![Page 1: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/1.jpg)
River Basin Management Plans
& Strategic Environmental Assessment &
Appropriate Assessment
Ray Spain
Local Authorities Workshop, 3rd December 2008
![Page 2: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/2.jpg)
What is SEA?
Purpose • to ensure that the environmental
consequences are assessed during preparation and prior to adoption of RBMP
• to ensure the RBMP & POMs are as robust as possible in the context of the wider environment
![Page 3: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/3.jpg)
What is the Process?
• Screening – Is an SEA needed?
• Scoping – What should it include?
• Environmental Assessment and Report – Alternatives
• SEA Statement
![Page 4: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/4.jpg)
SEA Screening
• The statutory bodies responsible for SEA in Ireland and
Northern Ireland are
• DEHLG
• EPA
• DCENR
• Northern Ireland Environment Agency (formerly EHS)
The statutory bodies concluded that SEA is required for RBMPs
and POMs (2007) at a RBD level – 8 SEAs for the island of
Ireland
![Page 5: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/5.jpg)
SEA SCOPING• What should it include?
• Scoping ran in parallel, and fed into, the Water Matters (SWMI) Report
• Scoping is complete! for each of the 8 RBD’s.
• Scoping Documentis available for download atwww.serbd.com
![Page 6: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/6.jpg)
SEA Environmental Assessment Report
• ALL legislative requirements of Schedule 2 of the SEA Regulations (1 - 10)
– Information on the current state of the environment and likely evolution in the absence of the Plan (business as usual)
– Environmental protection objectives relevant to the plan
– Reasons for selecting the alternatives (supplementary measures)
– Likely significant effects on the environment
– Mitigation and monitoring measures
![Page 7: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/7.jpg)
SEA PROCESS
Screening
Overall MethodologyRBMP PROCESS
Initial Characterisation
ScopingSignificant Issues
Alternatives
Status / Risk / Possible Measures
Set Objectives
Action Programme
Objectives / Indicators / Targets
Environmental ReportDraft RBMP
Final RBMP SEA Statement
Consultation
Implementation & review cycle - 2nd RBMP
![Page 8: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/8.jpg)
Habitats Directive Assessment
(Appropriate Assessment)
– Habitats Directive, Article 6 (92/43/EEC)
– SACs, SPAs (Natura 2000 sites), and Ramsar Sites
– Narrow focus - maintaining integrity and conservation objectives of the site
– Protection led
– Precautionary
Four main steps
Screening
Appropriate assessment (avoidance first, then mitigation)
Assessment of alternative solutions
Assessment where no alternatives exist (compensatory measures)
![Page 9: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/9.jpg)
Appropriate Assessment
SEA PROCESS
Screening
Scoping
Alternatives
SEA Statement
Potential Impacts to
SAC / SPA
HABITATS DIRECTIVE ASSESSMENT
Assessment of Alternatives
Assessment Where No Alternatives Exist
Screening
Appropriate Assessment
![Page 10: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/10.jpg)
Role of SEA & HDA
• SEA in decision making
– Provides for high level of protection of the environment
– Informs decision making
– Assist in making more environmentally sustainable decisions
• HDA in decision making – more focused
– Maintains the integrity of site and its features
– Influences decision making
– Prevents development that could harm sites
![Page 11: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/11.jpg)
Integration with RBMP
• RBMP must show how this was done
• SEA– RBMP must have regard to SEA
• HDA – mitigation measures must be included in RBMP
![Page 12: River Basin Management Plans & Strategic Environmental Assessment & Appropriate Assessment Ray Spain Local Authorities Workshop, 3 rd December 2008.](https://reader036.fdocuments.net/reader036/viewer/2022062321/56649e605503460f94b5b7ac/html5/thumbnails/12.jpg)
Timetable
Phase I: Environmental Assessment & Report (Jul – Dec 2008)
Phase II: Public Consultation (Jan – Jun 2009)
Phase III: Preparation of Submission Reports (Jul –Aug 2009)
Phase IV: Preparation of SEA Statements (Jul - Sep 2009)
Fixed Milestones: Draft RBMP 22 December 2008
Final RBMP 16 October 2009