Rib a Plan of Work 2013 Presentation

39
www.ribaplanofwork.com RIBA Plan of Work 2013

description

MJM.MAJITH

Transcript of Rib a Plan of Work 2013 Presentation

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013

  • www.ribaplanofwork.com

    The RIBA Plan of Work 2013: an overview

    1. What are the key benefits?

    2. Why now?

    3. How was it developed?

    4. What is new?

    5. What does it mean for users?

    PresenterPresentation NotesThis presentation provides an overview to the RIBA Plan of Work 2013 for architects and other construction industry stakeholders. It is divided into five sections, each taking the viewer through different aspects of the RIBA Plan of Work 2013 and provides references for further information.

  • www.ribaplanofwork.com

    What is the RIBA Plan of Work 2013?

    The RIBA Plan of Work 2013 organises the process of briefing, designing, constructing, maintaining, operating and using building projects into eight Work Stages

    It is not a schedule of services document

    It is not intended to be contractual

    but it does set the scene

  • www.ribaplanofwork.com

    Landscape relating to the Plan of Work

    Complex contract cartography

    Constantly changing

    PresenterPresentation NotesThis diagram illustrates the complex landscape of standards, appointment agreements, contracts, reference materials and codes of practice which may use the RIBA Plan of Work as a framework or reference point.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Key benefits

    Fit for purpose for the construction industry in the 21st century to help deliver capital and operational efficiencies, carbon reductions and better briefing and outcomes

    More efficient design processes

    Suitable for all size and type of project

    Suitable for all procurement routes

    For use by the whole project team

    Simple and adaptable online tool

    PresenterPresentation NotesRIBA consultation has confirmed that many practices undertake significant amounts of straightforward and traditionally procured work, but at the same time the use of design and build and other procurement approaches continues to increase.

    The RIBA Plan of Work 2013 is suitable for both simple and complex projects and can cover a range of procurement options.

    The language used has been carefully considered to ensure it is clear and jargon free.

    A major new initiative in the RIBA Plan of Work 2013 is the online version enabling practices to develop project specific versions.

  • www.ribaplanofwork.com

    The RIBA Plan of Work 2013: an overview

    1. What are the key benefits?

    2. Why now?

    3. How was it developed?

    4. What is new?

    5. What does it mean for users?

  • www.ribaplanofwork.com

    RIBA Plan of Work: History

    1967 1973 1998 2007 2013

    1963 Plan of Work for Design Team Operations

    PresenterPresentation NotesRIBA Plan of Work: history

    Definitive model for building design and construction processes since 1963 launch Simplicity in its stages and tasksNon-contractualEvolution via regular updates - the latest in 2007No major review of the structure until nowPreviously focused on the activities of the design team.

  • www.ribaplanofwork.com

    RIBA Outline Plan of Work 2007 STRENGTHS

    Simplicity

    Stages A D clearly understood WEAKNESSES

    Simplicity

    Stages E and F loosely defined

    Traditional procurement bias

    Planning not embedded

    Soft landings/whole life cycle emphasis not included

    Performance specified work not covered

    PresenterPresentation NotesThe RIBA Outline Plan of Work 2007 is widely used and referenced throughout the construction industry.

  • www.ribaplanofwork.com

    RIBA Plan of Work: Why make changes?

    To reflect the increasingly complex construction landscape including:

    UK Government Construction Strategy

    Changing procurement processes

    Need for earlier collaboration and project team assembly

    Importance of client briefing

    Importance of handover and post occupancy work

    Increasing use of information management including BIM

    Complexity of design stages including specialist subcontractor design

    Changes in approach to town planning

    PresenterPresentation NotesWhy change the RIBA Plan of Work?Procurement options Design ResponsibilityPlanning ApplicationsMajor conceptual shift from focus on the Design Team to the Project Team which includes clients and contractors.

  • www.ribaplanofwork.com

    The RIBA Plan of Work 2013: an overview

    1. What are the key benefits?

    2. Why now?

    3. How was it developed?

    4. What is new?

    5. What does it mean for users?

  • www.ribaplanofwork.com

    The RIBA Plan of Work 2013: an overview

    Continuing dialogue with construction

    industry

    BIM Overlay

    RIBA members

    consultation

    Green Overlay

    CPD & further

    Industry Engagement

    May Aug Oct

    2012 2013 2014 Feb 21 May

    UK Government Digital Plan

    of Work

    PresenterPresentation NotesRIBA Plan of Work 2013: How was it developed?

    Winter 2011/2012: RIBA Plan of Work Review Group establishedSummer 2012: RIBA member and expert advisory group consultationAutumn 2012: RIBA Council in principal approvalWinter 2012/13: Continuing dialogue with external stakeholders & other professional institutes including CIC & Cabinet OfficeSpring 2013: Detailed guidance and online versions finalised and testedMay 2013: RIBA Plan of Work 2013 goes live

  • www.ribaplanofwork.com

    The RIBA Plan of Work 2013: an overview

    1. What are the key benefits?

    2. Why now?

    3. How was it developed?

    4. What is new?

    5. What does it mean for users?

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: core components

    Eight Stages & Eight Task Bars

    Simplicity retained, Flexibility added

    Maps to Governments Digital Plan of Work

    New topics included

    Defined terms & project strategies

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Eight Task Bars

    Each task bar is either:

    Eigh

    t Tas

    k Ba

    rs Fixed or

    Variable or Switchable

    PresenterPresentation NotesThe RIBA Plan of Work 2013 recognises that many aspects of construction projects vary from project to project. The Task Bars have been introduced to allow flexibility and to enable customised versions of the RIBA Plan of Work 2013 to be produced to suit specific project or practice requirements.

    [Click] The Core Objectives, Key Support Tasks and Information Exchanges are fixed and applicable to every project.

    [Click] The Procurement, Programme and Planning task bars are variable and can be customised to suit the particular procurement method being used, creating flexibility to adjust the timing of planning applications, tendering activities and to allow overlapping of stages if required.

    [Click] The Sustainability Checkpoints and UK Government Information Exchanges, or Gateway task bars are switchable and can be turned on or off depending on client requirements.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013 includes:

    Procurement options

    Design Responsibility

    Planning Application options

    Design Team to Project Team

    Whole Life / Sustainability

    Intelligent Briefing / Project Outcomes

    Soft Landings / Project Handover

    Information Exchanges

    Health & Safety

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Mapping

    PresenterPresentation NotesThere are five main strategic changes in the RIBA Plan of Work 2013:

    The creation of a new Stage 0 (Strategic Definition) underlines the need to strategically appraise and define a project prior to developing an Initial Project Brief.

    Stage 3 (Developed Design) maps broadly to the former stage D and part of stage E. The difference is that in the RIBA Plan of Work 2013 the Developed Design will be co-ordinated and aligned with the Cost Information by the end of the stage. This may not increase the amount of design work required but will necessitate additional time for reviewing and co-ordinating information.

    At the end of Stage 4, the design work of these designers will be completed, although they may have to respond to Design Queries that arise from work undertaken on site during Stage 5. This stage also includes and recognises the importance of design work undertaken by specialist subcontractors and/or suppliers employed by the contractor (Performance Specified Work in JCT contracts) and the need to define this work early in the process in the Design Responsibility Matrix.

    To allow the RIBA Plan of Work 2013 to be used in conjunction with different procurement approaches, a procurement task bar replaces work stages G, H and J and sets out the key tendering and contract tasks occurring at each stage. Stage 7 (In Use) has been introduced to recognise that Post-occupancy Evaluation and other new duties can be undertaken during the In Use period of a building.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Stage 0 Core Objectives

    Identify clients Business Case and Strategic Brief and other core project requirements.

    PresenterPresentation NotesStage 0 is used to ensure that the clients Business Case and the Strategic Brief have been properly considered before the Initial Project Brief is developed.The Strategic Brief may require a review of a number of sites or alternative options, such as extensions, refurbishment or new build. By asking the right questions, the consultants, in collaboration with the client, can properly define the scope for a project, and the preparation and briefing process can then begin.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Stage 1 Core Objectives

    Develop Project Objectives including Quality Objectives and Project Outcomes, Sustainability Aspirations, Project Budget, other parameters or constraints and develop Initial Project Brief. Undertake Feasibility Studies and review of Site Information.

    PresenterPresentation NotesSeveral significant and parallel activities need to be carried out during Stage 1 Preparation and Brief to ensure that Stage 2 Concept Design is as productive as possible. These split broadly into three categories:Developing the Initial Project Brief and Feasibility StudiesDeveloping the procurement and (town) planning strategies and the Project ProgrammeAssembling the project team and defining each partys roles and responsibilities and the Information Exchanges.The preparation of the Initial Project Brief is the most important task undertaken during Stage 1. The time required to prepare it will depend on the complexity of the project. When preparing the Initial Project Brief, it is necessary to consider: The projects spatial requirementsThe desired Project Outcomes, which may be derived following Feedback from earlier and similar projectsThe site or context, by undertaking Site Appraisals and collating Site Information, including building surveysThe budget, considering the relationship between brief, site or context and Project Budget.A project Risk Assessment is required to determine the risks to each party. The development of the procurement strategy, Project Programme and in some instances, a (town) planning strategy are all part of this early risk analysis.The importance of properly establishing the project team cannot be underestimated, given the increasing use of technology that enables remote communication and project development using Building Information Modelling (BIM). For Stage 2 to commence in earnest, it is essential that the team is properly assembled. The process necessary to achieve this, and to produce the various documents required to accompany each team members appointment, is considered in greater detail in the Guide to Using the RIBA Plan of Work 2013.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Stage 2 Core Objectives

    Prepare Concept Design, including outline proposals for structural design, building services systems, outline specifications and preliminary Cost Information along with relevant Project Strategies in accordance with Design Programme. Agree alterations to brief and issue Final Project Brief.

    PresenterPresentation NotesDuring Stage 2, the initial Concept Design is produced in line with the requirements of the Initial Project Brief. The project team also develops, in parallel with the Concept Design, a number of Project Strategies. Their importance at this stage will depend on how they influence the Concept Design. For example, the Sustainability Strategy is likely to be a fundamental component of the Concept Design, whereas a security strategy may have minimal or no impact and can therefore be developed during a later stage. It is essential to revisit the brief during this stage and it should be updated and issued as the Final Project Brief as part of the Information Exchange at the end of Stage 2.In parallel with design activity, a number of other related tasks need to be progressed in response to the emerging design, including a review of the Cost Information and procurement strategy, the development of a Construction Strategy, a Maintenance and Operational Strategy and a Health and Safety Strategy and updating of the Project Execution Plan.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Stage 3 Core Objectives

    Prepare Developed Design, including coordinated and updated proposals for structural design, building services systems, outline specifications, Cost Information and Project Strategies in accordance with Design Programme.

    PresenterPresentation NotesDuring this stage, the Concept Design is further developed and, crucially, the design work of the core designers is progressed until the spatial coordination exercises have been completed. This process may require a number of iterations of the design and different tools may be used, including design workshops. By the end of Stage 3, the architectural, building services and structural engineering designs will all have been developed, and will have been checked by the lead designer, with the stage design coordinated and the Cost Information aligned to the Project Budget. Project Strategies that were prepared during Stage 2 should be developed further and in sufficient detail to allow the client to sign them off once the lead designer has checked each strategy and verified that the Cost Information incorporates adequate allowances. Change Control Procedures should be implemented to ensure that any changes to the Concept Design are properly considered and signed off, regardless of how they are instigated.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Stage 4 Core Objectives

    Prepare Technical Design in accordance with Design Responsibility Matrix and Project Strategies to include all architectural, structural and building services information, specialist subcontractor design and specifications, in accordance with Design Programme.

    PresenterPresentation NotesThe architectural, building services and structural engineering designs are now further refined to provide technical definition of the project and the design work of specialist subcontractors is developed and concluded. The level of detail produced by each designer will depend on whether the construction on site will be built in accordance with the information produced by the design team or based on information developed by a specialist subcontractor. The Design Responsibility Matrix sets out how these key design interfaces will be managed.

    Using the design coordinated during the previous stage, the designers should now be able to develop their Technical Designs independently, with a degree of autonomy. The lead designer will provide input to certain aspects, including a review of each designers work.

    Once the work of the design team has been progressed to the appropriate level of detail, as defined in the Design Responsibility Matrix and the Design Programme, specialist subcontractors and/or suppliers undertaking design work will be able to progress their design work. The lead designer and other designers, where required as part of their Schedule of Services, may have duties to review this design information and to ensure that specialist subcontractor design work is integrated with the coordinated design.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Stage 5 Core Objectives

    Offsite manufacturing and onsite Construction in accordance with Construction Programme and resolution of Design Queries from site as they arise.

    PresenterPresentation NotesDuring this stage, the building is constructed on site in accordance with the Construction Programme. Construction includes the erection of components that have been fabricated off site. The procurement strategy and/or the designers specific Schedule of Services will have set out the designers duties to respond to Design Queries from site generated in relation to the design, to carry out site inspections and to produce quality reports. The output of this stage is the As-constructed Information.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Stage 6 Core Objectives

    Handover of building and conclusion of Building Contract.

    PresenterPresentation NotesThe project teams priorities during this stage will be facilitating the successful handover of the building in line with the Project Programme and, in the period immediately following, concluding all aspects of the Building Contract, including the inspection of defects as they are rectified or the production of certification required by the Building Contract.Other services may also be required during this period. These will be dictated by project-specific Schedules of Services, which should be aligned with the procurement and Handover Strategies. Tasks in relation to the Handover Strategy can be wide-ranging and may include: attending Feedback workshopsconsidering how any lessons learned might be applied on future projectsundertaking formal Post-occupancy Evaluation that considers whether the desired Project Outcomes have been achievedundertaking tasks in relation to commissioning or ensuring the successful operation and management of the building.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Stage 7 Core Objectives

    Undertake In Use services in accordance with Schedule of Services.

    PresenterPresentation NotesThis is a new stage within the RIBA Plan of Work. It acknowledges the potential benefits of harnessing the project design information to assist with the successful operation and use of a building.While it is likely that many of the handover duties will be completed during Stage 6, prior to conclusion of the Building Contract, certain activities may be required or necessary afterwards. These should be confirmed in the relevant Schedule of Services.While the end of a buildings life might be considered at Stage 7, it is more likely that Stage 0 of the follow-on project or refurbishment would deal with these aspects as part of strategically defining the future of the building.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Procurement Task Bar

    PresenterPresentation NotesThe Procurement Task Bar can be customised to reflect the procurement method.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Procurement Options available when generating a practice or project specific Plan of Work

    PresenterPresentation NotesStage activities relating to procurement and tendering are adjusted to reflect the selected procurement method.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Programme Task Bar

    PresenterPresentation NotesSimilarly, the programme task bar can be customised to reflect where parallel or overlapping stage activities occur, depending upon a chosen procurement method.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Programme Options available when generating a practice or project specific Plan of Work

    PresenterPresentation NotesOverlapping and parallel activities may occur in stages 3, 4 or 5.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: (Town) Planning Task Bar

    PresenterPresentation NotesThe RIBA Plan of Work 2013 also offers flexibility around the timing of planning applications to reflect commercial realities.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Planning Options available when generating a practice or project specific Plan of Work

    PresenterPresentation NotesNormally planning applications will be made at the end of Stage 3, but in some circumstances clients may wish planning applications to be made on the basis of Stage 2 information.

    The RIBA Plan of Work 2013 can accommodate this, but the client needs to be made aware of the inherent risks of such an approach.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: The template

    PresenterPresentation NotesThis template provides an overall summary of the RIBA Plan of Work 2013 in one diagram.

  • www.ribaplanofwork.com

    The RIBA Plan of Work 2013: an overview

    1. What are the key benefits?

    2. Why now?

    3. How was it developed?

    4. What is new?

    5. What does it mean for users?

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: how to use it

    Online tool www.ribaplanofwork.com Customise a practice,

    or project, specific RIBA Plan of Work 2013

    Free to use Available now Practice Project

    Template

    PresenterPresentation NotesA small practice using predominantly traditional procurement may only need a single bespoke practice RIBA Plan of Work 2013.

    A practice which utilises a range of different procurement approaches may instead choose to generate project specific versions of the RIBA Plan of Work 2013.

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Defined Terms & Project Strategies

    All terms in the Plan of Work template are defined in plain English in the glossary

    The defined terms include a series of project strategies

    Project strategies are prepared, reviewed, updated and implemented at differing stages

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Building a continuous cycle of improvement

    Start at the end

    Defining outcomes

    Making early decisions on handover strategy

    Using post occupancy evaluation

    Learning from completed projects

    Additional services provided in Stages 0 and 7

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Supporting publications

    RIBA Plan of Work 2013 Overview - free publication including: - Glossary of terms - Frequently Asked Questions - Hard copy & pdf available via www.ribaplanofwork.com

    Guide to using the RIBA Plan of Work 2013

    Assembling the Collaborative Project Team

    RIBA Job Book

    RIBA Agreements: alternative schedules of services

    Other documents will continue to be updated

    See www.ribabookshops.com/plan-of-work for more information & offers

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: What does it mean for users?

    Fit for purpose for the construction industry in the 21st century to help deliver capital and operational efficiencies, carbon reductions and better briefing

    More efficient design processes

    Suitable for all size and type of project

    Suitable for all procurement routes

    For use by the whole project team

    Simple

    Adaptable

    Online tool

  • www.ribaplanofwork.com

    RIBA Plan of Work 2013: Common queries from users

    The RIBA Plan of Work remain available but will be phased out over time as the RIBA Plan of Work 2013 gains wider usage

    The RIBA supports a resource based approach to fee calculation and we suggest users consider how fees might be fairly and reasonably apportioned between the new stages

    Fees for stages 0, 1 and 7 will generally be on a time charge basis: the proportion of fees charged for the remaining stages will be determined by project specific factors

  • www.ribaplanofwork.com

    Comments & feedback are welcome, please email: [email protected]

    RIBA Plan of Work 2013

    Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26Slide Number 27Slide Number 28Slide Number 29Slide Number 30Slide Number 31Slide Number 32Slide Number 33Slide Number 34Slide Number 35Slide Number 36Slide Number 37Slide Number 38Slide Number 39