Risk Management in Value Engineering -...

36
Risk Management in Value Engineering AASHTO 2009 VE Conference, San Diego September 1, 2009 Rich Foley California Department of Transportation Rein Lemberg CALTROP Corporation

Transcript of Risk Management in Value Engineering -...

Page 1: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Risk Management in Value Engineering

AASHTO 2009 VE Conference, San DiegoSeptember 1, 2009

Rich FoleyCalifornia Department of Transportation

Rein LembergCALTROP Corporation

Page 2: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

A bit of background about Caltrans policies and our largest project

to date.

Page 3: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Caltrans Policies

Page 4: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Our Risk Management Program evolved on the San Francisco - Oakland Bay Bridge Program

Page 5: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

The SFOBB is a complex program with multiple construction sequences…

Page 6: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Multiple Interdependent Contracts

SSD West Tie-in Phase 1

(Tunnel Viaduct

Replacement)

Submarine Cable

Skyway

SAS Phase 1Erect Tower

E2/T1E2

Foundation

YBI Hinge K WB

YBI Construction

WB

SSD West Tie-in Phase

2

SSD East Tie-in

SSD Viaduct

SAS Phase 3Complete

EB

OTD 2Complete WB

SAS Phase 2 Complete

WB

OTD 1

SAS Phase 1Load

Transfer

YBI Hinge K EB

OTD 2 EB

SSD Demolition of

Existing Bridge

YBI Construction

EB

YBI Complete WB

Frame 2

YBI Complete EB

Frame 2

SAS Phase1Deck

Erection

SAS Phase1E2 Capbeam

SAS Phase1W2 Capbeam

OTD 2 EB Detour

SSD Traffic Switch

Bridge Closure

(Complete SSD WTI Phase 1)

SAS Phase 1Cable

InstallationE2/T1

T1Foundation

WB Traffic Switch

EB Traffic Switch

Page 7: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

How we apply quantitative risk analysis…

Quantitative Risk Analysis

Schedule Risk Analysis

Application to budgets and

decisions

Page 8: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Our quantitative risk analysis is simple

Output

Inputs

Model

Page 9: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

The inputs appear daunting but can be simplified.

BetaGammaNormal

α1

,α2 α,βμ,σ

Uniform

min max

Triangular

min peak max

Page 10: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

How we determine the input distribution…

Optimistic PessimisticMost Likely

$

Somewhere in between,if discernable.

Triangular distribution

Uniform distribution(if no Most Likely value)

Page 11: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

So that we have probability distributions for all of our input variables…

100 150$20 $35 $50

Risk item = Probability x Impact

Estimate

Line item = Quantity x Unit Price

Risks10% 30% $1M $3M

Page 12: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Input Distributions

…that we run through a Monte Carlo model to get the output probability distribution.

Monte Carlo Simulation

Page 13: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

We turn it into a “readable” probability curve

50% Probable Cost

10% Chance of Overrun90% Chance of Underrun

Page 14: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

We innovated in quantitative analysis of

schedule risks

Page 15: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Understanding Cost and Schedule Risk Analysis

1d

1d

1d

1d

1d

1d

1d

1d

$1

$1

$1

$1

$1

$1

$1

$1

3d4d

5d

1d

1d

1d

1d

1d

1d

1d

1d

$8 8d

Page 16: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

20

40

20

20

20

25

25

20

100

9080

20

40

20

20

20

25

25

20

Schedule risk analysis is handled differently...

?

? ??

?

?

Longest Path

Page 17: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

How do schedule risks affect the schedule?

Can change the critical (longest) path

Determine the length of the critical path

1. Probability of occurrencee.g 20%

2. Delay range0d 60d

20

40

20

20

20

25

25

20

?

? ??

?

?

Page 18: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

An example schedule…

Erect Temporary Works

Install Cable System

Transfer Load to Cable

Page 19: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

…we add duration uncertainties…

Erect Temporary Works

Install Cable System

Transfer Load to Cable

Page 20: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

…and introduce risks into the schedule.

Erect Temporary Works

Install Cable System

Transfer Load to CableRisk Risk Risk

Risk activity appears as zero-duration activity•

Has two properties: 1. probability that it may occur 2. three-point estimate of its duration IF it happens to occur

Page 21: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

We run schedule risk analysis software to get…

Probability DistributionFor Completion Milestone

Criticality Chart

50 55 60 65 70 75 80 85 90 95 100

002371  ‐ Install Suspenders000341  ‐ PWS System Installation

000351  ‐ Load Transfer Cable to Deck Sect.000841  ‐ Compact PWS/Cable Bands

000831  ‐ Erect Cable System Temporary Works001521  ‐ EB Completion Activities

000641  ‐ Stage 1 Demolition (Bent 39 to Bent 33)000691  ‐ Construct Abutment 23R

000751  ‐ Excavate & Light Weight Concrete Roadway000761  ‐ Construct Roadway & Complete Eastbound

002361  ‐ OBG Complete for Cable Erection002071  ‐ Erect Deck Lift 14W

002341  ‐ Align/Bolt /Weld Lifts 13W/14W002041  ‐ Erect Deck Lift 13W002051  ‐ Erect Deck Lift 13E

002191  ‐ Align/Bolt /Weld Lifts 12E/13E

Criticality (%)

Criticality

Page 22: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

…and determine the “Criticality Path”

100%

83%

92%

63%

72%

83%

75%

Criticality = percent of simulation trials that the activity is on a

critical path

Page 23: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

We apply our quantitative techniques

to decision support.Examples:

1.Evaluate VA study alternatives

2.Accelerate construction

3.Interaction of 2 contracts

?

Page 24: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Example: YBITS VA study

Page 25: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

EstimateEstimate

RisksRisks

Original Alternative

VA study produced 3 options…

EstimateEstimate

RisksRisks

EstimateEstimate

RisksRisks

Option 1 Option 2 Option 3

P50 = 90 P50 = 98 P50 = 103

P90 = 115 P90 = 115 P90 = 115

Page 26: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Considering risk, which option is best?

0%

20%

40%

60%

80%

100%

40 65 90 115 140

Prob

abili

ty o

f Gre

ater

Cos

t

Cost

Option 1 Option 2 Option 3

Page 27: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

27

Page 28: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Example: Contract acceleration options

Westbound

Eastbound OTD EB Contract

WB Open

EB Open

OTD EB Contract

Objective: shorten time between WB and EB open

Page 29: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Evaluated schedule risks of 3 options…

0 50 100 150 200 250

Days from WB Open

Option 1 Option 2 No change

Page 30: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

But, in the bigger picture, it is not just the OTD contract

SSD West Tie-in Phase 1

(Tunnel Viaduct

Replacement)

Submarine Cable

Skyway

SAS Phase 1Erect Tower

E2/T1E2

Foundation

YBI Hinge K WB

YBI Construction

WB

SSD West Tie-in Phase

2

SSD East Tie-in

SSD Viaduct

SAS Phase 3Complete

EB

OTD 2Complete WB

SAS Phase 2 Complete

WB

OTD 1

SAS Phase 1Load

Transfer

YBI Hinge K EB

OTD 2 EB

SSD Demolition of

Existing Bridge

YBI Construction

EB

YBI Complete WB

Frame 2

YBI Complete EB

Frame 2

SAS Phase1Deck

Erection

SAS Phase1E2 Capbeam

SAS Phase1W2 Capbeam

OTD 2 EB Detour

SSD Traffic Switch

Bridge Closure

(Complete SSD WTI Phase 1)

SAS Phase 1Cable

InstallationE2/T1

T1Foundation

WB Traffic Switch

EB Traffic Switch

Page 31: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

WB to EB opening is a three-horse race – SAS, YBITS and OTD

Westbound

Eastbound OTD EB Contract

SASYBITS

Two contracts complete the west end.

Slowest horse wins

Page 32: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

The 3-horse race has a different outcome

0 50 100 150 200 250 300

Days from WB Open

SAS YBITS OTD EB

Page 33: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Example: Interaction of 2 contracts

Foundations Contract

Bridge Contract

Foundations Required

Bridge Contract

Question:

Pay $$ to accelerate Foundations contract

schedule?

Delay of Bridge ContractTimescale

Page 34: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Used schedule risk analysis to evaluate delay…

Decision: Don’t pay

< 5% chance of Foundations delaying Bridge

Page 35: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Summary

Quantitative risk analysis is not rocket science.

Schedule risks are analyzed in the schedule logic.

Cost and schedule risk analysis provides an important perspective to decision-makers.

Page 36: Risk Management in Value Engineering - Alaskadot.alaska.gov/stwddes/dcsspecs/assets/pdf/2009_ve_conf... · 2012. 2. 9. · Risk Management in Value Engineering AASHTO 2009 VE Conference,

Discussion?

Project Risk Management

Contact Information:

Rich [email protected](510) 385-7189

Rein [email protected](510) 410-4344