Risk management on a large topsides design project
Transcript of Risk management on a large topsides design project
5/20/20105/20/2010
11
Risk management on a large topsides design project
Peter Astley
About myself
� Retired after 28 years cost engineering & project management with
Amec
� Six platform design projects, three refinery projects
� Currently short course lecturing for Cranfield University
� Active FIMechE, FACostE
5/20/20105/20/2010
22
Purpose
� Explain how I have used risk management on large topsides design projects
� Discuss what lessons I have learned
� Stimulate future process improvement
Britannia platform
5/20/20105/20/2010
33
P20
P50
P80
not to exceed cost
pro
babili
ty
final cost (1998)
Sanction estimate (1994)
variance decreases as risks are resolved
Britannia cost risk history
ICEC ICEC RoitterdamRoitterdam 19981998
Britannia topsides risk drivers
� Alliance working
� Cost
� Schedule
� Weight
5/20/20105/20/2010
44
Lessons learned
� Risk management is an essential cost control tool
� Use of different probability levels:
� stretched targets 20%
� budgets 50%
� corporate reporting 80%
� contingency management
� Risk management increases buy-in from project participants
� It is valid to change quantitative results to match intuitive
expectations
Amec´s adoption of risk management
� Focus on qualitative risk management process
� Risk matrix and risk register
� Company-wide training programme
� Facilitated brainstorming sessions
� Required for tenders and in-house project reporting
5/20/20105/20/2010
55
Amec´s risk driver
� Low margins/high risks in UK civil/construction contracting
� December 2007 Amec joined FTSE 100
� Oil & gas equipment & services sector
� Vision: to be the leading supplier of high-value consultancy,
engineering and project management services to the world’s
natural resources, nuclear, clean energy, water and environmental
sectors.
1010
Identify Identify
objectivesobjectives
DefineDefine
rolesroles
andand
responsibilitiesresponsibilities
Identify Identify
risksrisks
Assess Assess
and rankand rank
Plan Plan
responseresponse ExecuteExecute
Monitor Monitor
and and
explainexplain
Management of any Management of any uncertainuncertain event that might event that might affectaffect
thethe achievement achievement of our of our objectivesobjectives
Risk management process
5/20/20105/20/2010
66
Sakhalin development facilities
Different islands
5050°° NN
5/20/20105/20/2010
77
SEIC milestones
1991 Consortium formed of Marathon. McDermott, Mitsui, RF
1994 Production sharing agreement signed
1999 PA-A (Molitpak) installed
2000 Marathon traded its share with Shell
2001 Amec started design
2005 Environmental issues force sale of 50% share to Gazprom
2006 Lun-A (Lunskoye) installed
2007 Piltun drilling operational
2009 First LNG delivered
Risk drivers (revised)
� Arctic conditions
� winterisation
� safety
� wave height
� weather window
� Earthquake zone
� structural design
� pendulum bearings
� Project size
� resources
� management
� Schedule expectations
� rework
� Gas sales price
� Russian influence
� TEOC
� Russian content
� production sharing
agreement
� Change control
� client change
� conceptual design
� steel to concrete jacket
� Korean fabricator
� no topsides experience
� design support resources
� design construction overlap
� culture & communication
� Environmental protection
5/20/20105/20/2010
88
Amec bid/execution strategy
� Select team known to Marathon & Shell
� Subcontract Jacket design to TriOcean
� Subcontract Quarters design to Rubin ( St Petersburg)
� Use existing Amec Environmental consultant in Moscow
2007
DEFINITION ENGINEERING
PSTS, TEOC
20052002 2003 2004 2006
DETAILED DESIGN &
PROCUREMENT
2001
1ST OIL PRODUCED
1ST GAS TO EXPORT
DECK INSTALLATION MATING &
HOOK-UP
TOPSIDES
FABRICATION/LOADOUT
Sakhalin early high level schedule
5/20/20105/20/2010
99
Lunskoye transportation
Lunskoye installed winter 2007
5/20/20105/20/2010
1010
Piltun February 2009
Sakhalin production capacity
Production capacity cu m/day
Gas Cond Oil
PA-A 1.7 m 14 000
PA-B 2.6 m 11 000
Lun-A 50 m 7 900 2 500
5/20/20105/20/2010
1111
Qualitative risk score table
Probability
Score
(P)
Impact
Score (I) Design Cost Schedule
A Not very likely
0-20%
1 Accommodate
with no
significant effect
<£50,000 <2 weeks
B Unlikely
21-40%
2 Minor
consequential
effects
<£500,000 <1 month
C 50/50
41-60%
3 Multi-discipline
change/
rework
<£1
million
<3 month
D Likely
61-80%
4 Major abortive
work
<£2
million
<6 month
E Highly likely
81-100%
5 Major design
change
<£5
million
<6 month
Risk matrix
55 2626 66 11
27,27,
2828
18, 18,
1919
22 2222 2121 2020
23237724,24,
2525
161619, 19,
1515
1010 12,12,
1313
331111 99
3030 44 1717 2929 88E E
D D
CC
BB
A A
1 2 3 4 51 2 3 4 5
ProbabilityProbability
PP
Impact IImpact I
1717 Risk registerRisk register
numbernumber
Do not multiply P x I
5/20/20105/20/2010
1212
Risk drivers (used)
DD Detail design change
FC Fabrication contractor
FE FEED carry over
FU Functional change
GS Gravity base structure (GBS)
HU Hook up & commissioning
IS Instrument control & safety system
IC Installation contractor
LC Local content/approval
OM Load out/transportation grillage
OT Operations/maintenance
PR Other parties (not GBS)
SC Schedule risk
WI Winterisation
WT Weight engineering
Mitigation strategies
T Transfer
A Accept
M Mitigate
C Use contingency
5/20/20105/20/2010
1313
Simple risk register
Risk
No.
Risk
Driver
Risk Statement Mit.
Strat
Prob Impact Action
by
17 KF If vendor data from
fabricator is late then there
will be delays to design
schedule which will
subsequently affect
fabrication
C 5 3 SR
Risk categories
� Technical risks & design assumptions
� Cost/price/profit, finance/cash flow
� Contractual risks (form of contract, liabilities)
� Schedule
� HSE
� Legislation
� Reputation
� Stakeholders
� Interfaces
� Supply chain
5/20/20105/20/2010
1414
Risk management levels
00 PP 100100 MinMin MaxMaxMostMost
LikelyLikely
00 100100
PPAA--EE
II11--55
RR
Level 1 (Qualitative) Level 1 (Qualitative) Risk register Risk register
Level 2 (Quantitative) Level 2 (Quantitative) Monte Carlo AnalysisMonte Carlo Analysis
ICEC Ljubljana 2006ICEC Ljubljana 2006
Quantitative risk forecasting
� Base line forecast
� Select from risk register all risks with impact > 3
� Interview lead engineers ( 12 disciplines) . What uncertainties will
affect your forecast to complete?
� What is the probability of occurrence (including P=1)?
� What is the best case, worst case, most likely?
� Run Monte Carlo analysis
� Discuss results and rerun
� Check against resources and planned completion date.
5/20/20105/20/2010
1515
Lessons learned
+
� Involve the project team
� Consider all high impact risks
� Asking the 3 point question
� Cost engineering tool
� Use for contingency management
� Use stretched targets
∆
� Consistency across project WBS
� Improve cost driver identification
� Better risk correlation
� Better estimation of probability
� Consider systemic risk
� Opportunity management
� Don´t use risk as an excuse
Risk management, art or science?
People
Communication
Persuasion
Facilitation
Logic
Data collection
Measurement
Analysis
Vision
Professionalism
Leadership
Creativity
Organisation
Policies
Procedures
Coding structures
Art Science
5/20/20105/20/2010
1616
Questions & discussion