)

• Check timing – brho loop, loss mons., yellow dipole feedback– Run 6x6 bunch ramp with tune/coupling and orbit

feedback including data-stores for p.s. group– Do second 6x6 bunch ramp with feedback w/ data-stores– Run feed-forward ramp and tune ramp efficiencies– 4 pm: setup rebucketing and collisions– Once rebucketing is working, work on store setup

(scale IR corrections and check)• Fri. March 19

– continue collimation setup, store orbits– Start raising number of bunches– Physics by evening