Rescheduled Outages
Project P215-01 NPRR 758
Improved Transparency for
Outages having a High
Economic Impact.
PUBLIC
Background
In 2015 and early 2016, the Outage Coordination
Improvement Task Force (OCITF) and ERCOT met to
discuss ways to:
• Identify Outages which have historically resulted in high
congestion costs
• Encourage earlier submission of these Outages
• Formalize a rescheduling process if these Outages must
be withdrawn or moved
• Provide improved transparency to Market Participants if
these Outages are submitted with 90 days or less notice.
2
PUBLIC
BackgroundThe approved result of the committees work became Project
P215-01 NPRR 758 Improved Transparency for Outages
having a High Economic Impact.
Specific items proposed within this NPRR include:
• Identification and posting of High Impact Outages (HIOs)
and associated High Impact Transmission Elements
(HITEs); and
• Introduction of a new “Rescheduled Outage” type.
Implementation of this NPRR will:
• Improve the market’s ability to hedge against congestion
• Encourage earlier submission of Outages
• Increase visibility of HIOs to Market Participants, and
• Allow more efficient and transparent rescheduling
3
PUBLIC
Definitions, Protocol and Process Revisions
ERCOT Definitions and Terminology to be discussed
includes:
• Transmission Elements
• High Impact Transmission Elements (HITEs)
• Major Transmission Elements (MTEs)
• Rescheduled High Impact Outages (HIOs)
• Transmission Element Examples
• Revisions to Protocol Section 3.1.5
• Outage Scheduler User Interface (OSUI) Revisions
• HIO MIS Reports
4
PUBLIC
Definitions
Transmission Element:
Part of a physical Transmission Facility that is:
• an Electrical Bus, line, transformer, generator, Load, breaker,
switch, capacitor, reactor, phase shifter, or other similar device
5
High Impact Transmission Element (HITE)
A Transmission Element that may, in certain conditions, result in
High Congestion risk when taken out-of-service.
ERCOT, with input from Market Participants, shall annually
update the HITE list for approval by TAC
• Part of the ERCOT Transmission Grid
• Defined in the ERCOT Network Operations Model.
PUBLIC
Rescheduled High Impact Outage (RO)
An Outage on a High Impact Transmission Element (HITE) that was:
• Originally submitted and Approved as a Planned Transmission
Outage with greater than 90 days’ notice
• Being considered for rescheduling due to withdrawal of approval
by ERCOT of the original Planned Outage or subsequent
Rescheduled Outage(s).
NOTE: Only ERCOT shall be able to convert a Transmission
Planned High Impact Outage into a Rescheduled Outage after
discussion with the Requestor.
Definitions
High Impact Outage (HIO)
A Planned Outage or Rescheduled Outage that interrupts flow on
a High Impact Transmission Element (HITE).
6
PUBLIC
Major Transmission Elements (MTEs) and
High Impact Transmission Elements (HITEs)
The MTE & HITE List will be updated at least Annually with:
• Actual Outages associated with significant congestion1
during the previous years, including
• Multiple Outages
• Planned and Forced Outages
• Outages identified by Outage Coordination studies which
could have caused excessive generation re-dispatch under
certain conditions.
• Regardless of whether the outage actually occurred or not
• Additional elements as requested by Market Participants.1 Significant Congestion – incurred over $1 Million Dollars of Real-Time Congestion Rent during any given Month.
Congestion Rent $ is the difference in what is charged to Buyers and what is paid to Sellers when congestion occurs.
7
PUBLIC
Major Transmission Element (MTE) List
The Major Transmission Elements list is less detailed and is comprised
of:
• Line (LN), Transformer (XF), Bus, and Breaker/Switch that split the
bus.
• Congested Equipment Type (Lines, Transformers, Busses, Circuit
Breakers)
• Year and Month congestion occurred or was forecasted
• Contingencies and Resultant overloaded elements
• Whether based on Actual Congestion(RT) or Forecasted(ST)
• Whether based on Planned or Forced Outages
8
PUBLIC
High Impact Transmission Elements (HITE) List
The High Impact Transmission Elements list is more detailed
and is comprised of:
• All of the equipment associated with each MTE
• Station From/To Names
• Equipment Types (CB, LN, DSC) and Name
• Normal and Outage State (Open or Closed)
• Voltage (kV)
• TEID (Transmission Element ID) and RDFID (Resource Description
Framework ID)
9
PUBLIC
NPRR 758 Rescheduled Outages
High Impact
Transmission Element
Examples
10
PUBLIC 11
A
100
L01
L02
L0
4
L40
C200
S123
CT0
2
C300 CT0
3
ST23
L44
L22
138kV
345kV
L50
L32
L42
L60
AT10 AT20
L32
L58
A
400
A
200A
300
A
800
A
900
A
500
A
700
A
600
B
300
B
350B
360
B
310B
320
B
370
D
400
D
500D
600D
700
D
300D
200
S
235
Transmission Elements
The HITE list
includes all of the
Transmission
Elements that
would be outaged
for High Impact
Outages on:
• Lines
• Transformers
• Buses
• Bkr/Switches
138kV
PUBLIC 12
A
100
L01
L02
L0
4
L40
C200
S123
CT0
2
C300 CT0
3
ST23
L44
L22
138kV
345kV
L50
L32
L42
L60
AT10 AT20
L32
L58
A
400
A
200A
300
A
800
A
900
A
500
A
700
A
600
B
300
B
350B
360
B
310B
320
B
370
D
400
D
500D
600D
700
D
300D
200
S
235
138kV
Transmission Elements
The HITE list
includes all of the
Transmission
Elements that
would be outaged
for High Impact
Outages on:
• Lines
• Transformers
• Buses
• Bkr/Switches
PUBLIC 13
A
100
L01
L02
L0
4
L40
C200
S123
CT0
2
C300 CT0
3
ST23
L44
L22
138kV
345kV
L50
L32
L42
L60
AT10 AT20
L32
L58
A
400
A
200A
300
A
800
A
900
A
500
A
700
A
600
B
300
B
350B
360
B
310B
320
B
370
D
400
D
500D
600D
700
D
300D
200
S
235
138kV
Transmission Elements
The HITE list
includes all of the
Transmission
Elements that
would be outaged
for High Impact
Outages on:
• Lines
• Transformers
• Buses
• Bkr/Switches
PUBLIC 14
A
100
L01
L02
L0
4
L40
C200
S123
CT0
2
C300 CT0
3
ST23
L44
L22
138kV
345kV
L50
L32
L42
L60
AT10 AT20
L32
L58
A
400
A
200A
300
A
800
A
900
A
500
A
700
A
600
B
300
B
350B
360
B
310B
320
B
370
D
400
D
500D
600D
700
D
300D
200
S
235
138kV
Transmission Elements
The HITE list
includes all of the
Transmission
Elements that
would be outaged
for High Impact
Outages on:
• Lines
• Transformers
• Buses
• Bkr/Switches
PUBLIC 15
A
100
L01
L02
L0
4
L40
C200
S123
CT0
2
C300 CT0
3
ST23
L44
L22
138kV
345kV
L50
L32
L42
L60
AT10 AT20
L32
L58
A
400
A
200A
300
A
800
A
900
A
500
A
700
A
600
B
300
B
350B
360
B
310B
320
B
370
D
400
D
500D
600D
700
D
300D
200
S
235
NOTE:
An Outage on any
individual
Transmission
Element included
in a HITE list will
also be in the
Outage Scheduler
Summaries and in
the HIO < 90 Day
Notice Report
138kV
Transmission Elements
PUBLIC
NPRR 758 Improved Transparency for Outages
having a High Economic Impact
Protocol
Revisions
16
PUBLIC
NPRR 758 & Protocol 3.1.5.7[NPRR758: Replace Section 3.1.5.7 above with the following upon system
implementation:]
3.1.5.7 Withdrawal of Approval of Approved Planned Outages, Maintenance Outages,
and Rescheduled Outages of Transmission Facilities
(1) If ERCOT believes it cannot meet the applicable reliability standards and has exercised
reasonable options, ERCOT may contact the TSP for more information prior to its withdrawal
of the approval for a Planned Outage, Maintenance Outage, or Rescheduled Outage. ERCOT
shall inform the affected TSP both orally and in written or electronic form as soon as ERCOT
identifies a situation that may lead to the withdrawal of ERCOT’s approval. If ERCOT
withdraws its approval, the TSP may submit a new request for approval of the Planned
Outage or Maintenance Outage schedule provided the new request meets the submittal
requirements for Outage Scheduling.
(2) In determining whether to withdraw approval, ERCOT shall duly consider whether the
Planned Outage, Maintenance Outage, or Rescheduled Outage affects public infrastructure if
ERCOT is made aware of such potential impacts by the TSP (e.g., impacts on highways,
ports, municipalities, and counties).
(3) Prior to withdrawing the approval of a High Impact Outage (HIO) submitted with greater
than 90-days’ notice, ERCOT shall coordinate with the TSP and may convert the Planned
Outage to a Rescheduled Outage. The Rescheduled Outage shall retain the same priority as
the original Planned Outage. ERCOT shall attempt to keep the Outage within the same
calendar month.
17
PUBLIC
NPRR 758 & Protocol 3.1.5.11
3.1.5.11 Evaluation of Transmission Facilities Planned Outage or Maintenance Outage Requests
(1) ERCOT shall evaluate requests, approve, or reject Transmission Facilities Planned Outages and
Maintenance Outages according to the requirements of this section. ERCOT may approve Outage
requests provided the Outage in combination with other proposed Outages does not cause a violation of
applicable reliability standards. ERCOT shall reject Outage requests that do not meet the submittal
timeline specified in Section 3.1.5.12, Submittal Timeline for Transmission Facility Outage Requests.
ERCOT shall consider the following factors in its evaluation:
(e) Previously approved Planned Outages and Maintenance Outages;
. 18
PUBLIC
NPRR 758 & Protocol 3.1.5.13
3.1.5.13 Transmission Report
(1) ERCOT shall post on the MIS Secure Area:
(d) At least annually, an updated list of High Impact Transmission Elements
(HITEs) pursuant to Section 3.1.8, High Impact Transmission Element
(HITE) Identification.
19
PUBLIC
High Impact Outages – Submitted 90 Days or Less
• A once-a-day Current Day Report (CDR) titled “High Impact
Outages – Submitted 90 Days or Less” will be posted to the
MIS Secure at Grid>Transmission shortly after midnight.
• Report will contain only the Accepted or Approved HIOs in
the Outage Scheduler at 0000 hours submitted 90 days or
less in advance of the Planned Start!
• For Group Outages, the Non-HIO transmission elements will
not be included in the report!
Report format is
consistent with the
Hourly Consolidated
Transmission
Outage Report.
20
PUBLIC
NPRR 758 Improved Transparency for Outages
having a High Economic Impact
Incorporating the
Rescheduled Outage
into the
Outage Scheduler
User Interface.
21
PUBLIC
Outage Scheduler User Interface (OSUI)
22
To incorporate the new Rescheduled Outage type into the
existing Outage Scheduler User Interface (OSUI), the
following changes were made:
• On the Transmission Planned Outage request screens,
fields were added to alert the Requestor that:
o The selected transmission element
is on the High Impact Transmission
Element list (HIO with a “Y” flag)
o The High Impact Outage has been
requested greater than 90 days prior
to the Planned Start (HIO>90 Days
with a “Y” flag)
PUBLIC
Outage Scheduler User Interface (OSUI)
23
For Rescheduled Outages, no “N”’s will be displayed. Blank
fields mean “No” and indicate that:
• HIO fields - Element was not on the HITE List
• HIO>90 Day fields - Outage was submitted 90 days or
less in advance of the Planned Start
NOTE: The no “N” convention for HIO
and HIO>90 Day fields is utilized on
applicable Outage Scheduler User Interface
screens and Outage Scheduler reports.
PUBLIC
Outage Scheduler User Interface (OSUI)
24
Rescheduled Outage - Group Outage Rules:
• Elements may only be removed from a Rescheduled
Outage group, never added.
• If all of the HIO elements are removed from a
Rescheduled Outage group, the outage no longer
qualifies for Rescheduling.
PUBLIC
Outage Scheduler User Interface (OSUI)
25
HIO and HIO>90 Day fields have been added to the following
OSUI screens:
• Outage Scheduler Summary
• Show/Hide Preference
• Planned Transmission Outage Request
• Selecting Equipment pull-downs
• Associated Equipment pull-downs
PUBLIC
Outage Scheduler Summary Screen
26
Added HIO and HIO>90 columns on right edge of Summary
Screen
• “Y” in the HIO column indicates the outaged element is on
the HITE list
• “Y” in the HIO>90 column indicates that the outage was
submitted greater than 90 days prior to the Planned Start.
PUBLIC
Show/Hide Preferences
27
HIO and HIO>90 columns may be hidden by de-selecting
them on the Show/Hide Preferences screen.
PUBLIC
Custom Filter
28
Added Rescheduled Outage to the
Outage Type selection field
PUBLIC
Transmission Planned Outage Request Screen
29
Added indicators for:
• HIOs submitted greater than 90 days prior to
Planned Start (HIO>90 Days flag)
• Transmission Elements which are on the High
Impact Transmission Element list. (HIO flag)
Outage is
classified as a
High Impact
Outage if at least
one element is on
the HITE List
PUBLIC
Selecting Equipment Name Pull-Downs
30
HIO column has been
added to the Selecting
Equipment pull-downs
PUBLIC
Associated Equipment Summaries
31
High Impact Outage
fields have been added
to the Associated
Equipment Summaries
PUBLIC
Outage Scheduler Reports
32
HIO and HIO>90 Day data will be added to the following:
• Outage Scheduler User Interface
o Outage History
o Print Summary
o .csv Summary
o .xml Summary
• MIS
o Consolidated Transmission Outage Report
o High Impact Outages – Submitted 90 Days or Less (New)
PUBLIC
The High Impact
Outage Process.
33
NPRR 758 Rescheduled Outage Process
PUBLIC
HIO Process Overview – 90 days or less
HIOs submitted 90 days or less before the Planned Start:
• Accepted and Approved HIO Transmission outages are
posted daily to the MIS Secure.
• Are not eligible for Rescheduling.
• When ERCOT identifies that a HIO has been submitted with
90-days or less notice, ERCOT may coordinate with the
Requestor to make reasonable efforts to minimize any
detected impact.
34
PUBLIC
HIO Process Overview – greater than 90 days
HIOs submitted greater than 90 days prior to Planned Start
may be eligible for Rescheduling if ERCOT must consider for
Withdrawal.
a) ERCOT will discuss Rescheduling with Requestor.
b) If Requestor cannot Reschedule – ERCOT will Withdraw
c) If Requestor can Reschedule – ERCOT will convert into a
Rescheduled Outage.
d) Requestor must submit revised Planned Start and
Planned End dates and times (3 day minimum applies)
e) Requestor may remove Elements and modify fields after
Rescheduled Dates are submitted.
f) ERCOT will re-evaluate and, if no security violations exist,
issue Approval.
35
PUBLIC 36
When the Requestor can Reschedule the Transmission Outage:
• ERCOT will convert the Planned Outage into a Rescheduled Outage.
• Warning Message “Outage ABCD12345678 has been rescheduled, new
dates must be submitted” is issued
• Rescheduled Outage status will show as Rescheduled Outage -
Entered Not Yet Submitted (ENYS)
• Requestor must submit new Planned Start, Earliest Start, Planned End
and Latest End information (All four fields required).
o Three day minimum submittal applies
o Outage may start earlier or end later
o New outage duration cannot exceed the original duration.
• Requestor may edit the Name, Number and Notes fields
• Requestor may Cancel the request.
RO - Entered Not Yet Submitted status
PUBLIC 37
Editable Fields
ABC1234567
Single RO- Entered Not Yet Submitted status
Editable Fields
HIO Indicators
Original Request Date
Is Retained
PUBLIC 38
Editable Fields
ABC1234567
Group RO- Entered Not Yet Submitted status
Editable Fields
PUBLIC 39
While in ENYS status, ERCOT has the capability to
• Withdraw the Outage
• Revert the Rescheduled Outage – ENYS status back to a
Planned Outage– Approved status, after discussion with the
Requestor
RO - Entered Not Yet Submitted status
PUBLIC 40
While in Received at ERCOT status, Requestors may:
• Revise the Planned Start, Earliest Start, Planned End and
Latest End information.
o Three day minimum submittal applies
o Outage may start earlier or end later
o New outage duration cannot exceed the original
duration.
• Only remove elements from Group outages.
• Edit the Name, Number, Emergency Restoration, Nature of
Work and Notes fields
• Cancel the request.
RO - Received at ERCOT status
PUBLIC 41
May Only Remove from a Group
Editable Fields
RO - Received at ERCOT Status
PUBLIC 42
When the Requestor has completed it revisions while in
Received at ERCOT status, ERCOT shall evaluate the
Rescheduled Outage and either
• Approve the Rescheduled Outage or
• Reject the Request
RO - Received at ERCOT status
PUBLIC 43
When the Transmission Rescheduled Outage becomes
Approved, the normal rules and procedures for
Transmission Planned Outages apply.
RO – Approved Status
PUBLIC 44
While in Approved Status, ERCOT has the capability to
• Withdraw the Outage
• Revert the Rescheduled Outage – Approved status back to
a Rescheduled Outage– Entered Not Yet Submitted status,
after discussion with the Requestor
RO – Approved Status
PUBLIC 45
RO - Approved Status
May only remove from a Group
Editable Fields
PUBLIC
NPRR 758 - Rescheduled Outage Process
Questions?
46