11/17/2017 1 Survey No. 38, Cherlaguda Village, Shamshabad Mandal, RR District, Hyderabad- 501218 Phone: +91-40-30461661 Email: [email protected] Resources Planning Vinay Kumar Kalakbandi Assistant Professor Operations Management Operations Management - II PGDM 2017-19 11/17/2017 1 Introduction Computerised information system Aids in planning of materials in an organization Exploits certain unique characteristics of the production items Utilize information on lead time, inventory status and master production schedule to make material available exactly at the time of requirement Same logic could be extended to planning of other resources Called generally as resources planning 11/17/2017 2

Transcript of Resources Planning - VINAY...

11/17/2017

1

Survey No. 38, Cherlaguda Village, Shamshabad Mandal,

RR District, Hyderabad- 501218

Phone: +91-40-30461661

Email: [email protected]

Resources Planning

Vinay Kumar Kalakbandi Assistant Professor

Operations Management

Operations Management - II PGDM 2017-19

11/17/2017 1

Introduction • Computerised information system

– Aids in planning of materials in an organization

• Exploits certain unique characteristics of the production items – Utilize information on lead time, inventory status and master

production schedule to make material available exactly at the time of requirement

• Same logic could be extended to planning of other resources – Called generally as resources planning

11/17/2017 2

11/17/2017

2

Two types of inventories Distribution Inventory Independent Demand item

Operating Inventory Dependent demand item

11/17/2017 3

Characteristics of inventories Distribution Inventory

• Meant for market consumption

• Considerable uncertainty in demand

• Orders based on forecast

• 100% service level not feasible

• Continuous demand

Operating Inventory • Denotes all the resources

(broadly of material and capacity) that are available for the operating system to consume in the production process

• No uncertainty: Parent child relationship

• Production planning determines quantity

• Lumpy demand

11/17/2017 4

11/17/2017

3

Independent – Dependent Demand

11/17/2017 5

Dependency Relationship

11/17/2017 6

11/17/2017

4

Product structure

11/17/2017 7

level Level 4

Product structure

11/17/2017 8

11/17/2017

5

Bill of Materials – Single Level

11/17/2017 9

Indented BOM

11/17/2017 10

11/17/2017

6

Modular BOM

11/17/2017 11

MRP inputs and outputs

11/17/2017 12

11/17/2017

7

MRP Lot sizing rules

• Lot for Lot

• Economic Order Quantity

• Least Total Cost

• Least Unit Cost

11/17/2017 13

MRP terminologies • Explosion

– Iterative process of computing all requirements at a level and then moving down the level

• Product Structure – Graphically depicts relationships among various items that

make up final product

• Bill of Materials – List of all the materials needed to assemble one unit of

final product

11/17/2017 14

11/17/2017

8

Impact of Lead time

11/17/2017 15

Incorporating lead time

11/17/2017 16

11/17/2017

9

Lot Sizing Rules

11/17/2017 17

Master Production Schedule

• Drives MRP process with a schedule of finished products

• Quantities represent production not demand

• Quantities may consist of a combination of customer orders & demand forecasts

• Quantities represent what needs to be produced, not what can be produced

11/17/2017 18

11/17/2017

10

MRP Processing

• Takes the end item requirements specified by the master schedule and “explode” them into time-phased requirements for assemblies, parts, and raw materials using the bill of materials offset by the lead times

11/17/2017 19

Fields of MRP • Gross Requirements

– Total expected demand for an item or raw material in a time period

• Scheduled Receipts – Open orders scheduled to arrive from vendors or

elsewhere in the pipeline

• Project on-hand – Expected amount of inventory that will be on hand at the

beginning of each time period

11/17/2017 20

11/17/2017

11

Fields of MRP

• Net requirements – The actual amount needed in each time period

– Net requirements = gross requirements – Projected on hand + Safety stock

• Planned order releases – Planned amount to order in each time period

• Planned order receipts offset by lead time

11/17/2017 21

Fields of MRP

11/17/2017 22

11/17/2017

12

MRP Core logic

11/17/2017 23

Capacity Requirements planning

11/17/2017 24

11/17/2017

13

Comparison between MRP and CRP

11/17/2017 25

MPS – MRP – CRP

11/17/2017 26

11/17/2017

14

Manufacturing Requirements Planning (MRP II)

• Extension of MRP

• Plans all resources needed for running a business

• Variations include

– Service Requirements Planning (SRP)

– Business Requirements Planning (BRP)

– Distribution Requirements Planning (DRP)

11/17/2017 27

MRP II Modules • Forecasting • Customer order entry • Production planning / Master Production Scheduling • Product structure / Bill-of-Material processor • Inventory control • Material Requirements Planning • Capacity planning • Shop floor control • Purchasing • Accounting • Financial analysis

11/17/2017 28

11/17/2017

15

Enterprise Resource Planning (ERP)

11/17/2017 29

Typical modules of an ERP software • Sales and distribution • Production planning • Accounts payable/receivable, treasury • Operational (shop floor) control • Purchasing • Finance and cost control • Human resources

11/17/2017 30

11/17/2017

16

THANK YOU