MONTHLY CONSTRUCTION UPDATE
WORLD CLASS STATE-OF-THE ART ELEVATION
Light and Ventilation Maximized
As you may be aware, the government has introduced extensive changes in the GST regulations for the real estate sector at the 33rd GST Council meeting held on 24 th February, 2019 and has issued further noti�cations laying down the methodology for the transition of ongoing projects on 29 th March, 2019.
Under the new regulation, the company has been given a right to opt for charging GST either at the rate of 12% (and claim input credit) or charge GST at the rate of 5% (and not claim any input credit) with respect to ongoing projects, such as ours. The Company has to exercise the said option by 10 th May, 2019.
This amendment is a sweeping change in the GST statute and the Company is presently obtaining advice from experts as to which option it ought to select. Under the circumstances, the Company has decided to keep the charge of GST in this Demand Letter on hold until such a time that the Company exercises the option.
Once we exercise the option, a separate debit note will be issued to you for the GST chargeable in regards to this Demand Letter.
We thank you for your cooperation and request you to favor us with your payment for the full amount mentioned in this Demand Letter at the earliest.
GST NOTE
To our Esteemed Customers,
Riverdale Heights
2 BHK ─ Tower A | B | C | D
Tower - AŸ Terrace Slab. Complete
rdŸ Water-proo�ng done up to the 23 Floor
rdŸ Plumbing done up to the 23 Floor
rdŸ Drainage done up to the 23 Floor
rdŸ Electrical cabling done up to the 23 Floor
rdŸ Wall gypsum plastering done up to the 23 Floor
rdŸ Dado wall tiling Kitchen done up to the 23 Floor
rdŸ Dado wall tiling Toilets done up to the 23 Floor
rdŸ Floor tiling done up to 23 Floor
rdŸ Toilet False Ceiling done up to 23 Floor
rdŸ Lobby False Ceiling done up to the 23 Floor
rdŸ Service Staircase Tiling done up to the 23 FloorŸ Fire Staircase Tiling, work-in-progressŸ External Texture Paint, work-in-progressŸ Internal Wall Putty, work-in-progressŸ Unitized Glass Curtain Wall, work-in-progressŸ Passenger Lift installation, work-in-progress
ndŸ Lift Lobby �ooring done up to the 22 Floor
rdŸ Passenger Lift Granite Architrave done up to the 23 Floor
rdŸ ODU Platform done up to the 23 Floor
thŸ Main Door shutter �xing done up to the 10 FloorŸ Living room Terrace Railing, work-in-progress
Ÿ Terrace Slab, Completerd
Ÿ Water-proo�ng done up to the 23 Floorrd
Ÿ Plumbing done up to the 23 Floor rd
Ÿ Drainage done up to the 23 Floorrd
Ÿ Electrical cabling done up to the 23 Floorrd
Ÿ Wall gypsum plastering completed up to the 23 Floorrd
Ÿ Dado wall tiling Kitchen done up to the 23 Floor rd
Ÿ Dado wall tiling Toilets done up to the 23 Floor rd
Ÿ Floor tiling done up to the 23 Floor th
Ÿ Toilet False Ceiling 5 Floor, work-in-progressrd
Ÿ Lobby False Ceiling done up to the 23 FloorŸ Staircase Tiling, work-in-progressŸ External Texture Paint, work-in-progressŸ Internal Wall Putty, work-in-progressŸ Unitized Glass Curtain Wall, work-in-progressŸ Passenger Lift installation, work-in-progressŸ ODU Platform, work-in-progress
thŸ Main Door shutter done up to the 10 Floor
Tower - B
Tower - C
Tower - D
Riverdale Heights Towers A, B, C, D, and E
st Ÿ Complete up to the 21 Floor
thŸ Wall Gypsum Plasters up to the 10 Floor, work-in-progress
thŸ Internal Door Frame �xing up to the 10 Floor, work-in-progress
rdŸ Water-proo�ng done up to the 3 �oorŸ Kitchen Dado, work-in-progressŸ Staircase Railing, work-in-progressŸ Kitchen Platform, work-in-progress
thŸ Complete up to the 16 Floor
thŸ Wall gypsum plasters up to the 8 Floor, work-in-progress
thŸ Internal Door Frame �xing up to the 5 Floor, work-in-progressŸ Water-proo�ng, work-in-progreesŸ Dado wall tiling Kitchen, work-in-progressŸ Kitchen Platform, work-in-progress
Tower - EŸ Terrace Slab Complete
rdŸ AAC Block works up to the 23 Floor, work-in-progress
stŸ Water-proo�ng done up to the 21 Floor
ndŸ Plumbing done up to the 22 Floor
ndŸ Drainage done up to the 22 Floor
ndŸ Electrical conduiting and casing 22 Floor work-in-progress
ndŸ Wall gypsum plasters up to the 22 Floor, work-in-progress
ndŸ Dado wall tiling Kitchen up to the 22 Floor, work-in-progress
thŸ Dado wall tiling Toilets up to the 19 Floor, work-in-progress
st Ÿ Internal Door Frame �xing done up to the 21 FloorŸ External Cement Plaster, work-in-progressŸ Lobby False Ceiling, Work-in-progressŸ Lift shaft painting preparation, work-in-progress
ndŸ Kitchen Platform �xing up to the 22 Floor, work-in-progress
Tower A building passenger lift and garbage chute, work-in-progressSwimming Pool at Podium Level, work-in-progress
External WorksŸ Clubhouse, work-in-progressŸ Swimming Pool at Podium Level, work-in-progressŸ Podium Water-proo�ng for Green Landscape, work-in-progressŸ Curtain Wall (Facade) installation for Tower A and Tower B, work-in-progressŸ Ramp Driveway, completedŸ Fire Fighting installations and testing across all parking levels, work-in-progress Ÿ Step Garden Landscape RCC, work-in-progressŸ STP RCC, work-in-progressŸ Main Entry Bridge RCC Deck PT Slab, work-in-progress Ÿ Internal Driveway, work-in-progress Ÿ Electrical Transformer, work-in-progressŸ UGWT Pump Room, work-in-progress The Landscape Podium work-in-progress
Residential Fittings in the final stages at Tower A and Tower B
Suites
Riverdale SuitesŸ Plinth, work-in-progress Ÿ RCC Foundations, complete Ÿ Tie Beams, work-in-progressŸ Back �lling with compaction, work-in-progress
Riverdale Residences
rdE2 - 3 �oor slab shuttering and reinforcement, work-in-progress thE3 - 4 �oor level slab shuttering and reinforcement, work-in-progress
Ÿ E3- Fifth Floor MIVAN (Aluform) assembling, work-in-progress.Ÿ E2- Second Floor, complete.Ÿ RCC Foundations and Lift, completeŸ Ramp and Underground Water Tank RCC, works-in-progress.Ÿ Retaining Walls and Waterproo�ng works, work-in-progress
Earn a Referral Reward
INVITE YOUR FRIENDS AND FAMILYChildhood friend, Workplace buddy, Immediate relative, Close neighbour
Site Address: New Kharadi - Shivane Riverside Road, Behind Zensar IT Park, Kharadi, Pune 411 014 Maha RERA Registration No.: Riverdale Suites - P52100014163 | Riverdale Heights - P52100008035 | Riverdale Residences - P52100004692
*T&C Apply
K H A R A D I , P U N E
Call: +91 7620 974 974 / 9922 992 628
₹1.50 L 1 BHK - ₹65 K2 BHK - ₹1 L
Suites
₹50 K
Site Address: New Kharadi - Shivane Riverside Road, Behind Zensar IT Park, Kharadi, Pune 411 014 Maha RERA Registration No.: Riverdale Suites - P52100014163 | Riverdale Heights - P52100008035 | Riverdale Residences - P52100004692
Call: +91 7620 974 974 / 9922 992 628
Earn a loyalty bonus of in between Rs. 40,000/- and Rs. 1,60,000/-
if you decide to make another investment with us
K H A R A D I , P U N E
*T&C Apply
Suites
MAKE YOUR NEXT REAL ESTATE INVESTMENT EVEN MORE REWARDING
www.riverdalepune.com www.duvil le.com
thThe event was held at the Hyatt Regency, Pune on 20 February, 2019
CONCLAVE & EXCELLENCEAWARDS 2019
PUNE
th10
+91 76209 74974 Site Address: New Kharadi - Shivane Riverside Road, Behind Zensar IT Park, Kharadi, Pune 411 014RERA Registration No. : Riverdale Suites - P52100014163 Riverdale Heights - P52100008035 Riverdale Residences – I - P52100004692 https:// maharera.mahaonline.gov.in
BY
WINS THE PROUD RECIPIENT OF
“ ” EMERGING DEVELOPER OF THE YEARAWARD
Chairman Mr. Behram Dubash and Director Mr. Tushad Dubash of Duville Estates receiving the award presented by Uday Dharmadhikari, Chairman - Advisory Committee - Infra & Real estate, Indus Strategy Financial Advisors (ISFA), Nisha Jamvwal, Interior Architect, Lifestyle &
Design Columnist, Celebrity Social Thinker, Ar. Vivek Bhole, Principal Architect, Vivek Bhole Architects Pvt. Ltd.
www.riverdalepune.com www.duvil le.com
Swimming Pool at the Landscaped Pavilion
EXCLUSIVE 1, 2 & 2.5 BHK APARTMENTS
WINS THE PROUD RECIPIENT OF
“ ” BEST RESIDENTIAL DESIGN & PROJECT DELIVERY OF THE YEAR
AWARD
thThe event was held at the Hyatt Regency, Pune on 20 February, 2019
CONCLAVE & EXCELLENCEAWARDS 2019
PUNE
th10
+91 76209 74974 Site Address: New Kharadi - Shivane Riverside Road, Behind Zensar IT Park, Kharadi, Pune 411 014RERA Registration No. : Riverdale Suites - P52100014163 Riverdale Heights - P52100008035 Riverdale Residences – I - P52100004692 https:// maharera.mahaonline.gov.in