Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00...

117
Road Construction Department AT A GLANCE 25.05.2018

Transcript of Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00...

Page 1: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Road Construction Department

AT A GLANCE

25.05.2018

Page 2: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Road Network under RCD (in Km)

Category Total

Length

Single

lane

Intermediate

Lane

2-Lane More

than 2

lane

National Highways4917.19 729.21 819.95 2045.57 1322.47

% 14.83 16.68 41.60 26.89

State Highways4005.56 757.13 570.23 2654.64 23.56

% 18.90 14.24 66.27 0.59

Major District

Roads

11145.28 5717.81 3718.47 1543.26 165.74

% 51.30 33.36 13.85 1.49Total 20068.03 7204.15 5108.65 6243.47 1511.77

Overall % 35.90 25.46 31.11 7.53

Page 3: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Sl. No. Name of SchemeOutlay

(Crores)

Expenditure

(Crores)

1 Training 0.40 0.3338

2 Machine and equipment 0.15 0.1158

3 Bridge 689.7375 681.3333

4 Major Roads 1289.000 1273.1236

5 Major Roads (SC Components) 912.5424 907.4132

6 RIDF (NABARD) Bridge 1236.7100 1231.0644

7 Mukhya Mantri Setu Nirman Yojana 10.0000 5.7825

8 Central Road Fund (Central Share) 197.0000 194.7925

9 Central Road Fund (Sate Share) 0.0001 0.0000

10 ADB Project 1013.3200 1013.3200

11 Indo-Nepal Boder Road 401.0000 396.1544

12 Special Assistance (BRG-Road) 0.0000 0.0000

13 LWE (Central Share) 10.0000 10.0000

14 LWE (State Share) 10.0000 10.0000

Total 5769.86 5723.4337

ACHIEVEMENT 2017-18

% Expenditure – 99.20%

Page 4: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Sl. No. Name of SchemeOutlay

(Crores)

1 Training 0.5000

2 Machine and equipment 0.2000

3 State Plan (Bridge) 375.0702

4 RIDF (NABARD) 1136.7100

5 State Plan (Major Roads) 1000.0000

6 Mukhya Mantri Setu Nirman Yojana 1.5000

7 Central Road Fund (Central Share) 430.8500

8 ADB (Externally Funded Scheme) 1500.00

9 Indo-Nepal Border Road 0.0001

10 Major Roads (SC Component) 944.7296

11 Central Road Fund (State Share) 0.0001

12 LWE (Central Share) 415.0000

13 LWE (State Share) 100.0000

Total 5904.5600

OUTLAY FOR 2018-19

Page 5: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

NATIONAL HIGHWAYS

Total length of NHs in Bihar : 4917.19 Kms.

a) Length of NHs with RCD : 2584.92 Kms.

b) Length of NHs with NHAI : 2332.27 Kms.

Page 6: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

National Highways

Page 7: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

STATUS Good Fair Bad Total

NHs with RCD

Length (Km) 1386.82 794.89 92.10 2273.81

% 61.00 34.96 4.04

41.53 missing link & 150 km

has not been

transferredto NH Wing

NHs with NHAI

Length (Km) 1292.47 799.51 321.05 2413.03

% 53.56 33.13 13.31Note:- NH wise status are included in subsequent slides....

National Highways

Page 8: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Condition of NHs under N. H. Wing RCDSL.No.

NH No. Name of NH Length(In KM)

Condition(In KM) Remarks

Good Fair Bad

1 2CDehri-Akbarpur-Jadunathpur-Jardag Road

92.00 26.00 14.00 52.0040 Km work in progressBad 52 km ProtectedForest and missing link.

2 19UP Bihar - Manjhi-Chapra-Hazipur-Patna

28.70 28.70 0.00 0.00Rehabilitation of MG Setuin progress

328B

New NH-727

Chapwa-Bettiah-Kushinagar

109.80 67.80 23.20 18.80Bad condition in ProtectedForest

5 30AFatuha-Chandi -Harnaut-Saksohra- Barh

71.00 31.00 40.00Work in progress underNHIIP

6 80Mokama -Lakhisarai-Bhagalpur-Kahalgaon-Mirzachouki

1.43 1.43 0.00 W/S work in progress

120.60 88.10 24.00 7.5 Work in progress

16.73 Work in progress

7 81Korha - Katihar-Pranpur-Lava

55.40 34.00 12.04 9.36 Work in progress

Page 9: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Condition of NHs under N. H. Wing RCDSL.No.

NH No. Name of NH Length(In KM)

Condition(In KM) Remarks

Good Fair Bad

8 82 Gaya – Hisua – Rajgir -Biharsharif

95.00 38.00 56.70 0.30 4-laning by BSRDC

9 98 Patna(Anishabad)-Bhusaula-Naubatpr-Bihram-Mahablipur-Arwal-Aurangabad-Hariharganj

154.30 151.80 2.50 0.00 Work in progress under NHIIP

10 99 Dobhi to Gosaidih 11.40 11.40 0.00 0.00 W/S in progress

11 101 Chapra- Baniyapur-Mohammadpur

65.00 65.00 0.00 0.00 W/S in progress

12 103 Hajipur-Jandaha-Mushrigharari

58.51 44.51 14.00 0.00 Work sanctioned in 14 km, and in tender process.

13 104New NH-

227

Chakia- Madhuban-Shivhar- Sitamarhi-Bithamore-Jainagar-Khutauna- Narahiya

219.95 66.63 153.32 0.00 Work in progress

14 105 Darbhanga-Aunsi-Jainagar 53.76 51.76 2.00 Work in progress

15 106 Birpur-Madhepura-Bihpur 136.00 34.03 90.17 3.00 W/S work in progress under NHIIP. 8.80 is missing link in koshiriver.

16 110 Biharsharif-Ekangarsarai-Jehanabad- Arwal

88.96 78.96 10.00 0.00 Work in progress

Page 10: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Condition of NHs under N. H. Wing RCDSL.No.

NH No. Name of NH Length(In KM)

Condition(In KM) Remarks

Good Fair Bad

17 122A

Vishwanathpur Chowk on NH-22 (Old NH No-77) connecting Koili and terminating at Nanpur on NH-527C in The State of Bihar.

31.82 0.00 31.82PR work

sanctioned.

18 131A

Ahmadabad - Manihari -Katihar - Purnea( Extenstion from Katihar to Ahmadabad vide Gazette Notification No- 677 (E) Dt. 05.03.2014 under Section-V)

82.12 77.00 3.12 0.002 km is missing

link.

19 133

The Highway Starting from its Junction with NH-33 (Old NH No-80) in the State of Bihar connecting Godda and terminating at Choupa More on NH-114A in the State of Jharkhand.

10.96 10.76 0.00 0.20W/S work in

progress

20 219 Bhabua-Chand-Dharauli 46.80 46.80 0.00 0.00

Page 11: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

SL.No.

NH No. Name of NH Length(In KM)

Condition(In KM) Remarks

Good Fair Bad

21 327A

The Highway starting from Supaul on NH-327 and terminating at Bhaptiahion NH-27 (Old NH No-57) in the State of Bihar.

25.01 25.01 0.00 0.00

22 327EGalgalia-Thakurganj - Bahadurganj -Araria - Raniganj - Bhargawan -Triveniganj - Pipra - Supaul - Bariyahi

227.11 117.06 110.05 0.00 Work in progress in km 0.00 to 39.00, 56.00 to

68.00, 75.00 to 98.00 & 194 to 227.11

23 333Bariyarpur - Kharagpur - Lakshimpur- Jamui - Chakai

141.05 54.24 85.87 0.94W/S work in progress in km

62 to 75 & 117 to 141.05

24 333ABarbigha-Khaira-Jhajha-Katoria-Banka-Dhaka more-Panjwara.

198.93 100.00 98.93 0.00 Work in progress in km 180 to 198.92 & tender invited

in km 62 to 89.18 & km 142 to 144.

25 527APakaharauni-Madhubani-Rampatti-Jhanjarpur.

28.00 27.26 0.74 0.00

26 120Gaya-Daudnagar-Nasariganj-Dumaraon

145.00 111.00 20.00 0.00In tender process in km 103 to 142 & 182 to 201 & work awarded in km 143 to 167. 14 .00 km is missing link.

27 227AUP boarder-Mairawan-Siwan-Chhapawa

Total length – 147 km – Fair – 138 km, Bad – 9 Km

Not transferred to NH Wing

28 727A UP boarder-Rampur Bujurg-MairawanTotal length 4.5 km, -

Not transferred to NH Wing

Total=2315.34 1386.82 794.89 92.10

Page 12: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Road Condition of NHs under NHAISL.

No.NH No. Name of Section

Length

(in Km)

Condition(In KM)Remarks

Good Fair Bad

1 2Naubatpur to UP Bihar Border

and Barachatti, Bihar Section205.760 21.000 167.760 17.00 6 lanning work in progress

2 19 Chhapra- Hajipur 64.000 8.600 55.400 4 lanning work in progress

3 30

Arrah - Patna 50.000 45.00 5.00 Work awarded

Patna - Bakhtiyarpur 51.700 49.000 2.7004 lanning work completed

except service lane & ROB

Mohania- Kochas-Arrah 117.00 117.00

4 28

Bathna Kutti (UP Border) to

Muzaffarpur160.430 90.00 70.43 4 lanning work completed

Muzaffarpur - Musrigharari -

Dalsinghsharai- Barauni106.560 106.56 0.00

5 28APiprakothi to Raxaul

(km 0 to 69.241)69.241 56.371 5.520 7.35 W/S work in progress

6 31

Debour - Rajouli - Nawada -

Biharsharif - Harnout -

Bakhtiarpur

106.900 7.000 37.90 62.00 PR work to be sanctioned

Bakhtiyarpur-Mokama-

Barauni(Zero Mile)-Begusarai-

Khagaria

115.400 54.00 61.40 0.00 Work in progress

Khagraia- Purnea 140.000 84.00 56.000 0.00

Purnea - Dalkola Kishanganj-

West Bengal Boarder41.000 36.00 3.00 2.00 4 lanning completed

7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00

Page 13: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Road Condition of NHs under NHAISL.

No.NH No. Name of Section

Length

(in Km)

Condition(In KM)Remarks

Good Fair Bad

8 77

Hazipur -

Ramdayalu(Muzaffarpur)

Section

48.200 46.30 1.90 0.00

4 lanning substantially

completed except

ROB, Muz. Bypass

Muzaffarpur - Sonbarsa Section 82.700 82.70 0.00 0.00

9 80 Hathidah - Munger 68.000 63.000 5.000 0.00

10 82Biharsharif- Barbigha- Sarmera -

Mokama bypass Junction55.000 0.000 42.500 12.50

Work awarded for 2

lane with paved

shoulder

11 83 Patna - Gaya-Dobhi Section125.000 12.000 113.00 0.00 Work awarded

12 84 Arrah - Buxar 74.000 12.00 62.00 0.00 Work awarded

13 85 Chapra - Gopalganj 94.000 90.00 3.50 0.50 Work in progress

14 102Chapra - Rawaghat-

Muzaffarpur75.000 75.00 0.00 0.00 Work in progress

15 57A Forbisganj-Jogbani 9.000 0.000 8.000 1.00 Work in progress

16 133B Sabhaganj- Manihari Approach 7.500 0.000 0.000 0.00 LA work in progress

17 333BMunger at NH-33 old NH-80

Khagaria NH-3118.359

Approach of Rail-cum

– Road Bridge

18 527C Manjhalui-Charut Section 64.200 64.20 DPR work in progress

19 107Maheshkhunt-Sonbarsa-Saharsa-

Madhepur-Murliganj-Purnea180.00 93.00 49.50 37.50

After handing over to

NHAI estimate for

repair has been sent

Total= 2438.95 1292.471 799.51 321.05

Page 14: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Approval status of In-principle declared NH

No. of Roads - 34 nos.

Length - 1943 Km

Status of DPR:

• Presentation for Alignment & Feasibility for 15 roads

under NH In-Principle has been done in MoRT&H.

• DPR preparation in all 34 roads (1943 Km) is under

process. It is likely to be submitted within a month.

• Out of 34 roads, 13 roads of length 577 Km are in PM

Package & 1 road of length 92 Km is in Bharatmala.

Page 15: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Item NHAI RCD Total

Total Cost (Rs. Cr.) 30200 24500 54700

Total No of Works 24 58 82

Awarded works No. 14 32 46

Amount (Cr.) 11234 8115 19349

In Bidding /

Sanction stage

No. 04 9 13

Amount (Cr.) 4526 5500 10026

Total amount of works Awarded /

In Bidding / in Sanction (Cr.)

15760 13615 29375

In DPR stage 6 No.

(15260cr)

17 No.

(10885cr)

23 No.

(26145cr)

Abstract of PM Package

Page 16: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM PackageProjects under RCD

Sl.

No.Project Name

Length

(in km)

TPC

(in crore)Present Status

EAP ZONE :-

1 Km 0.0 km

69.6 of NH-

30A (Fatua –

Harnaut – Barh

section)

71.8 683.83 Start Date - 06.08.2016 & completion date – 05.08.2019.

46 km/71 km DBM has been done.

Physical progress is 65%.

Issues:-

3G of 2.393 Ha submitted by RCD to Ministry.

Work before schedule time.

2 Km 40 to 79.4

of NH 104

(Sheohar –

Sitamarhi

section

39.4 178.85 Start Date – (Lot-I -04.05.2016 & Completion date – (Lot-I

– 03.05.2018

Physical progress 16% (WMM - 4.50 km, DBM 3.20km, /28

km),

Issue:- Termination of contract has been recommended to

MoRT&H.

Work front available :- 85%

Page 17: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM PackageSl.

No.Project Name

Length

(in km)

TPC

(in crore)Present Status

EAP ZONE :-

3 Up-gradation (km

79.4 to km 156.5)

of NH 104 of

Sitamarhi –

Jainagar section

77.1 369.77 Start Date 30.06.2016, & Completion date 29.12.2018

Physical progress of Lot II- 13% / 40% (DBM 9.50km /

76km)

Issues:- Slow work by Contractor

Compensation distribution in Madhubani district to be

expedited (Disbursement of Rs. 44.60 cr out of Rs. 72 cr)

Work front available = 87%

4 Up-gradation (km

156.5 to 219.945)

of NH 104 of

Jainagar –

Narahia section

63.45 553.3 Start Date – 12.05.2016) & Completion date –

12.05.2019).

Physical progress 18% / 40% (DBM 9.20km / 56.5km.)

Issues:-

Slow work by Contractor

Issue:- Compensation distribution in Madhubani district to

be expedited

Work front available:- 80%

Page 18: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM PackageSl.

No.Project Name

Length

(in km)

TPC

(in crore)Present Status

EAP ZONE :-

5 Up-gradation of (km

0-106) Birpur –

Bihpur section of

NH-106

106.29 780.77 Start Date – 03.10.2016 & completion date –

02.10.2019.

Progress is 11% / 20%. (DBM – 4.50 km/106km)

Issues :-

Revised 3G from Madhepura and Supaul district

submitted to MoRT&H.

6 Four Laning of (km

0.00 to Km 92.935)

on NH-82. (Gaya –

Hisua – Rajgir –

Nalanda – Biharshrif

section) JICA Loan

Assistance

(BSRDCL)

92.935 1408.9 Date of commencement is 25.10.2016 & Completion

date is 24.10.2019

Progress – 23%, (DBM 18km/93km)

Issues:-

Revised Cost Estimate submitted to MoRT&H.

Total= 450.975 3975.42

Page 19: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM PackageBRIDGE ZONE :-

Sl. No. Project NameLength

(in km)

TPC

(in crore)Present Status

7 Construction and rehabilitation of

MG Setu of NH-195.6 1755 Work in progress. Dismantling of 29 nos. of span

completed. Dismantling of 8 nos. Pier head

completed

8 ROB in Km 12 of NH-103

(Bidupur)1 750 Work awarded/Not Started. L/A under process, 3D

submitted.

9 ROB in Km 132 of NH-19

(Majhanpura)1 Work awarded/Not Started. 70% land available. For

rest 3D submitted.

10 ROB in Km 135 of NH-19

(Simaria)1 Work awarded / Not started.. L/A under process, 3D

approved.

11 ROB in Km 119 of NH-30 (Ara) 1 Work is in progress. Foundation work completed.

12 ROB in Km 11 of NH-

327E(Thakurganj1 Work is in progress. Foundation completed. Forest

clearance under process.

Work awarded / Not started. L/A is in process under

perpetual lease.13 ROB in Km 100 of NH-327E

(Araria)1

14 ROB in Km 31 of NH-81 (Mania,

Katihar)1 Work Started., Foundation under progress. L/A,

Forest clearance under process.

15 ROB in Km 48 of NH-81 (Pranpu) 1 Work is in progress. Foundation completed.

Work Started. Forest clearance under process.16 ROB in Km 46 of NH-131A

(Sarifganj)1

Work awarded/Not Started. Forest clearance under

process.17 ROB in Km 1.11-1.12 of NH-101

(Chapra)1

Total= 15.6 2505

Page 20: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM Package

PROJECT IN BIDDING / SANCTION STAGE

Sl.

No.Project Name

Length

(in km)

TPC

(in crore)Present Status

18 Bridge Over river Kosi at

Fulaut on NH-106

1700.00 Sanction Stage

19 4 Lane bridge over river

Ganga parallel to existing

MG Setu Bridge at Patna

on NH-19

3300.00 Sanction / DPR Stage

20 ROB in Km 91 of NH-

28B(Bagha)

62.48 Tender received. Technical Bid under

evaluation.

21 ROB in Km 94 of NH-

28B (Bagha)

68.49 Tender received. Technical Bid under

evaluation.

Total= 0.00 5130.97

Page 21: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM Package

IN PRINCIPLE NH CATEGORYSl.

No.Project Name

Length

(in km)

TPC

(in crore)Present Status

22 Panduka Bridge on

river Sone at

Srinagar

2.5 2000.00 Sanction / DPR

Stage

Total= 2.5 2000.00

Page 22: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM Package

PROJECT ZONE :-

Sl.

No.Project Name

Length

(in km)

TPC

(in crore)Present Status

23 Widening to 2-lane with

paved shoulder from km

25.00 to km 40.00 ofNH-

28B (Betia – Misraulia

section)

15 88.61 Start Date – 30.09.2016 & completion date –

27.11.2018 DBM completed in 15km.

BC - 11.70 km, Service Road both side GSB - 3

km, WMM - 2.9 km, DBM - 1.65 km, BC - 0.5 km

24 Widening to 2 Lane with

Paved Shoulder from km

65 to 97 of NH-28B

(Parsoni – Bagaha

section)

33 243.1 Start Date – 17.10.2016 & completion date –

11.05.2019

WMM both side (8.5 km) and DBM completed in

3.35 km done. Work progress is about 25%.

25 Construction of

Bhagalpur Bypass of NH-

80

16.675 268 Start Date – 05.11.2015 & completion date –

04.11.2017

Work is in progress. 12.60km DBM, BC – 12.60

Km

Physical progress is 80%.

Issue:- L/A for 155m under process. 3D is to be

submitted.

Page 23: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM Package

PROJECT ZONE :-

Sl.

No.Project Name

Length

(in km)

TPC

(in crore)Present Status

26 Widening to 2 Lane with

Paved Shoulder from km.

0.00 to 10.903 of NH-133

(Pirpainti – Barahat

section)

10.9 28.04 Road Work completed and Junction improvement

work to be done.

Issue:- Encroachment in Pirpainti more to be

removed.

27 Widening to 2 Lane with

Paved Shoulder from km.

0.00 to 25.010 of NH-

327A (Supaul Bhaptiyahi

section)

25.01 77.55 Start Date – 27.11.2016 & completion date –

25.06.2018

WMM completed in 24 km and DBM in 24 km

done. Work progress on scheduled time.

28 Widening to four lane

with service lane from

Km. 93.612 to Km.

98.000 of NH-327E

(Araria Town portion)

4.39 64.52 Start Date – 26.01.2016, scheduled completion

date – 30.06.2017. Main carriageway has been

completed & likely to be completed by

30.06.2018. Physical progress is about 82%.

Service lane completed.

29 Widening to 2 Lane with

Paved Shoulder from km.

0.00 to 11.400 of NH-99

(Dobhi to Jharkhand

border)

11.4 45.22 Work is in progress. 10.90 km DBM, BC-10.90

km has been completed.

Physical progress is 90%. Start Date – 16.08.2016

& completion date – 15.02.2018

Page 24: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM PackagePROJECT ZONE :-

Sl.

No.Project Name

Length

(in km)

TPC

(in crore)Present Status

30 Widening & strengthening from

km 167 to 180 of NH-80

(Ramjanipur – Pirpainti)

12.9 21.37 Start Date – 01.10.2016 & completion date –

31.12.2017 Physical progress is 80%. 12 km

DBM, BC - 12 km completed.

31 Widening to 2 Lane with Paved

Shoulder from km. 0.00 to 19.04

of NH-81

(Gerabari – Katihar section)

19.04 111.3 Start date 07.08.2017. Completion date –

06.08.2019.

E/W – 16 km, GSB – 7 km completed.

Stage-I Forest clearance obtained.

32 Widening to 2 Lane with Paved

Shoulder from km. 0.00 to 40 of

NH-2C. (Dehri – Akbarpur

section)

40 230.34 Work awarded and GSB completed in 15 km,

PQC – 5.50 km, BC - 3.50 km, WMM - 7 km

Stage-I Forest clearance obtained.

33 NH-333 from km 62 to 75

(Gidhaur - Section)

14 68.506 Work is in progress. Date of completion

15.06.18

Stage-I forest clearance obtained.

34 NH-327E from km 56 to 68

(Bahadurganj – Araria section)

12 56.3 Work under progress. Date of completion

31.03.2018. GSB – 5 Km, WMM – 3 Km,

DBM – 2 km completed.

35 NH-327E from km 75 to 93

(Bahadurganj – Araria section)

18 86.16 Work under progress. Date of completion

30.11.18. GSB – 12 Km, WMM – 5.50 km,

DBM – 4.50 completed.

36 NH-327E:- from km 0 to 39

(Galgalia – Bahadurganj section)

39 146.11 Work under progress. GSB – 15 km, WMM –

13.5 km, DBM – 10 km completed.

Forest clearance for tree cutting under process.

Total= 271.315 1535.13

Page 25: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM Package

PROJECTS IN BIDDING / SANCTION STAGE

Sl.

No.Project Name

Length

(in km)

TPC

(in crore)Present Status

37Bhatia – Chakai section

from km 115 to 141 of

NH 333

26.00 100.00 Work awarded. Agreement under process.

38Araria – Raniganj – JBC

Canaal section from km

112 to 136 of NH 327E

24.00 100.00 Technical Bid under evaluation.

39Gaya to Goh section NH

120

43.00 125.00 Technical Bid under evaluation.

40Nasriganj to Bikramganj

section of NH-120

20.00 100.00 Technical Bid under evaluation.

41 Varuna Bridge –

Mushrigharari section of

NH 103

14.45 70.00 Sanction / DPR Stage

Total= 127.45 495.00

Page 26: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM Package

New NH Category

Sl.

No.Project Name

Length

(in km)

TPC

(in crore)Present Status

42Bhabhua to UP Border section

of NH 219

36 300.00 Sanction / DPR Stage

43Bikramganj – Dumraon section

of NH 120

50 250.00 Sanction / DPR Stage

44

Barbigha–Shekhpura – Jamui –

Jhaja – Simultalla – Banka –

Panjwara section of NH 333A

197 1500.00 Sanction / DPR Stage

45Bariyarpur – Jamui Bhatia

section of NH 333

100 500.00 Sanction / DPR Stage

46JBC Canal section to Supaul of

NH 327E

47 200.00 DPR sent to MoRT&H

Total= 430 2750.00

G . Total= 1871.84 22244.02

Page 27: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM PackageIn Principle NH Category

Sl.

No.Project Name

Length

(in km)

TPC

(in crore)Present Status

47 Buxar – Chausa - Mohania 64

5850.00

Sanction / DPR Stage

48 Hajipur – Mahnar - Bachwara 75 Sanction / DPR Stage

49Govidpur – Fatehpur – Narhat

- Sirdalla

50 Sanction / DPR Stage

50 Belaganj – Rajgir 75 Sanction / DPR Stage

51Bhagalpur – Dhaka more

Hansdiha

62 Sanction / DPR Stage

52Chatarwa – Dhanha – Bansi –

Padrauna

46 Sanction / DPR Stage

53Chharatpur – Japla –

Navinagar – Barun

34 Sanction / DPR Stage

54 Rosera - Darbhanga 55 Sanction / DPR Stage

55 Mehsi – Jhapaha vide Tetaria 50 Sanction / DPR Stage

56Siwan-Maharajganj-Janta

Bazar

35 Sanction / DPR Stage

57 Shrawan-Chakai 18 Sanction / DPR Stage

58Saraigarh(327A)- Lalganj-

Ganpatganj

10 Sanction / DPR Stage

Total= 574 5850

Page 28: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM Package

PROJECTS UNDER NHAI

Sl. No. Project NameLength

(in km)

TPC

(in crore)Present Status

59 2L with PS

Biharsharif -

Barbigha –Mokama 54.76 399.54

Work started on 06th Oct. 2017

Schedule completion date 06.10.2019

Work front available – 45.1km

Physical progress- 13.18%, Financial progress – 16.1%

3A/3D -56.84Ha, 3G-56.22Ha60 4 – laning of Patna –

Koilwar Section of

NH 30

33 761.2

Land available – 43.59%

3D-165.6Ha, 3G-165.6Ha61 4 – laning of Koilwar

– Bhojpur Section of

NH – 30 & NH – 84

44 1050.44

Total land available- 52.92%

Work started on 04th July 2017

Schedule completion date 02.01.2020

Physical progress- 13%, Financial progress – 6%

3A/3D/3G done -198.93Ha

62 4 laning of Bhojpur –

Buxar section of NH

– 84 48 867.77

Total land available – 58.68%

Appointed date - 18.04.2018

3A/3D/3G done -193.9Ha

Physical & Financial progress – 0.0%

Page 29: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM PackagePROJECTS UNDER NHAI

Sl. No. Project NameLength

(in km)

TPC

(in crore)Present Status

63 4- laning of

Bakhtiyarpur –

Mokama Section of

NH-31

45 1167.45

Work started on 14.06.2017

Schedule completion date 10.12.2019

Work is under progress.

3A-239.4Ha, 3D-235Ha, 3G-234.7Ha

64 4 lane of Simaria –

Khagaria on NH – 31

NHDP Phase – III

60 1062.58Work started on 05.10.2016,

Schedule completion date- 03.04.2019

Physical progress- 20.50%, Land required – 1 Ha

65 2 – laning with PS of

Gopalganj – Chhapra

Section NH-85 94 854.8

Work started on 07.12.2015, Scheduled completion date –

06.12.17

Anticipated completion date- 31.08.18

Physical progress – 71.62%

3A-190.906 Ha/3D – 174.5Ha/3G-136Ha

66 2 – laning with PS of

Chhapra – Rewaghat –

Muzaffarpur, NH-10273 516.13

Work started on 05.04.2016

Scheduled completion date- 04.04.2018, Likely completion date

– 30.06.18

Physical progress – 97.98%

67 4 laning of Forbesganj

– Jogbani Section of

NH – 57A

9 322.09Work started on 18.04.2016

Schedule Date of Completion- 17.04.2018

Physical progress- 20.70%, Financial 18.22%, LA pending.

68 4 laning of Patna –

Gaya – Dobhi Section

of NH – 83 with JICA

ODA loan assistance

127 1496.86

Work started on 10.04.2015

Schedule Date of Completion - 09.04.2018

Physical progress- 6.73% , E/W – 39.93 Km, GSB – 27.27 Km,

WMM – 26.81 km, DBM - 17.50 km completd.

3A/3D/3G done -707Ha

Page 30: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM PackagePROJECTS UNDER NHAI

Sl. No. Project NameLength

(in km)

TPC

(in crore)Present Status

69 New 4 – laned bridge across river

Ganga at Mokama on NH – 319 800

Appointed date to be fixed.

3A-58.68Ha/3D-44.12Ha/3G -43.38Ha70 Bridge at Munger (approach road

to be constructed and balance

amount to be released)

18.69 935

Appointed date to be fixed.

3A/3D-65.4Ha/3G -23.6Ha

71

&

72

Development to 2-laned with PS of

Maheshkhut- Saharsa- Purnia

section of NH- 107 (in two

packages)

171 1000Appointed date to be fixed.

3A/3D-197.6Ha/3G-13.5Ha.

73 Bridge on river Ganga connecting

Manihari in Bihar to Sahibganj in

Jharkhand (NH-131B & 131 A)

21.885 1954.77 Bid received. LOA issued on 06.12.17

74 Development of Manjholi –

choraut Section of NH-527 C65 700

Bid received and under evaluation

3A-212Ha/3D-108Ha/3G -0.0Ha

75 Construction of 2nd

Elevated

Flyove parallel (LCW) in

Kishanganj town on NH-31

3.18 196.948 LOA issued to BRPNNL by NHAI.

76 4 – laning of Narenpur – Purnea

Section of NH – 133A 49 1674.73

SFC pending for want of availability of

required land. 3A-141Ha/3D-101Ha/3G

done - 0.0Ha

77 4/6 laning of Patna Ring Road65 1500

DPR preparation under process by

consultant.

Page 31: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM Package

PROJECTS UNDER NHAI

Sl. No. Project NameLength

(in km)

TPC

(in crore)Present Status

78 4 – laning of Munger – Mirzachowki

Section

120 1800

DPR finalization under process.

3A under process.

Land to be acquired– 668.9Ha in

123 village

79 Roads connecting Raxaul and Sonbarsa

(Parallel to indo – Nepal Border) 90 1800

DPR of Raxaul Sonbarsa dropped

Chakia- Bargainia Connectivity

50 1000

DPR of Chakia Bairgania

completed

3a published.

3A under process.

80 Ramupr – Khajuriya-Kesariya end of

NH – 722

58 160

DPR in 3 packages done

Final DPR under approval.

CALA nomination received

3a under process.

Page 32: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Details of PM Package

PROJECTS UNDER NHAI

Sl. No. Project NameLength

(in km)

TPC

(in crore)Present Status

81 Uchhait Bhagawati Sthaan (Umgaon) -

Basopatti-Benipatti-Rahika-

Madhubani-Rampatti-Awam-Laufa-

Bheja-New proposed bridge over river

Kosi-Mehsi- Tarasthaan- Bangaon-

Bariyahi – Saharsa – connecting NH-

327A (22 kms out of 180km are parts of

National Highways No. 527A, 327E &

107.

160 5000

Draft DPR for entire stretch in

4 packages submitted by DPR

consultant in NHAI HQ.

82 Ram-Janki Marg as already declared

recently part of which falls in Bihar

from UP Bihar Border to Siwan –

Madhubani-Sitamarhi-Indo-Nepal –

Border200 4000

Final DPR done in two

packages

1st package of Siwan -

Masharakh and 2nd Package

Mashrakh - Chakia under

approval.

Tender for 2nd package is to be

done in July, 2018.

Total= 1668.52 31020.34

Page 33: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Rehabilitation of M.G. SetuProgress till date :

• Dismantling of Median – Span 1–37 & 39 completed and Span 40 in

progress.

• Dismantling of Foot Path and Hand Rail – Span 1-37, 39-41 completed

& Span 42 in progress.

• Dismantling of Segment – Span 1-29 completed, Span 30-31 in

progress.

• Dismantling of Pier Head – Pier No. 1-6, 8 & 26 completed and Pier No.

7-25 in progress.

• Shifting of debris material for Span 1-28 completed & Span 29 in

progress.

• Modification of Pier Cap – Pier No. 2-3 completed & Pier No. 4-6 in

progress.

• Weathering Steel – 5326.00 MT of material has been manufactured at

ESSAR.

• Weathering Steel – 2647.457 MT of material dispatched to Texmaco,

Kolkata and 2289 MT of weathering dispatched to Atmatsco, Bhilai.

• Fabrication work still not started.

Page 34: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

ISSUESIssues related to MoRTH

1) Approval & Sanction of DPR for construction of 4-lane bridge

parallel to existing Vikramshila Setu and declaration of Bhagalpur

Navgachia as new NH.

2) Bidding of Phulaut Bridge over river Koshi on NH-106 to be done.

3) New bridge parallel to MG Setu, Patna be sanctioned soon.

4) Work of MG Setu is very slow. Erection work be started soon.

5) Munger – Bhagalpur – Mirzachouki Section of NH-80 has been

entrusted to NHAI & DPR on Green field alignment is under

process. Maintenance of existing NH-80 be done by MoRTH as

this stretch is very important & lifeline of this area. Estimates

submitted for different stretches should be approved at the earliest.

6) Revision of estimate of NH-82 Gaya – Biharsharif is pending.

7) Balance portion of NH-30, from Mithapur to Anisabad in Patna be

taken over by NHAI for maintenance.

8) Approval of LA proposal of 155 m in Bhagalpur bypass and

proposal of RE wall to be approved.

Page 35: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

ISSUESIssues related to MoRTH

9) Elevated corridor at Rajgir on NH-82 may be considered for

approval.

10) Annual Action Plan (2018-19) submitted by State Govt. needs

approval of MORT&H.

11) 14 nos. of PR works to be tendered - pending for clarity on

DLP.

12) LA & Supervision charges –

(i) Administrative Cost for LA to be reduced to 2.5%

(ii) Undisbursed amount of compensation may be permitted

to deposit in LARR Authority.

(iii) Supervision charges for electrical utility shifting to be

reduced to 2.5%.

Page 36: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

ISSUESIssues related to NHAI

1) Work for Dumariaghat Bridge on NH-28 near Gopalganj to be restarted.

2) Repair and maintenance of Ara- Mohania Section of NH-30.

3) DPR of New Bridge parallel to J.P. Setu, Patna over proposed Patna Ring

Road be finalized soon to start bidding process.

4) DPR of Indo Nepal Border road under Bharatmala.

5) Four Laning of Ara – Sasaram Road. DPR to be finalized soon.

6) Elevated road on Patna – Koilwar section of NH-30 (Shivala - Bihta) to

be started.

7) Balance length of Patna - Koilwar to be reviewed early and work to be

started.

8) Proper maintenance of NH-19, NH-83 & NH-80.

9) Condition of NH-107 to be improved and progress of work to be expedited.

10) Feasibility of Extension of Patna – Buxar to Gazipur be expedited.

11) DPR for Patna Ring Road to be finalized and early steps for construction to be

taken in the portion where land is available.

12) DPR of roads under Bharatmala Pariyojna to be expedited.

13) Proposal & DPR for additional bridge parallel to Dumari Ghat bridge on NH-

107 be prepared soon.

14) Chapra Bypass & Sumerpatti Bridge on NH-19 to be completed on priority.

Page 37: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

State Highways

Page 38: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

State Highways

STATUS Good Fair Bad Total

Length (Km) 3508.91 300.53 195.56 4005.56

%(Length wise)

87.60 7.50 4.90

Note:- SH wise status are included in subsequent slides....

Page 39: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

State HighwaysS. No. SH No. Stretch of State Highway

Length

(Km)

Condition of the Road (in Km)Remarks

GOOD FAIR BAD

1 1 Sadikpur- Pabhera Masaurhi 38.20 5.00 33.20 0.00 2 lane–proposed under CRF

2 2 Bihta - Pali - Arwal 37.70 34.70 3.00 0.00 2 lane OPRMC3 4 Daniawan - Hilsa - Ekangarsarai -

Islampur - Khijarsarai - Gaya78.50 78.50 0.00 0.00 2 lane

CMBD/OPRMC4 8 Hisua - Nawada - Lakhisarai 93.35 93.35 0.00 0.00 2 lane OPRMC5 12 Ara - Piro - Bikram - Nokha -

Sasaram 94.85 94.85 0.00 0.00 2 lane OPRMC

6 13 Buxar - Chausa 12.80 12.80 0.00 0.00 2 lane CMBD7 14 Chausa - Ramnagar - Mohania -

Bhabhua48.74 48.74 0.00 0.00 2 lane

CMBD/OPRMC8 15 Dehri - Nasriganj - Vikramganj -

Dinara44.00 44.00 0.00 0.00 2 lane CMBD

9 16 Dehri - Tilauthu - Akbarpur -Banjari

9.28 9.28 0.00 0.00 2 lane OPRMC

10 17 Sasaram - Kargahar - Kochas -Chausa

63.05 63.05 0.00 0.00 2 laneCMBD/OPRMC

11 18 Shekhpura - Lakhisarai - Jamui 45.31 45.31 0.00 0.00 2 lane OPRMC

12 19 Bhagalpur - Dhakamore -Barahat - Hansdiha

61.32 61.32 0.00 0.00 2 lane CMBD/OPRMC

13 22 Dakamore - Katoria - Belhar -Tarapur - Sultanganj

97.67 97.67 0.00 0.00 2 lane CMBD/OPRMC

Page 40: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

S. No. SH No. Stretch of State HighwayLength

(Km)

Condition of the Road (in Km)Remarks

GOOD FAIR BAD

14 25 Bhagalpur - Amarpur - Banka -Katoria

44.30 41.30 3.00 0.00 2 lane OPRMC1.5 lane CMBD

15 47 Sarfara - Barharia - Siwan -Mairwa – Guthani

35.10 23.00 12.10 0.00 2 lane OPRMC

16 49 Hajipur - Mahua - Tajpur -Samastipur

62.95 62.95 0.00 0.00 2 lane OPRMC

17 50 Musari - Gharari - Pandasarai -Mabbi - Laheria Sarai

62.35 62.35 0.00 0.00 2 lane OPRMC

18 51 Darbhanga - Sakari - Jhanjharpur - Khutauna - Laukaha

32.70 32.70 0.00 0.00 2 lane OPRMC

19 52 Sitamarhi - Pupari - Benipatti -Rahika - Madhubani - Rampatti -Jhanjharpur

77.09 77.09 0.00 0.00 2 lane OPRMC1.5 lane CMBD

20 53 Chapra - Salempur 10.00 10.00 0.00 0.00 2 lane OPRMC21 54 Bettiah - Areraj - Motihari -

Dhaka - Belwaghat - Masaudha -Sheohar - Sitamarhi

121.65 105.25 16.40 0.00 2 lane / IRQPsanctioned

22 55 Begusarai - Manjhaul - Rosera -Samastipur

77.50 77.50 0.00 0.00 2 lane CMBD/ OPRMC

23 56 Darbhanga - Benipur - Biraul -Kusheshwar Asthan

64.00 64.00 0.00 0.00 2 lane OPRMC

24 57 Saharsa - Purnea 2.34 2.34 0.00 0.00 2 lane OPRMC

Page 41: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

S. No. SH No. Stretch of State HighwayLength

(Km)

Condition of the Road (in Km)Remarks

GOOD FAIR BAD

25 58 Udakishunganj - Chousa – LauaLagam Vijayghat

35.10 27.40 7.70 14.40 Existing Single lane Tendered for 2 lane with paved shoulder

26 59 Sonbarsa - Saurbazar - Baijnathpur 24.00 24.00 0.00 0.00 2 lane OPRMC27 60 Purnea - Araria - Forbesganj 35.17 35.17 0.00 0.00 Single / 1.5 lane/2

lane OPRMC28 62 Purnea - Katihar 1.75 1.75 0.00 0.00 2 lane OPRMC29 64 Bagaha - Balmikinagar 28.80 28.80 0.00 0.00 2 lane OPRMC30 65 Purnea - Dhamdaha - Rupauli -

Chandpur63.46 63.46 0.00 0.00 2 lane OPRMC

31 66 Saharsa - Bangaon - Supaul -Singheshwar Asthan

27.77 27.77 0.00 0.00 2 lane OPRMC

32 67 Kudra - Chenari - Shivsagar 40.20 40.20 0.00 0.00 2 lane OPRMC33 68 Sheoganj - Rafiganj - Goh -

Upahara - Deokund- Baidarabad83.05 83.05 0.00 0.00 2 lane BSRDCL

34 69 Dumaria - Imamganj - Sherghati -Karmain - Mathurapur - Guraru -Ahiapur - Tekari - Mau - Kurtha -Kinjar - Pali - Rani Talab

152.80 152.80 0.00 0.00 2 lane BSRDC

35 70 Gaya - Fatehpur - Sirdala - Rajauli 79.30 72.30 7.00 0.00 2 lane 36 71 Jehanabad - Ghoshi - Islampur -

Rajgir - Giriyak, Parwatipur 87.76 85.20 2.56 0.00 2 lane

37 73 Siwan - Basantpur - Masharakh -Taraiya - Amnour - Sonho- Parsa -Shitalpur

52.00 52.00 0.00 0.00 2 lane

Page 42: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

S. No. SH No. Stretch of State HighwayLength

(Km)

Condition of the Road (in

Km) Remarks

GOOD FAIR BAD

38 74 Hajipur - Vaishali - Deoria -Sahebganj - Kesaria - Khajuria -Areraj

121.13 121.13 0.00 0.00 2 lane

39 75 Darbhanga - Kamtaul - Basaitha -Madhwapur

47.00 0.00 47.00 0.00 2 lane

40 77 Kursela - Pothia - Falka - Mirganj -Sarsi - Kala Balua - Raniganj -Saifganj - Farbesganj

102.88 102.88 0.00 0.00 2 lane

41 78 Bihta - Naubatpur - Neva - Dumari - Beldarichak - Kansari - Daniawan & Chand - Noorsarai - Bhagan Bigaha -Rahui - Bind - Gopalbad -Sarmera

122.26 38.07 0.00 84.19 2 laning work in progress

42 80 Bhabhua - Adhaura 53.00 53.00 0.00 0.00

43 81 Sakkadi - Chandi - Sandesh - Sahar - Bihar - Danwar - Nasriganj

86.80 75.40 11.40 0.00 BSRDC - work in progress

44 82 Kadirganj - Roh - Kauakol - Khaira -Sono

65.83 65.83 0.00 0.00 Tendered for 2 lane with paved shoulder

45 83 Bagi - Bardiha - Barbigha 40.05 40.05 0.00 0.00 Under BSRDC

46 84 Ghogha - Sanhaula - Dhoraiya -Panjwara - Barahat

42.80 24.50 18.30 0.00 Tendered for 2 lane with paved shoulder

47 85 Akbarpur - Shahkund - Amarpur 29.40 18.00 11.40 0.00 Tendered for 2 lane with paved shoulder

48 86 Saraiya - Jaitpur - Motipur 28.18 28.18 0.00 0.00 under BSRDC

Page 43: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

S. No. SH No. Stretch of State HighwayLength

(Km)

Condition of the Road (in Km)Remarks

GOOD FAIR BAD

49 87 Runnisaidpur - Nanpur -Pupri - Sursand - Parihar -Bhiswa

67.49 45.24 15.00 7.25 Under construction

by BSRDC

50 88 NH-103 (Baruna Pul) -Rasiyari

120.34 42.23 20.13 57.98 - do-

51 89 Siwan - Siswan 31.27 29.71 1.56 0.00 Under BSRDC52 90 Mohammadpur - Rajpatti -

Mashrakh - Khaira - Chapra41.71 41.71 0.00 0.00 Under BSRDC

53 91 Balua - Jadia - Mirganj -Murliganj - Udakishunganj

101.70 95.20 0.00 6.50 Under construction by BSRDC

54 92 Saraigarh - Parwaha 75.79 60.35 1.10 14.34 NH declared. Bad portion is missing link

55 93 Hajipur - Bachhwara 70.00 68.50 1.50 0.00 Single/2 lane CMBD/OPRMC

56 95 Mansi - Hardi Chaughra 78.09 60.13 2.98 14.98 Alignment under process with 14.98 Km missing link.

57 96 Manjhi - Barauli 60.00 20.25 39.75 0.00 Single lane

Page 44: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

S. No. SH No. Stretch of State HighwayLength

(Km)

Condition of the Road (in Km)Remarks

GOOD FAIR BAD

58 97 Bishanpur -Ghoghrahachatti

47.70 47.70 0.00 0.00

59 98 Katihar - Balrampur 65.10 64.10 1.00 0.00

60 99 Baisi - Bahadurganj 77.10 77.10 0.00 0.00

61 100 Bandhuganj - Rohini 45.00 34.10 0.00 10.90 Single/1.5 lane

CMBD62 101 Amba - Gaya 85.90 83.90 2.00 0.00 Single lane63 102 Bihia - Bihta 52.75 52.75 0.00 0.00 Tendered64 103 Manjhway - Govindpur 45.37 45.37 0.00 0.00

65 104 Dighwara - Semri 69.68 27.23 42.45 0.00 Single lane/CMBD

66 105 Bettia - Lauria Road 68.20 68.20 0.00 0.00

67 106 Didarganj–Fatuha-Bakhtiyarpur

37.15 37.15 0.00 0.00 2 lane CMBD

Total 4005.56 3508.91 300.53 195.56

Page 45: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Major District Roads

Length maintained under OPRMC - 6167.16 Km

Length under different ongoing schemes - 4246.15 Km(under CMBD, CRF, NABARD, Plan etc.)

Length proposed under different schemes - 471.00 Km

Road length not covered under any scheme- 260.97 Km

11145.28 Km

• Length of roads (110 nos) notified for transfer

to RCD but yet to be upgraded as per IRC Standard - 1141.30 Km

Good

(Km)

Fair

(Km)

Bad

(Km)

Total

Length (Km) 8562.95 1120.59 1461.74 11145.28

% 76.83 10.05 13.12

Page 46: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Output & Performance based Road

Maintenance Contract (OPRMC) at a Glance

DescriptionInitial Status as

per AA

Current

StatusRemarks

Road network

length9064 Km 8039 Km

Deletion for widening/

strengthening/ transferred to NH

No. of packages 76 74Chhapra (40) rescinded and

Hajipur (41) under litigation

AA Amount 2579.17 Crore 2579.17 Crore --

Agreement

Amount2409.63 Crore 2386.68 Crore --

Date of Start Dec’2013 --

Contract Period 5 Years ( Upto Dec’2018) --

Expenditure upto

April’20182116.57 Crore 89 %

PM (Periodic

Maintenance)

Status upto

April’2018

6230 km out of 6807 km 92 %

Page 47: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Public Grievance Status( since 04.04.2015 till date)

Description Total Complaints Disposed PendingPercentage

Disposal

RCD (excluding

OPRMC)5744 5547 197 97%

OPRMC 887 887 0 100 %

Others

(Related to other

departments)

25277 13514 11763 53 %

Page 48: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Measures taken for effective monitoring of OPRMC

Public Awareness for Complains/Suggestion

Through Hoardings

Print & Electronic Media

Online Monitoring system for Inspection & Reporting by field

officers.

GPS installed on all Road Ambulances and monitored by Vehicle

Tracking System.

Call Recording and SMS integrated into RMPGRS. Voice

recording for improving quality of Grievance Handling.

Special Inspection Drive for proof checking of performances of

Divisions and Contractors.

Video evidencing of OPRMC roads on random basis.

Page 49: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Special Inspection Drive (under OPRMC) Special Independent Inspection Drive conducted to ascertain

ground status of every km of 8039 km of roads in 2017.

Reports were received online.

Major findings:

i. 7509 Kms of OPRMC road crust were found maintained out

of 8039 Kms. (93.4% of road length)

ii. Total 568 pots were found in rest 530 Kms of the stretch. [@

1.07 pots/Km]

iii. In 75 % road stretch, shoulder condition was found

satisfactory.

iv. Other parameters such as Road safety, Drain clearance/

Culvert maintenance requires more attention.

Contractors and Work Divisions identified where performance of

OPRMC was found unsatisfactory, department has initiated

action against such Contractors and Engineers.

Page 50: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Next phase of OPRMC (Phase-II)

Salient Features:

Next phase to start in DEC’ 2018 . Maintenance period 7 years.

To include all roads of RCD : Length approx 14000 km.

Maintenance plan prepared road wise.

DPR preparation under process.

Package size-150-200 km ; Costing 80-120 cr approx.

Maintenance cost – Rs. 7.55 Lakh per Km per year

Total cost of maintenance per year – Rs. 1030 crores

Periodic Renewal every four (4) years on each road.

Administrative Approval to be obtained division wise.

Emphasis on Road Safety in IR & MI.

Page 51: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

• Total 100 schemes sanctioned out of which 81 schemes have

been completed and 19 schemes are in progress.

• Total accrual till 01.04.2018 - 1168.59 Cr

• Total amount of schemes sanctioned till date - 1760.11 Cr

• Amount released till 01.04.2018 - 734.15 Cr

• Amount utilized till 01.04.2018 - 692.05 Cr

Central Road Fund

Page 52: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Status of ROB

• Under Tripartite Agreement between Railway, State Govt. and

IRCON, IRCON has taken up construction of 34 ROBs, out of

which 30 have been completed and 4 are under progress.

• State Government has conveyed its consent for construction of

47 ROBs. Railway is preparing GAD and DPR for construction

of ROBs.

• Railway has provided another list of 48 level crossings and

requested consent of State Government for 50% cost share.

Feasibility Report of these level crossing is under process in

RCD.

• Tripartite MOU to be signed among GoB, Railways and

MORT&H

Page 53: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

• TOTAL PROJECTS SANCTIONED : 326nos. (RIDF-XIV to XXIII)

Bridge Projects : 258 nos.

Road Projects : 68nos.

• TOTAL PROJECTS COMPLETED : 164nos.

Bridge Projects : 138 nos.

Road Projects : 26 nos.

• PROJECTS SUBMITTED TO NABARD IN 2018-19 UNDER RIDF-XXIV

No. of Road Schemes : 13 + 30 = 43 nos (724 Km)

Estimated Cost : 780 + 1238 = 2018.00 Cr.

No. of Bridge Schemes : 1 no. (9.09 Cr)

Status of Approval: Approval awaited from NABARD

Status of Projects funded under RIDF

Page 54: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Indo-Nepal Border Road Project

Total Length - 552.293 Km

Cost of construction shared by GoI - 1702.00 Cr.

Share of State Govt. - 3262.383 Cr.

[LA 2233.13 Cr + 121 nos Bridges 983.81 Cr]

Original amount of A/A - 2552.8630 Cr

1st Revised A/A amount - 3935.1304 Cr

Note:- Rs. 983.81 crores for construction 121 bridges sanctioned

under NABARD of State Plan

Status of Execution : Total Contract - 8 nos,

Under litigation – 4 nos.

Under progress – 4 nos. (1 package substantially

completed in Araria)

81.58 Km Black Top Road completed.

Land to be acquired 103.163 Km.

Page 55: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Indo-Nepal Border Road Project

District

To b

e A

cqu

ired

(Mau

za) To be

Acquired

(Acre) Acq

uir

ed

(Mau

za)

Acquired

(Acre)

Amt.

deposited

with DLAO

Balance Mauza/ Area to

be Acquired Balance Amt.

with DLAO

(6-15)Mauza

(Nos)

(2-4)

Area

(Acre)

(3-5)1 2 3 4 5 6 7 8 9

1 Bettiah 94 803.803 61 315.5125 301.5048 33 488.29 237.551

2 Motihari 47 570.350 40 402.0165 269.3009 7 168.33 57.829

3 Sitamarhi 61 558.510 52 508.2574 587.7244 9 50.25 408.203

4 Madhubani 17 103.374 17 103.3740 124.5700 0 0.00 82.880

5 Supaul 7 42.007 5 26.1077 106.5959 2 15.90 85.184

6 Araria 64 455.962 11 163.0300 591.6122 53 292.93 325.470

7 Kishanganj 65 349.180 56 293.9420 218.4985 9 55.24 127.069

8 Kishanganj

(Araria

Portion)

10 47.700 10 47.7000 28.9715 0 0.00 12.022

Total 365 2930.886 252 1859.9401 2228.7782 113 1070.95 1336.2059

Status of LA :

Total amount required for LA deposited to DLAOs.

Page 56: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

ROAD CONNECTIVITY PROJECT FOR LEFT WING EXTREMISM AFFECTED AREAS

(RCPLWEA) UNDER PMGSY

Page 57: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Approved Schemes by MoRD

Sl. No. Districts. No. of Road Length as per DPR

(Km)

1. Aurangabad 6 197.262

2. Gaya 11 155.69

3. Jamui 5 83.141

4. Banka 7 102.10

5. Muzaffarpur 23 326.723

Total 52 864.916

Sl. No. Districts. No. of Bridge Length as per

DPR (mtr.)

1 Muzaffarpur 1 148.80

Page 58: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Schemes yet to be Approved by MoRD

Sl. No. Districts. No. of Bridge

1. Aurangabad 8

2. Gaya 3

3. Jamui 0

4. Banka 15

5. Muzaffarpur 15

Total 41

Page 59: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Schemes yet to be Approved by MoRD Sl.

no.

District Name of Road Length of Road

(in Km)

1 2 3 4

1 Muzaffarpur Basghatta Chowk to Pupri via Pahsoul, Jajuaar 11.25

2 Muzaffarpur Aurai - Jale Road 10.00

3 Muzaffarpur Turki (NH-77) to Saraiya (NH-102) 21.90

4 Banka English more - Punasia via Jethaur Nath Road 12.70

5 Gaya Belaganj (NH-83) to Panchanpur via Singhaul Road 15.00

6 Gaya NH-83 to Tikari via Belhari Road 13.00

7 Gaya Gaya - Nalanda Road to Bairaka via Harli (Near

Mayapur) Saraia, Budhgharaia, Pale, Hudrahi, Gharaia,

Kobva Road

20.00

8 Gaya Chakand - Presheela - Kujapi Road 8.50

9 Jamui Baisakitand (NH- 333) – Simultala (NH- 333 A) Road 20.00

10 Aurgangabad Obra - Bel - Barahi Road 14.00

11 Aurgangabad Beri - Kalali to Bhadwa via Pirthu, Bishambharpur,

Karwa, Kharaukhar, Gothani Road

14.00

12 Aurgangabad Dihara to Obra Road 12.00

13 Aurgangabad Deo More to Kataki via Maharana Pratap College Deo

Road via Goujraya

13.00

14 Banka Shambhuganj-Asharganj Road 8.30

Grand Total:- 193.65

Page 60: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Status of Tender

Sl.

No.

Districts. No. of

Road

Length as per

DPR (Km)

Status of tender

1. Aurangabad 6 197.262 Tender invited & Tech Bid Opened.

2. Gaya 11 155.69 Tender invited Tech Bid opened for

9 Roads

3. Jamui 5 83.141 Tender invited

4. Banka 7 102.10 Tender invited & Tech Bid Opened

for 6 Roads

5. Muzaffarpur 23 326.723 Tender invited for 4 Roads & rest 19

Roads tender is in process.

Total 52 864.916

Sl.

No.

Districts. Name of Bridge Length as per

DPR (mtr.)

Status of tender

1 Muzaffarpur HL RCC Bridge in 26th Km over River Bagmati

148.80 Tender invited .

Page 61: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Status of Mega Projects implemented by

Bihar Rajya Pul Nirman Nigam Ltd.

Page 62: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Name of Project

Construction of Bridge over river Ganga between Arrah (NH-

30) and Chhapra (NH-19) via Babura –Doriganj in dist of

Bhojpur and Saran of Bihar.

Description of ProjectRCC High Level Bridge, Bridge length 4 Km, width 4 lane with

footpath (20.50 mt), Approach Road 16km.

Administrative ApprovalRs. 676.00 Cr. Vide RCD Letter No 7414(S) Dated 31.03,2010

(Revise Estimate for Rs. 886.00 Cr. Submitted to RCD)

Agreement Amount Rs. 625.78 Cr.

Date of Start 05.07.2010

Date of Completion (as per EOT) 31.05.2017

Date of Completion Bridge Inaugurated on 11.06.2017 and opened for Light Traffic.

Heavy Vehicles allowed since last week of August 2017.

Contractor SDB-SPS(JV)

Supervision Consultant AECOM-TES (JV)

Physical Progress Issues

Foundation Sub Structure Super Structure Approach 1-Land Acquisition for 2.5

Km Green Field connectivity

with NH-30

2-L.A. Issue in second lane

of road in Bhojpur Distt &

Guide Bund in Saran Distt

100% 100% 100% 75%

Page 63: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Bridge over river Ganga between Arrah (NH-30) and Chhapra (NH-19)

Page 64: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Name of ProjectConstruction of Northern Approach (Sonpur Side) of Rail–

cum–Road Bridge over river Ganga near Digha Ghat Patna.

Description of Project

RCC / Composite Elevated structure with Approach Road.

Length : 2.56 Km (1st Phase) + 3.142 Km (2nd Phase) = Total

5.703 Km.

Administrative Approval Rs. 244.99 Cr. Vide RCD Letter No 7175 (S) Dated 05.08.15

Agreement Amount Rs. 75.49 Cr. (1st Phase)

Date of Start 12.12.2015

Date of Completion (1st

Phase)

(as per agreement)

11.12.2016

Expected Date of

Completion

1st Phase Inaugurated on 11.06.2017 and Traffic opened

2nd Phase to be completed by June 2019

Contractor M/s S.P. Singla Construction Pvt. Ltd.

Remarks2nd Phase : Tender Awarded., Work and Land Acquisition in

Progress.

Physical Progress (1st Phase) Issues

Foundation Sub Structure Super Structure Approach L.A. for 2nd phase in

Saran Distt.100% 100% 100% 100%

Page 65: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Northern Approach (Sonpur Side) of Rail–cum–Road Bridge over river

Ganga near Digha Ghat Patna.

Page 66: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Name of Project

Construction of Flyover (2x2 lane, carriageway 5.5 m wide) from

Mithapur ROB to Chiraiyatand Flyover via Station Road

And

Extension of Chiraiyatand Flyover (1x2 Lane, Carriageway 7.5 m

wide) up to Gandhi Maidan in Exhibition Road

Description of Project RCC / Composite Fly Over.

Administrative Approval Rs. 167.85 Cr. Vide RCD Letter No 100 (S) Dated 08.02.13

Agreement Amount Rs. 97.01 Cr.

Date of Start 28.06.2013

Date of Completion (as per

EOT)30.06.2017

Date of Completion Inaugurated on 26.12.2017 & Traffic opened .

Contractor M/S S.P. Singla Construction Pvt. Ltd.

Supervision ConsultantSTUP in Association with Transtek. (Agreement closed in Dec.-

2017)

Physical Progress Issues

Foundation Sub Structure Super Structure Approach

-100% 100% 100% 100%

Page 67: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Mithapur ROB to Chiraiyatand Flyover via Station Road

Page 68: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Name of Project

Construction of High Level Bridge on Sone River Connecting

Daudnagar and Nasriganj including Approach Roads in District

Aurangabad and Rohtas, Bihar

Description of Project

RCC HL Bridge, Bridge Length -2.9 KM. Width - 4 Lane,

Minor Bridge - 4 Nos.,Trumpet Interchange -1 No., Hume Pipe Culvert

-23 Nos., Vehicular Underpass-5 Nos., Approach - 8.00 Km.

Administrative Approval Rs. 1006.56 Cr. Vide RCD Letter No 10100 (S) Dated 15.12.16

Agreement Amount Rs. 432.69 Cr.

Date of Start 04.03.2014

Date of Completion (as per

EOT)31.03.2018

Expected Date of

Completion

31.12.2018

(Bridge shall be completed by Dec.- 2018 & Traffic can be

opened through Barun – Daudnagar Road in Daudnagar Side

and RWD Road in Nasriganj Side)

Contractor Hindustan Construction Co.

Supervision ConsultantSTUP in Association with Transtek (Agreement closed in Dec.-

2017)

Physical Progress Issues

Foundation Sub Structure Super Structure Approach L.A.in Aurangabad

and Rohtas Distt.100% 100% 95% 30%

Page 69: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Bridge over river Sone connecting Daudnagar and Nasriganj

Page 70: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Bridge over river Sone connecting Daudnagar and Nasriganj

Page 71: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Name of Project

Construction of 13.00 Km (Approx) long extended portion of

Approach road of Baluaha Ghat Kosi Bridge between Baluahaghat

to Gandaul upto Biraul (Hanti Kothi) in Saharsa/Darbhanga.

Description of ProjectMajor Bridge 2 Nos, Minor Bridge 11 Nos, Box Culvert 21 Nos,

Approach Road 11.61 Km with Guide Bund

Administrative Approval Rs. 404.00 Cr. Vide RCD Letter No 1704 (S) Dated 24.10.16

Agreement Amount Rs. 231.15 Cr.

Date of Start 12.03.2013

Date of Completion (as per

EOT)30.06.2017

Expected Date of

Completion31.12.2018

Contractor Gammon India Ltd.

Supervision Consultant AECOM India Pvt Ltd.

Physical Progress Issues

Foundation Sub Structure Super Structure Approach L.A. in Darbhanga and

Saharsa Distt.100% 100% 98% 76%

Page 72: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Extended portion of Approach road of Baluaha Ghat Kosi Bridge between

Baluahaghat to Gandaul upto Biraul (Hanti Kothi) in Saharsa/Darbhanga.

Page 73: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Name of Project

Construction of 2x2 Lane Bridge with footpath across river

Ganga between Sultanganj (Bhagalpur District) and Aguwani

Ghat (Khagaria District) including navigational span of cable

stayed and approaches (Connecting NH31 and NH80) in the

state of Bihar on EPC mode

Description of ProjectRCC HL Bridge, Bridge length – 3.160 Km, width – 8.5mX2, Footpath

– 2X1.5m, Approach – 4Km Sultanganj Side & 16Km Aguani Side.

Administrative Approval Rs. 1710.77 Cr. Vide RCD Letter No 8797 (S) Dated 14.11.13

Agreement Amount Rs. 859.00 Cr.

Date of Start 02.05.2015

Date of Completion( as per

Agreement)01.11.2019

EPC Contractor M/S S.P. Singla Construction Pvt. Ltd.

Supervision Consultant Studio De Miranda in JV with Rodic Consultant Pvt Ltd

Physical Progress Issues

Foundation Sub Structure Super Structure Approach L.A. in Khagaria and

Bhagalpur Distt.88.26% 43.00% 8.40 -

Page 74: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Bridge over river Ganga between Sultanganj (Bhagalpur

District) and Aguwani Ghat (Khagaria District)

Page 75: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Name of ProjectConstruction of H.L P.S.C cast in situ bridge over river Gandak in

between Sattarghat and Faizullahpur in District Motihari (Bihar)

Description of ProjectRCC HL Bridge, Bridge Length – 1.440 Km, Width – 12m,

Approach-9.071 Km.

Administrative Approval Rs. 263.48 Cr. Vide RCD Letter No 4156 (S) Dated 13.04.12

Agreement Amount Rs. 209.18 Cr.

Date of Start 20.10.2012

Date of Completion (as per

EOT)30.06.2018

Expected Date of

Completion30.06.2019

Contractor Vasishta Construction Pvt Ltd. Hydrabad

Supervision Consultant VKS Infratech, New Delhi

Physical Progress Issues

Foundation Sub Structure Super Structure Approach LA Issue in East

Champaran and

Gopalganj Distt95% 76% 49% 54%

Page 76: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Bridge over river Gandak in between Sattarghat and

Faizullahpur in District Motihari (Bihar)

Page 77: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Name of Project

Construction of High Level Bridge across river

Gandak at Bangra ghat including 19 Km. length of

Approach Road connecting Muzaffarpur & Saran

District of North Bihar

Description of ProjectRCC HL Bridge, Bridge Length – 1.506 Km, Width – 14.80 m,

Length of Guide Bund – 2.225 Km, Approach Road -19 Km,

Administrative Approval Rs. 508.98 Cr. Vide RCD Letter No 8795 (S) Dated 14.11.13

Agreement Amount Rs. 299.51 Cr.

Date of Start 11.04.2014

Date of Completion (as per

EOT)09.04.2019

Expected Date of

Completion09.04.2019

Contractor M/s S.P. Singla Construction Pvt. Ltd.

Supervision Consultant AECOM-VIS (JV)

Physical Progress Issues

Foundation Sub Structure Super Structure Approach LA Issue in

Mujaffarpur, Gopalganj

& Saran Distt.87.20% 64.10% 29.24% 21.60%

Page 78: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

P-03

Bridge across river Gandak at Bangra Ghat

Page 79: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Name of Project

Construction of “Lohia Path Chakra” with Swap and grade

separated U-Turn based multi sectional interchange,

multiple Underpasses, Flyover, elevated section using U-

Girders & extra dosed cable stayed structures at Bailey

Road, Patna

Description of ProjectExtra Dosed Cable Stayed Bridge at Daroga Rai Path

Integral Spine Beam Bridge Near Lalit Bhawan Junction

Extra Dosed Cable Stayed Bridge Near BPSC Office

Administrative Approval Rs. 391.48 Cr. Vide RCD Letter No 7192 (S) Dated 05.08.15

Agreement Amount Rs. 381.60 Cr.

Date of Start 19.02.2015

Date of Completion (as per

Agreement)18.12.2017

Expected Date of

Completion (as per EOT)31.03.2019

Contractor M/S S.P. Singla Construction Pvt. Ltd.

Concept, Design &

Supervision

Foundation for Innovation & Technology Transfer, IIT,

Delhi

Physical Progress

Foundation Sub Structure Super Structure Approach

69% 17% - -

Page 80: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

R-05 Underpass water proofing work in progress 0+320 to 0+360 (Circular Road)

R-05 Underpass Crash Barrier reinforcement binding work is in progress 0+120 to 0+140 (Near Lalit Bhawan)

Page 81: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Lohia Path Chakra

Page 82: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Bihar Rajya Pul Nirman Nigam Ltd

Mukhya Mantri Setu Nirman Yojna

Total Sanctioned

Schemes

Completed

Schemes Ongoing Schemes

NosAmount in

Cr.Nos

Amount in

Cr.Nos

Amount in

Cr.

1157 2688.54 1132 2605.21 25 83.33

Page 83: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Status of Mega Projects implemented by

Bihar State Road Development Corporation

Page 84: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

ADB ASSISTED COMPLETED PROJECTS

BSHP PHASE-I (2009-12)

SH

No.Name of Road

Length

(km)Status

68 SHIVGUNJ-BAIDRABAD 83.051 Substantially Completed

69 DUMARIA-RANI TALAB 152.80 Substantially Completed

70 GAYA-RAJAULI 58.23 Completed

71 JEHANABAD-SHAHPUR 85.20 Completed

73 SIWAN-SHITALPUR 88.00 Completed

74 HAJIPUR - ARERAJ 87.06 Completed

75 DARBHANGA– MADHWAPUR 46.75 Completed

76 ARARIA – BHAPTIYAHI 121.00 Completed

77 KURSELA - FORBESGANJ 102.93 Completed

• Substantially Completed – SH-68: 2 Br. Superstructures remaining, SH-69: Approach Road in km 8 & 22 and

Superstruture work in Km 10 & 119 remaining.

Page 85: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

ADB ASSISTED PROJECTS

SH

No.Name of Road

Length

(km)Completion Date Status

78BIHTA - DANIYAWAN –CHANDI -

SARMERA94.20 30.06.2018 38.07 km Completed

81 SAKKADI - SAHAR - NASARIGANJ 83.25 31.05.2018 75.40 km Completed

89 SIWAN-SISWAN 31.27 - Completed

90MOHAMMADPUR-

KARANKUDARIYA -CHHAPRA64.70 31.05.2018 Completed

91 BIRPUR-UDAKISHANGANJ 100.84 31.03.2019 94.44 km Completed

83 BAGHI - BARBIGHA 37.646 - 36.55 km Completed

86 SARAIYA – MOTIPUR 28.204 16.10.2018 25.62 km Completed

87 RUNNISAIDPUR - BHISHWA 67.755 31.07.2018 47.75 km Completed

88 BARUNA BRIDGE - RASIYARI 120.901 30.09.2019 54.61 km Completed

BSHP PHASE-II (2011-19)

PROJECTS UNDER CONSIDERATION

SH

No.Name of Road

Length

(km)Status

58 UDAKISHANGANJ-BHATGWA ROAD 29.48

Date of Bidding is 07.6.2018

Except SH-105 for which DPR

preparation is in Progress.

82 KADIRGANJ-KHAIRA ROAD 75.10

84 GHOGHA-PANJWARA ROAD 43.35

85 AKBARNAGAR-AMARPUR ROAD 29.304

102 BEHEA-JAGDISHPUR –PIRO BIHTA ROAD 54.519

105 BETTIAH-NARKATIAGANJ-BIKHNA THORI ROAD 71.6

Page 86: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

(SH-78, BIHTA - DANIYAWAN – CHANDI - SARMERA)

PACKAGE-1 PACKAGE-2

CONTRACTOR M/s BSCPL Infrastructure

Ltd., Hyderabad

M/s BSCPL Infrastructure

Ltd., Hyderabad

CONTRACT LENGTH 46.70 km 47.5 km

CONTRACT AMOUNT 393.34 Cr. 287.16 Cr.

DATE OF COMMENCEMENT 29.08.2015 12.09.2015

DATE OF COMPLETION 30.06.2018 30.06.2018

FINANCIAL PROGRESS 26.86% 31.02%

WORK COMPLETION8.85 km (upto DBM) – by

Previous Contractor

14.75 km (upto DBM) – by

Previous Contractor

PHYSICAL PROGRESS 26.26 % 33.40 %

EMBANKMENT 14.903km 13.567 km

SUB – GRADE 12.225 km 10.246 km

GSB 10.862km 10.897 km

WMM 10.277km 10.232km

DBM 6.8 7.665

BC - -

Page 87: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

(SH-78, BIHTA - DANIYAWAN – CHANDI - SARMERA)

Page 88: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

PPP ON-GOING GREENFIELD BRIDGE ACROSS GANGA

CONNECTING BAKHTIYARPUR TO TAJPUR

Page 89: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

CONCESSIONAIRE M/s Navayuga Jahnavi Toll Bridge Pvt. Ltd.

CONCESSION PERIOD 30 Years including 4.5 years Const. period

MAIN BRIDGE LENGTH 5.525 km

APPROACH ROAD 45.745 km

APPOINTED DATE 30.11.2011

COMPLETION DATE 31.07.2019

VGF GoI 277.50 Cr.

VGF GoB 307.50 Cr.

FINANCIAL PROGRESS (w.r.t Total Fin Pkg.) Rs. 870.38 Cr. (54.41 %)

PHYSICAL PROGRESS (w.r.t EPC) Rs. 720.81 Cr. (49.71%)

FEATURESMajor Bridges – 03, ROB – 02, Grade Separator-03,

VUP- 16, Service Road (km)-10.05, Toll Plaza- 01

MAIN BRIDGE:

Foundation Piles – 270/272 (Nos.), Pile Caps – 41/46 (Nos.), Sub-structure- 30.3/46 (Nos.),

Segment Casting- 338/1722 (Nos.), Super-Structure launching Span – 1/45 (Nos.).

HIGHWAY : Road Embankment – 21.6/45.75 (km).

GREENFIELD BRIDGE BAKHTIYARPUR TO TAJPUR

Page 90: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

MAJOR BRIDGE :- 01 completed out of 4 Nos.

ROBs :- 02 ( 1 no. in progress up to Sub

structure).

GRADE SEPARATOR : 03 ( 1 no. in progress

up to Sub structure).

VUPs :- 10 ( 4 no. completed, 1 in progress, 5

nos. not started due to LA).

PUPs : 6 ( 3 no. completed, 1 is going to start, 2

nos. not started due to LA).

Page 91: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

GREENFIELD BRIDGE BAKHTIYARPUR TO TAJPUR

Page 92: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

EPC ON-GOING PROJECTSELEVATED CORRIDOR PROJECT PATNA (L-12.27 km)

Page 93: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

ELEVATED CORRIDOR PROJECT PATNA (L-12.27 km)

ADMINISTRATIVE APPROVAL 1231.06 Crores. (including NHAI Leftover)

AGREEMENT AMOUNT (WORK) Rs. 877.45 Crores.

NAME OF THE CONTRACTOR M/s Gammon Engineers & Contractors Pvt. Ltd.

AUTHORITY ENGINEER M/s AECOM-Rodic Consultants Pvt. Ltd. (JV)

MAJOR CROSSINGS Bailey Road, Ashok Rajpath

CONNECTIVITY With NH-30, NH-98, Ganga Path & NH-19

AGREEMENT DATE 11.10.2013

APPOINTED DATE 21.10.2013

COMPLETION DATE 31.10.2018

FINANCIAL PROGRESS 834.65 Crores

PHYSICAL PROGRESS:

Pile – 3046/3046 (Nos.), Pile Cap – 682/683 (Nos.), Pier – 680/683 (Nos.), Pier Cap – 675/683 (Nos.),

I-Girder Casting – 3800/4074 (span), I- Girder Erection – 3766/4074 (span), Deck Slab – 665/679

(span)

Page 94: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

ELEVATED CORRIDOR PROJECT PATNA (L-12.27 km)

Page 95: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

CONSTRUCTION OF SOUTH SIDE APPROACH ROAD, 2 LANE WITH PAVED SHOULDER OF DIGHA RAIL-

CUM-ROAD BRIDGE FROM AIIMS TO DIGHA

(NHAI LEFTOVER PORTION) TOTAL LENGTH 10.69 KM

Page 96: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

CONSTRUCTION OF SOUTH SIDE APPROACH ROAD, 2 LANE WITH PAVED SHOULDER OF DIGHA RAIL-

CUM-ROAD BRIDGE FROM AIIMS TO DIGHA

(NHAI LEFTOVER PORTION) TOTAL LENGTH 10.69 KM

ADMINISTRATIVE APPROVAL 1231.06 Crores. (including NHAI Leftover)

AGREEMENT AMOUNT (WORK) Rs. 157.14 Crores.

NAME OF THE CONTRACTOR M/s Gammon Engineers & Contractors Pvt. Ltd.

AUTHORITY ENGINEER M/s AECOM-Rodic Consultants Pvt. Ltd. (JV)

MAJOR CROSSINGS Bailey Road, Ashok Rajpath

CONNECTIVITY Bankipur-Danapur Road & South Side of ROB

AGREEMENT DATE 20.10.2016

COMPLETION DATE 19.04.2018

FINANCIAL PROGRESS 115.19 Crores

PHYSICAL PROGRESS:

Earthwork – 9067/ 9205 (m), Granular Sub-Base – 9067 / 9205 (m), WMM – 9067 /9205 (m), DBM –

8120 / 9205 (m), BC– 8120 / 9205 (m)

Flyover:-

Pile – 14 / 16 (Nos.), Pile Cap – 14 /16 (Nos.), Pier – 14 /16(Nos.)

J.P.Setu connectivity work already completed.

Page 97: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

CONSTRUCTION OF SOUTH SIDE APPROACH ROAD, 2 LANE WITH PAVED SHOULDER OF DIGHA RAIL-

CUM-ROAD BRIDGE FROM AIIMS TO DIGHA

(NHAI LEFTOVER PORTION) TOTAL LENGTH 10.69 KM

Page 98: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

GANGA PATH FROM DIGHA TO DEEDARGANJ AT PATNA

(Length- 21.5 km)

Page 99: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

ADMINISTRATIVE APPROVAL Rs. 3390 Crore

AGREEMENT AMOUNT Rs.1777.3715 Crore

NAME OF THE CONTRACTOR M/s Navayuga Engineering Co. Ltd.

AGREEMENT DATE 23.08.2013

APPOINTED DATE 09.09.2013

MODIFIED COMPLETION DATE EOT under process for 31.12.2019

FINANCIAL PROGRESS 24.64% (Rs. 455.70 Crores ) up to March 18

FEATURES

Length of Elevated Structure – 11.70 km, Embankment length – 8.8 km, Service Road – 8.2

km., Vehicular Underpass – 13, Grade Separator interchange – 01, ROB – 01, Culverts – 13,

FOB – 08 (both side), Toll Plaza – 02, Pedestrian Walkways- 05 km. (river side), Truck

laybys – 01, Bus laybys / Shelter – 16, Re-creation area – 07, Toll Plaza - 07 (including

connecting road), Connecting Road – 07 (LCT Ghat, A.N. Sinha Institute, PMCH, Krishna

Ghat, Kangan Ghat, Gaighat, Patna Ghat)

PHYSICAL PROGRESS

Pile- 397/762, Pile Cap- 74/163, Pier – 71/163, Pier Cap- 71/163, Segment Casting-

694/2431, Launching of Segment- 31. Earth work- 2 Km (in progress)/8.8 km

GANGA PATH (Length- 20.5 km)

Page 100: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Near Kurji Ghat-LCT Ghat Jack-up Barge

Collectrate Ghat Near LCT Ghat

GANGA PATH FROM DIGHA TO DEEDARGANJ AT PATNA

Page 101: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

SIX LANE BIHAR NEW GANGA BRIDGE PROJECT

(Bridge Length -9.76 km, Approach Length- 13 km)

Page 102: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Length of the Project : 22.76 Km. includes 9.76 Km. long Main Bridge

• Start Point : Kachchi Dargah at NH-30 in Patna District

• End Point : Bidupur at NH-103 in Vaishali District

Total Project Cost : INR 4988.4 Cr.

• ADB Assistance : INR 3000.00 Cr.

• Balance Amount (GOB ) : INR 1988.4 Cr.

Name of Civil Contractor : M/s Daewoo & L&T (JV)

Name of Authority Engineer : AECOM & RODIC (JV)

A/A for the Project : Rs. 4291.80 Cr. on 29.07.2015

A/A for Land Acquisition : Rs. 696.60 Cr. on 26.05.2015

Contract Amount

NGO

Agreement Date / Appointment Date

Completion Period / Date of Completion

:

:

Rs.3115.00 Crores

CITIZEN foundation

:10.02.2016 / 16.01.2017

: 4 years / 15.01.2021

Features :-

Major junctions – 06, Grade Separator – 01, 2-lane loop- 04, RAMPS – 08, Flyover- 02, Viaduct

– 06, Rotary – 02, Toll Plaza – 01, Truck lay-byes, Bus-byes and Bus-Shelter, Museum, Traffic

Aid Posts, Vehicle Rescue Posts, Telecom System, Intelligent Traffic System , Weigh-in-motion

Bridge

PHYSICAL PROGRESS of Main Ganga Bridge

Well Curb- 32/67 no. , Well Steining 716.55/3088.5 M, Well Sinking 485.96/3390 M

LA Status :- 243.12 acre out of 313 acre land acquired and balance is under process.

SIX LANE BIHAR NEW GANGA BRIDGE PROJECT

(Bridge Length -9.76 km, Approach Length- 13 km)

Page 103: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

SIX LANE BIHAR NEW GANGA BRIDGE PROJECT

(Bridge Length -9.76 km, Approach Length- 13 km)

Page 104: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Length – : 92.93 Km.

Project Sanctioned Amount- : INR 1408.85 Cr.

JICA Finance Portion (Project cost and

Consultancy cost)

: INR 1216.16 Cr.

Balance Amount to be Budgeted by

MoRTH, GoI (R&R, LA, Utility shifting &

Local Taxes.)

: INR 192.69 Cr.

Name of Civil Contractor : Gayatri Projects Ltd., Hyderabad

Date of Agreement : 20.10.2016

Amount of Agreement : INR 925.874 Crore

Date of Commencement : 20.10.2016

Date of Completion : 19.10.2019 ( 3 years)

STATUS : Work in progress

Financial Progress : 24.75 %

Up to date Physical Progress : 23.00 %

Unencumbered Length : 50.00 Km

C & G -27.28/ 50, Embankment – 21.58/50, Sub-grade – 19.36/50, GSB –

16.85/50, WMM- 16.16 /50, DBM- 15.40/50, BC (Overlay) -5.9/50(all in km)

H.P Culvert – 54/105, 5 in progress, Box Culvert – 62/118, 15 in progress ,

Minor Bridge- 17/33 , 4 in progress, major Bridge – All 6 are in progress, ROB-

out of 4 nos. 1 in Progress.

4-LANING OF NH-82 (GAYA - HISUA - RAJGIR -NALANDA -

BIHARSHARIF SECTION) under JICA

Page 105: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

4-LANING OF NH-82 (GAYA - HISUA - RAJGIR -NALANDA -

BIHARSHARIF SECTION)

Page 106: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

IMPROVEMENT OF MAJOR DISTRICT ROADs

DetailsTotal

(km)

Single Lane

(Km)

Intermediate

Lane (Km)

BLOCK TO DISTRICT

HEADQUARTER CONNECTIVITY491.28 456.74 34.54

SUB-DIVISION TO DISTRICT

HEADQUARTER CONNECTIVITY114.08 38.49 75.59

TOTAL LENGTH (KM) 605.36 495.23 110.13

Page 107: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

IMPROVEMENT OF MAJOR DISTRICT ROADsSUB-DIVISION TO DISTRICT HEADQUARTER CONNECTIVITY

S. No. DistrictSub-

division Name of Road

Length (in Km)

1 2 3 4 5

1 Supaul NirmaliNH-57 (Bhutha Chowk) to Nirmali –Madhepur PWD road via West Kosi

Embankment 6.05

2 SamastipurDalsinghsa

raiSamastipur-Dalsinghsarai Road 22.90

3 Samastipur Patori Samastipur-Sarairanjan-Patori Road 12.25

4East

ChamparanPakridayal Pakridyal-Sirha-Madhuban-Minapur Road 29.00

5 Saran MahrauraChapra - Marhowra Road

(km 8.8236 to 26.3)17.48

6 SiwanMaharajga

njMaharajganj-Tarwara Road 10.40

7 Begusarai Bakhri

Manjhaul Bakhari Roadkm 0 to 3.7, 4.3 to 16

15.40

Manjhaul Bakhari Roadkm 3.7 to 4.3

0.60

Total 114.08

Page 108: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

IMPROVEMENT OF MAJOR DISTRICT ROADsBlocks to District Headquarters Connectivity

S. No. District Block Name Road providing connectivityTotal Length

(in Km)1 2 3 4 5

1

Araria

KursakataAraria Kursakanta Kuwari Sikti Road(up to Kuwari) km 0 to 28

28.0

2 SiktiAraria Kursakanta Kuwari Sikti Road (up to Kuwari) km 29 p to 35p

6.5

3 Palasi Araria Jokihat Palasi Road 18.54

SaharsaNauhatta Panchgachia Nauhatta Road 8.5

5 Sattar Katiya Panchgachia Nauhatta Road 5.06 Patharghat Sour Bazar Pattarghat Road 10.37 Darbhanga Hayaghat Jatmalpur-Hayaghat-Hathauri Road 10.0

8Samastipur

VidyapatinagarVidyapatinagar-Kakarghati-Sarairanjan-NH-103 Road

21.5

9 Ujiyarpur Ujiarpur-Samastipur Road 12.010

West Champaran

Nautan Nautan-Bettiah Road 12.011 Bairia Bairia-Bettiah Road 10.012 Bhaitaha Bhaitana to Chautarwa via Dhanha-Ratwal Bridge 25.013 Gaunaha Narkatiaganj-Gaunaha Road 20.014

East Champaran

Kalyanpur Pipra-Kalyanpur Road 12.015 Tetaria Pakridyal-Sirha-Madhuban-Minapur road 29.0

16 PenharaKrishnanagar NH-104 to Fenhara block head quarter (RWD) road in k.m. 0 to 11.10

11.1

17 Bankatwa Chhouradono-Bankatwa Road 11.018 Adapur Narirgir-Champapur-Adapur road 15.0

Page 109: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

IMPROVEMENT OF MAJOR DISTRICT ROADsBlocks to District Headquarters Connectivity

S. No. District Block Name Road providing connectivityTotal

Length (in Km)

1 2 3 4 519 Saran Lahladpur Sikatia - Paigambarpur Road 15.220 Siwan Darauli Mairwa Darauli Road (0.00 - 19.00) 19.0

21 Lakhisarai PipariaPipariya-Walipur Main Road 2.1Walipur-Lakhisarai Road 7.7

22

Begusarai

Mansur Chak

Dalsinghsarai Kaidrabad Malti Road km 7 to 25,26.662 to 29.00, 29.970 to 30.00, 32.314 to 33.000, 33.867 to 34.00

22.2

Dalsinghsarai Kaidrabad Malti Road km 25.00 to 26.662, 29.00 to 29.970, 30.00 to 32.00, 32.00 to 32.314, 33.00 to 33.867, 34.00 to 36.00

7.8

23 Navkothi Pahsra-Bagras Road 8.0

24 DhandariNH-31 to Katarmala via Nurjummapur-Dhandhari Block Road

8.0

25Bhagalpur

IsmailpurIsmailpur-Chotti Parbatta Road 9.3Naugachhiya-Mahadeopur Ghhat Road 11.9

26 Kharik Kharik-Chorhar Road 6.827

NawadaKashichak Sarkatti More -Subhanpur Road 16.7

28 Meskaur Manjhwey-Meskaur-Tetariya Road 10.0

Page 110: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

IMPROVEMENT OF MAJOR DISTRICT ROADs

Blocks to District Headquarters Connectivity

S. No. District Block Name Road providing connectivityTotal

Length (in Km)

1 2 3 4 5

29 Gaya Gurua Gaya-Chekri via Baijudham Road 10.8

30 Bhojpur TarariNonar-Karath-Tarari-Bihta Road (km 13.0 to 22.0)

4.1

31

Rohtas

Dinara Dinara-Baraw Road 23.3

32 SuryapuraDhangai-Suryapura-Kalyani Road (km 3 to 7 (P)

4.5

33 Thilauthu Sasaram-Thilarathu Road 17.4

34 ArwalSonbhadra Bansi

SuryapurKarpi-Sherpur-Banshi Road 9.0

35 Nalanda KatrisaraiSoiba Belchhi Paroha Manpur Katrisarai Road

12.0

Total 491.3

Page 111: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

• At present 74 nos. Quality Control Laboratories functional under

RCD divisions and circles.

• 4 Flying Squad teams at HQ level to ensure Quality Assurance

through surprise inspection in addition to attended complaints (if

any).

– No. of schemes inspected in 2017-18 - 369 nos.

– No. of schemes inspected in 2018-19 till date - 48 nos.

• Before releasing the allotment to any schemes, its update quality

control reports are verified.

• Quality Control Report are being uploaded on Departmental

Website.

Quality Assurance

Page 112: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

• Special Inspection Drive of SHs & MDRs Roads to

ensure Quality Control as Third Party Independent

Quality Monitor.

• Total 550 nos. of schemes taken for inspection [Road

– 455 nos. ( 4700 km), Bridges - 90 nos. & Buildings –

5 nos.]

• 40 teams comprising one SE/EE and one AE are carrying

out Inspection in their designated Road Division.

• Daily online entry of Inspection data through PMIS is being

done by each team after field inspection.

Quality Assurance

Page 113: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Road Safety under RCD Roads

(a) Black Spot:

Road Category No. of identified

black spots

Status Report

Rectified Under

Rectification

NHNHAI 94 38 56

RCD 7 4 3

SH 9 5 4

MDR 14 10 4

(b) Activities under RCD for Road Safety:

(i) Road Safety Audit done (SH)

Design Stage Construction

Stage

Operational

Stage

Total

414 Km 525 Km 922 Km 1861 Km

Page 114: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Road Safety under RCD Roads

(b) Activities under RCD for Road Safety:

(ii) Road Safety Audit of SHs under process with CRRI,

New Delhi - 2200 Km

(iii) Capacity Building of Engineers on the subject “Road

Safety Audit and other Road Safety related aspects”

- 175 Engineers.

(iv) Mandatory Provision of Road Safety Audit in new

projects (5 km or above) at DPR stage.

(v) Social awakening in children and students through

arranging workshops in schools situated besides

RCD roads – 119 schools.

(vi) Provision of Zebra Crossing and Rumble Strips near

schools on SHs and construction of Foot over

Bridges / Under Pass as required.

Page 115: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

New Proposed Initiatives

1. Provision of Street Lights in Urban stretches for Road Safety.

2. Policy for development of way side amenities.

3. Land pooling policy for Ring Road / Bypass Roads

4. Planning for development of road infrastructure in Patna

Metropolitan area.

5. Policy for extraction of soil from public water bodies for

utilization in road embankment.

6. Online Project Monitoring System (PMIS).

7. Comprehensive financial management system.

8. Bihar Road Research Institute (BRRI).

9. Revenue generation methodology developed through

providing accessibility to Petrol Pump, Hospital & other

commercial institutes.

Page 116: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

Issue for Consideration

• Existing limit on BOS (Bank of Sanction) i.e (3 times of

allocation) may be relaxed by Finance Department for

taking up new road projects in following categories:-

Road transferred from other department required

improvement as per IRC Standards ~1000 Kms.

2 Laning of remaining State Highways ~600 Kms

Replacement of narrow & old bridges

Roads/bridges in compliance of directions received

during Nishchay Yatra.

Road connectivity to all blocks with 2 lane road.

Land acquisition within defined time frame to make

available 100% encumbrance free land to avoid cost

over run.

Page 117: Road Construction Department AT A GLANCEPurnea - Dalkola Kishanganj-West Bengal Boarder 41.000 36.00 3.00 2.00 4 lanning completed 7 57 Muzaffarpur-Purnea 310.000 261.00 49.00 0.00.

THANK YOU