Ricardo-AEA - techUK · 2018-12-01 · © Ricardo-AEA Ltd Ricardo-AEA 21 January 2015 Target...
Transcript of Ricardo-AEA - techUK · 2018-12-01 · © Ricardo-AEA Ltd Ricardo-AEA 21 January 2015 Target...
© Ricardo-AEA Ltd
www.ricardo-aea.com
Ricardo-AEA
21 January 2015
Target Period Reporting Templates and
Target Period Variations
Eugenia Bonifazi
© Ricardo-AEA LtdRicardo-AEA in Confidence2
Reporting spreadsheets:
• Absolute s/s
• Relative s/s
• CHP SRM
• Novem TU reporting at the individual product level
• Novem TU reporting at the aggregate product level
• Target Period Performance Results
• Surplus and Buy-Out
• Novem Carbon s/s
• Errors during submission
• Reporting Variations:
– Drop in throughput
– Disruption of energy supply
Agenda
© Ricardo-AEA LtdRicardo-AEA in Confidence3
• Each workbook contains two spreadsheets
– Instruction on how to complete the report
– The actual template where the data must be entered
• Section 1: Reporting Details
This section is the same for all target types and contains
some prepopulated information:
– Sector name
– Target Period: TP1
– Report Version
• V1 when the spreadsheet is first downloaded
• New version when a variation have been processed
• New version if spreadsheet in unlock
• New version for secondary Buy-Out
– Template version will show v2 – only v2 will be accepted by the registry
• Green cells should be populated by the SA/consultant – these cells will not be used
for validation
Section 1: Report details
© Ricardo-AEA LtdRicardo-AEA in Confidence4
• Section 2: Target Unit Details, Targets and previous performance
different for each target type
• Blue cells will be pre-populated with data from the Register
• Pink cells are calculated
Section 2: Target Unit Details, Targets and previous
performance
Absolute TU
Novem TU
Relative TU
© Ricardo-AEA LtdRicardo-AEA in Confidence5
Section 3: Target Period Data
Number of light green
column reflects the
number of facilities in
the TU
Information to be
entered about the
performance of the
target facility within the
target period.
Data can alternatively
be entered at a TU level
in the bright-green
column
Pre populated
carbon factors
for standard
fuels
Names and
carbon factor
to be entered
manually for
“other fuels”
“No data entered” / “Single Facility TU” / “TU & Facility Data Entered” / “TU data entered” / Facility Data Entered”
© Ricardo-AEA LtdRicardo-AEA in Confidence6
Section 3: Target Period Data
The Absolute Flag
When the actual throughput for
the target period is less than
90% of twice the throughput in
the base year (absolute targets
only) a flag will appear
The TU can submit a variation
to amend the Targets following
a drop in throughput.
Note: the flag will not
disappear after the TPR
variation because only the
targets will be modified – NOT
the baseline.
© Ricardo-AEA LtdRicardo-AEA in Confidence7
Data must be entered from the day of assent: (CCA Op Manual Section 10.3)
- The full 24 months target period for migrated facilities
- Data from the day of assent for facilities that joined the scheme after 1st April 2013
The throughput value in this section should always be the actual throughput (even if the
TU is applying CHP SRM)
The energy must be reported in the TU energy Unit, e.g. kWh, MWh, GJ or PJ.
EUETS energy must not be included in the reported data (CCA Op Manual Section 10.3.1)
Data should be entered to the decimal place agreed with the facilitator or to the 3dp. If
formula are used, these should be rounded
What data should you enter in Section 3?
© Ricardo-AEA LtdRicardo-AEA in Confidence8
Section 3a: CHP Special Reporting Mechanism (SRM)
- Target units with Novem or Relative targets may have chosen to apply the CHP SRM
- If the TU is applying the CHP SRM the TPR spreadsheet will contain Section 3a
Information to be entered about
CHP delivered electricity (in TU
energy unit) at a facility level in
the light-green cells
Alternatively the adjusted throughput
for the whole TU can be entered in
the bright-green cell
The adjusted throughput is
then automatically calculatedWhere data are entered at facility level in
Section 3, they must also be entered at
the facility level in Section 3a
Variation is needed if the TU is using CHP
SRM but this information is not flagged in
the Registry
© Ricardo-AEA LtdRicardo-AEA in Confidence9
Section 4: Novem TUs
• Target units with Novem targets may report data at the individual product level or at the aggregated product level
The data will be used to automatically calculate two quantities necessary
for determining Novem targets and performance
Product Name or ID
Y/N option
Base year production
(or first 12 months of production if
product introduced after the BY)
Target improvement
(full target for products
introduced after BY)
Base year energy consumption for
production
(or equivalent energy “as if the product
was produced in the BY”) CCA OP Manual B.13
Remember to enter adjusted throughput if CHP
SRM has been applied
Data needed to report at
Individual Product level:
Target period production
(for 24 months or from day of
assent)
© Ricardo-AEA LtdRicardo-AEA in Confidence10
Section 4: Novem Flags
The Novem TPR spreadsheet performs some checks to make sure that the data entered at a single
product level agree with what is in the registry.
Three checks are carried out: The BY energy hold in the register and pre-
populated in Section 2 is equal to the sum of
individual product level BY energies entered in
Section 4 at a individual level data
The total saving as sum of the targets
distributed at an individual product level is
equal to the TU latest agreement target
The TP throughput entered Section 3 is
equal to the sum of individual product level
TP throughput
These checks are not used as validation tests and will
not prevent the SA/consultant to submit the spreadsheet
© Ricardo-AEA LtdRicardo-AEA in Confidence11
Section 4: Novem targets reporting data at the aggregated
product level
If the target unit reports at the aggregate
product level, it must enter aggregate values
for the products in the bright green cells of
Section 4. These are the quantities that would
have been automatically calculated by the
workbook.
If the target unit is audited, these individual
product level records will be examined by
Environment Agency auditors.
© Ricardo-AEA LtdRicardo-AEA in Confidence12
• Section 4 for Absolute and Relative Target units only contains the Performance Results
• Performance Results are automatically calculated by the workbook using the data provided
• Relative TUs can have tolerance on percentage targets. The effect of tolerance on performance results is shown
in the figure.
Section 4: Target Period Performance results
(Absolute and Relative)
TP Performance= target + tolerance
Surplus used and/or buy-out required
Target met
Target met within
tolerance
TP Performance = target - tolerance
Base year (SEC0 )
Target period performance
TP Performance = target
Target Period Results can be:
• Target Met
• Target Met within Tolerance
• Surplus used
• Surplus used and buy-out required
• Buy-out required
Effect of tolerance on Target Period Result
© Ricardo-AEA LtdRicardo-AEA in Confidence13
Section 5: Carbon Surplus or Buy-Out Determination
Section 5 is the same for each Target Unit type and provides Surplus and Buy-Out calculations
Surplus Gained in Tonne
CO2
The equivalent energy is the
amount of energy by which
the TU has over-achieved its
targets
Always positive
Buyout required in £
The equivalent energy is the
amount of energy by which
the TU has under-achieved
its targets
Always negative
© Ricardo-AEA LtdRicardo-AEA in Confidence14
Section 5: Supplementary MOA Surplus and Buy Out
After the first submission deadline, 1st May 2015, the Buy-Out MoAs will be issued.
Amendments required to the reported performance after the 1st July, will require the completion of a
secondary buyout reporting workbook
Surplus cannot be used to meet performance during secondary reporting.
Any remaining deficit against the target will generate a secondary buy-out. Any buy-out paid for as part
of the initial reporting will be taken into account when calculating the secondary buy-out.
© Ricardo-AEA LtdRicardo-AEA in Confidence15
Novem Carbon TPR spreadsheet
• There are 28 Novem TUs with
Carbon targets
• A separate spreadsheet
developed
• Section 3 will need to be
populated with energy in kWh
• If CHP SRM is applied electricity
needs to be reported in
DELIVERED kWh
© Ricardo-AEA LtdRicardo-AEA in Confidence16
Novem Carbon TPR spreadsheet
• Target units with Novem targets
may report data at the individual
product level or at the aggregated
product level
• For Individual product level data
Section 4 must be filled in with
Carbon figures (not energy)
• Performance is measured in SCC
“Specific Carbon Consumption”
• Spreadsheet will perform the
same checks to check carbon and
production balance.
© Ricardo-AEA LtdRicardo-AEA in Confidence17
• Completed reporting workbooks must be submitted by the sector or its consultant via the
reporting area on the register.
• Submissions should be completed as soon as possible and not left until the end of the reporting
period! (reduce excess load on the register and reduce the risk of not being able to correct
possible issues)
• When a report is uploaded, the register will run a series of automatic validation checks, and may
reject the submission. A description of the error will be provided.
Submitting the TPR spreadsheet
© Ricardo-AEA LtdRicardo-AEA in Confidence18
Possible errors during submission
Error Action required
ERROR: Target unit ABC/T00001 cannot be
found as a reportable target unit in this
reporting period.
Check TUID and confirm it is correct. Ensure
that the TU had an agreement in place on
31st December
ERROR: Target unit ABC/T00001 does not
belong to this sector. To upload a report for a
different sector, navigate to the correct
sector's target period reporting submissions
page.
Check that the TU report is being uploaded to
the correct sector reporting page.
ERROR: Target unit ABC/T00001 cannot be
reported on at this time. To enable reporting
submissions for this target unit, please contact
the Administrator.
The TUID is "locked" for reporting (either
because the 1st May deadline has been
reached, the TU has already uploaded data,
or the administrator has manually locked the
TU).
ERROR: The template uploaded uses an old
version of the target unit template. Version v1
has been superseded by version v2. The
latest version must be completed and
uploaded to ensure correct reporting results.
Download the latest reporting workbook, re-
enter the data and re-submit.
© Ricardo-AEA LtdRicardo-AEA in Confidence19
Possible errors during submission
Error Action required
ERROR: Cells in the spreadsheet expecting
numeric data contain invalid values
Check data entry to ensure that the data
entered meets the requirements of all
elements of the reporting workbook. Amend
any errors and re-submit.
ERROR: Results calculated in the register do
not match values calculated in the submitted
workbook. Please ensure that calculated
cells within the workbook are not altered
when entering data. The most likely way to fix
this issue is to download the latest version of
the spreadsheet template and re-enter the
data.
Download the latest version of the reporting
template and re-enter the data.
ERROR: An unknown error occurred
processing this file. If it does not correct itself
shortly, please contact the Administrator.
Contact the Environment Agency if the error
persists
© Ricardo-AEA LtdRicardo-AEA in Confidence20
Remember to “Enable Editing”
Depending on the system “Security Settings” the TPR spreadsheet could not pick up the energy and
throughput units.
For example the base year energy bracket (cell C23) is now showing (kWh).
Click on “Enable
Editing” and all the
fields will be
populated.
© Ricardo-AEA LtdRicardo-AEA in Confidence21
Reporting Variations
• In two circumstances variations may be submitted to reflect changes which may impact on a
target unit's target:
• the actual throughput for the target period is less than 90% of twice the throughput in the
base year (Absolute TU)
• there has been an unexpected disruption in energy supply
• An Operator must notify the Administrator on or before 31st January in the year following the end
of a target period
• Spreadsheets have been developed to calculate the modified targets in these circumstances
• Once the data have been collected and the s/s filled in SA/consultant must submit a TPR variation
• TPR variations do not modify the baseline
• TPR variations will affect the TP % targets
© Ricardo-AEA LtdRicardo-AEA in Confidence22
TPR variation: Drop in Throughput
• Two methods operators can adopt to adjust their targets in line with the fall in throughput.
• Method 1: Operator cannot provide statistically valid data to prove strong energy-throughput
relationship. This method applied:
• a taper to be applied when the TP throughput is between 10% and 20% less than 2 times the
BY throughput
• full value of the taper is added back to the target if the actual TP throughput is 10% less than
twice the BY throughout
• no taper is added back to the target if the actual TP throughput is 20% or more less than twice
the BY throughput.
• Method 2: Operator can demonstrate a statistically valid energy–throughput relationship, i.e. r-
squared value of greater than 0.8
Method 1 Method 2
© Ricardo-AEA LtdRicardo-AEA in Confidence23
TPR variation: Drop in Throughput
Method 2
Method 1
Coefficient shown here must be >0.8 to apply Method 2
Monthly breakdown of base year throughput and
energy must sum up with values in the register
This cell tells you whether the TU can
adjust the target
This cell tells you whether you
can apply Method 2 or not
© Ricardo-AEA LtdRicardo-AEA in Confidence24
• A variation can be submitted to adjust the target in line with the extra energy associated with the
disruption of power supply
• Information required as part of variation
– qualitative evidence that the supply of energy was disrupted
– qualitative evidence to demonstrate that the failure could not have been anticipated
– data to allow an adjusted target to be calculated
• The adjusted target will take account of the difference between the primary energy consumption
that would normally have been required to support operations for the period of the supply failure,
and the primary energy consumption that was actually required
• Targets must have been not met due to the extra energy consumption related to the disruption of
power supply
• Spreadsheet well check whether the TU has not met the targets due to the disruption
• Once the data have been collected and the s/s filled in SA/consultant must submit a TPR variation
TPR variation: Disruption of energy supply
© Ricardo-AEA LtdRicardo-AEA in Confidence25
TPR variation: Disruption of energy supply
Total energy consumption in TP
(including extra energy due to supply
disruption)
Additional energy consumption due to
disruption. Calculated in separate
information provided
Was the TP target not met because the
supply disruption? YES
Was the TP target not met? YES
© Ricardo-AEA LtdRicardo-AEA in Confidence26
Novem: Add a new product introduced after the BY
• Use first 12 months of production and energy consumption for the
new product (if 12 months are not available contact facilitator)
• Select “NO” to the question “Was this a product in the base year?”
row 77 of the Section 4 of the Novem TPR s/s
• Insert the throughput value in the reporting spreadsheet (Section 4,
row 76) – even if this throughput did not occur in the BY
• Insert the “Equivalent Energy” in row 77. Equivalent energy is the
energy which would have been used in 2008 to produce the same
throughput.
• Let’s assume that the new product was introduce in 2012. The
reference energy in 2008 (BY) will be:
2008 0.000%
2009 1.250%
2010 2.500%
2011 3.750%
2012 5.000%
2013 6.250%
2014 7.500%
2015 8.750%
2016 10.000%
2017 11.250%
2018 12.500%
2019 13.750%
2020 15.000%
Example of TU profile
CCA manual “Introduction of a new product” in section 4.4.
Reference energy 2008 =Energy (first 12 month period in 2012)
(1 − % that should have been achieved in 2012)
© Ricardo-AEA Ltd
www.ricardo-aea.com
T:
E:
W:
Ricardo-AEA Ltd
The Gemini Building
Fermi Avenue
Harwell, Didcot,
OX11 0QR
Eugenia Bonifazi
01235 75 3006
www.ricardo-aea.com