Research Project Presentation
description
Transcript of Research Project Presentation
Research Project Research Project PresentationPresentation
SteveSteve HowarthHowarth
Presentation OutlinePresentation OutlineProject TitleProject Title
Project HypothesisProject Hypothesis
Project BackgroundProject Background
Project ObjectivesProject Objectives
Research MethodResearch Method
Scope of the ResearchScope of the Research
Survey ResultsSurvey Results
Literature ReviewLiterature Review
ConclusionConclusion
RecommendationsRecommendations
Benefits of the ResearchBenefits of the Research
““The development and The development and implementation of an implementation of an
effective management and effective management and monitoring system, to monitoring system, to
ensure that cranes comply ensure that cranes comply with statutory with statutory requirements”.requirements”.
Project TitleProject Title
“The non-compliance to statutory requirements will decrease upon the implementation of the
inspection regime”
HypothesisHypothesis
In January, 2001, the Labour In January, 2001, the Labour Department conducted a survey Department conducted a survey
of the cranes and lifting of the cranes and lifting appliances on the KCRC’s West appliances on the KCRC’s West
Rail project. Rail project.
Project BackgroundProject Background
It was found that It was found that 34%34% of the of the cranes were not fitted with an cranes were not fitted with an automatic safe load indicator, automatic safe load indicator,
or if fitted, it was not or if fitted, it was not functioning correctly.functioning correctly.
Shanghai
Project ObjectivesProject Objectives
To develop an inspection and
enforcing system for ensuring
compliance to the statutory
requirements;
To implement the system;
To revise and improve the system, following comments from those concerned in the implementation, and
Project Objectives (cont)Project Objectives (cont)
To review the effectiveness of the system, in ensuring compliance to statutory requirements.
Scope of the ProjectScope of the Project
KCRC’s, West Rail and East Rail Extensions projects;
23 construction sites;
Surveys conducted monthly over a 6 month period, May – Oct, 2001;
All cranes.
Research MethodResearch MethodParticipatory Action Research (PAR)
based on Lewin’s Cyclic Model
Act
Review
Plan
ReviewReview
Conduct a survey of all
cranes being used on the
2 projects to establish if
there is a high rate of
non- compliance to
statutory requirements.
PlanPlan
Review the Hong Kong
Legislation to identify what the
statutory requirements are;
Develop an inspection
checklist;
Train the surveyors to use the inspection checklist;
Plan (cont)Plan (cont)
Conduct a survey of all the cranes being used on the 2 projects to establish if there was a problem with the statutory compliance.
ActAct
The Hong Kong Legislation
was reviewed and 12 statutory
requirements were identified;
•Form 1. Report of Results of Weekly Inspection of Lifting Appliances•Form 2. Certificate of Test and Thorough Examination of Anchoring or Ballasting of Cranes•Form 3. Certificate of Test and Thorough Examination of Cranes, Crabs and Winches•Form 4. Certificate of Test and Thorough Examination of Lifting Appliances (Except Cranes, Crabs and Winches)•Form 5. Lifting Appliances Certificate of Thorough Examination in the Preceding Twelve Months•ASLI not fitted or not functioning properly•Obstructed view•Safe working load markings•Jib angle indicator fitted•Anti- collision device fitted•Over hoist limit switch fitted•Safety latch fitted on the hook
Statutory RequirementsStatutory Requirements
The inspection checklist was
developed by a team of staff;
Act (cont)Act (cont)
Crane and Lifting Appliance Safety Inspection Form
Contract Location Conducted by:
Date and Time of Inspection:
Ref. Number:
Crawler Crane Tower Crane Hydraulic Crane Type of Crane (Tick as appropriate)
Gantry Crane Piling Rig Lorry or Train Mounted Crane
Brand/model Identification Number:
Owner
Year of Manufacture Maximum SWL (Form 3)
Contractor’s own plant permit or labelling system
No Yes Issue Date
Form 1 Latest Dated: Form 2* (if necessary) Dated:
Form 3 * Dated: Form 4* (if necessary) Dated:
Form 5* Dated:
Name of RPE Registration Number:
Operator’s Certificate* Name: Issued by: Valid until: Class: Yes No
ASLI fitted, working and being used*
Over hoist/travel limit switch* (for Crane only)
Safety latch on the hook
Unobstructed view
SWL marking/Radius chart
Jib angle indicator (telescopic or lattice jib)
Safety Devices
Anti-collision devices functioning properly* (tower crane)
Permit to Move* The latest Permit Dated:
Permit to Operate* The latest Permit Dated:
Compliance to Permits* Yes No Yes No Compliance to the
Permit to Operate Compliance to the Permit to Move
Remarks * Major safety requirement. Non-compliance will lead to suspension of operation.
Conclusion Compliance with requirement
Non-compliance Suspended from operation
PVC holder issued Yes No
The surveyors were trained to use the inspection checklist;
Act (cont)Act (cont)
A survey was conducted of all the cranes being used on the 2 projects.
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
May
Mo
nth
ly N
on
-Co
mp
lian
ce R
ate
ERE Monthly Non-ComplianceRateWR Monthly Non-ComplianceRate
Results of the Initial SurveyResults of the Initial Survey
12.32%12.32%
0%0%
339 cranes were339 cranes were
Inspected:Inspected:
276 WR276 WR
63 ERE63 ERE
6 more surveys were conducted 6 more surveys were conducted using the PAR methodusing the PAR method
Act
Review
Plan
10.87
0.00
16.57
12.32
0.00
5.00
10.00
15.00
20.00
25.00
30.00
May Jun
Mo
nth
ly N
on
-Co
mp
lian
ce R
ate
0.00
5.00
10.00
15.00
20.00
25.00
Cu
mu
lati
ve N
on
-Co
mp
lian
ce R
ate
ERE Monthly Non-Compliance Rate
WR Monthly Non-Compliance Rate
ERE Cumulative Non-Compliance Rate
WR Cumulative Non-Compliance Rate
Results of the 2nd SurveyResults of the 2nd Survey
25.89
2.601.653.05
3.55
0.673.57
9.05
2.392.49
0.00
7.146.237.29
9.23
16.57
5.716.387.39
8.91
10.8712.32
0.00
5.00
10.00
15.00
20.00
25.00
30.00
MAY JUN JUL AUG SEP OCT
Per
cent
age
of N
on-c
ompl
ianc
es
ERE (Monthly)
WR (Monthly)
ERE (Cumulative)
WR (Cumulative)
Results of the 6Results of the 6thth & Final Survey & Final Survey
0.00
10.29
3.95
1.61
4.25
5.54
3.65
1.932.35
3.073.82
4.71
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
MAY JUN JUL AUG SEP OCT
ERE (Monthly)
WR (Monthly)
ERE (Cumulative)
WR (Cumulative)
Example of an Inspection Item Survey Example of an Inspection Item Survey Result – Form 1, Non ComplianceResult – Form 1, Non Compliance
24,82824,828items
were inspected
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
Statutory Requirement
Pe
rce
nta
ge
No
n-c
om
pli
an
ce
WR
ERE
Summary of the Results by ProjectSummary of the Results by Project
0.1
0.580.39
0.680.39
0.630.34
1.26
1.79
2.22
3.19
0.68
0
0.5
1
1.5
2
2.5
3
3.5
No For
m 1
No For
m 2
No For
m 3
No For
m 4
No For
m 5
ASLI n
ot fi
tted
or n
ot fu
nctio
ning
prop
erly
No O
ver H
oist
Switch
No Safe
ty Lat
ch o
n th
e Hoo
kO
bstru
cted
Vie
w
No Safe
Wor
king
Load
Mar
kings
No Jib
Ang
le In
dicat
or
No Anti-
Collisi
on D
evice
Statutory Requirement
Pe
rce
nta
ge
No
n-c
om
plia
nc
eSummary of the Results by ItemSummary of the Results by Item
63
276221
112 150 169 168164154 201 209182
826
1243
0
200
400
600
800
1000
1200
1400
MAY JUN JUL AUG SEP OCT
ERE (Monthly)
WR (Monthly)
ERE (Cumulative)
WR (Cumulative)
No’ of Cranes Inspected by MonthNo’ of Cranes Inspected by Month
Total 2,069Total 2,069
Types of Cranes InspectedTypes of Cranes Inspected
449
352
210 214
769
583 6
1226
410
213 220
0
200
400
600
800
1000
1200
1400
Crawler Hydraulic Lorry or TrainMounted
Tower
Num
ber o
f Cra
nes
WRERETotal
Literature ReviewLiterature Review
•Hong Kong Safety Legislation;•Crane and Lifting Appliance Legislation in Hong Kong;•Crane and Lifting Appliance Legislation in Other Countries;•Safety Management;•Risk Perception;•Human Behavior; •Supervisors Role, and•Senior Managers Role.
ConclusionConclusion
•The inspections and the inspection checklist were successful in reducing the number of non-conformances;
•The survey has identified areas of weakness in the safety management systems of the Contractor;
•There is no penalty system in place, other than from the Contractor, for the operator.
“The non-compliance to statutory requirements will decrease upon the implementation of the inspection regime”
Conclusion - HypothesisConclusion - Hypothesis
TRUE –
The results show that the number of non-
conformances did decrease following the
implementation of the inspection regime.
RecommendationsRecommendations
•Incorporate the inspection checklist into a
safety procedure for all sites;
•Continue the inspections and continue to
record and report the non-conformances;
•Implement effective Contractor safety
management systems to ensure statutory
compliance;
•Discuss with the Labour Department and the operator’s license issuing authority, the non-conformances and discuss measures for improvement;
Recommendations (cont)Recommendations (cont)
•Make the safety procedure available to other projects in Hong Kong.
Benefits from the ResearchBenefits from the Research
•Improved compliance to statutory requirements;
•Elimination of crane incidents;
•Increased inspections and monitoring;
•Formalised inspection procedure;
•Improved quality of the inspections;
•Is now being used on other non KCRC projects
•Standardised inspection procedure;
Benefits from the Research Benefits from the Research (cont)(cont)
QuestionsQuestions