Resolving Disputes on Public Contracts

85
Resolving Disputes on Public Contracts James F. Nagle Oles Morrison Rinker & Baker, LLP [email protected]

description

Resolving Disputes on Public Contracts. James F. Nagle Oles Morrison Rinker & Baker, LLP [email protected]. Phases of Dispute Resolution. Pre-contract During performance Making a claim The formal disputes process. Pre-contract—Advice to the Government. Pick a good contractor - PowerPoint PPT Presentation

Transcript of Resolving Disputes on Public Contracts

Page 1: Resolving Disputes on Public Contracts

Resolving Disputes on Public Contracts

James F. NagleOles Morrison Rinker & Baker, LLP

[email protected]

Page 2: Resolving Disputes on Public Contracts

Phases of Dispute Resolution

• Pre-contract• During performance• Making a claim• The formal disputes process

Resolving Disputes on Public Contracts 2

Page 3: Resolving Disputes on Public Contracts

Pre-contract—Advice to the Government

• Pick a good contractor– Don’t just use past performance ratings

• Don’t scare good contractors away with one-sided contracts

• Don’t ignore the red flags

Resolving Disputes on Public Contracts 3

Page 4: Resolving Disputes on Public Contracts

Pre-Contract—Advice to the Contractor

• Negotiate changes• Consider alternate bids • Avoid mistakes• Bid properly or run away

Resolving Disputes on Public Contracts 4

Page 5: Resolving Disputes on Public Contracts

Pre-Contract—Advice to Both Sides

• Resolve the disputes process up-front– Partnering– The disputes process itself

Resolving Disputes on Public Contracts 5

Page 6: Resolving Disputes on Public Contracts

During Performance– Advice to the Government

• Acknowledge problem• Offer consideration• Don’t mindlessly try to be tough• Understand the differences between legal rights

and practical value

Resolving Disputes on Public Contracts 6

Page 7: Resolving Disputes on Public Contracts

During Performance—Advice to the Contractor

• Recognize that suing your customer is not the best way to make friends and influence people

• Recognize that suing the sovereign is fraught with problems

Resolving Disputes on Public Contracts 7

Page 8: Resolving Disputes on Public Contracts

Making a Claim—Give Appropriate Notice

• Give notice to proper person• Consider the form of notice• Be as precise as possible regarding the

quantum portion

Resolving Disputes on Public Contracts 8

Page 9: Resolving Disputes on Public Contracts

Resolving the Claim—Advice to the Government

• Litigation is a drain on your resources • Fear of precedents

Resolving Disputes on Public Contracts 9

Page 10: Resolving Disputes on Public Contracts

Resolving the Claim—Advice to Contractors

• The longer it goes on, the more it will cost you• How to resolve it

– ADR– Litigation

Resolving Disputes on Public Contracts 10

Page 11: Resolving Disputes on Public Contracts

Typical Dispute Scenarios

• US —> Prime• Prime —> US• Prime —> Subcontractor• Subcontract —> Prime

Resolving Disputes on Public Contracts 11

Page 12: Resolving Disputes on Public Contracts

Typical Disputes

• Government/Buyer– Warranties– Deductive/Substitution Changes– Over Payment – Delay damages

Resolving Disputes on Public Contracts 12

Page 13: Resolving Disputes on Public Contracts

Typical Disputes

• Seller– Changes—constructive changes– Delays– Differing site conditions – Property issues– Terminations

Resolving Disputes on Public Contracts 13

Page 14: Resolving Disputes on Public Contracts

The Changes Clause

Resolving Disputes on Public Contracts

Subparagraph (a)

“The CO may, at any time, by written order, and without notice to the sureties, make changes within the general scope of the contract.”

Subparagraph (b)—Equitable Adjustment

Subparagraph (c)—Notice Requirements

Subparagraph (d)—Disposition of Property

Subparagraph (e)—Duty to Proceed

14

Page 15: Resolving Disputes on Public Contracts

Scope of the Contract

Resolving Disputes on Public Contracts

• No guidance in the regulations• Based on Statement of Work• No automatic test• Consideration of several factors

15

Page 16: Resolving Disputes on Public Contracts

Changes Outside Scope of Contract

Resolving Disputes on Public Contracts

Cardinal changes• Not covered by changes clause• Contractor does not have to perform• Others can protest• Must be funded with different money• Contractor can reprice contract

16

Page 17: Resolving Disputes on Public Contracts

Determining if Change is Out of Scope

Resolving Disputes on Public Contracts

• Nature of the item• Purpose of the contract• Dollar value• Complexity of the contract• Number of changes• Fairness to the contractor• Effect on the competition• Cumulative impact

17

Page 18: Resolving Disputes on Public Contracts

Constructive Changes

Resolving Disputes on Public Contracts

Implied or Inferred• What are the changes?• Why are the changes occurring?• Who can approve the change?• What factors should be considered before approval?

Elements• A change• An order

18

Page 19: Resolving Disputes on Public Contracts

Who Can Constructively Change the Contract?

Resolving Disputes on Public Contracts

Virtually anyone other than the contractor• COs• Other CO representatives• Specially authorized representatives• Inspectors• Project managers and officers• Auditors• Negotiators• Other contractors

19

Page 20: Resolving Disputes on Public Contracts

Disclaimer Statement

Resolving Disputes on Public Contracts

COR/COTR disclaimer

You are hereby notified that I do not have the authority to direct you in any way to alter your obligations or change the SOW in your contract. Further, if the government, as a result of the information obtained from today’s discussion, does desire to alter your contract obligations or change the contract SOW, changes will be issued in writing and signed by the CO. You should take no action on any change unless and until you receive such a change order.

20

Page 21: Resolving Disputes on Public Contracts

Factors in Determining Constructive Changes

Resolving Disputes on Public Contracts

• Authority of person giving “order”• Specifically expressed (not apparent)• Implied

• Amount of discretion or authority • Disclaimers

• Actions of CO• Vested person with implied authority• Ratified• Acquiesced—imputed knowledge

21

Page 22: Resolving Disputes on Public Contracts

Factors in Determining Constructive Changes (continued)

Resolving Disputes on Public Contracts

• Reasonableness of contractor’s action• Reasonable reliance• Duty to inquire—suspicion• Time to inquire• Contractor’s experience• Contractor’s knowledge

• Did the government get a benefit?• Volunteer not favored

• Good faith

22

Page 23: Resolving Disputes on Public Contracts

Types of Constructive or Implied Changes

Resolving Disputes on Public Contracts

• Contract interpretation• Interference and noncooperation• Defective specifications• Government information deficiencies

• Superior knowledge• Misrepresentation

• Acceleration

23

Page 24: Resolving Disputes on Public Contracts

Differing Site Conditions

Resolving Disputes on Public Contracts

• Differing Site Conditions Clause (FAR 52.236-2)• Required in all fixed-price construction,

dismantling, demolition, and removal of improvements contracts exceeding $25,000

• Stop• Give notice

24

Page 25: Resolving Disputes on Public Contracts

Differing Site Conditions (continued)

Resolving Disputes on Public Contracts

• Two types of differing site conditions allow adjustment:• Subsurface or latent physical conditions at the site

that differ materially from those indicated in the contract

• Unknown physical conditions at the site, of an unusual nature, that differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the contract

25

Page 26: Resolving Disputes on Public Contracts

Notice

Resolving Disputes on Public Contracts

• Who must you tell?• What must you tell?• When must you tell?• So, what if you don’t tell?

26

Page 27: Resolving Disputes on Public Contracts

Equitable Adjustment

Resolving Disputes on Public Contracts

• Difference between what would have cost to perform the original contract and the cost to perform the contract as changed• “Leave ‘em as you find ‘em”

27

Page 28: Resolving Disputes on Public Contracts

Understand the Basis of Claims

Resolving Disputes on Public Contracts

• Some clauses exclude cost/profit or cap costs• Excluding cost/profit

• Suspension of work or government delay of work • Multiyear SCA clauses

• Capping cost• Special termination cost in DOD

28

Page 29: Resolving Disputes on Public Contracts

Measure of an Equitable Adjustment

Resolving Disputes on Public Contracts 29

Page 30: Resolving Disputes on Public Contracts

Request for Equitable Adjustment

Resolving Disputes on Public Contracts

• Whichever side wants the benefit bears the burden• Must prove two things:

• Entitlement• Quantum-costs/time caused by the claimed

event

30

Page 31: Resolving Disputes on Public Contracts

Types of Changes Warranting Equitable Adjustments

Resolving Disputes on Public Contracts

• Adding work• Deleting work• Substituting work• Delaying work• Accelerating work• Disrupting work

31

Page 32: Resolving Disputes on Public Contracts

Admiral Corp.

Resolving Disputes on Public Contracts

ASBCA No. 8634, 1964 BCA 4161

Cost

Original component $7.52

Substituted component 11.63

Included in bid for this item 12.48

What result occurs?

32

Page 33: Resolving Disputes on Public Contracts

Types of Delay

Resolving Disputes on Public Contracts

• Inexcusable• Contractor responsible• Neither time nor money

• Excusable• Contractor not responsible• Contractor receives time but no money

• Compensable• Government responsible for a contractual act• Contractor receives time and money

33

Page 34: Resolving Disputes on Public Contracts

Concurrent Delays

Resolving Disputes on Public Contracts

• Inexcusable and excusable• Neither time nor money

• Inexcusable and compensable• Neither time nor money• Neither party can collect money damages from

the other• Excusable and compensable

• Time but no money

34

Page 35: Resolving Disputes on Public Contracts

Delays

Resolving Disputes on Public Contracts

• What was supposed to happen (as planned)?• Why did the delay occur?• What did happen (as-built)?• Who has assumed the risk?• How long did the delay last?

35

Page 36: Resolving Disputes on Public Contracts

Weather Delays

Resolving Disputes on Public Contracts

• Standard—unusually severe weather• Meeting the standard

• What is usual?• Time• Place• Yardstick—rainy days, inches of rainfall,

temperature, windchill, and so on• Length of historical database• Probability—above average?

36

Page 37: Resolving Disputes on Public Contracts

Weather Delays (continued)

Resolving Disputes on Public Contracts

• What was experienced?• Types of records• Where recorded• Work days and times

37

Page 38: Resolving Disputes on Public Contracts

Weather Delays (continued)

Resolving Disputes on Public Contracts

• Proving the delay• Impact on critical path• Whole or partial days• Types of impact (assess the damage)

• Lost time• Reduced productivity• Unplanned work• Lingering effects

38

Page 39: Resolving Disputes on Public Contracts

Weather Delays (continued)

Resolving Disputes on Public Contracts

• Did the contractor mitigate?• Reasonable precautions

• For type of weather experienced• For common effects

• Reasonable mitigation• Rescheduling• Substitutions

39

Page 40: Resolving Disputes on Public Contracts

Typical Delay Damages

Resolving Disputes on Public Contracts

• Idle labor• Idle equipment and facilities• Labor, material, and other cost escalation• Unabsorbed overhead• Disruption• Acceleration

40

Page 41: Resolving Disputes on Public Contracts

Equipment Costs

Resolving Disputes on Public Contracts

Entitlement requirements• Equipment was dedicated specifically to project• Equipment would have been used, if not for delay• Equipment could not have been used elsewhere• Equipment was in sound workable condition

41

Page 42: Resolving Disputes on Public Contracts

Equipment Costs (continued)

Resolving Disputes on Public Contracts

How to prove damages• Rented equipment

• Rent• Owned Equipment

• Actual costs• Contract rates• Industry rates

42

Page 43: Resolving Disputes on Public Contracts

Unabsorbed Overhead

Resolving Disputes on Public Contracts

• What is it?• What must the contractor prove for entitlement?• How does the contractor prove quantum?

43

Page 44: Resolving Disputes on Public Contracts

Unabsorbed Overhead (continued)

Resolving Disputes on Public Contracts

• Calculation• The difference between the amount bid and the

amount you were able to allocate or• The amount calculated using Eichleay formula

44

Page 45: Resolving Disputes on Public Contracts

Eichleay Formula

Resolving Disputes on Public Contracts

contract billings

contractor billings

contract overhead

days of performance

X contractor overhead = overhead allocable to contract

= daily overhead rate (DOR)

DOR X days of delay = unabsorbed overhead

*Includes period of delay

45

Page 46: Resolving Disputes on Public Contracts

Unabsorbed Overhead – Eichleay Method

Resolving Disputes on Public Contracts

Pro[p]serv, Inc., ASBCA No. 20768, 78-1 BCA ¶ 13066

$143,646

675,748

$12,801

365

$35.07 x 150 = $5,261

Profit at 15% = $ 789

$6,050

X 60,221.00 = $12,801

= $35.07

46

Page 47: Resolving Disputes on Public Contracts

Disruption, Loss of Efficiency, Loss of Productivity

Resolving Disputes on Public Contracts

“Death by a thousand cuts”• Work not necessarily stopped, just more difficult• Anything that affects the productivity the contractor

would have achieved• Can be combined with added, deleted, substituted,

delayed or accelerated work• Can be sole basis

47

Page 48: Resolving Disputes on Public Contracts

Disruption, Loss of Efficiency, Loss of Productivity (continued)

Resolving Disputes on Public Contracts

Causes• Delay due to adverse weather• Changes• Learning curve disruptions• Out-of-sequence work• Trade packing• Anything else that affects productivity

48

Page 49: Resolving Disputes on Public Contracts

Disruption, Loss of Efficiency, Loss of Productivity (continued)

Resolving Disputes on Public Contracts

• Increased labor costs• More direct hours to do the work• More time lost to absenteeism and tardiness• More time lost to rework

• Increased material costs due to rejects

49

Page 50: Resolving Disputes on Public Contracts

Proving Loss of Productivity

Resolving Disputes on Public Contracts

• Flexy Plan Industry—GSBCA 4117, 76-1 BCA 11713• Batteast Construction Co., Inc.—ASBCA 35818, 92-1

BCA 24697• Shea, Proving Productivity Losses in Government

Contracts, 18 Pub. Cont. L.J. 414 (1989)

50

Page 51: Resolving Disputes on Public Contracts

Acceleration Costs

Resolving Disputes on Public Contracts

• Hidden• Disruption—Loss of efficiency

• Clear• Overtime wages• More workers• More equipment• Expedited deliveries

51

Page 52: Resolving Disputes on Public Contracts

Actual Cost Method—Profitable Contract

Resolving Disputes on Public Contracts

Contract Price (A) $1,200,000

Cost to perform original contract (B) $1,000,000

Cost to perform revised contract $1,500,000because of claimed event (C)

Extra cost caused by the claimed $ 500,000event (C – B)

Contract price is irrelevant

52

Page 53: Resolving Disputes on Public Contracts

Actual Cost Method—Loss Contract

Resolving Disputes on Public Contracts

Contract price (A) $1,200,000

Cost to perform original contract (B) $1,400,000

Cost to perform revised contract $1,500,000because of claimed event (C)

Extra cost caused by the claimed $ 100,000event (C – B)

53

Page 54: Resolving Disputes on Public Contracts

Total Cost Method

Resolving Disputes on Public Contracts

Total Cost $2,000,000

Less bid price (1,200,000)

Costs claimed 800,000

Plus profit @ 10% 80,000

Total claim $ 880,000

54

Page 55: Resolving Disputes on Public Contracts

Total Cost Method #2

Resolving Disputes on Public Contracts

Total Cost $2,000,000

Less bid price (1,200,000)

Costs claimed 800,000

Plus profit @ 10%of $2,000,000 200,000

Total claim $1,000,000

55

Page 56: Resolving Disputes on Public Contracts

Total Cost Method #3

Resolving Disputes on Public Contracts

Total Cost $2,000,000

Less contract price (1,200,000)

Costs claimed 800,000

Plus profit in original price 200,000

Plus profit on added cost 80,000

Total profit 280,000

Total claims $1,080,000

56

Page 57: Resolving Disputes on Public Contracts

Modified Total Cost Method

Resolving Disputes on Public Contracts

Total Cost $2,000,000

Less bid price (1,200,000)

Costs claimed (gross) 800,000

Less bidding errors (100,000)

Less productivity problems (100,000)

Costs claimed (net) 600,000

Plus profit @ 10% 60,000

Total claim $ 660,000

57

Page 58: Resolving Disputes on Public Contracts

Jury Verdict Method

Resolving Disputes on Public Contracts

Western Alaska Contractor, J.V.ASBCA No. 46033, 95-1 BCA 27392

Contractor claim for equipment using $1,007,644.68Blue Book rates for 12 months

Government position based on book$ 73,530.00value minus depreciation for 6 months

Board decision $ 550,000.00

58

Page 59: Resolving Disputes on Public Contracts

Mechanics of the Modification Process

Resolving Disputes on Public Contracts

• Timing• Prospective• Retroactive

• Unilateral or bilateral• Definitized or not• Request for equitable adjustment• Truth in Negotiations Act• Release

59

Page 60: Resolving Disputes on Public Contracts

Disputes Process

Resolving Disputes on Public Contracts

• FAR Subpart 33.2• FAR 52.233-1—Disputes Clause

60

Page 61: Resolving Disputes on Public Contracts

Jurisdictional Path of a Claim

Resolving Disputes on Public Contracts 61

Page 62: Resolving Disputes on Public Contracts

Disputes Clause

Resolving Disputes on Public Contracts

Subparagraph (a)• Contracts

• Not grants• Not preaward• Can be waived

Subparagraph (b)• Matters reserved to other agency

• SBA, DOL, OSHA, EPA• Fraud• Torts• Remedies

62

Page 63: Resolving Disputes on Public Contracts

What Starts the Process?

Resolving Disputes on Public Contracts

Claim

A written demand or assertion by one of the contracting parties seeking, as a mater of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising or relating to the contract.

—FAR 52.233-1(c)

63

Page 64: Resolving Disputes on Public Contracts

Nagle’s Rules on Claims

Resolving Disputes on Public Contracts

• Keep it as simple as possible• Make it as detailed as necessary• Use contemporary documents whenever possible

64

Page 65: Resolving Disputes on Public Contracts

Reflectone Changes the Rules

Resolving Disputes on Public Contracts

• The court distinguished between routine and nonroutine requests for payment

• Routine requests are vouchers, invoices, and requests for progress payments

• Nonroutine requests include constructive changes and termination settlement proposals

• A nonroutine request need not be in dispute when submitted, but if it exceeds $100,000, it must be certified to be a claim

65

Page 66: Resolving Disputes on Public Contracts

Reflectone Causes Dilemma for Contractors

Resolving Disputes on Public Contracts

• If contractors want interest on their submission and a quick response, they should treat the submission as a claim under the Contract Disputes Act

• If contractors want to be able to recoup the costs of paying their consultant, they should not treat the submission as a claim but as a request for an equitable adjustment

66

Page 67: Resolving Disputes on Public Contracts

FASA Statute of Limitations

Resolving Disputes on Public Contracts

• Was created by the FASA 2351(a) amendment to the Contract Disputes Act (CDA)

• Places a 6-year time limit on the submission of CDA claims (that is, CDA claims must be filed within 6 years of their accrual)

• Creates an issue regarding when the contractor knew, or should have know, of its claim

• Applies only to contracts awarded after October 1, 1995 (FAR 33.206; 60 Federal Register 48224)

67

Page 68: Resolving Disputes on Public Contracts

Certification

Resolving Disputes on Public Contracts

If more than $100,000, then contractor claim must be certified•Good faith•Supporting data are accurate and complete to the best of contractor’s knowledge and belief•Amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable•Signer is duly authorized to certify claim

68

Page 69: Resolving Disputes on Public Contracts

Defective Certification

Resolving Disputes on Public Contracts

The CO must challenge improper certification within 60 days (FAR 33.211(e)).•If the CO fails to do so, the government waives its right to assert defects in the certification•However, the CO can require proper certification before making payment

69

Page 70: Resolving Disputes on Public Contracts

When Must the CO Decide?

Resolving Disputes on Public Contracts

• For contractor claims of $100,000 or less• Within 60 days of contractor’s written request

• For contractor claims exceeding $100,000• Within 60 days or notify contractor of reasonable

date by which decision will be made

70

Page 71: Resolving Disputes on Public Contracts

Contractor Options if the CO Does Not Issue a Timely Decision

Resolving Disputes on Public Contracts

• Go directly to board or court for order• Consider inaction a “deemed denial” of claim and

commence litigation

71

Page 72: Resolving Disputes on Public Contracts

CO’s Decision

Resolving Disputes on Public Contracts

• Is written and gives reasons• Is final unless timely appeal is made

72

Page 73: Resolving Disputes on Public Contracts

Alternative Dispute Resolution (ADR) Procedures

Resolving Disputes on Public Contracts

• ADR Act of 1996, 5 U.S.C. 571 et seq.• Partnering• Mediation• Binding arbitration (award final 30 days after service

but may be extended 30 days)• Nonbinding arbitration• Settlement judge (Board judge will act as mediator)• Mini-trial

73

Page 74: Resolving Disputes on Public Contracts

Interest

Resolving Disputes on Public Contracts

• Simple interest at rate provided by the Department of the Treasury

• From receipt of claim by CO until payment

74

Page 75: Resolving Disputes on Public Contracts

Duty to Continue

Resolving Disputes on Public Contracts

• Generally must continue performance while matter is disputed, unless breach of contract has occurred

• Disputes clause – alternative 1 requires continued performance even if a breach of contract has occurred (rarely used)

75

Page 76: Resolving Disputes on Public Contracts

Appeal

Resolving Disputes on Public Contracts

• To Board of Contract Appeals (BCA)• Make within 90 days of receipt of decision• Mail or otherwise provide written notice to BCA with

copy to CO• Indicate appeal, reference the decision, and give

the contract number• To U.S. Court of Federal Claims (CFC)

• Make within 12 months of receipt of decision

76

Page 77: Resolving Disputes on Public Contracts

Expertise

Resolving Disputes on Public Contracts

BCA• 5 years of experience in public contracts required• Only hears contract matters• Communal decision making

CFC• No requirement for public contract experience• Hears matters other than contracts• Individual judge decides

77

Page 78: Resolving Disputes on Public Contracts

Formality

Resolving Disputes on Public Contracts

BCA• Informal• Evidence

• Rule 4 File• No jury

• Procedure• Federal Rules of Civil Procedure (FRCP) do not

apply

78

Page 79: Resolving Disputes on Public Contracts

Formality (continued)

Resolving Disputes on Public Contracts

CFC• Formal judicial process• Evidence

• More rigid adherence to Federal Rules of Evidence (FRE)

• Procedure, under adherence to its version of FRCP

79

Page 80: Resolving Disputes on Public Contracts

Representation

Resolving Disputes on Public Contracts

BCA• Contractor

• Pro se or attorney• Government

• Agency Counsel—local or headquartersCFC• Contractor

• Partnership or corporation—must have attorney• Government

• Department of Justice (DOJ) with agency “of counsel”

80

Page 81: Resolving Disputes on Public Contracts

Settlement

Resolving Disputes on Public Contracts

BCA• CO makes the decision to settle• Perhaps with concurrence of chief trial attorney

CFC• DOJ attorney makes decision to settle• Regardless of whether CO wants to or not

81

Page 82: Resolving Disputes on Public Contracts

Fraud Jurisdiction

Resolving Disputes on Public Contracts

Fraud counterclaim• Yes at CFC• No at BCA

Forfeiture Act (28 U.S.C. 2514)• Yes at CFC• No at BCA

82

Page 83: Resolving Disputes on Public Contracts

Expedited and Accelerated BCA Cases

Resolving Disputes on Public Contracts

Claims of $50,000 and less--expedited

• Sole discretion of contractor

• Decision with 120 days

• One judge decides

• No appeal

Also applies to claims of $150,000 or less by a small business

Claims of $100,000 and less—accelerated

• Sole discretion of contractor

• Decision within 180 days

• Three judge panel

• Full appeal rights

83

Page 84: Resolving Disputes on Public Contracts

Appeals from BCA or U.S. Court of Federal Claims

Resolving Disputes on Public Contracts

• To Court of Appeals for the Federal Circuit• BCA—within 120 days• CFC—within 60 days

84

Page 85: Resolving Disputes on Public Contracts

Equal Access to Justice Act

Resolving Disputes on Public Contracts

• Small Contractor• Individual: Not more than $2 million in net worth at

the time action initiated• Partnership or corporation: Not more than $7 million

in net worth and not more than 500 employees—both at the time the case began

• Government position not substantially justified• Reasonable costs

85