Réseau électrique métropolitain (REM)
-
Upload
phamkhuong -
Category
Documents
-
view
226 -
download
4
Transcript of Réseau électrique métropolitain (REM)
0
Réseau électrique métropolitain(REM)
cdpqinfra.com
Technical briefingProject update
November 2016
AFTER 15 MONTHS OF WORK
> Review of all studies carried out in the past for two separate projects
> Review of assumptions – ridership, route, stations and operations – based on a single integrated project
> Continuous project management
> Consultations with stakeholders
> 6 open house sessions
> Meeting with + than 150 stakeholders
> BAPE public hearings
> Second series of open houses
> Land reserves – land proneto property speculation
> Technical plans and estimates
> Qualification process
> Environmental studies, analyses and reports
> Agreement with CN (access to Gare Centrale)
> Call for proposals process
> Business model relying on diverse sources of financing
> Technical solutions for three downtown Montréal stations
1
TECHNICAL SOLUTIONS – DOWNTOWN STATIONS 2
Édouard-Montpetit, McGill and Bassin Peel stations
> Technical solutions identifiedby the CDPQ Infra teams:
> meet the specificchallenges and needsof each station
> ensure efficient user transfer from the REM to the métro
TECHNICAL CHALLENGES MET 3
Mont-Royal4-elevator systemHigh-speed: 20 secondsHigh-capacity: 5,000 people / hour
> Integration of stations in the Mont-Royal Tunnel
Depth of the station70 metres – 20 floors
Densely built environmentMontréal’s underground city
Start of tunnel
Canora StationÉdouard-Montpetit Station
McGill Station Gare Centrale
McTavish ventilation unit
Édouard-Montpetit
ventilation unit
Technical features> Depth of the station: 70 metres(20 floors) – among the deepestin North America
> High-capacity elevators(5,000 people / hour), high-frequencyand high-speed, allowing access to the surface and the platform in 20 seconds
> Excavation of 25,000 m3 of rockExcavation methods similar to those usedin underground mining
ÉDOUARD-MONTPETIT STATION 4
Station 70 metres under Mont-Royal
20 floors in20 seconds
20-second connection by way of 4 elevators
Blue line
Technical features> Retainment work to support foundations of the surroundingbuildings and tunnel vaults
> Integration into urban technical networks
McGILL STATION 5
Station under McGill College Avenue
Different access points to Montréal’s underground city
Access to Place Montréal Trust
Access to Centre Eaton
Green line
BASSIN PEEL STATION 6
Technical features> Two potential stations (Bridge-Wellington and Du Havre) initially planned in this area> One station now planned to consolidate transit service and align with Montréal’sdevelopment plans for these areas
> Central platform for boarding in both directions> Two entrances will provide access to north and south:North: towards the Griffintown area / South: towards Pointe-Saint-Charles
> Substantial work to consolidate soil and rock under the Peel Basin
Griffintown
Pointe-Saint-Charles
Station under the Peel Basin
7
> Connecting the Blue and Green lines – connection 10 times faster
Current travel time: 30 minutes in both directions
Projected travel time: 2 to 3 minutes
2-3 min.
Édouard-Montpetit
McGill
Édouard-Montpetit
McGill
MAIN BENEFITS
MAIN BENEFITS 8
> Alleviates pressure on the Orange line south of the Blue lineNew high-frequency north-south
public transit axisConvergence point saturated
towards downtown
9
Mont-Royal
Examples of hubs served:• Université de Montréal• HEC Montréal• Polytechnique Montréal
Certain hospitals:• CHU Sainte-Justine• Jewish General Hospital• St. Mary’s Hospital
Examples of hubs served:• McGill University• Montréal’s underground city (RÉSO)• Business district
MAIN BENEFITS
> Different strategic hubs served
Édouard-Montpetit StationMcGill Station
MAIN BENEFITS 10
> New points of departure from downtown to the Montréal airport
Three direct points of departure to the airport from downtown
NEXT STEPS 11
Call for proposalsfrom qualifiedconsortiums
Second seriesof open houses
Governments’ final decisionon the project
Creationof a communityrelations office
Start of construction
Operationof first trains
Submissionof BAPE report
Submissionsof proposals
Fall2016
Winter2017
Spring2017 2020
End of December2016