RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications...

14
Effective as of September 30, 2020 # of Applicants # of MW Application Submitted 1 0 0 Initial Review 0 0 Supplemental Review 0 0 Detailed Study 0 0 Tendered Interconnection Agreement 2 7 9.83 Implementation 3 14 22.967 Provided Approved Building Permit from Authority Having Jurisdiction 4 2 .302 Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 66 117.111 Summary - - Total Pending Projects 21 32.797 Total Counted Towards Cap 5 54 44.023 Effective as of August 31, 2020 # of Applicants # of MW Application Submitted 1 0 0 Initial Review 0 0 Supplemental Review 1 .75 Detailed Study 0 0 Tendered Interconnection Agreement 2 7 9.83 Implementation 3 14 23.216 Provided Approved Building Permit from Authority Having Jurisdiction 4 2 .302 Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 22 33.796 Total Counted Towards Cap 5 54 44.023 RES-BCT Tracking Archive

Transcript of RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications...

Page 1: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of September 30, 2020 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 0 0

Tendered Interconnection Agreement2 7 9.83

Implementation3 14 22.967

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 52 43.721

Total Applications Withdrawn 66 117.111

Summary - -

Total Pending Projects 21 32.797

Total Counted Towards Cap5 54 44.023

Effective as of August 31, 2020 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 0 0

Supplemental Review 1 .75

Detailed Study 0 0

Tendered Interconnection Agreement2 7 9.83

Implementation3 14 23.216

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 52 43.721

Total Applications Withdrawn 65 116.111

Summary - -

Total Pending Projects 22 33.796

Total Counted Towards Cap5 54 44.023

RES-BCT Tracking Archive

Page 2: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of July 31, 2020 # of

Applicants # of MW

Application Submitted1 1 .75

Initial Review 1 2.52

Supplemental Review 0 0

Detailed Study 1 1.8

Tendered Interconnection Agreement2 5 5.51

Implementation3 14 23.216

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 52 43.721

Total Applications Withdrawn 65 116.111

Summary - -

Total Pending Projects 21 33.046

Total Counted Towards Cap5 54 44.023

Effective as of June 30, 2020 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 5 6.59

Supplemental Review 0 0

Detailed Study 1 1.8

Tendered Interconnection Agreement2 1 1.44

Implementation3 14 23.216

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 52 43.721

Total Applications Withdrawn 65 116.111

Summary - -

Total Pending Projects 21 33.046

Total Counted Towards Cap5 54 44.023

RES-BCT Tracking Archive

Page 3: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of May 31, 2020 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 5 6.59

Supplemental Review 0 0

Detailed Study 2 3.24

Tendered Interconnection Agreement2 1 .858

Implementation3 14 23.216

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 52 43.721

Total Applications Withdrawn 65 116.111

Summary - -

Total Pending Projects 21 33.046

Total Counted Towards Cap5 54 44.023

Effective as of April 30, 2020 # of

Applicants # of MW

Application Submitted1 5 6.59

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 2 3.24

Tendered Interconnection Agreement2 1 .858

Implementation3 13 22.358

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 52 43.721

Total Applications Withdrawn 65 116.111

Summary - -

Total Pending Projects 21 33.046

Total Counted Towards Cap5 54 44.023

RES-BCT Tracking Archive

Page 4: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of March 31, 2020 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 2 3.24

Tendered Interconnection Agreement2 1 .858

Implementation3 13 22.358

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 52 43.721

Total Applications Withdrawn 63 116.111

Summary - -

Total Pending Projects 16 26.456

Total Counted Towards Cap5 54 44.023

Effective as of February 29, 2020 # of

Applicants # of MW

Application Submitted1 1 1.80

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 2 3.422

Tendered Interconnection Agreement2 1 .858

Implementation3 15 32.358

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 51 43.721

Total Applications Withdrawn 62 104.129

Summary - -

Total Pending Projects 19 38.438

Total Counted Towards Cap5 54 44.023

RES-BCT Tracking Archive

Page 5: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of January 31, 2020 # of

Applicants # of MW

Application Submitted1 1 1.44

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 1 1.982

Tendered Interconnection Agreement2 3 2.506

Implementation3 15 32.616

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 51 43.121

Total Applications Withdrawn 61 102.823

Summary - -

Total Pending Projects 20 38.544

Total Counted Towards Cap5 53 43.423

Effective as of December 31, 2019 # of

Applicants # of MW

Application Submitted1 1 1.44

Initial Review 1 .313

Supplemental Review 0 0

Detailed Study 1 1.982

Tendered Interconnection Agreement2 3 2.414

Implementation3 14 32.366

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 51 43.121

Total Applications Withdrawn 62 103.423

Summary - -

Total Pending Projects 20 38.515

Total Counted Towards Cap5 53 43.423

RES-BCT Tracking Archive

Page 6: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of November 30, 2019 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 1 .313

Supplemental Review 0 0

Detailed Study 1 1.982

Tendered Interconnection Agreement2 3 2.414

Implementation3 15 32.966

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 51 43.121

Total Applications Withdrawn 61 102.823

Summary - -

Total Pending Projects 20 37.675

Total Counted Towards Cap5 53 43.423

Effective as of October 31, 2019 # of

Applicants # of MW

Application Submitted1 1 .313

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 1 1.982

Tendered Interconnection Agreement2 3 2.414

Implementation3 15 32.966

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 51 43.121

Total Applications Withdrawn 60 102.223

Summary - -

Total Pending Projects 20 37.675

Total Counted Towards Cap5 53 43.423

RES-BCT Tracking Archive

Page 7: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of September 30, 2019 # of

Applicants # of MW

Application Submitted1 1 .25

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 1 1.982

Tendered Interconnection Agreement2 2 2.164

Implementation3 15 32.966

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 52 43.121

Total Applications Withdrawn 60 103.519

Summary - -

Total Pending Projects 19 37.362

Total Counted Towards Cap5 54 43.423

Effective as of August 31, 2019 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 1 1.982

Tendered Interconnection Agreement2 3 4.414

Implementation3 15 32.708

Provided Approved Building Permit from Authority Having Jurisdiction4 2 .302

Total Interconnected Projects (PTO) 50 41.129

Total Applications Withdrawn 60 103.519

Summary - -

Total Pending Projects 19 39.104

Total Counted Towards Cap5 52 41.431

RES-BCT Tracking Archive

Page 8: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of July 31, 2019 # of

Applicants # of MW

Application Submitted1 1 1.992

Initial Review 0 0

Supplemental Review 1 2.250

Detailed Study 0 0

Tendered Interconnection Agreement2 2 2.164

Implementation3 16 34.408

Provided Approved Building Permit from Authority Having Jurisdiction4 0 0

Total Interconnected Projects (PTO) 50 41.129

Total Applications Withdrawn 59 101.819

Summary - -

Total Pending Projects 19 38.822

Total Counted Towards Cap5 52 41.431

Effective as of June 30, 2019 # of

Applicants # of MW

Application Submitted1 1 1.992

Initial Review 0 0

Supplemental Review 1 2.250

Detailed Study 0 0

Tendered Interconnection Agreement2 2 2.164

Implementation3 16 34.408

Provided Approved Building Permit from Authority Having Jurisdiction4 0 0

Total Interconnected Projects (PTO) 50 41.129

Total Applications Withdrawn 59 101.819

Summary - -

Total Pending Projects 19 38.822

Total Counted Towards Cap5 52 41.431

RES-BCT Tracking Archive

Page 9: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of May 31, 2019 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 1 2.25

Supplemental Review 0 0

Detailed Study 1 2

Tendered Interconnection Agreement2 4 6.27

Implementation3 16 32.935

Provided Approved Building Permit from Authority Having Jurisdiction4 3 0.882

Total Interconnected Projects (PTO) 49 40.549

Total Applications Withdrawn 57 97.766

Summary - -

Total Pending Projects 22 43.455

Total Counted Towards Cap5 52 41.431

Effective as of April 30, 2019 # of

Applicants # of MW

Application Submitted1 1 2.25

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 1 2

Tendered Interconnection Agreement2 4 6.27

Implementation3 18 35.202

Provided Approved Building Permit from Authority Having Jurisdiction4 3 0.882

Total Interconnected Projects (PTO) 48 40.227

Total Applications Withdrawn 58 97.946

Summary - -

Total Pending Projects 25 45.902

Total Counted Towards Cap5 51 41.109

RES-BCT Tracking Archive

Page 10: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of March 31, 2019 # of

Applicants # of MW

Application Submitted1 1 0.18

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 3 6.106

Tendered Interconnection Agreement2 2 2.164013

Implementation3 18 35.202

Provided Approved Building Permit from Authority Having Jurisdiction4 3 0.882

Total Interconnected Projects (PTO) 48 40.227

Total Applications Withdrawn 55 96.628

Summary - -

Total Pending Projects 24 43.646

Total Counted Towards Cap5 51 41.109

Effective as of February 28, 2019 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 3 6.100

Tendered Interconnection Agreement2 4 8.189

Implementation3 16 29.190

Provided Approved Building Permit from Authority Having Jurisdiction4 3 0.882

Total Interconnected Projects (PTO) 48 40.227

Total Applications Withdrawn 55 96.628

Summary - -

Total Pending Projects 23 43.479

Total Counted Towards Cap5 51 41.109

RES-BCT Tracking Archive

Page 11: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of January 31, 2019 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 4 7.406

Tendered Interconnection Agreement2 4 7.204

Implementation3 17 30.709

Provided Approved Building Permit from Authority Having Jurisdiction4 4 1.882

Total Interconnected Projects (PTO) 47 39.227

Total Applications Withdrawn 54 95.788

Summary - -

Total Pending Projects 25 45.319

Total Counted Towards Cap5 51 41.109

Effective as of December 31, 2018 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 6 10.127

Tendered Interconnection Agreement2 1 .858

Implementation3 16 34.008

Provided Approved Building Permit from Authority Having Jurisdiction4 1 1

Total Interconnected Projects (PTO) 47 39.227

Total Applications Withdrawn 54 94.673

Summary - -

Total Counted Towards Cap5 23 44.993

RES-BCT Tracking Archive

Page 12: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of November 30, 2018 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 0 0

Supplemental Review 0 0

Detailed Study 6 10.127

Tendered Interconnection Agreement2 1 .858

Implementation3 17 34.492

Provided Approved Building Permit from Authority Having Jurisdiction4 1 1

Total Interconnected Projects (PTO) 46 38.743

Total Applications Withdrawn 54 94.673

Summary - -

Total Pending Projects 24 45.477

Total Counted Towards Cap5 47 39.743

Effective as of October 31, 2018 # of

Applicants # of MW

Application Submitted1 0 0

Initial Review 0 0

Supplemental Review 2 3.553

Detailed Study 6 9.596

Tendered Interconnection Agreement2 4 6.938

Implementation3 16 32.211

Provided Approved Building Permit from Authority Having Jurisdiction4 1 1

Total Interconnected Projects (PTO) 45 37.94

Total Applications Withdrawn 51 88.041

Summary - -

Total Pending Projects 28 52.298

RES-BCT Tracking Archive

RES-BCT Tracking Archive

Page 13: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of September 30, 2018 # of

Applicants # of MW

Application Submitted1 1 3.781

Initial Review 0 0

Supplemental Review 2 3.632

Detailed Study 6 10.416

Tendered Interconnection Agreement2 2 1.658

Implementation3 18 37.492

Provided Approved Building Permit from Authority Having Jurisdiction4 1 1

Total Interconnected Projects (PTO) 45 37.94

Total Applications Withdrawn 51 88.041

Summary - -

Total Pending Projects 29 56.979

Total Counted Towards Cap5 46 38.94

Effective as of August 31, 2018 # of

Applicants # of MW

Application Submitted1 2 5.781

Initial Review 3 5.234

Supplemental Review N/A N/A

Detailed Study 7 12.203

Tendered Interconnection Agreement2 1 N/A

Implementation3 21 42.109

Provided Approved Building Permit from Authority Having Jurisdiction4 1 1

Total Interconnected Projects (PTO) 44 36.31

Total Counted Towards Cap5 45 37.31

Total Applications Withdrawn 49 86.011

RES-BCT Tracking Archive

Page 14: RES-BCT Tracking Archive · Total Interconnected Projects (PTO) 52 43.721 Total Applications Withdrawn 65 116.111 Summary - - Total Pending Projects 21 33.046 Total Counted Towards

Effective as of July 31, 2018 # of

Applicants # of MW

Application Submitted1 4 7.352

Initial Review 4 8.71

Supplemental Review 4 8.78

Detailed Study 3 5.382

Tendered Interconnection Agreement2 2 3

Implementation3 18 33.70

Provided Approved Building Permit from Authority Having Jurisdiction4 3 3.07

Total Interconnected Projects (PTO) 42 34.24

Total Counted Towards Cap5 45 37.31

Total Applications Withdrawn 49 86.01

RES-BCT Tracking Archive