Roberto Saban & Mirko Pojer
description
Transcript of Roberto Saban & Mirko Pojer
Training the dipoles A.Werveij
What did we learn without beam in 2008 ?
Superconducting electrical circuits K-H.Meß
The Sector 34 Incident Ph.Lebrun
Calorimetric and electrical measurements and related software
N.Catalan-Lasheras
LHC Cryogenics: What did we learn from cool-down to first beams
S.Claudet
What else did we learn? M.Pojer
Roberto Saban & Mirko Pojer
2LHC Performance Workshop Chamonix - What did we learn without beam in 2008?
Training the dipoles
R.Saban Feb 24th , 2009
8500
9000
9500
10000
10500
11000
11500
12000
12500
13000
1 10 100 1000
Quench number
Qu
ench
cu
rren
t [A
]
5.5 TeV
7 TeV
6.5 TeV
6 TeV
S45
S56 in SM-18
S56
S78
190
A.V
erw
eij
in sector 56
3LHC Performance Workshop Chamonix - What did we learn without beam in 2008?
Training the dipoles
R.Saban Feb 24th , 2009
A.V
erw
eij
7000
8000
9000
10000
11000
12000
13000
0 20 40 60 80 100 120 140
Magnet number (ordered by 1st quench in SM18)
Cu
rren
t [A
]
ALS: 1st training quench SM18
ANS: 1st training quench SM18
NOE: 1st training quench SM18
ANS: Quenches sector 56
NOE: Quenches sector 56
7 TeV
6 TeV
in sector 56
4LHC Performance Workshop Chamonix - What did we learn without beam in 2008?
Training the dipoles
R.Saban Feb 24th , 2009
A.V
erw
eij
in sector 56
Sector
Number of magnets Number of quenches to 7 TeV
ALS ANS NOE@ 6 TeV(±2)
@ 6.5 TeV
(±30%)Est. 1 Est. 2 Est. 3 Est. 4
1-2 49 96 9 0 4 22 41 40 49
2-3 56 60 38 1 8 23 97 92 130
3-4 56 65 33 1 8 21 87 83 116
4-5 46 46 62 2 12 22 145 136 198
5-6 28 42 84 1 15 21 190 178 262
6-7 57 36 61 2 12 20 142 133 194
7-8 54 40 60 2 12 14 140 132 192
8-1 64 24 66 2 13 19 151 142 208
Total 11 84 162 993 936 1349
Est. 1: Based on 115 MB’s that have been submitted to a thermal cycle in SM-18 (2008 before HWC, P. Xydi and A. Siemko)
Est. 2: Extrapolation from sector 5-6 data + estimate 1 for ALS & ANS
Est. 3: 2 quenches per NOE magnet + estimate 1 for ALS & ANS
Est. 4: 3 quenches per NOE magnet + estimate 1 for ALS & ANS
993 / 8 = 124124 / 3 = 41
5LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
K-H
.Meß
Superconducting electrical circuits
Harmless The third current lead shared by two circuits (Kirchoff’s Law) Short inside the dump resistor on the QF of Sector 45 Short to ground on the dump resistor on the QD of Sector 56 Missing resistor on one of the poles of an undulator which gave a
very exotic transfer function Leveling of the DFB to properly wet the superconducting cable
Potential inconvenience to operation Distribution of the conductors on cables sharing the same DFB but
on different circuits – symptom: apparent detraining The reference magnet puzzle – magnetization cycle
Potentially dangerous Symmetric quenches Transient spike when the dump switch opens due to the difference in
Eddy currents in the two apertures Quench back in corrector circuits inducing coupling on other circuits
… up to quenching the main magnets Pending: splice and voltage tap non-conformities
Unresolved MCBX and MCBY mystery: unexplainable transfer functions The hunch on the MCBYs Fast quench propagation observed on only the dipole circuits
Surprises
6LHC Performance Workshop Chamonix - What did we learn without beam in 2008?
Mandate of the Task Force Establish the sequence of facts, based on
experimental measurements before incident, observations after incident and timing
Analyse and explain the development of events, in relation with design assumptions, manufacturing & test data and risk analyses performed
Recommend preventive and corrective actions for Sector 3-4 and others
R.Saban Feb 24th , 2009
Ph.L
ebru
nThe Sector 34 Incident
0
10
20
30
40
50
60
70
80
1.85
1.87
1.89
1.91
1.93
1.95
1.97
1.99
18:00 19:00 20:00 21:00 22:00
Valv
e op
enin
g [%
], cu
rren
t [kA
], CC
flow
[g/s
]
Cold
-mas
s tem
pera
tue
[K]
LBALA_24R3_TT821.POSST
LBALA_25R3_TT821.POSST
LBALA_26R3_TT821.POSST
LBALA_27R3_TT821.POSST
LBALB_24R3_TT821.POSST
LBALB_26R3_TT821.POSST
LBBLA_24R3_TT821.POSST
LBBLA_25R3_TT821.POSST
LBBLA_26R3_TT821.POSST
LBBLA_27R3_TT821.POSST
LBBLD_25R3_TT821.POSST
LBBLD_27R3_TT821.POSST
LQASB_23R3_TT821.POSST
LQOAA_25R3_TT821.POSST
LQOBA_24R3_TT821.POSST
LQOBA_26R3_TT821.POSST
QRLAA_25R3_CV910.POSST
QRLAB_23R3_CV910.POSST
QURCA_4_FT201.POSST
RPTE.UA43.RB.A34:I_MEAS
-400
-200
0
200
400
600
800
1000
8400 8450 8500 8550 8600 8650 8700 8750
Current [A]
Vo
lta
ge
[mV
]
0
100
200
300
400
500
600
700
Te
mp
[K
]
V_meas (Timber)
V_meas (QPS data)
Voltage simulated [mV]
T_max simulated [K]
Arjan Verweij, TE-MPE
Temperature drift during the 7 kA current flat top (15 Sep 2008)
Measured versus simulated incident with 220 n joint and bad contact with U-profile and wedge
No electrical contact between wedge and U-profile with the bus on at least one side of the joint
No bonding at joint with the U-profile and the wedge
7LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
Ph.L
ebru
nThe Sector 34 Incident
The current decay from 8700 A
Energy MJ %
Stored in the magnets 595.0 100
Dissipated in UJ33 71.0 12
Dissipated in UA43 104.8 18
Dissipated in cold mass 144.4 24
Dissipated in electrical arcs 274.8 46
8LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
Ph.L
ebru
nThe Sector 34 Incident
PTQVQV QV QVQV SVSV
Cold-massVacuum vesselLine ECold support postWarm JackCompensator/BellowsVacuum barrier
Q D D QD D D QD D D QD D D QD
0
2000
4000
6000
8000
10000
12000
Time
Curr
ent (
A)
0
5
10
15
20
25
P H
e ve
ssel
(bar
), P
beam
(mba
r), P
insu
latio
n (b
ar)
Ins Vac A19R3
Ins Vac A23R3
Ins Vac A27R3
I DCCT
I dump 3
I dump 4
P CM Q19-21.R3
P CM Q23-25.R3
P CM Q27-29.R3
Vac beam 23R3.R
Vac beam 23R3.B
Vac beam 31R3.R
Vac beam 31R3.B
9LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
Ph.L
ebru
nThe Sector 34 Incident
• Calorimetric measurements• Electrical measurements on
«suspect» cells/subsectors powered at limited current
• During further power tests, track temperature evolution in normalized conditions
• Modify quench detection system to include interconnects and bus bar splices
• Consider option to measure currents in 13 kA circuits at both ends of sector and detect differentials
• Review possible improvement of mechanical clamping of interconnects and gradually implement whenever possible
Prevention of initial faultRecommendations
Mitigation of consequences• Increase number/size of relief
devices on cryostat vacuum vessels
• Review number, size & position of pressure relief devices on beam vacuum system
• Review closure logic of beam vacuum sector valves
• Consider possibility of triggered opening of quench relief valves below set pressure
• Consider general firing of quench heaters
• Reinforce external anchoring at locations of vacuum barriers
• Reexamine personnel underground access rules
• Review location of AUG in tunnel and protection from blast
• Review recorded signals, recording frequency and time stamping coherence among different systems
10LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
N.C
ata
lan-L
ash
era
sCalorimetric and electrical measurements
Sector 12
7 kA 7 kA 7 kA 9.3 kA+40 mK
-10 mK
Rela
tive t
em
p
1 or 2 hour flat tops
7 kA 7 kA 8.5 kA 7 kA
Rela
tive t
em
p
Sector 23 Sector 34 Sector 45
Sector 56 Sector 67 Sector 78 Sector 81
+40 mK
-10 mK
Rela
tive t
em
p
• All the current plateaux were scrutinized for suspect temperature increase
• Unstable conditions and dynamic temperature control prevent accurate calculations.
11LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
N.C
ata
lan-L
ash
era
sCalorimetric and electrical measurements
0
0.2
0.4
0.6
0.8
1
1.2
1.83
1.84
1.85
1.86
1.87
1.88
1.89
0 1 2 3 4
I / I p
late
au [-
]
Tem
pera
ture
[K]
Time [hour]
TemperatureCurrent
DU
(DT)
Assessment of the baseline slope (valve opening
mismatch)the temperature increase during
powering plateauthe internal energy variation (J/kg)the deposited energy assuming a
mass of 26 l/m of He
Before heating With heating
ΔU [J/kg] -1.1 78
M [kg] 823
ΔU [kJ] -0.92 64.2
t [s] 2880 6600
W [W] -0.3 9.7
ΔW [W] 10
31R1 31R6
15R1 23R331R7
0
5
10
15
20
25
-50 -40 -30 -20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
# o
f su
b-se
cto
rs [-]
Sub-sector resistance variation w/r to baseline [nW]
Dipole (5 sectors) Quadrupole (4 sectors)
NNXN: Confirmed by electrical measurements
~ 2 W @ 7 kA
The new powering procedures will demand mandatory calorimetric and electrical tests in ALL sectors at the beginning of the next LHC powering campaign
12LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
N.C
ata
lan-L
ash
era
sCalorimetric and electrical measurements
0.7mV/7kA=100nOhm0.7mV*7kA=4.9W
Snapshot on 03.09.08 : 0.85mV*8.4kA=7.1W
Calorimetric measurements spotted a suspect region in Sector 12
0 2000 4000 6000 8000 10000 12000 14000-0.20
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40D1_L-Ua
Current (A)
Vo
lta
ge
(m
V)
Error Bars:±2σ/√n
1.6 nOhms
105 nOhms
an inter-pole splice resistance of 105 nOhm in magnet 2334 (B16R1)
13LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
S.C
laudetCryogenics: from cool-down to first beams
≈15K/d x 13 d
≈8 K/d x 8 d
≈12 K/d x 4 d
“25 days for 20K”
+ 3 days for Filling
+ 2 days for 1.9K
30 days
(4 to 5 wks)
14LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
S.C
laudetCryogenics: from cool-down to first beams
Distribution Line Distribution Line
Magnet Cryostats Magnet Cryostats
Cold Compressorbox
Warm CompressorStation
Shaft
Su
rface
Cavern
Tun
nel
LHC Sector (3.3 km) LHC Sector (3.3 km)
New 4.5 K refrigerator 1.8 K Refrigeration Unit
Warm CompressorStation
Cold Box
Interconnection BoxCold Compressor
box
Warm CompressorStation
1.8 K Refrigeration Unit Ex-LEP 4.5 K Refrigerator
Upper Cold Box
Warm CompressorStation
Lower Cold Box
• Running two sectors with one cryoplant was tested during powering
• Not valid for large transients, but an interesting alternative for low beam loads. It is a validated fall-back scenario if serious problems with a refrigerator
15LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
S.C
laudetCryogenics: from cool-down to first beams
Non conformities were detected, workarounds found during the run and consolidations actions ongoing level gauges on stand alone magnets, DFBLC heat load, valves on current leads, heat loads on the triplet, etc.
Stability was achieved stable services, global refrigeration mastered, 15mbar established, DFB, current lead and beam screen cooling loops stabilised
Recovery from quenches or failures a lot of experience gained and results obtained
Towards more stable services electricity, cooling water controls, insulation vacuum
Getting ready for round the clock operation
16LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
M.P
oje
rWhat else did we learn?
The ProceduresThe Tools which implemented the procedures and assisted
the operators during the execution and the analysis
SequencerPost-Mortem browserPIC supervisionQPS supervisionPowering to Nominal (P2N)Databases… others were developed during the hc
efficiency, automation and no compromise
Some teething problems were identified and were corrected or are being corrected remote resets, communications problems, timing, coherence between time stamps, etc.
17LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
M.P
oje
rWhat else did we learn?
Hardware problems
600A-10V LHC type power converters QPS requires a smooth change in current, otherwise it trips
LHC 600A-10V: 0V-crossing distortionThe power converters generate some distortion when crossing through zero voltage with current in the load QPS trips
600 A-10 V Crowbar Issue Some PCs don’t have the crowbar and are not safe under certain conditions
Reduced dI/dt and d2I/dt2 which could limit operation and physics
Frequent clogging of water filters installed on cables and converters lines
flow reduction and stop of the converter
ECR to add crowbar on those circuits
A decision was taken to change all filters around the machine from the present 50 μ to 100 μ mesh
18LHC Performance Workshop Chamonix - What did we learn without beam in 2008?R.Saban Feb 24th , 2009
Conclusions
Many surprises: training & sector 34
During the commissioning the equipment owners and the operation crews gathered the experience which they expected to re-commission, run and debug the equipment
The incident in sector 34 requires modifications of the hardware, upgrade of protection systems and the development of additional test procedures
While during most of the commissioning campaign the observations matched what was expected; in a few cases however, they revealed non-conformities some of which remain to be understood, followed and corrected or coped with