RLV SB Process Sheet

download RLV SB Process Sheet

of 155

Transcript of RLV SB Process Sheet

  • 8/2/2019 RLV SB Process Sheet

    1/155

    PROCESS SHEET NO : REV.NO

    CLIENT :

    PART NAME : RLV-SB HEAD END MATL :

    RLV-SB

    OPN.NO STAGE

    005# Inspection

    010 CNC VTL

    015 Inspection

    020 CNC VTL

    Without disturbing setup, clamp the job from I/S & remove O/S clamp

    025 Inspection

    Form a groove as per sketch-2.

    Compute the depth

    Hold the job on VTL, True ID & Clamp the job from out side. Face to maintain,overall height 394mm. Bore 180+0.2/+0.0 through.

    Allot part Idn.No as RLV-HED-02-05.

    1) 180+0.2/+0.0 I/S Micrometer

    1) 25mm2) 1000+5.0 Vernier Caliper

    Vernier Caliper

    Turn OD 242.0 to 39.5mm depth.

    Inspect for the following

    Inspect & record the following

    DESCRIPTION TOOLINGS

    Note : The Idn shall be retained during m/cing & transferred to the job after machning.

    Verify the RMC No. and the acceptance of the material in co-relation with theTC issued by VSSC.

    RKE/RLV/68/PS-01 R1

    SUB ASSY NAME : REF DRG. NO. REV.NO. QUANTITY : 1 No per

    VSSC

    HEAT TREATED FORGING

    RAMAKRISHNA ENGINEERING COMPANY, CHENNAI-106.

    PROCESS AND QUALITY CONTROL PLAN

    RLV-SB MOTOR CASE

    SHEET NO : 1 OF 5 PROJECT : RLV-SB

    10.01.2009

    APPLICABILITY 02- 05

    Confirm H/T by verifying hardness reported in TC

    Supply condition to be reported and act accordingly.

    REFER SKETCH - 1

    REFER SKETCH - 2

    PART DRG.NO. REV. NO. 15CDV6

    DOME RING RKE-RD-06-234-01 R2

    HEAD END DOME PRE ASSY RD06-25-05-02-3-17-13-10-110 Sheet 1 & 2 R3 ASSY.

  • 8/2/2019 RLV SB Process Sheet

    2/155

    3) 89mm

  • 8/2/2019 RLV SB Process Sheet

    3/155

    OPN.NO STAGE

    030 CNC VTL

    035 # Inspection

    040 CNC VTL

    050 CNC VTL

    055 # Inspection

    060 CNC VTL

    070 # Inspection

    RKE-RO06-234-T-17

    Checking template No

    Dial setup

    UT gaugeO/S Mic & Compute

    TOOLINGSDESCRIPTION

    the programme for 'Y' ring machining and merge on ODWithout disturbing the setup, remove the outside clamp and clamp on OD. Execute

    Reverse the job, Load the fixture and true within 0.1mm

    face turn to maintain total height 384.35mm.

    RKE-RD06-234-T-03

    2) 2+0.2/+0.0 UT Gauge

    4) 384.35mm

    program & execute I/S profile by maintaining 996.00.2mm

    REFER SKETCH - 3

    2. 2+0.2/+0.0

    Inspect & record the following

    Vernier Caliper

    Load the job and Clamp on O/S. Check for runout within 0.1mm on 180

    REFER SKETCH - 4

    as shown in the sketch. Execute the programme for outside machining by

    maintaining 2 +0.2/-0.0 wall thickness and 144.25mm height. Turn 232 through.

    Checking template No.

    REFER SKETCH - 6

    3) 30mm

    1. 9930.2

    RKE-RD06-234-T-02

    In the same setup machine "V" groove as per drawing.

    Inspect & Record

    Inspect unload the job.

    Vernier Caliper

    2. 2.0+0.2 thk Vernier Caliper3. 232+1.0/-0.5 UT Gauge

    UT Gauge

    I/S Checking template

    I/S Mic

    Page 2 of 5

    Turn on OD to a depth of 30mm to maintain a wall thickness of 2+0.2/+0.0

    Checking template No :

    RKE-RD06-234-T-01

    REFER SKETCH - 5

    Machining Fixture No

    1) 9960.2

    1. 996.00.2

    Execute the programme as per detail "A" by maintaining 11.5+1.0/-0.50 wall thickness.

    Prepare weld edge angle 30and 0.5 to 1mm root face.

    Load the machining fixture on VTL and true within 0.05mm. Reverse the job & clamp

    Inspect and record the following dimensions

    // 0.2 C 0.1 B0.2 A

  • 8/2/2019 RLV SB Process Sheet

    4/155

  • 8/2/2019 RLV SB Process Sheet

    5/155

    OPN.NO STAGE

    18. 2.0 +0.2/-0.0

    20. 144.25

    22. DP Test all over

    # Mandatory stages to be cleared by RQS/VSSC

    * Dimensions to be checked in fixture condition.

    21. Ovality on 996 and 180 (8 generators) I/S Mic

    DP Kit

    Checking Template

    RKE-RD06-234-T-02

    Height Gauge

    Inside Micrometer

    Dial setup

    19. R100, R87.24,10.16 and angle11

    15. 3.5+0.2/-0.0 thk

    Vernier Caliper

    Detail "X"

    RKE-RD06-234-T-03

    16. 30, 0.5 to 1mm

    Height Guage7. 384.35

    B. Protractor/ V. CaliperDetail "A"

    Checking Template

    Ball Point Mic

    Ball Point Mic

    13. 11.5+1.0/-0.5

    12. 50.31.0

    RKE-RD06-234-T-04

    RKE-RD06-234-T-01

    Dial setup

    Dial setup

    Engrave Idn. number apply Black Japan & store.

    4. Perdendicularity

    Page 3 of 5

    Micrometer

    V/Caliper / B.Protractor

    17. (922.92) , (37) , 25.24, 8.9, angle18, angle 5639' and R2 Checking Template

    15. 9930.2

    Detail "Y"

    10. 180+0.2/-0.0

    Vernier Caliper

    Checking Template

    O/S Micrometer

    DESCRIPTION

    6. 25.0 & co-ordinate

    8. Angle 30& 0.5 to 1mm

    9. 195+0.0/-0.5

    14. 9,R5, 15,48' &17.3mm (400 & 68.8)

    5. Parallelism

    11.

    TOOLINGS

    0.1 B

    // 0.2 C

    0.2 A

  • 8/2/2019 RLV SB Process Sheet

    6/155

    PROCESS SHEET NO : REV.NO

    CLIENT :PART NAME : RLV-SB HEAD END MATL :

    RLV-SB

    OPN.NO STAGE

    005# Inspection

    010 VTL / Lathe

    015 Inspection

    020# Heat

    Treatment

    030 # Hardness Grind /machine to depth of 3mm

    Testing M/C

    040 VTL /

    CNC VTL

    050# CNC VTL

    VSSCRKE/RLV/68/PS-02 R1

    RING (ANNEALED)

    PART DRG.NO. REV NO. 15CDV6

    SKIRT RING RKE-RD-06-234-02 R2

    RAMAKRISHNA ENGINEERING COMPANY, CHENNAI-106.

    PROCESS AND QUALITY CONTROL PLAN

    RLV-SB MOTOR CASE

    SHEET NO : 1 OF 4 PROJECT : RLV-SB

    APPLICABILITY 02- 05

    10.01.2009

    SUB ASSY NAME : REF DRG. NO. REV.NO QUANTITY : 2 Nos. per

    DESCRIPTION TOOLINGS

    HEAD END SEGMENT

    Note : The Iden shall be retained during m/cing & transferred to the job after m/cing

    Verify the RMC No. and the acceptance of the material in correlation with the

    RD06-25-05-02-3-17-13-10-110 R3 ASSY.

    Inspect the dimensions as per sketch 1

    TC issued by VSSC.

    I/S, O/S Mic, Vernier

    Supply condition of the forgings to be ensured and act accordingly

    Allot part Iden.No as RLV-HES-02, 03 etc.,

    REFER SKETCH - 01

    True & Clamp the job from inside. Turn OD 1002x67mm depth.

    unload and reverse the job.

    Pre machining the forging as per sketch 1

    Hardness tester

    Load the job on VTL, True and clamp. Face to maintain a height of 112.0mm,

    REFER SKETCH-03

    Get clearance from VSSC for Heat treatment. Heat treat the forging as perDoc.No : MEE/QCI/QCP/007/2002, Issue 2, July 2005

    REFER SKETCH - 02

    Check hardness at 3 locations on both faces. Hardness value 34 to 40 HRC.

    Portable Grinder

    Note 1: Ensure that chart recorder is working

    Note 2: A copy of the chart to be attached with Inspection Report.

  • 8/2/2019 RLV SB Process Sheet

    7/155

    OPN.NO STAGE

    060# CNC VTL

    070# CNC VTL

    075# Inspection

    6) 20.1 (Inside )

    11) R20 (Inside) RKE-RD06-234-T-005

    RKE-RD06-234-T-0058) 40(Outside)

    7) 20.1 (Outside) Vernier Caliper

    10) 40 (Inside) Template No

    # Mandatory stages to be cleared by RQS/VSSC

    Mark/Paint Iden.no as RLV-HES-02,05,Apply Black Japan all over and preserve

    TOOLINGS

    12) 3.5+0.2-0

    Vernier Caliper/ B. Protractor

    Ball point mic

    13) D.P Check all over D.P. Kit

    Vernier Caliper

    2) 108.0+0.0-0.2

    DESCRIPTION

    Page 2 of 4

    Without disturbing the setup clamp the job from outside and remove the internal clamp.

    Execute the programme as shown in sketch. Bore 953 through.Face to maintain

    108.0/0.2mm Height.

    REFER SKETCH-05

    REFER SKETCH-04

    Without disturbing the setup clamp the job from inside and remove the external clamp.Turn OD by keeping 1040.0 through. Execute the programme to achieve

    1) 993+0.2/-0.0

    Inspect & record the following dimensions

    16)

    14) Ovality on 993 ( at 8 Generators)

    15) 30, 0.5-1mm land

    9) R20 (Outside)

    3) 1040

    5)

    Template No

    Line Inspected

    Vernier Caliper

    Compute from IDInside Mic

    Dial setupVernier Caliper

    4) 953

    3.5+0.2/-0.0. wall thickness R20 and 40angle.

    Dial setupInspect Concentricity before unloading the job.

    Inside Micrometer

    Prepare weld edge 0.5 to 1mm lip distance and 30angle.

    Inspect for 993.0, 953 and 1040 in the fixture condition.

    0.2 A

    0.2 A

  • 8/2/2019 RLV SB Process Sheet

    8/155

    PROCESS SHEET NO : REV.NO

    CLIENT :PART NAME : RLV-SB HEAD END MATL :

    SUB ASSY NAME : RLV-SB HEAD END

    OPN.NO STAGE

    weld joint to be identified as shown in the drawing.

    Note 2: Mismatch shall be calculated by taking thickness into account and reported

    at every 50mm interval

    Note 3: Apply Black Japan during all stages of fabricationNote 4: Mark RT zones by paint and retain the marking by paint and transfer

    005 # Inspection

    010 Welding

    015 # Inspection

    CS= Cirseam Weld

    Inspect for :

    RKE/RLV/68/PS-03 R1

    1. Head End Dome Ring

    2. Head End Skirt Ring

    RAMAKRISHNA ENGINEERING COMPANY, CHENNAI-106.

    PROCESS AND QUALITY CONTROL PLAN

    RLV-SB MOTOR CASE

    SHEET NO : 1 OF 1 PROJECT : RLV-SB

    Load Head End Dome Ring and Head End Skirt Ring on the Welding Fixture,true within 0.2.mm and tack weld at intervals of 50mm

    DESCRIPTION TOOLINGS

    APPLICABILITY 02- 05

    10.01.2009

    VSSCPART DRG.NO. REV NO. 15CDV6

    DOME PRE ASSY RKE-RD-06-234-03 R2

    REF DRG. NO. REV.NO QUANTITY : 1 NO PER

    SEG. WELDING RD06-25-05-02-3-17-13-10-110 R3 MOTOR CASE

    Verify the acceptance of the following components and record the idn nos.

    the RT marking to inspection log book.

    Note 1: Identification No. shall be retained at all stages of fabrication and the

    Note 5: The Film density shall be kept as 1.8 to 2.5mm for X-ray radiography

    Mismatch checking templates

    Feeler Gauge

    Vernier Caliper

    Vernier Caliper

    Root Gap

    Mismatch

    Dial Gauge setup

    Allot part identification number as RLV-HPA-02-05..Etc.,

    Tack length & Tack Spacing

    Welding Fixture

    XX= Set Serial Number

    1. 252.25+1.0/-0.5

    Engrave paint part Iden No. as RLV-HPA-02-05..Etc., on the component.

    2. Concentricity

    Identify the weld joint as RLV-HS-CS-XX- 01

    0.2 A

  • 8/2/2019 RLV SB Process Sheet

    9/155

  • 8/2/2019 RLV SB Process Sheet

    10/155

    12.01.2009

    PROCESS SHEET NO : REV.NO

    CLIENT :

    PART NAME : RLV-SB TONGUED RING MATL :

    RLV-SB

    OPN.NO STAGE

    005# Inspection

    010 CNC VTL

    015 Inspection

    020# Heat

    Treatment

    030 # Hardness

    Testing M/C

    040# CNC VTL

    True 1030 and clamp from outside. Face to maintain height 150mm

    Step Bore 982 to a depth of 45mm

    Turn ID 961.5 through Vernier Caliper

    Vernier Caliper

    Tape

    I/S, Mic, Vernier Cali

    Portable Grinder

    Hardness tester

    TC issued by VSSC.

    Allot part Iden.No as RLV-TR-03,04,05 etc.,Supply condition of the forging to be ensured and act accordingly.

    Note 1: Ensure that chart recorder is working

    Get clearance from RQS for Heat treatment. Heat treat the forging as per

    Note 2: A copy of the chart to be attached with Inspection Report.

    DESCRIPTION TOOLINGS

    Verify the RMC No. and the acceptance of the material in correlation with the

    Note : The Idn. No shall be retained during m/cing & transferred to the job after m/cing

    SUB ASSY NAME : REF DRG. NO. REV.NO QUANTITY : 2 NoS. per

    NOZZLE END AND MIDDLE SEGMENT RD06-25-05-02-3-17-13-10-130 R2 ASSEMBLY

    RKE/RLV/68/PS-04 R1 VSSC

    FORGING (ANNEALED)

    PART DRG.NO. REV NO. 15CDV6

    RKE-RD-06-234-04 R2

    RAMAKRISHNA ENGINEERING COMPANY, CHENNAI-106.

    PROCESS AND QUALITY CONTROL PLAN

    RLV-SB MOTOR CASE

    SHEET NO : 1 OF 5 PROJECT : RLV-SB

    APPLICABILITY 02- 05

    Grind/Machine to a depth of 3mm and check hardness at 3 locations

    REFER SKETCH - 2 I/S, O/S Mic

    both sides Hardness 34 to 40 HRC.

    Step Turn OD 1010 to a depth of 401mm

    Pre m/c the forging as per sketch-1

    Doc.No : MEE/QCI/QCP/007/2002, Issue 2, July 2005

    Inspect the dimensions as per sketch-1

  • 8/2/2019 RLV SB Process Sheet

    11/155

  • 8/2/2019 RLV SB Process Sheet

    12/155

    OPN.NO STAGE

    050# CNC VTL

    055 # Inspection

    (A)

    996.60.2mm. Execute the program for outside by maintaining

    DESCRIPTION

    Inspect 996.00.2 and concentricity before unloading the job from VTL

    2mm0.2/0.0 wall thickness. Prepare weld edge 30and root face of 0.5-1mm.

    Reverse the job & true ID 961.5 and clamp.

    1) 1010

    3) 961.5

    REFER SKETCH -3

    Template RKE-RD06-23

    I/S Mic

    Tape

    Vernier Caliper

    12) 25

    Vernier Caliper

    Vernier Caliper

    Vernier Caliper

    V. Caliper/ B.Protract

    Template RKE-RD06-23

    Computed from OD7) 982.0

    8) 961.5

    11) 145.0 1.0

    9) 45.010) 72.9

    I/S Mic

    (by computing thk)

    Dial Setup

    Vernier Caliper

    1) 9960.2

    2) Concentricity

    6) 1010

    Inspect the following dimensions

    1) 1000.0

    2) 996.0 0.2

    5) 10.0,5, R20 and 44.09

    3) 30x0.5 to 1mm

    4) 20.0, 252', +0.5/-0.0

    I/S Mic

    I/S Mic2) 982 I/S Mic

    Inspect for

    Page 2 of 5TOOLINGS

    Face to maintain 145mm height. Execute the programme for Inside turning by keeping

    I/S, O/S Mic

    0.2 A

  • 8/2/2019 RLV SB Process Sheet

    13/155

    OPN.NO STAGE

    Page 3 of 5DESCRIPTION TOOLINGS

    13) Concentricity

    # Mandatory stages to be cleared by RQS/VSSC

    Dial Gauge

    15) D.P test all over. D.P.Kit

    I/S Mic14) Ovality on 961.5 (minimum 8 reading)

    Apply Black Japan all over and preserve

    Mark/Paint idn.no as RLV-TR-03,04,05 etc.,

    0.2 A

  • 8/2/2019 RLV SB Process Sheet

    14/155

    er

  • 8/2/2019 RLV SB Process Sheet

    15/155

  • 8/2/2019 RLV SB Process Sheet

    16/155

    -T-09

    or

    -T-08

  • 8/2/2019 RLV SB Process Sheet

    17/155

  • 8/2/2019 RLV SB Process Sheet

    18/155

    12.01.2009

    PROCESS SHEET NO : REV.NOCLIENT :

    PART NAME : RLV-SB GROOVED RING MATL :

    RLV-SB

    OPN.NO STAGE

    005# Inspection

    010 VTL/Lathe

    015 Inspection

    020# Heat

    Treatment

    030 # Hardness

    Testing M/C

    040 VTL /

    CNC VTL

    Inspect & record the following dimensions

    RAMAKRISHNA ENGINEERING COMPANY, CHENNAI-106.

    PROCESS AND QUALITY CONTROL PLAN

    RLV-SB MOTOR CASE

    SHEET NO : 1 OF 4 PROJECT : RLV-SB

    APPLICABILITY 02- 05

    RKE/RLV/68/PS-05 R1 VSSC

    FORGING (ANNEALED)

    PART DRG.NO. REV NO. 15CDV6

    RKE-RD-06-234-05 R2

    HE AND MIDDLE SEGMENT RD06-25-05-02-3-17-13-10-110 R3 MOTOR CASE

    DESCRIPTION TOOLINGS

    SUB ASSY NAME : REF DRG. NO. REV.NO QUANTITY : 2 Nos. per

    TC issued by VSSC.

    Note: The Idn No shall be retained during m/cing & transferred to the job after m/ching

    Vernier Caliper

    Verify the RMC No. and the acceptance of the material in correlation with the

    Supply condition to be reported and act accordingly

    Pre m/c the forging as per sketch-1

    Tape

    I/S, Mic

    Allot part Iden.No as RLV-GR-03, 04, 05 etc.,

    Grind/machine to a depth of 3mm and check hardness at 3 locations on

    REFER SKETCH - 2

    3) 993.5

    True on 1030 clamp from O/S. Skin cut on the face bore ID 969.5 through.

    Step turn OD 1018.5mm x 62mm, Step turn 993.5mm x 19.7mm

    Get clearance from RQS for Heat treatment. Heat treat the forging as per

    Note 1: Ensure that chart recorder is working

    Note 2: A copy of the chart to be attached with Inspection Report.

    Doc.No : MEE/QCI/QCP/007/2002, Issue 2, July 2005

    I/S, Mic, Vernier

    both faces. Hardness 34 to 40 HRC.

    I/S Mic

    Hardness tester

    1) 969.5

    2) 1018.5 Vernier Caliper

    I/S, O/S Mic

    Vernier Caliper

    Vernier Caliper

    Portable Grinder

    REFER SKETCH - 1

    Inspect the dimensions as per sketch-1

  • 8/2/2019 RLV SB Process Sheet

    19/155

    OPN.NO STAGE

    050# VTL /

    CNC VTL

    055 # Inspection

    Inspect for

    3) Concentricity

    Page 2 of 4DESCRIPTION

    9) 2+0.2/-0.0

    1) 19.7

    6) 969.50.8

    4) 1018.51.0

    5) 993.50.8

    3) 142.5mm

    10) 20,41.3 and 3 Template RKF-RD06-234-T-07

    2) 40.5mm

    7) 63.62

    8) 9960.2

    I/S Mic

    Vernier Caliper

    I/S Mic

    UT Gauge

    I/S Mic

    12)10mm, 50.4,3,

    11) WEP 30, 0.5 to 1mm root face.

    Dial Setup

    Bevel Protractor

    Mark/Paint Idn.no as RLV-GR-03,04, etc.,

    15) carry out D.P.test

    13) Concentricity

    # Mandatory stages to be cleared by RQS/VSSC

    Apply Black Japan all over and preserve

    D.P.Kit

    14) Ovality 0n 969.5 (at 8 Generators)

    O/S Mic

    Vernier Caliper

    Template RKE-RD06-234-T-06

    Vernier Caliper

    I/S Mic

    Vernier Caliper

    2) 2.0 +0.2-0.0.

    I/S, O/S MicReverse the job True 969.5 & calmp on O/S. Face turn to maintain

    1) 9960.2UT Gauge

    I/S Mic

    2 +0.2/0.0. Prepare weld edge as per detail A.

    TOOLINGS

    Dial setup

    996+0.2/-0.0 & Execute the programme for outside profile maching by keeping

    142.5mm height. Execute the programme from Inside profile machining by keeping ID Vernier Caliper

    Inspect & record the following dimensions.

    Ball point mic

    REFER SKETCH - 3

    0.2 A

    0.2 A

  • 8/2/2019 RLV SB Process Sheet

    20/155

    PROCESS SHEET NO : REV.NOCLIENT :

    PART NAME : RLV-SB CYLINDERICAL MATL :

    OPN.NO STAGE

    005 # Inspection

    010 Fitting

    transfer the RMC numbers on the test pieces and left over portion by punching.

    020 Shearing Shear the test pieces as per marking and identify. Preserve the test pieces.

    2) 250 x 300 - 1no.

    1) 150 x300 - 6nos.

    Check the thickness at random.

    UT guage

    record.

    Mark for the test pieces as per layout sketch-1(2nos. of sheets per shell).

    Carry out Visual inpsection of the sheets for corosion etc.,

    Allot part Identification number as RLV-CS-11,12, 13 etc., and record in the log book

    2.2 mm thick sheet Annealed

    DESCRIPTION TOOLINGS

    Note 3: Mismatch shall be calculated by taking thickness into account and reported at every50mm interval. Mismatch tabulation shall contain thickness on either side of the weld, offset

    Note 4: Apply Black Japan during all stages of fabrication.

    Note 5: Mark RT zones by paint and retain the marking by paint and transfer the RT

    RD06-25-05-02-3-17-13-10-110 R3

    Note 6: Check hardness on the trimmed portion of the shell

    RKE/RLV/68/PS-06 R1

    QUANTITY : 10 No per

    MOTOR CASE

    VSSC

    PART DRG.NO. REV NO. 15CDV6

    SHELL RKE-RD-06-234-06 R2

    SUB ASSY NAME : REF DRG. NO. REV.NO

    marking to inspection log book.

    RLV-SB HE,NE & MS WELD ASSY

    Note 1: Idn.No shall be retained during all stages of fabrication like welding, Heat treatment andmachining.

    Note 2: Welding and Heat treatment inspection as per Doc No.MEE/QCI/QCP/007/

    2002-ISSUE 2, JULY 2005

    and centerline mismatch.

    RAMAKRISHNA ENGINEERING COMPANY, CHENNAI-106.

    FABRICATION PROCESS AND QUALITY CONTROL PLAN

    RLV-SB MOTOR

    SHEET NO : 1 OF 10 PROJECT : RLV-SB

    APPLICABILITY 02- 05

    Verify the RMC No. & acceptance of the sheets in correlation with the TC issued by VSSC and

    Note 7: The Film density shall be kept as 1.8 to 2.5mm for the X-ray radiograph.

    12.01.2009

  • 8/2/2019 RLV SB Process Sheet

    21/155

    OPN.NO STAGE

    030 Fitting /

    HBM

    035# Inspection

    040 Position the sheets set and clamp

    045# Inspection

    050 Welding

    055 # Inspection

    060 Fitting

    Fitting /

    Welding Clean the weld edges with emery and acetone. Welding fixture

    Tack weld the sheets at 100mm intervel and test pieces in the LS welding fixture.

    Prepare weld edge for 2 Nos of test pieces from each sheet and preserve the balance

    Mismatch

    TOOLINGS

    Page 2 of 9

    Mill one end of the sheet by discarding 25mm (minimum)

    Conduct DP test on the weld edges of sheets and test pieces 2 Nos each per sheet.

    - Filler wire code No and Dia.

    Identify the weld joint as RLV-CS-XX-LS1 where XX = Set serial No

    Prepare weld edge by maintaining 30angle and 0.5 to 1mm root face.

    Load the sheet on table and clamp at four locations using suitable clamp

    DESCRIPTION

    Note: Identify LS1 & LF1 test coupon.

    Inspect visual, weld bead dimensions & mismatch (Compute with thickness at 50mm interval)

    Carry out welding as per WPS.

    Start the welding on LS1 test coupon and finish LF1 coupon through the sheet.

    Vernier Caliper

    Ensure welders qualification and adaptation.Clean the weld edges for a band of 50mm with emery and acetone.

    Ensure welders qualification and adaptation. Inspect and record

    test piece.

    - Name of welder

    where XX=Set serial no.

    - Root gap

    Record current voltage, flow of argon gas for purging and shielding - filler wire size and

    UT Gauge

    Template

    Inspect for angle 30& land 0.5 to 1mm identify the sheet and test pieces. Bevel Protractor

    Vernier Caliper/ DP Kit

    Feeler Gauge

    Identify LS1 and LF1 test coupons by punching and preserve.

    Feeler Gauge- Mismatch (compute by taking thickness into account at an interval of 50mm)

    Checking template

    RMC NO.

    Identify the job as RLV-CS-11,12,13 etc and test coupons as RLV-CS-XX LS1/LF1

    Note 2: Mismatch tabulation shall contain thickness on either side of the weld, offset and

    centreline mismatch.

    location shall be provided.

    Note 1: If the mismatch observed is more than specified, detailed mapping of mismatch at that

    1. Fix adhesive tape on both sides of the welding before grinding.

    2. Flush grind the penetration (max 0.1 projection), without touching the parent metal.

  • 8/2/2019 RLV SB Process Sheet

    22/155

    OPN.NO STAGE

    065# Inspection

    070 Welding/

    080 Fitting

    Check the thickness at grids of 100mmx100mm interval and

    090 HBM

    Fitting

    Prepare weld edge 30angle and 0.5 to 1mm root face.

    095 Inspection

    5. Inspect the test pieces also for the above.

    100 Rolling

    Machine

    1. Devloped length at 6 generators.

    1) Machine rollers shall be thoroughly cleaned prior to bending.

    3. Visual inspection

    Mark the generation lines parallel to the edge.

    4. WEP 30, 0.5-1mm land.

    TOOLINGS

    Flatten the sheet with out beating the weld (surroundings area of weld within 50mm)

    Vernier CaliperCarry out repair, if any as per approved procedure and inspect.

    Reverse and mill the other end of the sheet by keeping the developed length .

    3) Carryout pre-bending of edges.

    2. D.P.test on weld edges.

    Inspect for

    Do not repair LS1 & LF1 Coupons.

    UT Gauged = ID of shell

    t = Average thickness

    Mill one end by keeping the long seam joint L-1 at middle of the developed length.

    DP Kit

    Incase if parent metal is touched, local thickness to be checked and reported.

    Film density 1.8-2.5

    2) Feed the sheet with generating lines on the top.

    D.P.Kit

    Bevel ProtractorVernier Caliper

    Inspect & record the thickness near the welds at 50 mm interval.

    Inspect visual for the penetration grinding.

    Conduct DP test

    Carry out 100% Xray radiography

    DESCRIPTION

    Page 3 of 9

    Magnifying glass 3X

    Prepare weld edge on 4 nos. of test pieces also (2 nos. each from one sheet)

    DP Kit

    Load the sheet on table and clamp at four sections using suitable plate

    (996+2.2) = 3137 mm

    compute for average thickness(t)

    Mark the developed length as (d+t) and record the length. Vernier Caliper

    Example for development length calculation. Average t = 2.2 and ID 996.0

  • 8/2/2019 RLV SB Process Sheet

    23/155

  • 8/2/2019 RLV SB Process Sheet

    24/155

    OPN.NO STAGE

    130 Fitting

    135 # Inspection

    140 Welding

    145 # Inspection

    Get clearance from VSSC for Heat treatment.

    150# Heat Note 1: Before loading confirm the RMC nos. of the shell and confirm the RMC number of test

    Treatment

    Note 2: Confirm that temperature recorder is working properly.

    Note 3: Copy of the recorded chart has to accompany the Heat treatment inspection report.

    Note 4: Ensure that shells and coupons are cleaned before heat treatment

    Note 1: While removing ovality use only soft hammer (MS with aluminium tips

    3. ID 996 0.2

    4. Visual Inspection

    1. Ovality 5.0mm (max)

    2. Penetration Grinding (0.1 Max projection)

    Micrometer

    Fix adhesive tape on both sides of the welding before flush grinding.

    I/S Mic

    Feeler Gauge

    Note 4: Incase if parent metal is touched while penertration grinding, local thickness to be

    checked and reported.

    Vernier Caliper

    Carryout repair if any as per approved process and inspect

    3X Magnifying glass

    Flush grind the penetration (max 0.1mm projection) without touching the parent metal. 2. Inside checking template

    Inspect for

    Note 3: Identify the shell as RLV-CS-11, 12,13 etc., and weld joint No as RLV-CS-XX-LS2

    Remove ovality (5mm max) by malleting with soft hammer.

    on both ends)Note 2: Weld should not be beaten.

    (xx = set serial no)

    Visually inspect for penetration grinding. Ensure parent metal is not touched.

    TOOLINGSDESCRIPTION

    Carryout DP test and 100% X-ray radiography Dp Kit

    X-ray machine

    Page 5 of 9

    1. Ovality removing set up

    coupons.

  • 8/2/2019 RLV SB Process Sheet

    25/155

    OPN.NO STAGE

    Carry out Heat treatment as per the cycle given below:

    Loading Temperature :

  • 8/2/2019 RLV SB Process Sheet

    26/155

    OPN.NO STAGE

    175# UTM

    Cross section area. Get clearnace from VSSC for further processing of the shell.

    180 Fititng

    185 # Inspection

    190 Welding

    200 Lathe

    205 # Inspection

    5. DP of WEP Sheet A

    9. 0.5 to 1mm other end

    10. Angle 30

    11. DP test on weld edge.

    12. Length 975mm (approx.)

    13. ID 9960.2

    DESCRIPTION

    Carry out mechanical testing as per ASTM-A370. Gauge length as 5.65 A, where A is theInspect the test specimen and record the dimensions in the log book.

    TOOLINGS

    beating should be done in and around weldments.) Ovality should be within 5 mm

    Inspect/Record for

    DP Kit

    1. 0.5 to 1mm for sheet A

    3. 0.5 to 1mm for sheet B Vernier caliper

    Vernier caliper

    DP Kit / X-ray m/c.

    Remove ovality (Use M.S.hammer with aluminium tips on both ends and no

    Page 7 of 9

    Bevel protractor

    Vernier caliper

    DP Kit

    Vernier caliper

    Bevel protractor

    Bevel protractor

    Vernier Caliper

    Face on one side and prepare weld edge maintaining 30angle 0.5 to 1mm root face

    Repair defects if any and inspect as per approved procedure.

    Load the shell on turning setup with spider and shaft between centers.

    Inspect for the thickness near the weld and the shell.

    Carryout 100% X-Ray radiography & D.P on both long seam weld joints

    DP Kit

    Vernier caliper

    Inside mic

    4. Angle 30

    2. Angle 30

    8. Angle 30 Bevel protractor

    True the job within 0.2mm.

    7. 0.5 to 1mm one end.

    6. DP of WEP Sheet B

    Note : Discard minimum 25mm from the edge of the shell. (WEP on one side only)

  • 8/2/2019 RLV SB Process Sheet

    27/155

    OPN.NO STAGE

    14.

    15. 0.5 to 1mm

    16. Angle 30

    17. DP test on weld edge18. Thickness 2.0+0.2+0.0

    19. T1,T2,T3,T4 Thickness near weld20. 180weld orientation

    Do not remove the spiders before cirseam weld setup. Report the Dia of shells and thicknessof the edges to planning

    Dial setup

    2. Ensure that all inspection reports are prepared before clearing the job for further operation

    Apply Black Japan and preserve

    Note : 1. # Mandatory stages to be cleared by RQS/VSSC

    DP Kit

    Page 8 of 9

    UT guage

    Vernier caliper

    Bevel protractor

    TOOLINGSDESCRIPTION

    0.1 C

  • 8/2/2019 RLV SB Process Sheet

    28/155

    PROCESS SHEET NO : REV.NO

    CLIENT :PART NAME : RLV-SB HE SEGMENT MATL :

    OPN.NO STAGE

    005# Inspection

    issue 2, July 2005.

    Note 5: Mark RT zones by paint and retain the marking by paint and transfer the RT

    marking to inspection log book

    untill proof pressure test with traceability.

    Template and Feeler guage

    to be identified as shown in drawing.Note 1: Idn.No shall be retained during all stages of fabrication and weld joint

    Allot Assembly identification as RLV-HES-02,03,04&05

    & Head End Dome pre assembly - 1No

    Note 2: Welding inspection as per Doc No MEE/QCI/QCP/007/2002-

    Note 3: Mismatch shall be calculated by taking thickness into account and checked by

    Note 4: Apply black japan during all stages of fabrication

    Verify the acceptance of Cylindrical Shell Qty-4 Nos. Grooved Ring - 1 No.

    template and feeler guage at an interval of 50mm. If the mismatch observed is more than

    Note 8: The Film density shall be kept as 1.8 to 2.5mm for X-Ray Radiography.

    Note 6: Selective Assembly of the shells shall be done to match Dia 996 +0.2-0.0

    Note 7: Hardness shall be checked on the trimmed portion of the shell and retained

    the specified, detailed mapping of mismatch at that location shall be provided.

    RLV-SB HE SEGMENT MACHINING RD06-25-05-02-3-17-13-10-110 R3 MOTOR CASE

    DESCRIPTION TOOLINGS

    RAMAKRISHNA ENGINEERING COMPANY, CHENNAI-106.

    PROCESS AND QUALITY CONTROL PLAN

    RLV-SB MOTOR CASE

    SHEET NO : 1 OF 9 PROJECT : RLV-SB

    10.01.2009APPLICABILITY 02- 05

    VSSCPART DRG.NO. REV NO. 15CDV 6

    RKE/RLV/68/PS-07 R1

    SUB ASSY NAME : REF DRG. NO. REV.NO QUANTITY : 1 NO PER

    WELDING RKE-RD-06-234-07 Sheet 1,2 &3 R4

  • 8/2/2019 RLV SB Process Sheet

    29/155

    OPN.NO STAGE

    010 Welding

    Lathe

    020 Fitting/

    Welding

    025# Inspection

    5. Mismatch

    030 Welding

    040 Lathe

    2. Trim one end of the shell by keeping 825mm length for shell 2 and prepare weld edge

    3. Set the purging fixture and set the shells by keeping 0.5 to 2mm root gap and

    2. Orientation of Long Seam Joint 90apart

    4. Root gap,

    3. Thickness of both ends at an interval of 50mm for computing mismatch UT Guage

    1.Compute for the length appx. 1775mm for shell assembly.

    Record the following

    Vernier caliper

    30 angle and 0.5 to 1 mm root face.

    3. Preserve the discarded portion.

    7. Get clearance from VSSC for welding

    Complete the welding by GTAW process in 1G position.

    shielding, inspect for the total length and record.

    Vernier Caliper

    Spider and shaft

    1. Clean 50mm width band from inside and outside for both the shells with emery and

    5. Inspect for the run out of the shell at both ends.

    shell level) facing each other and the each long seam weld is staggered by 90

    2. Spider should be positioned 60 mm inside from the shell end.

    6. Carryout DP test on WEP of both the shells and record.

    4. Load the shaft and spider assembly in the welding station and hold one end on the

    1. Load shell 1and shell 2 on shaft using 4 Nos of spiders and true within 0.3mm TIR

    D.P.Kit

    acetone.

    2. Clean the purging fixture also by blowing compressed air and finally by acetone.

    0.3mm mismatch or as per WPS

    1. Welder's qualification and adaptation

    4. Clean with acetone, ensure purging gas flow.

    Voltage, current, filler wire code number, diameter and gas flow for purging and

    5. Tack weld the joint at 75 to 100mm interval

    6. Tack length and spacing

    Mismatch checking template

    Feeler guage

    REFER STAGE-1 WELDING

    Page 2 of 9TOOLINGS

    chuck and other end on the tail stock.

    DESCRIPTION

    3. Shells should be positioned in such a way that prepared weld edges (at cylindrical

  • 8/2/2019 RLV SB Process Sheet

    30/155

    OPN.NO STAGE

    045# Inspection

    1

    2

    5. Angle 306. D.P.test

    7. Thickness near weld edge at 50mm interval & record

    050 Lathe

    REFER STAGE - 2 WELDING

    060 Fitting/ 1. Load the shell 3A on the shaft and check for the trueness, clamp, set the shell (shell 3A)Lathe

    5. Clean the purging fixture also by blowing compressed air and finally by acetone.

    6. Set the purging fixture and set the shells by keeping 0.5 to 2mm root gap and

    0.3mm mismatch

    7. Clean with acetone, ensure purging gas flow

    8. Tack weld the joint at 75 to 100mm interval.

    065# Inspection

    4. Root gap

    6. Tack length and spacing

    070 Welding

    and shell assembly with the root gap of 0.5 to 2mm and mismatch of 0.3mm or as per WPS Feeler Gauge2. The shells should be facing the WEP side of each other.

    Vernier caliper

    Dial setup

    Dial setup

    3. Thickness of both ends at an interval of 50mm UT guage

    Mismatch checking template

    Feeler guage

    Record the following

    Vernier caliper

    1. Welder's qualification and adaptation

    2. Orientation of shells LS 90apart

    5. Mismatch

    3. Long seam orientation should be staggered by 90for adjacent shells.4. Clean both the side of the shells with emery and acetone for a band of 50mm.

    Vernier Caliper

    3rd and 4th spiders at a distance of 375mm from the WEP edge.

    edge. Identify 430mm length shell as A & other shell as B.

    True the shell within 0.3mm TIR. Part off at a distance of 430mm from the prepared weld

    Mismatch checking template

    3. Length 1775 and ( 825mm)

    4. Root face 0.5 to 1mm

    Page 3 of 9

    DESCRIPTION TOOLINGS

    Vernier caliper

    Set the third shell by using four spiders, two numbers at both ends leaving 60mm and

    D.P.Kit

    UT Gauge/Ball Point Mic

    Bevel protractor

    Inspect for

    7. Get clearance from VSSC for welding

    Complete the welding by GTAW process in 1G position.

    Voltage, current, filler wire code number, diameter and gas flow purging and shielding

    0.1 A

    0.2 A

  • 8/2/2019 RLV SB Process Sheet

    31/155

    OPN.NO STAGE

    080 Lathe

    085# Inspection

    1

    2

    3. Length 2175 and (400mm)

    4. Root face 0.5 to 1mm

    5. Angle 30

    6. D.P. test

    090 Lathe Load the shell(4) on spiders by keeping the prepared weld edge facing

    Clean the weld edges with emery and acetone.

    Load the welding fixture and set the job in such a way that LS of welds are

    Adjust the spiders to control mismatch with 0.3mm and a root gap of

    095# Inspection

    100 Welding

    3.Preserve the discarded portions.

    staggered by 90 apart.

    REFER STAGE - 3 WELDING

    DESCRIPTION

    4. Root gap,

    7. Get clearance from VSSC for welding

    3. Thickness of both ends at an interval of 50mm

    Feeler guage

    6. Tack length and spacing

    Vernier caliper

    2. Orientation of shells LS 90apart

    5. Mismatch.

    each other as shown in Stage 3 Welding. True the shell on spider within 0.3mm.

    Dial setup

    Complete the welding by GTAW process in 1G position.

    Record the following

    Voltage, current, filler wire code number, diameter and gas flow for shielding and purging.

    Vernier caliper

    1.Compute for the total length of shell approx. 2175mm

    TOOLINGS

    root face and 30angle.

    Dial setup

    7. Thickness near weld edge at 50mm interval and record.

    Inspect for

    2. Trim the third shell by keeping a length of 400mm and prepare weld edges 0.5 to 1mm

    Page 4 of 9

    0.5 to 2 mm or as per WPS Tack weld at an intervel of 75 to100 mm

    1. Welder's qualification and adaptation

    Vernier caliper

    Bevel protractor

    D.P.Kit

    UT Guage / Ball Point Mic

    Mismatch checking template

    UT guage

    Unload the assembly from fixture, remove spider & shaft.

    0.1 A

    0.2 A

  • 8/2/2019 RLV SB Process Sheet

    32/155

    OPN.NO STAGE

    105# Inspection

    110 Fitting

    115# Inspection

    1. Mismatch

    the thickness where parent metal is touched and map the thickness.

    120# Welding/

    Inspection

    130 Fitting

    135# Inspection Inspect for

    1.

    4. Root face 0.5 to 1mm

    5. Angle 30

    UT gauge

    3. Compute for the total length of the shells approximately 3075mm.

    4. Trim one end of the shell (Shell 4) by keeping 900mm length and prepare weld edge

    5. Preserve the discarded portion.

    on tail stock.

    2. Load the assembly in the welding station and hold one end on the chuck and other end

    7. Thickness near the weld edge at 50mm interval and record.

    Inspect for

    DESCRIPTION TOOLINGS

    Note: Fix adhesive tape on both sides before grinding

    Flush grind the penetration without touching parent metal (0.1mm projection max permitted)

    purging fixture

    Template and feeler gauge

    Page 5 of 9

    6. D.P.test

    3. Total length 3075 & (900 mm) Vernier caliper

    3. DP test

    Dial setup

    Dial setup

    2.

    D.P.Kit

    1. Load the shell assembly on shaft and spider and true within 0.3mm TIR

    4. 100% RT

    30angle and 0.5 to 1mm root face.

    Carryout repairs if any by gouging the defective area , weld & Inspect as per approved

    procedure.

    Inspect visual, weld bead and penetration dimensions. Identify the weld joint as

    RLV-HS-CS-XX-02 (shell 1 & 2)

    Vernier Caliper

    Mismatch Checking Template

    2. Visual for penetration grinding

    Note: Ensure that parent metal is not touched. Incase if parent metal is touched, record

    RLV-HS-CS-XX-04 (shell 3 & 4)

    CS = Cirseam Joint

    XX = Set serial no

    HS = Head end segment

    RLV-HS-CS-XX-03 (shell 2 & 3)

    0.2 A

    0.1 A

  • 8/2/2019 RLV SB Process Sheet

    33/155

    OPN.NO STAGE

    140 Welding /

    Fitting

    150 Welding/

    Fitting

    155# Inspection

    4. Mismatch

    160 Welding

    shell.

    170 Lathe

    175# Inspection

    6. Get clearance from VSSC for welding

    purging for both Joints.

    1. Compute for the length 3276.16+0.5/-0.0.

    Get clearance from inspection department for the computed length considering

    groove ring height and get clearance from VSSC.

    3. Preserve the discarded portion.length of (900mm)

    Feeler guage

    2. Thickness of both ends at an interval of 50mm for computing mismatch

    Record the following

    Voltage, current, filler wire code number, diameter and gas flow for sheilding and

    Set the root gap 0.5 to 2mm and mismatch within 0.3mm or as per WPS

    Tack weld the joint at 75 to 100mm intervals

    3. Root gap,

    5. Tack length and spacing

    2. Considering the triming allowance, trim and prepare weld edge on first shell keeping a

    1. Welder's qualification and adaptation

    Complete the welding by GTAW process in 1G position for c/s of HEDR to skirt and

    Vernier Caliper

    Mismatch checking template

    UT Guage

    Page 6 of 9

    DESCRIPTION TOOLINGS

    and acetone.

    Ensure cleanliness of the purging fixture and purging gas flow.

    3. Clean WEP of HED Ring, HE skirt and 'Y' ring end (in tacked condition)

    4. Clean 50mm band of shell circumference at WEP end outside and inside with emery

    1. Load the HE Dome Pre Assembly and true within 0.2mm TIR

    2. Insert cirseam Purging fixture on cleaned end of the shell.

    REFER STAGE- 4 WELDING

  • 8/2/2019 RLV SB Process Sheet

    34/155

    OPN.NO STAGE

    1

    2

    3. Total Length 3276.16+0.5/-0.0 & (900mm)

    4. Lip distance 0.5 to 1mm

    5. D.P. test on weld edge.

    6. Thickness near the weld edge at 50mm

    180 Welding/ REFER STAGE - 5 WELDING

    Fitting

    185* Inspection

    5. Tack length and spacing

    6. Total length 3418.66

    190* Welding

    Inspect for

    1

    2

    3

    3. Root gap,

    6. Inspect for the total length (3418.66)

    5. Tack weld the joint at 75 to 100mm interval

    2. Install cirseam Purging fixture

    Vernier caliper

    and inside with emery and acetone.

    Ensure cleanliness of the purging fixture and purging gas flow.

    3. Clean WEP of Grooved Ring

    4. Set the grooved ring by keeping root gap of 0.5 to 2mm and mismatch within 0.3mm

    4. Mismatch.

    1. Welder's qualification and adaptation

    Vernier caliper4. Total Length 3418.66

    Dial setup

    Vernier caliper

    1.Clean 50mm band of shell circumference outside

    Load the grooved ring in the shaft and spider assembly

    D.P.Kit

    Dial setup

    Vernier caliper

    UT guage

    Purging Fixture

    UT Gauge / Ball Point Mic

    Dial setup

    Feeler guage

    Mismatch checking template

    Dial setup

    Dial setup

    Complete the welding by GTAW process in 1G position.

    7. Get clearance from VSSC for welding

    Voltage, current, filler wire code number, diameter and gas flow for purging & sheilding.

    Record the following

    unload the job from the machine. Remove spider & shaft

    TOOLINGS

    Page 7 of 9

    DESCRIPTION

    Inspect for

    2. Thickness of both ends at an interval of 50mm

    0.5 A

    0.2 A

    0.5 A

    0.1 A

    0.2 A

    P 8 f 9

  • 8/2/2019 RLV SB Process Sheet

    35/155

    OPN.NO STAGE

    195# Inspection

    Identify the weld joint as

    1. RLV-HS-CS-XX-01 (HEDR # HE Skirt)

    2. RLV-HS-CS-XX-05 (HEDR # Shell 4)

    3. RLV-HS-CS-XX-06 (Shell 1 # Grooved Ring)

    CS = Cirseam JointXX = Set serial no

    200 Fitting

    205# Inspection

    300# Welding/

    Inspection

    305* Inspection 1 of shell2

    2

    5. Angle 30

    7 of shell 3

    8

    9. Length (400), 2175

    Page 8 of 9

    Note 1: Fix Adhesive tape on both sides of the welding before grinding.

    3. Length (950), (825), (1775)

    Note 2: Grinding need not be done for C/S joint between skirt and HEDR

    6. D.P Test of weld edge of shell 2

    1. Visual for penetration grinding. Ensure that parent metal is not touched. In case if

    parent metal is touched, record the thickness where parent metal is touched and map.

    procedure.

    Record the inspected dimension and prepare inspection report

    4. Lip distance 0.5 to 1mm

    3. D.P.of weld joint

    Carryout repairs if any by gouging the defective area , weld & Inspect as per approved

    Inside mic

    4. 100% RT X-Ray machine

    HS = Head end segment

    TOOLINGS

    Inspect visual, weld bead and penetration of all joints

    DESCRIPTION

    Dial setup

    Bevel Protractor

    D.P.Kit

    Vernier caliper

    Vernier caliper

    D.P.Kit

    Dial setup

    Dial setup

    Vernier caliper

    Inspect..

    (0.1mm projection max. permitted)

    Flush grind penetration without touching the parent metal

    Dial setup

    3X magnifying glass

    2. Mismatch

    0.1 A

    0.2 A

    0.1 A

    0.2 A

    P 9 f 9

  • 8/2/2019 RLV SB Process Sheet

    36/155

    OPN.NO STAGE

    11. Angle 30

    13 of shell 4

    14

    19 of shell 1

    20 of shell 1

    23. Angle 30

    24. D.P test of shell 1

    25

    29. 3418.66

    # Mandatory stages to be cleared by VSSC

    15. (length (900), 3075)

    17. Angle 30

    21. Length 3276.16+0.5/0.0

    16. Lip distance 0.5 to 1mm

    26

    27

    Bevel Protractor

    Bevel Protractor

    18. D.P test of weld edge of shell 4

    Vernier caliper

    22. Lip distance 0.5 to 1mm of shell 1 Vernier caliper

    Dial setup

    Dial setup

    12. D.P test of shell 3 D.P.Kit

    10. Lip distance 0.5 to 1mm

    Get clearance from VSSC for further processing.

    28. LS weld staggered by 90

    Vernier caliper

    Inside mic

    Inside mic

    30. Ovality grooved ring at 16 generators

    31. Ovality HEDR at 16 generators

    Dial setup

    Vernier caliper

    Page 9 of 9

    DESCRIPTION TOOLINGS

    Vernier caliper

    Bevel Protractor

    Dial setup

    Dial setup

    Dial setup

    D.P.Kit

    Vernier caliper

    Dial setup

    D.P.Kit

    0.5 A

    0.5 A

    0.1 A

    0.2 A

    0.1 A

    0.2 A

    0.2 A

    RAMAKRISHNA ENGINEERING COMPANY CHENNAI 106

  • 8/2/2019 RLV SB Process Sheet

    37/155

    20.01.2009

    PROCESS SHEET NO : REV.NO

    CLIENT :

    PART NAME : RLV-SB HEAD END MATL :

    OPN.NO STAGE

    005# Inspection

    010 Lathe

    020 Lathe

    Vernier caliper

    Face to maintain 20mm length (Refer the computed value for total length)

    Bore ID 959.5 through

    Turn OD 226 and face to maintain thickness 7 (min)

    Vernier Caliper

    Note: Ensure minimum thickness is achieved at one cross section

    Bore ID 188+0.046 & ensure thickness 3.5min. form Radius 2.5

    Turn OD 1033.5 -0.195 - 0.360 through

    Inside Micrometer

    Tape

    UT Gauge

    Record the setting reading in log book

    MACHINING OF IGNITOR BOSS (Refer Drawing Detail H):

    Confirm the acceptance of Head End Segment weld assy.

    Spider & shaft

    Check for the face out of grooved ring and skirt ring

    True the shells within 0.3mm and record

    Check for the runout of skirt ring 1040 and OD of the grooved ring.

    Dial SetupTighten the spiders. Set HE,Skirt and Groove Ring to a minimum runout condition

    RLV-SB MOTOR CASE ASSY RD06-25-05-02-3-17-13-10-110 Sheet 1 &2 R3 ASSY.

    DESCRIPTION TOOLINGS

    Verify that the Idn.No RLV-HES-02,03 etc., is painted on the shell portion

    Load the job on spiders and shaft.

    RKE-RD-06-234-08 Sheet 1 & 2 R5

    SUB ASSY NAME : REF DRG. NO. REV.NO QUANTITY : 1 NO PER

    SEGMENT MACHINING

    15CDV6

    RAMAKRISHNA ENGINEERING COMPANY, CHENNAI-106.

    PROCESS AND QUALITY CONTROL PLAN

    SHEET NO : 1 OF 7 PROJECT : RLV-SB

    RLV-SB MOTOR CASE

    APPLICABILITY 02- 05

    RKE/RLV/68/PS-08 R1 VSSC

    Compute for the machining allowance and record

    MACHINING OF HE SKIRT RING (Refer Drawing Detail E):

    PART DRG.NO. REV NO.

    Dial on 180 and compute for the machining allowance to achieve 3.5mm thickness

    of the flange. Skin cut on skirt ring face, HE dome ring face and grooved ring face

    Page 2 of 7

  • 8/2/2019 RLV SB Process Sheet

    38/155

    OPN.NO STAGE

    025 # Inspection

    4) 226.0

    030 Lathe

    040 Fitting

    045# Inspection

    Vernier Caliper

    Vernier Caliper

    groove to a depth of 38+0.5/-0.0 and ID 991.5 +0.17/-0.31 and groove OD

    Note: Ensure smooth surface finish of 'O' ring groove. Inspect visual and record in

    Page 2 of 7TOOLINGS

    and form radius R0.5 at 4 locations Chemfer 2x45.

    1004.5+0.5/-0.0.Turn 987.5-0.17/-0.31 to a depth of 14.8mm ( 6.7 + 4.1+4)

    Taper turn 991.5-0.17/-0.31 to 987.5-0.17/-0.31 ensuring 21.7+0.5/-0.0

    length. Form 'O' ring groove (3.95 depth x 6.7+0.1/-0.0 width)

    Inspect for the following:

    Section-XX

    2) Length (3517.3),

    1) Length 3385.30.5

    Mark P+ Axis by taking reference on LS weld joint

    Visual by QC

    Compute for length 38+0.5/-0.0 and 3385.30.5 and face to maintain these lengths.

    3) 1033.5 -0.195-0.360

    MACHINING OF GROOVED RING (REFER DRAWING DETAIL F & F1):

    Step turn 991.5-0.17/-0.31 for 24.1mm length. Inspect and record. Bore the

    Inside Micrometer

    Inspect for

    I/S Micrometer

    Compute from OD2) 959.5

    DESCRIPTION

    1) 188+0.046/-0.0

    Vernier Caliper

    Micrometer

    Tape

    Turn OD 1014.5+0.1/-0.0 through

    Vernier Setup

    Dial Setup

    4) Skirt face

    Marking shall be on grooved ring, skirt ring, 226 of HE dome ring & face

    in log book.

    3) Length 131.5

    Mark 614.5,579.5,597 & 400 on HE Dome for weld pad location.

    Dial Setup

    5) Skirt OD

    Bore ID 973.5+0.09/-0.0 through Compute from ID

    0.1 C

    0.4 E

    Page 3 of 7

  • 8/2/2019 RLV SB Process Sheet

    39/155

    OPN.NO STAGE

    Detail E:

    15) 959.5

    16) 20 at two places.

    14) 1033.5 -0.195-0.360 Tape

    17) 1014.5+0.1

    Computed from OD

    Vernier Caliper

    Detail- F

    Tape

    TOOLINGS

    9) (3.5mm) minimum UT Gauge10) 7 (minimum) Vernier Caliper

    Detail - H:

    8) R2.5 Radius Gauge

    13) Perpendicularity on Ignitor Boss face Dial Setup

    6) 188+0.046 Inside Micrometer7) 226.0 Micrometer

    Vernier Caliper12) Concentricity on 188 Dial Setup

    22) Visual observation of groove

    23) 2x45

    29) 991.5-0.17/-0.31

    Detail - F1:26) 987.5-0.17/-0.31

    Dial Setup

    Dial Setup24) Perpendicularity on grooved ring inner lip

    Vernier Caliper

    27) 973.5+0.09 Inside Micrometer

    28) 979.60.1 Computed

    30) 21.7+0.5 Vernier Caliper

    18) 1004.5+0.5

    20) 24.1-0.1/-0.2

    DESCRIPTIONg

    Computed Value

    Depth Gauge

    11) (45.3)mm

    19) 38+0.5 Depth Gauge

    21) R0.5 at 2 places Visual

    25) Concentricity on 1004.5

    Computed for ID

    31) 6.7+0.1 Vernier Caliper

    Micrometer computed

    0.4 E

    0.1 C

    0.1 C

    0.2 E

    Page 4 of 7

  • 8/2/2019 RLV SB Process Sheet

    40/155

    OPN.NO STAGE

    050 Fitting DRILLING OF IGNITOR BOSS FLANGE:

    055 # Inspection

    060 Drilling Drill 4.9 holes 32nos. Equispaced on 210 PCD starting at Y+. Inspect and record

    the orientation of the holes get clearance from QC.

    065# Inspection

    070 Fitting DRILLING OF SKIRT FLANGE:

    075 # Inspection

    080 Drilling

    from QC. Tap M16 x1.5P 4 H 12 holes (tap depth 16 min).Note: Use first tap only

    g

    Vernier Caliper

    RKE-JRJ-1930-202-16

    2. Drill 4.9 holes 6 nos. at P+ axis (Drill depth 12 max). Inspect for orientation of

    Note: Use first tap only

    and record.

    DESCRIPTION

    32) (6.9)

    Clamp the jig & transfer Y+, Y- & P- axis from Jig to the job and record.

    Tap M6x1P -4H, 32 nos.

    Vernier Caliper

    TOOLINGS

    37) Concentricity on 991.5 Dial Setup

    36) 4.1+0.1 Vernier Caliper

    Clamp the jig & transfer P-, Y+ & Y- axis on the job from the jig and record.

    Dial Setup

    Drill Jig No:

    33) R0.5 at 4 places

    35) 4.0

    Get Clearance from VSSC for drilling operation.

    Position the drill Jig by locating on 188, coincide P+ marking of Jig and the job.

    Inspect for the holes with reference to Jig and get clearance for unloading the jig..

    Visual

    Visual

    Drill Jig No:Position the drill Jig by locating on 1033.5 and coincide the P+ marking.

    Inspect for the orientation of the drill Jig, alignment of P+ marking on the jig & job

    RKE-RD-06-234-T-23

    and record.

    1. Drill 14.3 holes 12nos. Starting at 2230 min from P+ towards Y+ and on

    Inspect for the orientation of drill Jig, alignment of P+ marking on the jig & job

    996.5 PCD (Drill depth 20 max). Inspect for orientation of the holes and get clearance

    34) Visual observation of groove

    38) Concentricity on 973.5

    the holes and get clearance from QC. Tap M6 x 1P 4H 6 holes (tap depth 9 min)

    0.2 E

    0.2 E

    Note: Use first tap only

  • 8/2/2019 RLV SB Process Sheet

    41/155

    Page 5 of 7

  • 8/2/2019 RLV SB Process Sheet

    42/155

    OPN.NO STAGE

    Tap M6 x 1P 4H 35 holes (tap depth 9 min)

    Note: 1. Use first tap only2. Inspect visual for the liner bush ID after each drilling/reaming for damage

    if any.

    085 # Inspection Inspect for the holes with reference to Jig .

    Get clearance from VSSC to unload the job from the machine.

    090 IC Jig DRILLING OF SEGMENT PIN HOLES:

    095# Inspection

    100 Drilling

    Ream the holes of 12+0.018.

    Check with GO NO GO Plug guage. Lock the holes with pins.

    Ream the holes of 12+0.018mm.

    105 # Inspection

    110 Fitting

    120 Fitting

    Mark the strap ring attachment holes at P+ and P-. Drill 3mm holes 6nos. each at

    Bore Dial Gauge

    Go & No Go Gauge

    Get clearance from VSSC to unload the job from the Jig.

    DESCRIPTION TOOLINGS

    Load the assy on interchangable drill Jig & coincide the P+ marking on jig and job

    Inspect for 12+0.018 & depth of 16.5mm+0.2 with Jig in position.

    Feeler Gauge

    True the groove ring OD within 0.1mm and clamp.

    orientation holes and get clearance from QC.

    Open up the hole to 11.5mm X 15mm depth.

    Inspect for face butting with feeler gauge(max. gap 0.05mm), Jig orientation and

    Drill 6 holes 3nos 120apart to a depth of 15.0mm and lock.

    Depth Gauge

    DRILLING OF STRAP RING ATTACHMENT HOLE:

    Unload the segment and load on the trolley.

    4. Drill 4.9 holes at 5 locations 7nos each (Drill depth 11 max). Inspect for the

    setup. Verify the P+marking on Jig and job are coincided .

    Complete tapping of M6 and M16 holes

    1005.5 PCD. Inspect for the orientation of holes and get clearance from QC.

    3. Drill and ream 5 holes 2 nos. at P+ axis 6 deep on 980.5 PCD and 7.5 deep on

    Note: Check with Go & No Go plug Gauge after reaming of every 5 holes

    Open up the hole to 11.5mm X 15mm depth.

    Drill 6 holes 69nos to a depth of 15.0mm.

    With flat drill increase the depth to 16.5mm,

    With flat drill increase the depth to 16.5mm,

    P+ and P- on grooved ring as shown in developed view R. Set one of the strap ring

  • 8/2/2019 RLV SB Process Sheet

    43/155

    OPN NO STAGE DESCRIPTION TOOLINGS

    Page 6 of 7

  • 8/2/2019 RLV SB Process Sheet

    44/155

    OPN.NO STAGE

    130 Fitting

    140 Fitting

    145 # Inspection

    Detail - F & Section ZZ:

    40) 16.5 + 0.2

    41) 42.1/-0.1/-0.2

    42) R0.5 at 2 places

    43) mm

    44) Visual observation of hole & finish

    49) 215' 0.2' (typ)

    50) 430' 0.2' (typ)

    51) 9 2' (typ)

    55) 5 Hole, 6 Deep

    56) 5 Hole, 7.5 Deep

    view R. Tap M5x0.8P (4H). Repeat for other position also.

    location as shown in view-M

    Mark the cutout as per sketch inline with the P+ and P- axis

    Drill 4.1holes x 6nos. each at P+ and P- on grooved ring as shown in Developed

    DESCRIPTION

    in position on grooved ring OD such that centre line of half ring matches with

    P+ axis on grooved ring. Hold the strap ring in position and clamp . Verify the

    Drill and open out the cutout 100x60mm and radius 30.0mm

    matching of 5.2 holes on strap ring & 3 holes on grooved ring. Remove the strap.

    53) 2230' 0.2' (typ)

    Drill 3.1, 5nos through and 1no. 8mm deep as per drawing.

    46) 439' 0.2' (typ)

    39) 12+0.018x72nos 230' from Y+

    Vernier Caliper

    Go No Go Plug / Bore Dial Gauge

    IC Jig

    TOOLINGS

    Tap M5x0.8P, 6H 2 nos.

    Drill 4.1, 2 nos.x 8mm depth.

    Inspect for the following:

    Tap M4 x 0.7P, 6H 6 nos.

    Go No Go Gauge / Vernier

    Depth Gauge

    Micrometer & Setup

    47) 918' 0.2' (typ)

    48)163' 0.2' (typ)

    View N - Section BB ,Section DD and Detail - C:

    45) M6 x1P 4H 41 holes 9(min) and 12(max)

    Visual

    Drill Jig

    52) M16 x 1.5 4H 12 holes 20(max) for drilling 16(min) for tapping

    57) M6x1 4H, 32nos starting at Y+

    54) 15 0.2' (typ)

    Drill Jig

    Go No Go Gauge

    Vernier Caliper

    Go No Go Gauge / Drill Jig

    18.0

    OPN NO STAGE

    Page 7of 7

    DESCRIPTION TOOLINGS

  • 8/2/2019 RLV SB Process Sheet

    45/155

    OPN.NO STAGE

    68) 65.0mm

    # Mandatory stages to be cleared by RQS/VSSC

    Get Clearance from VSSC for weld pad welding.

    P+ and P- axis x 8 deep.

    removal of Spider. Ovality inspected at earlier stage of weld assembly & reported.

    Note: Spider are not to be removed at this stage Ovality will be inspected after PPT &

    65) 80mm

    59) M4 x 0.7P 6H 6nos. each at P+and P- axis as shown.

    60) Cutout at 2 locations P+ and P- axis

    63) 40mm

    64) 16mm

    62) 60mm

    72) 5

    73) 18mm

    58) M5x0.8-6H holes, 2 nos. each 50mm centre distance from

    70) 115'

    66) 100mm

    67) 130mm

    Developed view - R & Section -YY:

    61) R30

    View-M & Section - KK:

    71) 345'

    Radius Gauge

    DESCRIPTION TOOLINGS

    Go No Go Gauge

    Go No Go Gauge69) M5x0.8-4H,6 nos each at P+ & P- inline with seg.holding pin

    Vernier Caliper

    Vernier Caliper

    Vernier Caliper

    Vernier Caliper

    Chord Measurements

    RAMAKRISHNA ENGINEERING COMPANY, CHENNAI-106.

  • 8/2/2019 RLV SB Process Sheet

    46/155

    PROCESS SHEET NO : REV.NO

    CLIENT :

    PART NAME : RLV-SB HEAD END MATL :

    OPN.NO STAGE

    #005 Inspection

    010 Fitting

    015 # Inspection

    020 Welding

    025# Inspection

    WELDING OF WIRE TUNNEL WELD PAD:

    Antenna Mounting weld pad - 8 Nos.

    Get clearance from VSSC for welding.

    face, and 250mm from the first pair of weld pad at 12 locations on P+ axis

    Set and tack weld wire tunnel weld pads at a distance of 223mm from the skirt ring

    Inspect for the weld pad locations and orientation of the weld pads with reference

    to the drawing.

    as shown in drawing.

    Mark the location of wire tunnel weld pads on segment assy with reference to

    Destruct System weld pads Part-II-4 Nos.

    Destruct System weld pads Part-I - 4 Nos.

    Destruct System weld pads Part -IV-8 Nos.

    Destruct System weld pads Part-V-16 Nos.

    DESCRIPTION

    Weld pad welding fixture No.

    Inspect for the weld pad orientation and fixture position.

    P+ axis as shown in drg. Clean the area with emery and acetone. RKE-RD-06-234-T-27

    Position the weld pad welding fixture and assemble the pads in position.

    Destruct System weld pads Part-III-10 Nos.

    QUANTITY : 1 No.

    TOOLINGS

    Confirm the acceptance of the following:

    Wire tunnel weld pad - 52 Nos.

    Head End Segment Assy - 1 No.

    RLV-SB MOTOR CASE ASSY RD06-25-05-02-3-17-13-10-170 R5

    SUB ASSY NAME : REF DRG. NO. REV.NO

    VSSCPART DRG.NO. REV NO. 15CDV6

    SEGMENT WELD PADS WELDING RKE-RD-06-234-09 Sheet 1& 2 R3

    RKE/RLV/68/PS-09 R1

    PROCESS AND QUALITY CONTROL PLAN

    RLV-SB MOTOR CASE

    SHEET NO : 1 OF 5 PROJECT : RLV-SB

    20.01.2009APPLICABILITY 02- 05

    OPN NO STAGE

    Page 2 of 5DESCRIPTION TOOLINGS

  • 8/2/2019 RLV SB Process Sheet

    47/155

    OPN.NO STAGE

    030 Welding

    040 Fitting/ Welding

    045 # Inspection

    050 Fitting

    055 Inspection

    060 Fitting

    070 Fitting/

    Welding

    075 Inspection

    080 Welding

    090 Fitting

    095# Inspection

    100 Fitting/

    Welding

    Carry out fillet weld of the pads on all four sides.

    Repeat operation 50 to 80 at 20from P-axis.

    Inspect for the orientation of weld pad.

    maintained and tack weld.

    1. Drill 4.1 holes 2nos. & Tap M5 x 0.8 P x 6H holes

    2. Drill 18 holes 1no.

    Position the weld pads in such a way that center distance of 88, 125 and 60mm are

    3. 60mm, 21mm, 125mm for weld pads.

    Inspect for marking.

    Mark the following at 20away from P+ and P- Axis.

    1. Centre distance of 60mm x12mm for two M5 x 0.8 P holes

    issue 2, July 2005)

    Complete the fillet welding (Ref. doc.no MEE/QCI/QCP/007/2002,

    WELDING OF ANTENNA MOUNTING WELD PAD (REFER DRAWING VIEW F)

    2. 67mm distance for 18 holes

    D.P. Kit

    Inspect the location of weld pad as per Section XX & Detail Z of the drawing.

    Repeat operation 10 to 30 for the completion of weld pad at P- axis.

    Mark 62', 718' position of weld pad part-I & part-II such a way that maintaining

    Carry out DP Test on the fillet welds.

    Mark the ref.circle 642.5, 597, 549 and transfer the center line P+,P-, Y+ & Y-

    WELDING OF DESTRUCT SYSTEM WELD PADS( PART I & II)

    Tack weld part I & II by maintaining 66mm & 11.5mm.

    35mm as per drg. Clean the area with Emery & Acetone.

    on head end dome.

    DESCRIPTION TOOLINGS

    Inspect for the location of weld pads, carry out DP test on fillet welds.

  • 8/2/2019 RLV SB Process Sheet

    48/155

    OPN.NO STAGE

    Page 3 of 5

    DESCRIPTION TOOLINGS

  • 8/2/2019 RLV SB Process Sheet

    49/155

    OPN.NO STAGE

    110 Welding/

    Fitting

    Tack weld part III & IV by maintaining 9mm & 34mm.

    120 Welding/Fitting

    125# Inspection

    130 Welding

    135 Inspection

    140# Inspection

    45(typ) at Y+ and Y- axis. Clean the area with Emery & Acetone.

    Mark the ref.circle 335.38, 400, 435.68 and mark line 14(typ) & 18(typ),

    Carry out fillet weld of the weld pads (Ref. doc.no MEE/QCI/QCP/007/2002,

    issue 2, July 2005)

    Inspect for the orientation of the weld pads and carry out DP Test on fillet weld.

    starting from P+ for weld pad & part-III. Clean the area with Emery & Acetone.

    Inspect for the following:

    9) 18(typ)

    10) 36(typ)

    View - N:

    8) 45(typ)

    WELDING OF DESTRUCT SYSTEM WELD PAD( Part III & IV)

    Detail - Z:

    4) 50

    5) 110

    6) 20

    7) Fillet weld size 3mm

    DESCRIPTION

    Drawing.

    Note: Fillet welding shall be done at two sides of the weld pad only as shown in

    Section - XX:

    Inspect the position of weld pads.

    1) 223mm

    2) 250x12nos.

    Mark the ref.circle 614.5, 597, 579.5 and mark line 36(typ), 18(typ)

    Welding Fixture No

    RKE-RD-06-234-T-23

    Tack weld part V by maintaining 9.67mm & 51.9mm.

    WELDING OF DESTRUCT SYSTEM WELD PAD( Part V)

    3) 38.0

    Vernier Caliper

    Vernier Caliper

    D.P.Kit

    TOOLINGS

    Vernier Caliper

  • 8/2/2019 RLV SB Process Sheet

    50/155

    OPN.NO STAGE DESCRIPTION TOOLINGS

    Page 4 of 5

  • 8/2/2019 RLV SB Process Sheet

    51/155

    View - F:

    37) 60mm

    30) Fillet size 3x45

    Vernier Caliper

    15) 665.5 (Ref)16) 551.5 (Ref)

    17) 11.5 + 2.0/+0.0

    31) (38)mm Vernier Caliper

    Detial - Z :

    13) 549

    14) 60(typ)

    12) 597 (Ref)

    11) 642.5

    Section - AA :

    32) (20)

    33) 50

    34) (110)mm

    36) Orientation 20from P+ and P-

    29) 35

    Detail - X :

    35) Fillet size 3 (typ)

    27) (718')

    28) (62')

    Vernier Caliper

    Vernier Caliper

    Vernier Caliper

    18) 66mm (typ)

    20) 597 (Ref)

    21) 579.5

    22) 34mm

    Section - BB :

    19) 614.5

    23) 635.5 (Ref)24) 576.5 (Ref)

    26) 60

    25) 9+2.0/+0.0

    Page 5 of 5

  • 8/2/2019 RLV SB Process Sheet

    52/155

    OPN.NO STAGE

    51) 435.68 (Ref)

    Vernier Caliper

    47) 75

    48) 9.67

    TOOLINGS

    40) 12.0

    GO NO GO Gauge

    49) 335.38

    50) 400 (Ref)

    44) 455.38 (Ref)

    45) 335.1 (Ref)

    46) 51.9 (typ)

    52) 14(typ)

    # Mandatory stages to be cleared by RQS/VSSC

    Vernier Caliper

    DP Kit / Vernier Caliper

    Vernier Caliper

    53) 18(typ)

    View - N:

    Section - CC:

    Get Clearance from VSSC for Proof Pressure Test.

    54) DP test on all fillets & f illet size.

    DESCRIPTION

    41) 88.0

    42) 125.043) 18 holes

    38) M5 x 0.8 P- 6 H x 10 deep

    39) 67.0

    RAMAKRISHNA ENGINEERING COMPANY, CHENNAI-106.

    PROCESS AND QUALITY CONTROL PLAN

  • 8/2/2019 RLV SB Process Sheet

    53/155

    PROCESS SHEET NO : REV.NO

    CLIENT :

    PART NAME : RLV-SB MIDDLE SEGMENT MATL :

    OPN.NO STAGE

    005# Inspection

    July 2005.

    RLV-SB MOTOR CASE

    SHEET NO : 1 OF 9 PROJECT : RLV-SB

    12.01.2009

    VSSC

    PART DRG.NO. REV NO. 15CDV 6

    SUB ASSY NAME : REF DRG. NO. REV.NO QUANTITY : 1 NO PER

    WELDING RKE-RD-06-234-10 Sheet 1,2 & 3 R2

    RKE/RLV/68/PS-10 R1

    RLV-SB MIDDLE SEGMENT MACHINING RD06-25-05-02-3-17-13-10-120 R0 MOTOR CASE

    DESCRIPTION TOOLINGS

    &Tongued Ring - 1No

    Verify the acceptance of Cylindrical Shell Qty-4 Nos. Grooved Ring - 1 No.

    template and feeler guage at an interval of 50mm. If the mismatch observed is more than

    Template and Feeler guage

    to be identified as shown in drawing.

    Allot Assembly identification as RLV-MS-02,03,04 & 05

    the specified, detailed mapping of mismatch at that location shall be provided.

    Note 8: The Film density shall be kept as 1.8 to 2.5mm for X-Ray Radiography.

    Note 6: Selective Assembly of the shells shall be done to match Dia 996 +0.2-0.0

    Note 7: Hardness shall be checked on the trimmed portion of the shell and retained

    Note 1: Idn.No shall be retained during all stages of fabrication and weld joint

    Note 2: Welding inspection as per Doc No MEE/QCI/QCP/007/2002- Issue 2,

    Note 3: Mismatch shall be calculated by taking thickness into account and checked by

    Note 4: Apply black japan during all stages of fabrication

    Note 5: Mark RT zones by paint and retain the marking by paint and transfer the RT

    marking to inspection log book

    untill proof pressure test with traceability.

    APPLICABILITY 02- 05

    OPN.NO STAGEREFER STAGE-1 WELDING

    TOOLINGSDESCRIPTIONPage 2 of 9

  • 8/2/2019 RLV SB Process Sheet

    54/155

    010 Welding

    Lathe

    020 Fitting/

    Welding

    025# Inspection

    5. Mismatch

    030 Welding

    040 Lathe

    3. Thickness of both ends at an interval of 50mm for computing mismatch

    REFER STAGE 1 WELDING

    4. Root gap,

    4. Load the shaft and spider assembly in the welding station and hold one end on the

    shielding, inspect for the total length and record.

    6. Carry out DP test on WEP of both the shells and record.

    7. Get clearance from VSSC for welding

    1. Welder's qualification and adaptation

    2. Orientation of Long Seam Joint 90apart

    3. Preserve the discarded portion.

    Feeler guage

    Voltage, current, filler wire code number, diameter and gas flow for purging and

    30 angle and 0.5 to 1 mm root face.

    chuck and other end on the tail stock.

    5. Tack weld the joint at 75 to 100mm interval

    4. Clean with acetone, ensure purging gas flow.

    D.P.Kit

    0.3mm mismatch or as per WPS

    3. Shells should be positioned in such a way that prepared weld edges (at cylindrical

    Spider and shaft

    2. Clean the purging fixture also by blowing compressed air and finally by acetone.

    1. Clean 50mm width band from inside and outside for both the shells with emery and

    1. Load shell 1 and shell 2 on shaft using 4 Nos of spiders and true within 0.3mm TIR

    shell level) facing each other and the each long seam weld is staggered by 90

    5. Inspect for the run out of the shell at both ends.

    acetone.

    2. Spider should be positioned 60 mm inside from the shell end.

    Complete the welding by GTAW process in 1G position.

    Vernier Caliper

    1.Compute for the total length of the shells app. 1895mm for shell assembly

    & accordingly discard

    Mismatch checking template

    Vernier caliper6. Tack length and spacing

    3. Set the purging fixture and set the shells by keeping 0.5 to 2mm root gap and

    2.Trim one end of the shell by keeping 945mm length for shell 2 and prepare weld edge

    UT Guage

    Record the following

    OPN.NO STAGE

    045# Inspection

    Page 3 of 9

    DESCRIPTION TOOLINGS

    Inspect for

  • 8/2/2019 RLV SB Process Sheet

    55/155

    045# Inspection

    1

    2

    3. Length 1895 & ( 945mm)

    4. Lip distance 0.5 to 1mm

    5. Angle 306. D.P.test

    7. Thickness near weld edge at 50mm interval & record

    REFER STAGE - 2 WELDING

    050 Fitting/ 1. Load the shell 3B on the shaft and check for the trueness, clamp, set the shell (shell 3B)

    Lathe

    5. Clean the purging fixture also by blowing compressed air and finally by acetone.

    6. Set the purging fixture and set the shells by keeping 0.5 to 1.5mm root gap and0.3mm mismatch

    7. Clean with acetone, ensure purging gas flow

    8. Tack weld the joint at 75 to 100mm interval.

    055# Inspection

    4. Root gap

    6. Tack length and spacing

    060 Welding

    Voltage, current, filler wire code number, diameter and gas flow purging and shielding.

    3. Thickness of both ends at an interval of 50mm

    Vernier caliper

    3. Long seam orientation should be staggered by 90for adjacent shells.

    UT guage

    7. Get clearance from VSSC for welding

    5. Mismatch

    Mismatch checking template

    Record the following:

    Mismatch checking template

    and shell assembly with the root gap of 0.5 to 2mm and mismatch of 0.2mm or as per WPS Feeler Gauge

    1. Welder's qualification and adaptation

    Feeler guage2. Orientation of shells LS 90apart

    Complete the welding by GTAW process in 1G position.

    Dial setup

    Dial setup

    UT Gauge/Ball Point Mic

    D.P.Kit

    4. Clean both the side of the shells with emery and acetone for a band of 50mm.

    Bevel protractor

    Vernier caliper

    2. The shells should be facing the WEP side of each other.

    Vernier caliper

    Inspect for

    0.1 A

    0.2 A

    OPN.NO STAGE

    070 Lathe

    DESCRIPTION

    Page 4 of 9TOOLINGS

    1. Compute for the total length of the shells app. 2352mm for shell assembly

  • 8/2/2019 RLV SB Process Sheet

    56/155

    075# Inspection

    1

    2

    3. Length 2352 &(457mm)

    4. Root face 0.5 to 1mm

    5. Angle 30

    6. D.P. test

    080 Lathe Load the shell(4) on spiders by keeping the prepared weld edge facing

    Clean the weld edges with emery and acetone.

    Load the welding fixture and set the job in such a way that LS of welds are

    Adjust the spiders to control mismatch with 0.2mm and a root gap of

    Tack weld at an intervel of 75 to100 mm

    085# Inspection

    090 Welding

    purging. Unload the assembly from the fixture, remove spider & shaft.

    REFER STAGE - 3 WELDING

    2. Trim one end of the shell by keeping 457mm length for shell 3B and prepare weld edge

    30 angle and 0.5 to 1 mm root face.

    Bevel protractor

    UT guageVernier caliper

    Dial setup

    Vernier caliper

    Vernier caliper

    Dial setup

    D.P.Kit

    UT Guage / Ball Point Mic

    1. Welder's qualification and adaptation

    3. Thickness of both ends at an interval of 50mm

    Inspect for

    3. Preserve the discarded portion.

    Mismatch checking template

    7. Thickness near weld edge at 50mm interval and record.

    staggered by 90 apart.

    0.5 to 2 mm or as per WPS

    each other as shown in Stage 3 Welding. True the shell on spider within 0.3mm.

    2. Orientation of shells LS 90apart Feeler guage

    5. Mismatch

    6. Tack length and spacing

    Record the following

    Complete the welding by GTAW process in 1G position.

    p g pp y

    & accordingly discard

    Voltage, current, filler wire code number diameter and gas flow for shielding and

    4. Root gap

    7. Get clearance from VSSC for welding

    0.1 A

    0.2 A

    OPN.NO STAGE

    095# Inspection Inspect visual, weld bead and penetration dimensions. Identify the weld joint as

    TOOLINGSDESCRIPTION

    Page 5 of 9

  • 8/2/2019 RLV SB Process Sheet

    57/155

    p

    100 Fitting

    105# Inspection

    1. Mismatch

    the thickness where parent metal is touched and map the thickness.

    110 Welding/

    Inspection

    120 Fitting

    130 Lathe

    30angle and 0.5 to 1mm root face.

    1. Load the shell assembly on shaft and spider and true within 0.3mm TIR

    2. Load the assembly in the welding station and hold one end on the chuck and other end purging fixture

    5. Preserve the discarded portion.

    on tail stock.

    3. Compute for the total length of the shells approximately 3302mm .

    4. Trim one end of the shell (Shell 4) by keeping 950mm length and prepare weld edge

    3. DP test D.P.Kit

    Carryout repairs if any by gouging the defective area , weld & Inspect as per approved

    procedure.

    4. 100% RT

    Inspect for

    MS = Middle segment

    2. Visual for penetration grinding

    Note: Ensure that parent metal is not touched. Incase if parent metal is touched, record UT gauge

    RLV- MS - CS - XX - 09 ( Shell 2 & 3B)

    RLV- MS - CS - XX - 10 ( Shell 1& 2)

    Note : Fix adhesive tape on both sides before grinding

    XX = Set serial no

    CS = Cirseam Joint

    Flush grind the penetration without touching parent metal (0.1mm projection max permitted)

    p p y j

    RLV- MS - CS - XX - 08 ( Shell 3B & 4)

    30 angle and 0.5 to 1 mm lip distances

    1. Compute for the total length of the shells app. 3302mm & accordingly discard

    Template and feeler gauge

    2. Trim one end of the shell (shell 4) by keeping 950mm length and prepare weld edge

    3. Preserve the discarded portion.

    OPN.NO STAGE

    135# Inspection Inspect for

    DESCRIPTION

    Page 6 of 9

    TOOLINGS

  • 8/2/2019 RLV SB Process Sheet

    58/155

    1

    2

    3. Total Length 3302 & (950mm)

    4. Root face 0.5 to 1mm

    5. Angle 30

    6. D.P. test

    7. Thickness near the weld edge at 50mm interval and record.

    140 Welding /

    Fitting

    150 Welding/

    Fitting

    155# Inspection

    4. Mismatch

    160 Welding

    170 Lathe

    175 # Inspection

    Note: Compute for the length 3421.6+0.5/-0.0 and discard accordingly.

    Get clearance from inspection department for the computed length considering

    grooved ring height and get clearance from VSSC.

    length of (950mm)

    D.P.Kit

    UT Guage

    Bevel protractor

    purging fixture

    Mismatch checking template

    Dial setup

    Vernier caliper

    Dial setup

    1. Load the Tongued ring on the shaft and true within 0.2mm TIR

    Complete the welding by GTAW process in 1G position for c/s of Tongued ring and shell.

    Feeler guage

    Voltage, current, filler wire code number,diameter and gas flow for sheilding and

    Vernier Caliper

    Considering the triming allowance, trim and prepare weld edge on first shell keeping a

    5. Tack length and spacing

    purging.

    emery and acetone.

    Record the following

    1. Welder's qualification and adaptation

    REFER STAGE - 4 WELDING

    Tack weld the joint at 75 to 100mm intervals

    6. Get clearance from VSSC for welding

    2. Insert cirseam Purging fixture on cleaned end of the shell.

    4. Clean 25mm band of shell circumference at WEP end outside and inside with

    Vernier caliper

    Set the root gap 0.5 to 1.5mm and mismatch within 0.2mm or as per WPS

    2. Thickness of both ends at an interval of 50mm for computing mismatch

    Ensure cleanliness of the purging fixture and purging gas flow.

    3. Clean WEP of Tongued Ring & Shell

    3. Root gap,

    0.1 A

    0.2 A

    OPN.NO STAGE DESCRIPTION

    Inspect for

    Page 7 of 9

    TOOLINGS

  • 8/2/2019 RLV SB Process Sheet

    59/155

    1

    2

    3. Total Length 3421.6+0.5/-0.0 & (950mm)

    4. Lip distance 0.5 to 1mm

    5. D.P. test on weld edge.6. Thickness near the weld edge at 50mm

    180 Welding/

    Fitting

    185# Inspection

    5. Tack length and spacing

    190# Welding

    Inspect for

    1

    2

    3

    Dial setup

    REFER STAGE - 5 WELDING

    1.Clean 50mm band of shell circumference outside

    Complete the welding by GTAW process in 1G position between GR & Shell 1.

    Dial setup

    Load the Grooved ring in the shaft and spider assembly and true within 0.5mm

    2. Install cirseam Purging fixture

    Ensure cleanliness of the purging fixture and purging gas flow.

    3. Clean WEP of Grooved Ring

    5. Tack weld the joint at 75 to 100mm interval

    Dial setup

    D.P.KitUT Gauge / Ball Point Mic

    Vernier caliper

    Purging Fixture

    and inside with emery and acetone.

    4. Set the Tongued ring by keeping root gap of 0.5 to 2mm and mismatch within 0.2mm

    Vernier caliper

    Dial setup

    unload the job from the machine. Remove spider & shaft

    Dial setup

    4. Total Length 3564.1 Vernier caliper

    3. Root gap,

    4. Mismatch.

    6. Get clearance from VSSC for welding

    Feeler guage

    1. Welder's qualification and adaptation

    2. Thickness of both ends at an interval of 50mm

    Record the followingVoltage, current, filler wire code number , diameter, gas flow for purging & sheilding.

    UT guage

    Mismatch checking template

    Vernier caliper 0.1 A

    0.2 A

    0.5 A

    0.2 A

    0.5 A

  • 8/2/2019 RLV SB Process Sheet

    60/155

    OPN.NO STAGE

    V i li

    TOOLINGS

    Page9 of 9

    DESCRIPTION

    16 Li di t 0 5 t 1

  • 8/2/2019 RLV SB Process Sheet

    61/155

    19 of shell 1

    20 of shell 1

    23. Angle 30

    24. D.P test of shell 1

    25

    29. 3564.1

    21. Length (950) & 32421.6+0.5/0.0

    26

    27

    18. D.P test of weld edge of shell 4

    22. Lip distance 0.5 to 1mm of shell 1

    Dial setup

    D.P.Kit

    Dial setup

    Bevel Protractor

    Bevel Protractor

    Vernier caliper

    Dial setup

    28. LS weld staggered by 90

    Vernier caliper

    Inside mic

    Inside mic31. Ovality Tongued ring 961.5 at 16 generators

    30. Ovality Grooved ring 969.5 at 16 generators

    Get Clearance from VSSC for weld pad welding.

    Vernier caliper

    Dial setup

    D.P.Kit

    Vernier caliper

    Dial setup

    # Mandatory stages to be cleared by VSSC

    17. Angle 30

    16. Lip distance 0.5 to 1mm

    0.5 A

    0.5 A

    0.1 A

    0.2 A

    0.2 A

    RAMAKRISHNA ENGINEERING COMPANY, CHENNAI-106.

    PROCESS AND QUALITY CONTROL PLAN

  • 8/2/2019 RLV SB Process Sheet

    62/155

    PROCESS SHEET NO : REV.NO

    CLIENT :

    PART NAME : RLV-SB MIDDLE SEGMENT MATL :

    OPN.NO STAGE005 # Inspection

    010 Lathe

    020 Lathe

    025 # Inspection

    Chamfer 2x45at 3 locations.

    Skin cut on tongued ring face and grooved ring face.

    Inspect for

    Face to maintain 53.5+0.5/-0.0 depth

    Bore 991.5+0.09+0.00 x 40.0 +.05/-0.0 depth

    Taper turn 987.5 to 991.5 by keeping 7mm (47-40) taper length

    Turn OD 1004.5-0.3/-0.7 through

    Bore ID 987.5 x 40mm length

    ptape/ Inside Mic & compute

    3) 965.5+0.09/+0.0

    Inspect for 987.5 +.09 +.00

    I/S Micrometer

    I/S Micrometer

    I/S Micrometer

    Compute for machining allowance and record. Record the setting reading in logbook.

    Inspect & Compute for length 68.7

    Face to maintain 68.7mm

    Form groove of 64.7 +0.10+.00 from face and 987.5+.09 +.00 & 973.5 - 0.17-0.31

    RLV-SB MOTOR CASE

    SHEET NO : 1 OF 6 PROJECT : RLV-SB

    20.01.2009

    APPLICABILITY 02- 05

    VSSC

    PART DRG.NO. REV. NO. 15CDV6

    MACHINING RKE-RD-06-234-11 R4

    RKE/RLV/68/PS-11 R1

    SUB ASSY NAME : REF DRG. NO. REV. NO. QUANTITY : 1 NO PER

    RLV-SB MOTOR CASE ASSY RD06-25-05-02-3-17-13-10-120 R0 ASSY

    True the shells within 0.3mm and record.

    Verify that the Idn.No RLV-MS-02,03 etc., is painted on the shell portion

    Load the job on spiders and shaft. Spider & shaft

    DESCRIPTION TOOLINGS

    Confirm the acceptance of the Middle segment Weld Assy.

    2) 991.5+0.09

    Tighten the spiders. Set for tongued ring and grooved ring with minimum runout. Dial Gauge setup

    Check for the faceout of tongued ring and grooved ring.Check for the runout of tongued ring OD and grooved ring OD.

    MACHINING OF TONGUED RING (REFER DRAWING DETAILS G & G1)

    Bore ID 965.5 +.09+.00 through

    I/S Micrometer1) 1004.5-0.3/-0.7

    OPN.NO STAGE

    Compute from OD5) 973 5 0 17/ 0 31

    Page 2 of 6DESCRIPTION TOOLINGS

    4) 987.5+0.09+0.00 checked before groove Machining I/S Micrometer

  • 8/2/2019 RLV SB Process Sheet

    63/155

    030 Lathe

    040 Fitting

    045# Inspection

    Compute from OD

    Face turn 24.1 depth and step turn 991.5-0.17/-0.31 for 24.1mm length and Inspect

    Inside Micrometer

    Note: Ensure smooth surface finish of 'O' ring groove and record.

    Turn OD 1014.5+0.1/-0.0 through

    Bore ID 973.5+0.09/-0.0 Compute from ID

    5) 973.5-0.17/-0.31

    Compute for length 38+0.5/-0.0 and 35300.5 and face.

    MACHINING OF GROOVED RING (REFER DRAWING DETAIL F & F1)

    Vernier Caliper

    Bore the groove to a depth of 38+0.5/-0.0 and ID 991.5 +0.17/-0.31

    Inspect for the following

    length. Form 'O' ring groove as per drawing (3.95 depth x 6.7+0.1/-0.0 width)

    and form radius R0.5 at 4 locations Chemfer 2x45

    6) Concentricity on 1004.5

    8) Concentricity on 973.5

    7) Concentricity on 987.5

    Tape

    and 1004.5+0.5/-0.0. Turn 987.5-0.17/-0.31, depth 14.8mm length ( 6.7 + 4.1+ 4)

    Taper turn 991.5-0.17/-0.31 to 987.5-0.17/-0.31 ensuring 21.7+0.5/-0.0

    Dial Setup

    Detail - G:

    Section - XX:

    3) 1004.5-0.3/-0.7

    Vernier Caliper

    4) 991.5+0.09 I/S Micrometer

    5) 965.5+0.09/+0.0 I/S Micrometer

    6) (75) Vernier Caliper

    7) (45) Vernier Caliper

    Vernier Caliper / Depth Gauge

    10) 53.5+0.5 Vernier Caliper

    9) (68.7)

    Mark P+ Axis by taking reference on LS weld joint

    Marking shall be on grooved ring and tongued ring OD & taper.

    1) 35300.5 Taper2) Concentricity on 1004.5 and 987.5

    8) 64.7+0.1/+0.05

    0.2 D

    0.2 D

    0.2 D

    0.2 E

    OPN.NO STAGE

    12) 40+0 5

    Page 3 of 6DESCRIPTION TOOLINGS

    11) 47+0.5 Vernier Caliper

    Vernier Caliper

  • 8/2/2019 RLV SB Process Sheet

    64/155

    22) Concentricity on 973.5

    14) Perpendicularity on Tongued Ring inner lip Dial setup

    30) Perpendicularity on Grooved ring Inner lip Dial setup

    16) Perpendicularity on Tongued ring Groove face.

    19) 987.5+0.09 Computed I/S Micrometer

    32) Concentricity on 1004.5

    12) 40+0.5

    31) Perpendicularity on Grooved ring Outer lip

    15) Perpendicularity on Tongued Ring outer lip

    17) Concentricity on 1004.5

    Vernier Caliper

    13) 2x45at 3 places Bevel Protractor

    Detail - G1:

    18) (15.2) Vernier Caliper

    20) 973.5-0.17/-0.31 Computed I/S Micrometer

    21) Concentricity on 987.5 Dial setup

    23) R0.5 at 2 places Visual

    24) 1014.5+0.1 TapeDetail - F:

    29) 2x45

    25) 1004.5+0.5 Computed

    26) 38+0.5 ; Vernier Caliper

    27) 24.1-0.1/-0.2

    28) R0.5 at 2 places

    I/S Micrometer

    35) 979.60.1

    34) 973.5+0.09

    Computed

    Detail - F1:

    33) 991.5-0.17/-0.31 Micrometer computed

    0.1 C

    0.1 C 0.1 C

    0.2 D

    0.2 D

    0.1 C

    0.1 C

    0.2 E

    0.2 D

    OPN.NO STAGE

    Page 4 of 6DESCRIPTION

    Vernier Caliper

    37) 6.7+0.1 Vernier Caliper

    TOOLINGS

    36) 987.5-0.17/-0.31

  • 8/2/2019 RLV SB Process Sheet

    65/155

    050 IC Jig

    055# Inspection

    060 Drilling

    Ream the holes of 12+0.018 x 16.5 +0.2/-0.0mm depth

    Check with GO NO GO Plug guage. Lock the holes with pins.

    Ream the holes of 12+0.018mm x 16.5 +0.2/-0.0mm depth.

    65 # Inspection

    70 IC Jig

    With flat drill increase the depth to 16.5mm,

    Load the assy on interchangable drill Jig by facing tongued ring at bottom and

    DRILLING OF SEGMENT PIN HOLES TONGUED RING:

    Coincide the P+ marking on the Jig & job.

    1. Load the assy on interchangable drill Jig by facing grooved ring at bottom and

    Drill 6 holes 69nos to a depth of 15.0mm.

    Depth Gauge

    coincide P+ marking on Jig & Job.

    Feeler Gauge

    2. True the groove ring OD within 0.1mm and clamp

    Open up the hole to 11.5mm X 15mm depth.

    Dial Setup

    Get clerance from VSSC to unload the job from the jig.

    True the tongued ring OD within 0.1mm and clamp.

    Inspect for 12+0.018 & depth of 16.5mm+0.2 with Jig in position. Go & No Go Gauge

    Open up the hole to 11.5mm X 15mm depth.

    Get clerance from VSSC to unload the job from the machine

    Vernier Caliper

    38) 21.7+0.5

    39) (6.9)

    With flat drill increase the depth to 16.5mm,

    P+ marking of the Jig and job are coincided.

    44) Concentricity on 991.5

    DRILLING OF SEGMENT PIN HOLES GROOVED RING:

    Dial Setup

    41) 4.1+0.1

    42) R0.5 at 4 places Radius Gauge

    43) Concentricity on 973.5

    37) 6.7+0.1 Vernier Caliper

    Vernier Caliper

    40) 4mm

    Vernier Caliper

    Note: Check with Go & No Go plug Gauge after reaming of every 5 holes

    Inspect for face butting, with feeler gauge ( max. gap 0.05mm) Jig orientation and setup.

    Drill 6 holes 3nos 120apart to a depth of 15.0mm and lock.

    0.2 E

    0.2 E

  • 8/2/2019 RLV SB Process Sheet

    66/155

    OPN.NO STAGE

    75# Inspection

    TOOLINGSDESCRIPTION

    Inspect for face butting, with feeler gauge (max. gap 0.05mm) Jig orientation and setup.

    Page 5 of 6

  • 8/2/2019 RLV SB Process Sheet

    67/155

    80 Drilling

    #85 Inspection

    090 Fitting

    100 Fitting

    105 # Inspection

    Open up the hole to 11.5mm.

    Check with GO NO GO Plug guage.

    Lock the holes with pins.

    45) 12+0.018, 72 nos Bore Dial Gauge

    46) Starting at 230' from Y+ towards P-

    Section - ZZ :

    Inspect the following dimensions:

    View - A: Go No Go Plug Gauge

    Go & No Go Gauge/ B.Gauge