RIV ACI 2-Pile Cap

12
 CLIENT CONSTRUCTION LIMITED Date PROJECT APARTMENTS By Location 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Proj ect: 135-006 Sub-Loc'n References: 2-PILE CAP DESIGN TO ACI 318-05M 30-Jun-15 Output Reference Calculation  - - , , 2 - ASCE 7-10, Minimum Design loads for Buildings & Other Structures, 2010 3 - Final Geotechnical report, *** 4 - STAAD output 5 - ASTM A615-04, Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement 6 - Foundation Analysis & Design - J E Bowles, 5th edition Summary of calculation checks Utilisation ratio (actual vs capacity) Pile spacing Okay in pile spacing  Allowable p ile capacity 0.80 OK in pile capacity Compression strut 0.30 OK in compression strut Pil e be ar in  ca ac it  0.11 OK in ile bear in ca acit Pedestal bearing 0.11 OK in pedestal bearing Single pile punching shear 0.15 OK in single pile punching shear Pile overlap punching shear 0.20 OK in pile overlap punching shear Two-way pedestal (punching) shear 0.33 OK in two-way (punching) shear  x-axis: Flexure 0.13 OK in flexure (x-axis) Minimum tensile steel 0.90 OK in required tensile steel area One way shear 0.99 OK in one-way shear (x-axis) **this condition governs** z-axis: Flexure 0.20 OK in flexure (z-axis) Minimum tensile steel 0.95 OK in required tensile steel area One way shear 0.93 OK in one-way shear (z-axis) Starter bar reinforcement OK starter bar min. rfct Starter bar embedment OK embed. depth Starter bar development length OK dev't length 0.99 SUGGESTED PILECAP GEOMETRY & MATERIAL PROPERTIES Note for user and reader: Bordered cells denote user-input, all other cells are calculated via this spreadsheet using the relevant base data, material and guidance from the noted References 500 5 350 2000 1100 5 350 200 1100 2000 900 400 7 75 400 Page 1 of 12 

description

2-pile cap design to ACI318-05M

Transcript of RIV ACI 2-Pile Cap

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    References:1 ACI 318M 05 Building Code requirements for Structural Concrete 2005

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    1 - ACI 318M-05, Building Code requirements for Structural Concrete, 20052 - ASCE 7-10, Minimum Design loads for Buildings & Other Structures, 20103 - Final Geotechnical report, ***4 - STAAD output5 - ASTM A615-04, Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement6 - Foundation Analysis & Design - J E Bowles, 5th edition

    Summary of calculation checks Utilisation ratio (actual vs capacity)Pile spacing Okay in pile spacing

    Allowable pile capacity 0.80 OK in pile capacityCompression strut 0.30 OK in compression strut

    Pile bearing capacity 0.11 OK in pile bearing capacitye bea g capac y 0 O p e bea g capac tyPedestal bearing 0.11 OK in pedestal bearing

    Single pile punching shear 0.15 OK in single pile punching shearPile overlap punching shear 0.20 OK in pile overlap punching shear

    Two-way pedestal (punching) shear 0.33 OK in two-way (punching) shearx-axis:

    Flexure 0.13 OK in flexure (x-axis)Minimum tensile steel 0.90 OK in required tensile steel area

    One way shear 0.99 OK in one-way shear (x-axis) **this condition governs**z-axis:

    Flexure 0.20 OK in flexure (z-axis)Minimum tensile steel 0.95 OK in required tensile steel area

    One way shear 0.93 OK in one-way shear (z-axis)

    Starter bar reinforcement OK starter bar min. rfctStarter bar embedment OK embed. depth

    Starter bar development length OK dev't length0.99

    SUGGESTED PILECAP GEOMETRY & MATERIAL PROPERTIES

    Note for user and reader: Bordered cells denote user-input, all other cells are calculated via this spreadsheet using the relevant base data, material and guidance from the noted References

    500

    50

    0

    350

    2000

    1100 5

    350

    200

    1100

    2000

    900

    400

    75

    0

    75

    400

    Page 1 of 12

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    Pilecap geometryPilecap geometrypile diameter, dpile = 400 mm dia.=400mm

    Ref 6, 18-2 Pile spacing, s = 900 mm Max s(mm)= 3200 Min s(mm) = 900 Okay in pile spacingOverhang = 350 mm

    pedestal width (in X-direction), px = 500 mm 500pedestal breadth (in Z-direction), pz = 500 mm 500

    pedestal height (in Y-direction), H 200 mm 200Ref 1: 15.7 Pilecap thickness, h = 750 mm 750

    Founding depth below GL 1000 mmPile embedment = 75 mm 75

    Length of pilecap (x-axis) = 2000 mm Width of pilecap (z-axis) = 1100 mmWidth of pilecap (z axis) 1100 mm

    w1 = 1100 mm

    Calculation of pilecap & soil surcharge weightRef 4: Tbl C3-2 Concrete density (kN/m3) 23.1 kN/m3

    Pilecap area in plan = 2.20 m2Pilecap volume = 1.65 m3Pilecap weight = 38.1 kN

    Pedestal weight = 1.2 kNSoil weight above pilecap (assumes =20kN/m3) = 9.8 kN

    Total pilecap & soil weight Ff = 49.0 kN

    Material properties28-day concrete comp. strength, f'c 35 N/mm2 f'c=35MPa

    Ref 1: 7.7.1 Cover to reinforcement 75 mmRef 5 Main reinforcement to be used A615 Gr 60

    Reinforcement yield strength, fy = 420 N/mm2Modular ratio, m = fy/(0.85f'c) = 14.12 [unitless]

    Ref 1: 10.2.7.3 1 ratio (stress block:neutral axis depth) = 0.80Ref 1: B8.4.3 Assuming balanced strain conditions, b = ('0.851f'c/fy)(600/(600+fy)

    b = 0.0333 [unitless]Ref 1: R10.3.5 max = 0.75b = 0.0250 [unitless]

    Effective depth, d (for x-axis checks) 655 mm Assuming 20mm bars on the bottom mat (lower layer) 328Effective depth, dz (for z-axis checks) 635 mm Assuming 20mm bars on the bottom mat (upper layer)

    Ref 3 Allowable individual pile capacity, pa 246 kN

    Page 2 of 12

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    LOADING DATALOADING DATA

    Serviceability Limit State resultsRef 4 From STAAD output, using Serviceability Limit state analysis:

    Fx (kN) Fy (kN) Fz (kN) Mx (kNm) My (kNm) Mz (kNm) NodeMaximum FY occurrence (SLS) 4.3 541.8 67.7 13.6 0.5 1.7 4005

    Total service load on piles = Ff+FY SLS = 590.8 kN Service load per pile = 196.9 kN

    Ratio of actual pile capacity to allowable = 0.80 [unitless] OK in pile capacity

    Note: Use Serviceability Limit state values when checking pile capacity calculation.

    Ultimate Limit State resultsRef 4 From STAAD output, using Ultimate Limit state analysis:

    Fx (kN) Fy (kN) Fz (kN) Mx (kNm) My (kNm) Mz (kNm) NodeMaximum FY occurrence (ULS) 7.6 907.0 309.1 89.4 2.6 2.7 4005

    Total ultimate load on footing, PF = 1.4Ff+FY ULS = 975.5 kN Ultimate load per pile, PU_pile = 487.8 kN (equally distributed between the two piles)

    Using the Strut & Tie Model975

    a = 675.0 mmb = 0.5s = 450.0 mm 2 2c = (a2+b2) = 811.2 mm

    d = effective depth = 655.0 mme = (a2+b2) = 811.2 mm

    = ATan (a/0.5b) = 71.6 SIN 0.95

    COS 0.32Compression within pilecap Cmax = PF/SIN = 1028.3 kN

    Tension within pilecap T = Cmax*COS = 325.2 kN

    Compression strut checkCheck the compression diagonal as an unreinforced column using a core equivalent of 2x pile diameterCheck the compression diagonal as an unreinforced column using a core equivalent of 2x pile diameter

    Ref 1: 22.5.2 Pn Pu [note: take Pu = Cmax]Ref 1: Eqn 22-4 Nominal axial strength of strut, Pn = 0.60f'c[1-(lc/32h)2]AstrutRef 1: C3.5 = 0.65

    length of compression strut, lc = e = 811.2 mm2thickness of member, h = 750.0 mm

    Equivalent core strut area, Astrut = 2*dpile2/4 = 251,327 mm2 Pn = 3426.7 kN

    Ratio of actual compression to allowable = 0.30 [unitless] OK in compression strut

    Page 3 of 12

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    Check bearing capacity of pilecap over pilesR f 1 22 5 5 B BRef 1: 22.5.5 Bn Bu

    Nominal bearing strength, Bn = 0.85f cAstrut(Apilecap/Astrut) (subject to (Apilecap/Astrut) 2Ref 1: C3.5 = 0.65

    Apile = 125,664 mm2Apilecap = 2.20E+06 mm2

    (Apilecap/Astrut) = 4.18 [unitless] use (Apilecap/Astrut) = 2.00 [unitless]

    Bn = 14953.98 kN Bn = 9720.1 kN

    Factored bearing load, Bu = Cmax = 1028.3 kNRatio of factored pile bearing cap. to allowable = 0.11 [unitless] OK in pile bearing capacity

    Check bearing capacity of pilecap under pedestalBn Bu

    Ref 1: 10.17.1 Nominal bearing strength, Bn = 0.85f cApedestal(Apilecap/Apedestal) (subject to (Apilecap/Apedestal) 2Ref 1: C3.5 = 0.65

    Apedestal = 250,000 mm2Apilecap = 2.20E+06 mm2

    (Apilecap/Apedestal) = 2.97 [unitless] use (Apilecap/Apedestal) = 2.00 [unitless]

    Bn = 14875.0 kN Bn = 9668.8 kN

    Factored bearing load, Bu = Cmax = 1028.3 kNRatio of factored pile bearing cap. to allowable = 0.11 [unitless] OK in pedestal bearing

    FLEXURE IN PILECAP

    1100

    Area of tension steel required for tied-arch behaviourAs arch = T(fy)

    Ref 1: Cl. 9.3.2.6 = 0.75 As arch = 102.4 mm2

    200

    Page 4 of 12

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    Moment at the face of the pedestal perpendicular to the x-axisLever arm distance x = 0 5(s-px)Lever arm distance, xf = 0.5(s px)

    xf = 200 mmLength of the critical section 1-1

    L1-1= 1100 mm

    Take moments about pedestal faceMux = PU_pile * xfMux = 97.6 kNm

    R = MUX/(bd2)Ref 1: Cl. 9.3.2.6 = 0.90

    b=L1-1= 1100 0 mm1-1 1100.0 mmd = 655.0 mm

    R = 0.230 mm2 = 0.85(fc/fy)[1-(1-(2R/0.85fc)]

    = 0.001Ref 1: 10.5.1 min= max[(0.25fc)/fy, 1.4/fy]

    min= 0.0035As req = MAX(,min)*b*d

    As req = 2537 mm2

    Reinforcement selectionTension Comp.

    Select bar diameter (mm) 20 10Select number of bars 9 9

    Provide bar spacing (to nearest 25mm) 125 125 mmAs [x] 2,827 707 mm2

    OK in required tensile steel area OK in required tensile steel arRef 1: 7.6.1 Okay in minimum bar spacing

    Check for minimum reinforcement required for shrinkageRef 1: 7.12.2.1 As, min (shrinkage) = 0.0018 (times gross sectional area)

    0.0018L1-1h = 1,485 mm2

    Reinforcement required (parallel to x-axis)

    As arch = 102 mm2As min (flexure) = 2,537 mm2As min (shrinkage) = 1,485 mm2

    As req'd = 2,537 mm2As prov = 2,827 mm2

    Actual reinforcement ratio, =As prov/(L1-1d) = 0.0039 [unitless]Kn = (1-(fy/1.7f c))fy

    Kn = 1.603 Nominal flexural strength in x-axis MNx = L1 1d2Kn [aka bd2K ]Nominal flexural strength in x axis, MNx L1-1d Kn [aka bd Kn] MNx = 756.3 kNm

    Ratio of Mux to MNx = 0.13 [unitless] OK in flexure (x-axis)

    Page 5 of 12

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    Moment at the face of the pedestal parallel to the z-axis

    250

    Lever arm distance, Zf = 0.5*pedestal length Zf = 250 mm

    Calculate the length of the critical section 2-2L2-2= 2000 mm

    2000

    Take moments about pedestal faceMuz = 2XPU_pile * ZfMuz = 243.9 kNm

    R = MUZ/(bdz2)Ref 1: Cl. 9.3.2.6 = 0.90

    b=L2-2= 2000.0 mmdz = 635.0 mm

    R = 0.336 mm2 = 0.85(fc/fy)[1-(1-(2R/0.85fc)]

    = 0.001max[(0 25f )/f 1 4/f ]Ref 1: 10.5.1 min= max[(0.25fc)/fy, 1.4/fy]

    min= 0.0035As req = MAX(,min)*b*dz

    As req = 4472 mm2

    Reinforcement selectionTension Comp.

    Select bar diameter (mm) 20 10Select number of bars 15 15

    Provide bar spacing (to nearest 25mm) 150 150 mmAs[z] 4,712 1,178 mm2

    OK in required tensile steel area OK i i d t il t lOK in required tensile steel area OK in required tensile steel arRef 1: 7.6.1 Okay in minimum bar spacing

    Page 6 of 12

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    Check for minimum reinforcement required for shrinkageCheck for minimum reinforcement required for shrinkageRef 1: 7.12.2.1 As, min (shrinkage) = 0.0018 (times gross sectional area)

    0.0018[L2-2]h = 2,286 mm2

    Reinforcement required (parallel to z-axis)

    As min (flexure) = 4,472 mm2As min (shrinkage) = 2,286 mm2

    As req'd = 4,472 mm2As prov = 4,712 mm2

    Actual reinforcement ratio, =As prov/(L2-2d) = 0.0037 [unitless]

    As req'd is the max of

    p [unitless]Kn = (1-(fy/1.7f c))fy

    Kn = 1.518 Nominal flexural strength in x-axis, MNz = L2-2d2Kn [aka bd2Kn] MNz = 1223.9 kNm

    Ratio of Muz to MNz = 0.20 [unitless] OK in flexure (z-axis)

    REINFORCEMENT SUMMARYAlong x-axis, bottom mat 9-T20-BM01-125 BAlong z-axis, bottom mat 15-T20-BM02-150 B

    Along x-axis, top mat 9-T10-BM03-125 TAlong z-axis, top mat 15-T10-BM04-150 T

    SHEAR CHECKSCheck for punching shear of a single pile

    Ref 1: 11.1.1 VnVc Assuming that no shear reinforcement is used in the footingRef 1: 9.3.2.3 Where 0.75Ref 1: 11.12.1.2 Shear perimeter for a single pile is located at a distance of 0.5d outside of the pile face

    Shear perimeter length, bo is given bybo = (dpile+d)

    dpile = 400 mmd = 655 mm 328

    bo = 3314 mm

    Calculate the nominal shear strength, VC of the pilecap(a) 0.17(1+2/)f'cbod

    Ref 1: 11.12.2.1 (b) 0.083([sd/bo]+2)f'cbod(c) 0.33f'cbod

    Condition (a)Ref 1: 15.3 For calculation of a circular shape, convert the area of the pile to an equivalent square area

    Equivalent square dimension = 354 mm each sideRatio of long side to short side of col, = 1.00 [unitless]

    f'c = 35.0 N/mm2bo = 3314 mm

    Vc (kN) = min of

    bo 3314 mmd = 655 mm

    Vc-condition (a) = 6,550.1 kNCondition (b)

    Pile location for determining s = EdgeRef 1: 11.12.2.1 s = 30

    Vc-condition (b) = 8,452.0 kNCondition (c)

    Vc-condition (c) = 4,238.3 kN

    (a) 6,550.1 kN(b) 8 452 0 kNVc = min of (b) 8,452.0 kN(c) 4,238.3 kN

    Use Vc = 4,238.3 kNVc = 3,178.7 kN

    VUpile = PUpile = 487.8 kNRatio of VUpile/Vc = 0.15 OK in single pile punching she

    c

    Page 7 of 12

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    Check for punching shear on overlapping pilesCheck for punching shear on overlapping piles

    5114 1657

    Ref 1: 11.12.1.2 Critical perimeter for overlapping piles is shown as bo overlap0.5d = 0.5*dpile = 200 mm

    Ref 1: R15.5.3 bo overlap = (dpile+d)+(2s) 1657bo overlap = 5114 mm

    Calculate the nominal shear strength, VC of the pilecap(a) 0.17(1+2/)f'cbo overlapd

    328 900

    Ref 1: 11.12.2.1 (b) 0.083([sd/bo overlap]+2)f'cbo overlapd(c) 0.33f'cbo overlapd

    Condition (a)Ref 1: 15.3 For calculation of a circular shape, convert the area of the pile to an equivalent square area

    Equivalent square dimension = 354 mm each sideRatio of long side to short side of col, = 1.00 [unitless]

    f'c = 35.0 N/mm2bo overlap = 5,114 mm

    d = 655 mmVc-condition (a) = 10,107.4 kN

    Vc (kN) = min of

    Condition (b)Pile location for determining s = Edge

    Ref 1: 11.12.2.1 s = 30Vc-condition (b) = 9,609.8 kN

    Condition (c)Vc-condition (c) = 6,540.1 kN

    (a) 10,107.4 kN(b) 9,609.8 kN(c) 6,540.1 kN

    Use Vc = 6 540 1 kN

    Vc = min of

    Use Vc 6,540.1 kNVc = 4,905.1 kN

    VUpile = 2 X PUpile = 975.5 kN [since both piles contribute to overlapping shear]Ratio of VUpile/Vc = 0.20 OK in pile overlap punching s

    Page 8 of 12

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    ONE WAY SHEARONE WAY SHEARRef 1: 11.12.1.1

    One-way shear parallel to x-axis at either the pile face or pedestal face (Section 2-2)Ref 1: 11.3.1.1 Vc = 0.17f'c(L2-2d)

    L2-2= 2000 mmVc = 1,317.5 kN

    Ref 1: 9.3.2.3 = 0.75 Vc = 988.1 kN

    VUpile = 2*PUpile = 975.5 kNRatio of VUpile/Vc = 0.99 OK in one-way shear (x-axis)

    The critical section for one-way (wide beam) shear occurs at either the pedestal face or the pile face

    One-way shear parallel to z-axis at either the pile face or pedestal face (Section 1-1)Ref 1: 11.3.1.1 Vc = 0.17f'c(L1-1dz)

    L1-1= 1100 mmVc = 702.5 kN

    Ref 1: 9.3.2.3 = 0.75 Vc = 526.9 kN

    VUpile = PUpile = 487.8 kNRatio of VUpile/Vc = 0.93 OK in one-way shear (z-axis)

    TWO WAY (PUNCHING) SHEARRef 1: 11.12.1.1Ref 1: 11.12.1.2 Critical perimeter for two-way (punching shear) is bo punching

    bo punching = 4620 mm

    Calculate the nominal shear strength, VC of the pilecap(a) 0.17(1+2/)f'cbo punchingd

    Ref 1: 11.12.2.1 (b) 0.083([sd/bo punching]+2)f'cbo punchingd(c) 0.33f'cbo punchingd

    Condition (a)Ratio of long side to short side of col, = 1.00 [unitless]

    f' = 35 0 2

    Vc (kN) = min of

    The critical section for two-way (punching) shear occurs at a distance of 0.5d from the pedestal face

    f'c = 35.0 N/mm2bo punching = 4,620 mm

    d = 655 mmVc-condition (a) = 9,130.4 kN

    Condition (b)Pile location for determining s = Edge

    Ref 1: 11.12.2.1 s = 30Vc-condition (b) = 9,291.8 kN

    Condition (c)Vc-condition (c) = 5,907.9 kN

    (a) 9 130 4 kN(a) 9,130.4 kN(b) 9,291.8 kN(c) 5,907.9 kN

    Use Vc = 5,907.9 kNVc = 4,430.9 kN

    VUpile = 3 x PUpile = 1,463.3 kNRatio of VUpile/Vc = 0.33 OK in two-way (punching) she

    Vc = min of

    Page 9 of 12

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    CHECK ON STARTER BARSCHECK ON STARTER BARS

    Check on minimum % reinforcement to starter barsdiameter of starter bar, db = 20 mm

    Number of starter bars = 4 Nr (note: minimum 4)Cross sectional area of bars = 1,257 mm2

    Ref 1: 15.8.2.1 Minimum As-starter = 0.005Agcolumn cross-section area Ag=(px*pz) = 250,000 mm2

    As-starter / Ag = 0.005 OK starter bar min. rfct

    Check on starter bar embedment into footingRef 1: 12 3 2 Min of 200 mmRef 1: 12.3.2 Min of 200 mm

    (0.24fy/f'c)db0.043fydb

    fy = 420 N/mm2db = 20 mmf'c = 35 N/mm2

    (0.24fy/f'c)db = 341 mm0.043fydb = 361 mm

    Use ldc as = 361 mm Say 365 mm (rounded up)Check on ldc versus depth of footing, h, and effective depth, d

    d = 655 mmh = 750 mm OK embed. depth

    length of embedment ldc = larger of

    Check on development length of starter barsCritical sections for the development length (ld) of the starter bars occur at the column/footing interface

    Ref 1: 12.2.2 ld =

    For tdepth of freshly cast concrete below ld

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    SUMMARY OUTPUTSUMMARY OUTPUT

    PLAN ON PILECAP500

    50

    0

    350

    2000

    1100

    f'c=35MPa

    SECTION THROUGH PILECAP

    350

    400 75

    0

    75

    400

    200

    dia.=400mm

    REINFORCEMENT PLAN

    15-T20-BM02-

    2000

    900 75

    REINFORCEMENT SECTION

    9-T20-BM01-125 B

    9-T10-BM03-125 T15-T10-BM04-

    Reinforcement scheduleBar Mark (BM) Type Dia. (mm) Nr. Length (mm) A B C Wt (kg)01 T 20 21 15 2225 240 1850 240 82.302 T 20 21 15 1325 240 950 240 49.003 T 10 21 9 2050 120 1850 120 11.404 T 10 21 15 1150 120 950 120 10.605 T 20 11 4 1650 515 1175 16.3

    169.6

    Shape code to BS866

    4-T20-BM05

    69 6

    SUMMARY OF MAIN QUANTITIESExcavation 2.20 m3Disposal 2.20 m350mm blinding 10MPa 0.11 m3Backfill around pedestal 0.49 m335MPa concrete

    Pedestal 0.05 m3Pilecap 1.65 m3

    Total concrete 1.70 m3

    Reinforcement to ASTM A615 Gr 60Total reinforcement 169.6 kg

    FormworkPedestal (x-axis) 0.20 m2Pedestal (z-axis) 0.20 m2Length 3.00 m2Breadth 1.65 m2

    Total formwork 5.05 m2

    Page 11 of 12

  • CLIENT CONSTRUCTION LIMITED DatePROJECT APARTMENTS ByLocation 3-BEDROOM APARTMENT MODEL, Location 3C and 3D Project: 135-006Sub-Loc'n

    2-PILE CAP DESIGN TO ACI 318-05M

    30-Jun-15

    OutputReference Calculation

    APPENDIX

    Ref 4

    Horizontal Vertical Horizontal Moment Node L/C Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm

    Max Fx 4000 1 1.0DL+1.0 72.80 346.88 -63.03 -11.83 1.16 -11.49Min Fx 4010 1 1.0DL+1.0 -73.53 348.00 -63.12 -11.84 -1.16 11.69Max Fy 4005 1 1.0DL+1.0 4.33 541.82 -67.67 -13.58 0.54 1.66Min Fy 1000 1 1.0DL+1.0 65.95 326.01 56.18 9.55 -1.20 -10.56

    The user is to carry out the analysis in STAAD and use the post-processing results to obtain the values shown in these tables. Note that two limit state Envelopes are used, Serviceability Limit State and Ultimate Limit State.

    SERVICEABILITY LIMIT STATE (1.0DL+1.0LL)

    APPENDIXSTAAD ANALYSIS OUTPUT

    Min Fy 1000 1 1.0DL 1.0 65.95 326.01 56.18 9.55 1.20 10.56Max Fz 1002 1 1.0DL+1.0 -54.01 355.60 74.69 10.06 0.69 5.37Min Fz 4002 1 1.0DL+1.0 -54.48 374.74 -68.47 -15.54 -0.38 5.52Max Mx 1002 1 1.0DL+1.0 -54.01 355.60 74.69 10.06 0.69 5.37Min Mx 4008 1 1.0DL+1.0 53.86 373.98 -68.45 -15.56 0.38 -5.34Max My 1010 1 1.0DL+1.0 -66.54 326.84 56.29 9.57 1.21 10.74Min My 1000 1 1.0DL+1.0 65.95 326.01 56.18 9.55 -1.20 -10.56Max Mz 4010 1 1.0DL+1.0 -73.53 348.00 -63.12 -11.84 -1.16 11.69Min Mz 4000 1 1.0DL+1.0 72.80 346.88 -63.03 -11.83 1.16 -11.49

    Maximum values 72.80 541.82 74.69 10.06 1.21 11.69Corresponding values at Fy max 4005 4.33 541.82 67.67 13.58 0.54 1.66

    Horizontal Vertical Horizontal Moment Node L/C Fx kN Fy kN Fz kN Mx kNm My kNm Mz kNm

    Max Fx 4000 1.0WL(+Z)+1 142.09 710.62 -245.18 -69.10 0.89 -22.88Min Fx 4010 1.0WL(+Z)+1 -143.06 712.02 -245.08 -69.04 -0.89 23.16Max Fy 4005 1.0WL(+Z)+1 7.63 906.97 -309.08 -89.44 2.61 2.69Min Fy 1003 0.9DL+1.0W 16.44 -26.42 -161.28 -61.44 -0.88 -2.22Max Fz 1005 1.0WL(-Z)+1 7.63 878.27 297.82 85.68 -2.53 2.49Min Fz 4005 1.0WL(+Z)+1 7.63 906.97 -309.08 -89.44 2.61 2.69Max Mx 1005 1.0WL(-Z)+1 7.63 878.27 297.82 85.68 -2.53 2.49Min Mx 4005 1.0WL(+Z)+1 7.63 906.97 -309.08 -89.44 2.61 2.69

    ULTIMATE LIMIT STATE (All Load Combs)

    Max My 4005 1.0WL(+Z)+1 7.63 906.97 -309.08 -89.44 2.61 2.69Min My 1005 1.0WL(-Z)+1 7.63 878.27 297.82 85.68 -2.53 2.49Max Mz 1010 1.0WL(-Z)+1 -139.04 689.20 232.82 65.00 0.98 23.37Min Mz 1000 1.0WL(-Z)+1 138.54 688.95 232.99 65.07 -0.98 -23.21

    Maximum values 142.09 906.97 297.82 85.68 2.61 23.37Corresponding values at Fy max 4005 7.63 906.97 309.08 89.44 2.61 2.69

    This is achieved with Load Combination: 106 1.2DL+1.0WL(+Z)+1.0LL+0.5LR

    Ref 2 Listing of Load combinations used: 100: 1.0DL 101: 1.0DL+1.0LL102: 1 4DL 102: 1.4DL 103: 1.2DL+1.6LL+0.5LR 104: 1.2DL+1.6LR+1.0LL 105: 1.2DL+1.0WL(+X)+1.0LL+0.5LR 106: 1.2DL+1.0WL(+Z)+1.0LL+0.5LR 107: 1.2DL+1.0WL(-X)+1.0LL+0.5LR 108: 1.2DL+1.0WL(-Z)+1.0LL+0.5LR 109: 1.2DL+1.0EQ(+X)+1.0LL 110: 1.2DL+1.0EQ(+Z)+1.0LL 111: 1.2DL+1.0EQ(-X)+1.0LL 112: 1.2DL+1.0EQ(-Z)+1.0LL 113: 0.9DL+1.0WL(+X)( ) 114: 0.9DL+1.0WL(+Z) 115: 0.9DL+1.0WL(-X) 116: 0.9DL+1.0WL(-Z) 117: 0.9DL+1.0EQ(+X) 118: 0.9DL+1.0EQ(+Z) 119: 0.9DL+1.0EQ(-X) 120: 0.9DL+1.0EQ(-Z)

    Page 12 of 12