RM Bridge Professional Engineering Software for Bridges of all Types RM Bridge V8i October 2010 TRAINING GETTING STARTED - RM - DIN

description

bridge design software

Transcript of RM E Getting Started DIN

  • RM Bridge Professional Engineering Software for Bridges of all Types

    RM Bridge V8i

    October 2010

    TRAINING GETTING STARTED - RM - DIN

  • RM Bridge

    Training Getting Started RM DIN I

    Bentley Systems Austria

    Contents

    1 General ......................................................................................................................... 1-1

    1.1 The Tutorial ......................................................................................................... 1-2

    1.2 Strucural System .................................................................................................. 1-2

    1.2.1 Support Scheme ............................................................................................... 1-3

    1.2.2 Cross Section ................................................................................................... 1-3

    1.2.3 Tendon Geometry ............................................................................................ 1-4

    1.2.4 Tendon Characteristics .................................................................................... 1-4

    1.2.5 Material Properties........................................................................................... 1-5

    1.3 Loading ................................................................................................................ 1-6

    1.3.1 Permanent Load ............................................................................................... 1-6

    1.3.2 Creep and Shrinkage: ....................................................................................... 1-6

    1.3.3 Additional Load ............................................................................................... 1-6

    1.3.4 Traffic Load ..................................................................................................... 1-6

    2 Starting a Calculation .................................................................................................. 2-7

    2.1 Recalculate ........................................................................................................... 2-7

    2.2 First Results ......................................................................................................... 2-8

    2.3 View Options ..................................................................................................... 2-11

    3 Material for PT Tendons ............................................................................................ 3-12

    3.1 Import of Material.............................................................................................. 3-12

    3.2 Definition of Tendon Geometry ........................................................................ 3-13

    3.3 Definition of Stressing Sequence ...................................................................... 3-19

    4 Load Definition .......................................................................................................... 4-23

    4.1 Load Management ............................................................................................. 4-23

    4.2 Loading Case Definition .................................................................................... 4-25

    5 Construction Schedule ............................................................................................... 5-31

    5.1 Stage Actions and Activation ............................................................................ 5-31

    5.1.1 Definition of Individual Stages ...................................................................... 5-31

    5.1.2 Activation of the New Stages ........................................................................ 5-33

    5.1.3 Calculation Actions for Each Stage ............................................................... 5-34

    6 Traffic ........................................................................................................................ 6-38

    6.1 Traffic Load Definition...................................................................................... 6-38

    6.2 Calculation Actions for Construction Stage ...................................................... 6-44

  • RM Bridge

    Training Getting Started RM DIN II

    Bentley Systems Austria

    7 Load Combinations for Design Code Checks ........................................................... 7-47

    7.1 Combination Table ............................................................................................ 7-47

    7.2 Calculation Actions for Load Combinations ..................................................... 7-48

    8 Design Code Checks .................................................................................................. 8-50

    8.1 Fibre Stress Checks (SLS) ................................................................................. 8-50

    8.1.1 Calculation Actions for Fibre Stress Check................................................... 8-50

    8.2 Ultimate Load Check (ULS) .............................................................................. 8-52

    8.2.1 Calculation Action for Ultimate Load Check ................................................ 8-52

    9 Calculating the Construction Schedule ...................................................................... 9-54

    9.1 Starting the Calculation ..................................................................................... 9-54

    10 Result Presentation Post-Processing ..................................................................... 10-55

    10.1 Numerical Results ............................................................................................ 10-55

    10.1.1 Standard Listings ..................................................................................... 10-55

    10.1.2 Interactive Result Viewing ...................................................................... 10-56

    10.2 Graphical Results ............................................................................................. 10-57

    10.2.1 RMSets .................................................................................................... 10-57

    10.2.2 Diagrams .................................................................................................. 10-59

    10.2.3 Listings .................................................................................................... 10-60

    10.2.4 RMSet in the Construction Schedule ....................................................... 10-61

    10.3 Graphical Result Presentation.......................................................................... 10-62

    10.3.1 Plot ........................................................................................................... 10-62

    10.3.2 Plot Profiles in the Construction Schedule .............................................. 10-65

    10.3.3 Interactive View of stress, force and displacment: .................................. 10-66

    11 Exporting and Storing .............................................................................................. 11-68

    11.1 Project Export .................................................................................................. 11-68

    11.2 Leaving the Program........................................................................................ 11-70

  • RM Bridge General

    Training Getting Started RM DIN 1-1

    Bentley Systems Austria

    1 General

    The following issues will be tackled in the following session in RM :

    Schedule:

    Starting the program

    Description of interface

    Importing material properties and variables

    Definition of material properties

    Definition of cross sections

    Definition of structural system

    Definition of tendon geometry

    Definition of loading

    Definition of traffic

    Definition of one construction stage

    Fibre stress check

    Ultimate load check

    Starting the calculation

    Post processing

    The following description of the necessary program input should be done simultaneously to

    the program evaluation in RM.

  • RM Bridge General

    Training Getting Started RM DIN 1-2

    Bentley Systems Austria

    1.1 The Tutorial

    A two span T-beam girder will be prepared and analysed in the following.

    The example consists of a straight, 60m long girder with a constant cross section. Each span

    is 30m long.

    1.2 Strucural System

    A1 A3 30m

    10x3m

    A2

    10x3m

    30m

    Axis in plan:

    Straight line: Station: 0-60 m

    Axis in elevation: Straight line: Station: 0-60 m

    System numbering: Node numbers (span wise): 101-111-121

    Element number (span wise): 101-110,111-120

    Support elements: 1100, 1200, 1300

  • RM Bridge General

    Training Getting Started RM DIN 1-3

    Bentley Systems Austria

    1.2.1 Support Scheme

    A 1 A2

    X

    Z

    101-110

    A 3

    111-120

    1100 1200 1300

    1.2.2 Cross Section

    8.00 m

    3.50 m 3.40 m

    0.10 m

    1.00 m

    2.0

    0 m

    1.6

    5 m

    0.2

    5 m

    0.1

    0 m

  • RM Bridge General

    Training Getting Started RM DIN 1-4

    Bentley Systems Austria

    1.2.3 Tendon Geometry

    Span 1 101 (9 Tendon) AT=1600mm2, AD=5000mm2 (101-112)

    Span 2 102 (9 Tendon) AT=1600mm2, AD=5000mm2 (109-120)

    1.2.4 Tendon Characteristics

    Friction losses: 0.20

    Wobble factor: 0.20 [Deg/m]

    Wedge slip: 6 mm = 0.006 m

    Allowable stresses in tendon:

    Stressing Before wedge After wedge Before wedge After wedge

    fpk 1860000 0,8 0,7 1488000 1302000

    fp0.1k 1674000 0,9 0,8 1506600 1339200

  • RM Bridge General

    Training Getting Started RM DIN 1-5

    Bentley Systems Austria

    1.2.5 Material Properties

    Material name :C_35/45

    E-Modulus longitudinally 0.33300E+08

    Poisson`s ratio 0.20000

    Shear-Modulus 0.13875E+08

    Coeff. of thermal expansion 0.10000E-04

    Specific weight 25.00000

    Coeff. of consistency 2

    Degree of cement hardening 2

    Water cement ratio 0.40000

    Cement content in concrete 3.00000

    Char.compr. cylinder strength of concrete at 28 days 35000.00000

    Char.compr. cubic strength of concrete at 28 days 45000.00000

    Mean value of concrete compresive strength 43000.00000

    Mean value of axial tensile strength of concrete 3200.00000

    Tension split strenght 2240.00000

    Material name :BSt500-S(A)

    E-Modulus longitudinally 0.20000E+09

    Poisson`s ratio 0.30000

    Shear-Modulus 0.76923E+08

    Coeff. of thermal expansion 0.10000E-04

    Specific weight 78.50000

    Yield strength of reinforcement 0.50000E+06

    Design yield strength of reinforcement 0.43478E+06

    Relaxation class 0

    Material name :Litzen-1570/1770

    E-Modulus longitudinally 0.19500E+09

    Poisson`s ratio 0.30000

    Shear-Modulus 0.75000E+08

    Coeff. of thermal expansion 0.10000E-04

    Specific weight 78.50000

    E-Modulus of prestressing 0.19500E+09

    Stressing limit 0.12560E+07

    Tensile strength of prestressing steel 0.17700E+07

    Design tensile strength of prestressing steel 0.15391E+07

    Relaxation class 0

  • RM Bridge General

    Training Getting Started RM DIN 1-6

    Bentley Systems Austria

    1.3 Loading

    1.3.1 Permanent Load

    Self weight concrete: 25,0 kN/m3

    Permanent load: 30,0 kN/m

    1.3.2 Creep and Shrinkage:

    Creep and Shrinkage will be considered according to EC2 (Austrian interpretation NORM

    B4750).

    1.3.3 Additional Load

    Temperature

    Temperature coefficient: 1e-5 per C

    Temperature gradient: +10C top

    Wind

    Transversal wind: 2.00 kN/m2

    1.3.4 Traffic Load

    To keep the input simple only one load train will be considered (~4*25t truck with uniform

    load on 12m width).

    15 [kN/m]

    200 [kN]

    2 [m] 2 [m]

    15 [kN/m]

    200 [kN]

    2 [m]

  • RM Bridge Starting a Calculation

    Training Getting Started RM DIN 2-7

    Bentley Systems Austria

    2 Starting a Calculation

    After the export from Modeler to Analyzer a lot of relevant definitions such as node coordinates, element, material and cross section assignment are already available.

    Before defining further input data a check of the current situation is suggested. Use the cal-

    culation-function to start a cross-section calculation and structure check. The calculation

    can check the stability of the system and obtain the relevant cross-section parameters (area,

    eccentric and moment of inertia).

    2.1 Recalculate

    Recalc

    ula

    te

    The Recalc-button can

    be found on the top of

    view-window.

    Sta

    rt c

    alc

    ula

    tion

    Since there is no other

    definition than the sys-

    tem data available at

    the moment it is suffi-

    cient to select Cross

    section calculation and

    Structure check at

    this stage.

    To execute press Re-

    calce

  • RM Bridge Starting a Calculation

    Training Getting Started RM DIN 2-8

    Bentley Systems Austria

    Sto

    p

    During the calculation

    the status line (see

    lower edge of RM win-dow) shows the calcu-

    lation progress. The

    Calculation stop info

    shows that the calcula-

    tion has finished, no

    errors and warnings

    appeared.

    2.2 First Results

    The view of the structural system on the screen can be changed using either the buttons at

    the left vertical menu line or using the freehand symbols (rotate, zooming in, zooming

    out,.).

    Select the freehand

    symbol info button

    from the main menu on

    top of the screen to see

    the available zooming

    options.

    Please use the CTRL

    key together with the

    left mouse button when

    drawing the symbol on

    the screen.

    Select

  • RM Bridge Starting a Calculation

    Training Getting Started RM DIN 2-9

    Bentley Systems Austria

    Syste

    m V

    isualis

    ation

    After the system check

    the screen view

    changes with any

    zooming action. The

    structural parts can be

    viewed now, the system

    line is now shifted to

    the correct position (at

    the centre of gravity of

    all cross sections.

    Other available information now are cross-section properties (areas, inertias, ....). In order

    to check these values, the following steps are required:

    Cro

    ss S

    ection

    Select Properties in

    the navigation and

    Cross-Sections in the

    Sub menu to view all

    cross-sections used in

    the project.

  • RM Bridge Starting a Calculation

    Training Getting Started RM DIN 2-10

    Bentley Systems Austria

    Cro

    ss S

    ection -

    Info

    All values can be

    checked here, like

    Moment of Inertia,

    cross section area,

    shear area. Please note

    that modifications can

    be done here, but it is

    recommended to do

    that in Modeler in order to have a consis-

    tent data base.

  • RM Bridge Starting a Calculation

    Training Getting Started RM DIN 2-11

    Bentley Systems Austria

    2.3 View Options

    In addition to the possibilities shown above (zoom in, zoom out, move,.) also other view

    options are available.

    Vie

    ws

    Pressing the right

    mouse button whilst the

    mouse cursor is in the

    view area the following

    menu pops up.

    Select View Options.

    Vie

    w O

    ptions

    Several possibilities are

    given to change the

    point of view of your

    construction. For ex-

    ample; tick Draw cross

    section and Draw ele-

    ment bodies and you

    get a complete 3D-

    view, including your

    defined cross section.

    Cofirm

  • RM Bridge Material for PT Tendons

    Training Getting Started RM DIN 3-12

    Bentley Systems Austria

    3 Material for PT Tendons

    3.1 Import of Material

    All materials that are defined in Modeler will be imported from the standard material da-tabase to the project directory during an export from Modeler to Analyzer. Due to the fact that the tendon definition has to be added in Analyzer the material used for the ten-dons has to be imported from the available material database manually.

    Import

    of M

    ate

    ria

    l

    Select File in the

    main menu and Re-

    load Default Proper-

    ties to open the listing

    of available standards

    and codes.

    Import

    of M

    ate

    ria

    l

    Select the wanted stan-

    dard/code and double

    click (name turns red)

    the wanted material

    (left column for De-

    fault database).

    Use to ap-

    ply the selected mate-

    rial to the current direc-

    tory.

  • RM Bridge Material for PT Tendons

    Training Getting Started RM DIN 3-13

    Bentley Systems Austria

    3.2 Definition of Tendon Geometry

    The last missing part of the structural system are the tendons. The tendon creation and ge-

    ometry assignment is done in the following:

    Tendon D

    ata

    Select Structure,

    Tendons to open the

    corresponding input

    window.

    Tendon G

    eom

    etr

    y

    All defined tendons

    together with the prop-

    erties are shown in the

    upper listing (empty at

    the moment). The

    lower listing will show

    the element assignment

    and the geometry defi-

    nition.

    Select Insert after above the upper listing to open the following input window:

  • RM Bridge Material for PT Tendons

    Training Getting Started RM DIN 3-14

    Bentley Systems Austria

    Tendon -

    Pro

    pe

    rtie

    s

    The tendon group is

    defined here.

    In this example the

    tendon 101 will be for

    the PT in stage 1.

    9 tendons will be in this

    group, please define the

    area for one tendon, for

    one duct, Beta (see

    Manuel) and friction

    coefficient.

    Confirm

    Assig

    nm

    en

    t

    First the element for

    tendon 101 will be de-

    fined. Select Assign-

    ment.

    Select the Insert after button above the lower listing to open the input window.

    Assig

    nm

    en

    t

    Tendon 101 will be

    defined for the ele-

    ments 101 to 112, this

    corresponds to the acti-

    vation of the first stage.

    Confirm

    Geom

    etr

    y

    Change to Geometry

    definition in the lower

    listing.

  • RM Bridge Material for PT Tendons

    Training Getting Started RM DIN 3-15

    Bentley Systems Austria

    The numeric input can be combined with an immediate graphic check. Select the Info

    button above the lower listing to get both, the numeric and graphic input window.

    Tendon g

    eom

    etr

    y

    The selected elements

    (101 to 112) are shown

    in the graphic field to-

    gether with the cross

    sections.

    Gra

    phic

    The input can be con-

    trolled by toggling be-

    tween cross-section and

    general view.

    Select the Insert after button above the listing at the bottom.

    Tendoon G

    eom

    etr

    y

    The frame shown at the left allows

    the definition of:

    - position of tendon inside the elements

    - tangent of tendon at loca-tion.

    x/l is the position inside the

    element, the eccentricities ey

    and ez define the offset.

    Confirm

    Select the Insert after button above the listing at the bottom to add a second line.

  • RM Bridge Material for PT Tendons

    Training Getting Started RM DIN 3-16

    Bentley Systems Austria

    Tendoon G

    eom

    etr

    y

    Please see the input at

    the left to define the

    second input line. We

    use the defined stress

    point SP-B as refer-

    ence for the second

    geometry point.

    Confirm

    Continue to select the Insert after button above the listing at the bottom to add all other

    geometry points for the tendon geometry.

    Input T

    able

    Tendon Number: 101

    Type: Type:

    Normal Normal Normal Normal Normal

    Ref. Elem.: 101 104 107 110 112

    CS Pnt: - SP_B SP_B - -

    x/l: 0 0 1 1 1

    eY [m]: 0.00 0.25 0.20 0.00 0.00

    eZ [m]: 0.00 0.00 0.00 0.00 0.00

    Relative to: Elem CS Pnt. CS Pnt. Elem Elem

    Alpha1: Frei Value Value Value Free

    Value: - 0.00 0.00 0.00 -

    Alpha2: Frei Value Value Value Free

    Value: - 0.00 0.00 0.00 -

    Relative to: Elem Elem Elem Elem Elem

  • RM Bridge Material for PT Tendons

    Training Getting Started RM DIN 3-17

    Bentley Systems Austria

    Tendon -

    Pro

    pe

    rtie

    s

    The second tendon

    group (with number

    102) will be for the

    second stage.

    Again the necessary

    properties are defined.

    Confirm

    Assig

    nm

    en

    t

    Switch to Assign-

    ment to define the

    element for tendon 102.

    Select the insert after button above the lower listing the following input window comes

    up:

    Tendon A

    ssig

    nm

    en

    t

    The tendon 102 will be

    assigned to the ele-

    ments 109 to 120.

    Confirm

    Geom

    etr

    y

    Change to Geometry

    for the geometry defini-

    tion.

  • RM Bridge Material for PT Tendons

    Training Getting Started RM DIN 3-18

    Bentley Systems Austria

    Continue to use the Insert after button to add all necessary input lines in the right or-

    der.

    Input T

    able

    Tendon No.: 102

    Type Type

    Normal Normal Normal Normal Normal

    Ref. Elem.: 109 110 113 117 120

    C Pkt: - - ST_B ST_B -

    x/l: 0 1 1 1 1

    eY [m]: 0.00 0.00 0.20 0.25 0.00

    eZ [m]: 0.00 0.00 0.00 0.00 0.00

    Relative to: Elem Elem CS Pnt CS Pnt Elem

    Alpha1: Frei Value Value Value Free

    Value: - 0.00 0.00 0.00 -

    Alpha2: Frei Value Value Value Free

    Value: - 0.00 0.00 0.00 -

    Relative to: Elem Elem Elem Elem Elem

  • RM Bridge Material for PT Tendons

    Training Getting Started RM DIN 3-19

    Bentley Systems Austria

    3.3 Definition of Stressing Sequence

    Once the tendon geometry is defined for all 3 tendon groups the stressing sequence will

    follow (initial stressing, wedge slip,.).

    All actions on the tendons are done in this table, please consider the right order!

    Define the following actions:

    1. Stress tendon group 101 with factor 1.06 (6% short term overstress) at one (left) end.

    2. Losses due to wedge slip at the same (left) end of 6 mm.

    3. Stress the tendon group 101 at the right end again with a factor of 1.06.

    4. Losses due to wedge slip at the same (right) end of again 6 mm.

    Constr

    uction s

    chedule

    Select Schedule from

    the navigation tree and

    Stages in the sub

    menu.

    Tendon

    Select Tendon to

    open the input window

    for tendon actions.

    Select Insert after to define the first stressing action.

  • RM Bridge Material for PT Tendons

    Training Getting Started RM DIN 3-20

    Bentley Systems Austria

    Tendon A

    ctio

    n

    As described above the

    tendon 101 is stressed,

    see input at the left.

    The corresponding im-

    pact on the structure

    will be made available

    in the Stress label

    CS1.

    Confirm

  • RM Bridge Material for PT Tendons

    Training Getting Started RM DIN 3-21

    Bentley Systems Austria

    The next two actions refer to the right end of the tendon 101. The actions are similar to the

    first ones.

    Select Insert after to define the new stressing action. Please define the data as shown in

    the table below:

    Table

    Stress/Release: Stress/Release:

    PREL - PRER -

    Force/Factor: Factor - Factor -

    Wedge slip: - WEDL - WEDR

    Tendon: 101 101 101 101

    Fact of SIGmax: 1.06 1 1

    Wedge slip: - 0.006 - 0.006

    Stress label: CS1 CS1 CS1 CS1

    Description: - - - -

    Select Insert after button to define the stressing sequence for tendon 102.

    Table

    Stress/Release: Stress/Release:

    PRER -

    Force/Factor: Factor -

    Wedge slip: - WEDR

    Kabel: 102 102

    Fact of SIGmax: 1 1

    Wedge slip: - 0.006

    Stress label: CS2 CS2

    Description: - -

    Str

    essin

    g A

    ctions

    The screen shot at the

    left shows all necessary

    stressing actions on

    both tendons (101 and

    102).

  • RM Bridge Material for PT Tendons

    Training Getting Started RM DIN 3-22

    Bentley Systems Austria

    A graphical control is available when using the Info button on top. Select the wanted

    line in the input table and hit the button to see the corresponding graphic.

    Tendon A

    ction

    The graphic shows the

    normal force in the

    tendon together with all

    losses due to friction,

    wobble and geometry.

    The initial stressing as

    well as the losses due

    to wedge slip can be

    viewed.

    Tendon A

    ction

    Furthermore it is possi-

    ble to see the influences

    on the tendon force due

    to further actions on the

    structure (creep, other

    PT, other loads,...).

    Not available at this

    stage of our example.

  • RM Bridge Load Definition

    Training Getting Started RM DIN 4-23

    Bentley Systems Austria

    4 Load Definition

    Each load is defined in an individual loading case.

    An automatic accumulation of all loading case results is available using the Load man-ager facilities.

    The loading results can be combined to create needed load combinations.

    These created combinations can be combined with other combinations to create total envelopes.

    Multiplication (safety) factors can be assigned to any result combination easily using a combination table.

    4.1 Load Management

    Constr

    . S

    ched.

    Select Schedule in

    the navigation tree and

    Load Definition in

    the sub menu to open

    the relevant input win-

    dow.

    LM

    ana

    ge

    Select LManage in

    the sub menu to see the

    input table for the Load

    Management.

    select

  • RM Bridge Load Definition

    Training Getting Started RM DIN 4-24

    Bentley Systems Austria

    Select the Insert after button to define the first load type group. (G1).

    LM

    ana

    ge

    G1

    All loading cases iden-

    tified with the LoadInfo

    G1 will be accumu-

    lated in the summation

    loading case G1 and

    DL-SUM (DL-Sum

    contains all permanent

    load, G1 will contain

    the summation of self

    weight only).

    Confirm

    Select the Insert after button above the upper table to define the first input (G1).

    Table

    Load Manag.: Load Manag.:

    G1 G2 PT CS

    Load Case 1: G1 G2 PT CS

    Type: Total Total Total Total

    Load Case 2: DL-SUM DL-SUM DL-SUM DL-SUM

    Type: Total Total Total Total

    Load Case 3: - - - -

    Type: Total Total Total Total

  • RM Bridge Load Definition

    Training Getting Started RM DIN 4-25

    Bentley Systems Austria

    4.2 Loading Case Definition

    Constr

    . S

    ched.

    Select Schedule in

    the main menu and

    Load Definition in

    the submenu to open

    the load input.

    Select Load Case

    Definition in the lower

    table to see the relevant

    tables for load input.

    Select the Insert after button above the upper listing to open the first loading case (G1-

    101).

    LC

    ase

    G1

    Loading Case G1-101

    will be used now for

    the self weight defini-

    tion of the main girder

    at the first construction

    stage. Note, if Load

    only elements, acti-

    vated in current stage

    is chosen, no considera-

    tion for element load-

    ing needs to be done.(Is

    automatically done by

    activation of the ele-

    ments.)

    Use to switch the Duration Type (Permanent or Non-Permanent).

    Select the pull down arrow at the right of the Load Manag. input field to open the fol-

    lowing input.

  • RM Bridge Load Definition

    Training Getting Started RM DIN 4-26

    Bentley Systems Austria

    LM

    ana

    ge -

    Lis

    ting

    Assign the new loading

    case to one of the exist-

    ing groups of the Load

    Management. (G1, G2,

    ..). This information is

    used to add the Lcase

    results to the result ac-

    cumulation.

    Confirm

    LC

    ase L

    isting

    The Loading Case is

    added in the upper list-

    ing.

    The actually load is

    defined in the lower

    listing.

    Select the Insert after button above the lower listing to the define the loading for the

    first loading case (G1-101).

    Lo

    ad

    da

    ta

    Select Uniform load

    and Self weight-just as

    load to define the nec-

    essary load.

    Confirm

  • RM Bridge Load Definition

    Training Getting Started RM DIN 4-27

    Bentley Systems Austria

    Self W

    eig

    ht

    Define the elements to

    be considered for the

    self weight load. The

    direction vector is sup-

    posed to point in the

    negative vertical global

    direction. Note, all

    elements are chosen

    because Load only

    elements, activated in

    current stage is cho-

    sen in the upper table.

    Confirm

    All other loadings are defined in the same way, please see the following tables.

    Select Insert after above the upper listing to define one more Loading Case. Note, tick

    Load only elements, activated in current stage!

    Table

    Name: Name:

    G1-101 G1-102

    Duration-Type: P P

    Loadmanag.: G1 G1

    Description: Self weight for

    stage1 Self weight for

    stage2

    Select Insert after above the upper listing to define one more Loading Case.

    Table

    Name: Name:

    G2-299

    Duration-Type: P

    Loadmanag.: G2

    Description: Additional permanent load

    Select Insert after above the upper listing to define two more Loading Cases.

    Table

    Name: Name:

    PT-501 PT-502

    Duration-Type: P P

    Loadmanag.: PT PT

    Description: Pre-stressing

    for stage1 Pre-stressing

    for stage2

    Select Insert after above the upper listing to define three more Loading Cases.

  • RM Bridge Load Definition

    Training Getting Started RM DIN 4-28

    Bentley Systems Austria

    Table

    Name: Name:

    CS-601 CS-602 CS-699

    Duration-Type: P P P

    Loadmanag.: CS CS CS

    Description: Creep and Shrinkage

    stage1

    Creep and Shrinkage

    stage2

    Creep and Shrinkage for

    t=oo

    Select Insert after above the upper listing to define two more Loading Cases..

    Table

    Name: Name:

    LC-TG LC-W

    Duration-Type: NP NP

    Loadmanag.: - -

    Description: Temperature-

    gradient (+10C)

    Wind

    Definition of the actual loading for the created loading cases. Select the relevant loading

    case in the upper listing and use the Insert after button above the lower listing to define

    the loading.

    See the following table for the load input.

    Select the Insert after button above the lower listing to define the following loading.

    LC

    S

    elf W

    eig

    ht

    Loading Case: Loading Case:

    G1-101 G1-102

    Insert: Lower Listing Lower Listing

    Actual loading: Uniform load Uniform load

    Loading type: Self Weight Self Weight

    Confirm: OK OK

    From: 101 101

    To: 120 120

    Step: 1 1

    Rx: - -

    Ry: -1 -1

    Rz: - -

    Type: Real length Real length

    Confirm: OK OK

    All elements are se-

    lected because of

    Load only elements,

    activated in current

    stage is activated.

    (see page 4-25). It is

    also possible to only

    define the elements

    from 101 to 112 for

    the loadcase G1-101.

  • RM Bridge Load Definition

    Training Getting Started RM DIN 4-29

    Bentley Systems Austria

    Chose a loading case in the upper listing and select the Insert after for the lower listing

    to define the other loading.

    LC

    p

    erm

    anent lo

    ad

    Loading case: Loading case:

    G2-299

    Insert: Lower Listing

    Actual load: Uniform load

    Loading type: Concentric load

    Confirm: OK

    From: 101

    To: 120

    Step: 1

    Qx: -

    Qy: -30.0

    Qz: -

    Type1: Global

    Type2: Real length

    Type3: Load/Length

    unit

    Confirm: OK

    Choose a loading case in the upper listing and select the Insert after for the lower list-

    ing to define the other loading.

    LC

    P

    re-s

    tressin

    g

    Loading case: Loading case:

    PT-501 PT-502

    Insert: Lower Listing Lower Listing

    Actual load: Pre-

    stressing Pre-

    stressing

    Loading type: Stress tendon Stress tendon

    Confirm: OK OK

    From: 101 102

    To: 101 102

    Step: 1 1

    Type: Increment -

    Force Increment -

    Force

    Confirm: OK OK

    Chose a loading case in the upper listing and select the Insert after for the lower listing

    to define the other loading.

    LC

    C

    &S

    Loading case:

    Loading case: CS-601 CS-602 CS-699

    Insert: Lower Listing not necessary

    Lower Listing not necessary

    Lower Listing not necessary

  • RM Bridge Load Definition

    Training Getting Started RM DIN 4-30

    Bentley Systems Austria

    Chose a loading case in the upper listing and select the Insert after for the lower listing

    to define the other loading.

    Additio

    nal P

    erm

    anent Load

    Loading case: Loading case:

    LC-TG

    Loading case: LC-W

    Insert: Lower Listing Insert: Lower Listing

    Actual Load: Initial

    Stress/Strain Actual Load: Uniform Load

    Load Type: Temperature

    load Load Type: Concentric load

    Confirm: OK Confirm: OK

    From: 101 From: 101

    To: 120 To: 120

    Step: 1 Step: 1

    Alpha (1/C): 1e-005 Qx: -

    DT-G (C): - Qy: -

    DT-Y (C): 10.0 Qz: 2.00

    H-Y (m): Global Typ1: Global

    DT-Z (C): - Typ2: Real Length

    H-Z (m): - Typ3: Qz multiply

    Load with Cs height

    Confirm: OK Confirm: OK

  • RM Bridge Construction Schedule

    Training Getting Started RM DIN 5-31

    Bentley Systems Austria

    5 Construction Schedule

    Everything that is needed for a erection sequence simulation is grouped in this menu. Exist-

    ing elements are activated according to the defined schedule.

    The upper listing shows all available construction stages, the correct order is important!

    The lower listing shows all elements activated in this construction stage. Previously and not

    yet activated elements are not shown. Furthermore the activation age of the new elements is

    shown.

    5.1 Stage Actions and Activation

    5.1.1 Definition of Individual Stages

    Constr

    . S

    tages

    Select Schedule and

    Stages to define a

    new stage.

    Select Insert after above the upper listing to create a new construction stage.

    Constr

    . S

    tage

    Select a number or a

    short name for the new

    stage (Stage1).

    confirm

  • RM Bridge Construction Schedule

    Training Getting Started RM DIN 5-32

    Bentley Systems Austria

    Select Insert after above the upper listing to create all other new construction stages.

    Table

    Name: Name:

    Stage1 Stage2 Stage99 AddLoads

    List: - - - -

    Duration: - - - -

    Description: Stage 1 Stage 2 Stage 3 Add. Loads

  • RM Bridge Construction Schedule

    Training Getting Started RM DIN 5-33

    Bentley Systems Austria

    5.1.2 Activation of the New Stages

    Constr

    . S

    tage

    For each new stage the

    corresponding elements

    for activation will be

    defined now (lower

    listing). Select stage 1

    in the upper listing.

    Activation

    Select Insert after above the lower listing to activate the elements for stage 1.

    Activation

    For stage 1 the ele-

    ments 101 to 112 will

    be activated. Not to

    forget the support ele-

    ments 1100 and 1200!

    Confirm

    Select Insert after above the lower listing to activate the elements for stage 2, select

    stage 2 in the upper listing first!

    Activation

    Constr. Stage: Constr. Stage:

    Stage1 Stage1

    Insert: Lower Listing Lower Listing

    Type: Active Active

    From: 101 1100

    To: 112 1200

    Step: 1 100

    Age: 14 14

    ts: - -

    Confirm: OK OK

  • RM Bridge Construction Schedule

    Training Getting Started RM DIN 5-34

    Bentley Systems Austria

    Activation

    Constr. Stage: Constr. Stage:

    Stage2 Stage2

    Insert: Lower Listing Lower Listing

    Type: Active Active

    From: 113 1300

    To: 120 1300

    Step: 1 100

    Age: 14 14

    ts: - -

    Confirm: OK OK

    5.1.3 Calculation Actions for Each Stage

    Action

    Change from Activa-

    tion to Schedule Ac-

    tion.

    Select Insert after in the lower listing to define the first action for stage 1 (select stage

    1 in upper listing first!).

  • RM Bridge Construction Schedule

    Training Getting Started RM DIN 5-35

    Bentley Systems Austria

    Actions

    Several groups for ac-

    tions are available.

    Each one contains the

    available action for the

    specific group.

    You remember the

    Load manager? The

    loading cases defined

    there need to be initial-

    ised (set results in this

    sum loading cases to

    0) first. Do this as a

    first step at the begin of

    the calculation. Select

    the group

    LC/Envelope actions

    and the function

    LcInit.

    Confirm

    Actions

    The input field Out-

    put1 is used to define

    the loading case G1.

    Confirm

    Select Insert after above the lower listing to define all other actions for this first stage.

  • RM Bridge Construction Schedule

    Training Getting Started RM DIN 5-36

    Bentley Systems Austria

    Actions

    Sta

    ge1

    Constr. Stage: Constr. Stage:

    Stage1 Stage1 Stage1 Stage1 Stage1

    Insert: Untere Liste Untere Liste Untere Liste Untere Liste Untere Liste

    Action: LC/Envelope Actions

    LC/ En-velope Ac-

    tions

    LC/ En-velope Ac-

    tions

    LC/ En-velope Ac-

    tions

    LC/ En-velope Ac-

    tions

    Type: LcInit LcInit LcInit LcInit LcInit

    Confirm: OK OK OK OK OK

    Input 1: - - - - -

    Input 2: - - - - -

    Input 3: - - - - -

    Output 1: G1 G2 PT CS DL-SUM

    Output 2: - - - - -

    Delta-T: - - - - -

    Description: - - - - -

    Confirm: OK OK OK OK OK

    Actions

    Sta

    ge1

    Constr. Stage: Constr. Stage:

    Stage1 Stage1 Stage1 Stage1 Stage1

    Insert: Lower Listing Lower Listing Lower Listing Lower Listing Lower Listing

    Action: Calcula-tion (Static)

    Calcula-tion (Static)

    Calcula-tion (Static)

    Calcula-tion (Static)

    Calcula-tion (Static)

    Type: Calc Stress Calc Grout Creep

    Confirm: OK OK OK OK OK

    Input 1: G1-101 - PT-501 101 1

    Input 2: - CS1 - - -

    Input 3: - - - - -

    Output 1: - - - - CS-601

    Output 2: * - * - *

    Delta-T: - - - - 28

    Description: - - - - -

    Confirm: OK OK OK OK OK

    Select Insert after to define further actions for the stages.

    Actions

    Sta

    ge2

    Constr. Stage: Constr. Stage:

    Stage2 Stage2 Stage2 Stage2 Stage2

    Insert: Lower Listing Lower Listing Lower Listing Lower Listing Lower Listing

    Action: Calcula-tion (Static)

    Calcula-tion (Static)

    Calcula-tion (Static)

    Calcula-tion (Static)

    Calcula-tion (Static)

    Type: Calc Stress Calc Grout Creep

    Confirm: OK OK OK OK OK

    Input 1: G1-102 - PT-502 102 1

    Input 2: - CS2 - - -

    Input 3: - - - - -

    Output 1: - - - - CS-602

    Output 2: * - * - *

    Delta-T: - - - - 28

    Description: - - - - -

    Confirm: OK OK OK OK OK

    Select Insert after to define further actions for the stages.

  • RM Bridge Construction Schedule

    Training Getting Started RM DIN 5-37

    Bentley Systems Austria

    Actions

    Sta

    ge99

    Constr. Stage: Constr. Stage:

    Stage99 Stage99

    Insert: Lower Listing Lower Listing

    Action: Calcula-tion (Static)

    Calcula-tion (Static)

    Type: Calc Creep

    Confirm: OK OK

    Input 1: G2-299 1

    Input 2: - -

    Input 3: - -

    Output 1: - CS-699

    Output 2: * *

    Delta-T: - 10000

    Description: - -

    Confirm: OK OK

    Select Insert after to define further actions for the stages.

    Actions

    AddL

    oads

    Constr. Stage: Constr. Stage:

    AddLoads AddLoads AddLoads AddLoads

    Insert: Lower Listing Lower Listing Lower Listing Lower Listing

    Action: Calcula-tion (Static)

    Calcula-tion (Static)

    LC/envelope actions

    LC/ en-velope ac-

    tions

    Type: Calc Calc SupInit SupAndXLc

    Confirm: OK OK OK OK

    Input 1: LC-TG LC-W - Wind.sup

    Input 2: - - - LC-W

    Input 3: - - - -

    Output 1: - - Wind.sup -

    Output 2: * * - *

    Delta-T: - - - -

    Description: - - - -

    Confirm: OK OK OK OK

    All kind of graphics will be explained in chapter 12.

  • RM Bridge Traffic

    Training Getting Started RM DIN 6-38

    Bentley Systems Austria

    6 Traffic

    6.1 Traffic Load Definition

    The traffic load in this example does not correspond with any specific design code, we are

    explaining the principles here.

    Constr

    . S

    chedule

    - L

    an

    e

    Select Schedule in

    the navigation tree and

    Load Definition in

    the sub menu.

    Select Traffic Lanes

    in the menu at the bot-

    tom to see the listing of

    traffic lanes (empty).

    Select

    Select Insert after above the upper listing to define the first lane.

    La

    ne

    1

    Select Number 1 for

    the first lane.

    Confirm

  • RM Bridge Traffic

    Training Getting Started RM DIN 6-39

    Bentley Systems Austria

    Select Insert after above the lower listing to define the position of lane 1.

    La

    ne

    1

    MACROs are available

    for input of lanes for

    element series. The

    listing at the left shows

    all these Macros (unit

    loads for the influence

    line calculation are

    established according

    to the vehicle posi-

    tions).

    Select Macro2 for

    Lanes that are eccentric

    to the main girder.

    Confirm

    La

    ne

    1

    The empty listing for

    Macro 2 appears.

    Click Insert after to

    define the element se-

    ries.

    Insert

    La

    ne

    1

    Define the values as

    shown at the left.

    This input shows an

    eccentricity of -2m for

    the lane 1 along the

    elements 101 to 120.

  • RM Bridge Traffic

    Training Getting Started RM DIN 6-40

    Bentley Systems Austria

    Confirm

    Confirm the input

    Close the input window .

    La

    ne

    1

    The new lane is shown

    in the upper listing. The

    corresponding unit load

    positions are shown in

    the lower listing.

    Confirm

    The second lane is nearly the same, except the offset is +2m.

    La

    ne

    2

    Define the values as

    shown at the left.

    This input shows an

    eccentricity of +2m for

    the lane 1 along the

    elements 101 to 120.

    Confirm

    Confirm input with .

    Close input with .

    The lane definitions are now complete.

  • RM Bridge Traffic

    Training Getting Started RM DIN 6-41

    Bentley Systems Austria

    Next Step will be the load train definition.

    LT

    rain

    Select Load trains to

    open the input window.

    Select

    All load train are shown in the upper listing. The lower listing shows the details for each

    load train.

    Select Insert after above the upper listing to define the first load train.

    LT

    rain

    Default proposal is ok

    1.

    Note: some codes have

    different factors for

    minimum and maximum

    traffic load evaluation.

    Confirm

  • RM Bridge Traffic

    Training Getting Started RM DIN 6-42

    Bentley Systems Austria

    LT

    rain

    In our example the traf-

    fic load consist of uni-

    form load of 15kN/m

    and two concentrated

    loads of 200kN each.

    Two meters before and

    2m after the conc.

    Loads no uniform load

    will be applied. See

    load scheme at the left.

    Select Insert after above the lower listing to define the load train as discussed.

    LT

    rain

    First define the uniform

    load (-15.0 kN/m). The

    actual load will be ap-

    plied according to the

    influence line.

    Confirm

    Select Insert after above the lower listing to define all other loads for this load train.

    15 [kN/m]

    200 [kN]

    2 [m] 2 [m]

    15 [kN/m]

    200 [kN]

    2 [m]

    Input 1

    Input 2

    Input 3

    Input 4

    Input 5

  • RM Bridge Traffic

    Training Getting Started RM DIN 6-43

    Bentley Systems Austria

    Table

    Load train: Load train:

    1 1 1 1 1

    Insert: Lower Listing Lower Listing Lower Listing Lower Listing Lower Listing

    Q [kN/m]: -15.0 - - - -15.0

    F [kN]: - - -200.0 -200.0 -

    Input 1: - - - - -

    Input 2: Free

    Length - - -

    Free

    Length

    L-from: - 2 2 2 -

    L-to: - 2 2 2 -

    L-step: - 2 2 2 -

    Confirm: OK OK OK OK OK

  • RM Bridge Traffic

    Training Getting Started RM DIN 6-44

    Bentley Systems Austria

    6.2 Calculation Actions for Construction Stage

    Constr

    . S

    chedule

    Select Schedule and

    Stages and Activa-

    tions to define a new

    construction stage for

    the traffic load calcula-

    tion.

    Select Insert to define a new stage.

    Table

    Name: Name:

    TRAFFIC

    List: -

    Duration.: -

    Description: Traffic load

    No activation necessary (everything is already active).

    Action

    Select Schedule Ac-

    tion to define the nec-

    essary input

  • RM Bridge Traffic

    Training Getting Started RM DIN 6-45

    Bentley Systems Austria

    Select Insert after above the lower listing to define the needed actions for traffic load

    calculation.

    Table

    Constr. stage: Constr. stage:

    TRAFFIC TRAFFIC TRAFFIC

    Insert: Lower Listing Lower Listing v

    Action: LC/Envelope action

    LC/Envelope action

    LC/Envelope action

    Type: SupInit SupInit SupInit

    Confirm: OK OK OK

    Input 1: - - -

    Input 2: - - -

    Input 3: - - -

    Output 1: Lane1.sup Lane2.sup Traffic.sup

    Output 2: - - -

    Delta-T: - - -

    Description: - - -

    Confirm: OK OK OK

    Select Insert after above the lower listing to define the needed actions for traffic load

    calculation.

    Table

    Constr. stage: Constr. stage:

    TRAFFIC TRAFFIC TRAFFIC TRAFFIC

    Insert: Lower Listing Lower Listing Lower Listing Lower Listing

    Action: Calcula-tion (Static)

    Calcula-tion (Static)

    Calcula-tion (Static)

    Calcula-tion (Static)

    Type: Infl Infl LivelL LivelL

    Confirm: OK OK OK OK

    Input 1: 1 2 1 2

    Input 2: - - 1 1

    Input 3: - - - -

    Output 1: lane0001.inf lane0002.inf Lane1.sup Lane2.sup

    Output 2: * * - -

    Delta-T: - - - -

    Description: - - - -

    Confirm: OK OK OK OK

    Table

    Constr. stage: Constr. stage:

    BAVERK BAVERK

    Insert: Lower List Lower List

    Action: LC/Envelope action

    LC/Envelope action

    Type: SupAddSup SupAddSup

    Confirm: OK OK

    Input 1: Traffic.sup Traffic.sup

    Input 2: Lane1.sup Lane2.sup

    Input 3: - -

    Output 1: - -

    Output 2: * *

    Delta-T: - -

    Description: - -

    Confirm: OK OK

  • RM Bridge Traffic

    Training Getting Started RM DIN 6-46

    Bentley Systems Austria

  • RM Bridge Load Combinations for Design Code Checks

    Training Getting Started RM DIN 7-47

    Bentley Systems Austria

    7 Load Combinations for Design Code Checks

    7.1 Combination Table

    Constr

    . S

    ched.-

    Com

    b.

    Select Schedule and

    Load Definition to

    open the load input

    definitions.

    Select Load Combina-

    tion to see the combi-

    nation table.

    Select Insert after to define iput tin the combination table.

    Com

    bin

    ations

    Select Load Case and

    the corresponding load

    group (G1 Self

    weight).

    Using the combination

    law SupAddLc result

    from the selected load-

    ing cases will added to

    create a load combina-

    tion.

    Confirm

  • RM Bridge Load Combinations for Design Code Checks

    Training Getting Started RM DIN 7-48

    Bentley Systems Austria

    Select Insert after to define the following combination table input.

    Table

    Comb. Table: Comb. Table:

    Result Type: LCase LCase LCase LCase

    Name: G1 G2 PT CS

    Comb. Law: SupAddLc SupAddLc SupAddLc SupAddLc

    favourable I: 1 1 1 1

    unfavourable I: 1 1 1 1

    favourable II: 1.35 1.35 1 1

    unfavourable II: 1.35 1.35 1 1

    favourable III: - - - -

    unfavourable III: - - - -

    Confirm: OK OK OK OK

    Table

    Comb. Table: Comb. Table:

    Result Type: LCase superpo-

    sition superpo-

    sition

    Name: LC-TG Wind.sup Traffic.sup

    Comb. Law: SupAddLc SupAddSup SupAddSup

    favourable I: 1 1 1

    unfavourable I: 1 1 1

    favourable II: 0.8 0.8 1.5

    unfavourable II: 0.8 0.8 1.5

    favourable III: - - -

    unfavourable III: - - -

    Confirm: OK OK OK

    7.2 Calculation Actions for Load Combinations

    Constr

    . S

    ched.

    Select Schedule and

    Stages to open the

    listing of stages.

    Select Insert after above the upper listing to define a new stage where the load combi-

    nations will be defined.

  • RM Bridge Load Combinations for Design Code Checks

    Training Getting Started RM DIN 7-49

    Bentley Systems Austria

    Table

    Name: Name:

    Comb

    List file: -

    Duration.: -

    Description: Load Combination

    Action

    Select Schedule Ac-

    tions to open to start

    the action input for load

    combination.

    Select

    Select Insert after above the lower listing to open the input window.

    Table

    Constr. Stage: Constr. Stage:

    Comb Comb

    Insert: Lower List Lower List

    Action: LC/envelope action

    LC/envelope action

    Type: SupComb SupComb

    Confirm: OK OK

    Input 1: 1 2

    Input 2: - -

    Input 3: - -

    Output 1: Comb1.sup Comb2.sup

    Output 2: - -

    Delta-T: - -

    Description: - -

    Confirm: OK OK

  • RM Bridge Design Code Checks

    Training Getting Started RM DIN 8-50

    Bentley Systems Austria

    8 Design Code Checks

    8.1 Fibre Stress Checks (SLS)

    8.1.1 Calculation Actions for Fibre Stress Check

    Constr

    . S

    ched.

    Select Schedule and

    Stages to define a

    new stage for the fibre

    stress checks.

    Select Insert after above the upper listing to define a new stage.

    Table

    Name: Name:

    SLS

    List file: -

    Duration.: -

    Description: Fibre stress check

    Action

    Select Schedule Ac-

    tion to define the nec-

    essary actions.

  • RM Bridge Design Code Checks

    Training Getting Started RM DIN 8-51

    Bentley Systems Austria

    Select

    Select Insert after above the lower listing to define the necessary actions.

    Table

    Constr. Stage: Constr. Stage:

    SLS

    Insert: Lower Listing

    Action: Check

    Actions (UE)

    Type: FibSup

    Confirm: OK

    Input 1: Comb1.sup

    Input 2: 1

    Input 3: -

    Output 1: -

    Output 2: *

    Delta-T: -

    Description: -

    Confirm: OK

  • RM Bridge Design Code Checks

    Training Getting Started RM DIN 8-52

    Bentley Systems Austria

    8.2 Ultimate Load Check (ULS)

    8.2.1 Calculation Action for Ultimate Load Check

    Constr

    . S

    tage

    Select Schedule and

    Stages to define a

    new stage for this part.

    Select Insert after above the upper listing to define a new stage for the ultimate load

    check.

    Table

    Name: Name:

    ULS

    List file: -

    Duration.: -

    Description: Ultimate load check

    Action

    Select Schedule Ac-

    tions to open the input

    window.

    Select

  • RM Bridge Design Code Checks

    Training Getting Started RM DIN 8-53

    Bentley Systems Austria

    Select Insert after above the lower listing to define the necessary actions.

    Table

    Constr. Stage: Constr. Stage:

    ULS ULS ULS ULS

    Insert: Lower Listing Lower Listing Lower Listing Lower Listing

    Action: LC/Envel

    pe action Checking action (Sup)

    Checking action (Sup)

    Checking action (Sup)

    Type: SupInit ReiIni UltSup UltSup

    Confirm: OK OK OK OK

    Input 1: - - Comb2.sup Comb2.sup

    Input 2: - - Rein UltMz

    Input 3: - - - -

    Output 1: Ult-

    Comb2.sup - -

    Ult-Comb2.sup

    Output 2: - - * *

    Delta-T: - - - -

    Description: - - - -

    Confirm: OK OK OK OK

  • RM Bridge Calculating the Construction Schedule

    Training Getting Started RM DIN 9-54

    Bentley Systems Austria

    9 Calculating the Construction Schedule

    After the definition of all necessary construction stages the calculation can be started. Such

    a calculation can be done at any time, all available data will be considered. All actions in

    the construction schedule will be calculated.

    9.1 Starting the Calculation

    Syste

    m C

    alc

    ula

    tion

    Klick the Recalc-button

    on the top of view win-

    dow to open the calcu-

    lation-options.

    Before the calculation

    can actually be started,

    the definitions for

    SumLC for the sum-

    mation loading case

    DL-SUM needs to be

    defined.

    Start the calculation by

    clicking .

    Recalc

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-55

    Bentley Systems Austria

    10 Result Presentation Post-Processing

    Any kind of result (forces, displacement, stresses,..) can be displayed numerically or

    graphically. In case graphics should be created during the stages the corresponding actions

    need to be added in the appropriate stage as calculation action.

    10.1 Numerical Results

    10.1.1 Standard Listings

    Several list files are generated automatically during the run of the calculation. The results of

    the loading cases (and others) can be viewed using the editor. All these listing contain dis-

    placements and internal forces for nodes, elements and tendons.

    Additionally list files containing information about structural data, material, cross section

    and stressing action + tendon geometry are available. (struct.lst, material.lst, cross.lst,

    stress.lst, ..).

    Select TextPad to load one of the files (top of screen).

    RM

    Set

    - N

    ew

    Select the sub directory

    for (Default Sched-

    ule) and the wanted

    file.

    Open

    The textpad editor opens and allows to view the results files.

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-56

    Bentley Systems Austria

    10.1.2 Interactive Result Viewing

    All results can be viewed interactively as well. The following procedure shows how to do

    this.

    Results

    Select Results and

    Loading Cases to

    open the spread sheet

    for results.

    LC

    ase R

    esults

    The shown listing

    shows the local internal

    forces for loading case

    G1. Please feel free to

    change LCase and all

    other buttons on the

    screen.

    Minimum and Maximum results can be searched, too.

    The results from Pre-Stressing and Creep&Shrinkage loading cases are available in three

    ways:

    Primary: P*e state for PT and distribution forces for C&S.

    Secondary: Secondary effects for PT and C&S.

    Total: Primary + Secondary = Total.

    Selecting Diagram (bottom right) the wanted result component can be displayed graphi-

    cally in an easy way.

    Select Results and Envelopes to view the results of superposition files in the same way.

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-57

    Bentley Systems Austria

    10.2 Graphical Results

    10.2.1 RMSets

    For a quick and easy to use graphical viewing of internal forces, displacements, stresses and

    reinforcement there exists the possibility to define so called RMSets. With some few

    commands such a plot can be defined, viewed and also incorporated in the Construction

    schedule.

    RM

    Sets

    Select Properties and

    RMSets to define one

    or several groups for

    graphic (and numeric)

    result presentation.

    RM

    Sets

    The upper listing shows

    the names for the rele-

    vant RMSets (empty at

    the moment). All

    RMSets can be used in

    the run of the construc-

    tion stages as well. Feel

    free to add the accord-

    ing action at any time

    in the stage definitions.

    The RMSets will pro-

    duce graphics and list-

    ings.

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-58

    Bentley Systems Austria

    Select Insert after above the upper listing to define a new RMSet.

    RM

    Set

    - N

    ew

    This new RMSet is

    supposed to show the

    ending moment MZ at

    the end of the first con-

    struction stage.

    (Stage1-Mz).

    Confirm

    Select the Info button to open the interactive input pad.

    Ele

    ment

    Lis

    te

    Select Elements and Nodes to define the elements to be plotted.

    Select Element of a

    group: MG.

    After all elements are

    defined, confirm input

    with insert before.

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-59

    Bentley Systems Austria

    Ele

    ment

    Lis

    ting

    Select Load Cases to define the wanted Loading Case.

    Select Load Case DL-

    SUM.

    Select the wanted result

    component - Mz.

    Select insert before

    Save all RMSet defini-

    tions using Save.

    10.2.2 Diagrams

    RM

    Set P

    lott

    ing

    For the defined con-

    figuration a name for

    the resulting graphic

    file can be chosen.

    Define Dgm-CS1-

    Mz.pl

    To see the result of

    your settings press

    plot diagram file

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-60

    Bentley Systems Austria

    10.2.3 Listings

    RM

    Set P

    rin

    ting

    For the defined con-

    figuration a name for

    the resulting list file

    can be chosen.

    Define Rep-CS1-

    Mz.lst

    To see the result of

    your settings press

    write to report file

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-61

    Bentley Systems Austria

    10.2.4 RMSet in the Construction Schedule

    Ele

    ment

    Lis

    ting

    RMSets can be incor-

    porated in the construc-

    tion schedule. When

    ever the a result during

    the calculation should

    be stored graphically or

    numerically a corre-

    sponding action can be

    inserted.

    The action DgmSet is

    used to use an RMSet

    for a diagram plot.

    The action DoRep is

    used to use an RMSet

    for a result listing.

    Confirm

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-62

    Bentley Systems Austria

    10.3 Graphical Result Presentation

    Plo

    ttin

    g

    Select Results, Plot

    and Directory to

    show all existing

    graphics.

    10.3.1 Plot

    Plot contains following types:

    Directory: All Rm-Sets are listed here as a plot.

    Plot Container: One or several Plots with RM Plot-Definitions. (see below)

    RMSet: All RM-Sets are listed

    PLSYS: A listing of ASCII *.rm files that might exist from earlier RM versions.

    C&S: Kreep and Shrinkage

    Select Plot Container and open a new Plot-Container.

    Plo

    t C

    onta

    iner

    Select a new name or

    accept the one pro-

    posed by the program.

    Confirm

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-63

    Bentley Systems Austria

    Plo

    t P

    rofil

    Press Insert After

    Plo

    t P

    rofil

    Select a new name or

    accept the one pro-

    posed by the program.

    Confirm

    Similarly prepared standard plots of structure and results can be created using several Mac-

    ros.

    Macro

    Select Macro to cre-

    ate a standard plot.

    Select

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-64

    Bentley Systems Austria

    Macro

    Select Loading case

    result to show results

    from a loading case.

    The input field for

    Plot Profile is used to

    save the created input.

    Press: Run Macro

    Macro

    Select the elements to

    be shown (Group:

    MG).

    Select the results to be

    shown together with

    the elements (Dis-

    placments and Force)

    Dependent on the Plot-Container type the plot editor opens when hitting the Info button.

    Modifications or additional definitions can be done in here.

    Select the Info button to open the plot content (= plot editor).

    The plot editor allows the definition or modification of graphics and plot profiles. The re-

    sult will be a plot file. These plot files contain paper size (page) and one or several views.

    The views it selves contain one or several objects.

    Three levels can be defined or modified. The most important modify, copy and delete func-

    tions can be selected in the upper menu line or via the right mouse button.

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-65

    Bentley Systems Austria

    10.3.2 Plot Profiles in the Construction Schedule

    Plo

    ttin

    g

    Plot Profiles can also

    be inserted in the con-

    struction stages at any-

    time at any position.

    The action DoPlot is

    used to define an exist-

    ing plot container and

    an existing plot profile

    in order to create a plot

    file.

    Plo

    ttin

    g

    Use the arrow next to

    the input field to select

    a plot container and a

    plot profile.

    Use input1 and iput2 to

    define eventually exist-

    ing variables in the plot

    profile.

    Confirm

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-66

    Bentley Systems Austria

    10.3.3 Interactive View of stress, force and displacment:

    Plo

    ttin

    g

    Right click with your

    mouse in the middle of

    the window gives you

    the following menu, as

    shown in the right fig-

    ure.

    Select View Options

    Plo

    ttin

    g

    Tick Draw cross sec-

    tions and Draw CS

    mesh

    Tick Draw element

    bodies and Draw de-

    tailed bodies

    Tick Result and press

    Choose

  • RM Bridge Result Presentation Post-Processing

    Training Getting Started RM DIN 10-67

    Bentley Systems Austria

    Plo

    ttin

    g

    Set Load Case as

    DL-SUM.

    Tick Stresses and fi-

    nally press OK

    Plo

    ttin

    g

    The figure on the left

    side shows the stress-

    distribution in the ele-

    ments (red colour

    means high- green col-

    our low stresses).

    It can be easily

    switched to a force- or

    displacement distribu-

    tion (see picture be-

    low).

  • RM Bridge Exporting and Storing

    Training Getting Started RM DIN 11-68

    Bentley Systems Austria

    11 Exporting and Storing

    11.1 Project Export

    All data (cross sections, material, system, schedules,.) can written into an ASCII file with

    a special (and very powerful) format. RM uses TCL, a special script programming language to work on existing ASCII files.

    Export

    Select File and Ex-

    port TCL Project Data

    to create the ASCII file.

    No results, only input

    data is stored.

  • RM Bridge Exporting and Storing

    Training Getting Started RM DIN 11-69

    Bentley Systems Austria

    Export

    Define a new file name

    which will contain all

    data after the export.

    Additional selections

    can be ticked as you

    can see at the left (to

    export certain parts of

    the data only).

    After confirmation the

    ASCII file can be

    opened using the editor

    button in the main

    menu. View it, and if

    something is modified,

    re-import it into RM (Recalc must be run

    then to update the re-

    sults).

    Confirm

  • RM Bridge Exporting and Storing

    Training Getting Started RM DIN 11-70

    Bentley Systems Austria

    11.2 Leaving the Program

    Fin

    ish R

    M

    Feel free to add any

    data at any place and

    using other available

    descriptions (training

    examples, manuals,).

    If no additional data is

    defined the session can

    be closed and RM can be finished.

    Select File and Exit

    RM.

    After clicking Exit RM the session will be closed automatically. All data that have been input before are automatically stored in the database. To store all necessary information that

    have been defined up to this state there exists also the possibility to export the data to a

    TCL file which can be imported at any time into any directory later on.

    1 General1.1 The Tutorial1.2 Strucural System1.2.1 Support Scheme1.2.2 Cross Section1.2.3 Tendon Geometry1.2.4 Tendon Characteristics1.2.5 Material Properties1.3 Loading1.3.1 Permanent Load1.3.2 Creep and Shrinkage:1.3.3 Additional Load1.3.4 Traffic Load2 Starting a Calculation2.1 Recalculate2.2 First Results2.3 View Options3 Material for PT Tendons3.1 Import of Material3.2 Definition of Tendon Geometry3.3 Definition of Stressing Sequence4 Load Definition4.1 Load Management4.2 Loading Case Definition5 Construction Schedule5.1 Stage Actions and Activation5.1.1 Definition of Individual Stages5.1.2 Activation of the New Stages5.1.3 Calculation Actions for Each Stage6 Traffic6.1 Traffic Load Definition6.2 Calculation Actions for Construction Stage7 Load Combinations for Design Code Checks7.1 Combination Table7.2 Calculation Actions for Load Combinations8 Design Code Checks8.1 Fibre Stress Checks (SLS)8.1.1 Calculation Actions for Fibre Stress Check8.2 Ultimate Load Check (ULS)8.2.1 Calculation Action for Ultimate Load Check9 Calculating the Construction Schedule9.1 Starting the Calculation10 Result Presentation Post-Processing10.1 Numerical Results10.1.1 Standard Listings10.1.2 Interactive Result Viewing10.2 Graphical Results10.2.1 RMSets10.2.2 Diagrams10.2.3 Listings10.2.4 RMSet in the Construction Schedule10.3 Graphical Result Presentation10.3.1 Plot10.3.2 Plot Profiles in the Construction Schedule10.3.3 Interactive View of stress, force and displacment:11 Exporting and Storing11.1 Project Export11.2 Leaving the Program